Refine search Expand filter

Reports

Published

Actions for Newcastle Urban Transformation and Transport Program

Newcastle Urban Transformation and Transport Program

Transport
Planning
Compliance
Infrastructure
Management and administration
Procurement
Project management

The urban renewal projects on former railway land in the Newcastle city centre are well targeted to support the objectives of the Newcastle Urban Transformation and Transport Program (the Program), according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the government. However, the evidence that the cost of the light rail will be justified by its contribution to the Program is not convincing.

The Newcastle Urban Transformation and Transport Program (the Program) is an urban renewal and transport program in the Newcastle city centre. The Hunter and Central Coast Development Corporation (HCCDC) has led the Program since 2017. UrbanGrowth NSW led the Program from 2014 until 2017. Transport for NSW has been responsible for delivering the transport parts of the Program since the Program commenced. All references to HCCDC in this report relate to both HCCDC and its predecessor, the Hunter Development Corporation. All references to UrbanGrowth NSW in this report relate only to its Newcastle office from 2014 to 2017.

This audit had two objectives:

  1. To assess the economy of the approach chosen to achieve the objectives of the Program.
  2. To assess the effectiveness of the consultation and oversight of the Program.

We addressed the audit objectives by answering the following questions:

a) Was the decision to build light rail an economical option for achieving Program objectives?
b) Has the best value been obtained for the use of the former railway land?
c) Was good practice used in consultation on key Program decisions?
d) Did governance arrangements support delivery of the program?

Conclusion
1. The urban renewal projects on the former railway land are well targeted to support the objectives of the Program. However, there is insufficient evidence that the cost of the light rail will be justified by its contribution to Program objectives.

The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the Government. HCCDC, and previously UrbanGrowth NSW, identified and considered options for land use that would best meet Program objectives. Required probity processes were followed for developments that involved financial transactions. Our audit did not assess the achievement of these objectives because none of the projects have been completed yet.

Analysis presented in the Program business case and other planning documents showed that the light rail would have small transport benefits and was expected to make a modest contribution to broader Program objectives. Analysis in the Program business case argued that despite this, the light rail was justified because it would attract investment and promote economic development around the route. The Program business case referred to several international examples to support this argument, but did not make a convincing case that these examples were comparable to the proposed light rail in Newcastle.

The audited agencies argue that the contribution of light rail cannot be assessed separately because it is a part of a broader Program. The cost of the light rail makes up around 53 per cent of the total Program funding. Given the cost of the light rail, agencies need to be able to demonstrate that this investment provides value for money by making a measurable contribution to the Program objectives.

2. Consultation and oversight were mostly effective during the implementation stages of the Program. There were weaknesses in both areas in the planning stages.

Consultations about the urban renewal activities from around 2015 onward followed good practice standards. These consultations were based on an internationally accepted framework and met their stated objectives. Community consultations on the decision to close the train line were held in 2006 and 2009. However, the final decision in 2012 was made without a specific community consultation. There was no community consultation on the decision to build a light rail.

The governance arrangements that were in place during the planning stages of the Program did not provide effective oversight. This meant there was not a single agreed set of Program objectives until 2016 and roles and responsibilities for the Program were not clear. Leadership and oversight improved during the implementation phase of the Program. Roles and responsibilities were clarified and a multi-agency steering committee was established to resolve issues that needed multi-agency coordination.
The light rail is not justified by conventional cost-benefit analysis and there is insufficient evidence that the indirect contribution of light rail to achieving the economic development objectives of the Program will justify the cost.
Analysis presented in Program business cases and other planning documents showed that the light rail would have small transport benefits and was expected to make a modest contribution to broader Program objectives. Analysis in the Program business case argued that despite this, the light rail was justified because it would attract investment and promote economic development around the route. The Program business case referred to several international examples to support this argument, but did not make a convincing case that these examples were comparable to the proposed light rail in Newcastle.
The business case analysis of the benefits and costs of light rail was prepared after the decision to build light rail had been made and announced. Our previous reports, and recent reports by others, have emphasised the importance of completing thorough analysis before announcing infrastructure projects. Some advice provided after the initial light rail decision was announced was overly optimistic. It included benefits that cannot reasonably be attributed to light rail and underestimated the scope and cost of the project.
The audited agencies argue that the contribution of light rail cannot be assessed separately because it is part of a broader Program. The cost of the light rail makes up around 53 per cent of the total Program funding. Given the high cost of the light rail, we believe agencies need to be able to demonstrate that this investment provides value for money by making a measurable contribution to the Program objectives.

Recommendations
For future infrastructure programs, NSW Government agencies should support economical decision-making on infrastructure projects by:
  • providing balanced advice to decision makers on the benefits and risks of large infrastructure investments at all stages of the decision-making process
  • providing scope and cost estimates that are as accurate and complete as possible when initial funding decisions are being made
  • making business cases available to the public.​​​​​​
The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the government.

The planned uses of the former railway land align with the objectives of encouraging people to visit and live in the city centre, creating attractive public spaces, and supporting growth in employment in the city. The transport benefits of the activities are less clear, because the light rail is the major transport project and this will not make significant improvements to transport in Newcastle.

The processes used for selling and leasing parts of the former railway land followed industry standards. Options for the former railway land were identified and assessed systematically. Competitive processes were used for most transactions and the required assessment and approval processes were followed. The sale of land to the University of Newcastle did not use a competitive process, but required processes for direct negotiations were followed.

Recommendation
By March 2019, the Hunter and Central Coast Development Corporation should:
  • work with relevant stakeholders to explore options for increasing the focus on the heritage objective of the Program in projects on the former railway land. This could include projects that recognise the cultural and industrial heritage of Newcastle.
Consultations about the urban renewal activities followed good practice standards, but consultation on transport decisions for the Program did not.

Consultations focusing on urban renewal options for the Program included a range of stakeholders and provided opportunities for input into decisions about the use of the former railway land. These consultations received mostly positive feedback from participants. Changes and additions were made to the objectives of the Program and specific projects in response to feedback received. 

There had been several decades of debate about the potential closure of the train line, including community consultations in 2006 and 2009. However, the final decision to close the train line was made and announced in 2012 without a specific community consultation. HCCDC states that consultation with industry and business representatives constitutes community consultation because industry representatives are also members of the community. This does not meet good practice standards because it is not a representative sample of the community.

There was no community consultation on the decision to build a light rail. There were subsequent opportunities for members of the community to comment on the implementation options, but the decision to build it had already been made. A community and industry consultation was held on which route the light rail should use, but the results of this were not made public. 

Recommendation
For future infrastructure programs, NSW Government agencies should consult with a wide range of stakeholders before major decisions are made and announced, and report publicly on the results and outcomes of consultations. 

The governance arrangements that were in place during the planning stages of the Program did not provide effective oversight. Project leadership and oversight improved during the implementation phase of the Program.

Multi-agency coordination and oversight were ineffective during the planning stages of the Program. Examples include: multiple versions of Program objectives being in circulation; unclear reporting lines for project management groups; and poor role definition for the initial advisory board. Program ownership was clarified in mid-2016 with the appointment of a new Program Director with clear accountability for the delivery of the Program. This was supported by the creation of a multi-agency steering committee that was more effective than previous oversight bodies.

The limitations that existed in multi-agency coordination and oversight had some negative consequences in important aspects of project management for the Program. This included whole-of-government benefits management and the coordination of work to mitigate impacts of the Program on small businesses.

Recommendations
For future infrastructure programs, NSW Government agencies should: 

  • develop and implement a benefits management approach from the beginning of a program to ensure responsibility for defining benefits and measuring their achievement is clear
  • establish whole-of-government oversight early in the program to guide major decisions. This should include:
    • agreeing on objectives and ensuring all agencies understand these
    • clearly defining roles and responsibilities for all agencies
    • establishing whole-of-government coordination for the assessment and mitigation of the impact of major construction projects on businesses and the community.

By March 2019, the Hunter and Central Coast Development Corporation should update and implement the Program Benefits Realisation Plan. This should include:

  • setting measurable targets for the desired benefits
  • clearly allocating ownership for achieving the desired benefits
  • monitoring progress toward achieving the desired benefits and reporting publicly on the results.

Appendix one - Response from agencies    

Appendix two - About the audit

Appendix three - Performance auditing

 

Parliamentary reference - Report number #310 - released 12 December 2018

Published

Actions for Family and Community Services 2018

Family and Community Services 2018

Community Services
Compliance
Financial reporting
Information technology
Management and administration
Project management
Risk
Service delivery
Workforce and capability

The Auditor-General for New South Wales, Margaret Crawford released her report today on the Family and Community Services cluster. The report focuses on key observations and findings from the most recent financial audits of agencies in the cluster. Cluster entities received unqualified audit opinions for their 30 June 2018 financial statements. Opportunities to improve the quality of financial reporting were identified and reported to management.

This report analyses the results of our audits of financial statements of the Family and Community Services cluster for the year ended 30 June 2018. The table below summarises our key observations.

This report provides NSW Parliament and other users of the financial statements of Family and Community Services' agencies with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations
  • service delivery.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Family and Community Services cluster for 2018.

Observation Conclusions and recommendations
2.1 Quality of financial reporting
Unqualified audit opinions were issued for all cluster agencies' financial statements. Conclusion: Sufficient audit evidence was obtained to conclude the financial statements were free of material misstatement.
Agencies complied with NSW Treasury’s mandatory early close requirements.

