Refine search Expand filter

Reports

Published

Actions for Treasury 2022

Treasury 2022

Treasury
Asset valuation
Compliance
Cyber security
Financial reporting
Information technology
Internal controls and governance
Management and administration
Procurement
Regulation
Risk
Service delivery
Shared services and collaboration

What the report is about

Results of the Treasury cluster agencies' financial statement audits for the year ended 30 June 2022.

The results of the audit of the NSW Government's consolidated Total State Sector Accounts (TSSA), which is prepared by NSW Treasury, are reported separately in our report on 'State Finances 2022'.

What we found

Unmodified audit opinions were issued on all 30 June 2022 general purpose financial statement audits.

Qualified audit opinions were issued on three of the 25 other engagements prepared by cluster agencies. These related to payments made from Special Deposit Accounts (SDA) that did not comply with the relevant legislation.

What the key issues were

Commercial agreements were signed between TAHE, the operators and Transport for NSW in June 2022, which reflected an expected rate of return of 2.5% on contributed equity. However, it remains critical that the government continue to provide sufficient funding to the operators so they can pay for access and use TAHE assets. These findings are reported in our report on 'State Finances 2022'.

Eight high-risk issues were raised in 2021–22, of which five relate to NSW Treasury.

A number of previously reported audit findings and recommendations with respect to icare continue to be ongoing issues. This includes the Workers Compensation Nominal Insurer continuing to hold less assets than the estimated present value of its future payment obligations, when measured in accordance with the accounting framework.

What we recommended

Our report on 'State Finances 2022' made several recommendations to improve NSW Treasury's processes.

In this report, we recommended icare should ensure:

  • it has sufficient controls in place over claim payments, including an effective quality assurance program, to minimise claim payment errors
  • that documentation to support PIAWE calculations is appropriately maintained, and that the minimum documentation requirements are set out in a policy.

This report provides Parliament and other users of the Treasury cluster’s financial statements with the results of our audits, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision-making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Treasury cluster (the cluster) for 2022.

Section highlights

  • Unqualified audit opinions were issued on the general purpose financial statements of all cluster agencies.
  • A qualified opinion was issued on the NSW Government's consolidated Total State Sector Accounts (TSSA), which are prepared by NSW Treasury. This is reported separately in our 'State Finances 2022' NSW Auditor-General's Report to Parliament.
  • Three qualified audit opinions were issued on special purpose financial reports, relating to whether payments from the funds complied with the relevant legislation.
  • Reported corrected misstatements increased from seven in 2020–21 to ten in 2021–22 with a gross value of $808.6 million. Reported uncorrected misstatements decreased from 17 in 2020–21 to 11 in 2021–22 with a gross value of $85.7 million.
  • Nine of 15 cluster agencies either did not submit or did not complete certain mandatory early close procedures on time.
  • NSW Treasury corrected a $39.7 million prior period error retrospectively in the financial statements as it overstated its accrual at 30 June 2021 relating to hotel quarantine costs.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the Treasury cluster.

Section highlights

  • Eight high-risk issues were identified in 2021–22, an increase from four high-risk and one extreme risk in 2020–21. A further 31 moderate risk findings were reported in 2021–22, of which 12 were repeat findings.
  • Inconsistencies in the Government Sector Finance Act 2018 (GSF Act) and Government Sector Audit Act 1983 (GSA Act) relating to key statutory timeframes have been addressed.
  • Further to last year's reporting, some agencies have again spent moneys without an authorised delegation. 
  • There was a lack of quality review of submissions for audit by NSW Treasury.
  • The Nominal Insurer's net assets decreased from a $2.5 billion surplus at 30 June 2018, to a $1.2 billion deficiency at 30 June 2022.
  • The Nominal Insurer's return-to-work rates stabilised, but remain below the performance levels prior to the COVID-19 pandemic.
  • The Nominal Insurer paid $29.5 million in 2021–22 to remediate historical underpayment of compensation benefits to workers (Pre-Injury Average Weekly Earnings (PIAWE) payments), and a further $8.5 million was payable at 30 June 2022.
  • During its review of historical PIAWE errors, icare found that indexation may have been incorrectly applied, or failed to have been applied when determining injured worker entitlements within the Nominal Insurer between 2012 and 2019. Based on calculations provided by icare, the Audit Office reported an uncorrected judgemental misstatement of $28.5 million (understatement).

Appendix one – Misstatements in financial statements submitted for audit

Appendix two – Early close procedures

Appendix three – Timeliness of financial reporting

Appendix four – Financial data

Appendix five – Acquittals and other opinions

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for State Finances 2022

State Finances 2022

Treasury
Whole of Government
Asset valuation
Compliance
Cyber security
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Regulation
Risk

What the report is about

Results of the 2021–22 consolidated General Government Sector (GGS) and Total State Sector (TSS) financial statements audits.

What we found

The Independent Auditor’s Report on the 2021–22 GGS and TSS financial statements was modified with a limitation of scope and also contained an emphasis of matter.

The opinion in the TSS Independent Auditor’s Report was modified with a limitation of scope on certain balances consolidated in the TSS financial statements because the Catholic Metropolitan Cemeteries Trust (CMCT) denied access to its management, books and records for the purpose of conducting a financial audit.

The Independent Auditor’s Report also includes an emphasis of matter drawing attention to the significant uncertainties associated with the GGS’s equity investment in Transport Asset Holding Entity (TAHE). The significant uncertainty relates to key assumptions and estimates used to forecast a 2.5% return from GGS investments into TAHE that supports the accounting treatment as an equity injection, including:

  • funding to support the Rail Operators to pay TAHE’s contracted and forecast access and licence fees up until 2045–46. The Rail Operators are dependent on funding from the GGS to pay access and licence fees. Forecast modelling notes a requirement of a further $10.2 billion in budget funding to pay TAHE to the end of the ten-year contract period in 2030–31, in addition to the $5.5 billion allocated in the forward estimates and up to $50.8 billion for the period 2032 to 2046
  • a significant portion of the projected returns are earnt outside of the ten-year contract period and there is a risk that TAHE may not be able to recontract fees at levels consistent with current projections.

What we recommended

The report includes a number of recommendations including:

  • continued monitoring that TAHE controls the reported assets ensuring the CMCT, Category 2 Statutory Land Managers (SLM) and Commons Trusts meet their statutory reporting obligations
  • ensuring accounting and audit position papers are sufficiently consulted with key stakeholders and are concluded on a timely basis
  • ensuring agencies support the timely conclusion of audits by bringing to the auditors' attention key Cabinet records and identifying references relating to accounting issues impacting the financial statements
  • for Special Deposit Accounts (SDA) responsible managers should ensure amounts appropriated under any Act or law for payment into the account are appropriately recorded, ensuring payments from SDAs are allowable and made in accordance with Treasurer's delegations and standing authorisation.
Image
Margaret Crawford, Auditor-General for New South Wales

Pursuant to section 52A of the Government Sector Audit Act 1983 I am pleased to present my Auditor-General’s Report on State Finances 2022.

Once again this year has presented considerable challenges for the state sector and my Office as we collectively grapple with uncertainties related to COVID-19 and the disruption of emergency events impacting New South Wales. In addition, there were many recommendations arising from last year’s audit to be addressed.

While there is more to do to ensure good financial stewardship of the State, resolution of matters was helped by constructive engagement with the NSW Treasury at the most senior levels. Personally I wish to thank the Treasurer and Secretary for their commitment to instilling integrity in financial management systems and processes. The support Treasury provided for recent amendments to the Government Sector Audit Act 1983 to provide ‘follow the dollar’ powers and other changes recommended by the Public Accounts Committee quadrennial review of my Office is also acknowledged.

Finally I want to thank the teams that contributed to this year’s audit of the Total State Accounts for their diligence, professionalism and commitment. I am very proud of your work.

Margaret Crawford

Auditor-General for New South Wales

The Independent Auditor's Report was qualified and also included an emphasis of matter

The audit opinion on the State's 2021–22 financial statements was modified. The delayed signing of the NSW Total State Sector Accounts (TSSA) by NSW Treasury was in order to resolve significant accounting issues that were material to the TSSA. The key areas requiring significant audit effort included reviewing the State's accounting for TCorp Investment Management (IM) Funds and responding to the risks related to the Catholic Metropolitan Cemeteries Trust (CMCT) denying access to its management and books and records, which is detailed in this Report.

NSW Treasury aimed to sign the TSSA by 19 October 2022. This was delayed by nearly six weeks and the TSSA audit opinion was subsequently signed on the statutory deadline imposed on the Treasurer for tabling of the TSSA in the Legislative Assembly of 30 November 2022.

The Independent Auditor’s Report was modified due to a limitation of scope on the balances consolidated in the TSSA relating to the CMCT

The opinion in the Independent Auditor’s Report was modified with a limitation of scope due to the inability to access management, books and records of a controlled entity, the CMCT.

This year, NSW Treasury, after reconsidering all facts and the perspectives of the CMCT, reconfirmed that the CMCT is a controlled entity of the State for financial reporting purposes. This means CMCT is a GSF agency under the provisions of the Government Sector Finance Act 2018 (GSF Act). As such NSW Treasury is required by Australian Accounting Standards to consolidate the CMCT into the Total State Sector Accounts (TSSA). The value of assets and liabilities of CMCT consolidated into the TSSA is $310.3 million and $15.1 million, respectively, and the loss of CMCT consolidated into the TSSA for the year is $2.4 million.

To date, CMCT has not met its statutory obligations to prepare financial statements under the GSF Act and give them to the Auditor-General. CMCT has not submitted its financial statements to the Auditor-General for audit as required despite repeated requests and has not provided access to its books and records for the purposes of a financial audit. The Secretary of the Department of Planning and Environment wrote to CMCT to request it work with, and offer full assistance to, the Auditor-General in the exercise of her duties.

NSW Treasury has met with and considered CMCT's perspectives. NSW Treasury’s position remains that CMCT is a controlled entity of the State for financial reporting purposes. Consequently, CMCT has not met its statutory obligations as a controlled entity to submit its financial statements for audit and provide access to its books and records. Therefore, the Audit Office was unable to obtain sufficient appropriate audit evidence about the carrying amount of assets and liabilities consolidated into the Total State Sector Accounts as at 30 June 2022 and of the amount of income and expenses for the year then ended. Accordingly a modified audit opinion was issued on the NSW Government's 2021–22 consolidated financial statements.

Section 3 of this report titled 'Limitation of Scope relating to CMCT' discusses this matter in further detail.

An emphasis of matter drawing attention to uncertainty relating to the General Government Sector's investment in the Transport Asset Holding Entity (TAHE) remains

The Independent Auditor’s Report also includes an emphasis of matter, drawing attention to the significant uncertainties associated with the General Government Sector's (GGS) equity investment in TAHE. The significant uncertainty relates to key assumptions used to forecast returns from investments into TAHE in order to support the recognition of the government's funding of TAHE as an equity injection.

