Actions for Property Asset Utilisation
Property Asset Utilisation
Property NSW’s effectiveness in managing NSW Government owned and leased commercial office property is limited in three areas according to a report released today by the Auditor-General for New South Wales, Margaret Crawford.
At 30 June 2018, the NSW Government owned $160 billion worth of land and buildings. The NSW Treasury predicts this figure will rise over the coming years. Property NSW manages more than 900 leased office properties across the state. Approximately 250 of these are owned by Property NSW. Other NSW Government agencies maintain ownership and control of properties considered essential for service provision, such as schools, prisons and hospitals. Between 2012–13 and 2017–18 sales of property assets across the whole of the NSW Government have raised $10 billion, of which Property NSW has sold property assets of approximately $2 billion.
In September 2012, the Property Asset Utilisation Taskforce (the Taskforce) released its report on ‘real property asset management across government’ and concluded that the government has accumulated, over time, ‘a real property asset portfolio it cannot afford to maintain or protect’. The Taskforce noted that ‘a lack of centralised information seriously inhibits any whole-of-government strategic asset planning’ and that maintaining under-utilised or unnecessary properties diverted funds from areas where they might be better used. The Taskforce’s key findings included:
- the NSW Government should own property only as a means to deliver or enhance services
- many government properties were under-utilised, poorly maintained and inappropriate to support service delivery.
The Taskforce recommended the creation of Property NSW, as a replacement for the State Property Authority, to improve property asset utilisation and to drive efficiencies in the government’s owned and leased property portfolio. Property NSW was to achieve these goals by:
- collating property information across the whole-of-government
- working with agencies on longer-term strategic real property asset planning to:
- provide services to agencies as customers
- bring a whole-of-government perspective to real property asset planning.
In response to the Taskforce report, in December 2012, the Premier's Memorandum M2012-20 (the Memorandum) established Property NSW to improve the management of the NSW Government's owned and leased real property portfolio.
Under the Memorandum, Property NSW is responsible for:
- management of all leased and owned commercial office accommodation
- acting as the central acquisition and disposal agency
- providing advice to the government on property matters and developing property policy
- conducting regular and ongoing reviews of agencies portfolios, working with agencies to identify efficiencies to improve service delivery, in relation to the review of capital planning1
- maintaining the register of all government owned property.
The Memorandum states that ownership of all commercial office property should be vested in Property NSW.
This audit assessed whether Property NSW is effective in the management of NSW Government owned and leased commercial office property. To do this we assessed whether NSW Government leased commercial office space is being effectively utilised and whether the Government Property Register, a register of all government owned property, is accurate and up-to-date.
In December 2017, Property NSW started working across the NSW Government to help agencies identify real property assets, including commercial office properties, that are under-utilised or surplus and that could be recycled, repurposed, or vested to Property NSW.
1 Capital Planning was previously referred to as Total Asset Management (TAM).
By December 2019, Property NSW should:
- combine the results of property portfolio reviews to produce a whole-of-government picture of the NSW Government property portfolio
- devise a strategy and plan to recycle or repurpose under-utilised properties using a whole-of-government picture of the NSW Government property portfolio
- develop and report on indicators for progress in reducing the number and value of under-utilised properties at the whole-of-government level, referencing progress against an accurate baseline stocktake.
By December 2019, Property NSW should:
4. improve the data held on government owned and leased properties by combining and automating data feeds to construct a single, consolidated and accurate whole-of-government property data set.
By December 2019, Property NSW should:
5. document and communicate to stakeholders how its assessment criteria inform key decisions including agency relocations, lease renewals and rectifying under-utilisation
6. include customer satisfaction measures in its annual reports and reviews, in accordance with the requirements set out in the Premier's Memorandum M2012-20
7. improve record-keeping and compliance with the State Records Act 1998 and the Department of Finance, Services and Innovation Records Management Policy.
Appendix one - Response from agency
Appendix two - Audit Office response
Appendix three - About the audit
Appendix four - Performance auditing
Parliamentary reference - Report number #312 - released 18 December 2018
Actions for Planning and Environment 2018
Planning and Environment 2018
The Auditor-General for New South Wales, Margaret Crawford, released her report today on the NSW Planning and Environment cluster. The report focuses on key observations and findings from the most recent financial audits of these agencies. Unqualified audit opinions were issued for all agencies' financial statements. However, some cultural institutions had challenges valuing collection assets in 2017–18. These issues were resolved before the financial statements were finalised.
This report analyses the results of our audits of financial statements of the Planning and Environment cluster for the year ended 30 June 2018. The table below summarises our key observations.
This report provides parliament and other users of the Planning and Environment cluster agencies' financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:
- financial reporting
- audit observations
- service delivery.
Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making is enhanced when financial reporting is accurate and timely.
This chapter outlines our audit observations related to the financial reporting of agencies in the Planning and Environment cluster for 2018.
Observation | Conclusions and recommendations |
2.1 Quality of financial reporting | |
Unqualified audit opinions were issued for all agencies' financial statements. | The quality of financial reporting remains high across the cluster. |
2.2 Key accounting issues | |
There were errors in some cultural institutions' collection asset valuations. | Recommendation: Collection asset valuations could be improved by:
|
2.3 Timeliness of financial reporting | |
Except for two agencies, the audits of cluster agencies’ financial statements were completed within the statutory timeframe. | Issues with asset revaluations delayed the finalisation of two environment and heritage agencies' financial statement audits. |
Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.