Completing other early close procedures was inconsistent and not always supported by adequate evidence.
Conclusion: There are opportunities for agencies to improve the quality of financial reporting by:
  • documenting all significant judgements and assumptions used when preparing the financial statements
  • regularly reconciling inter-agency balances and transactions
  • reconciling key account balances on a timely basis
  • quantifying the impact of new and revised accounting standards.
2.2 Timeliness of financial reporting
Agencies completed revaluations of property, plant and equipment and submitted 31 March 2018 financial statements by the due date as required by NSW Treasury.

Agencies submitted year-end financial statements by the statutory deadline.
Conclusion: Early revaluations of property, plant and equipment contributes to agencies meeting the year-end statutory reporting deadline.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from:

  • our financial statement audits of agencies in the Family and Community Services cluster for 2018
  • the areas of focus identified in the Audit Office annual work program.

The Audit Office Annual Work Program provides a summary of all audits to be conducted within the proposed time period as well as detailed information on the areas of focus for each NSW Government cluster.

Observation Conclusions and recommendations
3.1 Internal controls
The 2017–18 audits reported 47 internal control weaknesses. While none were high risk, there were 15 repeat issues.

Conclusion: Management accepted audit findings and advised they are actioning recommendations. Timely action is important to ensure internal controls operate effectively.

Twenty-two of these internal control weaknesses related to information technology processes and control environment. Conclusion: Control weaknesses in information systems may compromise the integrity and security of financial data used for decision making and financial reporting.

Recommendation: Agencies should strengthen user access administration to prevent inappropriate access to key IT systems by:
  • ensuring privileged user access is limited to those requiring access to maintain the IT systems
  • monitoring privileged user access to address risks from unauthorised activity
  • ensuring IT password settings comply with password policies
  • ensuring timely removal of access to business systems for terminated and casual employees.
The Department, NSW Land and Housing Corporation (LAHC) and three other cluster agencies’ contract registers are incomplete and/or inaccurate. Recommendation: Agencies should ensure their contract registers are complete and accurate so they can more effectively govern contracts and manage compliance obligations.
3.2 Audit Office annual work program
Financial impact of the commissioning approach.

The transfer of disability services to the National Disability Insurance Scheme and other commissioning of service delivery has contributed to a 36 per cent decrease in frontline employee numbers since 2015–16. Similarly, corporate services’ employee numbers reduced by 34 per cent.

The Department’s salary costs have reduced by $232 million or 18 per cent from 2016–17.
Conclusion: The ratio of corporate services employee numbers to support frontline and support services has remained at 1:10 since 2015–16, which indicates restructures have been planned to align with the transfer of disability services.
Impact of the new social housing maintenance contract

Maintenance expenses have increased by about 40 per cent since the new maintenance contract commenced in April 2016. LAHC measures the benefits of the new maintenance contract such as improved tenant satisfaction.
Conclusion: The new maintenance contract has contributed to some positive social outcomes such as tenants being employed by the contractors to conduct maintenance, as call centre operators and in administration. However, more can be done to ensure value for money is being achieved.
ChildStory IT Project

Whilst phase one of the ChildStory IT project went 'live' in 2017–18, the planned timetable has not been met and the revised date for full implementation is end of 2018.

According to the 2014–15 NSW Budget, the budget for ChildStory was $100 million over a four-year period. During the design and implementation stage, this amount was revised to $128 million, with approval of the Expenditure Review Committee. The actual cost incurred over the four years until 30 June 2018, is approximately $131 million.

We identified issues with the data migration from the legacy systems to ChildStory.
Conclusion: To inform future IT projects, we understand the Department is capturing our findings, along with the findings from the Department of Finance, Services and Innovation’s ‘Healthchecks’.

This chapter outlines certain service delivery outcomes for 2017–18. The data on activity levels and performance is provided by Cluster agencies. The Audit Office does not have a specific mandate to audit performance information. Accordingly, the information in this chapter is unaudited.

In our recent performance audit, Progress and measurement of Premier's Priorities, we identified 12 limitations of performance measurement and performance data. We recommended that the Department of Premier and Cabinet ensure that processes to check and verify data are in place for all agency data sources.

Published

Actions for Transport 2018

Transport 2018

Transport
Asset valuation
Compliance
Financial reporting
Infrastructure
Management and administration
Procurement
Risk
Service delivery
Workforce and capability

The Auditor-General for New South Wales, Margaret Crawford released her report today on key observations and findings from the 30 June 2018 financial statement audits of agencies in the Transport cluster. Unqualified audit opinions were issued for all agencies' financial statements. However, assessing the fair value of the broad range of transport related assets creates challenges.

This report analyses the results of our audits of financial statements of the Transport cluster for the year ended 30 June 2018. The table below summarises our key observations.

This report provides Parliament and other users of the Transport cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Transport cluster for 2018.

Observation Conclusions and recommendations
2.1 Quality of financial reporting
Unqualified audit opinions were issued for all agencies' financial statements Sufficient audit evidence was obtained to conclude the financial statements were free of material misstatement.
2.2 Key accounting issues
Valuation of assets continues to create challenges. Although agencies complied with the requirements of the accounting standards and Treasury policies on valuations, we identified some opportunities for improvements at RMS.

RMS incorporated data from its asset condition assessments for the first time in the valuation methodology which improved the valuation outcome. Overall, we were satisfied with the valuation methodology and key assumptions, but we noted some deficiencies in the asset data in relation to asset component unit rates and old condition data for some components of assets. 

Also, a bypass and tunnel were incorrectly excluded from RMS records and valuation process since 2013. This resulted in an increase for these assets’ value by $133 million.

The valuation inputs for Wetlands and Moorings were revised this year to better reflect the assets' characteristics resulting in a $98.0 million increase.

2.3 Timeliness of financial reporting
Residual Transport Corporation did not submit its financial statements by the statutory reporting deadline. Residual Transport Corporation remained a dormant entity with no transactions for the year ended 30 June 2018.
With the exception of Residual Transport Corporation, all agencies completed early close procedures and submitted financial statements within statutory timeframes. Early close procedures allow financial reporting issues and risks to be addressed early in the reporting and audit process.
2.4 Financial sustainability
NSW Trains and the Chief Investigator of the Office of Transport Safety Investigations reported negative net assets of $75.7 million and $89,000 respectively at 30 June 2018.  NSW Trains and the Chief Investigator of the Office of Transport Safety Investigations continue to require letters of financial support to confirm their ability to pay liabilities as they fall due. 
2.5 Passenger revenue and patronage
Transport agencies revenue growth increased at a higher rate than patronage. Public transport passenger revenue increased by $114 million (8.3 per cent) in 2017–18, and patronage increased by 37.1 million (5.1 per cent) across all modes of transport based on data provided by TfNSW. 
Negative balance Opal Cards resulted in $3.8 million in revenue not collected in 2017–18 and $7.8 million since the introduction of Opal. A total of 1.1 million Opal cards issued since its introduction have negative balances. Transport for NSW advised it is liaising with the ticketing vendor to implement system changes and are investigating other ways to reduce the occurrences.
2.6 Cost recovery from public transport users
Overall cost recovery from users has decreased. Overall cost recovery from public transport users (on rail and bus services by STA) decreased from 23.2 per cent to 22.4 per cent between 2016–17 and 2017–18. The main reason for the decrease is due to expenditure increasing at a faster rate than revenue in 2017–18.


 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from:

  • our financial statement audits of agencies in the Transport cluster for 2018
  • the areas of focus identified in the Audit Office annual work program.

The Audit Office Annual Work Program provides a summary of all audits to be conducted within the proposed time period as well as detailed information on the areas of focus for each of the NSW Government clusters. 

Observation Conclusions and recommendations
3.1 Internal controls 
There was an increase in findings on internal controls across the Transport cluster. Key themes related to information technology, employee leave entitlements and asset management. Eighteen per cent of all issues were repeat issues.
3.2 Audit Office Annual work program
The Transport cluster wrote-off over $200 million of assets which were replaced by new assets or technology.

Majority of this write-off was recognised by RMS, with $199 million relating to the write-off of existing assets which have been replaced during the year. 

RailCorp is expected to convert to TAHE from 1 July 2019. Several working groups are considering different aspects of the TAHE transition including its status as a for-profit Public Trading Enterprise and which assets to transfer to TAHE. We will continue to monitor developments on TAHE for any impact to the financial statements.
RMS' estimated maintenance backlog at 30 June 2018 of $3.4 billion is lower than last year. Sydney Trains' estimated maintenance backlog at 30 June 2018 increased by 20.6 per cent to $434 million. TfNSW does not quantify its backlog maintenance. TfNSW advised it is liaising with Infrastructure NSW to develop a consistent definition of maintenance backlog across all transport service providers. 
Not all agencies monitor unplanned maintenance across the Transport cluster. Unplanned maintenance can be more expensive than planned maintenance. TfNSW should develop a consistent approach to define, monitor and track unplanned maintenance across the cluster.

This chapter outlines certain service delivery outcomes for 2017–18. The data on activity levels and performance is provided by Cluster agencies. The Audit Office does not have a specific mandate to audit performance information. Accordingly, the information in this chapter is unaudited. 

We report this information on service delivery to provide additional context to understand the operations of the Transport cluster and to collate and present service information for different modes of transport in one report. 

In our recent performance audit, Progress and measurement of Premier's Priorities, we identified 12 limitations of performance measurement and performance data. We recommended that the Department of Premier and Cabinet ensure that processes to check and verify data are in place for all agency data sources.

