Reports
Actions for Volume Nine 2015 Planning and Environment
Volume Nine 2015 Planning and Environment
The NSW Environment Protection Authority has reduced the average time to assess contaminated sites from 203 days in 2013-14 to 73 days in 2014-15. It is also improving transparency by making more information on its performance publicly available.
In 2014-15, the Department of Planning and Environment increased new housing approvals across New South Wales by 12 per cent to 58,252, exceeding the State priority target of 50,000. It also reduced the time taken to assess major projects from about three years in 2013-14 to four months in 2014-15.
Actions for Volume Eight 2015 Family and Community Services
Volume Eight 2015 Family and Community Services
Placement reviews are not undertaken for all children and young people in statutory care. Caseworkers are required to review placements annually to assess the health, wellbeing, education and social life of the child. Over three-quarters of children and young people received placement reviews in 2014-15 compared to about half of them in the previous twelve months.
Actions for Community Housing
Community Housing
On 16 September 2015 the NSW Acting Auditor-General, Tony Whitfield, released a report on community housing. The audit examines the Department of Family and Community Services’ transfer of public housing to non-government community housing providers.
The Department has worked collaboratively with community housing providers and industry groups to develop the community housing sector. Although there have been some delays, it has managed the transfer of public housing reasonably well and has improved the sustainability of the sector.
Parliamentary reference - Report number #259 - released 16 September 2015
Actions for Transferring out-of-home care to non-government organisations
Transferring out-of-home care to non-government organisations
The audit assessed how well the Department of Family and Community Services has transferred the management of children in out-of-home care to non-government organisations (NGOs).
The Department has put considerable effort into developing the out-of-home care sector and is progressing well towards its goal of transferring all children in statutory care to NGOs. Since 2011, the number of children with an accredited NGO has more than doubled. This is a positive outcome as children are more likely to receive quality care because these providers meet NSW standards for outof-home care.
However, it is difficult to assess whether overall outcomes for children in care have improved. This is because the Department has yet to determine what wellbeing outcomes it wants to achieve, such as improvements in a child’s health, education and welfare. The Department is currently developing a quality assurance framework which will include such outcomes. We also found that the number of children in care returned to their birth family has declined, and the number of adoptions has remained relatively unchanged.
Parliamentary reference - Report number #257 - released 2 September 2015
Actions for Identifying productivity in the public sector
Identifying productivity in the public sector
This report examines selected areas of government activity to see if sufficient information was available to identify and assess changes in productivity. The areas examined were primary and secondary school public education, acute inpatient care in NSW public hospitals, CityRail, the NSW Police Force, and the NSW Local Court.
Productivity is commonly defined as the amount of output per unit of input.
Parliamentary reference - Report number #256 - released 16 July 2015
Actions for Implementing performance audit recommendations
Implementing performance audit recommendations
NSW Government agencies have sound processes for implementing performance audit recommendations in Auditor-General’s Reports to Parliament. There are many cases of good practice. For example, some agencies formed a steering committee and developed a detailed plan to implement recommendations. Another incorporated the implementation of recommendations into both its business plan and the work plans of individual officers who were managing projects. Most agencies also used their Audit and Risk Committees to monitor recommendations.
We found some cases where agencies can improve how they coordinate actions to address recommendations. Most agencies were not revisiting these actions to determine whether they remain appropriate.
Parliamentary reference - Report number #254 - released 24 June 2015
Actions for Large construction projects
Large construction projects
The independent assurance given to the NSW Government and sponsor agencies on the viability of large capital projects throughout their lifecycle is inadequate. Government policy is regularly not followed and not properly communicated to those responsible for implementing such policy.
This audit sought to test the effectiveness of the NSW capital project assurance system - which includes gateway reviews and reporting - but significant levels of non-compliance identified in our case studies prevented this. The NSW Commission of Audit also identified this issue in 2012. Gateway reviews are conducted by independent reviewers at key stages of a project’s life cycle and provide an independent assessment on a project’s readiness to proceed to the next stage.
Parliamentary reference - Report number #252 - released 7 May 2015
Actions for Country towns water supply and sewerage program
Country towns water supply and sewerage program
The Country Towns Water Supply and Sewerage Program has effectively promoted adoption of better management practices by local water utilities, but will not achieve its objective of eliminating the water supply and sewerage infrastructure backlog in urban areas of country NSW.
The $1.2 billion Program aims to help local water utilities provide appropriate, affordable, cost effective and well-managed water supply and sewerage services in the urban areas of country NSW. It has two broad elements:
- promoting adoption of better practices
- providing financial assistance towards the capital cost of infrastructure backlog works.
Parliamentary reference - Report number #251 - released 4 May 2015
Actions for Areas of focus from 2014
Areas of focus from 2014
Actions for Security of critical IT infrastructure
Security of critical IT infrastructure
Roads and Maritime Services and Transport for NSW have deployed many controls to protect traffic management systems but these would have been only partially effective in detecting and preventing incidents and unlikely to support a timely response. There was a potential for unauthorised access to sensitive information and systems that could have disrupted traffic.
Until Roads and Maritime Services’ IT disaster recovery site is fully commissioned, a disaster involving the main data centre is likely to lead to higher congestion in the short-term as traffic controllers would be operating on a regional basis without the benefit of the Traffic Management Centre.
Parliamentary reference - Report number #248 - released 21 January 2015