Actions for Planning, Industry and Environment 2021

Planning, Industry and Environment 2021

Environment
Industry
Local Government
Planning
Asset valuation
Financial reporting
Information technology
Internal controls and governance
Risk

This report analyses the results of our audits of the Planning, Industry and Environment cluster agencies for the year ended 30 June 2021.

Our preferred approach is to table the ‘Report on State Finances’ in Parliament before any other cluster report. This is because the 'Report on State Finances' focuses on the audit results and observations relating to the Total State Sector Accounts, in effect a consolidation of all government agencies. This year the 'Report on State Finances' has been delayed due to significant accounting issues being considered in the Total State Sector Accounts and which may impact the Treasury and Transport clusters.

As there are no outstanding matters relating to audits in the Planning, Industry and Environment cluster impacting the Total State Sector Accounts we have decided to break with normal practice and table this cluster report ahead of the ‘Report on State Finances’.

What the report is about

The results of the Planning, Industry and Environment cluster agencies' financial statements audits for the year ended 30 June 2021.

What we found

Unmodified audit opinions were issued for all completed 30 June 2021 financial statements audits of cluster agencies. Three audits are ongoing.

An 'Other Matter' paragraph was included in the Independent Planning Commission's (the IPC) audit opinion because the prior year comparative figures were not audited. Prior to 2020–21, the IPC was not required to prepare separate financial statements under the Public Finance and Audit Act 1983 (PF&A Act). The financial reporting provisions of the Government Sector Finance Act 2018 now require the IPC to prepare financial statements.

The number of identified misstatements increased from 51 in 2019–20 to 54 in 2020–21.

The 2010–11 to 2019–20 audits of the Water Administration Ministerial Corporation’s (the Corporation) financial statements are incomplete due to insufficient records and evidence to support the transactions of the Corporation, particularly for the earlier years. Management has commenced actions to improve the governance and financial management of the Corporation. These audits are currently in progress and the 2020–21 audit will commence shortly.

There are 609 State controlled Crown land managers (CLMs) across New South Wales that predominantly manage small parcels of Crown land.

Eight CLMs prepared and submitted 2019–20 financial statements by the revised deadline of 30 June 2021. A further 24 CLMs did not prepare financial statements in accordance with the PF&A Act. The remaining CLMs were not required to prepare 2019–20 financial statements as they met NSW Treasury's financial reporting exemption criteria.

The Department of Planning, Industry and Environment's (the department) preliminary assessment indicates that 60 CLMs are required to prepare financial statements in 2020–21. To date, no CLMs have prepared and submitted financial statements for audit in 2020–21.

There are also 120 common trusts that have never submitted financial statements for audit. Common trusts are responsible for the care, control and management of land that has been set aside for specific use in a certain locality, such as grazing, camping or bushwalking.

What the key issues were

The number of matters we reported to management increased from 135 in 2019–20 to 180 in 2020–21, of which 40 per cent were repeat findings.

Seven high-risk issues were identified in 2020–21:

  • system control deficiencies at the department relating to user access to HR and payroll management systems, vendor master data management and journal processing, which require manual reviews to mitigate risks
  • deficiencies related to the Centennial Park and Moore Park Trust's tree assets valuation methodology
  • the Lord Howe Island Board did not regularly review and monitor privileged user access rights to key information systems
  • the Natural Resources Access Regulator identified and adjusted three prior period errors retrospectively, which indicate deficiencies within the financial reporting processes
  • deficiencies relating to the Parramatta Park Trust's tree assets valuation methodology
  • lease arrangements have not been confirmed between the Planning Ministerial Corporation and Office of Sport regarding the Sydney International Regatta Centre
  • the Wentworth Park Sporting Complex land manager (the land manager) has a $6.5 million loan with Greyhound Racing NSW (GRNSW). GRNSW requested the land manager to repay the loan. However, the land manager subsequently requested GRNSW to convert the loan to a grant. Should this request be denied, the land manager would not be able to continue as a going concern without financial support. This matter remains unresolved for many years.

There continues to be significant deficiencies in Crown land records. The department uses the Crown Land Information Database (CLID) to record key information relating to Crown land in New South Wales that are managed and controlled by the department and land managers (including councils and land managers controlled by the state). The CLID system was not designed to facilitate financial reporting and the department is required to conduct extensive adjustments and reconciliations to produce accurate information for the financial statements.

The department is implementing a new system to record Crown land (the CrownTracker project). The department advised that the project completion date will be confirmed by June 2022.

What we recommended

The department should ensure CLMs and common trusts meet their statutory reporting obligations.

Cluster agencies should prioritise and action recommendations to address internal control deficiencies, with a focus on addressing high-risk and repeat issues.

The department should prioritise action to ensure the Crown land database is complete and accurate. This will allow the department and CLMs to be better informed about the Crown land they control.

Fast facts

The Planning, Industry and Environment cluster aims to make the lives of people in New South Wales better by developing well-connected communities, preserving the environment, supporting industries and contributing to a strong economy.

There are 54 agencies, 609 State controlled Crown land managers that predominantly manage small parcels of Crown land and 120 common trusts in the cluster.

  • 42% of the area of NSW is Crown land
  • $33.2b water and electricity infrastructure as at 30 June 2021
  • 100% unqualified audit opinions were issued for all completed 30 June 2021 financial statements audits
  • 7 high-risk management letter findings were identified
  • 54 monetary misstatements were reported in 2020–21
  • 40% of reported issues were repeat issues

This report provides parliament and other users of the Planning, Industry and Environment cluster (the cluster) agencies’ financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision-making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Planning, Industry and Environment cluster (the cluster) for 2021.

Section highlights

  • Unmodified audit opinions were issued for all completed 30 June 2021 financial statements audits of cluster agencies. Three audits are ongoing.
  • An 'Other Matter' paragraph was included in the Independent Planning Commission’s (the IPC) audit opinion because the prior year comparative figures were not audited. Prior to 2020–21, the IPC was not required to prepare separate financial statements under the Public Finance and Audit Act 1983. From 2020–21, the IPC is required to prepare financial statements under the Government Sector Finance Act 2018.
  • The 2010–11 to 2019–20 audits of the Water Administration Ministerial Corporation’s (the Corporation) financial statements were incomplete due to insufficient records and evidence to support the transactions of the Corporation, particularly for the earlier years. These audits are currently underway, and the 2020–21 audit will commence shortly.
  • The Department of Planning, Industry and Environment's (the department) preliminary assessment indicates that 60 State controlled Crown land managers (CLMs) are required to prepare financial statements in 2020–21. To date, no CLMs have prepared and submitted financial statements for audit in 2020–21. All 120 common trusts have never submitted their financial statements for audit. The department needs to do more to ensure that the CLMs and common trusts meet their statutory reporting obligations.
  • Nine agencies that were required to perform early close procedures did not complete a total of 20 mandatory procedures. The most common incomplete early close procedures include the revaluation of property, plant and equipment, documenting all significant management judgments and assumptions, and the implementation of new and updated accounting standards.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision-making.

This chapter outlines our observations and insights from our financial statements audits of agencies in the Planning, Industry and Environment cluster.

Section highlights

  • The number of findings reported to management has increased from 135 in 2019–20 to 180 in 2020–21, and 40 per cent were repeat issues.
  • Seven high-risk issues were identified in 2020–21, and three high-risk findings were repeat issues.
  • There continues to be significant deficiencies in Crown land records. The department should prioritise action to ensure the Crown land database is complete and accurate.

Appendix one - Misstatements in financial statements submitted for audit

Appendix two – Early close procedures

Appendix three – Timeliness of financial reporting

Appendix four – Financial data

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Stronger Communities 2021

Stronger Communities 2021

Justice
Community Services
Financial reporting
Internal controls and governance

This report analyses the results of our audits of the Stronger Communities cluster agencies for the year ended 30 June 2021.

Our preferred approach is to table the ‘Report on State Finances’ in Parliament before any other cluster report. This is because the 'Report on State Finances' focuses on the audit results and observations relating to the Total State Sector Accounts, in effect a consolidation of all government agencies. This year the 'Report on State Finances' has been delayed due to significant accounting issues being considered in the Total State Sector Accounts and which may impact the Treasury and Transport clusters.

As there are no outstanding matters relating to audits in the Stronger Communities cluster impacting the Total State Sector Accounts we have decided to break with normal practice and table this cluster report ahead of the ‘Report on State Finances’.

What the report is about

The results of the Stronger Communities cluster agencies' financial statement audits for the year ended 30 June 2021.

What we found

Unqualified audit opinions were issued for all 30 June 2021 financial statements of cluster agencies.

Eleven of the 15 cluster agencies required to submit 2020–21 early close financial statements and other mandatory procedures did not meet the statutory deadline. Five agencies did not perform all mandatory procedures.

The implementation of AASB 1059 'Service Concession Arrangements: Grantors' had a significant impact on the Department of Communities and Justice's (the department) 2020–21 financial statements. The department applied a modified retrospective approach upon initial adoption at 1 July 2020 and recognised service concession assets and liabilities of $1.0 billion and $1.2 billion respectively (relating to three correctional centres with private sector operators).

The department was, this year for the first time, able to reliably measure Incurred But Not Reported (IBNR) claims relating to its Victims Support Scheme. The department recorded a liability of $200 million at 30 June 2021. Liabilities for Child Sexual Assault IBNR claim continue to be not recorded on the basis they are unable to be reliably measured.

