The Auditor-General for New South Wales, Margaret Crawford, released a report today examining the effectiveness of Service NSW’s handling of customers’ personal information to ensure its privacy.

The audit found that Service NSW is not effectively handling personal customer and business information to ensure its privacy. Service NSW continues to use business processes that pose a risk to the privacy of personal information. This includes the routine emailing of personal information between Service NSW service centres and other agencies, which is one of the processes that contributed to the data breach earlier this year. The audit found that previously identified risks and recommended solutions had not been implemented on a timely basis.

The Auditor-General made eight recommendations aimed at ensuring improved processes, technologies, and governance arrangements for how Service NSW handles customers’ personal information.

The Hon. Victor Dominello, MP, Minister for Customer Service, requested this audit under section 27(B)(3)(c) of the Public Finance and Audit Act 1983 following public reports in May 2020 of a cyber security attack which had led to a breach of Service NSW customer information. This audit also included the Department of Customer Service which supports Service NSW with privacy, risk and governance functions.

Service NSW was established in 2013 with the intention that it would, over time, 'become the primary interaction point for customers accessing New South Wales Government transaction services'.

Service NSW's functions are set out in the Service NSW (One stop Access to Government Services) Act 2013. This legislation allows for other NSW Government agencies to delegate to and enter into agreements with the Chief Executive Officer of Service NSW in order for Service NSW to undertake service functions for the agency.

Service NSW now has agreements with 36 NSW Government client agencies to facilitate over 1,200 types of interactions and transactions for the community.

The nature of each agreement between Service NSW and its client agencies varies. Some client agencies have delegated authority to allow Service NSW staff to conduct transactions on their behalf in the agencies' systems. Other arrangements do not include the same degree of delegation. In these cases, Service NSW provides services such as responding to enquiries and validating documents.

In addition, Service NSW conducts transactions for its own programs, such as the Seniors Card. Personal information for these programs, as well as information for customers' MyServiceNSW accounts, are stored by Service NSW on its Salesforce Customer Relationship Management (CRM) system.

In March 2020, Service NSW suffered two cyber security attacks in short succession. Technical analysis undertaken by the Department of Customer Service (DCS) concluded that these attacks resulted from a phishing exercise through which external threat actors gained access to the email accounts of 47 staff members. These attacks resulted in the breach of a large amount of personal customer information that was contained in these email accounts. See Section 1.1 for further details.

This audit is being conducted in response to a request from the Hon. Victor Dominello, Minister for Customer Service, under section 27B(3)(c) of the Public Finance and Audit Act 1983. Minister Dominello requested that the Auditor General conduct a performance audit in relation to Service NSW's handling of sensitive customer and business information.

This audit assessed how effectively Service NSW handles personal customer and business information to ensure its privacy.

It addressed the following:

  • Does Service NSW have processes and governance in place to identify and manage risks to the privacy of personal customer and business information?
  • Does Service NSW have policies, processes and systems in place that support the effective handling of personal customer and business information to ensure its privacy?
  • Has Service NSW effectively implemented its policies, processes and systems for managing personal customer and business information?

Conclusion

Service NSW is not effectively handling personal customer and business information to ensure its privacy. It continues to use business processes that pose a risk to the privacy of personal information. These include routinely emailing personal customer information to client agencies, which is one of the processes that contributed to the March 2020 data breach. Previously identified risks and recommended solutions had not been implemented on a timely basis.

Service NSW identifies privacy as a strategic risk in both its Risk Management Guideline and enterprise risk register and sets out a zero level appetite for privacy risk in its risk appetite statement. That said, the governance, policies, and processes established by Service NSW to mitigate privacy risk are not effective in ensuring the privacy of personal customer and business information. While Service NSW had risk identification and management processes in place at the time of the March 2020 data breach, these did not prevent the breach occurring.

Some of the practices that contributed to the data breach are still being followed by Service NSW staff. For example, business processes still require Service NSW staff to scan and email personal information to some client agencies.

The lack of multi factor authentication has been identified as another key contributing factor to the March 2020 data breach as this enabled the external threat actors to gain access to staff email accounts once they had obtained the user account details through a phishing exercise. Service NSW had identified the lack of multi factor authentication on its webmail platform as a risk more than a year prior to the breach and had committed to addressing this by June 2019. It was not implemented until after the breach occurred.

There are weaknesses in the general IT and security controls implemented by Service NSW over its Salesforce Customer Relationship Management (CRM) system, which holds the personal information of over four million NSW residents.

Internal audits carried out by Service NSW, including one completed in August 2020, have identified significant weaknesses in the general IT and security controls implemented by Service NSW over its Salesforce CRM system. These include deficiencies in the management of role based access, monitoring and audit of user access, and partitioning of program specific transaction information. These deficiencies create an increased risk of unauthorised access to the personal information of over four million customers held in the system.

Lines of responsibility for meeting privacy obligations are not clearly drawn between Service NSW and its client agencies.

Service NSW has agreements in place with client agencies. However, the agreements lack detail and clarity about the roles and responsibilities of the agencies in relation to the collection, storage and security of customer's personal information. This lack of clarity raises the risk that privacy obligations will become confused and missed between the agencies.

Service NSW carries out privacy impact assessments for major new projects but does not routinely review existing processes and systems.

Service NSW carries out privacy impact assessments as part of its routine processes for implementing major new projects, ensuring that privacy management is considered as part of project design. Service NSW does not regularly undertake privacy impact assessments or reviews of existing or legacy processes and systems, which has resulted in some processes continuing despite posing significant risks to the privacy of personal information, such as the scanning, emailing, and storing of identification documents.

1. Key findings

Service NSW identifies privacy risks, but the controls and processes it put in place to mitigate these privacy risks were not adequate to prevent or limit the extent of the data breach that occurred in March 2020

Service NSW’s approach to risk management is framed by its Risk Management Guideline, which defines 'privacy and compliance' as one of the key types of risk for the agency. Service NSW's enterprise risk register identifies four strategic privacy related risks. Service NSW has set out a zero level appetite for privacy risk in its risk appetite statement.

Service NSW has assessed the adequacy of its controls for privacy risks as needing improvement. To be fully effective, the Risk Management Guideline says that these controls should have a focus that is ‘largely preventative and address the root causes’.

One of the business processes that was a key contributing factor to the data breach was the emailing of personal information by Service NSW staff to client agencies.

This process had been identified as a risk prior to the breach and some steps had been put in place to mitigate the risk. In particular, staff were required to manually delete emails that contained personal information. However, these measures were ineffective in preventing the breach, as the external threat actors still gained access to 47 staff email accounts that contained a large amount of personal information.

It is unclear why Service NSW did not effectively mitigate this risk prior to the breaches. However, Service NSW has advised that it implemented measures in June and October 2020 to automatically archive emails likely to contain personal information. This is expected to limit the quantity of information retained in email accounts for extended periods.

Service NSW has not put in place any technical or other solutions to avoid Service NSW staff having to scan and email personal information to some client agencies. Urgent action is needed to remove the requirement for staff to email personal information to client agencies, thereby mitigating the risk inherent in sending and storing this information using email.

There are weaknesses in the general IT and security controls implemented by Service NSW over its Salesforce CRM system, which holds the personal information of over four million customers

There are weaknesses in the general IT and security controls implemented by Service NSW over its Salesforce CRM system. These weaknesses include deficiencies in governance of role based access, monitoring and audit of staff access, and partitioning of program specific transaction information. These deficiencies create an increased risk of unauthorised access to the personal information of over four million customers which is stored in this system.

In addition, there is an absence of important controls to safeguard customers' privacy, such as multi factor authentication and reviewable logs of access history to their information. Such controls, when properly implemented, would enhance the control that customers are able to exercise over their personal information.

A privacy impact assessment conducted on Service NSW’s Salesforce CRM system in 2015 recommended that the system include the ability for customers to review access history to their personal information, as well as the option for customers to apply multi factor authentication to their accounts. While both these recommendations appeared positively received by Service NSW, neither have been implemented.

Since its inception, Service NSW’s use of Salesforce has extended to storing transaction data, particularly for transactions for which Service NSW is responsible, such as the Seniors Card. It also holds details of over four million MyServiceNSW account holders, including name, email address and phone number, and optional address details. It was not originally intended for the system to hold this volume and nature of customer information.

Lines of responsibility for meeting privacy obligations are unclear between Service NSW and its client agencies

Service NSW's privacy management plan does not clearly set out the privacy obligations of Service NSW and its client agencies. It sets out that 'compliance with the privacy principles will primarily be the responsibility of that [client] agency'. However, Service NSW has its own obligations under the security principles of the Privacy and Personal Information Protection Act 1998 (PPIP Act) to take reasonable steps to prevent unauthorised access to personal information, which is not made clear in the privacy management plan.

The agreements between Service NSW and client agencies reviewed for this audit only include general and high level references to privacy. Most do not include details of each parties' privacy responsibilities such as: which agency will provide the customer with a privacy notice explaining how their personal information will be handled, how personal information will be kept secure, how long Service NSW will retain information, what processes will be followed for internal reviews, and what specific planning is in place to respond to data breaches.

Service NSW's privacy management plan has not been updated to include new programs and governance changes

Service NSW's privacy management plan includes most of the matters required by law or good practice, with some exceptions. It does not explain any exemptions that the agency commonly relies on under the PPIP Act and does not address any health information that Service NSW may handle. It had also not been updated to reflect governance changes and the fact that, at the time this audit commenced, Service NSW was disclosing the content of internal review applications (the formal expression for 'complaints') to the Department of Customer Service (DCS). These governance changes were part of the centralisation of Service NSW's corporate support functions into DCS in late 2019, though internal review staff were seconded back into Service NSW during the course of this audit.

The current July 2019 privacy management plan has also not been updated since the rollout of a number of major new initiatives in 2020. These include 2019–20 bushfire emergency recovery initiatives (such as small business grants) and COVID 19 pandemic response initiatives (such as small business grants, border permits and the COVID safe check in app).

Service NSW routinely conducts privacy impact assessments for new initiatives, though privacy risks remain in legacy systems and processes

Service NSW routinely conducts privacy impact assessments for major new initiatives and the assessments reviewed for this audit largely accorded with good practice guidance.

Service NSW does not routinely review existing processes and systems to ensure that they are effective in ensuring the privacy of customer personal information. Business processes that create the highest risk to privacy, such as emailing of personal information, are more common in these longstanding legacy systems.

Service NSW's significant and rapid growth has outpaced the establishment of a robust control environment which has exacerbated privacy risks

Since it was established in 2013, Service NSW has experienced significant growth in the number and diversity of the types of transactions it provides, as well as the number of client agencies with which it works. The pace and extent of this growth has contributed to important controls not being properly implemented on a timely basis, which has heightened privacy risks, particularly in regard to existing, legacy systems and processes.

The pace of change and increasing demand for new program implementation has limited the opportunity for Service NSW, in collaboration with its client agencies, to revisit and redesign legacy business practices which pose a greater privacy risk. This includes the scanning and emailing of personal information.

While 2019–20 has seen additional demands placed on Service NSW in responding to the 2019–20 bushfire emergency and COVID 19 pandemic, it is the nature of the agency’s work that it operates in a fast paced and complex environment, where it is required to respond to multiple client agencies and stakeholders. Ensuring customer privacy should be integral to Service NSW’s business as usual operations.

2. Recommendations

Service NSW commissioned a number of external reviews and investigations stemming from the data breaches. The Auditor General's recommendations below have taken these other reviews into account. In order to offer assurance that it is appropriately protecting the privacy of its customers, Service NSW should address the full breadth of findings and recommendations made across all relevant reviews.

As a matter of urgency, Service NSW should:

1. in consultation with relevant client agencies and the Department of Customer Service, implement a solution for a secure method of transferring personal information between Service NSW and client agencies

2. review the need to store scanned copies of personal information and, if still required, implement a more secure method of storing this information and regular deletion of material.