This chapter outlines our observations and insights from:
- our financial statement audits of agencies in the Planning and Environment cluster for 2018
- the areas of focus identified in the Audit Office work program.
The Audit Office annual work program provides a summary of all audits to be conducted within the proposed time period as well as detailed information on the areas of focus for each of the NSW Government clusters.
Observation | Conclusions and recommendations |
3.1 Internal controls | |
One in five internal control weaknesses reported in 2017–18 were repeat issues. | Delays in implementing audit recommendations can prolong the risk of fraud and error. Recommendation (repeat issue): Management letter recommendations to address internal control weaknesses should be actioned promptly, with a focus on addressing repeat issues. |
One extreme risk was identified relating to the National Art School. The School does not have an occupancy agreement for the Darlinghurst campus. | Lack of formal agreement creates uncertainty over the School's continued occupancy of the Darlinghurst site. The School should continue to liaise with stakeholders to formalise the occupancy arrangement. |
3.2 Information technology controls | |
The controls and governance arrangements when migrating payroll data from the Aurion system to SAP HR system were effective. | Data migration from the Aurion system to SAP HR system had no significant issues. |
The Department can improve controls over user access to SAP system. | The Department needs to ensure the SAP user access controls are appropriate, including investigation of excess access rights and resolving segregation of duties issues. |
3.3 Annual work program | |
Agencies used different benchmarks to monitor their maintenance expenditure. | The cluster agencies under review operate in different industries. As a result, they do not use the same benchmarks to assess the adequacy of their maintenance spend. |
This chapter outlines certain service delivery outcomes for 2017–18. The data on activity levels and performance is provided by cluster agencies. The Audit Office does not have a specific mandate to audit performance information. Accordingly, the information in this chapter is unaudited.
We report this information on service delivery to provide additional context to understand the operations of the Planning and Environment cluster, and to collate and present service information for different segments of the cluster in one report.
In our recent performance audit, ‘Progress and measurement of Premier's Priorities’, we identified 12 limitations of performance measurement and performance data. We recommended the Department of Premier and Cabinet ensure that processes to check and verify data are in place for all relevant agency data sources.
Actions for Newcastle Urban Transformation and Transport Program
Newcastle Urban Transformation and Transport Program
The urban renewal projects on former railway land in the Newcastle city centre are well targeted to support the objectives of the Newcastle Urban Transformation and Transport Program (the Program), according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the government. However, the evidence that the cost of the light rail will be justified by its contribution to the Program is not convincing.
The Newcastle Urban Transformation and Transport Program (the Program) is an urban renewal and transport program in the Newcastle city centre. The Hunter and Central Coast Development Corporation (HCCDC) has led the Program since 2017. UrbanGrowth NSW led the Program from 2014 until 2017. Transport for NSW has been responsible for delivering the transport parts of the Program since the Program commenced. All references to HCCDC in this report relate to both HCCDC and its predecessor, the Hunter Development Corporation. All references to UrbanGrowth NSW in this report relate only to its Newcastle office from 2014 to 2017.
This audit had two objectives:
- To assess the economy of the approach chosen to achieve the objectives of the Program.
- To assess the effectiveness of the consultation and oversight of the Program.
We addressed the audit objectives by answering the following questions:
a) Was the decision to build light rail an economical option for achieving Program objectives?
b) Has the best value been obtained for the use of the former railway land?
c) Was good practice used in consultation on key Program decisions?
d) Did governance arrangements support delivery of the program?
1. The urban renewal projects on the former railway land are well targeted to support the objectives of the Program. However, there is insufficient evidence that the cost of the light rail will be justified by its contribution to Program objectives.
The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the Government. HCCDC, and previously UrbanGrowth NSW, identified and considered options for land use that would best meet Program objectives. Required probity processes were followed for developments that involved financial transactions. Our audit did not assess the achievement of these objectives because none of the projects have been completed yet.
Analysis presented in the Program business case and other planning documents showed that the light rail would have small transport benefits and was expected to make a modest contribution to broader Program objectives. Analysis in the Program business case argued that despite this, the light rail was justified because it would attract investment and promote economic development around the route. The Program business case referred to several international examples to support this argument, but did not make a convincing case that these examples were comparable to the proposed light rail in Newcastle.
The audited agencies argue that the contribution of light rail cannot be assessed separately because it is a part of a broader Program. The cost of the light rail makes up around 53 per cent of the total Program funding. Given the cost of the light rail, agencies need to be able to demonstrate that this investment provides value for money by making a measurable contribution to the Program objectives.
2. Consultation and oversight were mostly effective during the implementation stages of the Program. There were weaknesses in both areas in the planning stages.
Consultations about the urban renewal activities from around 2015 onward followed good practice standards. These consultations were based on an internationally accepted framework and met their stated objectives. Community consultations on the decision to close the train line were held in 2006 and 2009. However, the final decision in 2012 was made without a specific community consultation. There was no community consultation on the decision to build a light rail.
The governance arrangements that were in place during the planning stages of the Program did not provide effective oversight. This meant there was not a single agreed set of Program objectives until 2016 and roles and responsibilities for the Program were not clear. Leadership and oversight improved during the implementation phase of the Program. Roles and responsibilities were clarified and a multi-agency steering committee was established to resolve issues that needed multi-agency coordination.
