Refine search Expand filter

Reports

Published

Actions for WestConnex: Assurance to the Government

WestConnex: Assurance to the Government

Transport
Treasury
Premier and Cabinet
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk

This audit assesses the assurance provided to the NSW Government for the initial stages of the WestConnex project.

The audit examined the WestConnex project from concept development to the pre-tender phase for Stage 1A – M4 (Parramatta to Homebush Bay). It did not examine the merit of the project or whether it represented value-for-money.

This audit found a number of shortcomings with the governance of the WestConnex project during its early stages and makes recommendations on how to better govern the remainder of the project to minimise the risk of failure.

 

Parliamentary reference - Report number #247 - released 18 December 2014

Published

Actions for Volume Fourteen 2014 Focusing on Trade and Investment

Volume Fourteen 2014 Focusing on Trade and Investment

Planning
Finance
Asset valuation
Financial reporting
Information technology
Internal controls and governance
Risk

There are 63 agencies in the DTIRIS cluster. These agencies include nine electricity and eight water agencies that were reported in the NSW Auditor-General’s report to Parliament Volume Five 2014 on 11 November 2014. Commentary in this volume is on the remaining 46 DTIRIS cluster agencies. The findings found the quality of financial statements in the trade and investment cluster needs to improve.

Published

Actions for Volume Thirteen 2014 Focusing on Education and Communities

Volume Thirteen 2014 Focusing on Education and Communities

Education
Community Services
Asset valuation
Compliance
Financial reporting
Information technology
Internal controls and governance
Project management
Risk

The quality of financial statements in the education and communities cluster continues to improve with fewer reported misstatements over the last three years. The financial statements of all agencies within this cluster received unqualified audit opinions. The Department of Education and Communities has 24 performance targets for early childhood through to tertiary education. Seven of these are either not being achieved or unlikely to be achieved.

Published

Actions for Volume Seven 2014 Focusing on Transport

Volume Seven 2014 Focusing on Transport

Transport
Asset valuation
Compliance
Financial reporting
Information technology
Internal controls and governance
Project management
Risk

All agencies in transport cluster received unqualified audit opinions for the year ended 30 June 2014. The quality of financial reporting continues to improve with the number of misstatements identified during audits falling for the fifth year in a row.

Published

Actions for Regional Road Funding - Block Grant and REPAIR Programs

Regional Road Funding - Block Grant and REPAIR Programs

Transport
Internal controls and governance
Management and administration
Project management
Risk

In 2013–14, Roads and Maritime Services (RMS) provided over $170 million to local councils through the Block Grant and REPAIR programs to spend on Regional Roads. Regional Roads are the link between State Roads and Local Roads.

 

Parliamentary reference - Report number #241 - released 8 May 2014

Published

Actions for Volume One 2014 - Areas of focus from 2013

Volume One 2014 - Areas of focus from 2013

Education
Community Services
Finance
Health
Industry
Justice
Local Government
Planning
Premier and Cabinet
Transport
Treasury
Universities
Whole of Government
Environment
Asset valuation
Compliance
Financial reporting
Fraud
Information technology
Internal controls and governance
Procurement
Project management
Risk

Today the Auditor-General of New South Wales, Grant Hehir, released his Volume One Report to Parliament for 2014. The observations included in this report are designed to inform readers of common findings from the 2013 financial and performance audits so agencies and audit committees can use them to identify issues that may be relevant to their organisations.

Published

Actions for Volume Nine 2011 focus on Education and Communities

Volume Nine 2011 focus on Education and Communities

Education
Community Services
Asset valuation
Internal controls and governance
Management and administration
Project management
Workforce and capability

The report includes comments on financial audits of government agencies in the Education and Communities sectors. The audits of the above entities’ financial statements for the year ended 30 June 2011 resulted in unmodified audit opinions within the Independent Auditor’s Reports. A key finding was that Treasury should consider issuing further guidance to arts and cultural bodies on collection valuation methodologies due to the significance of these assets to the State’s asset base.

Published

Actions for Volume Eight 2011 Focus on Transport and Ports

Volume Eight 2011 Focus on Transport and Ports

Transport
Industry
Asset valuation
Financial reporting
Fraud
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Workforce and capability

The report includes comments on financial audits of government agencies in the Transport and Ports sectors. The audit of corporations’ financial statements for the year ended 30 June 2011 resulted in unmodified audit opinions within the Independent Auditor’s Reports. A key recommendation from the report is that Sydney Ports Corporation should continue working with other government authorities and industry stakeholders to improve the effectiveness of program initiatives for increasing container freight movements by rail. The Corporation should review the underlying causes hindering growth in the rail mode and develop and implement strategies to address the unfavourable trend.

Published

Actions for Solar Bonus Scheme

Solar Bonus Scheme

Premier and Cabinet
Compliance
Infrastructure
Management and administration
Project management
Regulation
Risk
Service delivery

A NSW Auditor General’s Report has found that the NSW Government and its agencies grossly underestimated the cost and number of people that would install systems under the Solar Bonus Scheme.

By October 2010, the estimated cost of the Scheme, if it continued the way it was going, would have reached $3.988 billion. More than ten times the original estimate of $362 million. In response to the increased cost, the gross tariff for new applicants was reduced from 60 to 20 cents reducing the estimated cost to $1.954 billion.

It was a statutory requirement that when 50 mega watts of installed capacity was reached, the Government would review the Scheme. By the time the review was completed the installed capacity had reached 101 mega watts.

Published

Actions for Prequalification Scheme: Performance and Management Services

Prequalification Scheme: Performance and Management Services

Premier and Cabinet
Finance
Compliance
Internal controls and governance
Management and administration
Regulation
Risk
Workforce and capability

There have been tangible improvements in the time it takes NSW Government agencies to engage consultants through the Government’s Prequalification Scheme. The Scheme was introduced in February 2008 to improve agencies’ procurement of consultants. More than 300 service providers have been prequalified and over $300 million worth of consultancy services have been provided. Ideally agencies should know what assignments each consultant has won, for what services, what their rates are and how well they have performed. Agencies should then be free to contact other agencies before engaging a consultant.

 

Parliamentary reference - Report number #216 - released 28 September 2011