By March 2021, Service NSW should:

3. ensure that all new agreements entered into with client agencies from 1 April 2021 address the deficiencies identified in this audit, including that they provide clarity on:

  • the content and provision of privacy collection notices
  • the terms by which personal information will be retained, stored, archived, and disposed of when no longer required
  • steps that will be taken by each agency to ensure that personal information is kept secure
  • the circumstances in which, and processes by which, applications for internal review will be referred by one agency to the other
  • how identified breaches of privacy will be handled between agencies

4. in collaboration with the Department of Customer Service, review its privacy management plan to address the deficiencies raised in this audit, including:

  • to clarify Service NSW's understanding of how responsibility for meeting privacy obligations are delineated between Service NSW and client agencies
  • to better reflect the full scope and complexity of personal information handled by Service NSW
  • to better explain how applications for internal review are handled between Service NSW and the Department of Customer Service
  • to ensure regular ongoing review, either according to a schedule or when Service NSW experiences substantial change to its programs and handling of personal information

5. in consultation with the Department of Customer Service, review its policies and processes for the management of privacy risks, including to:

  • ensure that there are appropriate mechanisms to escalate identified privacy risks from business units to the Executive Leadership Team
  • ensure that there are action plans to address strategic privacy risks that are assessed as having ineffective controls.
By June 2021, Service NSW should:

6. address deficiencies in the controls over, and security for, its Salesforce customer relationship management and related systems that hold customer personal information, including:

  • establish policies and processes for regular access reviews and monitoring of user activity in these systems, including for privileged users
  • enable partitioning and role based access restrictions to personal information collected for different programs
  • provide customers the choice to use multi factor authentication to further secure their MyServiceNSW accounts
  • enable customers to view the transaction history of their personal information to detect possible mishandling.
By December 2021, Service NSW should:

7. ensure that all existing agreements with client agencies address the deficiencies identified in this audit, including that they provide clarity on:

  • the content and provision of privacy collection notices
  • the terms by which personal information will be retained, stored, archived, and disposed of when no longer required
  • steps that will be taken by each agency to ensure that personal information is kept secure
  • the circumstances in which, and processes by which, applications for internal review will be referred by one agency to the other
  • how identified breaches of privacy will be handled between agencies

8. carry out a risk assessment of all processes, systems and transactions that involve the handling of personal information and undertake a privacy impact assessment for those that:

  • are identified as high risk and have not previously had a privacy impact assessment
  • have had major changes or updates since the privacy impact assessment was completed.

Appendix one – Responses from agencies

Appendix two – About the audit

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Stronger Communities 2020

Stronger Communities 2020

Justice
Community Services
Asset valuation
Compliance
Financial reporting
Information technology
Internal controls and governance
Management and administration
Service delivery

This report analyses the results of our audits of financial statements of the agencies comprising the Stronger Communities cluster for the year ended 30 June 2020. The table below summarises our key observations.

1. Financial reporting

Quality of financial reporting Unqualified audit opinions were issued for all agencies' 30 June 2020 financial statements.
Compliance with financial reporting requirements

The Treasury extended the statutory deadline for the submission of the 2019–20 financial statements. For agencies subject to Treasurer's Directions, Treasury required agencies to submit their 30 June 2020 financial statements by 5 August 2020. For other agencies, the deadline was extended to 31 October 2020. All agencies in the cluster met the revised statutory deadlines.

Cluster agencies substantially completed the mandatory early close procedures set by NSW Treasury. However, nine agencies including the Department of Communities and Justice (the department) did not complete one or more mandatory requirements, such as assessing the impact of new and updated accounting standards.

Financial implications of recent emergencies

Emergency events significantly impacted cluster agencies in 2019–20. Our review of seven cluster agencies most affected highlighted some had incurred additional expenditure because of the bushfires and floods. Others lost revenue due to the COVID-19 pandemic.

During the year these agencies collectively received additional funding of $1.1 billion from the State to respond to:

  • increased demand for homeless people seeking temporary accommodation
  • additional cleaning requirements
  • bushfire recovery efforts
  • emergency support for eligible small businesses.

The Sydney Cricket Ground Trust, Venues NSW and Office of Sport lodged insurance claims of $51.3 million with the Treasury Managed Fund with respect to lost revenues from the pandemic. The losses were mainly due to event cancellations and covered various periods ranging from mid-March to 31 December 2020.

The change in economic conditions caused by the COVID-19 pandemic resulted in the NSW Government cancelling the refurbishment of Stadium Australia it had previously approved in August 2019. Venues NSW wrote off $16.8 million of redevelopment costs during 2019–20.

Restatement of the Sydney Cricket Ground valuation The valuation of the Sydney Cricket Ground (the Stadium) included costs of $28.6 million which were not eligible for capitalisation. The financial statements were restated to reflect the reduction in the value of the Stadium and the asset revaluation reserve.
Unresolved data quality issues in the VS Connect system

The department continues to address significant data quality issues resulting from its implementation of the VS Connect system (the System) in 2019. The issues relate to the completeness and accuracy of the data transferred from the legacy system. The System is used by the department to manage its Victims Support Services (VSS) and for financial reporting purposes.

An independent actuary helps the department estimate its liability for VSS claims. The actuary's valuation at 30 June 2020 was again impacted by the data quality issues. Consequently, the actuary adopted a revised valuation methodology compared to previous years.

Recommendation (repeat issue):

The department should resolve the data quality issues in the VS Connect System before 31 March 2021.

AASB 16 'Leases' resulted in significant changes to agencies' financial position

Cluster agencies implemented three new accounting standards for the first time in 2019–20. Adoption of AASB 16 'Leases' resulted in cluster agencies collectively recognising right-of-use assets and lease liabilities of $1.7 billion and $1.1 billion respectively on 1 July 2019.

Significant misstatements in how lease related balances had been calculated were found in 17 of the 29 cluster agencies. The cluster outsources the management of most of its owned and leased property portfolio to Property NSW, but cluster agencies remain responsible for any deliverables under that arrangement. The misstatements were mainly caused by late revisions of key assumptions and issues with the accuracy and completeness of Property NSW's lease information.

2. Audit observations

Internal control deficiencies

Our 2019–20 financial audits identified 191 internal control issues. Of these, two were high risk and almost one-third were repeat findings from previous audits. While repeat findings reduced by 5.7 percentage points in 2019–20, the number remains high.

Recommendation (repeat issue):

Cluster agencies should action recommendations to address internal control weaknesses promptly. Focus should be given to addressing high risk and repeat issues.

Agencies response to recent emergencies

The severity of the recent bushfires and floods meant natural disaster expenses incurred by emergency services agencies rose from $67.4 million in 2018–19 to $497 million in 2019–20.

The COVID-19 pandemic presented unprecedented challenges for the cluster. Social distancing and other infection control measures disrupted the traditional means of delivering services. Agencies established committees or response teams to respond to these challenges.

The department introduced measures to minimise the risk of the spread of COVID-19 amongst inmates in custodial settings.

Managing excess annual leave

Managing excess annual leave was a challenge for cluster agencies directly involved in the government's response to the emergency events. Employees in frontline cluster agencies deferred leave plans and many have taken little or no annual leave during the reporting period.

Annual leave liabilities rose at the department, NSW Police Force, Fire and Rescue NSW, Office of the NSW Rural Fire Service, the Legal Aid Commission of New South Wales and the Office of the Director of Public Prosecutions. The combined liabilities increased from $620 million to $692 million or 11.6 per cent between 30 June 2019 and 30 June 2020.

Implementation of Machinery of Government (MoG) changes

Administrative Arrangement Orders effective from 1 July 2019, created the department of Communities and Justice and transferred functions and staff, together with associated assets and liabilities into the department from the former departments of Justice and Family and Community Services.

The department continues to establish its governance arrangements following the MoG changes.

Recommendation:

The department should finalise appropriate governance arrangements for its new organisational structure as soon as possible. This includes:

  • harmonising policies and procedures to ensure a unified approach across the department
  • finalising risk management and monitoring processes across the department
  • updating its delegation instruments to reflect the current organisational structure, delegation limits and roles and responsibilities.
Delivery of the Prison Bed Capacity Program

The department continued to expand prison system capacity through the NSW Government's $3.8 billion Prison Bed Capacity Program. The department reported it spent $480 million on the Program in 2019–20. Six prison expansion projects were completed during the year, which added 1,660 new and 395 refurbished beds to the NSW prison system.

Data from the department shows the number of adult inmates in the NSW prison system reached a maximum of 14,165 during the year. Operational capacity was 16,096 beds on 19 August 2020.

 

This report provides parliament and other users of the financial statements of agencies in the Stronger Communities cluster with the results of our audits, our observations, analysis, conclusions and recommendations.

Agencies in the Stronger Communities cluster were significantly impacted by the bushfires, floods and the COVID-19 pandemic in 2019–20. Our 2019–20 financial audits of the seven cluster agencies most significantly impacted by the recent emergency events considered:

  • the financial implications of the emergency events
  • changes to agencies' operating models and control environments
  • delivery of new or expanded projects, programs or services at short notice.

Our findings on these seven agencies' responses to the recent emergencies are included throughout this report. These agencies are:

  • Department of Communities and Justice
  • Fire and Rescue NSW
  • NSW Police Force
  • Office of the NSW Rural Fire Service
  • Office of the NSW State Emergency Service
  • Sydney Cricket and Sports Ground Trust
  • Venues NSW.

The Department of Communities and Justice is the principal agency of the cluster. The names of all agencies in the Stronger Communities cluster are included in Appendix one.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Stronger Communities cluster for 2020, including any financial implications from the recent emergency events.

Section highlights

  • Unqualified audit opinions were issued for all agencies' 30 June 2020 financial statements. All agencies met the revised statutory deadlines for completing early close procedures and submitting their financial statements.
  • Emergency events significantly impacted cluster agencies in 2019–20. Agencies received additional funding of $1.1 billion to respond to the emergencies.
  • Cluster agencies implemented three new accounting standards in 2019–20. Adoption of AASB 16 'Leases' resulted in significant changes to agencies' financial statements.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our:

  • observations and insights from our financial statement audits of agencies in the Stronger Communities cluster
  • assessment of how well cluster agencies adapted their systems, policies and procedures, and governance arrangements in response to recent emergencies
  • review of how the cluster agencies managed the increased risks associated with new programs aimed at stemming the spread of COVID-19 and stimulating the economy.

Section highlights

  • Almost one-third of internal control issues reported were repeat findings. Cluster agencies should address these issues more promptly.
  • The severity of the recent bushfires and floods meant natural disaster expenses incurred by emergency services agencies increased by $430 million in 2019–20.
  • The department continues to establish its governance arrangements following Machinery of Government changes effective 1 July 2019.

 

Appendix one – Timeliness of financial reporting by agency

Appendix two – Management letter findings by agency

Appendix three – List of 2020 recommendations 

Appendix four – Status of 2019 recommendations 

Appendix five – Selected agencies for review of response to emergency events 

Appendix six – Financial data 

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Internal controls and governance 2020

Internal controls and governance 2020

Education
Environment
Community Services
Finance
Health
Industry
Justice
Premier and Cabinet
Transport
Treasury
Compliance
Cyber security
Information technology
Internal controls and governance
Management and administration
Procurement

The Auditor-General for New South Wales, Margaret Crawford today released her report on the findings and recommendations from the 2019–20 financial audits that relate to internal controls and governance at 40 of the largest agencies in the NSW public sector.

The bushfire and flood emergencies and the COVID‑19 pandemic continue to have a significant impact on the people and public sector of New South Wales. The scale of the government response to these events has been significant. The report focuses on the effectiveness of internal controls and governance processes, including relevant agencies’ response to the emergencies. In particular, the report focuses on:

  • financial and information technology controls
  • business continuity and disaster recovery planning arrangements
  • procurement, including emergency procurement
  • delegations that support timely and effective decision-making.

Due to the ongoing impact of COVID‑19 agencies have not yet returned to a business‑as‑usual environment. ‘Agencies will need to assess their response to the recent emergencies and update their business continuity, disaster recovery and other business resilience frameworks to reflect the lessons learnt from these events’ the Auditor-General said.

