NSW Government agencies have sound processes for implementing performance audit recommendations in Auditor-General’s Reports to Parliament. There are many cases of good practice. For example, some agencies formed a steering committee and developed a detailed plan to implement recommendations. Another incorporated the implementation of recommendations into both its business plan and the work plans of individual officers who were managing projects. Most agencies also used their Audit and Risk Committees to monitor recommendations.
 
We found some cases where agencies can improve how they coordinate actions to address recommendations. Most agencies were not revisiting these actions to determine whether they remain appropriate.

 

Parliamentary reference - Report number #254 - released 24 June 2015

Published

Actions for Large construction projects

Large construction projects

Treasury
Transport
Health
Industry
Planning
Premier and Cabinet
Whole of Government
Compliance
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management

The independent assurance given to the NSW Government and sponsor agencies on the viability of large capital projects throughout their lifecycle is inadequate. Government policy is regularly not followed and not properly communicated to those responsible for implementing such policy.
 
This audit sought to test the effectiveness of the NSW capital project assurance system - which includes gateway reviews and reporting - but significant levels of non-compliance identified in our case studies prevented this. The NSW Commission of Audit also identified this issue in 2012. Gateway reviews are conducted by independent reviewers at key stages of a project’s life cycle and provide an independent assessment on a project’s readiness to proceed to the next stage.

 

Parliamentary reference - Report number #252 - released 7 May 2015

Published

Actions for Helping older people access a residential aged care facility

Helping older people access a residential aged care facility

Health
Community Services
Compliance
Internal controls and governance
Management and administration
Risk
Service delivery
Shared services and collaboration
Workforce and capability

Assessment processes for older people needing to go to an Residential Aged Care Facility (RACF) vary depending on the processes of the Aged Care Assessement Teams (ACAT) they see and whether or not they are in hospital. The data collected on ACAT performance was significantly revised during 2004 making comparisons with subsequent years problematic. ACATs have more responsibilities than assessing older people for residential care. It is not clear whether they have sufficient resources for this additional workload.

 