The number of monetary misstatements identified during the audit of the financial statements for the cluster increased from 61 in 2019–20 to 72 in 2020–21.

What the key issues were

The number of issues reported to management decreased from 191 in 2019–20 to 172 in 2020–21. However, 45 per cent were repeat issues related to information technology, governance and oversight controls.

Seven high risk issues were identified in 2020–21, an increase of five compared to last year. High risk issues related to deficiencies in IT access controls at Sydney Cricket and Sports Ground Trust; a lack of a formal agreement between the Office of Sport and Planning Ministerial Corporation over the management of a sporting venue; asset revaluations at both Fire and Rescue NSW and the Trustees of the Anzac Memorial Building; and three issues related to revenue recognition control deficiencies at New South Wales Aboriginal Land Council and two of its subsidiaries.

What we recommended

Cluster agencies should ensure all applicable mandatory early close procedures are completed and the outcomes provided to the audit team in accordance with the deadlines set by NSW Treasury.

We recommend cluster agencies action recommendations to address internal control weaknesses promptly. Focus should be given to addressing high risk and repeat issues.

Fast facts

The Stronger Communities cluster, consisting of 28 agencies, aims to deliver community services that support a safe and just New South Wales.

  • $14.0b property, plant and equipment as at 30 June 2021 
  • $20.9b total expenditure incurred in 2020–21
  • 100% unqualified audit opinions were issued for all 30 June 2021 financial statements
  • 7 high risk management letter findings were identified
  • 72 monetary misstatements were reported in 2020–21
  • 45% of reported issues were repeat issues.

This report provides Parliament and other users of the Stronger Communities cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Stronger Communities cluster (the cluster) for 2021.

Section highlights

  • Unqualified audit opinions were issued for all 30 June 2021 financial statements of cluster agencies including the acquittal and compliance audits for the Legal Aid Commission of New South Wales and Crown Solicitor's Office.
  • An 'Other Matter' paragraph was included within the Multicultural NSW and Office of the Ageing and Disability Commissioner’s Independent Auditor's Report. While the paragraph did not modify the audit opinion, it noted the agencies did not have a signed instrument of delegation from their responsible Minister(s) to incur expenditure for the 2020–21 financial year and therefore were non‑compliant with section 5.5 of the Government Sector Finance Act 2018 .
  • 11 of the 15 cluster agencies required to submit 2020–21 early close financial statements and all other mandatory procedures did not meet the statutory deadlines. The agencies cited changes in key staff, delays in finalising actuarial and valuation work and the timing of Audit and Risk Committee meetings as the main reasons for not meeting the deadlines. Five agencies did not complete all mandatory procedures.
  • The Department of Communities and Justice (the department) was, for the first time, able to reliably measure and record a liability of $200 million at 30 June 2021 for Incurred But Not Reported (IBNR) claims relating to its Victims Support Scheme. Child Sexual Assault IBNR claim liabilities continue to be not recorded on the basis they are still unable to be reliably measured.
  • The International Financial Reporting Standards Interpretations Committee released an agenda decision on 'Configuration or customisation costs in a cloud computing arrangement' (the IFRIC agenda decision). The department treated the financial impacts of the IFRIC agenda decision as a change in accounting policy and retrospectively recorded prepaid assets and expenses of $52.3 million and $90.5 million respectively relating to intangible assets they had previously capitalised.
  • The implementation of AASB 1059 'Service Concession Arrangements: Grantors' had a significant impact on the department's 2020–21 financial statements. The department applied a modified retrospective approach upon initial adoption at 1 July 2020 and recognised service concession assets and liabilities of $1.0 billion and $1.2 billion respectively in relation to three correctional centres with private sector operators.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the Stronger Communities cluster.

Section highlights

  • The number of issues reported to management has decreased from 191 in 2019–20 to 172 in 2020–21, and 45 per cent were repeat issues. Many repeat issues related to information technology, governance and oversight controls.
  • Seven high risk issues were identified in 2020–21, an increase of five compared to last year.
  • The two high risk issues identified in 2019–20 relating to New South Wales Institute of Sport were resolved.

Findings reported to management

The overall number of findings has decreased, but the level of repeat issues increased

Breakdowns and weaknesses in internal controls increase the risk of fraud and error. Deficiencies in internal controls, matters of governance interest and unresolved issues were reported to management and those charged with governance of agencies. The Audit Office does this through management letters, which include observations, related implications, recommendations and risk ratings.

In 2020–21, there were 172 findings raised across the cluster (191 in 2019–20). 45 per cent of all issues were repeat issues (32 per cent in 2019–20).

Repeat issues largely related to weaknesses in controls over information technology (IT), governance and oversight.

A delay in implementing audit recommendations increases the risk of intentional and accidental errors in processing information, producing management reports and generating financial statements. This can impair decision‑making, affect service delivery and expose agencies to fraud, financial loss and reputational damage. Poor controls may also mean agency staff are less likely to follow internal policies, inadvertently causing the agency not to comply with legislation, regulation and central agency policies.

2020–21 audits identified seven high risk findings

High risk findings were reported at the following cluster agencies. Two high risk findings reported in 2019–20 were resolved.

Agency Description
2020–21 findings
Sydney Cricket and Sports Ground Trust (new finding) * The audit of Sydney Cricket and Sports Ground Trust's IT access controls identified:
  • activity (audit) logs of privileged access within iPOS (purchasing system) and Microsoft Dynamics (sales system) are not maintained and periodically reviewed by an independent officer
  • the review of privileged activity logs of booking system Event Business Management Software (EBMS) is not formally documented
  • 8 generic super user accounts are being shared across four IT systems including iPOS, Microsoft Dynamics, EBMS and SUN (accounting system).
The matter has been included as a high risk finding in the management letter as there is an increased risk of:
  • unauthorised transactions and changes to financial data
  • unauthorised users gaining access to financial systems
  • data breaches or financial loss.
Fire and Rescue NSW (new finding) Fire and Rescue NSW (FRNSW) completed a comprehensive revaluation of its fire appliances in 2020–21. The audit of the revaluation found there was inadequate analysis and quality control by management over the valuation process prior to the outcomes being included in the financial statements.
FRNSW had 57 fleet assets that have not been revalued due to problems with data supplied by the valuer. The written down value:
  • did not agree to the valuer's calculations for 28 assets
  • was provided by the valuer for 29 assets, but there were no supporting calculations.
These assets have been left at their previous book values of $3.0 million. The accounting standards require the entire class of assets to be revalued when a revaluation is performed.
The review also found:
  • inconsistent valuation of vehicles of the same make, model, age and specifications
  • errors had been made when the previous valuation was uploaded into the fixed asset register
  • the valuer incorrectly included additional equipment in the replacement cost estimate for vehicles that did not have that equipment.
The matter has been included as a high risk finding as it resulted in monetary misstatements and caused delays to the overall timeframes for the audit.
New South Wales Aboriginal Land Council (NSWALC) (new finding) The audit of NSWALC's revenue identified there was no formal assessment of relevant contracts for the nature, amount and timing of revenue recognition before preparing the financial statements.
This matter has been included as a high risk finding as it contributed to material monetary misstatements and disclosure deficiencies relating to revenue transactions.
NSWALC Employment and Training Limited (new finding) The audit of NSWALC Employment and Training Limited's revenue found:
  • there was no formal assessment of relevant contracts for the nature, amount and timing of revenue recognition before preparing the financial statements
  • the financial statements' preparation did not include updated accounting policies reflecting the requirements of AASB 15 'Revenue from Contracts with Customers' (AASB 15) and AASB 1058 'Income of Not-for-Profit Entities' (AASB 1058).
This matter has been included as a high risk finding as it contributed to material monetary misstatements and disclosure deficiencies relating to revenue transactions.
NSWALC Housing Limited (new finding) The audit of NSWALC Housing Limited's revenue identified it:
  • did not perform formal assessments of relevant contracts for the nature, amount and timing of revenue recognition before preparing the financial statements
  • deferred revenue recognition for funding received from NSWALC  (the parent entity). There are no sufficiently specific performance obligations in the funding letter, hence revenue should be recognised on receipt of the funding
  • recognised rental income from managing properties from the Aboriginal Housing Office (AHO) without considering the agreement, which requires remittance of profit to the AHO
  • the financial statements did not include updated accounting policies according to the requirements of AASB 15 and AASB 1058.
This matter has been included as a high risk finding as it contributed to material monetary misstatements and disclosure deficiencies relating to revenue transactions.
Office of Sport (new finding)

The Olympic Co-ordination Authority Dissolution Act 2002 transferred the assets, rights and liabilities relating to the Sydney International Regatta Centre (SIRC) to the Planning Ministerial Corporation (the Corporation) effective from 1 July 2002. The Corporation recognised the related land assets but did not recognise any of the built assets at the time of transfer. The total value of the land and built assets at 30 June 2021 was
$13.8 million and $11.2 million (written down value) respectively.

The SIRC has been managed by the Office of Sport (the Office) for many years in accordance with a not yet executed management agreement.

It appears there was a clear intention in 2005 that the control of SIRC built assets was to be transferred from the then Department of Planning to the then Department of Tourism, Sport and Recreation (a predecessor of the Office), through the exchange of letters between the relevant Ministers and an Administrative Order (the Order). The Order transferred the SIRC staff from the then Department of Planning to the then Department of Tourism, Sport and Recreation. However, it was silent on whether the relevant built assets were transferred.