The report noted that special procurement provisions were put in place to allow agencies to better respond to the COVID-19 pandemic. The Auditor-General recommended agencies update their procurement policies to reflect the current requirements of the NSW Procurement Framework and the emergency procurement requirements.

Read the PDF report

This report analyses the internal controls and governance of 40 of the largest agencies in the NSW public sector for the year ended 30 June 2020. These 40 agencies constitute an estimated 85 per cent of total expenditure for all NSW public sector agencies.

1. Internal control trends
New, repeat and high risk findings

Internal control deficiencies increased by 13 per cent compared to last year. This is predominately due to a seven per cent increase in new internal control deficiencies and 24 per cent increase in repeat internal control deficiencies. There were ten high risk findings compared to four last year.

The recent emergencies have consumed agency time and resources and may have contributed to the increase in internal control deficiencies, particularly repeat deficiencies.

Agencies should:

  • prioritise addressing high-risk findings
  • address repeat internal control deficiencies by re-setting action plans and timeframes and monitoring the implementation status of recommendations.
Common findings

A number of findings remain common across multiple agencies over the last four years, including:

  • out of date or missing policies to guide appropriate decisions
  • poor record keeping and document retention
  • incomplete or inaccurate centralised registers or gaps in these registers.
2. Information technology controls
IT general controls

We found deficiencies in information security controls over key financial systems including:

  • user access administration deficiencies relating to inadequate oversight of the granting, review and removal of user access at 53 per cent of agencies
  • privileged users were not appropriately monitored at 43 per cent of agencies
  • deficient password controls that did not align to the agency's own password policies at 25 per cent of agencies.

The deficiencies above increase the risk of non-compliance with the NSW Cyber Security Policy, which requires agencies to have processes in place to manage user access, including privileged user access to sensitive information or systems and remove that access once it is not required or employment is terminated.

3. Business continuity and disaster recovery planning
Assessing risks to business continuity and Scenario testing

The response to the recent emergencies and the COVID-19 pandemic has encompassed a wide range of activities, including policy setting, on-going service delivery, safety and availability of staff, availability of IT and other systems and financial management. Agencies were required to activate their business continuity plans in response, and with the continued impact of COVID-19 have not yet returned to a business-as-usual environment.

Our audits focused on the preparedness of agency business continuity and disaster recovery planning arrangements prior to the onset of the COVID-19 pandemic.

We identified deficiencies in agency business continuity and disaster recovery planning arrangements. Twenty-three per cent of agencies had not conducted a business impact analysis (BIA) to identify critical business functions and determine business continuity priorities. Agencies can also improve the content of their BIA. For example, ten per cent of agencies' BIAs did not include recovery time objectives and six per cent of agencies did not identify key IT systems that support critical business functions. Scenario testing improves the effectiveness with which a live crisis is handled, but 40 per cent of agencies had not conducted a business continuity scenario testing exercise in the period from 1 January 2019 to 31 December 2019. There were also opportunities to improve the effectiveness of scenario testing exercises by:

  • involving key dependent or inter-dependent third parties who support or deliver critical business functions
  • testing one or more high impact scenarios identified in their business continuity plan
  • preparing a formalpost-exercise report documenting the outcome of their scenario testing.

Agencies have responded to the recent emergencies but addressing deficiencies will ensure agencies have adequate safeguards in their processes to again respond in the future, if required.

During 2020–21 we plan to conduct a performance audit on 'Business continuity and disaster recovery planning'. This audit will consider the effectiveness of agency business continuity planning arrangements to maintain business continuity through the recent emergencies and/or COVID-19 pandemic and return to a business-as-usual environment. We also plan to conduct a performance audit on whole-of-government 'Coordination of emergency responses'.

Responding to disruptions

We found agencies' governance functions could have been better informed about responses to disruptive incidents that had activated a business continuity or disaster recovery response between 1 January 2019 to 31 December 2019. For instance:

in 89 per cent of instances where a business continuity response was activated, a post-incident review had been performed. In 82 per cent of these instances, the outcomes were reported to a relevant governance or executive management committee

in 95 per cent of instances where a disaster recovery response was activated, a post incident review had been performed. In 86 per cent of these instances, the outcomes were reported to a relevant governance committee or executive management committee.

Examples of recorded incidents included extensive air quality issues and power outages due to bushfires, system and network outages, and infected and hijacked servers.

Agencies should assess their response to the recent emergencies and the COVID-19 pandemic and update business continuity, disaster recovery and other business resilience frameworks to incorporate lessons learned. Agencies should report to those charged with governance on the results and planned actions.

Management review and oversight Eighty-two per cent and 86 per cent of agencies report to their audit and risk committees (ARC) on their business continuity and disaster recovery planning arrangements, respectively. Only 18 per cent and five per cent of ARCs are briefed on the results of respective scenario testing. Briefing ARCs on the results of scenario testing exercises helps inform their decisions about whether sound and effective business continuity and disaster recovery arrangements have been established.
4. Procurement, including emergency procurement
Policy framework

Agency procurement policies did not capture the requirements of several key NSW Procurement Board Directions (the Directions), increasing the risk of non-compliance with the Directions. We noted: 

  • 67 per cent of agencies did specify that procurement above $650,000 must be open to market unless exempt or procured through an existing Whole of Government Scheme or contract
  • 36 per cent of agencies did specify that procurements above $500,000 payable in foreign currencies must be hedged
  • 69 per cent of agencies' policies did specify that the agency head or cluster CFO must authorise the engagement of consultants where the engagement of the supplier does not comply with the standard commercial framework.

Recommendation: Agencies should review their procurement policies and guidelines to ensure they capture the key requirements of the NSW Government Procurement Policy Framework, including NSW Procurement Board Directions.

Managing contracts

Eighty-eight per cent of agencies maintain a central contract register to record all details of contracts above $150,000, which is a requirement of GIPA legislation. Of the agencies that maintained registers, 13 per cent did not capture all contracts and eight per cent did not include all relevant contract details.

Sixteen per cent of agencies did not periodically review their contract register. Timely review increases compliance with GIPA legislation, and enhances the effectiveness with which procurement business units monitor contract end dates, contract extensions and commence new procurement.

Training and support

Ninety-three per cent of agencies provide training to staff involved in procurement processes, and a further 77 per cent of agencies provide this training on an on-going basis. Of the seven per cent of agencies that had not provided training to staff, we noted gaps in aspects of their procurement activity, including:

  • not conducting value for money assessments prior to renewing or extending the contract with their existing supplier
  • not obtaining approval from a delegated authority to commence the procurement process
  • procurement documentation not specifying certain key details such as the conditions for participation including any financial guarantees and dates for the delivery of goods or supply of services.

Training on procurement activities ensures there is effective management of procurement processes to support operational requirements, and compliance with procurement directions.

Procurement activities While agencies had implemented controls for tender activities above $650,000, 43 per cent of unaccredited agencies did not comply with the NSW Procurement Policy Framework because they had not had their procurement endorsed by an accredited agency within the cluster or by NSW Procurement. This endorsement aims to ensure the procurement is properly planned to deliver a value for money outcome before it commences.
Emergency procurement

As at 30 June 2020, agencies within the scope of this report reported conducting 32,239 emergency procurements with a total contract value of $316,908,485. Emergency procurement activities included the purchase of COVID-19 cleaning and hygiene supplies.

The government, through NSW Procurement released the 'COVID-19 Emergency procurement procedure', which relaxed procurement requirements to allow agencies to make COVID-19 emergency procurements. Our review against the emergency procurement measures found most agencies complied with requirements. For example:

  • 95 per cent of agencies documented an assessment of the need for the emergency procurement for the good and/or service
  • 86 per cent of agencies obtained authorisation of the emergency procurement by the agency head or the nominated employee under Public Works and Procurement Regulation 2019
  • 76 per cent of agencies reported the emergency procurement to the NSW Procurement Board.

Complying with the procedure helps to ensure government resources are being efficiently, effectively, economically and in accordance with the law.

Recommendation: Agency procurement frameworks should be reviewed and updated so they can respond effectively to emergency situations that may arise in the future. This includes:

  • updating procurement policies and guidelines to define an emergency situation, specify who can approve emergency procurement and capture other key requirements
  • using standard templates and documentation to prompt users to capture key requirements, such as needs analysis, supplier selection criteria, price assessment criteria, licence and insurance checks
  • having processes for reporting on emergency procurements to those charged with governance and NSW Procurement.
5. Delegations
Instruments of delegation

We found that agencies have established financial and human resources delegations, but some had not revisited their delegation manuals following the legislative and machinery of government changes. For those agencies impacted by machinery of government changes we noted:

  • 16 per cent of agencies had not updated their financial delegations to reflect the changes
  • 16 per cent of agencies did not update their human resources delegations to reflect the changes.

Delegations manuals are not always complete; 16 per cent of agencies had no delegation for writing off bad debts and 26 per cent of agencies had no delegation for writing off capital assets.

Recommendation: Agencies should ensure their financial and human resources delegation manuals contain regular set review dates and are updated to reflect the Government Sector Finance Act 2018, machinery of government changes and their current organisational structure and roles and responsibilities.

Compliance with delegations

Agencies did not understand or correctly apply the requirements of the Government Sector Finance Act 2018 (GSF Act), resulting in non-compliance with the Act. We found that 18 per cent of agencies spent deemed appropriations without obtaining an authorised delegation from the relevant Minister(s), as required by sections 4.6(1) and 5.5(3) of the GSF Act.

Further detail on this issue will be included in our Auditor-General's Reports to Parliament on Central Agencies, Education, Health and Stronger Communities, which will be tabled throughout December 2020.

Recommendation: Agencies should review financial and human resources delegations to ensure they capture all key functions of laws and regulations, and clearly specify the relevant power or function being conferred on the officer.

6. Status of 2019 recommendations
Progress implementing last year's recommendations

Recommendations were made last year to improve transparency over reporting on gifts and benefits and improve the visibility management and those charged with governance had over actions taken to address conflicts of interest that may arise. This year, we continue to note:

  • 38 per cent of agencies have not updated their gifts and benefits register to include all the key fields required under the minimum standards set by the Public Service Commission
  • 56 per cent of agencies have not provided training to staff and 63 per cent of agencies have not implemented an annual attestation process for senior management
  • 97 per cent of agencies have not published their gifts and benefits register on their website and 41 per cent of agencies are not reporting on trends in the gifts and benefits register to those charged with governance.

While we acknowledge the significance of the recent emergencies, which have consumed agency time and resources, we note limited progress has been made implementing these recommendations. Further detail on the status of implementing all recommendations is in Appendix 2.

Recommendation: Agencies should re-visit the recommendations made in last year's report on internal controls and governance and action these recommendations.

Internal controls are processes, policies and procedures that help agencies to:

  • operate effectively and efficiently
  • produce reliable financial reports
  • comply with laws and regulations
  • support ethical government.

This chapter outlines the overall trends for agency controls and governance issues, including the number of audit findings, the degree of risk those deficiencies pose to the agency, and a summary of the most common deficiencies we found across agencies. The rest of this report presents this year’s controls and governance findings in more detail.

Section highlights

We identified ten high risk findings, compared to four last year with two findings repeated from the previous year. There was an overall increase of 13 per cent in the number of internal control deficiencies compared to last year due to a seven per cent increase in new internal control deficiencies, and a 24 per cent increase in repeat internal control deficiencies. The recent emergencies have consumed agency time and resources and may have contributed to the increase in internal control deficiencies, particularly repeat deficiencies.

We identified a number of findings that remain common across multiple agencies over the last four years. Some of these findings related to areas that are fundamental to good internal control environments and effective organisational governance. Examples include:

  • out of date or missing policies to guide appropriate decisions
  • poor record keeping and document retention
  • incomplete or inaccurate centralised registers, or gaps in these registers.

Policies, procedures and internal controls should be properly designed, be appropriate for the current organisational structure and its business activities, and work effectively.

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency controls to manage key financial systems.