At the time of signing the Independent Auditor's Report, there was significant uncertainty with regards to assumptions and estimates used to forecast a return from the GGS investment into TAHE, which supports the recognition of an equity injection. There is significant uncertainty relating to:

  • the 2022–23 Budget committed $5.5 billion to fund TAHE's key customers, Sydney Trains and NSW Trains (the operators), to support their payment of access and licence fees agreed on 23 June 2022. However, this funding only extends out to the end of the forward estimates period in 2025–26, which falls short of the ten-year contractual periods to 2030–31 and the projected period to 2045–46 to achieve a 2.5% return from the government's equity investment. The government will need to fund the operators an additional $10.2 billion in Budget funding so that they can meet their contractual obligations to TAHE from 2026–27 to 2030–31, and a further projected funding of $50.8 billion from 2031 to 2046. This additional funding is not within the government's published Budget figures, leading to uncertainty on whether the government-funded operators can pay access and licence fees beyond the forward estimates period of 2025–26
  • a significant portion of the projected returns are earnt outside the ten-year contract period (terminating 30 June 2031) and there is a risk that TAHE will not be able to recontract for access and licence fees at a level that is consistent with current projections. There is also a risk that funding for TAHE's key customers will not be sufficient to fund payment of access and licence fees at a level that is consistent with current projections.

The 'State Finances 2021' report made recommendations regarding the significant accounting issues relating to TAHE. The State's response to these recommendations are detailed in Section 4 of this report titled ‘Investment in the Transport Asset Holding Entity’. Other significant matters related to the TSSA audit are covered in Section 8 titled ‘Key audit findings’.

Other financial reporting matters

All government agencies were granted an extra week to submit financial statements for audit

A one-week extension provided agencies across the sector with additional time to resolve key accounting issues and submit financial statements for audit by 1 August 2022.

Further extensions were approved for the following seven agencies (ten in 2020–21):

  • State Insurance Regulatory Authority (3 August 2022)
  • Dams Safety NSW (8 August 2022)
  • Jenolan Caves Reserve Trust (8 August 2022)
  • Transport for NSW (8 August 2022)
  • Department of Enterprise, Investment and Trade (22 August 2022)
  • Transport Asset Holding Entity (22 August 2022)
  • Department of Transport (26 August 2022).

Additional extensions provided agencies with more time to complete:

  • asset valuations
  • valuations of actuarially assessed liabilities.

An initial draft of the TSSA was provided to audit on 15 September 2022. This version was incomplete and excluded the impact of consolidating the State's TCorp IM funds under the correct Australian Accounting Standards. An additional three versions of the draft TSSA were provided to audit progressively to update the TCorp IM fund consolidated balances. The final complete version of the TSSA was submitted on 27 October 2022 which included all adjustments relating to the TCorp IM fund consolidation. Refer to section 8.1 for more details on the material restatements relating to the consolidation of the TCorp IM funds.

In 2021–22, agency financial statements presented for audit contained 20 errors exceeding $20 million (24 in 2020–21). The total value of these errors was $973 million, a decrease from the previous year ($6.6 billion in 2020–21).

The graph below shows the number of reported errors exceeding $20 million over the past five years in agencies’ financial statements presented for audit.

The errors resulted from:

  • incorrect application of Australian Accounting Standards and NSW Treasury policies
  • incorrect judgements and assumptions when valuing non-current physical assets and liabilities.

NSW Treasury concluded CMCT is a controlled entity of the State

In response to our recommendation in the ‘State Finances 2021’ report, NSW Treasury reconfirmed that the Catholic Metropolitan Cemeteries Trust (CMCT) is a controlled entity of the State. The Audit Office accepted the position of NSW Treasury.

The reaffirmation of this position means CMCT is a GSF agency under the provisions of the Government Sector Finance Act 2018 (GSF Act). Section 7.6 of the GSF Act places an obligation on CMCT to prepare financial statements and give them to the Auditor-General. Further, section 34 of the Government Sector Audit Act 1983 (the GSA Act) requires the Auditor-General to furnish an audit report on these financial statements.

To date, CMCT has not met its statutory obligations to prepare financial statements under the GSF Act and give them to the Auditor-General. CMCT has not submitted their financial statements to the Auditor-General for audit despite repeated requests and has not provided access to its books and records for the purposes of a financial audit. There was extensive correspondence between the Audit Office of NSW, CMCT, NSW Treasury and the Department of Planning and Environment in 2022 regarding this matter.

Recommendation

NSW Treasury and the Department of Planning and Environment should ensure the Catholic Metropolitan Cemeteries Trust meets its statutory reporting obligations.

In addition, on 10 December 2021, the then Minister for Water, Property and Housing wrote to the Auditor-General requesting a financial and performance audit be performed pursuant to section 27B(3)(c) of the GSA Act. The audit would cover the financial affairs of CMCT, including whether funds have been used for the proper purpose. The Audit Office of New South Wales has written to CMCT on a number of occasions to request the provision of documentation and access to management in order to conduct the performance audit. CMCT has not provided the Audit Office of New South Wales access to its management, books and records for the purpose of the required performance audit.

NSW Treasury has met with and considered CMCT's perspectives. NSW Treasury’s position remains that CMCT is a controlled entity of the State for financial reporting purposes. Consequently, CMCT did not meet its statutory obligations as a controlled entity to submit its financial statements for audit and provide access to its books and records.

The TSSA audit opinion included a limitation of scope

The opinion in the TSSA Independent Auditor’s Report was modified with a limitation of scope due to an inability to access management and the books and records of CMCT. This limitation was appropriately disclosed in Note 1 'Statement of Significant Accounting Policies' of the TSSA. The Statement of Compliance signed by the Secretary of Treasury and the Treasurer on 29 November 2022 was also updated to acknowledge the disclosure in Note 1 regarding CMCT.

The Audit Office was unable to obtain sufficient appropriate audit evidence about the carrying amount of assets and liabilities consolidated into the Total State Sector Accounts as at 30 June 2022 and of the amount of income and expenses for the year then ended. Accordingly a modified audit opinion was issued on the NSW Government's 2021–22 consolidated financial statements.

The process of information sharing by NSW Treasury continues to require improvement

In last year’s ‘State Finances 2021’ report an extreme risk management letter finding was reported for NSW Treasury to ensure it significantly improve its processes so that all relevant information is identified and shared with the Audit Office to support material transactions and balances of the State.

A number of events reconfirmed that NSW Treasury needs to continue improving its process with respect to information sharing with the Audit Office. Notably, NSW Treasury’s finance team had not demonstrated that all available information (on their systems) was considered by them when assessing the State’s control over CMCT.

Critical information relating to CMCT was in the possession of NSW Treasury since late October 2021 but not considered when reconfirming their accounting position on the State's control of CMCT this year. A further reconfirmation of the State's control over CMCT was needed by NSW Treasury to ensure this information was considered in their accounting assessment.

The above demonstrates that more effective consultation is required by NSW Treasury with key stakeholders to ensure all information relevant to forming an accounting position relating to the TSSA is captured. This will ensure new information is not identified late in the audit process and NSW Treasury considers all information when concluding on the accounting position of the State.

Recommendation

NSW Treasury should ensure when drafting position papers and concluding on accounting issues impacting the State, these are provided to audit on a timely basis and reflect a complete and accurate understanding of the key public sector issues being considered.

Last year's report highlighted that NSW Government actions avoided a qualified opinion in 2020–21 relating to the General Government Sector's $2.4 billion cash contribution to Transport Asset Holding Entity (TAHE). These actions included the NSW Government agreeing to provide additional future funding to TAHE's key government customers Sydney Trains and NSW Trains (the operators) to support increases in access and licence fees to be paid to TAHE.

The additional funding by the government was necessary to demonstrate that a reasonable expectation of a sufficient rate of return would be earned on its equity invested in TAHE. Last year, there was no government policy on what the minimum return should be on investments in other public sector entities, so the long-term inflation rate was used as a benchmark. A recommendation was made in last year's State Finances report that NSW Treasury establish a policy on the minimum expected return from its investments.

On 6 September 2022, NSW Treasury finalised its policy relating to the government’s returns on equity investments. The application of this policy is limited to State Owned Corporations and similar to the Commonwealth framework for commercial businesses, which requires the expected return be at least equal to the long-term inflation rate.

The government's commitment to additional funding was conveyed last year through revised shareholder expectations being published in the 2021–22 'NSW Budget-Half yearly Review' on 16 December 2021, increasing the expected returns on equity from 1.5% to the expected long-term inflation rate of 2.5%. On 18 December 2021, Transport for NSW (TfNSW) and the operators entered into a Heads of Agreement (HoA). This formed the basis of negotiations to revise the pricing within the existing ten-year contracts and deliver upon the shareholders’ expected return of 2.5% on contributed equity to be earned over the estimated weighted average remaining useful lives of TAHE's assets.

Further information on last year's audit of the government’s investment in TAHE can be found in our 'State Finances 2021' report.

Ten-year commercial agreements were signed between TAHE, operators and TfNSW

Last year's State Finances report recommended that NSW Treasury facilitate revised commercial agreements to reflect the access and licence fees detailed in the HoA. As these agreements were not executed by 30 June 2021, last year's audit opinion of the Total State Sector Accounts (TSSA) included an Emphasis of Matter drawing attention to the uncertainty that existed at balance date as these agreements were not finalised.

On 23 June 2022, commercial agreements were signed between TAHE, the operators and Transport for NSW through a deed of variation. The revised access and licence fees for the ten-year period 2021–22 to 2030–31 was $16.6 billion, which is $520 million less than the HoA fees of $17.1 billion.

Comparison FY22
$m
FY23
$m
FY24
$m
FY25
$m
FY26
$m
FY27
$m
FY28
$m
FY29
$m
FY30
$m
FY31
$m
Total
$m
Revised commercial agreements 641.1 911.8 1,298.1 1,585 1,807.3 1,921.8 1,992 2,065.4 2,139.1 2,252.8 16,614.4
HoA 679.9 1,081.4 1,236 1,398.9 1,645.8 1,826.1 2,023.3 2,209.4 2,404.5 2,629.2 17,134.6
Difference (38.8) (169.6) 62.1 186.1 161.5 95.7 (31.3) (144) (265.4) (376.4) (520.2)

TAHE's main customers principally rely on government funding to pay access and licence fees

Whilst TAHE has agreed ten-year access and licence fees of $16.6 billion with its two main customers Sydney Trains and NSW Trains, these two operators significantly rely on government funding when making these payments to TAHE. At 30 June 2022, TAHE's expected return of 2.5% is contingent upon the GGS funding the operators to support their payment of access and licence fees that have been agreed with TAHE for the ten-year contracted period and for non-contracted periods from 2031–32 to 2045–46.

The 2022–23 NSW Budget has allocated $5.5 billion to fund the operators, to support their payment of access and licence fees. However, this funding extends to the end of the forward estimates period in 2025–26, which falls short of the ten-year contractual period to 2030–2031 and the projected period to 2045–46 to achieve the 2.5% return.

  2022–261
$b
2027–20312
$b
2032–46
$b
Total
$b
Access and licence fees3 5.5 10.2 50.8 66.5

1 Represents the 2022–23 Budget year and three-year forward estimates which includes: FY2024–26.
2 Whilst excluded from the 2022–23 NSW Budget, these access and licence fees are included in the ten-year commercial agreement between TAHE, operators and TfNSW.
3 Represents cumulative access and licence fees for the period stated.

The government will need to fund the operators an additional $10.2 billion in budget funding to meet their contractual obligations to TAHE from 2026–27 to 2030–2031, and a further projected funding of $50.8 billion from 2032 to 2046. This is needed to ensure the government continues to demonstrate its expected return on investment of 2.5%. This additional funding is not within the government's published 2022–23 NSW Budget figures, leading to uncertainty on whether the government funded operators can pay access and licence fees beyond the forward estimate period of 2025–26.