Currently, the Office recognises the SIRC built assets in the financial statements whilst the Corporation recognises the land assets as the legal owner of the property.

This matter has been included as a high risk finding as the lack of a formal management agreement casts doubt over the accounting treatment of SIRC property.

The Trustees of the Anzac Memorial Building (new finding)

The audit of the Trustees of the Anzac Memorial Building's property, plant and equipment identified:

  • the fixed assets register for plant and equipment had not previously included sufficient detail about the individual assets to which costs related to reconcile it to the work performed by management's valuation expert
  • the financial statements did not meet the requirement of AASB 108 ‘Accounting Policies, Changes in Accounting Estimates and Errors’  to disclose the nature and reason why it corrected a prior period error of $778,000.

This matter has been included as a high risk finding as it contributed to material monetary misstatements and disclosure deficiencies relating to property, plant and equipment.


*         The finding related to the former Sydney Cricket and Sports Ground Trust (based on the completion audit for the period 1 March 2020 to 30 November 2020). This agency was dissolved and transferred to Venues NSW on 1 December 2020.
 

Recommendation (repeat issue)

We recommend cluster agencies action recommendations to address internal control weaknesses promptly. Focus should be given to addressing high risk and repeat issues.

The table below describes issues commonly identified across the cluster by category and risk rating.

Risk rating Issue
Information technology

High3
1 new

The financial audits identified weaknesses in information technology processes and controls that support the integrity of financial data used to prepare agencies' financial statements. Of particular concern are issues with:

  • user access administration
  • cyber security including governance arrangements, monitoring of third-party system access and patch management
  • password security and policy parameters
  • development, review and testing of disaster recovery plans.

Moderate2
8 new,
22 repeat

Low1
5 new,
6 repeat
Internal control deficiencies or improvements

High3
1 new

The financial audits identified internal control weaknesses across the following key business processes: 

  • expenditure, including the approval of purchase requisitions and review of open purchase orders
  • supplier and employee masterfile maintenance
  • segregation of duties.

Moderate2
6 new,
3 repeat

 Low1
23 new,
7 repeat

Financial reporting

High3
4 new

The financial audits identified weaknesses in financial reporting processes, including:

  • fully depreciated assets still in use, indicating the need to perform more frequent assessments of useful lives of assets
  • robustness of property, plant and equipment asset revaluations
  • incomplete or inaccurate recording of balances in the financial statements.

Moderate2
9 new,
1 repeat

Low1
11 new,
5 repeat

Governance and oversight
High3
1 new

The financial audits identified areas where agencies could strengthen governance and oversight processes, including:

  • review and update of policies and procedures
  • formalising existing key business arrangements
  • records management practices.
Moderate2
5 new,
11 repeat
Low1
12 new,
8 repeat
Non-compliance with key legislation and/or central agency policies
Moderate2
7 new,
6 repeat

The financial audits identified the need for agencies to improve their compliance with key legislation and/or central agency policies, including:

  • management of excessive annual leave balances
  • existence of and compliance with financial delegations
  • related party transactions disclosures from key management personnel.
Low1
2 new,
8 repeat

4 Extreme risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.
3 High risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.
2 Moderate risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.
1 Low risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.
Note: Management letter findings are based either on final management letters issued to agencies, or draft letters where findings have been agreed with management.

The number of moderate risk findings decreased from prior year

Seventy‑eight moderate risk findings were reported in 2020–21, representing a 22 per cent decrease from 2019–20. Of these, 43 were repeat findings, and 35 were new issues.

Moderate risk findings reported in 2020–21 include:

  • weaknesses in governance arrangements, including outdated policies and procedures and arrangements that do not align with NSW Government guidelines, such as the NSW Government Procurement Policy Framework and NSW Cyber Security Policy
  • weaknesses in user access administration including:
    • user access reviews
    • monitoring of privileged user access and activities
    • password policy configuration
  • cyber security improvements including:
    • implementation and update of governance arrangements
    • monitoring of third‑party system access
    • patch management improvement
  • outdated instruments of financial delegation and non‑compliance with established financial delegations
  • weaknesses in supplier and employee masterfile maintenance.

Appendix one – Misstatements in financial statements submitted for audit

Appendix two – Early close procedures

Appendix three – Timeliness of financial reporting

Appendix four – Financial data

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Published

Actions for Regional NSW 2021

Regional NSW 2021

Environment
Industry
Asset valuation
Compliance
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Service delivery

This report analyses the results of our audits of the Regional NSW cluster agencies for the year ended 30 June 2021.

Our preferred approach is to table the ‘Report on State Finances’ in Parliament before any other cluster report. This is because the 'Report on State Finances' focuses on the audit results and observations relating to the Total State Sector Accounts, in effect a consolidation of all government agencies. This year the 'Report on State Finances' has been delayed due to significant accounting issues being considered in the Total State Sector Accounts and which may impact the Treasury and Transport clusters.

As there are no outstanding matters relating to audits in the Regional NSW cluster impacting the Total State Sector Accounts we have decided to break with normal practice and table this cluster report ahead of the ‘Report on State Finances’.

What the report is about

The results of the Regional NSW cluster (the cluster) agencies’ financial statement audits for the year ended 30 June 2021.

What we found

Unmodified audit opinions were issued for all completed 30 June 2021 financial statement audits of cluster agencies. Four audits are ongoing.

The number of misstatements identified in the financial statements of cluster agencies decreased from 27 in 2019–20 to seven in 2020–21.

The Department corrected an understatement of $82.2 million in prepaid income related to the Bushfire Clean-up Program.

What the key issues were

Local Land Services (LLS) undertook a comprehensive revaluation of asset improvements on land reserves used for moving stock (travelling stock reserves).

The revaluation process identified that improvements on land reserves, with a value of $93.0 million, had not been previously recognised in the financial statements. LLS corrected this error by restating the 2019–20 comparative balances in its 2020–21 financial statements.

The Forestry Corporation of NSW revalued its biological assets that comprise approximately 225,000 hectares of softwood plantations and 34,000 hectares of hardwood forests. The current year valuation resulted in $71.4 million decrement in the total biological assets from $824.9 million in 2019–20 to $753.5 million in 2020–21.

The number of matters reported to management decreased from 36 in 2019–20 to 19 in 2020–21. Twelve moderate risk issues were identified and 47 per cent of reported issues were repeat issues.

What we recommended

Cluster agencies should prioritise and action recommendations to address internal control deficiencies.

 

Fast facts

The Regional NSW cluster plans and delivers regional programs and infrastructure to respond to regional issues, creating and preserving regional jobs, driving regional economy, growing existing and supporting emerging industries. There are 31 agencies in the cluster.

  • $2.3b of regional land and buildings as at 30 June 2021.

  • 100% unqualified audit opinions were issued for all completed 30 June 2021 financial statements audits.

  • monetary misstatements were reported in 2020–21.

  • $603m of grants and subsidies administered to the regional community in 2020–21.

  • 12 moderate risk management letter findings were identified and reported to management.

  • 47% of reported issues were repeat issues. 

This report provides Parliament and other users of the Regional NSW cluster agencies’ financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Regional NSW cluster for 2021.

Section highlights

  • Unqualified audit opinions were issued for all completed 30 June 2021 financial statements audits of cluster agencies. Four audits are ongoing.
  • The number of monetary misstatements identified during the audit decreased from 27 in 2019–20 to seven in 2020–21.
  • Three cluster agencies could improve their early close process by completing all required procedures.
  • Local Land Services disclosed a prior period error relating to the completeness of asset improvements on travelling stock reserves.

 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the Regional NSW cluster.

Section highlights

  • The number of findings reported to management decreased from 36 in 2019–20 to 19 in 2020–21, and 47 per cent were repeat findings.
  • The 2020–21 audits identified 12 moderate risk and seven low risk issues across the cluster.
  • Four moderate risk issues and five low risk issues were repeat findings from
    2019–20.

 

Appendix one - Misstatements in financial statements submitted for audit

Appendix two - Early close procedures

Appendix three - Financial data

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Fast-tracked Assessment Program

Fast-tracked Assessment Program

Planning
Industry
Environment
Compliance
Internal controls and governance
Management and administration
Service delivery

What the report is about

This report examines the effectiveness of the Fast-tracked Assessment Program, administered by the Department of Planning, Industry and Environment (DPIE) between April 2020 and October 2020. 

The program aimed to support the construction industry during the COVID-19 crisis by accelerating the final assessment stages for planning proposals and development applications. 

DPIE selected projects and planning proposals for fast tracked assessment that demonstrated the potential to:

  • deliver jobs
  • progress to the next stage of development within six months of determination
  • deliver public benefit.

The audit assessed whether the Fast-tracked Assessment Program achieved its objectives while complying with planning controls.

What we found

Through tranches three to six of the program, DPIE successfully accelerated the final stages of 53 assessments. DPIE reported that 89 per cent of these proceeded to the next stage of development within six months.

Assessment of projects and planning proposals was compliant with legislation and other requirements. However, the audit found gaps in DPIE's management of conflicts of interest.

DPIE has not evaluated or costed the program and is not able to demonstrate the extent to which it provided support to the construction industry during COVID-19. 

Aspects of the program have been incorporated into longer term reforms to create a new level of transparency over the progress and status of planning assessments. 

What we recommended

DPIE should:

  • strengthen controls over conflicts of interest 
  • evaluate the Fast-tracked Assessment Program.