Section highlights

Government agencies’ financial reporting is heavily reliant on information technology (IT). We continue to see a high number of deficiencies related to IT general controls, particularly those related to user access administration. These controls are key in adequately protecting IT systems from inappropriate access and misuse.

IT is also important to the delivery of agency services. These systems often provide the data to help monitor the efficiency and effectiveness of agency processes and services they deliver. Our financial audits do not review all agency IT systems. For example, IT systems used to support agency service delivery are generally outside the scope of our financial audit. However, agencies should also consider the relevance of our findings to these systems.

Agencies need to continue to focus on assessing the risks of inappropriate access and misuse and the implementation of controls to adequately protect their systems, focussing on the processes in place to grant, remove and monitor user access, particularly privileged user access.

 

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency business continuity and disaster recovery planning arrangements.

Section highlights

We identified deficiencies in agency business continuity and disaster recovery planning arrangements and opportunities for agencies to enhance their business continuity management and disaster recovery planning arrangements. This will better prepare them to respond to a disruption to their critical functions, resulting from an emergency or other serious event. Twenty-three per cent of agencies had not conducted a business impact analysis (BIA) to identify critical business functions and determine business continuity priorities and 40 per cent of agencies had not conducted a business continuity scenario testing exercise in the period from 1 January 2019 to 31 December 2019. Scenario testing improves the effectiveness with which a live crisis is handled.

This section focusses on the preparedness of agency business continuity and disaster recovery planning arrangements prior to the onset of the COVID-19 pandemic. While agencies have responded to the recent emergencies, proactively addressing deficiencies will ensure agencies have adequate safeguards in their processes to again respond in the future, if required.

During 2020–21 we plan to conduct a performance audit on 'Business continuity and disaster recovery planning'. This audit will consider the effectiveness of agency business continuity planning arrangements to maintain business continuity through the recent emergencies and/or COVID-19 pandemic and return to a business-as-usual environment. We also plan to conduct a performance audit on whole-of-government 'Coordination of emergency responses'.

 

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of procurement agency procurement policies and procurement activity.

Section highlights

We found agencies have procurement policies in place to manage procurement activity, but the content of these policies was not sufficiently detailed to ensure compliance with NSW Procurement Board Directions (the Directions). The Directions aim to ensure procurement activity achieves value for money and meets the principles of probity and fairness.

Agencies have generally implemented controls over their procurement process. In relation to emergency procurement activity, agencies reported conducting 32,239 emergency procurements with a total contract value of $316,908,485 up to 30 June 2020. Our review of emergency procurement activity conducted during 2019–20 identified areas where some agencies did not fully comply with the 'COVID-19 Emergency procurement procedure'.

We also found not all agencies are maintaining complete and accurate contract registers. This not only increases the risk of non-compliance with GIPA legislation, but also limits the effectiveness of procurement business units to monitor contract end dates, contract extensions and commence new procurement in a timely manner. We noted instances where agencies renewed or extended contracts without going through a competitive tender process during the year.

 

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency compliance with financial and human resources delegations.

Section highlights
We found that agencies are not always regularly reviewing and updating their financial and human resources delegations when there are changes to legislation or other organisational changes within the agency or from machinery of government changes. For example, agencies did not understand or correctly apply the requirements of the GSF Act, resulting in non-compliance with the Act. We found that 18 per cent of agencies spent deemed appropriations without obtaining an authorised delegation from the relevant Minister(s), as required by sections 4.6(1) and 5.5(3) of the GSF Act.
In order for agencies to operate efficiently, make necessary expenditure and human resource decisions quickly and lawfully, particularly in emergency situations, it is important that delegations are kept up to date, provide clear authority to decision makers and are widely communicated.

Appendix one – List of 2020 recommendations 

Appendix two – Status of 2019 recommendations

Appendix three – Cluster agencies

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Government advertising 2018-19 and 2019-20

Government advertising 2018-19 and 2019-20

Whole of Government
Finance
Community Services
Compliance
Management and administration
Procurement

A report released today by the Auditor-General for New South Wales, Margaret Crawford found that select advertising campaigns conducted by Service NSW and the NSW Rural Fire Service met most requirements of the Government Advertising Act, regulations, Guidelines and other laws. However, the audit found that Service NSW inappropriately used its post campaign evaluation to measure sentiment towards and confidence in the NSW Government.  

While agency analysis shows that the ‘Cost of Living’ (phases 2 and 3)  and ‘How Fireproof is Your Plan?’ campaigns achieved most of their objectives, the campaign objectives and targets set by both agencies were not sufficient to measure all aspects of campaign effectiveness. 

The report makes two recommendations to the Department of Customer Service. The first is to review its guidance to ensure agencies are not using post campaign evaluations to measure sentiment towards the government. The second, to review its guidance and the new process of peer review to ensure they support agencies to comply with the Act, the regulations and the Guidelines. 

The Government Advertising Act 2011 requires the Auditor General to conduct an annual performance audit of one or more government agencies to see whether their advertising activities were carried out in an effective, economical and efficient manner and in compliance with the Government Advertising Act 2011.
 

Read full report (PDF)

The Government Advertising Act 2011 (the Act) requires the Auditor-General to conduct a performance audit on the activities of one or more government agencies in relation to government advertising campaigns in each financial year. The performance audit assesses whether a government agency or agencies have carried out activities in relation to government advertising in an effective, economical and efficient manner and in compliance with the Act, the regulations, other laws and the Government Advertising Guidelines (the Guidelines). This audit examined two campaigns run during the 2018–19 and 2019–20 financial years respectively:

  • the 'Cost of Living' campaign run by Service NSW (phases 2 and 3 delivered in 2018–19)
  • the 'How Fireproof Is Your Plan?' (Fireproof) campaign run by NSW Rural Fire Service (year two of a three-year campaign delivered in 2019–20).

Section 6 of the Act prohibits political advertising. Under this section, material that is part of a government advertising campaign must not contain the name, voice or image of a minister, member of parliament or a candidate nominated for election to parliament or the name, logo or any slogan of a political party. Further, a campaign must not be designed to influence (directly or indirectly) support for a political party.

Conclusion

Neither campaign breached the prohibition on political advertising contained in section 6 of the Act. While both campaigns met most requirements of the Act, the regulations, other laws and the Guidelines, we identified some instances of non-compliance. Service NSW inappropriately used its post campaign evaluation to measure sentiment towards and confidence in the NSW Government.

Service NSW used its post-campaign evaluation to measure sentiment towards and confidence in the NSW Government. While neither campaign breached the prohibition on political advertising contained in section 6 of the Act, measuring sentiment towards and confidence in the NSW Government is not an appropriate use of the post-campaign evaluation and creates a risk that the results may be used for party political purposes. This risk is heightened as both phases 2 and 3 of the Cost of Living campaign were run immediately before the NSW state election. We have made this finding previously in our report 'Government advertising 2017–18'.

The campaign objectives and targets set by both agencies were not sufficient to fully measure campaign effectiveness. Service NSW advertised seven rebates in phase 2 of the campaign but only set targets for the awareness and uptake of three of these rebates. NSW Rural Fire Service set objectives and targets to be achieved over the life of the three-year campaign but did not set targets to be achieved for each year of the campaign. While the Fireproof campaign is a three-year campaign, each year of the campaign is subject to a separate approval and peer review process.

Agency analysis shows that both campaigns achieved most of their objectives. There was some overlap in the timing of phases 2 and 3 of the Cost of Living campaign and both phases had similar high-level objectives to increase awareness of rebates, making it difficult to evaluate the effectiveness of each distinct campaign phase. NSW Rural Fire Service conducted a post-campaign evaluation for year two of the Fireproof campaign (2019–20) but although this showed positive results against the overall objectives of the three-year campaign, NSW Rural Fire Service did not set specific targets for year two of the campaign, making it difficult to evaluate effectiveness for that year.

Service NSW was not able to demonstrate that its campaign was economical as it directly negotiated with a single supplier for the creative materials for phase 2. This is contrary to the NSW Government's procurement rules which require agencies to obtain three quotes when using suppliers on a prequalification scheme. Service NSW did not comply with its own procurement policy, which restricts Service NSW employees from entering into discussions with a supplier until the appropriate delegate approves a direct procurement. NSW Rural Fire Service achieved cost efficiencies by re-using creative material developed in the first year of the campaign. NSW Rural Fire Service also received $4 million worth of free advertising time and space.

The cost benefit analyses prepared by both agencies did not fully meet the requirements in the Guidelines. Both agencies identified an alternative to advertising but did not assess the costs and benefits of that alternative. We have made this finding previously in our report 'Government advertising 2017–18' and in our report 'Government advertising 2015–16 and 2016–17'.

In 2018–19, Service NSW delivered phases 2 and 3 of the 'Cost of Living' campaign. The Cost of Living advertising campaign aimed to build awareness of the help available to ease the cost of living for people under financial pressure including awareness of specific rebates that can be claimed. As part of the Cost of Living program, Service NSW developed a webpage designed as a single portal to access more than 40 NSW Government savings, rebates and initiatives (which originated from over 12 different agencies). It also launched the Cost of Living service which includes face to face meetings and phone interviews to help people claim rebates from the NSW Government. Phase 2 of the campaign ran from September 2018 to August 2019. Phase 3 of the campaign ran from January 2019 to July 2019. The budgets for phases 2 and 3 were $4.127 million and $934,800 respectively. See Appendix two for more details on this campaign.

Service NSW complied with most requirements of the Act, the Regulations and the Guidelines. Campaign materials that we reviewed did not breach the prohibition on political advertising contained in section 6 of the Act. However, Service NSW used its post-campaign evaluation to measure sentiment towards, and confidence in, the NSW Government. This is not an appropriate use of the post-campaign evaluation and creates a risk that the results may be used for party political purposes. This risk is heightened as both phases 2 and 3 of the Cost of Living campaign were run immediately before the NSW state election.
The post-campaign evaluation shows that the campaign was effective in achieving most of its objectives. However, in phase 2, Service NSW did not set targets for all of the rebates it advertised. There was some overlap in the timing of phases 2 and 3 of the Cost of Living campaign and both phases had similar high-level objectives to increase awareness of rebates, making it difficult to evaluate the effectiveness of each distinct campaign phase.
Service NSW was not able to demonstrate that its campaign was economical as it directly negotiated with a single supplier for the creative materials in phase 2 (total cost $731,480). This is contrary to the NSW Government's procurement rules which require agencies to obtain three quotes when using suppliers on a prequalification scheme where the estimated cost is more than $150,000. Service NSW did not comply with its own procurement policy, which restricts Service NSW employees from entering into discussions with a supplier until the appropriate delegate approves a direct procurement.
The cost benefit analysis for phase 2 did not accurately assess the benefits of the campaign as Service NSW did not know which rebates would be included in the advertisements at the time the cost benefit analysis was developed. The cost benefit analysis for phase 2 did not assess the costs and benefits of alternatives to advertising.

Campaign materials we reviewed did not breach section 6 of the Act

The audit team reviewed campaign materials developed as part of the paid advertising campaign including radio transcripts, digital videos and display. The audit team did not review the use of social media outside paid social media content as section four of the Act defines government advertising as the dissemination of information which is funded by or on behalf of a government agency. See Appendix two for examples of campaign materials for this campaign.

Section 6 of the Act prohibits political advertising as part of a government advertising campaign. A government advertising campaign must not:

  • be designed to influence (directly or indirectly) support for a political party
  • contain the name, voice or image of a minister, a member of parliament or a candidate nominated for election to parliament
  • contain the name, logo, slogan or any other reference to a political party.

The audit found no breaches of section 6 of the Act in the campaign material we reviewed. 

Post-campaign evaluations measured sentiment towards and confidence in the NSW Government

The post-campaign evaluation for phases 2 and 3 measured levels of confidence with the statement ‘the NSW Government has your best interests at heart’, despite the fact this was not a stated objective of the campaign. This is not an appropriate use of the post-campaign evaluation, which should measure the success of the campaign against its stated objectives. The post-campaign evaluation for phase 3 found that exposure to the campaign improved sentiment towards the government amongst those who did not have confidence in the NSW Government.