Significant funding uncertainties remain

While the ten-year access and licence fee agreements were communicated to the NSW Government's Expenditure Review Committee, it is yet to be fully provided for in the government's budget figures. As TAHE's projections are highly dependent on the operators as its key customers, it remains critical that the government continue to provide sufficient funding to the operators so they can pay for access and use of TAHE assets. This means the significant funding uncertainties reported in last year's TSSA audit opinion remain for 2021–22.

The government has estimated $37.9 billion in returns (equivalent to 2.5% on contributed equity) is to be earned from its investment in TAHE over the period from 1 July 2022 to 30 June 2046. As previously reported, TAHE derives most of its revenue from access and licence fee agreements from the operators, who in turn are both funded by grants through TfNSW from the GGS. More than 95% of these returns are estimated to be earned outside of the ten-year contract period (terminating 30 June 2031).

  2022–261
$b
2027–20312
$b
2032–46
$b
Total
$b
Returns to GGS 1.8 4.7 31.5 37.9

1 Represents the 2022–23 budget year and three-year forward estimates which includes: 2023–24, 2024–25 and 2025–26.
2 Whilst excluded from the 2022–23 NSW Budget, these access and licence fees are included in the ten-year commercial agreement between TAHE, operators and TfNSW.

There remains risk that:

  • TAHE will not be able to recontract for access and licence fees at a level that is consistent with current projections
  • future governments' funding to TAHE's key customers will not be sufficient to fund payment of access and licence fees at a level that is consistent with current projections
  • TAHE will be unable to grow its non-government revenues.

This significant funding uncertainty was also reported in last year's TSSA audit opinion and will remain for 2021–22.

In 2021–22, TAHE and NSW Treasury prepared further modelling to support the Government's intent to earn a 2.5% return inclusive of recovering the holding (revaluation) loss of $20.3 billion on its investment in TAHE

Last year's State Finances report highlighted that NSW Treasury, with TAHE, should prepare robust projections and business plans to support the expected returns forecast beyond FY2031.

This year TAHE engaged an expert to help develop a model demonstrating the government's expected returns from its investment in TAHE. The model mathematically forecasts that returns of 2.5% will be achieved by 2046 and this will include recovery of the revaluation losses of $20.3 billion relating to 2020–21.

The current model includes some key assumptions:

  • The main source of revenue is the access and licence fees expected from the two public rail operators (Sydney Trains and NSW Trains) contributing to more than 80% of TAHE's projected revenue. The rail operators are largely funded by the government when paying access and licence fees to TAHE.
  • For the first ten years, the access and licence fees are based on the signed agreements between TAHE and the public rail operators.
  • Beyond the ten-year contracted period, the model assumes existing contractual terms for access and licence fees will continue unchanged allowing for an annual rise for inflation (2.5% per annum), and increased fees to enable a 7.62% return for renewed assets.
  • The capital expenditure included in the model is only the amounts approved by the Expenditure Review Committee (ERC) as part of the ten-year forecast. The model beyond ten years includes expected investment in renewed and replacement assets but excludes any forecasts relating to growth capex that is not approved by the ERC, and any related depreciation expenses for growth capex.

While management has developed a 35-year long term financial model to support the returns, we note this will need to be refined over the next few years. Furthermore, these are forecasted figures and we have not seen sufficient evidence of whether this reflects reality (that is, the achievement of dividends representing a return on equity) as it is still very early. Therefore, this will remain a high-risk matter until we have seen sufficient evidence of reality to the forecasted figures.

There is negative net impact on the budget after 2024–25 and this will grow in the future

There are some key points to highlight with this modelling and these are best conveyed with the graph below. This graph shows total cash injections made by the GGS since the government first announced the creation of TAHE as a for-profit entity in the 2015–16 NSW Budget. It also conveys the forecast returns from TAHE to the GGS and the level of funding operators will need from the GGS to pay TAHE's access and licence fees over the 30-year period. These cash flows are key inputs used in the modelling which calculates a 2.5% return from TAHE inclusive of recovering the holding (revaluation) loss of $20.3 billion.

The government continues to respond to the impact of the COVID-19 pandemic on New South Wales through its economic stimulus measures

The COVID-19 pandemic continued to significantly impact the State’s finances, reducing revenue and increasing expenses especially in sectors directly responsible for responding to the COVID-19 pandemic, such as Health. In October 2021, the government announced through the 'COVID-19 Economic Recovery Strategy' an additional $2.8 billion in economic stimulus and response measures following the conclusion of the three-month lockdown due to the Delta COVID-19 outbreak. Measures included:

  • $739 million in household and social support, including housing support for Aboriginal communities and survivors of domestic violence, and vouchers to thank parents for their efforts to support learning from home
  • $500 million to consumers and businesses including expansion of the 'Dine & Discover' and 'Stay & Rediscover' voucher programs
  • $495 million in education support addressing learning gaps for children and helping schools prepare for future learning disruptions
  • $487 million in combined funding for tourism, events, sports, and recreation throughout New South Wales
  • $130 million to fund mental health services for individuals whose mental health was impacted by the pandemic.

The 2021–22 financial year included $21.9 billion for pandemic response and economic stimulus measures. Of this, $17.9 billion was spent in 2021–22 while a further $1 billion of the budgeted amount from 2021–22 was carried forward into 2022–23. The graph below shows the total allocation and spend by cluster for 2022 compared to target spend.

There were 14 natural disaster declarations including four severe weather events in 2021–22

Natural disasters such as bushfires, storms, floods, and other adverse weather events can have a significant impact on the State's finances. Costs associated with natural disasters include direct response costs such as clean-up and recovery, temporary accommodation, and as well as financial assistance provided to impacted communities such as recovery and business support grants.

The NSW Government can make a natural disaster declaration allowing eligible individuals and communities from impacted Local Government Areas access to a range of special financial assistance measures.

In 2021–22, there were 14 natural disaster declarations announced comparable to 14 in the previous year. These natural disaster declarations largely related to storms and floods throughout the State. In 2021–22, there was a larger number of 'severe weather' events declared, with four in 2021–22 (nil in 2020–21).

Natural disaster expenses increased 143% to $1.4 billion in 2021–22, up from $569 million last year

Over 2021–22, the budgeted cost for declared natural disasters was $1.9 billion ($725 million in 2020–21). Actual expenditure by the State on disaster response increased by $815 million to $1.4 billion. The graph below shows the total allocation and spend by cluster for 2022 compared to their budget spend.

Deficit of $15.3 billion compared with a budgeted deficit of $8.6 billion

The outcomes of the government’s overall activity and policies are reflected in its net operating balance (budget result). This is the difference between the cost of general government service delivery and the revenue earned to fund these sectors.

The General Government Sector, which comprises 196 entities, generally provides goods and services funded centrally by the State.

In addition to the 196 entities within the General Government Sector, a further 85 government controlled businesses are included within the consolidated Total State Sector financial statements. These businesses generally provide goods and services, such as water, electricity and financial services for which consumers pay for directly, and form part of the PNFC (31) and PFC (54) sectors.

The budget result for the 2021–22 financial year was a deficit of $15.3 billion compared to an original forecast of a budget deficit of $8.6 billion.

Revenues increased $16.1 billion to $106.7 billion

The State’s total revenues increased $16.1 billion to $106.7 billion, an increase of 17.8% compared to the previous year. Total revenue growth in 2020–21 was 5.1%. The State's increase in revenue was mostly from $9.2 billion in grants and subsidies and $4.6 billion in taxation.

Taxation revenue increased by 13.3%

Taxation revenue increased by $4.6 billion, mainly due to the net of:

  • $4.9 billion higher stamp duties collected from property sales driven by growth in property transaction volumes and prices during 2021–22. This was growth was experienced across residential and commercial property markets
  • $296 million lower gambling and betting taxes compared to 2020–21. Decrease was primarily attributed to the ongoing effects of COVID-19 restrictions and venue closures within the first half of 2021–22.

Stamp duties of $16.6 billion remains the largest source of taxation revenue, $7.7 billion higher than payroll tax of $8.9 billion, the second-largest source of taxation revenue.

Assets grew by $53 billion to $571 billion

The State’s assets include physical assets such as land, buildings and infrastructure, and financial assets such as cash, and other financial instruments and equity investments. The value of total assets increased by $53.2 billion or 10.3% to $571 billion. The increase was largely due to increases in the carrying value of land, buildings and infrastructure systems.

Valuing the State’s physical assets

State’s physical assets valued at $437 billion

The value of the State’s physical assets increased by $46.8 billion to $437 billion in 2021–22 ($724 million increase in 2020–21). The State’s physical assets include land and buildings ($198 billion), infrastructure systems ($221 billion), and plant and equipment ($18 billion).

The movement in physical asset values between years includes additions, disposals, depreciation and valuation adjustments. Other movements include assets reclassified to held for sale and other opening balance adjustments.

Appendix one – Prescribed entities

Appendix two – Legal opinions

Appendix three – TSS sectors and entities

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Coordination of the response to COVID-19 (June to November 2021)

Coordination of the response to COVID-19 (June to November 2021)

Premier and Cabinet
Community Services
Health
Justice
Whole of Government
Internal controls and governance
Risk
Service delivery
Shared services and collaboration

What the report is about

This audit assessed the effectiveness of NSW Government agencies’ coordination of the response to COVID-19, with a focus on the Delta variant outbreak in the Dubbo and Fairfield Local Government Areas (LGA) between June and November 2021. We audited five agencies - the Department of Premier and Cabinet, NSW Health, the NSW Police Force, Resilience NSW and the Department of Customer Service.

The audit also considered relevant planning and preparation activities that occurred prior to June 2021 to examine how emergency management and public health responses learned from previous events.

What we found

Prior to Delta, agencies developed capability to respond to COVID-19 related challenges.

However, lessons learned from prior reviews of emergency management arrangements, and from other jurisdictions, had not been implemented when Delta emerged in June 2021. As a result, agencies were not as fully prepared as they could have been to respond to the additional challenges presented by Delta.

Gaps in emergency management plans affected agencies' ability to support individuals, families and businesses impacted by restrictions to movement and gathering such as stay-at-home orders. In LGAs of concern, modest delays of a few days had a significant impact on people, especially those most vulnerable.

On 23 July 2021, the NSW Government established a cross-government coordinating approach, the Delta Microstrategy, which complemented existing emergency management arrangements, improved coordination between NSW Government agencies and led to more effective local responses.

Where possible, advice provided to government was supported by cross-government consultation, up-to-date evidence and insights. Public Health Orders were updated as the response to Delta intensified or to address unintended consequences of previous orders. The frequency of changes hampered agencies' ability to effectively communicate changes to frontline staff and the community in a rapidly evolving situation.

The NSW Government could provide greater transparency and accountability over decisions to apply Public Health Orders during a pandemic.

What we recommended

The audit made seven recommendations intended to improve transparency, accountability and preparedness for future emergency events.

This audit assessed the effectiveness of NSW Government agencies’ coordination (focused on the Department of Premier and Cabinet, NSW Health, the NSW Police Force, Resilience NSW and the Department of Customer Service) of the COVID-19 response in selected Local Government Areas (Fairfield City Council and Dubbo Regional Council) between June and November 2021.

As noted in this report, Resilience NSW was responsible for the coordination of welfare services as part of the emergency management arrangements. On 16 December 2022, the NSW Government abolished Resilience NSW.

During the audited period, Resilience NSW was tasked with supporting the needs of communities subject to stay-at-home orders or stricter restrictions and it provided secretariat support to the State Emergency Management Committee (SEMC). The SEMC was, and remains, responsible for the coordination and oversight of emergency management policy and preparedness.