Published

Actions for Internal Controls and Governance 2018

Internal Controls and Governance 2018

Education
Community Services
Finance
Health
Industry
Justice
Planning
Premier and Cabinet
Transport
Treasury
Whole of Government
Environment
Compliance
Cyber security
Financial reporting
Fraud
Information technology
Internal controls and governance
Management and administration
Procurement
Project management

The Auditor-General for New South Wales Margaret Crawford found that as NSW state government agencies’ digital footprint increases they need to do more to address new and emerging information technology (IT) risks. This is one of the key findings to emerge from the second stand-alone report on internal controls and governance of the 40 largest NSW state government agencies.

This report analyses the internal controls and governance of the 40 largest agencies in the NSW public sector for the year ended 30 June 2018.

This report covers the findings and recommendations from our 2017–18 financial audits that relate to internal controls and governance at the 40 largest agencies (refer to Appendix three) in the NSW public sector.

This report offers insights into internal controls and governance in the NSW public sector

This is our second report dedicated to internal controls and governance at NSW State Government agencies. The report provides insights into the effectiveness of controls and governance processes in the NSW public sector by:

  • highlighting the potential risks posed by weaknesses in controls and governance processes
  • helping agencies benchmark the adequacy of their processes against their peers
  • focusing on new and emerging risks, and the internal controls and governance processes that might address those risks.

Without strong governance systems and internal controls, agencies increase the risks associated with effectively managing their finances and delivering services to citizens. The way agencies deliver services increasingly relies on contracts and partnerships with the private sector. Many of these arrangements deliver front line services, but others provide less visible back office support. For example, an agency may rely on an IT service provider to manage a key system used to provide services to the community. The contract and service level agreements are only truly effective where they are actively managed to reduce risks to continuous quality service delivery, such as interruptions caused by system outages, cyber security attacks and data security breaches.

Our audits do not review all aspects of internal controls and governance every year. We select a range of measures, and report on those that present heightened risks for agencies to mitigate. This report divides these into the following five areas:

  1. Internal control trends
  2. Information technology (IT), including IT vendor management
  3. Transparency and performance reporting
  4. Management of purchasing cards and taxis
  5. Fraud and corruption control.

The findings in this report should not be used to draw conclusions on the effectiveness of individual agency control environments and governance arrangements. Specific financial reporting, controls and service delivery comments are included in the individual 2018 cluster financial audit reports, which will be tabled in Parliament from November to December 2018.

The focus of the report has changed since last year

Last year's report topics included asset management, ethics and conduct, and risk management. We are reporting on new topics this year. We plan to introduce new topics and re-visit our previous topics in subsequent reports on a cyclical basis. This will provide a baseline against which to measure the NSW public sectors’ progress in implementing appropriate internal controls and governance processes to mitigate existing, new and emerging risks in the public sector.

Agencies selected for the volume account for 95 per cent of the state's expenditure

While we have covered only 40 agencies in this report, those selected are a large enough group to identify common issues and insights. They represent about 95 per cent of total expenditure for all NSW public sector agencies.

Internal controls are processes, policies and procedures that help agencies to:

  • operate effectively and efficiently
  • produce reliable financial reports
  • comply with laws and regulations
  • support ethical government.

This chapter outlines the overall trends for agency controls and governance issues, including the number of findings, level of risk and the most common deficiencies we found across agencies. The rest of this volume presents this year’s controls and governance findings in more detail.

Observation Conclusions and recommendations
2.1 High risk findings
We found six high risk findings (seven in 2016–17), one of which was repeated from both last year and 2015–16. Recommendation: Agencies should reduce risk by addressing high risk internal control deficiencies as a priority.
2.2 Common findings
We found several internal controls and governance findings common to multiple agencies. Conclusion: Central agencies or the lead agency in a cluster can play a lead role in helping ensure agency responses to common findings are consistent, timely, efficient and effective.
2.3 New and repeat findings
Although internal control deficiencies decreased over the last four years, this year has seen a 42 per cent increase in internal control deficiencies. The increase in new IT control deficiencies and repeat IT control deficiencies signifies an emerging risk for agencies.
IT control deficiencies feature in this increase, having risen by 63 per cent since last year. The number of repeat IT control deficiencies has doubled and is driven by the increasing digital footprint left by agencies as government prioritises on-line interfaces with citizens, and the number of transactions conducted through digital channels increases

Recommendation: Agencies should reduce IT risks by:

  • assigning ownership of recommendations to address IT control deficiencies, with timeframes and actions plans for implementation
  • ensuring audit and risk committees and agency management regularly monitor the implementation status of recommendations.

 

Government agencies’ financial reporting is now heavily reliant on information technology (IT). IT is also increasingly important to the delivery of agency services. These systems often provide the data to help monitor the efficiency and effectiveness of agency processes and services they deliver. Our audits reviewed whether agencies have effective controls in place to manage both key financial systems and IT service contracts.

Observation Conclusions and recommendations
3.1 Management of IT vendors
Contract management framework 
Although 87 per cent of agencies have a contract management policy to manage IT vendors, one fifth require review.
 

Conclusion: Agencies can more effectively manage IT vendor contracts by developing policies and procedures to ensure vendor management frameworks are kept up to date, plans are in place to manage vendor performance and risk, and compliance with the framework is monitored by:

  • internal audit focusing on key contracting activities
  • experienced officers who are independent of contract administration performing spot checks or peer reviews
  • targeted analysis of data in contract registers.
Contract risk management
Forty-one per cent of agencies are not using contract management plans and do not assess contract risks. Half of the agencies that did assess contract risks, had not updated the risk assessments since the commencement of the contract.
 
Conclusion: Instead of applying a 'set and forget' approach in relation to management of contract risks, agencies should assess risk regularly and develop a plan to actively manage identified risks throughout the contract lifecycle - from negotiation and commencement, to termination.

Performance management
Eighty-six per cent of agencies meet with vendors to discuss performance. 

Only 24 per cent of agencies sought assurance about the accuracy of vendor reporting against KPIs, yet sixty-seven per cent of the IT contracts allow agencies to determine performance based payments and/or penalise underperformance.

Conclusion: Agencies are monitoring IT vendor performance, but could improve outcomes and more effectively manage under-performance by:

  • a more active, rigorous approach to both risk and performance management
  • checking the accuracy of vendor reporting against those KPIs and where appropriate seeking assurance over their accuracy
  • invoking performance based payments clauses in contracts when performance falls below agreed standards.

Transitioning services
Forty-three per cent of the IT vendor contracts did not contain transitioning-out provisions.

Where IT vendor contracts do make provision for transitioning-out, only 28 per cent of agencies have developed a transitioning-out plan with their IT vendor.

Conclusion: Contract transition/phase out clauses and plans can mitigate risks to service disruption, ensure internal controls remain in place, avoid unnecessary costs and reduce the risk of 'vendor lock-in'.
Contract Registers
Eleven out of forty agencies did not have a contract register, or have registers that are not accurate and/or complete.

Conclusion: A contract register helps to manage an agency’s compliance obligations under the Government Information (Public Access) Act 2009 (the GIPA Act). However, it also helps agencies more effectively manage IT vendors by:

  • monitoring contract end dates and contract extensions, and commence new procurements through their central procurement teams in a timely manner
  • managing their contractual commitments, budgeting and cash flow requirements.

Recommendation: Agencies should ensure their contract registers are complete and accurate so they can more effectively govern contracts and manage compliance obligations.

3.2 IT general controls
Governance
Ninety-five per cent of agencies have established policies to manage key IT processes and functions within the agency, with ten per cent of those due for review.
 
Conclusion: Regular review of IT policies ensures risks are considered and appropriate strategies and procedures are implemented to manage these risks on a consistent basis. An absence of policies can lead to ad-hoc responses to risks, and failure to consider emerging IT risks and changes to agency IT environments. 

User access administration
Seventy-two deficiencies were identified related to user access administration, including:

  • thirty issues related to granting user access across 43 per cent of agencies
  • sixteen issues related to removing user access across 30 per cent of agencies
  • twenty-six issues related to periodic reviews of user access across 50 per cent of agencies.
Recommendation: Agencies should strengthen the administration of user access to prevent inappropriate access to key systems.
Privileged access
Forty per cent of agencies do not periodically review logs of the activities of privileged users to identify suspicious or unauthorised activities.

Recommendation: Agencies should:

  • review the number of, and access granted to privileged users, and assess and document the risks associated with their activities
  • monitor user access to address risks from unauthorised activity.
Password controls
Twenty-three per cent of agencies did not comply with their own policy on password parameters.
Recommendation: Agencies should ensure IT password settings comply with their password policies.
Program changes
Fifteen per cent of agencies had deficient IT program change controls mainly related to segregation of duties and authorisation and testing of IT program changes prior to deployment.
Recommendation: Agencies should maintain appropriate segregation of duties in their IT functions and test system changes before they are deployed.

 

This chapter outlines our audit observations, conclusions and recommendations from our review of how agencies reported their performance in their 2016–17 annual reports. The Annual Reports (Statutory Bodies) Regulation 2015 and Annual Reports (Departments) Regulation 2015 (annual reports regulation) currently prescribes the minimum requirements for agency annual reports.

Observation Conclusion or recommendation
4.1 Reporting on performance

Only 57 per cent of agencies linked reporting on performance to their strategic objectives.

The use of targets and reporting performance over time was limited and applied inconsistently.

Conclusion: There is significant disparity in the quality and consistency of how agencies report on their performance in their annual reports. This limits the reliability and transparency of reported performance information.

Agencies could improve performance reporting by clearly linking strategic objectives to reported outcomes, and reporting on performance against targets over time. NSW Treasury may need to provide more guidance to agencies to support consistent and high-quality performance reporting in annual reports.

There is no independent assurance that the performance metrics agencies report in their annual reports are accurate.