Recommendations
For future infrastructure programs, NSW Government agencies should support economical decision-making on infrastructure projects by:
- providing balanced advice to decision makers on the benefits and risks of large infrastructure investments at all stages of the decision-making process
- providing scope and cost estimates that are as accurate and complete as possible when initial funding decisions are being made
- making business cases available to the public.
The planned uses of the former railway land align with the objectives of encouraging people to visit and live in the city centre, creating attractive public spaces, and supporting growth in employment in the city. The transport benefits of the activities are less clear, because the light rail is the major transport project and this will not make significant improvements to transport in Newcastle.
The processes used for selling and leasing parts of the former railway land followed industry standards. Options for the former railway land were identified and assessed systematically. Competitive processes were used for most transactions and the required assessment and approval processes were followed. The sale of land to the University of Newcastle did not use a competitive process, but required processes for direct negotiations were followed.
Recommendation
By March 2019, the Hunter and Central Coast Development Corporation should:
- work with relevant stakeholders to explore options for increasing the focus on the heritage objective of the Program in projects on the former railway land. This could include projects that recognise the cultural and industrial heritage of Newcastle.
Consultations focusing on urban renewal options for the Program included a range of stakeholders and provided opportunities for input into decisions about the use of the former railway land. These consultations received mostly positive feedback from participants. Changes and additions were made to the objectives of the Program and specific projects in response to feedback received.
There had been several decades of debate about the potential closure of the train line, including community consultations in 2006 and 2009. However, the final decision to close the train line was made and announced in 2012 without a specific community consultation. HCCDC states that consultation with industry and business representatives constitutes community consultation because industry representatives are also members of the community. This does not meet good practice standards because it is not a representative sample of the community.
There was no community consultation on the decision to build a light rail. There were subsequent opportunities for members of the community to comment on the implementation options, but the decision to build it had already been made. A community and industry consultation was held on which route the light rail should use, but the results of this were not made public.
Recommendation
For future infrastructure programs, NSW Government agencies should consult with a wide range of stakeholders before major decisions are made and announced, and report publicly on the results and outcomes of consultations.
The governance arrangements that were in place during the planning stages of the Program did not provide effective oversight. Project leadership and oversight improved during the implementation phase of the Program.
Multi-agency coordination and oversight were ineffective during the planning stages of the Program. Examples include: multiple versions of Program objectives being in circulation; unclear reporting lines for project management groups; and poor role definition for the initial advisory board. Program ownership was clarified in mid-2016 with the appointment of a new Program Director with clear accountability for the delivery of the Program. This was supported by the creation of a multi-agency steering committee that was more effective than previous oversight bodies.
The limitations that existed in multi-agency coordination and oversight had some negative consequences in important aspects of project management for the Program. This included whole-of-government benefits management and the coordination of work to mitigate impacts of the Program on small businesses.
Recommendations
For future infrastructure programs, NSW Government agencies should:
- develop and implement a benefits management approach from the beginning of a program to ensure responsibility for defining benefits and measuring their achievement is clear
- establish whole-of-government oversight early in the program to guide major decisions. This should include:
- agreeing on objectives and ensuring all agencies understand these
- clearly defining roles and responsibilities for all agencies
- establishing whole-of-government coordination for the assessment and mitigation of the impact of major construction projects on businesses and the community.
By March 2019, the Hunter and Central Coast Development Corporation should update and implement the Program Benefits Realisation Plan. This should include:
- setting measurable targets for the desired benefits
- clearly allocating ownership for achieving the desired benefits
- monitoring progress toward achieving the desired benefits and reporting publicly on the results.
Appendix one - Response from agencies
Appendix two - About the audit
Appendix three - Performance auditing
Parliamentary reference - Report number #310 - released 12 December 2018
Actions for Central Agencies 2018
Central Agencies 2018
The Auditor-General for New South Wales, Margaret Crawford, released her report today on the results of the financial audits of NSW Government central agencies. The report focuses on key observations and findings from the most recent financial statement audits of agencies in the Treasury, Premier and Cabinet, and Finance, Services and Innovation clusters. While clear audit opinions were issued on all agency financial statements, the report notes that some complex accounting requirements caused significant errors in agency financial statements submitted for audit, which were corrected before the financial statements were approved.
This report analyses the results of our audits of the Treasury, Premier and Cabinet and Finance, Services and Innovation cluster agencies for the year ended 30 June 2018. The table below summarises our key observations.
This report provides parliament and other users of the NSW Government's central agencies and their cluster agencies financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:
- financial reporting
- audit observations
- liquidity risk management
- government financial services.
The central agencies and their key responsibilities are set out below.
Central agencies | Key central agency responsibilities | Cluster responsibilities |
The Treasury |
|
The cluster:
|
Department of Premier and Cabinet |
|
The cluster:
|
Department of Finance, Services and Innovation |
|
The cluster:
|
Public Service Commission |
|
|
A full list of agencies that this report covers by relevant cluster is included in Appendix three.
Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.
This chapter outlines our audit observations related to the financial reporting of agencies in the Treasury, Premier and Cabinet and Finance, Services and Innovation clusters for 2018.