Our work for this performance audit was completed on 15 November 2022, when we issued the final report to the five audited agencies. While the audit report does not make specific recommendations to Resilience NSW, it does include five recommendations to the State Emergency Management Committee. On 8 December 2022, the then Commissioner of Resilience NSW provided a response to the final report, which we include as it is the formal response from the audited entity at the time the audit was conducted.

The community of New South Wales has experienced significant emergency events during the past three years. COVID-19 first emerged in New South Wales after bushfire and flooding emergencies in 2019–20. The pandemic is now into its third year, and there have been further extreme weather and flooding events during 2021 and 2022.

Lessons taken from the experience of these events are important to informing future responses and reducing future risks to the community from emergencies.

This audit focuses on the NSW Government's response to the COVID-19 pandemic, and in particular, the Delta variant (Delta) that occurred between June and November 2021. The response to the Delta represents six months of heightened challenges for the NSW Government.

Government responses to emergencies are guided by legislation. The State Emergency and Rescue Management Act 1989 (SERM Act) establishes emergency management arrangements in New South Wales and covers:

  • coordination at state, regional and local levels through emergency management committees
  • emergency management plans, supporting plans and functional areas including the State Emergency Management Plan (EMPLAN)
  • operations centres and controllers at state, regional and local levels.

This audit focuses on the activities of five agencies during the audit period:

  • The NSW Police Force led the emergency management response and was responsible for coordinating agencies across government in providing the tactical and operational elements that supported and enhanced the health response to the pandemic. The NSW Police Force also led the compliance response which enforced Public Health Orders and included household checks on those required to isolate at home after testing positive to COVID-19. In some parts of NSW, they were supported by the Australian Defence Force in this role.
  • NSW Health was responsible for leading the health response which coordinated all parts of the health system, initially to prevent, and then to manage, the pandemic.
  • Resilience NSW coordinated welfare services as part of the emergency management arrangements and provided secretariat support to the State Emergency Management Committee (SEMC). The SEMC is responsible for the coordination and oversight of emergency management policy and preparedness. Resilience NSW was also tasked with supporting the needs of communities subject to stay-at-home orders or stricter restrictions.
  • The Department of Customer Service (DCS) was responsible for the statewide strategic communications response.
  • The Department of Premier and Cabinet (DPC) held a key role in providing policy and legal services, as well as supporting the coordination of activity across a range of functional areas and decision-making by our State’s leaders.

This audit assessed the effectiveness of NSW Government agencies’ coordination (focused on the Department of Premier and Cabinet, NSW Health, the NSW Police Force, Resilience NSW and the Department of Customer Service) of the COVID-19 response in selected Local Government Areas (LGA) (Fairfield City Council and Dubbo Regional Council) after June 2021.

The audit investigated whether:

  • government decisions to apply LGA-specific Public Health Orders were supported by effective crisis management governance and planning frameworks
  • agencies effectively coordinated in the communication (and enforcement) of Public Health Orders.

While focusing on the coordination of NSW Government agencies’ response to the Delta variant in June through to November 2021, the audit also considered relevant planning and preparation activities that occurred prior to June 2021 to examine how emergency management and public health responses learned from previous events.

This audit does not assess the effectiveness of other specific COVID-19 responses such as business support. It refers to the preparedness, planning and delivery of these activities in the context of supporting communities in selected LGAs. NSW Health's contribution to the Australian COVID-19 vaccine rollout was also subject to a separate audit titled 'New South Wales COVID-19 vaccine rollout' tabled in NSW Parliament on 7 December 2022. 

This audit is part of a series of audits which have been completed, or are in progress, regarding the New South Wales COVID-19 emergency response. The Audit Office of New South Wales '2022–2025 Annual Work Program' details the ongoing focus our audits will have on providing assurance on the effectiveness of emergency responses.

In this document Aboriginal refers to the First Nations peoples of the land and waters now called Australia, and includes Aboriginal and Torres Strait Islander peoples.

Conclusion

Prior to June 2021, agencies worked effectively together to adapt and refine pre-existing emergency management arrangements to respond to COVID-19. However, lessons learned from prior reviews of emergency management arrangements, and from other jurisdictions, had not been implemented when Delta emerged in June 2021. As a result, agencies were not as fully prepared as they could have been to respond to the additional challenges presented by Delta.

In the period March 2020 to June 2021, the State's Emergency Management (EM) arrangements coordinated the New South Wales emergency response to COVID-19 with support from the Department of Premier and Cabinet (DPC) which led the cross-government COVID-19 Taskforce. NSW Government agencies enhanced the EM arrangements, which until then had typically been activated in response to natural disasters, to meet the specific circumstances of the pandemic.

However, the State Emergency Management Committee (SEMC), supported by Resilience NSW, did not address relevant recommendations arising from the 2020 Bushfires Inquiry before June 2021 and agencies did not always integrate lessons learned from other jurisdictions or scenario training exercises into emergency management plans or strategies before Delta. As a result, deficiencies in the EM arrangements, including representation of vulnerable communities on EM bodies, well-being support for multicultural communities in locked down environments and cross-agency information sharing, persisted when Delta emerged in June 2021.

It should be noted that for the purposes of this audit there is no benchmark, informed by precedent, that articulates what level of preparation would have been sufficient or proportionate. However, the steps required to address these gaps were reasonable and achievable, and the failure to do so meant that agencies were not as fully prepared as they could have been for the scale and escalation of Delta’s spread across the State.

The Delta Microstrategy complemented the EM arrangements to support greater coordination and agencies are working to improve their capability for future events

The Delta Microstrategy (the Microstrategy) led to innovations in information sharing and collaboration across the public service. Agencies involved in the response have completed, or are completing, reviews of their contribution to the response. That said, none of these reviews includes a focus on whole-of-government coordination.

On 23 July 2021, the NSW Government approved the establishment of the Microstrategy to respond to the additional challenges presented by Delta including the need to support communities most impacted by restrictions to movement and gathering in the LGAs of concern. An extensive range of government agencies were represented across eight Microstrategy workstreams, which coordinated with the existing EM arrangements to deliver targeted strategies to communities in high-risk locations and improve data and information sharing across government. This enhanced the public health, compliance, income and food support, communications and community engagement aspects of the response.

Agencies also leveraged learnings from early weeks of the Delta wave and were able to replicate those lessons in other locations. The use of pre-staging hubs in Fairfield to support food and personal hamper distribution was used a month later in Dubbo which acted as a central hub for more remote parts of the State.

Emergency management plans did not enable government to respond immediately to support vulnerable communities in high-risk LGAs or regional NSW

There are gaps in the emergency management plans relating to the support for individuals, families and businesses impacted by the stay-at-home orders and other restrictions to movement and gathering. These gaps affected agencies' ability to respond immediately when the need arose during Delta.

Emergency management plans and supporting instruments did not include provision for immediate relief for households, which meant arrangements for isolation income support and food security measures had to be designed in the early stages of Delta before it could be approved and deployed.

There were delays – sometimes only days, on occasion, weeks - in providing support to affected communities. In particular, there were delays to the provision of income support and in scaling up efforts to coordinate food and grocery hampers to households in isolation. In LGAs of concern, modest delays of a few days had a significant impact on people, especially those most vulnerable.

Although government issued stricter restrictions for workers in the Fairfield LGA on 14 July 2021, it only approved targeted income support for people in LGAs of concern on 16 August 2021.

Overall, agencies coordinated effectively to provide advice to government but there are opportunities to learn lessons to improve preparedness for future events

Agencies coordinated in providing advice to government. The advice was supported by timely public health information, although this was in the context of a pandemic, where data and information about the virus and its variants was changing regularly. However, agencies did not always consider the impact on key industries or supply chains when they provided advice to government, which meant that Public Health Orders would sometimes need to be corrected.

Public Health Orders were also updated as the response to Delta intensified or to address unintended consequences of previous orders. The frequency of changes hampered agencies' ability to effectively communicate changes to frontline staff and the community in a rapidly evolving situation.

The audit identified several occasions where there were delays, ranging from three to 21 days, between the provision of advice to government and subsequent decision-making (which we have not detailed due to the confidentiality of Cabinet deliberations). Agency officers advised of instances where they were not provided sufficient notice of changes to Public Health Orders to organise local infrastructure (such as traffic support for testing clinics) to support compliance with new requirements.

The COVID-19 pandemic arrived in Australia in late January 2020 as the bushfire and localised flooding emergencies were in their final stages. Between 2020 and mid-2021, agencies responded to the initial variants of COVID-19, managed a border closure with Victoria that lasted nearly four months and dealt with localised ‘flare-ups’ that required postcode-based restrictions on mobility in northern parts of Sydney and regional New South Wales. During this period, New South Wales had the opportunity to learn from events in Victoria which imposed strict restrictions on mobility across the State and the growing emergence of the Delta variant (Delta) across the Asia Pacific.

This section of the report assesses how emergency management and public health responses adapted to these lessons and determined preparedness for, and responses to, widespread community transmission of Delta in New South Wales.

The previous chapter discusses how agencies had refined the existing emergency management arrangements to suit the needs of a pandemic and describes some gaps that were not addressed. This chapter explores the first month of Delta (mid-June to mid-July 2021). It explores the areas where agencies were prepared and responses in place for the outbreak. It also discusses the impact of the gaps that were not addressed in the period prior to Delta and other issues that emerged.

NSW Health provided advice on the removal of restrictions based on up-to-date advice

The NSW Government discussed the gradual process for removing restrictions using the Doherty Institute modelling provided to National Cabinet on 10 August 2021. NSW Health highlighted the importance of maintaining a level of public health and safety measure bundles to further suppress case numbers. This was based on additional modelling from the Doherty Institute.

The Department of Regional NSW led discussion and planning around reopening with a range of proposal through August and September 2021. The Department of Premier and Cabinet and NSW Health jointly developed a paper to provide options on the restrictions when the State reached a level of 70% double dose vaccinations.

The roadmap to reopening was originally published on 9 September 2021. However, by 11 October 2021, the restrictions were relaxed when the 70% double dose threshold was reached to allow:

  • up to ten fully vaccinated visitors to a home (increased from five)
  • up to 30 fully vaccinated people attending outdoor gatherings (increased from 20)
  • weddings and funerals limits increased to 100 people (from 50)
  • the reopening of indoor pools for training, exercise and learning purposes only.

On the same day, the NSW Government announced further relaxation of restrictions once the 80% double dose threshold was reached. These restrictions were further relaxed on 8 November 2021. This included the removal of capacity restrictions to the number of visitors to a private residence, indoor pools to reopen for all purposes and density limits of one person for every two square metres, dancing allowed in nightclubs and 100% capacity in major stadia.

The NSW Government allowed workers in regional areas who received one vaccination dose to return to their workplace from 11 October 2021.

The Premier extended the date of easing of restrictions for unvaccinated people aged over 16 from 1 December to 15 December 2021.

Many agencies have undertaken reviews of their response to the Delta outbreak but a whole-of-government review has yet to be conducted

Various agencies and entities associated with the response to the Delta outbreak conducted after-action review processes. These processes assessed the achievements delivered, lessons learned and opportunities for improvement. However, a whole-of-government level review has not been conducted. This limits the New South Wales public service's ability to improve how it coordinates responses in future emergencies.

The agencies/entities that conducted reviews included:

  • South West Metropolitan region, Western NSW region, Fairfield Local Emergency Management Committee (LEMC), Dubbo Local Emergency Operations Controller (LEOCON), which were collated centrally by the State Emergency Operations Centre (SEOC)
  • Aboriginal Affairs NSW assessed representation and relevance of the emergency management arrangements for Aboriginal communities following the 2019 bushfires
  • Resilience NSW developed case studies to capture improved practice with regard to food security and supply chains
  • a community support and empowerment-focused after-action review undertaken by the Pillar 5 workstream of the Microstrategy.