Prior performance audits have noted issues related to the collection of performance information. For example, our 2016 Report on Red Tape Reduction highlighted inaccuracies in how the dollar-value of red tape reduction had been reported.

Conclusion: The ability of Parliament and the public to rely on reported information as a relevant and accurate reflection of an agency's performance is limited.

The relevance and accuracy of performance information is enhanced when:

  • policies and guidance support the consistent and accurate collection of data
  • internal review processes and management oversight are effective
  • independent review processes are established to provide effective challenge to the assumptions, judgements and methodology used to collect the reported performance information.
4.2 Reporting on reports

Agency reporting on major projects does not meet the requirements of the annual reports regulation.

Forty-seven per cent of agencies did not report on costs to date and estimated completion dates for major works in progress. Of the 47 per cent of agencies that reported on major works, only one agency reported detail about significant cost overruns, delays, amendments, deferments or cancellations.

NSW Treasury produce an annual report checklist to help agencies comply with their annual report obligations.

Recommendation: Agencies should comply with the annual reports regulation and report on all mandatory fields, including significant cost overruns and delays, for their major works in progress.

The information the annual reports regulation requires agencies to report deals only with major works in progress. There is no requirement to report on completed works.

Sixteen of 30 agencies reported some information on completed major works.

Conclusion: Agencies could improve their transparency if they reported, or were required to report:

  • on both works in progress and projects completed during the year
  • actual costs and completion dates, and forecast completion dates for major works, against original and revised budgets and original expected completion dates
  • explanations for significant cost overruns, delays and key project performance metrics.

 

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency preventative and detective controls over purchasing card and taxi use for 2017–18.

Observation Conclusion or recommendation
5.1 Management of purchasing cards
Volume of credit card spend
Purchasing card expenditure has increased by 76 per cent over the last four years in response to a government review into the cost savings possible from using purchasing cards for low value, high volume procurement.
 
Conclusion: The increasing use of purchasing cards highlights the importance of an effective framework for the use and management of purchasing cards.
Policy framework
We found all agencies that held purchasing cards had a policy in place, but 26 per cent of agencies have not reviewed their purchasing card policy by the scheduled date, or do not have a scheduled revision date stated within their policy.
Recommendation: Agencies should mitigate the risks associated with increased purchasing card use by ensuring policies and purchasing card frameworks remain current and compliant with the core requirements of TPP 17–09 'Use and Management of NSW Government Purchasing Cards'.
Preventative controls
We found that:
  • all agencies maintained purchasing card registers
  • seventy-six per cent provided training to cardholders prior to being issued with a card
  • eighty-nine per cent appointed a program administrator, but only half of these had clearly defined roles and responsibilities
  • thirty-two per cent of agencies place merchant blocks on purchasing cards
  • forty-seven per cent of agencies place geographic restrictions on purchasing cards.

Agencies have designed and implemented preventative controls aimed at deterring the potential misuse of purchasing cards.

Conclusion: Further opportunities exist for agencies to better control the use of purchasing cards, such as:

  • updating purchasing card registers to contain all mandatory fields required by TPP17–09
  • appointing a program administrator for the agency's purchasing card framework and defining their role and responsibility for the function
  • strengthening preventive controls to prevent misuse.

Detective controls
Ninety-two per cent of agencies have designed and implemented at least one control to monitor purchasing card activity.

Major reviews, such as data analytics (29 per cent of agencies) and independent spot checks (49 per cent of agencies) are not widely used.

Agencies have designed and implemented detective controls aimed at identifying potential misuse of purchasing cards.

Conclusion: More effective monitoring using purchasing card data can provide better visibility over spending activity and can be used to:

  • detect misuse and investigate exceptions
  • analyse trends to highlight cost saving opportunities.
5.2 Management of taxis
Policy framework
Thirteen per cent of agencies have not developed and implemented a policy to manage taxi use. In addition:
  • a further 41 per cent of agencies have not reviewed their policies by the scheduled revision date, or do not have a scheduled revision date
  • more than half of all agencies’ policies do not offer alternative travel options. For example, only 36 per cent of policies promoted the use of general Opal cards.
Conclusion: Agencies can promote savings and provide more options to staff where their taxi use policies:
  • limit the circumstances where taxi use is appropriate
  • offer alternate, lower cost options to using taxis, such as general Opal cards and rideshare.
Detective controls
All agencies approve taxi expenditure by expense reimbursement, purchasing card and Cabcharge, and have implemented controls around this approval process. However, beyond this there is minimal monitoring and review activity, such as data monitoring, independent spot checks or internal audit reviews.
Conclusion: Taxi spend at agencies is not significant in terms of its dollar value, but it is significant from a probity perspective. Agencies can better address the probity risk by incorporating taxi use into a broader purchasing card or fraud monitoring program.

 

Fraud and corruption control is one of the 17 key elements of our governance lighthouse. Recent reports from ICAC into state agencies and local government councils highlight the need for effective fraud control and ethical frameworks. Effective frameworks can help protect an agency from events that risk serious reputational damage and financial loss.

Our 2016 Fraud Survey found the NSW Government agencies we surveyed reported 1,077 frauds over the three year period to 30 June 2015. For those frauds where an estimate of losses was made, the reported value exceeded $10.0 million. The report also highlighted that the full extent of fraud in the NSW public sector could be higher than reported because:

  • unreported frauds in organisations can be almost three times the number of reported frauds
  • our 2015 survey did not include all NSW public sector agencies, nor did it include any NSW universities or local councils
  • fraud committed by citizens such as fare evasion and fraudulent state tax self-assessments was not within the scope of our 2015 survey
  • agencies did not estimate a value for 599 of the 1,077 (56 per cent) reported frauds.

Commissioning and outsourcing of services to the private sector and the advancement of digital technology are changing the fraud and corruption risks agencies face. Fraud risk assessments should be updated regularly and in particular where there are changes in agency business models. NSW Treasury Circular TC18-02 NSW Fraud and Corruption Control Policy now requires agencies develop, implement and maintain a fraud and corruption control framework, effective from 1 July 2018. 

Our Fraud Control Improvement Kit provides guidance and practical advice to help organisations implement an effective fraud control framework. The kit is divided into ten attributes. Three key attributes have been assessed below; prevention, detection and notification systems.

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency fraud and corruption controls for 2017–18.

Observation Conclusion or recommendation
6.1 Prevention systems

Prevention systems
Ninety-two per cent of agencies have a fraud control plan in place, 81 per cent maintain a fraud database and 79 per cent report fraud and corruption matters as a standing item on audit and risk committee agendas.

Only 54 per cent of agencies have an employment screening policy and all agencies have IT security policies, but gaps in IT security controls could undermine their policies.

Conclusion: Most agencies have implemented fraud prevention systems to reduce the risk of fraud. However poor IT security along with other gaps in agency prevention systems, such as employment screening practices heightens the risk of fraud and inappropriate use of data.

Agencies can improve their fraud prevention systems by:

  • completing regular fraud risk assessments, embedding fraud risk assessment into their enterprise risk management process and reporting the results of the assessment to the audit and risk committee
  • maintaining a fraud database and reviewing it regularly for systemic issues and reporting a redacted version of the database on the agency's website to inform corruption prevention networks
  • developing policies and procedures for employee screening and benchmarking their current processes against ICAC's publication ‘Strengthening Employment Screening Practices in the NSW Public Sector’
  • developing and maintaining up to date IT security policies and monitoring compliance with the policy.
Twenty-three per cent of agencies were not performing fraud risk assessments and some agency fraud risk assessments may not be as robust as they could be.  Conclusion: Agencies' systems of internal controls may be less effective where new and emerging fraud risks have been overlooked, or known weaknesses have not been rectified.
6.2 Detection systems
Detection systems
Several agencies reported they were developing a data monitoring program, but only 38 per cent of agencies had already implemented a program.
 

Studies have shown data monitoring, whereby entire populations of transactional data are analysed for indicators of fraudulent activity, is one of the most effective methods of early detection. Early detection decreases the duration a fraud remains undetected thereby limiting the extent of losses.

Conclusion: Data monitoring is an effective tool for early detection of fraud and is more effective when informed by a comprehensive fraud risk assessment.

6.3 Notification systems
Notification system
All agencies have notification systems for reporting actual or suspected fraud and corruption. Most agencies provide multiple reporting lines, provide training and publicise options for staff to report actual or suspected fraud and corruption.
Conclusion: Training staff about their obligations and the use of fraud notification systems promotes a fraud-aware culture

 

Published

Actions for Mobile speed cameras

Mobile speed cameras

Transport
Compliance
Financial reporting
Information technology
Internal controls and governance
Management and administration
Regulation
Service delivery

Key aspects of the state’s mobile speed camera program need to be improved to maximise road safety benefits, according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. Mobile speed cameras are deployed in a limited number of locations with a small number of these being used frequently. This, along with decisions to limit the hours that mobile speed cameras operate, and to use multiple warning signs, have reduced the broad deterrence of speeding across the general network - the main policy objective of the mobile speed camera program.

The primary goal of speed cameras is to reduce speeding and make the roads safer. Our 2011 performance audit on speed cameras found that, in general, speed cameras change driver behaviour and have a positive impact on road safety.

Transport for NSW published the NSW Speed Camera Strategy in June 2012 in response to our audit. According to the Strategy, the main purpose of mobile speed cameras is to reduce speeding across the road network by providing a general deterrence through anywhere, anytime enforcement and by creating a perceived risk of detection across the road network. Fixed and red-light speed cameras aim to reduce speeding at specific locations.