Observation | Conclusions and recommendations |
2.1 Quality of financial reporting | |
Unqualified opinions were issued for all agencies' financial statements submitted to the Audit Office. Complex accounting requirements caused significant errors in some agency financial statements, which were corrected before the financial statements were approved. |
Sufficient audit evidence was obtained to conclude the financial statements were free of material misstatement. Recommendation: Agencies should respond to key accounting issues when they are identified by preparing accounting papers and engaging with Treasury, the Audit Office and their Audit and Risk Committee when these matters are identified. |
2.2 Timeliness of financial reporting | |
Most agencies complied with the statutory timeframe for completion of early close procedures, 48 agencies in the Treasury cluster did not comply with the statutory requirement to prepare financial statements, and the audits of nine agencies in the Treasury cluster were not completed within the statutory timeframe. All financial statement information of the 48 agencies that did not prepare financial statements has been captured in the consolidated financial statements of their parent entity, which was subject to audit. |
Early close procedures allow financial reporting issues and risks to be addressed early in the audit process. The timeliness of financial reporting can be improved by performing more robust early close procedures. |
Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.
This chapter outlines our observations and insights from:
- our financial statement audits of agencies in the Treasury, Premier and Cabinet and Finance, Services and Innovation cluster for 2018
- the areas of focus identified in the Audit Office work program.
The Audit Office work program provides a summary of all audits to be conducted within the proposed time period as well as detailed information on the areas of focus for each of the NSW Government clusters.
Observation | Conclusions and recommendations |
3.1 Internal controls | |
The 2017–18 audits found one high risk issue and 83 moderate risk issues across the agencies. Nineteen per cent of all issues were repeat issues. | Agencies should focus on rectifying repeat issues. |
The high risk issue at Service NSW related to several deficiencies in procurement and contract management processes. | Service NSW may not be achieving value-for-money from their procurement and contract management activities. The high risk issue should be rectified as a matter of priority. This includes updating and implementing its procurement, vendor and contract management frameworks and delivering training to key staff involved in procurement and contract management activities. |
Property NSW has implemented several controls during the year to rectify the high risk issue identified last year related to its transition to a new property and facility management service provider. However, the service providers performance remains below expectations and there are further opportunities to improve oversight and lift performance. | Property NSW can better define roles and accountabilities with the service provider and formalise policies and processes associated with its monitoring and oversight of the service provider. Implementing relevant KPIs, receiving timely reports and providing timely review and feedback to the service provider may help to lift performance. |
GovConnect received unqualified opinions from their service auditor on all business process controls, except for information technology controls provided by Unisys, where a qualified opinion was received from the service auditor. A qualified opinion was received because of several deficiencies in user access controls. | These internal control deficiencies increase the risk of unauthorised access to key business systems, and increase audit effort and costs associated with addressing the risks arising from the deficiencies. |
3.2 Audit Office annual work program | |
Remediation of the Barangaroo site is now estimated to cost the Barangaroo Delivery Authority in excess of net $400 million. |
Measuring the remaining costs to remediate requires the use of estimation techniques and judgements, making the actual outcome inherently uncertain. We reviewed evidence to support the provision for remediation, including future costs estimates and this evidence supported management’s estimate. |
The State Insurance Regulatory Authority have administered the refund of $138 million in Green slip refunds to policy holders through Service NSW during 2017–18. At 30 June 2018, $112 million in refunds are yet to be claimed. We reviewed the systems and processes supporting the refund process. While we found that this supports the disbursement of refunds to policyholders there were some deficiencies in Service NSW’s project controls when the program was being developed. |
Service NSW should apply the lessons learnt from this program to other programs it is delivering or will be delivering for agencies. |
Revenue NSW recorded $30.4 billion from taxes, fines and fees in 2017–18 ($30.0 billion in 2016–17) to support the State’s finances. |
Crown revenue has steadily increased over the last five years predominately driven by rises in payroll tax and land tax and responsibility for collection of the Emergency Services Levy transferring to Revenue NSW under the Emergency Services Levy Act 2017 effective from July 2017. |
3.3 Managing maintenance | |
Place Management NSW manages significant commercial and retail leases and maintains public domain spaces and other assets around the harbour foreshore. It has consistently underspent its asset maintenance budget. In 2017–18, asset maintenance expenses were only 34 per cent of budgeted maintenance expense. Currently, Place Management NSW does not use any ratios or benchmarks to determine the adequacy of its maintenance spend or to monitor whether it is achieving its budgeted maintenance program. |
This may be contributing to a high proportion of unplanned maintenance, which Place Management NSW reports was 38 per cent of total maintenance expense in 2017–18. Place Management NSW is outsourcing its property and facilities management function from 1 December 2018 to an external service provider. |
This chapter outlines our audit observations, conclusions and recommendations specific to NSW Government agencies providing financial services.