Key lessons collated from the after-action reviews include:

  • the impact of variation in capability across agencies on the management of key aspects of the response including welfare support and logistics
  • issues with boundary differences between NSW Police Force regions, local government areas (LGA and local health districts (LHD) caused issues in delivering and coordinating services in an emergency situation 
  • the need to improve relationships between state and local Government outside of acute emergency responses to improve service delivery 
  • issues arising from impediments to information sharing between agencies and jurisdictions, such as:
    • timeliness and accuracy of data used to direct compliance activities
    • the impact of insufficient advance notice on changes to Public Health Orders
    • timely access to data across public sector agencies and other jurisdictions to inform decision-making, analysis and communications
    • gaps in data around ethnicity, geolocation of recent positive cases and infection/vaccination rates in Aboriginal communities.
  • the lack of Aboriginal community representation on many LEMCs
  • compared with the response to COVID-19 in 2020, improved coordination of communications with Culturally and Linguistically Diverse (CALD) populations with a reduction in overlapping messages and over-communication
  • improved attendance from agency representatives in LEMCs, and regional emergency operations centres (REOC) to improve interagency communications, planning, capability development and community engagement issues
  • deficiencies in succession planning and fatigue management practices
  • the potential for REOC Welfare/Well-being subgroups to be included as part of the wider efforts to community needs during emergencies.

NSW Health commenced a whole of system review of its COVID-19 response in May 2022. At the time of writing, the completion due date for the debrief is 7 November 2022. This debrief is expected to explore:

  • governance
  • engagement 
  • innovation and technology 
  • community impact 
  • workforce impact
  • system impact and performance.

NSW Health is also undertaking a parallel Intra-Action Review that is focused on the public health aspects of the response with finalisation estimated for the end of November 2022. At the time of completing this performance audit report, NSW Health had not finalised these reviews and, as a result, we cannot validate their findings against our own observations.

Recent inquiries are likely to impact the governance of emergency management in New South Wales

In March 2022, the NSW Government established an independent inquiry to examine and report on the causes of, preparedness for, response to and recovery from the 2022 floods. The Flood Inquiry report made 28 recommendations, which the NSW Government supported in full or in principle. Some of the recommendations relate directly to the governance and leadership of emergency management arrangements in New South Wales. 

The State Emergency Management Committee (SEMC) will likely be involved in, and impacted by, the recommendations arising from the Flood Inquiry with potential changes to its membership and reshaping of functional areas and agencies. At the same time, the SEMC may have a role in overseeing the changes that emerge from the SEOC consolidated after-action reviews. This can also extend to ensuring local and regional bodies have incorporated the required actions. There is a risk that the recommendations from the pandemic-based after-action reviews may not be considered due to the priority of action resulting from the Flood Inquiry.

Furthermore, there is potential for the SEMC to work with NSW Health during its system-wide review. Such an approach is likely to improve preparedness for future events.

Appendix one – Response from agencies

Appendix two – Chronology 2020–2021

Appendix three – About the audit

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #371 - released 20 December 2022

Published

Actions for Enterprise, Investment and Trade 2022

Enterprise, Investment and Trade 2022

Finance
Asset valuation
Compliance
Cyber security
Financial reporting
Information technology
Internal controls and governance
Management and administration
Procurement
Regulation
Risk

What the report is about

Result of the Enterprise, Investment and Trade cluster agencies' financial statement audits for the year ended 30 June 2022.

What we found

The Machinery of Government changes within the Enterprise, Investment and Trade cluster resulted in the creation of the Department of Enterprise, Investment and Trade and the transfer of $1.0 billion of net assets into the new department.

Unmodified audit opinions were issued for all completed cluster agencies' 2021–22 financial statements audits. Two audits are ongoing.

An 'Other Matter' paragraph was included in the audit opinion for the Jobs for NSW Fund's 30 June 2021 financial report to reflect the non-compliance with the Jobs for NSW Act 2015 (the Act) and Government Sector Finance Act 2018. The Act requires the board to consist of seven members that include the Secretary of the Treasury, the Secretary of the Department of Premier and Cabinet, and five ministerial appointments. The board has consisted of two secretaries since 24 May 2019 when the independent members resigned. The remaining five members have not been appointed by the ministers as required by section 5(2) of the Act.

Three cluster agencies accepted changes to their office leasing arrangements managed by Property NSW. This has resulted in the collective derecognition of $24.8 million of right-of-use assets and $26.7 million in lease liabilities, and recognition of $1.9 million of other gains.

What the key issues were

The number of issues we reported to management decreased from 108 in 2020–21 to 103 in 2021–22. Thirty per cent of issues were repeated from the prior year.

Six high-risk issues were identified across the cluster related to the quality and timeliness of financial reporting, governance processes and internal controls.

Recommendations were made to address these deficiencies.

This report provides Parliament and other users of the Enterprise, Investment and Trade cluster's financial statements with the results of our audits, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision-making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Enterprise, Investment and Trade cluster (the cluster) for 2022.

Section highlights

  • Unqualified audit opinions were issued for all completed cluster agencies 2021–22 financial statements audits. The Jobs for NSW Fund and Responsible Gambling Fund audits are ongoing.
  • An 'Emphasis of Matter' paragraph was included in the Australian Institute of Asian Culture and Visual Arts Limited's 30 June 2022 financial statements to draw attention to management’s disclosures that the entity's financial statements for the year ended 30 June 2022 were prepared on a non-going concern basis following cessation of its operations and resolution by the directors in October 2021 to deregister the entity.
  • An 'Other Matter' paragraph was included in the Jobs for NSW Fund's 30 June 2021 financial report to reflect the non-compliance with the Jobs for NSW Act 2015 and Government Sector Finance Act 2018.
    The Act requires the board to consist of seven members that include the Secretary of the Treasury, the Secretary of the Department of Premier and Cabinet (or their nominees) and five ministerial appointments, one of whom is to be appointed as Chair of the board. The board has consisted of the two secretaries since 24 May 2019 when the independent members resigned. The remaining five members have not been appointed by the ministers as required by section 5(2) of the Act.
  • An 'Emphasis of Matter' paragraph was included in the Jobs for NSW Fund's 30 June 2021 financial report to draw attention to the financial report being prepared for the purpose of fulfilling the Jobs for NSW Fund's financial reporting responsibilities as requested by the Treasurer's delegate.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision-making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the Enterprise, Investment and Trade cluster.

Section highlights

  • In 2021–22, there were 103 findings raised across the cluster, a decrease from 2020–21.
  • In total, six high-risk findings were identified during 2021–22. Two related to 2021–22 whilst four were related to the audit of Jobs for NSW Fund's 30 June 2021 financial report.
  • Thirty per cent of all findings during 2021–22 were repeat issues. The most common repeat issues related to information technology controls and accounting for property plant and equipment notably fair value assessment and valuation.

Appendix one – Misstatements in financial statements submitted for audit 

Appendix two – Early close procedures 

Appendix three – Timeliness of financial reporting 

Appendix four – Financial data 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Planning and Environment 2022

Planning and Environment 2022

Environment
Industry
Local Government
Planning
Asset valuation
Compliance
Financial reporting
Information technology
Infrastructure
Internal controls and governance
Management and administration
Risk

What the report is about

Result of the Planning and Environment cluster agencies' financial statements audits for the year ended 30 June 2022.

What we found

Unmodified audit opinions were issued for all completed 30 June 2022 financial statements audits of cluster agencies. Seven audits are ongoing.

Disclaimed audit opinions were issued for the 2010–11 to 2015–16 financial statements of the Water Administration Ministerial Corporation (WAMC), as management was unable to certify that the financial statements exhibit a true and fair view of WAMC's financial position and financial performance.

Qualified audit opinions were issued for WAMC's 2016–17 and 2017–18 financial statements due to insufficient evidence to support the completeness and valuation of water meters infrastructure assets, the impairment of water meters, and the completeness of buildings at Nimmie Caira.

Unqualified audit opinions were issued for WAMC's 2018–19 and 2019–20 financial statements.

The Department of Planning and Environment (the department) assessed 45 Category 2 Statutory Land Managers (SLM) did not meet the reporting exemption criteria and therefore were required to prepare 2021–22 financial statements. None of these 45 Category 2 SLMs prepared and submitted their 30 June 2022 financial statements by the statutory reporting deadline.

All 119 Commons Trusts have never submitted their financial statements for audit as required by the Government Sector Finance Act 2018 (GSF Act).

NSW Treasury has confirmed that the Catholic Metropolitan Cemeteries Trust (CMCT) is a controlled entity of the State. To date, CMCT has not met its obligations to prepare financial statements under the GSF Act and it has not submitted financial statements to the Auditor-General for audit.

What the key issues were

Since 2017, the Audit Office has recommended the department address the different practices across the local government sector in accounting for rural firefighting equipment. Despite repeated recommendations, the department did little to resolve this issue. At the time of writing, 32 of 118 completed council audits received qualified audit opinions on their 30 June 2022 financial statements.

There continues to be significant deficiencies in Crown land records. The department uses the Crown Land Information Database (CLID) to record key information relating to Crown land in New South Wales that is managed and controlled by the department and land managers. The CLID system was not designed to facilitate financial reporting, and the department is required to conduct extensive adjustments and reconciliations to produce accurate information for the financial statements.

The department implemented the CrownTracker system as a replacement for CLID. The project was finalised in June 2022, but it has not achieved the intended outcomes.

Nine high-risk issues were identified across the cluster related to the findings outlined above and weaknesses in IT general controls, financial reporting, governance processes and internal controls.

Recommendations were made to address these deficiencies.

This report provides Parliament and other users of the Planning and Environment cluster’s financial statements with the results of our audits, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision-making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Planning and Environment cluster (the cluster) for 2022.

Section highlights

  • Unqualified audit opinions were issued for all completed 30 June 2022 financial statements audits of cluster agencies. Seven audits are ongoing. The audit of the Catholic Metropolitan Cemeteries Trust(CMCT) has not been able to commence, despite repeated requests to do so.
     
  • The audits of the Water Administration Ministerial Corporation's (WAMC) financial statements for the years ended 30 June 2011 to 30 June 2020 were completed in November 2022. These audits had been long outstanding due to insufficient records and evidence to support the transactions and balances of WAMC, particularly for the earlier years. In recent years, management commenced actions to improve WAMC's governance and financial management, and finalise the outstanding audits.

    Disclaimed audit opinions were issued on the 2010–11 to 2015–16 financial statements as management was unable to certify that the financial statements exhibit a true and fair view of WAMC's financial position and financial performance.

    Qualified audit opinions were issued for the 2016–17 and 2017–18 financial statements due to insufficient evidence to support the completeness and valuation of water meters infrastructure assets, the impairment of water meters, and the completeness of buildings at Nimmie Caira.

    Unqualified audit opinions were issued for the 2018–19 and 2019–20 financial statements.

    The 2020–21 and 2021–22 WAMC audits are in progress.
     
  • The Department of Planning and Environment (the department) assessed 45 Category 2 Statutory Land Managers (SLM) did not meet the reporting exemption criteria and therefore were required to prepare 2021–22 financial statements. None of these 45 Category 2 SLMs prepared and submitted their 30 June 2022 financial statements by the statutory reporting deadline.

