Actions for Volume Ten 2010 focus on Education and Communities

Volume Ten 2010 focus on Education and Communities

Education
Community Services
Asset valuation
Compliance
Financial reporting
Internal controls and governance
Management and administration
Procurement
Project management
Workforce and capability

The report includes a review on the Building the Education Revolution and outcomes of his financial audits on NSW Government agencies for Education and Communities 2009-10. Whilst the Department of Education appears to have achieved its key objective of rapidly constructing school facilities, costs were higher than business as usual and the preferences of local communities were not always met.

Published

Actions for Volume Nine 2010 focus on Transport, Planning and Industry

Volume Nine 2010 focus on Transport, Planning and Industry

Transport
Planning
Industry
Asset valuation
Compliance
Internal controls and governance
Management and administration
Procurement
Project management
Regulation
Risk
Workforce and capability

The report includes comments on his financial audits of NSW Government transport, planning and industry agencies for 2009-10. A key recommendation from the report is that the New South Wales Government identify lessons learnt from the metro experience and ensure that future decision processes are developed to ensure the State never again expends such a large amount of scarce transport funding dollars and valuable time on a project that does not proceed.

Published

Actions for Volume Seven 2010 focus on Environment, Climate Change and Water

Volume Seven 2010 focus on Environment, Climate Change and Water

Planning
Industry
Environment
Compliance
Information technology
Management and administration
Project management
Regulation
Workforce and capability

The report includes comments on his financial audits of NSW Government environment, climate change and water agencies. The audits of these agencies’ financial reports for the year ended 30 June 2010 resulted in one qualified Independent Auditor’s Report. Sydney Water has not recognised assets and liabilities of the Build-Own-Operate schemes in their statement of financial position. The combined profit after tax of the four largest water utilities increased substantially from $300 million in 2008-09 to $584 million in 2009-10. Distributions to the Government were $379 million up 17 per cent or $55 million from last year.

Published

Actions for Protecting the Environment: Pollution Incidents

Protecting the Environment: Pollution Incidents

Planning
Environment
Compliance
Management and administration
Regulation
Risk

The department has a systematic approach to receiving, investigating and responding to reports of pollution incidents. However, the department does not analyse and report on the extent of environmental harm caused by pollution incidents reported to it, whether its response has minimised harm to the environment, whether its regulatory approach has improved compliance, particularly by Environment Protection Licence (EPL) holders (licensees).

 

Parliamentary reference - Report number #205 - released 15 September 2010

Published

Actions for Knowing the Collections

Knowing the Collections

Planning
Environment
Asset valuation
Internal controls and governance
Management and administration

The Museum is doing much to improve access to its collections. However, as with other natural history museums, only a small proportion is on public display. Its efforts range from placing information on the internet for use by the public and scientific users, to helping indigenous Australian and Pacific Islander communities reconnect with their respective cultures.

 

Parliamentary reference - Report number #203 - released 1 September 2010

Published

Actions for Severance Payments to Special Temporary Employees

Severance Payments to Special Temporary Employees

Premier and Cabinet
Compliance
Internal controls and governance
Management and administration
Workforce and capability

In reviewing both the severance pay guidelines and a sample of payments, we found the guidelines to be clear and all except two payments were made in accordance with them. In these two cases the severance payment was stipulated in the employment contract guaranteeing the STE a minimum of six months pay on termination, irrespective of the length of service.

 

Parliamentary reference - Report number #201 - released 16 June 2010

Published

Actions for Access to Overnight Centre-Based Disability Respite

Access to Overnight Centre-Based Disability Respite

Community Services
Management and administration
Service delivery

We found that ADHC is providing and funding more respite to help people with disabilities and their carers. The number of people using respite centres increased by 20 per cent between 2006-07 and 2008-09 from 2,769 to 3,326. Both NGOs and carer organisations told us that ADHC had improved the management of respite.

 

Parliamentary reference - Report number #200 - released 5 May 2010

Published

Actions for Working With Children Check

Working With Children Check

Community Services
Compliance
Internal controls and governance
Management and administration
Regulation
Risk
Workforce and capability

To be effective the WWCC has to be thorough. Gaps in the checking process such as employers not checking everyone they should mean that people who may pose a risk to children are not identified. We found that the WWCC does not reliably identify all those who may pose a risk to children. Audit conclusion and recommendations Working With Children Check 3 In addition, we found the Commission does not monitor the compliance of employers, the self-employed or volunteer organisations with their obligations or have a formal strategy to promote awareness of the WWCC.

 

Parliamentary reference - Report number #196 - released 24 February 2010