Roads and Maritime Services and Transport for NSW deploy mobile speed cameras (MSCs) in consultation with NSW Police. The cameras are operated by contractors authorised by Roads and Maritime Services. MSC locations are stretches of road that can be more than 20 kilometres long. MSC sites are specific places within these locations that meet the requirements for a MSC vehicle to be able to operate there.

This audit assessed whether the mobile speed camera program is effectively managed to maximise road safety benefits across the NSW road network.

Conclusion

The mobile speed camera program requires improvements to key aspects of its management to maximise road safety benefits. While camera locations have been selected based on crash history, the limited number of locations restricts network coverage. It also makes enforcement more predictable, reducing the ability to provide a general deterrence. Implementation of the program has been consistent with government decisions to limit its hours of operation and use multiple warning signs. These factors limit the ability of the mobile speed camera program to effectively deliver a broad general network deterrence from speeding.

Many locations are needed to enable network-wide coverage and ensure MSC sessions are randomised and not predictable. However, there are insufficient locations available to operate MSCs that meet strict criteria for crash history, operator safety, signage and technical requirements. MSC performance would be improved if there were more locations.

A scheduling system is meant to randomise MSC location visits to ensure they are not predictable. However, a relatively small number of locations have been visited many times making their deployment more predictable in these places. The allocation of MSCs across the time of day, day of week and across regions is prioritised based on crash history but the frequency of location visits does not correspond with the crash risk for each location.

There is evidence of a reduction in fatal and serious crashes at the 30 best-performing MSC locations. However, there is limited evidence that the current MSC program in NSW has led to a behavioural change in drivers by creating a general network deterrence. While the overall reduction in serious injuries on roads has continued, fatalities have started to climb again. Compliance with speed limits has improved at the sites and locations that MSCs operate, but the results of overall network speed surveys vary, with recent improvements in some speed zones but not others.
There is no supporting justification for the number of hours of operation for the program. The rate of MSC enforcement (hours per capita) in NSW is less than Queensland and Victoria. The government decision to use multiple warning signs has made it harder to identify and maintain suitable MSC locations, and impeded their use for enforcement in both traffic directions and in school zones. 

Appendix one - Response from agency

Appendix two - About the audit

Appendix three - Performance auditing

 

Parliamentary reference - Report number #308 - released 18 October 2018

Published

Actions for Managing Antisocial behaviour in public housing

Managing Antisocial behaviour in public housing

Community Services
Asset valuation
Infrastructure
Regulation
Service delivery
Workforce and capability

The Department of Family and Community Services (FACS) has not adequately supported or resourced its staff to manage antisocial behaviour in public housing according to a report released today by the Deputy Auditor-General for New South Wales, Ian Goodwin. 

In recent decades, policy makers and legislators in Australian states and territories have developed and implemented initiatives to manage antisocial behaviour in public housing environments. All jurisdictions now have some form of legislation or policy to encourage public housing tenants to comply with rules and obligations of ‘good neighbourliness’. In November 2015, the NSW Parliament changed legislation to introduce a new approach to manage antisocial behaviour in public housing. This approach is commonly described as the ‘strikes’ approach. 

When introduced in the NSW Parliament, the ‘strikes’ approach was described as a means to:

  • improve the behaviour of a minority of tenants engaging in antisocial behaviour 
  • create better, safer communities for law abiding tenants, including those who are ageing and vulnerable.

FACS has a number of tasks as a landlord, including a responsibility to collect rent and organise housing maintenance. FACS also has a role to support tenants with complex needs and manage antisocial behaviour. These roles have some inherent tensions. The FACS antisocial behaviour management policy aims are: 

to balance the responsibilities of tenants, the rights of their neighbours in social housing, private residents and the broader community with the need to support tenants to sustain their public housing tenancies.

This audit assessed the efficiency and effectiveness of the ‘strikes’ approach to managing antisocial behaviour in public housing environments.

We examined whether:

  • the approach is being implemented as intended and leading to improved safety and security in social housing environments
  • FACS and its partner agencies have the capability and capacity to implement the approach
  • there are effective mechanisms to monitor, report and progressively improve the approach.
Conclusion

FACS has not adequately supported or resourced its staff to implement the antisocial behaviour policy. FACS antisocial behaviour data is incomplete and unreliable. Accordingly, there is insufficient data to determine the nature and extent of the problem and whether the implementation of the policy is leading to improved safety and security

FACS management of minor and moderate incidents of antisocial behaviour is poor. FACS has not dedicated sufficient training to equip frontline housing staff with the relevant skills to apply the antisocial behaviour management policy. At more than half of the housing offices we visited, staff had not been trained to:

  • conduct effective interviews to determine whether an antisocial behaviour complaint can be substantiated

  • de escalate conflict and manage complex behaviours when required

  • properly manage the safety of staff and tenants

  • establish information sharing arrangements with police

  • collect evidence that meets requirements at the NSW Civil and Administrative Tribunal

  • record and manage antisocial behaviour incidents using the information management system HOMES ASB.

When frontline housing staff are informed about serious and severe illegal antisocial behaviour incidents, they generally refer them to the FACS Legal Division. Staff in the Legal Division are trained and proficient in managing antisocial behaviour in compliance with the policy and therefore, the more serious incidents are managed effectively using HOMES ASB. 


FACS provides housing services to most remote townships via outreach visits from the Dubbo office. In remote townships, the policy is not being fully implemented due to insufficient frontline housing staff. There is very limited knowledge of the policy in these areas and FACS data shows few recorded antisocial behaviour incidents in remote regions. 


The FACS information management system (HOMES ASB) is poorly designed and has significant functional limitations that impede the ability of staff to record and manage antisocial behaviour. Staff at most of the housing offices we visited were unable to accurately record antisocial behaviour matters in HOMES ASB, making the data incorrect and unreliable.

Published

Actions for Regional Assistance Programs

Regional Assistance Programs

Premier and Cabinet
Planning
Transport
Compliance
Infrastructure
Management and administration
Project management

Infrastructure NSW effectively manages how grant applications for regional assistance programs are assessed and recommended for funding. Its contract management processes are also effective. However, we are unable to conclude whether the objectives of these programs have been achieved as the relevant agencies have not yet measured their benefits, according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. 

In 2011, the NSW Government established Restart NSW to fund new infrastructure with the proceeds from the sale and lease of government assets. From 2011 to 2017, the NSW Government allocated $1.7 billion from the fund for infrastructure in regional areas, with an additional commitment of $1.3 billion to be allocated by 2021. The NSW Government allocates these funds through regional assistance programs such as Resources for Regions and Fixing Country Roads. NSW councils are the primary recipients of funding provided under these programs.

The NSW Government announced the Resources for Regions program in 2012 with the aim of addressing infrastructure constraints in mining affected communities. Infrastructure NSW administers the program, with support from the Department of Premier and Cabinet.

The NSW Government announced the Fixing Country Roads program in 2014 with the aim of building more efficient road freight networks. Transport for NSW and Infrastructure NSW jointly administer this program, which funds local councils to deliver projects that help connect local and regional roads to state highways and freight hubs.

This audit assessed whether these two programs (Resources for Regions and Fixing Country Roads) were being effectively managed and achieved their objectives. In making this assessment, we answered the following questions:

  • How well are the relevant agencies managing the assessment and recommendation process?
  • How do the relevant agencies ensure that funded projects are being delivered?
  • Do the funded projects meet program and project objectives?

The audit focussed on four rounds of Resources for Regions funding between 2013–14 to 2015–16, as well as the first two rounds of Fixing Country Roads funding in 2014–15 and 2015–16.

Conclusion
Infrastructure NSW effectively manages how grant applications are assessed and recommended for funding. Infrastructure NSW’s contract management processes are also effective. However, we are unable to conclude on whether program objectives are being achieved as Infrastructure NSW has not yet measured program benefits.
While Infrastructure NSW and Transport for NSW managed the assessment processes effectively overall, they have not fully maintained all required documentation, such as conflict of interest registers. Keeping accurate records is important to support transparency and accountability to the public about funding allocation. The relevant agencies have taken steps to address this in the current funding rounds for both programs.
For both programs assessed, the relevant agencies have developed good strategies over time to support councils through the application process. These strategies include workshops, briefings and feedback for unsuccessful applicants. Transport for NSW and the Department of Premier and Cabinet have implemented effective tools to assist applicants in demonstrating the economic impact of their projects.
Infrastructure NSW is effective in identifying projects that are 'at‑risk' and assists in bringing them back on track. Infrastructure NSW has a risk‑based methodology to verify payment claims, which includes elements of good practice in grants administration. For example, it requires grant recipients to provide photos and engages Public Works Advisory to review progress claims and visit project sites.
Infrastructure NSW collects project completion reports for all Resources for Regions and Fixing Country Roads funded projects. Infrastructure NSW intends to assess benefits for both programs once each project in a funding round is completed. To date, no funding round has been completed. As a result, no benefits assessment has been done for any completed project funded in either program.
 

The project selection criteria are consistent with the program objectives set by the NSW Government, and the RIAP applied the criteria consistently. Probity and record keeping practices did not fully comply with the probity plans.

The assessment methodology designed by Infrastructure NSW is consistent with2 the program objectives and criteria. In the rounds that we reviewed, all funded projects met the assessment criteria.

Infrastructure NSW developed probity plans for both programs which provided guidance on the record keeping required to maintain an audit trail, including the use of conflict of interest registers. Infrastructure NSW and Transport for NSW did not fully comply with these requirements. The relevant agencies have taken steps to address this in the current funding rounds for both programs.