Observation | Conclusions and recommendation |
5.1 Superannuation funds | |
The SAS Trustee Corporation (STC) Pooled Fund and the Parliamentary Contributory Superannuation (PCS) Fund are not required to comply with the prudential and reporting standards issued by the Australian Prudential Regulation Authority (APRA). However, legislation allows the responsible Minister to prescribe prudential standards, reporting and audit requirements. |
Structured and comprehensive prudential oversight of these Funds is important as they operate in a volatile financial sector, have 103,000 members and manage investments of $43.3 billion. Recommendation: Treasury should consult with the Trustees of the STC Pooled Fund and PCS Fund to prescribe appropriate prudential standards and requirements, including oversight arrangements. |
5.2 Insurance and compensation | |
Nominal Insurer and NSW Self Insurance Corporation investment performance marginally exceeded benchmark over the past five years. | Investment returns can impact on the premiums required to maintain an adequate funding ratio in addition to other factors such as claims experience and discount rates. |
The Workers Compensation Nominal Insurer (Nominal Insurer) and NSW Self Insurance Corporation's net collected premiums and contributions decreased over the past five years. | The insurance schemes' investment performance and stable claim payments have enabled less reliance on net collected premiums and contributions as a source of funding, over the past five years. |
Reforms were introduced to manage the Home Warranty Scheme's financial sustainability risks. | The Home Warranty Scheme has not collected sufficient premiums to fund expected claims costs, since commencing operations in 2011. In 2017–18, the Crown contributed $181 million for historical shortfalls. New reforms started on 1 January 2018 enabling the Scheme to price premiums based on risk. |
Actions for Transport 2018
Transport 2018
The Auditor-General for New South Wales, Margaret Crawford released her report today on key observations and findings from the 30 June 2018 financial statement audits of agencies in the Transport cluster. Unqualified audit opinions were issued for all agencies' financial statements. However, assessing the fair value of the broad range of transport related assets creates challenges.
This report analyses the results of our audits of financial statements of the Transport cluster for the year ended 30 June 2018. The table below summarises our key observations.
This report provides Parliament and other users of the Transport cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:
- financial reporting
- audit observations.
Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.
This chapter outlines our audit observations related to the financial reporting of agencies in the Transport cluster for 2018.
Observation | Conclusions and recommendations |
2.1 Quality of financial reporting | |
Unqualified audit opinions were issued for all agencies' financial statements | Sufficient audit evidence was obtained to conclude the financial statements were free of material misstatement. |
2.2 Key accounting issues | |
Valuation of assets continues to create challenges. Although agencies complied with the requirements of the accounting standards and Treasury policies on valuations, we identified some opportunities for improvements at RMS. |
RMS incorporated data from its asset condition assessments for the first time in the valuation methodology which improved the valuation outcome. Overall, we were satisfied with the valuation methodology and key assumptions, but we noted some deficiencies in the asset data in relation to asset component unit rates and old condition data for some components of assets. Also, a bypass and tunnel were incorrectly excluded from RMS records and valuation process since 2013. This resulted in an increase for these assets’ value by $133 million. The valuation inputs for Wetlands and Moorings were revised this year to better reflect the assets' characteristics resulting in a $98.0 million increase. |
2.3 Timeliness of financial reporting | |
Residual Transport Corporation did not submit its financial statements by the statutory reporting deadline. | Residual Transport Corporation remained a dormant entity with no transactions for the year ended 30 June 2018. |
With the exception of Residual Transport Corporation, all agencies completed early close procedures and submitted financial statements within statutory timeframes. | Early close procedures allow financial reporting issues and risks to be addressed early in the reporting and audit process. |
2.4 Financial sustainability | |
NSW Trains and the Chief Investigator of the Office of Transport Safety Investigations reported negative net assets of $75.7 million and $89,000 respectively at 30 June 2018. | NSW Trains and the Chief Investigator of the Office of Transport Safety Investigations continue to require letters of financial support to confirm their ability to pay liabilities as they fall due. |
2.5 Passenger revenue and patronage | |
Transport agencies revenue growth increased at a higher rate than patronage. | Public transport passenger revenue increased by $114 million (8.3 per cent) in 2017–18, and patronage increased by 37.1 million (5.1 per cent) across all modes of transport based on data provided by TfNSW. |
Negative balance Opal Cards resulted in $3.8 million in revenue not collected in 2017–18 and $7.8 million since the introduction of Opal. A total of 1.1 million Opal cards issued since its introduction have negative balances. | Transport for NSW advised it is liaising with the ticketing vendor to implement system changes and are investigating other ways to reduce the occurrences. |
2.6 Cost recovery from public transport users | |
Overall cost recovery from users has decreased. | Overall cost recovery from public transport users (on rail and bus services by STA) decreased from 23.2 per cent to 22.4 per cent between 2016–17 and 2017–18. The main reason for the decrease is due to expenditure increasing at a faster rate than revenue in 2017–18. |
Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.
This chapter outlines our observations and insights from:
- our financial statement audits of agencies in the Transport cluster for 2018
- the areas of focus identified in the Audit Office annual work program.
The Audit Office Annual Work Program provides a summary of all audits to be conducted within the proposed time period as well as detailed information on the areas of focus for each of the NSW Government clusters.
Observation | Conclusions and recommendations |
3.1 Internal controls | |
There was an increase in findings on internal controls across the Transport cluster. | Key themes related to information technology, employee leave entitlements and asset management. Eighteen per cent of all issues were repeat issues. |
3.2 Audit Office Annual work program | |
The Transport cluster wrote-off over $200 million of assets which were replaced by new assets or technology. |
Majority of this write-off was recognised by RMS, with $199 million relating to the write-off of existing assets which have been replaced during the year. |
RailCorp is expected to convert to TAHE from 1 July 2019. | Several working groups are considering different aspects of the TAHE transition including its status as a for-profit Public Trading Enterprise and which assets to transfer to TAHE. We will continue to monitor developments on TAHE for any impact to the financial statements. |
RMS' estimated maintenance backlog at 30 June 2018 of $3.4 billion is lower than last year. Sydney Trains' estimated maintenance backlog at 30 June 2018 increased by 20.6 per cent to $434 million. TfNSW does not quantify its backlog maintenance. | TfNSW advised it is liaising with Infrastructure NSW to develop a consistent definition of maintenance backlog across all transport service providers. |
Not all agencies monitor unplanned maintenance across the Transport cluster. | Unplanned maintenance can be more expensive than planned maintenance. TfNSW should develop a consistent approach to define, monitor and track unplanned maintenance across the cluster. |
This chapter outlines certain service delivery outcomes for 2017–18. The data on activity levels and performance is provided by Cluster agencies. The Audit Office does not have a specific mandate to audit performance information. Accordingly, the information in this chapter is unaudited.