Fast facts

Construction industry support 
  • The program aimed at providing immediate support to the construction industry during the COVID-19 crisis
59 fast-tracked projects 
  • 59 projects and 42 planning proposals projects were assessed in six tranches
89% of all fast-tracked assessments in tranches three to six progressed to the next stage of the planning process within six months of determination

In April 2020, the Department of Planning, Industry and Environment (DPIE) introduced programs aimed at providing immediate support to the construction industry during the COVID-19 crisis. One of these was the Fast-tracked Assessment Program. This program identified planning proposals and development applications (DAs), across six tranches, that were partially-assessed and could be accelerated to determination.

In accordance with the program objectives, the planning proposals and DAs selected for fast-tracked assessment had to:

  • deliver jobs – particularly in the construction industry
  • be capable of progressing to the next stage of development within six months of determination
  • deliver public benefit.

At the same time, the Fast-tracked Assessment Program was to lay a foundation for future reform of the planning system by piloting changes in the assessment process that could be adopted in the medium to long term.

This audit assessed whether the Fast-tracked Assessment Program achieved its objectives while complying with planning controls. The audit focused on tranches three to six of the program, which were determined between July 2020 and October 2020. The rationale for focusing on these four tranches was that the program design had been slightly modified after the first two tranches to address identified risks.

Conclusion

Through tranches three to six of the Fast-tracked Assessment Program, DPIE successfully accelerated the final stages of 53 assessments. DPIE’s internal monitoring indicates that 31 DAs and 16 planning proposals selected in these tranches proceeded to the next stage of development within six months of determination. DPIE achieved this while also successfully managing the risk of non-compliance with planning controls arising from the accelerated process. While DPIE has incorporated components of the Fast-tracked Assessment Program into other longer-term reforms, it has not evaluated the program and is not able to demonstrate the extent to which the program provided support to the construction industry during COVID-19.

Between April and October 2020, DPIE adopted a case management approach to accelerate the final stages of assessment for 42 planning proposals and 59 DAs in six tranches. Tranches three to six were the focus of this audit and included 22 planning proposals and 31 DAs. Applicants involved in the program were expected to progress their projects to the next stage of development within six months of determination. While DPIE had no way of compelling applicants to do this and relied on non-binding commitments obtained from applicants, DPIE’s internal monitoring indicates that 47 of the 53 applicants selected in tranches three to six honoured this commitment.

Fast-tracked assessment only applied to the final stages of assessment and required DPIE staff and other stakeholders to work towards a determination deadline. DPIE effectively used a case management approach to manage the risk that the accelerated timeframe could result in planning controls not being fully compliant with legislation. There is some room for improvement in the process, as four of 28 staff assessing planning proposals and DAs had not lodged current conflict of interest declarations.

Based on the results of and learnings from the Fast-tracked Assessment Program, DPIE has incorporated some elements of the program into other longer-term reforms. There is now increased transparency about when applicants can expect to receive a planning determination and DPIE has also introduced a case management approach for strategic and high priority planning applications. Applicants benefiting from case-managed assessment are now required to commit to a formal service charter that specifies the obligations of both DPIE and the applicant.

DPIE has not evaluated the Fast-tracked Assessment Program to understand the costs and benefits of the program, nor which aspects of the program were most effective as a basis for future reform.

Appendix one – Response from agency

Appendix two – Planning determination pathways

Appendix three – About the audit

Appendix four – Performance auditing

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #354 - released (27 July 2021).

Published

Actions for Addressing public inquiry recommendations - Emergency response agencies

Addressing public inquiry recommendations - Emergency response agencies

Community Services
Justice
Environment
Internal controls and governance

The Auditor-General for New South Wales, Margaret Crawford, released a report today examining how effectively NSW emergency response agencies address public inquiry recommendations.

The audit found that agencies’ governance arrangements to address public inquiry recommendations have important and consistent gaps. 

The agencies did not sufficiently verify that they had implemented accepted recommendations as intended, and in line with the outcomes sought. This creates a risk that issues with disaster prevention or responses highlighted by public inquiries are not addressed in a complete or timely way and may persist or recur in the future. 

The audit also found that agencies did not always nominate milestone dates or priority rankings for accepted recommendations, and so could not demonstrate they were managing or monitoring them effectively.

The audit examined how five emergency response agencies – Fire and Rescue NSW, National Parks and Wildlife Service, NSW Rural Fire Service, NSW State Emergency Service and Resilience NSW – have addressed accepted recommendations from public inquiries over the last ten years. The audit assessed the effectiveness of governance arrangements to track recommendation implementation.

The report makes six recommendations to improve disaster response agency arrangements to address public inquiry recommendations.  

While the focus of this audit was agencies that responded to natural disasters, the findings and recommendations from this report have the potential to be applied across the NSW public sector in response to public inquiries related to other areas of government activity.

Major disasters and emergencies often trigger public post-event inquiries and reviews. The purpose of these reviews is to identify the causes of disaster or emergency events and areas for future improvement in prevention, preparedness, response and recovery. Areas identified for future improvement are then the subject of recommendations to government or government agencies and, when accepted, become public commitments to action.

Responses to the bushfires of 2019–20 followed this pattern, producing both NSW and Australian Government commissioned inquiries: the NSW Bushfire Inquiry and the Royal Commission into National Natural Disaster Arrangements. Both highlighted the significant volume of inquiries in recent years. Both asked whether agency responses to previous inquiries were improving Australia's capacity to prevent, prepare for, respond to and recover from natural disasters. The inquiries reflected on the difficulty of answering this question due to insufficient clarity and transparency on whether the improvements and risks that inquiries identified have been addressed in practice.

This audit stems from similar questions about how effectively government agencies in NSW are delivering on public inquiry recommendations. It assessed how five emergency response agencies have addressed accepted recommendations from 17 public inquiries over the last ten years. For this audit, we considered inquiries and reviews that affected agencies' operational capacity to respond to and recover from bushfire, floods and storms. The in scope public inquiries for this audit relate to:

  • the 2013–14, the 2016–17 and the 2017–18 bushfire seasons
  • severe storms and floods in 2015, 2016 and 2017
  • workforce issues affecting the ability of agencies to respond to natural disasters.

The public inquiries we reviewed included coronial inquiries and inquests, parliamentary inquiries, independent reports and reviews, performance audits and recovery coordinator reports. In total, we looked at the processes that agencies used to implement 191 recommendations from these 17 public inquiries.

The objective of this audit was to determine how effective emergency response agencies are in addressing accepted recommendations from public inquiries. To answer our audit objective, we asked two questions:

  • Do agencies have effective governance arrangements in place to respond to, monitor and implement accepted recommendations from public reviews and inquiries?
  • Do agencies provide timely and accurate information on the implementation of accepted inquiry recommendations to senior decision makers and the public?

The agencies reviewed were:

  • Fire and Rescue NSW
  • NSW National Parks and Wildlife Service (now a division of the Department of Planning, Industry and Environment)
  • NSW Rural Fire Service
  • NSW State Emergency Service
  • Resilience NSW (formerly the Ministry for Police and Emergency Services; and the Office of Emergency Management).

While the focus of this audit was agencies that respond to natural disasters (flood, bushfire and storms), the findings and recommendations from this report have the potential to be applied across the NSW public sector in response to public inquiries related to other areas of government activity.

Conclusion

The arrangements used by NSW emergency response agencies to address public inquiry recommendations have important and consistent gaps.

For two-thirds of the recommendations reviewed as part of this audit, the agencies did not sufficiently verify that they had been implemented as intended, and in line with the outcomes sought. This exposes risks that gaps in disaster responses are not addressed in a complete or timely way and persist or recur in the future.

Two-thirds of the recommendations reviewed as part of this audit had also not been allocated milestone dates or priority rankings, and as such the audited agencies are less accountable and could not demonstrate they were managing or monitoring them effectively.

None of the agencies publicly report the status of actions taken to address public inquiry recommendations, limiting accountability and transparency.

The agencies subject to this audit all address accepted recommendations from public inquiries with varying degrees of formality and transparency. No agency maintained a central and comprehensive approach – such as a register – to track recommendations for all public inquiries.

The agencies do not consistently review evidence that recommendations have been implemented effectively, and in line with the intention of the inquiry. The agencies also often failed to set milestone dates or test that recommendations had been actioned as committed. This increases the risk that recommendations are overlooked or not addressed in line with the intent, priority and risk of the recommendation. In turn, this raises the possibility that gaps and issues identified by public inquiries are not adequately resolved and could persist or recur in future disasters.

None of the audited agencies published a summary of progress made in implementing accepted recommendations to update the public. There are transparency and accountability benefits in doing so. This echoes the findings of the NSW Bushfire Inquiry and the Royal Commission into National Natural Disaster Arrangements. Both inquiries noted that it is difficult, and sometimes impossible, to determine the implementation status for many recommendations by publicly available information.

One factor hindering agencies from publishing this information is the lack of a consistent means of tracking public inquiry recommendation implementation. Adopting a consistent approach, within and across agencies, should help to overcome this barrier in the future. 

This chapter reviews the way agencies have responded to, monitored and ensured they have implemented accepted recommendations from public inquiries.

This chapter reviews how agencies provided information to senior decision makers, agency Audit and Risk Committees and the public on the implementation of accepted recommendations from public inquiries.

Appendix one – Response from agencies

Appendix two – Identifying in scope inquiries

Appendix three – In scope inquiries

Appendix four – Recommendations reported by agencies as still in progress (detail)

Appendix five – Agency reported recommendation implementation status (unaudited) 

Appendix six – About the audit 

Appendix seven – Performance auditing

 

Copyright Notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #348 - released (22 April 2021).

