Reports
Actions for WestConnex: Assurance to the Government
WestConnex: Assurance to the Government
This audit assesses the assurance provided to the NSW Government for the initial stages of the WestConnex project. The audit examined the WestConnex project from concept development to the pre-tender phase for Stage 1A – M4 (Parramatta to Homebush Bay). It did not examine the merit of the project or whether it represented value-for-money. This audit found a number of shortcomings with the governance of the WestConnex project during its early stages and
Actions for Making the Most of Government Purchasing Power - Telecommunications
Making the Most of Government Purchasing Power - Telecommunications
The Auditor-General has found that agencies have consistently failed to negotiate the best price for their telecommunication contracts and are not getting value for money because of inadequate contract and expense management processes. The audit examined six agencies to assess whether the government was getting value for money from its telecommunications contracts. It again raised problems with the way NSW government agencies manage contracts.
Actions for Use of Purchasing Cards and Electronic Payment Methods
Use of Purchasing Cards and Electronic Payment Methods
NSW government agencies are not making sufficient use of purchasing cards and EFTs to pay for goods and services. There are potential savings in processing costs of around $22 per transaction from purchasing cards and over $7 when using EFTs instead of cheques. Parliamentary reference - Report number #243 - released 5 June 2014
Actions for Regional Road Funding - Block Grant and REPAIR Programs
Regional Road Funding - Block Grant and REPAIR Programs
In 2013–14, Roads and Maritime Services (RMS) provided over $170 million to local councils through the Block Grant and REPAIR programs to spend on Regional Roads. Regional Roads are the link between State Roads and Local Roads. Parliamentary reference - Report number #241 - released 8 May 2014
Actions for Outsourcing Information Technology
Outsourcing Information Technology
Agencies have managed the planning of outsourcing in a competent way. All agencies satisfactorily managed the contractual aspects of outsourcing. The Audit Office is of the opinion, however, that there is no objective evidence to demonstrate that agencies have achieved their goals in outsourcing IT. Most agencies had identified the current and expected costs and risks of outsourcing. Agencies were not able to demonstrate that the actual costs of outsourc
Actions for Bus Maintenance and Bus Contracts
Bus Maintenance and Bus Contracts
State Transit has developed fleet management plans and maintenance standards that meet its regulatory and contractual obligations as a bus operator and are consistent with vehicle manufacturers’ standards and best practice. However, assumptions used in fleet management plans to forecast fleet growth may not result in the most efficient and effective outcome for State Transit. Forecasts fail to take account of opportunities to redesign or reduce services
Actions for Government Property Register
Government Property Register
Despite the issue being on the agenda for many years (formally, at least since 1988), at present there is not a comprehensive record of all government property assets in NSW. Whilst initiatives currently underway are promising, they will require continued priority to achieve tangible results. And careful coordination will be required to avoid duplication and waste. Parliamentary reference - Report number #93 - released 31 January 2002