We report this information on service delivery to provide additional context to understand the operations of the Transport cluster and to collate and present service information for different modes of transport in one report.
In our recent performance audit, Progress and measurement of Premier's Priorities, we identified 12 limitations of performance measurement and performance data. We recommended that the Department of Premier and Cabinet ensure that processes to check and verify data are in place for all agency data sources.
Actions for Mobile speed cameras
Mobile speed cameras
The primary goal of speed cameras is to reduce speeding and make the roads safer. Our 2011 performance audit on speed cameras found that, in general, speed cameras change driver behaviour and have a positive impact on road safety.
Transport for NSW published the NSW Speed Camera Strategy in June 2012 in response to our audit. According to the Strategy, the main purpose of mobile speed cameras is to reduce speeding across the road network by providing a general deterrence through anywhere, anytime enforcement and by creating a perceived risk of detection across the road network. Fixed and red-light speed cameras aim to reduce speeding at specific locations.
Roads and Maritime Services and Transport for NSW deploy mobile speed cameras (MSCs) in consultation with NSW Police. The cameras are operated by contractors authorised by Roads and Maritime Services. MSC locations are stretches of road that can be more than 20 kilometres long. MSC sites are specific places within these locations that meet the requirements for a MSC vehicle to be able to operate there.
This audit assessed whether the mobile speed camera program is effectively managed to maximise road safety benefits across the NSW road network.
The mobile speed camera program requires improvements to key aspects of its management to maximise road safety benefits. While camera locations have been selected based on crash history, the limited number of locations restricts network coverage. It also makes enforcement more predictable, reducing the ability to provide a general deterrence. Implementation of the program has been consistent with government decisions to limit its hours of operation and use multiple warning signs. These factors limit the ability of the mobile speed camera program to effectively deliver a broad general network deterrence from speeding.
Many locations are needed to enable network-wide coverage and ensure MSC sessions are randomised and not predictable. However, there are insufficient locations available to operate MSCs that meet strict criteria for crash history, operator safety, signage and technical requirements. MSC performance would be improved if there were more locations.
A scheduling system is meant to randomise MSC location visits to ensure they are not predictable. However, a relatively small number of locations have been visited many times making their deployment more predictable in these places. The allocation of MSCs across the time of day, day of week and across regions is prioritised based on crash history but the frequency of location visits does not correspond with the crash risk for each location.
There is evidence of a reduction in fatal and serious crashes at the 30 best-performing MSC locations. However, there is limited evidence that the current MSC program in NSW has led to a behavioural change in drivers by creating a general network deterrence. While the overall reduction in serious injuries on roads has continued, fatalities have started to climb again. Compliance with speed limits has improved at the sites and locations that MSCs operate, but the results of overall network speed surveys vary, with recent improvements in some speed zones but not others.
There is no supporting justification for the number of hours of operation for the program. The rate of MSC enforcement (hours per capita) in NSW is less than Queensland and Victoria. The government decision to use multiple warning signs has made it harder to identify and maintain suitable MSC locations, and impeded their use for enforcement in both traffic directions and in school zones.
Appendix one - Response from agency
Appendix two - About the audit
Appendix three - Performance auditing
Parliamentary reference - Report number #308 - released 18 October 2018
Actions for Regulation of water pollution in drinking water catchments and illegal disposal of solid waste
Regulation of water pollution in drinking water catchments and illegal disposal of solid waste
There are important gaps in how the Environmental Protection Authority (EPA) implements its regulatory framework for water pollution in drinking water catchments and illegal solid waste disposal. This limits the effectiveness of its regulatory responses, according to a report released today by the Auditor-General for New South Wales, Margaret Crawford.
By 31 December 2018, to improve governance and oversight, the EPA should: | |
1. | implement a more effective performance framework with regular reports to the Chief Executive Officer and to the EPA Board on outcomes-based key result areas that assess its environmental and regulatory performance and trends over time |
By 30 June 2019, to improve consistency in its practices, the EPA should: | |
2. | progressively update and make accessible its policies and procedures for regulatory operations, and mandate procedures where necessary to ensure consistent application |
3. | implement internal controls to monitor the consistency and quality of its regulatory operations. |
By 30 June 2019, to address worsening water quality in Lake Burragorang, the EPA should: | |
4. | (a) review the impact of its licensed activities on water quality in Lake Burragorang, and |
(b) develop strategies relating to its licensed activities (in consultation with other relevant NSW Government agencies) to improve and maintain the lake's water quality. |
To improve compliance monitoring, the EPA should implement procedures to: | |
5. | by 30 June 2019, validate self-reported information, eliminate hardcopy submissions and require licensees to report on their breaches of the Act and associated regulations in their annual returns |
6. | by 31 December 2018, conduct mandatory site inspections under the risk-based licensing scheme to assess compliance with all regulatory requirements and licence conditions. |
By 31 December 2018 to improve enforcement, the EPA should: | |
7. | Implement procedures to systematically assess non-compliances with licence conditions and breaches of the Act and to implement appropriate and consistent regulatory actions. |
Appendix one – Response from agency
Appendix two – List of enforcement tools
Appendix three – The EPA's organisational structure
Appendix four – The EPA's regions and branches
Appendix five – About the audit
Appendix six – Performance auditing
Parliamentary reference - Report number #304 - released 28 June 2018
Actions for Regional Assistance Programs
Regional Assistance Programs
Infrastructure NSW effectively manages how grant applications for regional assistance programs are assessed and recommended for funding. Its contract management processes are also effective. However, we are unable to conclude whether the objectives of these programs have been achieved as the relevant agencies have not yet measured their benefits, according to a report released today by the Auditor-General for New South Wales, Margaret Crawford.