Service NSW advised that it was important to measure the sentiment of the advertising including the wording 'best interests' as it did not want the whole of government brand to be detrimental to customer engagement with applying for the rebates.

Following phase 2, Service NSW conducted analysis of media sentiment using the key words 'cost of living' and the names of the Premier, Treasurer and Minister for Customer Service. The analysis presented the level of positive, negative and neutral media sentiment. The Government Advertising Guidelines 2012 list the purposes that government advertising may serve which do not include improving the perception of the government. The inclusion of this analysis in Service NSW's post-campaign evaluation creates a risk that the results may be used for party political purposes.

Section 10 of the Act restricts agencies from carrying out a campaign after 26 January in the calendar year before the Legislative Assembly is due to expire and before the election for the Legislative Assembly in that year. Service NSW authorised a media agency to book media in line with the media plans for the campaign. The media plans for the campaign show that Service NSW did not authorise or plan to run any advertisements between 27 January 2019 and 23 March 2019.

Service NSW did not set targets for all rebates advertised in phase 2

Service NSW did not set targets for four of the seven rebates that were advertised as part of phase 2 of the campaign. These rebates were the Family Energy Rebate, Appliance Replacement Offer, National Parks Concession Offer and the Pensioner Travel Voucher. As a result, it was unable to evaluate whether the advertisements for these rebates were effective. Service NSW advised that at the time the campaign went to peer review, when campaign objectives are set, it did not know which rebates would be included in the advertisements.

Service NSW stated in its submission to the Department of Premier and Cabinet that it may change the creative content for phase 2 as it announced new initiatives and rebates. The peer review process should have ensured that Service NSW set targets for any additional rebates or savings it intended to advertise before that advertising commenced to ensure a strategic approach to the campaigns that clearly demonstrated anticipated benefits were in place.

The post-campaign evaluation for phase 2 shows that the advertising campaign met most of its objectives

Service NSW set overall campaign objectives and specific targets for some rebates advertised as part of phase 2 of the campaign. The objectives, targets and results for phase 2 are shown in Exhibit 5. In phase 2, Service NSW established baseline data on levels of awareness of government rebates during the peer review process. The baseline level of awareness for government rebates was 44 per cent. The level of awareness for specific rebates was 46 per cent for the Compulsory Third Party (CTP) green slip refund, and 21 per cent for both Active Kids and Toll Relief.

Post-campaign evaluation reports for phase 2 show that the campaign met its objective to raise awareness of NSW Government rebates, achieving a 16 per cent increase in awareness from 44 per cent to 51 per cent. The campaign did not meet its target to increase awareness of the CTP green slip refund by ten per cent.

Service NSW did not report the results of the uptake of the CTP green slip refund, Active Kids and Toll Relief in its post campaign effectiveness report submitted to the Department of Premier and Cabinet. However, other post-campaign evaluation documentation, which Service NSW advise was submitted to the Department of Premier and Cabinet, show that these targets were met.

Service NSW did not report to the Department of Premier and Cabinet on whether it achieved the target of a ten per cent increase of average monthly visits to the Cost of Living webpage. Service NSW reported that it had achieved an average of 11,753 visitors to the webpage per day during the campaign. These average daily results indicate that the target was met.

Exhibit 5: Phase 2 - campaign objectives, targets and results
Campaign objectives and targets Does the post-campaign evaluation show that the target was met?
1. a) Increase awareness of rebates from the NSW Government by ten per cent.
Image
mauve circle with tick inside

    b) Increase average monthly visits to the Cost of Living webpage by ten per cent.

Image
mauve circle with tick inside and asterisk to the right

2. Increase awareness of rebates and savings by ten per cent for:

 
  • CTP green slip refund
Image
gold circle with white minus symbol inside
  • Active Kids
Image
mauve circle with tick inside
  • Toll Relief.
Image
mauve circle with tick inside
3. Increase awareness that NSW Government initiatives relating to the cost of living are available via Service NSW by ten per cent.
Image
mauve circle with tick inside
4. Increase the uptake of rebates and savings for the CTP green slip refund, Active Kids and Toll Relief by ten per cent.
Image
mauve circle with tick inside and asterisk to the right
Key
Image
mauve circle with tick inside
Yes
Image
gold circle with white minus symbol inside
Not Fully

*  Some issues with reporting on target.
Source: Service NSW. Audit Office analysis.

The post-campaign evaluation for phase 3 shows that the advertising campaign met most of its objectives

Service NSW set overall campaign objectives and specific targets for the two rebates advertised as part of phase 3 of the campaign. The objectives, targets and results for phase 3 are shown in Exhibit 6.

In phase 3, Service NSW established baseline data on levels of awareness during the peer review process. The baseline level of awareness for government rebates was 44 per cent. This is the same baseline that was used to measure performance for phase 2 of the campaign. Service NSW did not set baselines for awareness and uptake of Energy Switch and Creative Kids as these were new services.

Post-campaign evaluation reports for phase 3 show that the campaign met its objective to raise awareness of NSW Government rebates by ten per cent, achieving a 30 per cent increase in awareness from 44 per cent to 57 per cent. The overall increase in message take-out was met with 43 per cent agreeing with the message that the NSW Government is taking steps to ease the cost of living. The campaign achieved awareness and uptake targets for the specific rebates included in phase 3, except for awareness of Creative Kids which achieved 28 per cent awareness, falling short of the 30 per cent awareness target.

Exhibit 6: Phase 3 - campaign objectives, targets and results
Campaign objectives and targets Does the post-campaign evaluation show that the target was met?
1. Increase message takeout that ‘The NSW Government is taking steps to help ease the cost of living in NSW’ by ten per cent for those who can recall the campaign.
2. Increase awareness that the NSW Government has a range of rebates and savings by ten per cent.
3. Generate awareness with NSW residents aged 18+ of:
 
 
  • Energy Switch (15 per cent awareness)
  • Creative Kids (30 per cent awareness).
4. Create uptake of Energy Switch and Creative Kids (8,356 clicks on the Energy Switch website and 107,938 Creative Kids vouchers downloaded with 70 per cent conversion).
Key
Yes
Not Fully

Source: Service NSW. Audit Office analysis.

The timing of campaign phases meant that it was difficult for Service NSW to evaluate each distinct campaign phase and reduced opportunities to incorporate learnings from previous phases

Service NSW commenced planning for phase 2 of the campaign while phase 1 was still underway. This limited the opportunity for Service NSW to incorporate learnings from phase 1 into phase 2. There was some overlap in the timing of phase 2 and the start of phase 3 of the campaign, making it difficult to evaluate the effectiveness of each distinct campaign phase. Both phases 2 and 3 had the same high-level outcome objective to raise awareness of rebates by ten per cent. The baseline measures that were used to evaluate performance for phase 3 were the same as those used to evaluate phase 2. As a result, Service NSW was not able to separately evaluate these two phases of the campaign. This is important given the budgets for phases 2 and 3 were $4.127million and $934,800 respectively.

Service NSW allocated 7.5 per cent of its media budget to communications with culturally and linguistically diverse (CALD) and Aboriginal audiences

The NSW Government CALD and Aboriginal Advertising Policy requires that agencies spend at least 7.5 per cent of an advertising campaign media budget on direct communications with CALD and Aboriginal audiences. Service NSW authorised a media company to book media in line with the media plans for the campaign. The media plans for phases 2 and 3 of the campaign indicate that Service NSW met this requirement, with 7.5 per cent of the budget allocated to these audiences in phase 2 and 10.4 per cent in phase 3.

The post campaign evaluation for phases 1 and 2 of the Cost of Living campaign contained a recommendation to look at other opportunities to reach CALD audiences. Effective communication with CALD audiences was particularly important in phase 3 of the campaign, where they made up 30 per cent of the target audience for the Creative Kids advertisement. The post-campaign analysis for phase 3 showed that the campaign performed well with some, but not all CALD audiences. The post-campaign analysis also showed low awareness and uptake with Aboriginal audiences. Pre-campaign focus groups in phase 3 found Aboriginal audiences had a negative reaction to the campaign tag line ‘NSW Government is helping with the cost of living’ however this tagline was still used in some advertisements in phase 3.

The cost-benefit analysis (CBA) for phase 2 did not accurately assess the benefits of the campaign and did not assess the costs and benefits of alternatives to advertising

Under the Government Advertising Act 2011, agencies are required to prepare a CBA when the cost of the campaign is likely to exceed $1 million. The CBA conducted by Service NSW for phase 2 includes $8 million in benefits attributed to the advertisements for the Energy Switch tool and $6.9 million in benefits attributed to the advertisements for Creative Kids vouchers. These benefits should not have been included in the CBA for phase 2 as they were not included in this phase of the campaign. The CBA did not estimate the benefits of some other rebates and savings advertised in phase 2 of the campaign. This means that the CBA did not accurately assess the benefits of the campaign. Service NSW advised that at the time the CBA was developed it had not selected the rebates to be included in the campaign.

The Government Advertising Guidelines require agencies to consider options other than advertising to achieve the desired objective including a comparison of costs and benefits. The CBA developed as part of phase 2 identified using existing NSW Government communication channels as an alternative to advertising but did not assess the costs and benefits of this alternative.

This is a repeat finding from two previous government advertising audits. The report ‘Government Advertising: 2015–16 and 2016–17’ found that both agencies subject to the audit did not meet the requirements in the guidelines to consider alternatives to advertising. The report made a recommendation to the Department of Premier and Cabinet to work with Treasury to ensure the requirements of the guidelines are fully reflected in the 'Cost-Benefit Analysis Framework for Government Advertising and Information Campaigns'. The report ‘Government advertising 2017–18’ found that one agency subject to the audit did not identify to what extent the benefits could be achieved without advertising, nor did it consider alternatives to advertising which could achieve the same impact as the advertising campaign.

Service NSW negotiated with a single creative agency in phase 2, making it difficult to demonstrate value for money

Agencies are required to obtain three quotes when procuring a creative agency on the prequalification scheme if the estimated cost of the creative content is greater than $150,000. In phase 2 of the campaign, Service NSW extended the contract with the creative agency used for phase 1 of the campaign and did not obtain three quotes despite the cost of the creative content for phase 2 being $731,480. The requirement to obtain three quotes was met in phase 1 when initially selecting this creative agency.

Service NSWs procurement policy details that direct negotiation may be appropriate where there is a compelling reason to renew or rollover a contract beyond temporal or convenience reasons or in the cases of a genuine emergency. In its briefing to the Chief Executive, Service NSW stated that this contract extension was sought due to the time-sensitive nature of the project and that if work was delayed by a tender process, Service NSW may not be able to meet marketing milestones and this could result in limited customer uptake. This reason is not a genuine emergency and is not compelling as it does not explain what consequences would occur if it did not meet the marketing milestones or if there was limited customer uptake.

Service NSW's procurement policy also states that under no circumstances must Service NSW employees enter into discussions with a supplier until the delegate has formally made their decision to enter into direct negotiation. Service NSW briefed the Chief Executive of Service NSW in relation to extending the contract on 5 September 2018. The briefing states that the creative agency had already begun developing creative content for phase 2 and Service NSW had already received quotes from the creative provider for the proposed work prior to 5 September 2018. Procurement sign-offs were not completed until 7 September 2018. The engagement of the creative provider prior to appropriate approvals was contrary to Service NSWs procurement policy.

The economy of the campaign may have been limited by not meeting the procurement requirements in phase 2. It is possible that the creative provider may have offered a more competitive rate if it was aware that Service NSW was seeking quotes from other creative providers. Additionally, it is possible that another creative provider could have provided better value for money.

In phase 3 of the campaign, the estimated cost of the creative exceeded $150,000 however Service NSW chose to contract two different creative agencies, and the cost for each agency fell below the threshold to obtain three quotes. Agencies are permitted to obtain one quote when using a creative provider on the prequalification scheme if the cost is between $50,000 to $150,000. Service NSW advised that it contracted two creative providers as two different project teams were responsible for the rebates, each with separate marketing budgets.