Published

Actions for Internal Controls and Governance 2017

Internal Controls and Governance 2017

Finance
Education
Community Services
Health
Justice
Whole of Government
Asset valuation
Compliance
Cyber security
Information technology
Internal controls and governance
Project management
Risk

Agencies need to do more to address risks posed by information technology (IT).

Effective internal controls and governance systems help agencies to operate efficiently and effectively and comply with relevant laws, standards and policies. We assessed how well agencies are implementing these systems, and highlighted opportunities for improvement.
 

1. Overall trends

New and repeat findings

The number of reported financial and IT control deficiencies has fallen, but many previously reported findings remain unresolved.

High risk findings

Poor systems implementations contributed to the seven high risk internal control deficiencies that could affect agencies.

Common findings

Poor IT controls are the most commonly reported deficiency across agencies, followed by governance issues relating to cyber security, capital projects, continuous disclosure, shared services, ethics and risk management maturity.

2. Information Technology

IT security

Only two-thirds of agencies are complying with their own policies on IT security. Agencies need to tighten user access and password controls.

Cyber security

Agencies do not have a common view on what constitutes a cyber attack, which limits understanding the extent of the cyber security threat.

Other IT systems

Agencies can improve their disaster recovery plans and the change control processes they use when updating IT systems.

3. Asset Management

Capital investment

Agencies report delays delivering against the significant increase in their budgets for capital projects.

Capital projects

Agencies are underspending their capital budgets and some can improve capital project governance.

Asset disposals

Eleven per cent of agencies were required to sell their real property through Property NSW but didn’t. And eight per cent of agencies can improve their asset disposal processes.

4. Governance

Governance arrangements

Sixty-four per cent of agencies’ disclosure policies support communication of key performance information and prompt public reporting of significant issues.

Shared services

Fifty-nine per cent of agencies use shared services, yet 14 per cent do not have service level agreements in place and 20 per cent can strengthen the performance standards they set.

5. Ethics and Conduct

Ethical framework

Agencies can reinforce their ethical frameworks by updating code‑of‑conduct policies and publishing a Statement of Business Ethics.

Conflicts of interest

All agencies we reviewed have a code of conduct, but they can still improve the way they update and manage their codes to reduce the risk of fraud and unethical behaviour.

6. Risk Management 

Risk management maturity

All agencies have implemented risk management frameworks, but with varying levels of maturity.

Risk management elements

Many agencies can improve risk registers and strengthen their risk culture, particularly in the way that they report risks to their lead agency.

This report covers the findings and recommendations from our 2016–17 financial audits related to the internal controls and governance of the 39 largest agencies (refer to Appendix three) in the NSW public sector. These agencies represent about 95 per cent of total expenditure for all NSW agencies and were considered to be a large enough group to identify common issues and insights.

The findings in this report should not be used to draw conclusions on the effectiveness of individual agency control environments and governance arrangements. Specific financial reporting, controls and service delivery comments are included in the individual 2017 cluster financial audit reports tabled in Parliament from October to December 2017.

This new report offers strategic insight on the public sector as a whole

In previous years, we have commented on internal control and governance issues in the volumes we published on each ‘cluster’ or agency sector, generally between October and December. To add further value, we then commented more broadly about the issues identified for the public sector as a whole at the start of the following year.

This year, we have created this report dedicated to internal controls and governance. This will help Parliament to understand broad issues affecting the public sector, and help agencies to compare their own performance against that of their peers.

Without strong control measures and governance systems, agencies face increased risks in their financial management and service delivery. If they do not, for example, properly authorise payments or manage conflicts of interest, they are at greater risk of fraud. If they do not have strong information technology (IT) systems, sensitive and trusted information may be at risk of unauthorised access and misuse.

These problems can in turn reduce the efficiency of agency operations, increase their costs and reduce the quality of the services they deliver.

Our audits do not review every control or governance measure every year. We select a range of measures, and report on those that present the most significant risks that agencies should mitigate. This report divides these into the following six areas:

  1. Overall trends
  2. Information technology
  3. Asset management
  4. Governance
  5. Ethics and conduct
  6. Risk management.

Internal controls are processes, policies and procedures that help agencies to:

  • operate effectively and efficiently
  • produce reliable financial reports
  • comply with laws and regulations.

This chapter outlines the overall trends for agency controls and governance issues, including the number of findings, level of risk and the most common deficiencies we found across agencies. The rest of this volume then illustrates this year’s controls and governance findings in more detail.

Issues

Recommendations

1.1 New and repeat findings

The number of internal control deficiencies reduced over the past three years, but new higher-risk information technology (IT) control deficiencies were reported in 2016–17.

Deficiencies repeated from previous years still make up a sizeable proportion of all internal control deficiencies.

Recommendation

Agencies should focus on emerging IT risks, but also manage new IT risks, reduce existing IT control deficiencies, and address repeat internal control deficiencies on a more timely basis.

1.2 High risk findings

We found seven high risk internal control deficiencies, which might significantly affect agencies.

Recommendation

Agencies should rectify high risk internal control deficiencies as a priority

1.3 Common findings

The most common internal control deficiencies related to poor or absent IT controls.

We found some common governance deficiencies across multiple agencies.

Recommendation

Agencies should coordinate actions and resources to help rectify common IT control and governance deficiencies.

Information technology (IT) has become increasingly important for government agencies’ financial reporting and to deliver their services efficiently and effectively. Our audits reviewed whether agencies have effective controls in place over their IT systems. We found that IT security remains the source of many control weakness in agencies.

Issues Recommendations

2.1 IT security

User access administration

While 95 per cent of agencies have policies about user access, about two-thirds were compliant with these policies. Agencies can improve how they grant, change and end user access to their systems.

Recommendation

Agencies should strengthen user access administration to prevent inappropriate access to sensitive systems. Agencies should:

  • establish and enforce clear policies and procedures
  • review user access regularly
  • remove user access for terminated staff promptly
  • change user access for transferred staff promptly.

Privileged access

Sixty-eight per cent of agencies do not adequately manage who can access their information systems, and many do not sufficiently monitor or restrict privileged access.

Recommendation

Agencies should tighten privileged user access to protect their information systems and reduce the risks of data misuse and fraud. Agencies should ensure they:

  • only grant privileged access in line with the responsibilities of a position
  • review the level of access regularly
  • limit privileged access to necessary functions and data
  • monitor privileged user account activity on a regular basis.

Password controls

Forty-one per cent of agencies did not meet either their own standards or minimum standards for password controls.

Recommendation

Agencies should review and enforce password controls to strengthen security over sensitive systems. As a minimum, password parameters should include:

  • minimum password lengths and complexity requirements
  • limits on the number of failed log-in attempts
  • password history (such as the number of passwords remembered)
  • maximum and minimum password ages.

2.2 Cyber Security

Cyber security framework

Agencies do not have a common view on what constitutes a cyber attack, which limits understanding the extent of the cyber security threat.

Recommendation

The Department of Finance, Services and Innovation should revisit its existing framework to develop a shared cyber security terminology and strengthen the current reporting requirements for cyber incidents.

Cyber security strategies

While 82 per cent of agencies have dedicated resources to address cyber security, they can strengthen their strategies, expertise and staff awareness.

Recommendations

The Department of Finance, Services and Innovation should:

  • mandate minimum standards and require agencies to regularly assess and report on how well they mitigate cyber security risks against these standards
  • develop a framework that provides for cyber security training.

Agencies should ensure they adequately resource staff dedicated to cyber security.

2.3 Other IT systems

Change control processes

Some agencies need to improve change control processes to avoid unauthorised or inaccurate system changes.

Recommendation

Agencies should consistently perform user acceptance testing before system upgrades and changes. They should also properly approve and document changes to IT systems.

Disaster recovery planning

Agencies can do more to adequately assess critical business systems to enforce effective disaster recovery plans. This includes reviewing and testing their plans on a timely basis.

Recommendation

Agencies should complete business impact analyses to strengthen disaster recovery plans, then regularly test and update their plans.

Agency service delivery relies on developing and renewing infrastructure assets such as schools, hospitals, roads, or public housing. Agencies are currently investing significantly in new assets. Agencies need to manage the scale and volume of current capital projects in order to deliver new infrastructure on time, on budget and realise the intended benefits. We found agencies can improve how they:

  • manage their major capital projects
  • dispose of existing assets.
Issues Recommendations or conclusions

3.1 Capital investment

Capital asset investment ratios

Most agencies report high capital investment ratios, but one-third of agencies’ capital investment ratios are less than one.

Recommendation

Agencies with high capital asset investment ratios should ensure their project management and delivery functions have the capacity to deliver their current and forward work programs.

Volume of capital spending

Most agencies have significant forward spending commitments for capital projects. However, agencies’ actual capital expenditure has been below budget for the last three years.

Conclusion

The significant increase in capital budget underspends warrant investigation, particularly where this has resulted from slower than expected delivery of projects from previous years.

3.2 Capital projects

Major capital projects

Agencies’ major capital projects were underspent by 13 percent against their budgets.

Conclusion

The causes of agency budget underspends warrant investigation to ensure the NSW Government’s infrastructure commitment is delivered on time.

Capital project governance

Agencies do not consistently prepare business cases or use project steering committees to oversee major capital projects.

Conclusion

Agencies that have project management processes that include robust business cases and regular updates to their steering committees (or equivalent) are better able to provide those projects with strategic direction and oversight.