In 2011, the NSW Government established Restart NSW to fund new infrastructure with the proceeds from the sale and lease of government assets. From 2011 to 2017, the NSW Government allocated $1.7 billion from the fund for infrastructure in regional areas, with an additional commitment of $1.3 billion to be allocated by 2021. The NSW Government allocates these funds through regional assistance programs such as Resources for Regions and Fixing Country Roads. NSW councils are the primary recipients of funding provided under these programs.
The NSW Government announced the Resources for Regions program in 2012 with the aim of addressing infrastructure constraints in mining affected communities. Infrastructure NSW administers the program, with support from the Department of Premier and Cabinet.
The NSW Government announced the Fixing Country Roads program in 2014 with the aim of building more efficient road freight networks. Transport for NSW and Infrastructure NSW jointly administer this program, which funds local councils to deliver projects that help connect local and regional roads to state highways and freight hubs.
This audit assessed whether these two programs (Resources for Regions and Fixing Country Roads) were being effectively managed and achieved their objectives. In making this assessment, we answered the following questions:
- How well are the relevant agencies managing the assessment and recommendation process?
- How do the relevant agencies ensure that funded projects are being delivered?
- Do the funded projects meet program and project objectives?
The audit focussed on four rounds of Resources for Regions funding between 2013–14 to 2015–16, as well as the first two rounds of Fixing Country Roads funding in 2014–15 and 2015–16.
The project selection criteria are consistent with the program objectives set by the NSW Government, and the RIAP applied the criteria consistently. Probity and record keeping practices did not fully comply with the probity plans.
The assessment methodology designed by Infrastructure NSW is consistent with2 the program objectives and criteria. In the rounds that we reviewed, all funded projects met the assessment criteria.
Infrastructure NSW developed probity plans for both programs which provided guidance on the record keeping required to maintain an audit trail, including the use of conflict of interest registers. Infrastructure NSW and Transport for NSW did not fully comply with these requirements. The relevant agencies have taken steps to address this in the current funding rounds for both programs.
NSW Procurement Board Directions require agencies to ensure that they do not engage a probity advisor that is engaged elsewhere in the agency. Infrastructure NSW has not fully complied with this requirement. A conflict of interest arose when Infrastructure NSW engaged the same consultancy to act as its internal auditor and probity advisor.
While these infringements of probity arrangements are unlikely to have had a major impact on the assessment process, they weaken the transparency and accountability of the process.
Some councils have identified resourcing and capability issues which impact on their ability to participate in the application process. For both programs, the relevant agencies conducted briefings and webinars with applicants to provide advice on the objectives of the programs and how to improve the quality of their applications. Additionally, Transport for NSW and the Department of Premier and Cabinet have developed tools to assist councils to demonstrate the economic impact of their applications.
The relevant agencies provided feedback on unsuccessful applications to councils. Councils reported that the quality of this feedback has improved over time.
Recommendations
- By June 2018, Infrastructure NSW should:
- ensure probity reports address whether all elements of the probity plan have been effectively implemented.
- By June 2018, Infrastructure NSW and Transport for NSW should:
- maintain and store all documentation regarding assessment and probity matters according to the State Records Act 1998, the NSW Standard on Records Management and the relevant probity plans
Infrastructure NSW is responsible for overseeing and monitoring projects funded under Resources for Regions and Fixing Country Roads. Infrastructure NSW effectively manages projects to keep them on track, however it could do more to assure itself that all recipients have complied with funding deeds. Benefits and outcomes should also start to be measured and reported as soon as practicable after projects are completed to inform assessment of future projects.
Infrastructure NSW identifies projects experiencing unreasonable delays or higher than expected expenses as 'at‑risk'. After Infrastructure NSW identifies a project as 'at‑risk', it puts in place processes to resolve issues to bring them back on track. Infrastructure NSW, working with Public Works Advisory regional offices, employs a risk‑based approach to validate payment claims, however this process should be strengthened. Infrastructure NSW would get better assurance by also conducting annual audits of compliance with the funding deed for a random sample of projects.
Infrastructure NSW collects project completion reports for all Resources for Regions and Fixing Country Roads funded projects. It applies the Infrastructure Investor Assurance Framework to Resources for Regions and Fixing Country Roads at a program level. This means that each round of funding (under both programs) is treated as a distinct program for the purposes of benefits realisation. It plans to assess whether benefits have been realised once each project in a funding round is completed. As a result, no benefits realisation assessment has been done for any project funded under either Resources for Regions or Fixing Country Roads. Without project‑level benefits realisation, future decisions are not informed by the lessons from previous investments.