NSW Procurement Board Directions require agencies to ensure that they do not engage a probity advisor that is engaged elsewhere in the agency. Infrastructure NSW has not fully complied with this requirement. A conflict of interest arose when Infrastructure NSW engaged the same consultancy to act as its internal auditor and probity advisor.

While these infringements of probity arrangements are unlikely to have had a major impact on the assessment process, they weaken the transparency and accountability of the process.

Some councils have identified resourcing and capability issues which impact on their ability to participate in the application process. For both programs, the relevant agencies conducted briefings and webinars with applicants to provide advice on the objectives of the programs and how to improve the quality of their applications. Additionally, Transport for NSW and the Department of Premier and Cabinet have developed tools to assist councils to demonstrate the economic impact of their applications.

The relevant agencies provided feedback on unsuccessful applications to councils. Councils reported that the quality of this feedback has improved over time.

Recommendations

  1. By June 2018, Infrastructure NSW should:
    • ensure probity reports address whether all elements of the probity plan have been effectively implemented.
  1. By June 2018, Infrastructure NSW and Transport for NSW should:
    • maintain and store all documentation regarding assessment and probity matters according to the State Records Act 1998, the NSW Standard on Records Management and the relevant probity plans

Infrastructure NSW is responsible for overseeing and monitoring projects funded under Resources for Regions and Fixing Country Roads. Infrastructure NSW effectively manages projects to keep them on track, however it could do more to assure itself that all recipients have complied with funding deeds. Benefits and outcomes should also start to be measured and reported as soon as practicable after projects are completed to inform assessment of future projects.

Infrastructure NSW identifies projects experiencing unreasonable delays or higher than expected expenses as 'at‑risk'. After Infrastructure NSW identifies a project as 'at‑risk', it puts in place processes to resolve issues to bring them back on track. Infrastructure NSW, working with Public Works Advisory regional offices, employs a risk‑based approach to validate payment claims, however this process should be strengthened. Infrastructure NSW would get better assurance by also conducting annual audits of compliance with the funding deed for a random sample of projects.

Infrastructure NSW collects project completion reports for all Resources for Regions and Fixing Country Roads funded projects. It applies the Infrastructure Investor Assurance Framework to Resources for Regions and Fixing Country Roads at a program level. This means that each round of funding (under both programs) is treated as a distinct program for the purposes of benefits realisation. It plans to assess whether benefits have been realised once each project in a funding round is completed. As a result, no benefits realisation assessment has been done for any project funded under either Resources for Regions or Fixing Country Roads. Without project‑level benefits realisation, future decisions are not informed by the lessons from previous investments.

Recommendations

  1. By December 2018, Infrastructure NSW should:
    • conduct annual audits of compliance with the funding deed for a random sample of projects funded under Resources for Regions and Fixing Country Roads
    • publish the circumstances under which unspent funds can be allocated to changes in project scope
    • measure benefits delivered by projects that were completed before December 2017
    • implement an annual process to measure benefits for projects completed after December 2017
  1. By December 2018, Transport for NSW and Infrastructure NSW should:
    • incorporate a benefits realisation framework as part of the detailed application.

Published

Actions for Managing demand for ambulance services 2017

Managing demand for ambulance services 2017

Health
Information technology
Management and administration
Risk
Service delivery
Shared services and collaboration
Workforce and capability

NSW Ambulance has introduced several initiatives over the past decade to better manage the number of unnecessary ambulance responses and transports to hospital emergency departments. However, there is no overall strategy to guide the development of these initiatives nor do NSW Ambulance's data systems properly monitor their impact. As a result, the Audit Office was unable to assess whether NSW Ambulance's approach to managing demand is improving the efficiency of ambulance services.

Demand for ambulance services is increasing. Demographic factors including population growth and ageing have contributed to this and ongoing growth in demand is likely. It is important that NSW Ambulance finds ways to respond to this demand more efficiently, while maintaining patient safety standards and meeting community expectations.

Most triple zero calls to NSW Ambulance do not involve medical issues that require an emergency response. NSW Ambulance has introduced a range of initiatives to change the way it manages these less urgent requests for assistance. Its major demand management initiatives include using a telephone advice line, referring some patients to services other than hospital emergency departments and using specialist paramedics to respond to less urgent cases.

The role of NSW Ambulance has changed in recent years. It is aiming to become a ‘mobile health service’ that identifies the needs of patients and provides or refers them to the most appropriate type of care. This change involves a significant expansion of the clinical decision-making role of paramedics. Considerable strategic and organisational efforts are required to make this work. The successful implementation of demand management initiatives is important to NSW Ambulance's ability to continue to meet demand for its services.

This audit assessed NSW Ambulance's major demand management initiatives that aim to reduce unnecessary demand for ambulance responses and unnecessary transport to hospital emergency departments. It aimed to assess the extent to which these initiatives have improved the efficiency of its services.

Conclusion

NSW Ambulance has introduced several initiatives that aim to manage demand for its services from less urgent cases more efficiently. There is no overall strategy for these initiatives and NSW Ambulance’s data systems do not measure their outputs or outcomes. As a result, we are unable to assess the impact of NSW Ambulance's demand management initiatives on the efficiency of ambulance services. More focus is needed to ensure these initiatives achieve the efficiency improvements necessary to help NSW Ambulance meet future increases in demand.

Increasing demand for ambulance services is a key issue for NSW Ambulance. Demand has increased at a faster rate than population growth in recent years and continued growth is expected. NSW Ambulance has introduced several initiatives that aim to manage demand for its services from people with less urgent medical issues more efficiently and align its approach with the rest of the health system in New South Wales.

These individual initiatives lack a broader strategy to guide their development. NSW Ambulance’s demand management initiatives also lack clear goals and performance targets, with insufficient organisational resources allocated to support their implementation. NSW Ambulance does not have a data system that allows it to conduct accurate routine monitoring of the activity and performance of these initiatives.

More effort is required to make demand management initiatives a core part of NSW Ambulance's work. Key relationships with other health services to support demand management initiatives have only recently been established. NSW Ambulance has not communicated proactively with the public about its demand management initiatives. To ensure paramedics are as well prepared as possible for their expanded roles, they need better professional development and up to date technology.

Demand for ambulance services in New South Wales is increasing steadily. Forecast future increases in demand due to population growth and ageing mean that NSW Ambulance must improve its efficiency to maintain its performance.

Demand for ambulance services is growing at a rate higher than population growth. The increase in demand is likely to continue as the population continues to grow and age. NSW Ambulance has made several recent changes to remove large parts of demand for its services, including moving non-emergency patient transport to a separate government agency and changing the way triple zero calls are categorised.

These changes were expected to improve emergency response time performance, but the anticipated improvements have not been achieved. If demand continues to increase as forecast, NSW Ambulance will need to find more efficient ways to manage demand to maintain its performance.

NSW Ambulance has introduced initiatives to change the way it manages demand from patients who have less urgent medical issues. These have the potential to achieve positive results, but we were unable to fully assess their impact because of weaknesses in data systems and monitoring. More needs to be done to demonstrate progress toward the efficiency improvements required.

NSW Ambulance uses a telephone referral system to manage triple zero calls from people with medical issues that do not require an ambulance. This has the potential to achieve efficiency improvements but there are weaknesses in NSW Ambulance's use and monitoring of this system. Paramedics are now able to make decisions about whether patients need transport to a hospital emergency department. NSW Ambulance does not routinely measure or monitor the decisions paramedics make, so it does not know whether these decisions are improving efficiency. Extended Care Paramedics who have additional skills in diagnosing and treating patients with less urgent medical issues were introduced in 2007. NSW Ambulance analysis indicates that these paramedics have the potential to improve efficiency, but have not been used as effectively as possible.

Our 2013 audit of NSW Ambulance found that accurate monitoring of activity and performance was not being conducted. More than four years later, this remains the case. 

NSW Ambulance has recognised the need to change the way it manages demand and has developed initiatives that have the potential to improve efficiency. However, there are significant weaknesses in the strategy for and implementation of its demand management initiatives.

NSW Ambulance has identified the goal of moving from an emergency transport provider to a mobile health service and developed several initiatives to support this. Its demand management initiatives have the potential to contribute to the broader policy directions for the health system in New South Wales. However, there is no clear overall strategy guiding these initiatives and their implementation has been poor.

NSW Ambulance's reasons for changing its approach to demand management have not been communicated proactively to the community. Demand management initiatives that have been operating for over a decade still do not have clear performance measures or targets. Project management of new initiatives has been inadequate, with insufficient organisational resources to oversee them and inadequate engagement with other healthcare providers.

NSW Ambulance uses an in-house Vocational Education and Training course to recruit some paramedics, as well as recruiting paramedics who have completed a university degree. No other Australian ambulance services continue to provide their own Vocational Education and Training qualifications. Paramedics will need more support in several key areas to be able to fulfil their expanded roles in providing a mobile health service. Performance and development systems for paramedics are not used effectively. Up to date technology would help paramedics make better decisions and improve NSW Ambulance's ability to monitor demand management activity.

There are gaps in NSW Ambulance's oversight of the risks of some of the initiatives it has introduced, particularly its lack of information on the outcomes for patients who are not transported to hospital. Weaknesses in the way NSW Ambulance uses its data limit its ability to properly assess the risks of the demand management initiatives it has introduced.

Appendix one - Response from agency

Appendix two - About the audit

Appendix three - Performance auditing

 

Parliamentary reference - Report number #295 - released 13 December 2017

Published

Actions for Health 2017

Health 2017

Health
Asset valuation
Compliance
Financial reporting
Fraud
Information technology
Internal controls and governance
Management and administration
Procurement
Project management

The following report highlights results of the financial audits of entities in the NSW health cluster. The report focuses on key observations and findings from the most recent audits of these entities.