3.3. Asset disposals

Asset disposal procedures

Agencies need to strengthen their asset disposal procedures.

Recommendations

Agencies should have formal processes for disposing of surplus properties.

Agencies should use Property NSW to manage real property sales unless, as in the case for State owned corporations, they have been granted an exemption.

Governance refers to the high-level frameworks, processes and behaviours that help an organisation to achieve its objectives, comply with legal and other requirements, and meet a high standard of probity, accountability and transparency.

This chapter sets out the governance lighthouse model the Audit Office developed to help agencies reach best practice. It then focuses on two key areas: continuous disclosure and shared services arrangements. The following two chapters look at findings related to ethics and risk management.

Issues Recommendations or conclusions

4.1 Governance arrangements

Continuous disclosure

Continuous disclosure promotes improved performance and public trust and aides better decision-making. Continuous disclosure is only mandatory for NSW Government Businesses such as State owned corporations.

Conclusion

Some agencies promote transparency and accountability by publishing on their websites a continuous disclosure policy that provides for, and encourages:

  • regular public disclosure of key performance information
  • disclosure of both positive and negative information
  • prompt reporting of significant issues.

4.2 Shared services

Service level agreements

Some agencies do not have service level agreements for their shared service arrangements.

Many of the agreements that do exist do not adequately specify controls, performance or reporting requirements. This reduces the effectiveness of shared services arrangements.

Conclusion

Agencies are better able to manage the quality and timeliness of shared service arrangements where they have a service level agreement in place. Ideally, the terms of service should be agreed before services are transferred to the service provider and:

  • specify the controls a provider must maintain
  • specify key performance targets
  • include penalties for non-compliance.

Shared service performance

Some agencies do not set performance standards for their shared service providers or regularly review performance results.

Conclusion

Agencies can achieve better results from shared service arrangements when they regularly monitor the performance of shared service providers using key measures for the benefits realised, costs saved and quality of services received.

Before agencies extend or renegotiate a contract, they should comprehensively assess the services received and test the market to maximise value for money.

All government sector employees must demonstrate the highest levels of ethical conduct, in line with standards set by The Code of Ethics and Conduct for NSW government sector employees.

This chapter looks at how well agencies are managing these requirements, and where they can improve their policies and processes.

We found that agencies mostly have the appropriate codes, frameworks and policies in place. But we have highlighted opportunities to improve the way they manage those systems to reduce the risks of unethical conduct.

Issues Recommendations or conclusions

5.1 Ethical framework

Code of conduct

All agencies we reviewed have a code of conduct, but they can still improve the way they update and manage their codes to reduce the risk of fraud and unethical behaviour.

Recommendation

Agencies should regularly review their code-of-conduct policies and ensure they keep their codes of conduct up-to-date.

Statement of business ethics

Most agencies maintain an ethical framework, but some can enhance their related processes, particularly when dealing with external clients, customers, suppliers and contractors.

Conclusion

Agencies can enhance their ethical frameworks by publishing a Statement of Business Ethics, which communicates their values and culture.

5.2 Potential conflicts of interest

Conflicts of interest

All agencies have a conflicts-of-interest policy, but most can improve how they identify, manage and avoid conflicts of interest.

Recommendation

Agencies should improve the way they manage conflicts of interest, particularly by:

  • requiring senior executives to make a conflict-of-interest declaration at least annually
  • implementing processes to identify and address outstanding declarations
  • providing annual training to staff
  • maintaining current registers of conflicts of interest.

Gifts and benefits

While all agencies already have a formal gifts-and-benefits policy, we found gaps in the management of gifts and benefits by some that increase the risk of unethical conduct.

Recommendation

Agencies should improve the way they manage gifts and benefits by promptly updating registers and providing annual training to staff.

Risk management is an integral part of effective corporate governance. It helps agencies to identify, assess and prioritise the risks they face and in turn minimise, monitor and control the impact of unforeseen events. It also means agencies can respond to opportunities that may emerge and improve their services and activities.

This year we looked at the overall maturity of the risk management frameworks that agencies use, along with two important risk management elements: risk culture and risk registers.

Issues Recommendations or conclusions

6.1 Risk management maturity

All agencies have implemented risk management frameworks, but with varying levels of maturity in their application.

Agencies’ averaged a score of 3.1 out of five across five critical assessment criteria for risk management. While strategy and governance fared best, the areas that most need to improve are risk culture, and systems and intelligence.

Conclusion

Agencies have introduced risk management frameworks and practices as required by the Treasury’s:

  • 'Risk Management Toolkit for the NSW Public Sector'
  • 'Internal Audit and Risk Management Policy for the NSW Public Sector'.

However, more can be done to progress risk management maturity and embed risk management in agency culture.

6.2 Risk management elements

Risk culture

Most agencies have started to embed risk management into the culture of their organisation. But only some have successfully done so, and most agencies can improve their risk culture.

 

 

Conclusion

Agencies can improve their risk culture by:

  • setting an appropriate tone from the top
  • training all staff in effective risk management
  • ensuring desired risk behaviours and culture are supported, monitored, and reinforced through business plans, or the equivalent and employees' performance assessments.

Risk registers and reporting

Some agencies do not report their significant risks to their lead agency, which may impair the way resources are allocated in their cluster. Some agencies do not integrate risk registers at a divisional and whole-of-enterprise level.

Conclusion

Agencies not reporting significant risks at the cluster level increases the likelihood that significant risks are not being mitigated appropriately.

Effective risk management can improve agency decision-making, protect reputations and lead to significant efficiencies and cost savings. By embedding risk management directly into their operations, agencies can also derive extra value for their activities and services.

Published

Actions for Planning and Environment 2017

Planning and Environment 2017

Planning
Environment
Asset valuation
Information technology
Internal controls and governance
Management and administration
Project management

The following report highlights results of financial audits of agencies in the Planning and Environment cluster. The report focuses on key observations and findings from the most recent audits of these agencies.

The audits were completed for most agencies in the cluster and unqualified audit opinions issued. Issues identified during the financial statement audits of seven small agencies delayed their finalisation beyond the statutory deadline, and six of these remain incomplete. Apart from these small agencies, the quality of financial reporting across the cluster remained at a high standard.

1. Financial reporting and controls

Financial reporting Unqualified audit opinions were issued for 39 of the 45 cluster agencies. Issues identified during the financial statement audits of seven small agencies delayed their finalisation beyond the statutory deadline. Six of these audits remain incomplete at the date of this report.
  Agencies completed early close procedures mandated by the Treasury. We noted opportunities for agencies to improve the effectiveness of these procedures.
Internal Controls One in six internal control weaknesses identified during the financial audits were repeat issues. Agencies should action audit recommendations promptly.
  User administration over financial systems needs to be strengthened to prevent inappropriate access to financial information.

2. Service Delivery

 
Housing completions Australian Bureau of Statistics data indicates the Department of Planning and Environment achieved the Premier's priority for housing completions in 2016–17. 
Increasing housing supply Australian Bureau of Statistics data shows the Department of Planning and Environment achieved the annual target of delivering over 50,000 housing approvals over the past three years.
Major project assessment Progress against the State priority target to reduce time taken to assess planning applications for State significant developments is difficult to determine as the measure is unclear.
Litter management The Environment Protection Authority's data indicates that progress towards the Premier's priority target for litter reduction slowed in 2016–17.
Cultural participation The Department of Planning and Environment’s data indicates overall attendance at cultural venues and events in New South Wales increased by 16 per cent in 2015–16.

This report provides Parliament and others with the audit results, observations and recommendations for Planning and Environment cluster agencies. The report has been structured into two chapters focussing on financial reporting and controls and service delivery.

The Planning and Environment cluster plays a role in ensuring each community across New South Wales receives the services and infrastructure it needs.

This chapter outlines our audit observations and recommendations related to financial reporting and controls of Planning and Environment cluster agencies for 2016–17.

Observation Conclusion or recommendation

2.1 Quality of financial reporting

Unqualified audit opinions were issued for 39 of the 45 cluster agencies' financial statements.

Issues identified during the financial statement audits of seven smaller agencies delayed their completion. Six audits remain incomplete at the date of this report.

Apart from these seven small agency audits, the quality of financial reporting across the cluster remained at a high standard.

2.2 Timeliness of financial reporting

Seven agencies' financial statement audits were not completed by the statutory deadline with six audits incomplete at the date of this report.

Issues identified during the financial statement audits of seven smaller agencies delayed their finalisation beyond the statutory deadline. These agencies would benefit from performing additional early close procedures in future reporting periods.

2.3 Financial and sustainability analysis

Water and Electricity utility agencies continue to operate with low liquidity ratios.

A liquidity ratio below one is an indicator that an entity may not be able to pay its debts as and when they fall due.

Whilst liquidity ratios were below one, utility agencies demonstrated they can continue to support ongoing operations due to:

  • access to regulated revenue streams

  • assets with long useful lives to generate revenue

  • debt funding limits approved by the NSW Treasurer under the Public Authorities (Financial Arrangements) Act 1987.

2.5 Internal controls

One in six internal control weaknesses reported in 2016–17 were repeat issues.

Delays in implementing audit recommendations can prolong the risk of fraud and error.

Recommendation (repeat issue): anagement letter recommendations to address internal control weaknesses should be actioned promptly, with a focus on addressing repeat issues.

Nine of these internal control weaknesses related to the creation, modification, deletion and review of user access to financial systems.