    All 119 Commons Trusts have never submitted their financial statements for audit as required by the Government Sector Finance Act 2018 (GSF Act).

    The department needs to do more to ensure Category 2 SLMs and Commons Trusts meet their statutory reporting obligations.

    The department and Category 2 SLMs should finalise their reporting exemption assessments earlier to allow sufficient time for the non-exempted SLMs to prepare and submit annual financial statements by the statutory reporting deadline.
     
  • NSW Treasury has met with the Catholic Metropolitan Cemeteries Trust (CMCT) to consider their perspective as part of confirming CMCT is a controlled entity of the State for the purposes of financial reporting. NSW Treasury has confirmed that the CMCT is a controlled entity of the State. This means that the CMCT is statutorily obliged under section 7.6 of the GSF Act to prepare financial statements in accordance with the GSF Act and Treasurer's Directions, and give them to the Auditor-General for audit pursuant to the Government Sector Audit Act 1983 (GSA Act). Section 34 of the GSA Act requires the Auditor-General to furnish an audit report on these financial statements.

    The department wrote to CMCT to request it work with, and offer full assistance to, the Auditor-General in the exercise of her duties. To date, the CMCT has not met its obligations to prepare financial statements under the GSF Act as it has not submitted its financial statements to the Auditor-General for audit despite repeated requests, and has not provided access to its books and records for the purposes of a financial audit. The CMCT contends that they are not a GSF agency as defined by the GSF Act and therefore not a controlled entity of the State.
     
  • Six agencies required to perform early close procedures did not complete a total of 11 mandatory procedures. Incomplete procedures included the delayed resolution of matters raised in prior years and two agencies did not record movements in the fair value of physical assets in the financial statements.

 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision-making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the Planning and Environment cluster.

Section highlights

  • Since 2017, the Audit Office of New South Wales has recommended that the Department of Planning and Environment (the department) address the different practices across the local government sector in accounting for rural firefighting equipment. Despite repeated recommendations, the department did little to resolve this issue, and in 2022, 32 of 118 completed audits of councils received qualified audit opinions on their 2022 financial statements.
    Consistent with the department’s role to assess councils' compliance with legislative responsibilities, standards or guidelines, the department should intervene where councils do not recognise rural firefighting equipment.
  • There continues to be significant deficiencies in Crown land records. The department should implement an action plan to ensure the Crown land database is complete and accurate.
  • The number of findings reported to management decreased from 161 in 2020–21 to 132 in 2021–22. Eight high-risk findings were identified during 2021–22, of which six were repeat issues. One new high-risk finding related to deficiencies in governance processes and internal controls identified as a part of the Water Administration Ministerial Corporation's 2011–2020 financial statements audits.
  • The department and NSW Treasury did not comply with section 35 of the Energy and Utilities Administration Act 1987 (EUA Act). However, complying with the EUA Act could create non-compliance with other pieces of legislation. Amendments to the EUA Act have been made to resolve this inconsistency. The amendment took effect from April 1999.

 

Appendix one – Misstatements in financial statements submitted for audit

Appendix two – Early close procedures

Appendix three – Timeliness of financial reporting

Appendix four – Financial data

Appendix five – Councils received qualified audit opinions 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Stronger Communities 2022

Stronger Communities 2022

Justice
Community Services
Asset valuation
Compliance
Cyber security
Financial reporting
Information technology
Internal controls and governance
Management and administration
Procurement
Project management
Risk

What the report is about

Results of the Stronger Communities cluster agencies' financial statement audits for the year ended 30 June 2022.

What we found

Unqualified audit opinions were issued on all completed 30 June 2022 financial statement audits. One audit is ongoing.

All 13 cluster agencies that have accommodation arrangements with Property NSW derecognised right-of-use assets and lease liabilities of $917 million and $1 billion respectively. The agencies also collectively recorded a gain on derecognition of $136 million.

The Department of Communities and Justice (the department) assumed the responsibility for delivery of the Process and Technology Harmonisation program from the Department of Customer Service. In 2021–22, the department incurred costs of $42.8 million in relation to the project, which remains ongoing.

The number of monetary misstatements identified during the audits decreased from 50 in 2020–21 to 48 in 2021–22.

What the key issues were

Six of the 15 cluster agencies required to submit 2021–22 mandatory early close procedures did not meet the statutory deadlines. One agency did not complete all mandatory procedures.

Five high-risk findings were identified in 2021–22. They related to deficiencies in:

  • user access administration at the department, NSW Rural Fire Service and New South Wales Aboriginal Land Council (NSWALC)
  • segregation of duties at the NSW Trustee and Guardian and NSWALC.

Recommendations were made to those agencies to address these control deficiencies.

This report provides Parliament and other users of the Stronger Communities cluster’s financial statements with the results of our audits, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Stronger Communities cluster (the cluster) for 2022.

Section highlights

  • Unqualified audit opinions were issued on all completed 30 June 2022 financial statement audits of cluster agencies, including the acquittal and compliance audits for the Legal Aid Commission of New South Wales and Crown Solicitor's Office. One audit is ongoing.

  • Reported corrected misstatements decreased from 30 in 2020–21 to 23 with a gross value of $187 million in 2021–22 ($101 million in 2020–21). Reported uncorrected misstatements increased from 20 in 2020–21 to 25 with a gross value of $92.3 million in 2021–22 ($107 million in 2020–21).

  • Six of the 15 cluster agencies required to submit 2021–22 early close financial statements and all other mandatory procedures did not meet the statutory deadlines. One agency did not complete all mandatory procedures.

  • All 13 cluster agencies that have accommodation arrangements with Property NSW accepted the changes in the Client Acceptance Letters, resulting in the derecognition of right-of-use assets and lease liabilities of $917 million and $1 billion respectively. The agencies also collectively recorded a gain on derecognition of $136 million.

  • The Department of Communities and Justice (the department) assumed the responsibility to deliver the Process and Technology Harmonisation program from the Department of Customer Service. In 2021–22, the department incurred costs of $42.8 million in relation to the project.

  • In 2021–22, the department continued to implement the International Financial Reporting Standards Interpretations Committee's agenda decision on 'Configuration or customisation costs in a cloud computing arrangement'. The department's review of the remaining arrangements, with a net book value of $233 million at 30 June 2021, resulted in the recognition as an expense (through accumulated funds at 1 July 2020) of previously capitalised intangible assets totalling $106 million.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the Stronger Communities cluster.

Section highlights

  • The number of issues reported to management has decreased from 130 in 2020–21, to 110 in 2021–22, and 43% were repeat issues (51% in 2020–21). Many repeat issues related to information technology, governance and oversight controls, and non-compliance with key legislation and/or agency policies.

  • Five high-risk issues were identified in 2021–22, all of which are repeat issues and related to user access administration and segregation of duties.

  • Of the 24 newly identified moderate risk issues, 11 related to information technology. The rest related to governance and oversight controls and internal control deficiencies or improvements in payroll, asset management and other processes.

Appendix one – Misstatements in financial statements submitted for audit

Appendix two – Early close procedures

Appendix three – Timeliness of financial reporting

Appendix four – Financial data

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Regional NSW 2022

Regional NSW 2022

Environment
Industry
Planning
Asset valuation
Compliance
Financial reporting
Fraud
Information technology
Infrastructure
Internal controls and governance
Management and administration
Regulation
Risk
Shared services and collaboration

What the report is about

Result of the Regional NSW cluster agencies' financial statement audits for the year ended 30 June 2022.

What we found

Unmodified audit opinions were issued for Regional NSW cluster agencies. Two audits are ongoing.

What the key issues were

The Department of Regional NSW (the department) and Local Land Services (LLS) accepted changes to their office leasing arrangements managed by Property NSW.

These changes resulted in the collective derecognition of $100.6 million of rights-of-use-assets and $110.4 million of lease liabilities.

In 2021–22, the cluster agencies continued to assist communities in their recovery from recent weather emergencies, including significant flooding in New South Wales.

The Northern Rivers Reconstruction Corporation was established in May 2022 to rebuild communities in the Lismore and Northern Rivers region impacted by floods.

The number of matters reported to management decreased from 36 in 2020–21 to 14 in 2021–22.

Five moderate risk issues were identified and 14% of reported issues were repeat issues.

One moderate risk issue was a repeat issue related to Local Land Services' annual fair value assessment of the asset improvements on land reserves used for moving stock.

This report provides Parliament and other users of the Regional NSW cluster financial statements with the results of our audits, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision-making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Regional NSW cluster (the cluster) for 2022.

Section highlights

  • Unqualified audit opinions were issued on the financial statements of cluster agencies. Two audits are ongoing.
  • Cluster agencies completed all required early close procedures.
  • Changes to accommodation arrangements managed by Property NSW on behalf of the department and cluster agencies resulted in the collective derecognition of approximately $100.6 million in right-of-use assets and corresponding lease liabilities totalling $110.4 million from the balance sheets of these agencies.
  • Cluster agencies continue to provide financial assistance to communities affected by natural disasters.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision-making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the Regional NSW cluster.

Section highlights

  • The 2021–22 audits identified five moderate issues across the cluster. One moderate risk issue was a repeat issue related to Local Land Services' annual fair value assessment of the asset improvements on land reserves used for moving stock.
  • Of the four newly identified moderate rated issues, one related to internal control deficiencies and improvements and three related to financial reporting.
  • The number of findings reported to management has decreased from 36 in 2020–21 to 14 in 2021–22.

Published

Actions for Customer Service 2022

Customer Service 2022

Finance
Asset valuation
Compliance
Cyber security
Financial reporting
Information technology
Internal controls and governance
Management and administration
Procurement
Regulation
Risk
Service delivery
Shared services and collaboration

What the report is about

Result of the Customer Service cluster agencies' financial statement audits for the year ended 30 June 2022.

What we found

Unmodified audit opinions were issued for Customer Service cluster agencies.

What the key issues were

The number and size of Service NSW's administered grant programs have increased significantly in response to emergency events. Improvements are required to address gaps in Service NSW's policies, systems and processes in administering and financial reporting of grant programs.

The Department of Customer Service (the department) reported a retrospective correction of a prior period error of $33.3 million understatement of the land titling database, which is a service concession asset managed by a private operator.

The 2021–22 audits identified five high-risk issues across the cluster:

  • the department:
    • control weaknesses in user access to GovConnect systems
    • significant control deficiencies in information technology change management controls
  • Rental Bond Board:
    • legislation amendment required to better support the accounting treatment of rental bonds
    • no delegation instrument to government officers authorising them to approve expenditures
  • Service NSW:
    • improvements required in the timeliness and quality of grant administration revenue assessment and controls over the recovery of grant administration costs.

Recommendations were made to address these deficiencies.

This report provides Parliament and other users of the Customer Service cluster's financial statements with the results of our audits, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision-making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Customer Service cluster (the cluster) for 2022.

Section highlights

  • Unqualified audit opinions were issued on the financial statements of cluster agencies.
  • Reported corrected misstatements decreased from 33 in 2020–21 to 30 with a gross value of $406 million in 2021–22 ($418.9 million in 2020–21). Reported uncorrected misstatements decreased from 13 in 2020–21 to nine with a gross value of $31.8 million in 2021–22 ($78 million).
  • Seven of nine cluster agencies did not submit or complete certain mandatory early close procedures on time.
  • Service NSW's late resolution of the accounting of $256 million revenue from administering COVID-19 and flood grant programs resulted in misstatements and delays in financial reporting and audit.
  • The Department of Customer Service corrected prior period errors retrospectively related to the valuation of a service concession asset (land titling database) which reduced the prior year comparative for service concession asset by $33.3 million in the financial statements.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision-making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the Customer Service cluster.