The report also includes a range of findings on service delivery. Overall, NSW Health is achieving most of their targets. Some local health districts are continuing to experience increased demand for their services and are finding it more difficult to meet their targets. For example, three local health districts had not achieved some emergency department response time targets for three consecutive years.

1. Financial reporting and controls

Financial Reporting

All health cluster entities received unqualified audit opinions and the quality of financial reporting remains high across the cluster.

Early close procedures were largely completed and all financial statements were submitted by the deadlines.

Financial performance

Overall, NSW Health recorded an operating surplus of $407 million in 2016–17. Eleven local health districts/specialty networks recorded operating deficits in 2016–17, four more than 2015–16.

Expenses across NSW Health increased by 4.4 per cent in 2016–17 (6.0 per cent in 2015–16), lower than the expected long term annual expense growth rate.

Excess annual leave Managing excess annual leave is a continual challenge for NSW Health, with thirty–five per cent of the workforce having excess balances.
Overtime payments NSW Health entities are generally managing overtime well; however NSW Ambulance’s overtime payments, $74.6 million in 2016–17, remain significantly higher than other health entities.
Time and leave recording practices Unapproved employee timesheets continue to be a problem for health entities. Weak timesheet approval controls increase the risk of staff claiming and being paid for hours they have not worked. There is also an increased risk of high volumes of roster adjustments, manual pays, salary overpayments and leave not being recorded accurately.

2. Service Delivery

Service Agreements Most of the service agreements between the Secretary of NSW Health and health entities were signed earlier than prior years.
Performance monitoring Five NSW Health entities are not meeting the Ministry of Health’s performance expectations at 30 June 2017.
Emergency department performance Data provided by the Ministry indicates NSW Health, on average, met emergency department triage response time targets across all triage categories for the fourth consecutive year.
Ambulance response times Data provided by the Ministry shows NSW Ambulance response times for imminently life‑threatening incidents of 7.5 minutes in 2016–17 was within the Ministry’s target of 10.0 minutes.

Data provided by the Ministry indicates NSW Ambulance response times for potentially life‑threatening incidents did not improve in 2016–17. The median response time of 11.1 minutes in 2016–17 was similar to 2015–16 (11.0 minutes). This is despite the number of Priority 1 responses reducing by 4.3 per cent.
Unplanned hospital re-admissions Data provided by the Ministry shows eight local health districts achieved the Ministry of Health’s unplanned hospital re‑admissions target in 2016–17. The target is for local health districts to reduce re‑admission rates from the previous financial year.

This report sets out the results of the 30 June 2017 financial statement audits of Health cluster entities.

The report has been structured into two chapters focusing on:

  • Financial reporting and controls
  • Service delivery.

This chapter outlines audit observations, conclusions and recommendations related to financial reporting and internal controls of entities for 2016-17.

Observation Conclusion or recommendation

2.1 Quality of financial reporting

All cluster entities received unqualified audit opinions and misstatements identified in financial statements fell. The quality of financial reporting remains high across the cluster.

2.2 Timeliness of financial reporting

Early close procedures were largely completed and all financial statements were submitted by the deadlines. Health entities controlled by the Ministry of Health continued submitting their financial statements well ahead of the statutory deadlines.

2.4 Financial and sustainability analysis

NSW Health recorded an operating surplus of $407 million in 2016–17.



Eleven local health districts/specialty networks recorded operating deficits in 2016–17, four more than 2015–16.


Expenses across NSW Health increased by 4.4 per cent in 2016–17 (6.0 per cent in
2015–16).

The capital replacement ratio of local health districts/specialty networks ranged from 0.5 to 5.7 in 2016–17. Seven local health districts had capital replacement ratio higher than one.

The statewide operating surplus was $84 million higher than 2015–16. Net surpluses contribute to NSW Health’s ability to invest in new facilities, upgrades and redevelopments.

The 2016–17 financial results were once again impacted by the NSW Government initiative to improve cash management across the sector.

The expense growth rate for NSW Health is 1.6 percentage points lower than the expected long term annual expense growth rate.

Substantial ongoing investment in hospitals and other assets across NSW Health is evidenced by high capital replacement ratios for some health entities in 2016–17.

2.5 Performance against budget
Ten local health districts/specialty networks’ expense budget variance was outside performance expectations agreed with the Ministry at the beginning of 2016–17. The Ministry continues to manage performance across NSW Health to improve the accuracy of budgeting practices.
2.7 Human Resources    

Thirty-five per cent of NSW Health’s workforce have excess annual leave balances.

 

 

 

 

 

 

NSW Ambulance had the highest average sick leave rate in NSW Health of 85.2 hours per FTE in 2016–17 (78.7 hours in 2015–16). This was higher than the statewide average of 62.1 hours (62.0 hours in 2015–16).

NSW Ambulance’s overtime payments in 2016–17 totalled $74.6 million; $2.8 million more than 2015–16 and significantly higher than other health entities

Other NSW Health entities are generally managing overtime well.

 

Unapproved employee timesheets continue to be a problem for health entities. Weak timesheet approval controls increase the risk of staff claiming and being paid for hours they have not worked.

 

Managing excess annual leave is a continual challenge for health entities.

Recommendation: Health entities should further review the approach to managing excess annual leave in 2017–18. They should:

  • monitor current and projected leave balances to the end of the financial year on a monthly basis
  • agree formal leave plans with employees to reduce leave balances over an acceptable timeframe.


NSW Ambulance continues to face significant challenges in managing sick leave.

Recommendation: NSW Ambulance should further implement and monitor targeted human resource strategies to address the high rates of sick leave taken

Recommendation: NSW Ambulance should further review the effectiveness of its rostering practices to identify strategies to reduce excessive overtime payments.

Recommendation: Health entities should conduct a risk‑based review of time and leave recording practices to ensure control weaknesses are identified and fixed.

This chapter outlines our audit observations, conclusions and recommendations relating to service delivery for 2016–17.

Observation Conclusion or recommendation
3.1 Service agreements in NSW Health

Most of the service agreements between the Secretary of NSW Health and health entities were signed earlier than prior years.

Thirteen local health districts/specialty networks signed their service agreements by the 31 July 2017 due date. This is a significant improvement with only seven local health districts/specialty networks meeting the date in 2015–16.

Having service agreements signed as close as possible to the start of each year provides the Ministry and NSW Health entities with clarity around roles, responsibilities, performance measures, budgets, and service volumes and levels.
3.2 Performance of NSW Health entities
Five NSW Health entities were not meeting the Ministry’s performance expectations at 30 June 2017. The Ministry is managing the five entities in accordance with its performance review process.
3.4 Emergency department response times

Data provided by the Ministry indicates NSW Health again, on average, met emergency department triage response time targets across all triage categories for the fourth consecutive year.

The Ministry manages performance across NSW Health to ensure patients presenting at emergency departments receive care in a clinically appropriate timeframe.

Based on the Ministry’s data, local health districts/specialty networks are, on average, meeting triage targets despite increasing emergency department attendances.

The data shows eleven local health districts met all triage targets in 2016–17, compared to eight in
2015–16. 

3.5 Emergency treatment performance

The Ministry manages public patient access to emergency services in public hospitals.

It has an emergency treatment performance target of 81 per cent of patients leaving emergency departments within four hours.

Data provided by the Ministry indicates NSW Health maintained its overall emergency treatment performance in 2016–17, but did not achieve its target. The State average emergency treatment performance was 74.2 per cent (74.2 per cent in 2015–16).

Based on the Ministry’s data, only four local health districts achieved the target in 2016–17, five in
2015–16.

3.6 Ambulance response times
NSW Ambulance has a response time target of 10.0 minutes for imminently life‑threatening incidents in New South Wales. Data provided by the Ministry indicates NSW Ambulance response times for imminently life-threatening incidents of 7.5 minutes in 2016–17 was within the Ministry’s target.
 
3.7 Transfer of care
The Ministry has a target of 90 per cent for the number of ambulance arrivals within a 30 minute ‘transfer of care’ timeframe. Data provided by the Ministry indicates the rate of ambulance arrivals within a 30 minute 'transfer of care' timeframe improved from 87.6 per cent in
2015–16 to 91.7 per cent in 2016–17, exceeding the Ministry’s target.
3.8 Average length of stay in hospital
Based on the Ministry’s 2016–17 data, the average length of stay for acute episodes was 3.0 days. The average length of stay in New South Wales hospitals is lower than the national average of 3.2 days (in 2015–16). The Ministry’s data shows the average length of stay by patients for acute episodes has remained stable in New South Wales hospitals for four years. 
3.9 Elective surgery access performance
Data provided by the Ministry indicates NSW Health continues to manage waiting times for elective surgery in public hospitals. The Ministry’s data shows NSW Health improved on‑time admission of patients for elective surgery in 2016–17 despite a 1.8 per cent increase in admissions. While the result improved, only one of the three targets for elective surgery waiting times was met in 2016–17.
3.10 Unplanned hospital re-admissions

Data provided by the Ministry indicates NSW Health, on average, did not reduce the rate of unplanned hospital re‑admissions in 2016–17. The Ministry has a target of reducing unplanned hospital re‑admissions compared to the previous financial year.

Low re‑admission rates may indicate good patient management practices and post-discharge care.