These control weaknesses may compromise the integrity and security of financial data.

Recommendation (repeat issue): Management of user administration over financial systems should be strengthened to prevent inappropriate access to financial information.

This chapter outlines our audit observations, conclusions and recommendations relating to service delivery for 2016–17.

Observation Conclusion or recommendation

3.1 Premier's and State priorities

The Planning and Environment cluster is responsible for delivering five Premier's and State priorities.

One priority target was achieved in 2016–17, two targets are on track to be achieved and progress towards one target slowed.

Progress against one target cannot be determined.

3.2 Planning

Housing Completion

 
There were 63,506 housing completions in
2016–17. This was 4.1 per cent above the Premier’s priority target of delivering 61,000 housing completions per year.
The Australian Bureau of Statistics data shows the housing completions target was achieved in
2016–17.

Housing supply

The number of approvals for new houses in
2016–17 was 72,472 against the State priority target of more than 50,000 approvals per year.
The Australian Bureau of Statistics data indicates the housing approvals target was achieved in
2016–17.

Major project assessment

 
State significant developments are not clearly defined for the purposes of reporting against the State priority target. The Department of Planning and Environment will clarify with the Department of Premier and Cabinet which developments are captured by the State priority target.
The Department of Planning and Environment’s data shows the time taken to assess complex State significant developments increased by 16 per cent in 2016–17 while the time taken to assess less complex developments reduced by 20 per cent. The Department of Planning and Environment considers it is on track to meet the State priority target of halving the time taken to assess State significant developments, despite uncertainty over the target measure.

Housing acceleration fund

 

Program business cases were not developed for projects in Housing Acceleration Fund Rounds 1 to 4.

The Department advised a program business case will be developed for Housing Acceleration Fund Round 5 projects.

A program business case is necessary to ensure related projects are evaluated, managed and coordinated effectively.
 

A benefit realisation review process has not yet been approved for Housing Acceleration Fund projects.

The Department of Planning and Environment advised it is developing a benefit realisation review process.

A benefit realisation review process is necessary to determine whether funded projects achieved intended outcomes.

Greater Sydney Commission

 
The Greater Sydney Commission forecasts a further 725,000 dwellings in the greater Sydney region will be required up to 2036 to meet housing demand. In response to population growth, the Commission has set a five-year housing supply target of 189,100 houses across the five Greater Sydney Commission districts.

ePlanning system

 
The Department of Planning and Environment did not perform a benefit realisation review for phase one of the ePlanning project. It has committed to performing a benefit realisation review after completion of phase two in 2018. It cannot be determined if phase one of the project delivered expected outcomes as a benefit realisation review was not performed.

3.3. Environment and Heritage

Litter volume in New South Wales was 6.6 litres per 1,000 square metres in 2016–17, an increase of 16 per cent from the prior year. This is above the Premier's priority litter volume target of 4.2 litres per 1,000 square metres by 2020. The Environment Protection Authority's data indicates the progress towards the target of reducing the volume of litter by 40 per cent by 2020 has slowed.
The NSW Government plans to invest $240 million to facilitate strategic biodiversity conservation on private land. Performance measures have not yet been developed for the private land conservation program.

3.4 Water

IPART reduced water usage charges for most Sydney Water Corporation customers in 2016–17. Water usage prices in New South Wales compare favourably to larger water utilities in other jurisdictions.

Hunter Water Corporation's water recycling and water conservation performance has been stable over recent years.

The volume of Sydney Water Corporation’s recycled water reduced by 12 per cent in 2016–17 compared to the previous year.

Sydney Water Corporation experienced reduced industry demand for recycled water. Several large industrial customers relocated away from Sydney.

3.5 Arts and culture

A State priority target is to increase overall attendance at cultural venues and events in New South Wales by 15 per cent from 2014–15 levels by 2019. The Department of Planning and Environment's data indicates overall attendance increased by 16 per cent in 2015–16, although attendance fluctuated across individual venues and events. This indicates progress towards achieving the overall target by 2019.

Published

Actions for Industry 2017

Industry 2017

Industry
Asset valuation
Compliance
Internal controls and governance
Procurement
Project management
Risk

The following report highlights the results of the financial audits of NSW Government entities in the Industry cluster. The report focuses on key observations and findings from the most recent audits of these entities.

The report notes that TAFE NSW will continue to incur extra costs each year to produce reliable financial information due to deficiencies in its student administration system. TAFE NSW plans to replace its Student Administration and Learning Management system in 2018-19 at an estimated cost of $89 million.

1. Financial reporting and controls

Financial reporting

Unqualified audit opinions were issued for 44 out of 48 financial statement audits with four audits incomplete. Early close procedures continue to promote earlier and better quality financial reporting.
Financial performance The cluster recorded a net deficit of $107 million in 2016–17 ($78.0 million in 2015–16). Contributing to the overall cluster net deficit was the Department's $226 million net deficit offset by net surpluses at Water NSW and the Forestry Corporation of New South Wales.
TAFE NSW continues to experience system issues TAFE NSW incurs extra costs each year to produce reliable financial information due to deficiencies in its student administration system. TAFE NSW plans to replace its Student Administration and Learning Management system in 2018–19 at an estimated cost of $89 million.
Internal controls

We identified 180 internal control issues, including 61 repeat issues across the cluster. We rated four of these issues as 'high' risk, 98 as ‘moderate’ risk and 78 as ‘low’ risk.

Of the 180 issues raised, 37 related to financial reporting and 52 related to controls over processes such as procurement and fixed assets.

Some internal control issues and recommendations identified in previous years, have been repeated and should be addressed promptly to reduce risks and improve processes.

Deficient user administration access Agencies need to strengthen user access administration to critical financial systems.

2. Service delivery

Premier and State Priorities    

Australian Bureau of Statistics data shows the Premier's priority for job creation has been achieved.

While performance has declined for the State priority to increase the proportion of people completing apprenticeships and traineeships, the Department advises it has initiatives in place to achieve this State priority, and the State priority for New South Wales to lead Australia in business confidence.

Crown land   The Department is working to respond to the recommendations from a Parliamentary Inquiry into Crown Land and to implement the revised framework contained in the Crown Land Management Act 2016.
Aboriginal land claims

Despite a continued focus, the Department has been unsuccessful in reducing the number of unprocessed Aboriginal land claims.

The Department should continue to implement measures to reduce the backlog of unprocessed Aboriginal land claims.

This report focuses on agencies in the Industry cluster. The report focuses on audit results, observations, conclusions and recommendations for financial reporting and controls, and service delivery.

This cluster leads the State's promotion of New South Wales as the place to invest and produce goods and services. Significant cluster agencies deliver services in the following areas:

Confidence in public sector decision-making and transparency is enhanced when financial reporting is accurate and timely. Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies.

This chapter outlines audit observations, conclusions and recommendations for the financial reporting and controls of agencies in the cluster for 2016–17.

Observation Conclusion or recommendation
2.1 Quality of financial reporting
Unqualified audit opinions were issued for 44 out of 48 financial statement audits. Four audits are continuing. Ongoing improvements in the preparation of financial statements helped identify and resolve material issues.
The number of misstatements within the cluster fell from 104 in 2015–16 to 70 in 2016–17. The ‘early close procedures’ initiative introduced by the Treasury in 2011–12 has reduced the number of misstatements each year.
2.2 Timeliness of financial reporting
Most agencies complied with the Treasury’s early close procedures and the timetable for the preparation and audit of financial statements. Greater focus on financial reporting and effective early close procedures has improved the timeliness of financial reporting, but further improvements are required.
2.3 Key financial issues from cluster agencies
The Department of Industry completed a revaluation of Crown land and continues work on improving the accounting for Crown land. The value of Crown land recognised in the Department's financial statements at 30 June 2017 was $5.3 billion. The revaluation was carried out using a revised mass valuation approach which reduced complexity and subjectivity and improved transparency.
There is no process in place to ensure agencies recognise all the Crown land they manage and control. Recommendation: The Department should confirm the completeness and accuracy of the Crown land database with other organisations that manage and control Crown land to improve the reliability of its records.
TAFE NSW incurred approximately $6 million of direct costs to deal with issues in its student administration system and establish the integrity of its financial data for 2016–17. TAFE NSW will continue to incur extra costs each year to produce reliable financial information. TAFE NSW advises it intends to replace the Student Administration and Learning Management system it jointly implemented with the Department of Education three years ago at a cost $40.2 million. TAFE plans to implement the new system in 2018–19 at an estimated cost of $89 million.
 
2.4 Key financial information  
The cluster recorded a net deficit of $107 million in 2016–17 ($78.0 million in 2015–16). The overall cluster net deficit included the Department's $226 million net deficit which was partly offset by net surpluses in a number of other agencies, including Water NSW and the Forestry Corporation of New South Wales. Most agencies in the cluster, including the Department, but excluding the State owned corporations, are dependent on the NSW Government for the majority of their revenue.
 
2.5 Financial performance and sustainability  
We assessed the performance of certain agencies against key financial sustainability indicators. This identified four agencies with adjusted net deficits and two agencies with liquidity ratios below one. Overall, based on our analysis these agencies are not at high risk of sustainability concerns.
2.6 Internal controls  
A significant number of repeat internal control issues were again raised with management for certain agencies in the cluster.
 
Recommendation (repeat issue): Internal control issues and recommendations from previous years should be addressed promptly to reduce risks and improve processes.
User access administration over financial systems needs to be improved. 17 moderate risk issues related to user access administration across nine agencies were identified.