Section highlights

  • The 2021–22 audits identified five high risks (three in 2020–21) and 36 moderate risk issues (59 in 2020–21) across the cluster. Fifty-three per cent of the issues (42% in 2020–21) were repeat issues. Many repeat issues related to information technology controls around user access management.
  • While improvement was noted in the number of control deficiencies in GovConnect ASAE 3402 controls assurance reports, internal control qualification and control deviation issues continued to occur in 2021–22. Ineffective controls at service providers increase the risk of fraud, error and security to data.
  • Cyber security governance and management requires improvement. The department is yet to fully implement Essential 8 Mitigation Strategies and the maturity level for several Essential 8 strategies is at Level Zero in the current maturity model. The department is in the process of completing the roll out of some long outstanding system patches.
  • Significant gaps were identified in Service NSW's policies, systems and processes in administering and financial reporting of grant programs.

Appendix one – Misstatements in financial statements submitted for audit 

Appendix two – Early close procedures 

Appendix three – Timeliness of financial reporting 

Appendix four – Financial data

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Audit Insights 2018-2022

Audit Insights 2018-2022

Community Services
Education
Environment
Finance
Health
Industry
Justice
Local Government
Premier and Cabinet
Planning
Transport
Treasury
Universities
Whole of Government
Asset valuation
Cross-agency collaboration
Compliance
Cyber security
Financial reporting
Fraud
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Regulation
Risk
Service delivery
Shared services and collaboration
Workforce and capability

What the report is about

In this report, we have analysed the key findings and recommendations from our audit reports over the past four years.

This analysis includes financial audits, performance audits, and compliance audits of state and local government entities that were tabled in NSW Parliament between July 2018 and February 2022.

The report is framed by recognition that the past four years have seen significant challenges and emergency events.

The scale of government responses to these events has been wide-ranging, involving emergency response coordination, service delivery, governance and policy.

The report is a resource to support public sector agencies and local government to improve future programs and activities.

What we found

Our analysis of findings and recommendations is structured around six key themes:

  • Integrity and transparency
  • Performance and monitoring
  • Governance and oversight
  • Cyber security and data
  • System planning for disruption
  • Resource management.

The report draws from this analysis to present recommendations for elements of good practice that government agencies should consider in relation to these themes. It also includes relevant examples from recent audit reports.

In this report we particularly call out threats to the integrity of government systems, processes and governance arrangements.

The report highlights the need for balanced advice to government on options and risks, for transparent documentation and reporting of directions and decisions, and for early and open sharing of information with integrity bodies and audit.

A number of the matters highlighted in this report are similar to those described in our previous Insights Report, (Performance Audit Insights: key findings from 2014–2018) specifically in relation to cyber and information security, to performance measurement, reporting and evaluation, and system and workforce planning and capability.

Fast facts

  • 72 audits included in the Audit Insights 2018–2022 analysis
  • 4 years of audits tabled by the Auditor-General for New South Wales
  • 6 key themes for Audit Insights 2018–2022.

picture of Margaret Crawford Auditor-General for New South Wales in black dress with city skyline as backgroundI am pleased to present the Audit Insights 2018–2022 report. This report describes key findings, trends and lessons learned from the last four years of audit. It seeks to inform the New South Wales Parliament of key risks identified and to provide insights and suggestions to the agencies we audit to improve performance across the public sector.

The report is framed by a very clear recognition that governments have been responding to significant events, in number, character and scale, over recent years. Further, it acknowledges that public servants at both state and council levels generally bring their best selves to work and diligently strive to deliver great outcomes for citizens and communities. The role of audit in this context is to provide necessary assurance over government spending, programs and services, and make suggestions for continuous improvement.

A number of the matters highlighted in this report are similar to those described in our previous Insights Report, (Performance Audit Insights: key findings from 2014–2018) specifically in relation to cyber and information security, to performance measurement, reporting and evaluation, and system and workforce planning and capability.

However, in this report we particularly call out threats to the integrity of government systems, processes and governance arrangements. We highlight the need for balanced advice to government on options and risks, for transparent documentation and reporting of directions and decisions, and for early and open sharing of information with integrity bodies and audit. Arguably, these considerations are never more important than in an increasingly complex environment and in the face of significant emergency events and they will be key areas of focus in our future audit program.

While we have acknowledged the challenges of the last few years have required rapid responses to address the short-term impacts of emergency events, there is much to be learned to improve future programs. I trust that the insights developed in this report provide a helpful resource to public sector agencies and local government across New South Wales. I would be pleased to receive any feedback you may wish to offer.

Margaret Crawford
Auditor-General for New South Wales

Integrity and transparency Performance and monitoring Governance and oversight Cyber security and data System planning Resource management
Insufficient documentation of decisions reduces the ability to identify, or rule out, misconduct or corruption. Failure to apply lessons learned risks mistakes being repeated and undermines future decisions on the use of public funds. The control environment should be risk-based and keep pace with changes in the quantum and diversity of agency work. Building effective cyber resilience requires leadership and committed executive management, along with dedicated resourcing to build improvements in cyber security and culture. Priorities to meet forecast demand should incorporate regular assessment of need and any emerging risks or trends. Absence of an overarching strategy to guide decision-making results in project-by-project decisions lacking coordination. Governments must weigh up the cost of reliance on consultants at the expense of internal capability, and actively manage contracts and conflicts of interest.
Government entities should report to the public at both system and project level for transparency and accountability. Government activities benefit from a clear statement of objectives and associated performance measures to support systematic monitoring and reporting on outcomes and impact. Management of risk should include mechanisms to escalate risks, and action plans to mitigate risks with effective controls. In implementing strategies to mitigate cyber risk, agencies must set target cyber maturity levels, and document their acceptance of cyber risks consistent with their risk appetite. Service planning should establish future service offerings and service levels relative to current capacity, address risks to avoid or mitigate disruption of business and service delivery, and coordinate across other relevant plans and stakeholders. Negotiations on outsourced services and major transactions must maintain focus on integrity and seeking value for public funds.
Entities must provide balanced advice to decision-makers on the benefits and risks of investments. Benefits realisation should identify responsibility for benefits management, set baselines and targets for benefits, review during delivery, and evaluate costs and benefits post-delivery. Active review of policies and procedures in line with current business activities supports more effective risk management. Governments hold repositories of valuable data and data capabilities that should be leveraged and shared across government and non-government entities to improve strategic planning and forecasting. Formal structures and systems to facilitate coordination between agencies is critical to more efficient allocation of resources and to facilitate a timely response to unexpected events. Transformation programs can be improved by resourcing a program management office.
Clear guidelines and transparency of decisions are critical in distributing grant funding. Quality assurance should underpin key inputs that support performance monitoring and accounting judgements. Governance arrangements can enable input into key decisions from both government and non-government partners, and those with direct experience of complex issues.     Workforce planning should consider service continuity and ensure that specialist and targeted roles can be resourced and allocated to meet community need.
Governments must ensure timely and complete provision of information to support governance, integrity and audit processes.          
Read more Read more Read more Read more Read more Read more

 

This report brings together a summary of key findings arising from NSW Audit Office reports tabled in the New South Wales Parliament between July 2018 and February 2022. This includes analysis of financial audits, performance audits, and compliance audits tabled over this period.

  • Financial audits provide an independent opinion on the financial statements of NSW Government entities, universities and councils and identify whether they comply with accounting standards, relevant laws, regulations, and government directions.
  • Performance audits determine whether government entities carry out their activities effectively, are doing so economically and efficiently, and in accordance with relevant laws. The activities examined by a performance audit may include a selected program or service, all or part of an entity, or more than one government entity. Performance audits can consider issues which affect the whole state and/or the local government sectors.
  • Compliance audits and other assurance reviews are audits that assess whether specific legislation, directions, and regulations have been adhered to.

This report follows our earlier edition titled 'Performance Audit Insights: key findings from 2014–2018'. That report sought to highlight issues and themes emerging from performance audit findings, and to share lessons common across government. In this report, we have analysed the key findings and recommendations from our reports over the past four years. The full list of reports is included in Appendix 1. The analysis included findings and recommendations from 58 performance audits, as well as selected financial and compliance reports tabled between July 2018 and February 2022. The number of recommendations and key findings made across different areas of activity and the top issues are summarised at Exhibit 1.

The past four years have seen unprecedented challenges and several emergency events, and the scale of government responses to these events has been wide-ranging involving emergency response coordination, service delivery, governance and policy. While these emergencies are having a significant impact today, they are also likely to continue to have an impact into the future. There is much to learn from the response to those events that will help the government sector to prepare for and respond to future disruption. The following chapters bring together our recommendations for core elements of good practice across a number of areas of government activity, along with relevant examples from recent audit reports.

This 'Audit Insights 2018–2022' report does not make comparative analysis of trends in public sector performance since our 2018 Insights report, but instead highlights areas where government continues to face challenges, as well as new issues that our audits have identified since our 2018 report. We will continue to use the findings of our Insights analysis to shape our future audit priorities, in line with our purpose to help Parliament hold government accountable for its use of public resources in New South Wales.

Appendix one – Included reports, 2018–2022

Appendix two – About this report

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Local Government 2021

Local Government 2021

Local Government
Asset valuation
Cyber security
Financial reporting
Information technology

What the report is about

Results of the local government sector council financial statement audits for the year ended 30 June 2021.

What we found

Unqualified audit opinions were issued for 126 councils, 13 joint organisation audits and nine county councils in 2020–21. 

A qualified audit opinion was issued for Central Coast Council who was unable to provide evidence to support the carrying value of $5.5 billion of roads, bridges, footpaths, bulk earthworks, stormwater drainage, water supply and sewerage network assets.

The audit of Kiama Municipal Council is still in progress as at the date of this report due to significant accounting issues not resolved resulting in corrections to the financial statements and prior period errors.

Forty-one councils and joint organisations (2020: 16) received extensions to submit audited financial statements to the Office of Local Government (OLG). 

Councils were impacted by recent emergency events, including bushfires, floods and the COVID-19 pandemic. The financial implications from these events varied across councils. Councils adapted systems, processes and controls to enable staff to work flexibly.

What the key issues were

There were 1,277 audit findings reported to councils in audit management letters.

Ninety-two high-risk matters were identified across the sector:

  • 69 high-risk matters relating to asset management (see page 30)
  • six high-risk matters relating to information technology (see page 39)
  • six high-risk matters relating to financial reporting (see page 26)
  • six high-risk matters to council governance procedures (see page 22)
  • five high-risk matters relating to financial accounting (see page 28).

More needs to be done to reduce the number of errors identified in financial reports. Twenty-nine councils required material adjustments to correct errors in previous audited financial statements.

Rural firefighting equipment

Sixty-eight councils did not record rural firefighting equipment estimated to be $145 million in their financial statements.

The financial statements of the NSW Total State Sector and the NSW Rural Fire Service do not include these assets, as the State is of the view that rural firefighting equipment that has been vested to councils under the Rural Fires Act 1997 is not controlled by the State. In reaching this conclusion, the State argued that on balance it would appear the councils control rural firefighting equipment that has been vested to them.

The continued non-recording of rural firefighting equipment in financial management systems of some councils increases the risk that these assets are not properly maintained and managed.

What we recommended

Councils should perform a full asset stocktake of rural firefighting equipment, including a condition assessment for 30 June 2022 financial reporting purposes and recognise this equipment as assets in their financial statements. 