Service NSW allowed sufficient time for cost-efficient media placement

During the peer review process, the Department of Premier and Cabinet advised agencies about the time they should allow to ensure cost-efficient media placement. For example, the Department of Premier and Cabinet advised that agencies book television advertising six to 12 weeks in advance and that agencies book radio advertising two to eight weeks in advance.

Service NSW allowed sufficient time between the completion of the peer review process and the commencement of the first advertising. Service NSW signed the agreement with the approved Media Agency Services provider with sufficient time to achieve cost-efficient media placement for all types of media used in this campaign.

The campaign may have been misleading for some people who were not eligible for rebates

Advertisements we reviewed focused on the amount of savings that could be obtained from rebates, for example ‘Save up to $285’, and ended with a statement ‘To save, visit service.nsw.gov.au. This directed viewers to the Cost of Living website which contains eligibility information. However, the advertisements in phases 2 and 3 we reviewed did not contain any details on the eligibility for these rebates and not all advertisements stated that eligibility criteria apply. Service NSW advised that the eligibility criteria for each rebate is extensive and that it was not possible to include this in the creative material.

Post-campaign evaluations in phase 3 recommended that advertisements for Creative Kids should indicate eligibility (e.g. age criteria) as statements on savings have the potential to be misleading when not all viewers will be eligible for rebates. Social media analysis conducted following phase 2 showed ineligibility or inability to claim rebates or refunds caused anger for some respondents.

Some advertisements in phase 2 stated ‘we've got something for everyone’. However, as rebates were subject to eligibility criteria, it is possible that some residents in NSW would not be eligible for any rebates as part of the Cost of Living initiative. As such, this statement has the potential to be misleading.

The campaign included statements that underestimated the savings that some customers could obtain

The Guidelines require accuracy in the presentation of all facts, statistics, comparisons and other arguments. The Guidelines also require that all claims of fact included in government advertising campaigns must be able to be substantiated.

In phase 2, the possible savings customers could obtain for two rebates or savings exceeded the amounts stated in the advertising campaign. Exhibit 7 shows some advertisements in phase 2 which stated, ‘My Green Slip Saving Save up to $60’. However, the State Insurance Regulatory Authority website shows that savings for some types of motor vehicles under the 2017 CTP scheme exceed $60. The State Insurance Regulatory Authority website states that the average saving under this scheme has been $129. Service NSW advised that these advertisements were designed for regional markets and that it used different advertisements for metropolitan areas which contained different amounts of savings.

Some advertisements in phase 2 stated, ‘My Toll Relief save up to $700’. The Service NSW website states that drivers can obtain free vehicle registration if they have spent $1,352 or more in tolls in the previous financial year. The cost of registration for some vehicles exceeds $700. This means the savings detailed in the advertisement were lower than what some customers could actually save.

NSW Rural Fire Service conducted the 'How FireProof Is Your Plan?' (Fireproof) campaign. The Fireproof campaign is a three-year campaign which ran in 2018–19 (year one), 2019–20 (year two) and is planned for 2020–21 (year three). This audit examined year two of the campaign (2019–20).

The Fireproof campaign is a public safety campaign encouraging people to plan and prepare for bush fires across the summer period. The campaign aims to improve the quality of bush fire planning and preparation in the community and decrease the impact of fires on the community when they occur.

The Fireproof campaign (year two) complied with most requirements of the Act, the Regulations and the Guidelines. The campaign materials that we reviewed did not breach the prohibition on political advertising contained in section 6 of the Act. NSW Rural Fire Service set objectives and targets to be achieved over the life of the three-year Fireproof campaign. Post-campaign evaluation shows that the Fireproof campaign was effective in achieving increases against its three-year objectives during year two. However, NSW Rural Fire Service did not set targets to be achieved for each year of the campaign, making it difficult to evaluate the effectiveness of year two of the campaign. NSW Rural Fire Service achieved cost efficiencies by re-using creative material developed in the first year of the campaign. NSW Rural Fire Service received $4 million worth of free advertising time and space. The cost benefit analysis for the Fireproof campaign did not assess the costs and benefits of alternatives to advertising.

Campaign materials we reviewed did not breach section 6 of the Act

The audit team reviewed campaign materials developed as part of the paid advertising campaign for example radio advertisements, television commercials and digital displays. The audit team did not review the use of social media outside paid social media content as section four of the Act defines government advertising as the dissemination of information which is funded by or on behalf of a government agency. Examples of campaign materials are shown in Appendix two.

Section 6 of the Act prohibits political advertising as part of a government advertising campaign. A government advertising campaign must not:

  • be designed to influence (directly or indirectly) support for a political party
  • contain the name, voice or image of a minister, a member of parliament or a candidate nominated for election to parliament
  • contain the name, logo, slogan or any other reference to a political party.

The audit found no breaches of section 6 of the Act in the campaign material we reviewed. 

NSW Rural Fire Service did not set targets for the second year of the campaign

The second year of the Fireproof campaign (2019–20) had the same objectives as the first year of the campaign (2018–19), however no specific targets were set for the second year. The advertising submission for the first year of the campaign (2018–19) details the targets for each objective as an increase of ten per cent against the baseline data to be achieved by March 2021, at the end of the three-year campaign.

The second year of the Fireproof campaign (2019–20) was one of the first campaigns approved under the new budget and peer review processes introduced by the Department of Customer Service in 2019–20. The new process for peer review introduced a new template for campaign submissions. The former template for campaign submissions contained more prompts for agencies to ensure the submission contained sufficient detail of campaign objectives, baseline measures, targets, dates for measurement and detail on how they would measure objectives. Despite this, the peer review process should have identified that NSW Rural Fire Service did not set targets for the second year of the campaign.

The 2016 Guidelines for Implementing NSW Government Evaluation Framework for Advertising and Communications requires campaign objectives to be SMART (specific, measurable, achievable, realistic and timed). NSW Rural Fire Service did not meet this requirement for year two of the Fireproof campaign.

Post-campaign evaluations showed increases against four out of five objectives, however there were no specific targets

NSW Rural Fire Service set three campaign objectives at the time it submitted the second year of the campaign (2019–20) to the Department of Customer Service for peer review. However, the post-campaign effectiveness report submitted to the Department of Customer Service measured campaign effectiveness against five campaign objectives. The objectives in the post-campaign effectiveness report were the same objectives set for the first year of the campaign, which is appropriate as this was a repeat campaign.

NSW Rural Fire Service achieved increases against four of their five objectives. However, as noted above there were no specific targets (such as percentage increases) against which performance of the 2019–20 campaign could be measured. Despite this, at the end of the second year, the Fireproof campaign had already achieved some of the targets that NSW Rural Fire Service had set for the end of the third year of the campaign. The post-campaign research showed that both audience recall and exposure to the campaign increased significantly from the prior year. The campaign objectives and results are shown in Exhibit 8.

For those people who already have a bush fire plan, the campaign aimed to increase the number of those plans which have included two or more elements from the Guide to Making a Bush Fire Survival Plan. Elements from the Guide to Making A Bush Fire Survival Plan include actions such as deciding what to take with you if you leave, ensuring you have the right equipment for defending your home and allocating responsibilities to members of a household. The post-campaign evaluation showed that the campaign did not achieve an increase against this objective for people who planned to stay and defend their property rather than leave.

Exhibit 8: Campaign objectives and results
Campaign objectives Does the post-campaign evaluation show increases against the objective?
1. Continue to increase the number of people that have discussed and/or written a plan with regards to what they will do in the event of a fire.
2. Of those who indicate they have a plan, increase the number of people who have included two or more elements from the Guide to Making a Bush Fire Survival Plan:  
  • for those who plan to leave
  • for those who plan to stay and defend.
3. Increase the frequency in completing preparation activities around a person’s property.
4. Increase the number of people who correctly assess it is their responsibility to complete preparation activities and enact their plan without direct intervention from emergency services.
5. Visits to MyFirePlan website.
Key
Yes
No

Source: NSW Rural Fire Service. Audit Office analysis.

NSW Rural Fire Service achieved cost efficiencies by reusing creative content developed in the first year of the campaign

Total creative and production costs incurred in year one of the campaign were $1.08 million. Rather than commissioning new creative materials, NSW Rural Fire Service re-used the same creative content in year two of the campaign. NSW Rural Fire Service incurred $100,000 in creative and production costs in year two of the campaign and achieved cost-efficiencies by reusing the same creative developed in the prior year.

NSW Rural Fire Service allowed sufficient time for cost-efficient media placement and received free media placements

The Department of Customer Service advises agencies to work with media contacts to book media in advance to ensure a cost-efficient placement. Prior to 2019–20, the Department of Premier and Cabinet provided suggested timeframes for agencies to book media as part of the peer review process. For example, it advised agencies to book television six to 12 weeks in advance and book radio advertising two to eight weeks in advance. NSW Rural Fire Service allowed sufficient time for a cost-efficient media placement.

NSW Rural Fire Service received $4 million of free advertising time and space donated by media companies due to the extent and impact of the 2019–20 fire season.

The cost benefit analysis (CBA) did not assess the costs and benefits of alternatives to advertising

Under the Government Advertising Act 2011, agencies are required to prepare a CBA when the cost of the campaign is likely to exceed $1 million. As part of the CBA, the Government Advertising Guidelines require agencies to consider options other than advertising to achieve the desired objective including a comparison of costs and benefits.

The CBA for the Fireproof campaign (year two) notes that the proposed campaign is one component of a broader community engagement strategy which has been developed over time and is based on research and evaluation. The CBA considers two options to achieve the objectives of the campaign. The first option is community engagement activities without an advertising campaign and the second option is community engagement activities alongside an advertising campaign. The CBA does not identify and assess the costs and benefits of both of the options in order to assess the most cost-efficient option.

This is a repeat finding from two previous government advertising audits. The report ‘Government Advertising: 2015–16 and 2016–17’ found that both agencies subject to the audit did not meet the requirements in the guidelines to consider alternatives to advertising. The report made a recommendation to the Department of Premier and Cabinet to work with Treasury to ensure the requirements of the guidelines are fully reflected in the 'Cost-Benefit Analysis Framework for Government Advertising and Information Campaigns'. The report ‘Government advertising 2017–18’ found that one agency subject to the audit did not identify to what extent the benefits could be achieved without advertising, nor did it consider alternatives to advertising which could achieve the same impact as the advertising campaign.

Appendix one – Responses from agencies

Appendix two – About the campaigns

Appendix three – About the audit

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #342 - released 19 November 2020

Published

Actions for Health capital works

Health capital works

Health
Compliance
Infrastructure
Procurement
Project management

This report examines whether NSW Health effectively planned and delivered major capital works to meet the demand for health services in New South Wales.

The report found that NSW Health has substantially expanded health infrastructure across New South Wales since 2015. However, the program was driven by Local Health District priorities without assessment of the State’s broader and future‑focussed health requirements.

The report found that unclear decision making roles and responsibilities between Health Infrastructure and the Ministry of Health limited the ability of NSW Health to effectively test and analyse investment options.

Project delays and budget overruns on some major projects indicate that Health Infrastructure's project governance, risk assessment and management systems could be improved.

The Auditor‑General recommends that NSW Health ensure its capital projects offer the greatest value to New South Wales by establishing effective policy guidance and enhancing project governance and management systems.

Read full report (PDF)

Since 2011–12, NSW Health has aimed to improve its facilities and build 'future focused' infrastructure. The NSW Government’s 2015–16 election commitments established a four-year $5.0 billion capital program for NSW Health to build and upgrade more than 60 hospitals and health services. The 2019–20 State Budget committed a further $10.1 billion over four years for another 29 projects. This is the largest investment to date on health capital works in New South Wales.

Recent reviews of infrastructure have recognised that population and demographic growth will require a change in the delivery and composition of health infrastructure, including considering greater use of non-traditional, non-capital health service options and assets.