The Ministry’s data shows eight local health district met the target to reduce the rate of re‑admissions compared to the previous financial year. The statewide average rate increased from 6.3 per cent to 6.4 per cent.
3.11 Post discharge care for acute mental health patients
NSW Health has a goal to increase community-based care to acute mental health patients after they are discharged. Continuity of care in the community can lead to reduced symptom severity, lower re‑admission rates, and improved quality of life. The Ministry’s 2016–17 data shows the statewide average for post discharge follow-up of acute mental health patients within seven days was 70.0 per cent (66.0 per cent in 2015–16). The statewide average improved and met the NSW Health target of 70 per cent. Nine local health districts exceeded the NSW Health target.
3.12 Mental health acute re-admissions
NSW Health has a goal to reduce acute public sector mental health re-admissions. High re‑admission rates may indicate deficiencies in inpatient treatment and follow up care. The Ministry’s data shows twelve local health districts did not achieve the NSW Health target of 13 per cent mental health acute re‑admissions in 2016–17.
3.13 Unplanned and emergency re‑presentations

NSW Health aims to reduce the number of unplanned and emergency re‑presentations to emergency departments.

The Ministry’s 2016–17 data shows the State average of emergency department re‑presentations decreased marginally from 5.0 per cent in 2015–16 to 4.9 per cent.

Patients attending rural emergency departments are more likely to re‑present within 48 hours of being discharged than those in regional or metropolitan emergency departments.
3.14 Healthcare associated infection
The national target for the rate of Staphylococcus aureus (golden staph) bloodstream infection is two cases per 10,000 bed days. Data provided by the Ministry indicates the rate of golden staph bloodstream infection in New South Wales hospitals continues to be well below the target and national benchmark at 0.72 cases per 10,000 bed days in 2016–17 (0.75 in 2015–16).
3.15 Patient experience and satisfaction

The Bureau of Health Information analyses and reports on the results of patient surveys.

The Bureau’s survey shows 65 per cent of adult admitted patients rated the care they received in hospital as ‘very good’ and 29 per cent rated it as ‘good’.

NSW Health recognises that patient surveys are an important feedback mechanism on the health care system that can only come from personal experiences.

Published

Actions for Planning and evaluating palliative care services in NSW

Planning and evaluating palliative care services in NSW

Health
Management and administration
Service delivery
Workforce and capability

NSW Health’s approach to planning and evaluating palliative care is not effectively coordinated. There is no overall policy framework for palliative and end-of-life care, nor is there comprehensive monitoring and reporting on services and outcomes.

Palliative care is an essential component of modern health care services and an increasingly important part of the wider health and social care systems. Palliative care is healthcare and support for people with a life-limiting illness, their families and carers. It is provided by, or informed by, professionals who specialise in palliative care. ‘End of life’ care is provided to people approaching the end of life by health professionals, who may work in the health, community or aged care systems. Not everyone receiving end of life care needs palliative care.

NSW Health has a policy and planning role in palliative and end-of-life care, and it coordinates a wide range of service providers. Local Health Districts (LHDs) provide care services in settings such as homes, hospitals and clinics to patients with varying needs. There are several care providers that can be involved.

Due to this shared nature of palliative care — where many people, services and settings are involved in delivering care to the patient — availability and communication of information is critical. For service planning, data and evidence must be drawn from various sources in a timely and efficient way.

This audit assessed whether NSW Health is effectively planning and evaluating palliative care services, in the context of rising demand, increasingly complex needs, and the diversity of service providers.

Conclusion 

NSW Health’s approach to planning and evaluating palliative care is not effectively coordinated. There is no overall policy framework for palliative and end-of-life care, nor is there comprehensive monitoring and reporting on services and outcomes.  

NSW Health has a limited understanding of the quantity and quality of palliative care services across the state, which reduces its ability to plan for future demand and the workforce needed to deliver it. At the district level, planning is sometimes ad hoc and accountability for performance is unclear.

The capacity of LHDs to use accurate and complete data to plan and deliver services is hindered by multiple disjointed information systems and manual data collections. Further, a data collection on patient outcomes, for benchmarking and quality improvement, is not used universally. This limits the ability of districts to plan, benchmark and improve services based on outcomes data.

NSW Health's engagement with stakeholders is not systematic. The lack of an overall stakeholder engagement strategy puts at risk the sustainability and value of stakeholder input in planning and limits transparency.

Over the last two years, NSW Health has taken steps to improve its planning and support for districts. The Agency for Clinical Innovation has produced an online resource which will assist LHDs in constructing their own, localised models of care. eHealth, which coordinates information communication technology for the state’s healthcare, aims to invest in integrating and improving information systems. These initiatives should help to address many of the issues now inhibiting integrated service delivery, reporting on activity and outcomes, and planning for the future.

1. By July 2018, NSW Health should develop an integrated palliative and end-of-life care policy framework that:

  • clearly articulates the interface between palliative and end of life care and outlines the priorities for the respective areas
  • defines policy goals and objectives, and a performance and evaluation framework for palliative care service planning and delivery
  • informs a related workforce plan which supports the policy framework and is linked to the Health Professional Workforce Plan 2012–2022
  • reviews the funding allocation model to ensure future enhancement funds are distributed equitably and transparently based on the need and population of districts.

By December 2018, NSW Health should:

2. assess how the functionality provided in data collection programs such as the Palliative Care Outcomes Collaboration program can be provided across all palliative care services in NSW

3. complete its statewide review of systems and reporting for end of life management including specialist palliative care, and develop a business case to implement a more integrated set of solutions to:

  • support providers delivering end of life and palliative care
  • help monitor service quality and quantity
  • provide comprehensive data for service planning

4. improve stakeholder engagement by:

  • developing a statewide stakeholder engagement strategy that brings together current activity and good practice, and is transparent and publicly available
  • defining accountability for overseeing and implementing the strategy at state and district levels.

1. Performance monitoring is inadequate

NSW Government policy on palliative care is outlined in the NSW Government Plan to Increase Access to Palliative Care 2012–2016 (the Plan). Under the Plan, the overarching policy is ‘to ensure that everyone has access to quality palliative care regardless of their economic or social circumstances, their geographical location or their medical condition.’ Some initiatives under the Plan are still being implemented.

NSW Health only has measures in place to assess some processes and activities for individual initiatives under the Plan. There is no tracking of outcomes relating to the policy goals set out in the Plan, such as increased choice to die at home or the location of the patient’s choice, and improved access to specialist palliative care services. NSW Health has not conducted an overall assessment of the Plan’s outcomes to guide future priorities.

Further, there is no overall performance and reporting framework for palliative and end of life care, meaning there is no monitoring of performance of palliative care services for NSW as a whole. This lack of evaluation and performance measurement impacts on NSW Health's ability to monitor progress and achievements, address gaps in service, and plan for future service enhancement. 

2. Statewide planning and evaluation lacks coordination

Currently, palliative care services are complex to plan and evaluate. Many policies, strategies, guidelines, directives and data collections currently inform services. Even definitions of services vary. The split of policy functions for palliative care and end-of-life care between different branches within NSW Health adds further complexity. These arrangements create the risk of confusion, gaps in advice and support for LHDs.

Consistency is needed in the use of terminology and planning to achieve an integrated approach at all levels, including:

  • standard definitions of palliative care and end-of-life care
  • planning within a single structured policy framework to help clarify what services are to be delivered, who is accountable for delivering them and how to measure their outcomes.

Workforce planning is also affected. While NSW Health has identified significant gaps in the specialist palliative care workforce (especially in regional and remote areas) and it previously made workforce capacity one of its priorities, limited work has been undertaken in producing a statewide strategy to reduce these gaps.

3. District planning is not systematic and some external providers are poorly managed

An integrated approach would inform district-level service planning for palliative care. Planning in the districts we visited was sometimes ad hoc and accountability for performance unclear. Districts would benefit from:

  • better integrating data collection systems with planning
  • clearer guidelines, easy-to-use tools, monitoring and accountability systems.

The recently developed guide – A Blueprint for Improvement, from the Agency for Clinical Innovation – should help districts plan more effectively and consistently as it rolls out more widely in 2017. This takes an integrated approach to palliative and end-of-life care. Only one district we visited has finalised a comprehensive plan using the Blueprint.

Issues with district planning extend to external agreements with service providers, as these are sometimes poorly managed and do not support improved patient outcomes. Examples we reviewed showed a significant reporting burden with process-focused reporting. We also found little evidence of monitoring or action as a result of these reports.

4. Diverse information systems mean data collection and use are inconsistent

NSW Health gathers a broad range of data from many collection points and systems to inform palliative care services at hospital, ward or unit level, and community teams. However, the current data is limited because: 

  • activity is under-reported, particularly in community-based services
  • collection is not universal across districts and services.

Districts also struggle with evidence-based planning and service delivery because multiple information systems mean data may be incomplete or inaccurate. Too often, clinicians and service managers rely on manual collection and paper-based systems. 

eHealth, which coordinates information communication technology (ICT) for the state’s healthcare, is planning a statewide approach to capture information and report on all palliative care activity. The current plans of eHealth to review and improve systems should make data more complete, robust and accessible for quality improvement and planning.

5. An overarching stakeholder strategy would strengthen engagement

Just as data is central to effective planning and evaluation, so too is stakeholder engagement. However, there is currently no explicit stakeholder strategy, which means consultation is inconsistent across the state and not systematic at a district level.

While NSW Health uses a range of platforms to consult, the purpose and value is often not clear to stakeholders. Individual districts have some good practices, but there are limited mechanisms to identify and share these with other areas. A state-wide strategy would improve the quality and consistency of engagement, which will in turn inform service planning and delivery.

A stakeholder engagement strategy would integrate current initiatives, such as the two major networks that consult with health planning staff and clinicians. But it will also need to extend the feedback gathered from families, carers and volunteers, and from the peak bodies that represent them.