Consistent with OLG’s role to assess council’s compliance with legislative responsibilities, standards or guidelines, OLG should intervene where councils do not recognise rural firefighting equipment.

Fast facts

  • 150 councils and joint organisations in the sector
  • 99% unqualified audit opinions issued for the 30 June 2021 financial statements
  • 489 monetary misstatements reported in 2020–21
  • 54 prior period errors reported
  • 92 high-risk management letter findings identified
  • 53% of reported issues were repeat issues.

Early financial reporting procedures

Fifty-nine per cent of councils performed some early financial reporting procedures, less than the prior year.

What we recommended

OLG should require early financial reporting procedures across the local government sector by April 2023. Policy requirements should be discussed with key stakeholders to ensure benefits of the procedures are realised.

Asset valuations

Audit management letters reported 288 findings relating to asset management. Fifty-eight councils had deficiencies in their processes to revalue infrastructure assets.

Thirty-five councils corrected errors relating to revaluations amounting to $1 billion and 13 councils had prior period errors relating to asset revaluations that amounted to $253 million.

What we recommended

Councils should have all asset revaluations completed by April of the financial year subject to audit.

Integrity/completeness of asset records

Sixty-seven councils had weak processes over maintenance, completeness and security of fixed asset registers.

Thirty-five councils corrected errors to the financial statements relating to poor record keeping of asset data that amounted to $102.1 million. Nineteen councils had 27 prior period financial statement errors that amounted to $417.1 million relating to the quality of asset records such as found and duplicate assets.

What we recommended

Councils need to improve controls and processes to ensure integrity and completeness of asset source records.

Cybersecurity

Our audits found that cybersecurity frameworks and related controls were not in place at 65 councils.

These councils have yet to implement basic governance and internal controls to manage cybersecurity such as having a cybersecurity framework, policy and procedure, register of cyber incidents, system penetrations testing and training.

What we recommended

OLG needs to develop a cybersecurity policy to be applied by councils as a matter of high priority in order to ensure cybersecurity risks over key data and IT assets are appropriately managed across councils and key data is safeguarded.

Councils should monitor the implementation of recommendations

Fifty-three per cent of total findings reported in 2020–21 audit management letters were repeat or partial repeat findings from prior years.

What we recommended

Councils and those charged with governance should track the progress of implementing recommendations from financial audits, performance audits and public inquiries.

Key financial information

In 2020–21, councils:

  • collected $7.6b in rates and annual charges
  • received $5.1b in grants and contributions
  • incurred $4.8b of employee benefits and on costs
  • held $15.3b of cash and investments
  • managed $161.7b of infrastructure, property, plant and equipment
  • entered into $3.4b of borrowings.

Pursuant to the Local Government Act 1993 I present my report Local Government 2021. My report provides the results of the 2020–21 financial audits of 127 councils, 13 joint organisations and nine county councils.

Unqualified audit opinions were issued for 126 councils, 13 joint organisation and nine county councils in 2020–21. My independent auditor’s opinion was qualified for Central Coast Council who was unable to provide evidence to support the carrying value of $5.5 billion of roads, bridges, footpaths, bulk earthworks, stormwater drainage, water supply and sewerage network assets.

The 2020–21 year was challenging from many perspectives, not least being the continuing impact of and response to the recent emergency events, including bushfires, floods and the COVID-19 pandemic. We appreciate the efforts of council staff and management right across local government and they must be congratulated for their responsiveness and resilience in meeting their financial reporting obligations in such challenging circumstances.

This report makes a number of recommendations to councils and to the regulator, the Office of Local Government within the Department of Planning and Environment. These are intended to support councils to further improve the timeliness, accuracy and strength of financial reporting and their governance arrangements. Arguably, when faced with challenges, it is even more important to prioritise and invest in systems and processes to protect the integrity of councils' operations and promote accurate and transparent reporting.

I look forward to continuing engagement and constructive dialogue with councils in 2022–23 and beyond.

Margaret Crawford
Auditor-General for New South Wales

Financial reporting is an important element of good governance. Confidence in and transparency of public sector decision-making are enhanced when financial reporting is accurate and timely.

This chapter outlines audit observations related to the financial reporting of councils and joint organisations.

Highlights

  • One hundred and nine councils and joint organisations (2020: 133) lodged audited financial statements with OLG by the statutory deadline of 31 October (2020: 30 November).
  • Forty-one councils and joint organisations (2020: 16) received extensions to submit audited financial statements to OLG.
  • Unqualified audit opinions were issued for 126 councils, 13 joint organisations and nine county councils in 2020–21. A qualified audit opinion was issued for Central Coast Council in both 2019–20 and 2020–21.
  • The audit of Kiama Municipal Council is still in progress as at the date of this report due to significant accounting issues.
  • Fifty-nine per cent of councils performed some early financial reporting procedures, less than the prior year. We recommended that OLG should require early close procedures across the local government sector by 30 April 2023.
  • The total number and dollar value of corrected financial statement errors increased compared with the prior year, however uncorrected financial statement errors and prior period financial statement errors decreased compared to the prior year.
  • Sixty-eight councils (2020: 68 councils) did not record rural firefighting equipment in their financial statements worth an estimated $145 million (2020: $119 million). The NSW Government has confirmed these assets are not controlled by the NSW Rural Fire Service and are not recognised in the financial records of the NSW Government. We recommended that consistent with the OLG's role to assess council’s compliance with legislative responsibilities, standards or guidelines, OLG should intervene where councils do not recognise rural firefighting equipment. Councils should perform a full asset stocktake of rural firefighting equipment, including a condition assessment for 30 June 2022 financial reporting purposes.

A strong system of internal controls enables councils to operate effectively and efficiently, produce reliable financial reports, comply with laws and regulations, and support ethical government.

This chapter outlines the overall trends in governance and internal control findings across councils, county councils and joint organisations in 2020–21.

Financial audits focus on key governance matters and internal controls supporting the preparation of councils' financial statements. Audit findings are reported to management and those charged with governance through audit management letters.

Highlights

  • Total number of audit findings reported in audit management letters decreased from 1,435 in 2019–20 to 1,277 in 2020–21.
  • No extreme risk audit findings were identified in 2020–21 (2019–20: 1).
  • Total number of high-risk audit findings increased from 53 in 2019–20 to 92 in 2020–21. Sixty of the high-risk findings in 2020–21 related to the non-recording of rural firefighting equipment in councils' financial statements. Twenty-six per cent of the high-risk findings identified in 2019–20 were reported as high-risk findings in 2020–21.
  • Fifty-three per cent of findings reported in audit management letters were repeat or partial repeat findings. We recommend councils and those charged with governance should track progress of implementing recommendation from our audits.
  • Governance, asset management and information technology comprise over 62% of findings and continue to be key areas requiring improvement.
  • A number of recommendations were made relating to asset valuations and integrity of asset data records, in response to the findings that:
    • 67 councils had weak processes over maintenance and security of fixed asset registers
    • 58 councils had deficiencies in their processes to revalue infrastructure assets.
  • Sixty-five councils have yet to implement basic governance and internal controls to manage cybersecurity. We recommended that OLG needs to develop a cybersecurity policy to be applied by councils as a matter of high priority.

Total number of findings reported in audit management letters decreased

In 2020–21, 1,277 audit findings were reported in audit management letters (2019–20: 1,435 findings). No extreme audit risk findings were identified this year. The extreme risk relating to Central Coast Council's use of externally restricted funds in 2019–20 was partially addressed by management and has been rated as a high-risk for 2020–21. The total number of high-risk findings increased to 92 (2019–20: 53 high-risk findings).

Findings are classified as new, repeat or ongoing, based on:

  • new findings were first reported in 2020–21 audits
  • repeat findings were first reported in prior year audits, but remain unresolved in 2020–21
  • ongoing findings were first reported in prior year audits, but the action due dates to address the findings are after 2020–21.

Findings are categorised as governance, financial reporting, financial accounting, asset management, purchases and payables, payroll, cash and banking, revenue and receivables, or information technology. The high-risk and common audit findings across these areas are explored further in this chapter.

Audit Office’s annual work program for 2021–22 onwards

Focus on integrity of systems, good governance and good advice

We have a fundamental role in helping the Parliament hold government accountable for the use of public resources. In doing so, we examine whether councils' systems and processes are effective in supporting integrity, accountability and transparency. Key aspects of integrity that we expect to through conduct of our financial and performance audits over the next three years include the integrity of systems, good governance and good advice. These focus areas have arisen from the collation of key findings and recommendations from our past reports.

Focus on local councils' continued response to recent emergencies

The COVID-19 pandemic continues to have a significant impact on the people and the public sector of New South Wales. Local councils are continuing to assist communities in their recovery from the 2019–20 bushfires and subsequent and recent flooding. The full extent of some of these events remain unclear and will likely continue to have an impact into the future.

Image of a bus stop that's been completely burned because of a bushfire

The Office of Local Government within the Department of Planning and Environment continues to work with other state agencies to assist local councils and their communities to recover from these unprecedented events.

The increasing and changing risk environment presented by these events has meant that we have recalibrated and focused our efforts on providing assurance on how effectively aspects of responses to these emergencies have been delivered.

This includes financial and governance risks arising from the scale and complexity of government responses to these events.

We will take a phased approach to ensure our financial and performance audits address the following elements of the emergencies and the Local Government's responses:

  • local councils' planning and preparedness for emergencies
  • local councils' initial responses to support people and communities impacted by COVID-19 and the 2019–20 bushfires and recent floods
  • governance and oversight risks that arise from the need for quick decision-making and responsiveness to emergencies
  • effectiveness and robustness of processes to direct resources toward recovery efforts and ensure good governance and transparency in doing so
  • the mid to long-term impact of government responses to the natural disasters and COVID-19
  • whether government investment has achieved desired outcomes.

Focus on the effectiveness of cybersecurity in local government

The increasing global interconnectivity between computer networks has dramatically increased the risk of cybersecurity incidents. Such incidents can harm local government service delivery and may include theft of information, denial of access to critical technology, or even hijacking of systems for profit or malicious intent.

Outdated IT systems and capability present risks to government cybersecurity. Local councils need to be alert to the need to update and replace legacy systems, and regularly train and upskill staff in their use. To add to this, cybersecurity risks have been exacerbated by recent emergencies, which have resulted in greater and more diverse use of digital technology.

Our approach to auditing cybersecurity across in the sector involves:

  • considering how local councils are responding to the risks associated with cybersecurity across our financial audits
  • examining the effectiveness of cybersecurity planning and governance arrangements within local councils
  • conducting deep-dive performance audits of the effectiveness of cybersecurity measures in selected councils.

Local government elections

Local government elections took place in 2021–22

The local government elections were deferred for one year due to the COVID-19 pandemic and were held on 4 December 2021.

As part of our audits, we will consider the impact of any significant change on key decisions and activities for councils, county councils and joint organisations following the local government elections.

New rate peg methodology to support growing councils

The Independent Pricing and Regulatory Tribunal (IPART) has completed its review of the local government rate peg methodology to include population growth.

On 10 September 2021, IPART provided the final report on this review to the Minister for Local Government.

The minister has endorsed the new rate peg methodology and has asked IPART to give effect to it in setting the rate peg from the 2022–23 financial year.

As part of our audits, we will consider the impact of these changes on the financial statements and on key decisions and activities for councils, county councils and joint organisations.

Appendix one – Response from the Office of Local Government within the Department of Planning and Environment

Appendix two – Status of previous recommendations

Appendix three – Status of audits

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.