Recommendation: Agencies should ensure administration of user access to critical systems

  • retains documentation of approvals to create, modify and deactivate user access
  • allocates appropriate access rights
  • performs and documents regular user access reviews
  • logs and monitors privileged/super user account activity
  • deactivates terminated user access on a timely basis
  • does not allow shared generic user accounts, instead of unique user accounts for staff performing administration tasks.

Government outcomes can be achieved by delivering services through a mix of the public, private or not-for-profit sectors. Service delivery reform is most successful if there is clear accountability for service delivery outcomes, decisions are aligned to the government's strategic direction, and performance and value for money are monitored and evaluated.

This chapter outlines our audit observations, conclusions and recommendations for the service delivery of agencies in the cluster for 2016–17.

Issues Conclusion or recommendation

3.1 Measuring and reporting on performance

The Department is responsible for two State priorities (increasing apprenticeships and business confidence) and the Premier's priority of creating jobs. The Department also supports four state priorities. Australian Bureau of Statistics data shows the Premier's priority for job creation continues to be achieved. The Department reported that the number of people completing apprenticeships and traineeships had declined to 59 per cent against a 2019 target of 65 per cent, while the State was ranked first or second on a range of business confidence indicators.

3.2 Improvements required in the administration of Crown land

The Department faces many challenges in the administration of Crown land. These challenges range from inadequate systems and processes through to satisfying competing commercial, environmental, and community interests.

The Department has implemented, or is implementing the recommendations from a performance audit on the Sale and Lease of Crown land and the Parliamentary Inquiry into Crown land.

It is also implementing the revised framework for Crown land contained in the Crown Land Management Act 2016.

3.3 Aboriginal land claims over Crown land

The number of unprocessed Aboriginal land claims continues to increase. Work on finalising Aboriginal Land Agreements, which may help address the claims backlog, is continuing. Recommendation (repeat Issue): The Department should continue to implement measures to reduce the number of unprocessed Aboriginal land claims.
 

3.4 Skills development

Eleven contracted Smart and Skilled service providers had their contracts cancelled for quality issues. There were 391 providers of Smart and Skilled qualifications as at October 2017. The Department of Industry spent $1.4 billion on the provision of vocational education and training. The Department has controls in place to monitor the performance of contracted service providers to ensure quality delivery of training.

Published

Actions for Family and Community Services 2017

Family and Community Services 2017

Community Services
Asset valuation
Compliance
Financial reporting
Information technology
Internal controls and governance
Procurement
Project management

The following report focuses on key observations and findings from the most recent audits of agencies in the Family and Community Services cluster.

The report includes a range of findings on service delivery. The Department of Family and Community Services' data indicates that family preservation programs are having a positive impact on children and young people entering statutory care. On the other hand, waiting times for social housing applicants increased in 2016-17.
 

1. Financial reporting and controls

Quality of financial reporting Unqualified audit opinions were issued for all cluster agencies' financial statements.   
Timeliness of financial reporting Agencies completed mandatory early close procedures and all but one agency submitted financial statements by the statutory deadline.
Internal controls The 2016–17 audits reported 29 internal control improvements to cluster agencies’ management. None of these findings were high risk. Eleven related to information technology control weaknesses in key financial business systems.

2. Service Delivery

Commissioning Non-government organisations (NGOs) received $2.6 billion in 2016–17 to deliver services.
Children and young people

The Department of Family and Community Services data indicates that family preservation programs are reducing the number of children and young people entering statutory care.

The Department's data shows 86 per cent of children and young people in statutory care had their placements reviewed in the 12 months to 30 June 2017. Legislation requires all placements are reviewed at least every 12 months.

Social Housing The Department's data shows waiting times for social housing applicants are longer than last year.
People with disability Under the current timetable for implementing the National Disability Insurance Scheme, the Department plans to transfer direct disability services to NGOs by 30 June 2018.

This report provides Parliament and others with the audit results, observations, conclusions and recommendations for Family and Community Services cluster agencies. The report has been structured into two chapters focusing on financial reporting and controls and service delivery.

The Family and Community Services cluster works with children, adults, families and communities to improve lives and help people realise their potential.

This chapter outlines audit observations, conclusions and recommendations related to the financial reporting and controls of agencies in the Family and Community Services cluster for 2016–17.

Financial reporting is an important element of good governance. Confidence in public sector decision making and transparency is enhanced when financial reporting is accurate and timely.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

Observation Conclusion or recommendation
2.1 Quality of financial reporting
Unqualified audit opinions were issued for all cluster agencies' financial statements. The quality of financial reporting remains high across the cluster.
2.2 Timeliness of financial reporting
Agencies completed mandatory early close procedures and all but one submitted financial statements by the deadline. Early close procedures continue to allow issues and financial reporting risk areas to be addressed early in the audit process. There are opportunities to improve effectiveness of early close procedures.
2.3 Internal controls
The 2016–17 audits reported 29 internal control weaknesses. While none were high risk, the Department had five repeat issues.

 
Management accepted the audit findings and advised they are actioning recommendations. Timely action is important to ensure internal controls operate effectively.
Eleven of these internal control weaknesses were related to IT system user access administration and security over financial systems.

Controls weaknesses may compromise the integrity and security of financial data.

Recommendation

Agencies should:

  • ensure policies for creating, modifying and deactivating user access are documented
  • enhance the current user access review process
  • log and monitor highly privileged user account activity
  • ensure timely removal of access to business systems for terminated and casual employees
  • ensure password parameters comply with internal policies.

Government outcomes can be improved by delivering the right mix of services, whether from the public, private or not for profit sectors. Service delivery reform will be most successful if there is clear accountability for service delivery outcomes, decisions are aligned to strategic direction and performance is monitored and evaluated.

This chapter outlines our audit observations, conclusions and recommendations related to service delivery by agencies in the Family and Community Services cluster for 2016–17.

Observation Conclusion or recommendation

3.1 Commissioning

Non-government organisations (NGOs) received $2.6 billion funding in 2016–17 to deliver services. Commissioning of service delivery can change the profile of risks that need to be managed. The Department has established a Commissioning Division and developed its ‘Commissioning for Better Outcomes Framework’. 

3.2 Children and young people

All the Department's Districts are accredited to provide out-of-home care services.

The Department's data indicates 66 more children and young people were in statutory care at 30 June 2017 compared to 30 June 2016. This contrasts to the previous year where 1,150 more children were in statutory care at 30 June 2016 than at 30 June 2015.

The Department is complying with out-of-home care service standards, but one District has an additional condition attached to its accreditation.

Department’s data indicates that family preservation programs are having a positive impact..

The Department's data shows 86 per cent of children and young people in statutory care had their placement reviewed at 30 June 2017.

The Department’s data shows, at 30 June 2017, 41 per cent of children and young people with closed case plans for the 12 months ended 30 June 2016 were re-reported at risk of significant harm.

The Department did not meet the legislative requirement to review the placement of all children and young people in statutory care annually.

The number of children being re-reported at risk of significant harm is above the Premier’s Priority target of 34 per cent by June 2019.
 

3.3. Social Housing

Waiting time for priority and non-priority social housing applicants increased in 2016–17, by 19 per cent and 3 per cent respectively. Some factors impacting waiting time for social housing applicants are outside the control of the Department.

3.4 People with disability

A Bilateral Agreement between the Australian and NSW Governments sets out how eligible persons access the National Disability Insurance Scheme (NDIS) between 1 July 2016 and 30 June 2018.
 
Under the timetable for the NDIS, the Department plans to transfer direct disability services to NGOs.
 

Published

Actions for Agency compliance with NSW Government travel policies

Agency compliance with NSW Government travel policies

Education
Community Services
Finance
Health
Industry
Justice
Local Government
Planning
Premier and Cabinet
Transport
Treasury
Universities
Whole of Government
Compliance
Internal controls and governance
Procurement

Overall, agencies materially complied with NSW Government travel policies.

However, the Auditor-General found some agencies:

  • did not always book official travel through the approved supplier
  • had weaknesses in their travel approval processes
  • had travel policies that were inconsistent with the NSW Government policy
  • did not adequately manage their travel records.   

Last year the NSW Government spent almost $250 million on travel. The government’s travel policies aim to help agencies make better travel decisions and reduce costs. The Department of Finance, Services and Innovation (DFSI) is responsible for the government’s travel policy and manages the government contract with an approved private sector provider to procure travel services.

This audit assessed how effective agency processes were to ensure compliance with:

  • the ‘Policy on Official Travel within Australia and Overseas’ issued by the Department of Premier and Cabinet in Circular OFS-2014–07 ‘Official Travel in Australia and Overseas’ (the former policy)
  • the ‘NSW Government Travel and Transport Policy’ issued by DFSI (the new policy), effective from 28 September 2016.

We examined 15 agencies from different NSW Government clusters with significant travel expenditure. For a list of participating agencies, refer to the Appendix two.

Conclusion

We found that overall, agencies materially complied with NSW Government travel policies. However, some agencies:

  • did not always book official travel through the approved supplier
  • had weaknesses in their travel approval processes
  • had travel policies that were inconsistent with the government policy
  • did not adequately manage their travel records.

Self-assessments indicate agencies comply with most aspects of the new policy. Agencies also believe more guidance from DFSI about certain aspects of the policy would increase compliance.

We asked the 15 participating agencies to complete a self assessment of the processes they have implemented to comply with the new policy. The key observations are summarised below.