To ensure that expenditure on capital works represents the best value for money, NSW Health's business cases need to be robust and supported by evidence that demonstrates they are worthy investments. The NSW Process of Facility Planning has been the main framework guiding the detailed planning and development of NSW Health's capital works proposals. This framework was developed by the then NSW Department of Health in 2010. Its aim is to ensure investment proposals are supported by rigorous planning processes that address health service needs and provide value for money.

Infrastructure projects of the complexity and scale being delivered by NSW Health carry inherent risks. For example, unplanned cost escalations can potentially impact on the State’s finances. Unforeseen delays can also reduce the intended benefits. The growth in the State’s health capital spend and project profile, means its exposure to such risks has increased over time.

The objective of this audit was to assess the effectiveness of planning and delivery of major capital works to meet demand for health services in New South Wales. To address this objective, the audit examined whether:

  • the Ministry of Health has effective procedures for planning and prioritising investments in major health capital works
  • Health Infrastructure develops robust business cases for initiated major capital works that reliably inform government decision making
  • Health Infrastructure has effective project governance and management systems that support delivering projects on-time, within budget and achievement of intended benefits.

The audit focused on the Ministry of Health and Health Infrastructure – being the lead agencies within NSW Health responsible for prioritising, planning and delivering major health capital works across the State. The audit examined 13 business cases for eight discrete projects over a ten-year period.

Conclusion

NSW Health has substantially expanded health infrastructure across New South Wales since 2015. However, its planning and prioritisation processes were not assessed against a long-term statewide health infrastructure plan and lacked rigorous assessment against non-capital options creating a risk that they do not maximise value for New South Wales.

The scale of NSW Health's capital investment is significant and has grown substantially in recent years. The NSW Government’s election commitments in 2015–16 and 2019–20 collectively set out a $15.0 billion capital program to build and upgrade 89 hospitals and health services. NSW Health developed this infrastructure program in the absence of a statewide health infrastructure strategy and investment framework to focus its planning and decisions on the types of capital investments required to meet the long-term needs of the NSW health system.

Consequently, locally focused priorities of the State’s 17 Local Health Districts have been the primary drivers of NSW Health’s capital investments since 2015–16. Local Health District investment proposals for hospitals were developed without consideration of alternative health options such as community health service models, technology-driven eHealth care, or private sector options. Without rigorous assessment against a range of potential health service options, there is a risk that selected projects do not maximise value for New South Wales.

In recognition of the need for a statewide approach to infrastructure planning, the Ministry of Health recently developed a 20-year Health Infrastructure Strategy and prioritisation framework in 2019. The strategy was approved by the NSW Government in April 2020.

NSW Health's ability to effectively test and analyse its capital investment options has been compromised by unclear decision-making roles and responsibilities between its Health Infrastructure and the Ministry of Health agencies.

While both Health Infrastructure and the Ministry of Health have responsibilities for the assessment of business cases for proposed infrastructure projects, confusion about the roles of each agency at key steps compromised the efficacy of the process. Health Infrastructure and the Ministry of Health have differing views about which agency is responsible for testing business case inputs and conducting comprehensive options appraisals.

As a result of this confusion, Health Infrastructure and the Ministry of Health did not rigorously test Local Health District capital investment proposals against defined statewide health infrastructure investment priorities. The NSW Process of Facility Planning does not clarify the responsibilities of all parties in validating and prioritising Local Health District's Clinical Service Plans and progressing them to business cases.

NSW Health's infrastructure priorities are not sufficiently supported by transparent documentation of selection methodology and the rationale for decisions. Consequently, there is a risk that recommended options, whilst having some economic and health service merit, do not represent the greatest value.

Substantial delays and budget overruns on some major projects indicate that Health Infrastructure's project governance, risk assessment and management systems could be improved.

Health Infrastructure did not fully comply with NSW Government guidelines for developing business cases and making economic appraisals for proposed capital investments. These weaknesses, along with delays and budget overruns on some projects, demonstrate a need for Health Infrastructure to strengthen its project governance, management and quality control systems.

 

Over the period of review, NSW Government policies for business case development and submission have emphasised that effective governance arrangements are critical to a proposal's successful implementation.

NSW Health's Process of Facility Planning similarly highlights the importance of effective governance and project management for achieving good outcomes. It prescribes a general governance structure managed by Health Infrastructure that can be tailored to the planning and delivery of health infrastructure projects greater than $10.0 million.

Project challenges indicate opportunities for strengthening governance and project management

The three major hospital redevelopments examined in metropolitan, regional and rural areas had a combined Estimated Total Cost of more than $1.2 billion and comprised eight discrete projects and 13 separate business cases.

Almost all these projects experienced delivery challenges which impacted achievement of their original objectives and intended benefits. This is expected in complex and large-scale health infrastructure programs. However, in some projects the impacts were significant and resulted in substantial delays, unforeseen costs, and diversion of resources from other priority areas.

Our review of the selected case studies highlighted opportunities for enhancing governance and project management. Specifically, it indicates a need for improving transparency in the management of contingencies, risk management and assessments particularly relating to adverse site conditions and the selection of contractors. There is also a need to strengthen forward planning for options to address unfunded priorities within business cases that risk complicating the delivery of future project stages resulting in unforeseen costs and potentially avoidable budget overruns.

Need for increased transparency and accountability in the management of contingency funds

In February 2017, the Ministry's Capital Strategy Group approved the use of surplus funds of $13.76 million from Stage 1 of the Hornsby Ku-ring-gai Hospital Redevelopment for new works deemed needed to support Stage 2. Following this decision, Health Infrastructure finalised and submitted a business case addendum for Stage 1 to the Ministry in March 2017, addressing the new works comprising a two-storey building for medical imaging and paediatric floors. The business case addendum also addressed options to fit out and procure major medical imaging equipment. The Ministry approved the Stage 1 business case in July 2017, noting the Ministry's Capital Strategy Group had already approved the use of remaining Stage 1 funds to deliver the new works.

Stage 1 was completed in 2015, almost two years before the Stage 1 business case addendum was prepared in February 2017.

The Ministry's decision to approve the new works using $13.76 million of surplus Stage 1 funds did not comply with the NSW Treasury Circular TC 12/20. This policy establishes the Treasurer's approval must be sought and received before a new capital project with an Estimated Total Cost of $5.0 million or more can be approved by NSW Health. The Ministry therefore exceeded its delegated authority in making this decision, as it was not evident it had sought and received the Treasurer's approval prior to doing so.

Consequently, the surplus Stage 1 funds should not have been used by the Ministry to deliver new works in the circumstances. Instead, they should have been released from the Stage 1 project in accordance with established NSW Health procedures, and the Stage 1 Estimated Total Cost revised down accordingly. This did not occur, and NSW Health ultimately directed $11.0 million in surplus Stage 1 funds to the new works.

These circumstances indicate a need to strengthen transparency and accountability within NSW Health for the approval of new projects, and how contingency funds are used in the management of major health capital works. They also demonstrate the impact of weaknesses with options appraisal as the initial Stage 1 business case did not consider alternative options for addressing the initially unfunded works later covered by the Stage 1 business case addendum and ultimately funded from the Stage 1 contingency provision.

Weaknesses in service delivery planning resulted in unaccounted-for costs

In addition to proposing the above-noted new works, the 2017 Stage 1 Business Case Addendum for the Hornsby-Ku-ring-gai development sought to retrospectively address the estimated funding gap of around $14.0 million for the internal fit out, supply of major medical imaging equipment, and cost to operate the medical imaging service at Hornsby Ku-ring-gai Hospital also not addressed in the originally Stage 1 business case.

The Stage 1 business case addendum considered various procurement options to purchase and run the medical imaging services ranging from State operation purchase options to private operation purchase options.

It recommended outsourcing the operation and provision of equipment to the private sector based on estimated savings to the public sector initially of around $650,000 per annum reducing over time to $270,000. The Ministry endorsed this option in June 2017, but it did not ultimately proceed.

A July 2018 report to the Executive Steering Committee on the project shows NSW Health later decided to deliver operation of the medical imaging unit 'traditionally' with an updated estimate of the cost at approximately $16.4 million. The report also shows the Ministry supported the costs now being met by the Northern Sydney Local Health District.

This means the funding gap previously identified in the Stage 1 business case addendum for fitting out the medical imaging building and supply of major medical equipment would need to be met fully by the State, representing a $16.4 million cost overrun for the project.

Examined reports to the Executive Steering Committee show this was largely funded by the Northern Sydney Local Health District via the disposal of land realising approximately $15.0 million in proceeds.

This initially unforeseen cost, along with the additional $11.0 million for the new works approved under the Stage 1 business case addendum, were ultimately merged with the Stage 2 project initially approved in 2017–18 with an Estimated Total Cost of $200 million.

The extent of budget variation on the Hornsby Kur-ring-gai development has not been transparent

The 2019–20 State Budget provided an additional $65.0 million for a further Stage 2A to deliver additional built capacity to support outpatient services, enhanced allied health services, re-housed community health services and the delivery of prioritised clinical services unfunded as part of Stage 2. The funds were approved based on an Investment Decision Template (IDT) that examined two options in addition to the base case representing scoping alternatives to the preferred master planned capital solution.

However, we found the IDT showed around 23 per cent of the $65.0 million sought (i.e. $15.0 million) was to be allocated to fund the deficit in Stage 2, which had arisen as a result of project delays due to adverse site conditions. This was not discussed in the IDT.

The February 2020 report to the Executive Steering Committee shows a combined Stage 2 and 2A final forecast cost of $292.6 million against a potential budget of $290.7 million representing an overall deficit for the project of around 0.6 per cent.

However, this favourable final budget position does not transparently show the funding challenges experienced over the project's implementation to-date. The three major budget issues include:

  • inappropriate use of around $11.0 million in Stage 1 contingency for originally unfunded works contrary to Treasury policy
  • the additional $16.4 million cost unforeseen in the Stage 1 business case for delivering medical imaging services mostly funded through the sale of land
  • an additional $15.0 million from Stage 2A to cover the budget overrun in Stage 2 due to adverse site conditions.

The cumulative impact of these events is that Stages 1 and 2 of the Hornsby project cost approximately $42.4 million than it should have in the circumstances around 14 per cent more than what the revised combined Estimated Total Cost for both stages should have been after releasing the $11.0 million in surplus Stage 1 funds, with Stage 2 delayed by around 14 months.

Opportunity for strengthening risk management for adverse site conditions

Major construction projects often experience adverse site conditions which can be difficult to fully detect in advance. However, we found this was a common occurrence in the projects we examined sometimes with significant time and/or budget impacts indicating scope to enhance related risk and cost assessments. Specifically:

  • Hornsby Ku-ring-gai Hospital Redevelopment Stage 2: adverse site conditions during demolition works resulted in an 11-month delay for delivering the medical imaging unit and 14-month delay completing Stage 2 main works including need for additional $15.0 million in funds to cover the resultant budget deficit for the project.
  • Blacktown Mt Druitt Hospital Redevelopment Stage 2: adverse site conditions combined with project complexity delayed completion of the early works by approximately five months. This contributed to the delay in completing the main construction works which occurred around nine months later than planned in the business case.
  • Dubbo Health Service Redevelopment Stages 3 and 4: Health Infrastructure advised adverse site conditions including asbestos containing materials and ground conditions delayed works for the main building with completion forecast for March 2021, around 21 months later than planned in the final business case. This resulted in the need for additional $13.5 million to cover increased construction costs and risks, increasing the Stage 3 and 4 forecast final cost from $150 million to $163.5 million as at February 2020.

These examples indicate a risk the cumulative impact of adverse site conditions may be substantial when measured across both time and Health Infrastructure's full delivery program. They also point to potential for Health Infrastructure to achieve efficiencies and improved outcomes from strengthening its approach to assessing and mitigating the risks from adverse site conditions.

Limited due diligence with prospective contractors risks avoidable delays and costs

Main construction works on Stage 1 of the Dubbo Health Service Redevelopment were completed in October 2015, approximately 13 months later than planned in the final business case. Delays were mainly due to insolvency of the early works contractor resulting in their departure from the project. The ensuing 11-month delay in completing the early works significantly impacted the overall schedule and delivery of main construction works.