Recommendations
- By December 2018, Infrastructure NSW should:
- conduct annual audits of compliance with the funding deed for a random sample of projects funded under Resources for Regions and Fixing Country Roads
- publish the circumstances under which unspent funds can be allocated to changes in project scope
- measure benefits delivered by projects that were completed before December 2017
- implement an annual process to measure benefits for projects completed after December 2017
- By December 2018, Transport for NSW and Infrastructure NSW should:
- incorporate a benefits realisation framework as part of the detailed application.
Appendix one - Response from agencies
Appendix two - Maps of funded projects
Appendix three - About the audit
Appendix four - Performance auditing
Parliamentary reference - Report number #300 - released 17 May 2018
Actions for Managing risks in the NSW public sector: risk culture and capability
Managing risks in the NSW public sector: risk culture and capability
The Ministry of Health, NSW Fair Trading, NSW Police Force, and NSW Treasury Corporation are taking steps to strengthen their risk culture, according to a report released today by the Auditor-General, Margaret Crawford. 'Senior management communicates the importance of managing risk to their staff, and there are many examples of risk management being integrated into daily activities', the Auditor-General said.
We did find that three of the agencies we examined could strengthen their culture so that all employees feel comfortable speaking openly about risks. To support innovation, senior management could also do better at communicating to their staff the levels of risk they are willing to accept.
Effective risk management is essential to good governance, and supports staff at all levels to make informed judgements and decisions. At a time when government is encouraging innovation and exploring new service delivery models, effective risk management is about seizing opportunities as well as managing threats.
Over the past decade, governments and regulators around the world have increasingly turned their attention to risk culture. It is now widely accepted that organisational culture is a key element of risk management because it influences how people recognise and engage with risk. Neglecting this ‘soft’ side of risk management can prevent institutions from managing risks that threaten their success and lead to missed opportunities for change, improvement or innovation.
This audit assessed how effectively NSW Government agencies are building risk management capabilities and embedding a sound risk culture throughout their organisations. To do this we examined whether:
- agencies can demonstrate that senior management is committed to risk management
- information about risk is communicated effectively throughout agencies
- agencies are building risk management capabilities.
The audit examined four agencies: the Ministry of Health, the NSW Fair Trading function within the Department of Finance, Services and Innovation, NSW Police Force and NSW Treasury Corporation (TCorp). NSW Treasury was also included as the agency responsible for the NSW Government's risk management framework.
In assessing an agency’s risk culture, we focused on four key areas:
Executive sponsorship (tone at the top)
In the four agencies we reviewed, senior management is communicating the importance of managing risk. They have endorsed risk management frameworks and funded central functions tasked with overseeing risk management within their agencies.
That said, we found that three case study agencies do not measure their existing risk culture. Without clear measures of how employees identify and engage with risk, it is difficult for agencies to tell whether employee's behaviours are aligned with the 'tone' set by the executive and management.
For example, in some agencies we examined we found a disconnect between risk tolerances espoused by senior management and how these concepts were understood by staff.
Employee perceptions of risk management
Our survey of staff indicated that while senior leaders have communicated the importance of managing risk, more could be done to strengthen a culture of open communication so that all employees feel comfortable speaking openly about risks. We found that senior management could better communicate to their staff the levels of risk they should be willing to accept.
Integration of risk management into daily activities and links to decision-making
We found examples of risk management being integrated into daily activities. On the other hand, we also identified areas where risk management deviated from good practice. For example, we found that corporate risk registers are not consistently used as a tool to support decision-making.
Support and guidance to help staff manage risks
Most case study agencies are monitoring risk-related skills and knowledge of their workforce, but only one agency has addressed the gaps it identified. While agencies are providing risk management training, surveyed staff in three case study agencies reported that risk management training is not adequate.
NSW Treasury provides agencies with direction and guidance on risk management through policy and guidelines. In line with better practice, NSW Treasury's principles-based policy acknowledges that individual agencies are in a better position to understand their own risks and design risk management frameworks that address those risks. Nevertheless, there is scope for NSW Treasury to refine its guidance material to support a better risk culture in the NSW public sector.
Recommendation
By May 2019, NSW Treasury should:
- Review the scope of its risk management guidance, and identify additional guidance, training or activities to improve risk culture across the NSW public sector. This should focus on encouraging agency heads to form a view on the current risk culture in their agencies, identify desirable changes to that risk culture, and take steps to address those changes.
Appendix one - Response from agencies
Appendix three - About the audit
Appendix four - Performance auditing
Parliamentary reference - Report number #298 - released 23 April 2018
Actions for Liverpool to Parramatta Bus Transitway
Liverpool to Parramatta Bus Transitway
Several of my recent audits have identified a need to improve our public transport system – both for the benefit of travellers and to assist in achieving better air quality.
Bus Transitways can provide a good public transport solution for lower density population areas, potentially at a relatively low capital cost. This audit examines the transitway running between Liverpool and Parramatta, the first of several planned for Sydney. This audit should contribute to a better understanding of the lessons learnt from this first project, and so to future transitways providing better value for money.
But this audit also raises broader issues.
It highlights the importance of accurately projecting the total cost of major infrastructure projects before governments lock in their decisions. It also highlights the need for sound decision-making processes when government agencies compete with the private sector. The principles and recommendations flowing from these issues are ones I would draw to the attention of all agencies, and to the Government.
Parliamentary reference - Report number #146 - released 5 December 2005