The insolvency event was significant as it affected nine separate Health Infrastructure projects – three of which had yet to reach practical completion. It also affected state-funded projects in other sectors. It resulted in the need for additional funding of $11.5 million that was provided in the 2014–15 State Budget increasing the total Stage 1 and 2 budget from $79.8 million to $91.3 million.

Health Infrastructure’s analysis of lessons learned shows it worked actively to mitigate the impacts of the insolvency event across all affected projects. However, it also indicates a risk the lessons were mainly focused on mitigating the impacts after an insolvency event occurred rather than on prevention.

Although Health Infrastructure initially commissioned a financial assessment of the now insolvent early works contractor before engagement, it did not detect any risks of the impending insolvency and instead concluded the contractor was in a strong financial position. However, the contractor became insolvent shortly after commencement approximately seven months later. This indicates a risk of weaknesses in the assessment performed that was not explicitly addressed by the lessons learned.

Delivery of the main construction works were further impacted by disputes with the main works contractor over the scope of works for the renal unit resulting in Health Infrastructure terminating the contract in November 2016 following lengthy negotiations over several months.

The scope of works relating to the renal unit were ultimately transferred to Stages 3 and 4 and were delivered in December 2019, around five years later than originally planned in the business case.

Health Infrastructure advised the delay was ultimately beneficial to the project because the refurbishment works for the renal unit, initially scheduled for Stages 1 and 2, would have been demolished to accommodate the new Western Cancer Centre proposed after Stages 1 and 2 and currently being delivered in parallel with Stages 3 and 4.

Health Infrastructure advised the actual cost of Stages 1 and 2 was $84.7 million against the budget of $91.3 million. The residual $6.6 million relates to the renal works not delivered during Stage 1 and 2 and transferred to Stage 3 and 4.

Health Infrastructure advised the contractual provisions for mitigating insolvency events 'in-flight' are limited highlighting the importance of proactive and effective due diligence prior to engaging contractors for significant construction projects.

Need for a quality framework linked to staff training and capability development

Health Infrastructure's 2017-20 Corporate Plan identifies the development of a quality framework to support delivery of future-focused outcomes as a key organisational priority. Related initiatives within the Corporate Plan describe a framework underpinned by a Quality Committee providing advice on:

  • records management, to meet the requirements of the State Records Act 1998
  • project assurance, to ensure future focused outcomes and enhance Health Infrastructure's Standards, Policies, Procedures and Guidelines, Templates and Design Guidance Notes
  • knowledge management and library services, to promote and leverage from project learnings.

Although Health Infrastructure has some elements of a quality framework it is not yet fully in place. Health Infrastructure advised it had yet to establish the quality framework and related committee described in its Corporate Plan due in part to its focus on responding to the growth of its capital program.

Health Infrastructure's Development and Innovation team has been active in supporting continuous improvement in knowledge and project management including development of business cases. Although useful, these initiatives have relied heavily on leveraging and disseminating insights from Gateway reviews and have not formed part of a systematic quality and continuous improvement framework.

The limited focus on the quality of business cases is reflected in internal performance monitoring and reporting which focuses mainly on tracking the delivery of projects against internal benchmarks, often revised from the baselines in the business case, and expenditure against cashflow targets. There is no evident internal monitoring and/or reporting to the Chief Executive and Board on defined quality metrics linked to business case development and staff capability.

Performance reporting on balanced scorecard metrics has similarly focused mainly on process rather than quality and has been inconsistent in recent years.

Appendix one – Response from agency

Appendix two – About the audit

Appendix three – Performance auditing

Appendix four – Ministry of Health planning tools and guidelines

Appendix five – Streamlined investment decision process for Health Capital Projects

Appendix six – Timeline of business cases and relevant policy guidelines

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #338 - released 12 August 2020

Published

Actions for Universities 2019 audits

Universities 2019 audits

Universities
Cyber security
Financial reporting
Internal controls and governance
Procurement

This report contains findings on the results of financial audits of NSW universities for the year ended 31 December 2019.

All ten NSW universities received unqualified audit opinions. The 2019 financial results for universities are reported as at 31 December and reflect results from operations before the impact of the COVID‑19 pandemic.

The combined revenues for all NSW universities increased by $381 million to $11.4 billion in 2019, driven by increases in student revenues. Revenue from overseas students continued to grow faster than that from domestic students and contributed $3.6 billion in course fees to NSW universities in 2019.

Overseas students from the top three countries of origin, being China, India and Nepal, represented 72.4 per cent of all enrolments of overseas students and 65.4 per cent of all overseas student revenues for 2019. Revenue from students from these three countries comprised 40.9 per cent of total student revenues for all NSW universities, creating a considerable concentration risk for NSW universities.

The COVID‑19 pandemic may significantly impact the financial results of NSW universities in 2020. NSW universities provided data on COVID‑19 impacted student enrolments for semester one 2020. Overall numbers of student enrolments in semester one 2020 were 5.8 per cent beneath projections. Overseas student enrolments were 13.8 per cent beneath expectations and domestic student enrolments were 2.4 per cent below expectations.

The report makes recommendations to the NSW universities, aimed at strengthening controls over information technology, cyber security, validating published performance information, procurement practices and the oversight of their overseas controlled entities' legal and policy compliance functions.

Read full report (PDF)

This report analyses the results of our audits of the financial statements of the ten NSW universities for the year ended 31 December 2019. The table below summarises our key observations.

1. Financial reporting

Financial reporting

The 2019 financial statements of all ten NSW universities received unmodified audit opinions.

One controlled entity of the Western Sydney University received a qualified audit opinion.

Five NSW universities finalised their audited financial statements this year on or before the date they did last year.

New accounting standards, which changed how universities report income and treat operating leases, became effective from 1 January 2019.

Sources of revenue from operations

Government grants as a proportion of the total income of NSW universities continued to decrease.

Fee revenue from overseas students continued to grow faster than fees from domestic students. Forty-one per cent of NSW universities' total student revenue came from overseas students from three countries.

Five NSW universities increased the proportion of revenue they receive from overseas students from a single country. Two universities sourced over 73 per cent of their total overseas student revenue from students from a single country of origin in 2019.

Other revenues Two universities attracted over 69.5 per cent of the total philanthropic revenue of $174 million received by all NSW universities in 2019.
Operating expenditures Combined total operating expenditure for NSW universities increased to $9.9 billion in 2019, a rise of 5.2 per cent from 2018.
Current ratio At 31 December 2019, five NSW universities had a current ratio of less than one, meaning those universities need to actively manage their cash to meet current obligations.
Controlled entities

All six NSW universities with overseas controlled entities have devolved responsibility for governance and legislative compliance to their overseas controlled entities.

Recommendation (repeat issue): NSW universities should strengthen their governance arrangements to oversight their overseas controlled entities' legal and policy compliance functions.

COVID-19 impacts and responses

The 2019 financial results for universities are reported as at 31 December. Consequently, the results for the 2019 year were unaffected by the impact of the COVID-19 pandemic.

NSW universities provided data on the COVID-19 impacted student enrolments for semester one 2020. Overall numbers of student enrolments were 5.8 per cent beneath projections. Overseas student enrolments were 13.8 per cent beneath expectations and domestic student enrolments were 2.4 per cent beneath expectations.

NSW universities are responding to the challenges presented by COVID-19 by moving course delivery online, expanding student support and introducing cost saving measures.

2. Internal controls and governance

Internal control findings

Our audits identified 108 internal control deficiencies in 2019 (99 in 2018).

Gaps in information technology (IT) controls comprised the majority of these deficiencies. Deficiencies included a lack of sufficient user access reviews, inadequate review and approval of change management processes, and issues with password settings.

We identified one high risk financial control deficiency at the University of New South Wales, which resulted in the University providing for a potential underpayment of casual staff salaries.

NSW universities continue to implement recommendations arising from 35 findings raised in previous years.

Performance reporting

Five NSW universities still do not have formal processes to internally review and validate performance information published in their annual reports.

Recommendation (repeat issue): NSW universities should strengthen processes to review and validate published performance information.

Cyber security

Two universities have not yet implemented a cyber risk policy and three universities have not formally trained staff in cyber awareness.

Recommendation (repeat issue): NSW universities should strengthen cyber security frameworks and controls to protect sensitive data and prevent financial and reputational losses.

Management of IT service providers NSW universities have contracts with vendors to support their computer systems. Five universities have not formally established frameworks to manage these contracts. Poor contract management can compound risks associated with IT control deficiencies.
Data breach management Universities are required to maintain the privacy of sensitive data which, if disclosed or used inappropriately, could result in harm to individuals, financial loss, or loss of intellectual property. Two NSW universities have not established formal policies to manage data breaches.
Procurement

All universities have a procurement policy. Most universities have a documented procurement manual and contact management policy.

Recommendation: NSW universities should review their procurement and contract management policies and procedures to ensure that they are relevant and effective in reducing risk and improving purchasing outcomes.

3. Teaching and research

Graduate employment outcomes Eight out of ten NSW universities exceeded the national average for full-time employment rates of their undergraduates in 2019. Six universities performed better than the national average for full-time employment outcomes of their postgraduates in 2019.
Student enrolments by field of education Enrolments at NSW universities increased the most in Management and Commerce courses in 2019.
Achieving diversity outcomes

Five universities in 2018 (five in 2017) met the target enrolment rate for students from low socio-economic status (SES) backgrounds.

Eight universities increased enrolments of students from Aboriginal and Torres Strait Islander backgrounds in 2018.

 

This report provides Parliament with the results of our financial audits of New South Wales universities and their controlled entities in 2019, including our analysis, observations and recommendations in the following areas:

  • financial reporting
  • internal controls and governance
  • teaching and research.

Financial reporting is an important element of governance. Confidence and transparency in university sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations on the financial reporting of NSW universities for 2019.

Appropriate and robust internal controls help reduce risks associated with managing finances, compliance and administration of NSW universities.

This chapter outlines the internal controls related observations and insights across NSW universities for 2019, including overall trends in findings, level of risk and implications.

Our audits do not review all aspects of internal controls and governance every year. The more significant issues and risks are included in this chapter. These along with the less significant ones are reported to universities for them to address.

Universities' primary objectives are teaching and research. They invest most of their resources to achieve quality outcomes in academia and student experience. Universities have committed to achieving certain government targets and compete to advance their reputation and international and Australian rankings.

This chapter outlines teaching and research outcomes for NSW universities for 2019.

Appendix one – List of 2019 recommendations

Appendix two – Status of 2018 recommendations

Appendix three – NSW universities’ controlled entities and associated entities

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Funding enhancements for police technology

Funding enhancements for police technology

Justice
Community Services
Information technology
Management and administration
Procurement
Project management

This report focuses on how the NSW Police Force managed a $100 million program to acquire new technology. The program invested in technologies intended to make police work safer and quicker. These included body-worn video (BWV) cameras, smart phone devices, mobile fingerprint scanners and hand-held drug testing devices.

The audit found that while the NSW Police Force mostly managed the ‘Policing for Tomorrow’ program effectively, investment decision making could be improved in the future. The NSW Police Force missed an opportunity to take a whole-of-organisation approach to identify capability gaps and target the acquired technologies to plug these.

The NSW Police Force has processes in place to monitor the benefits of some of the larger technology, but it does not do this consistently for all procured technology. It could not demonstrate that smaller projects are improving the efficiency or effectiveness of policing.

The audit also found that the NSW Police Force does not routinely engage with external stakeholders on the use or impacts of new technology that changes how officers interact with the public, noting that this will not always be possible for particularly sensitive procurements that involve covert technologies or methodologies.

The Auditor-General made three recommendations to guide improvement of NSW Police Force ICT procurement, benefits management and stakeholder engagement processes.

Read full report (PDF)

Ahead of the March 2015 election, the NSW Government announced a $100 million Policing for Tomorrow fund for the NSW Police Force to acquire technology intended to make police work safer and quicker. The announcement committed the NSW Police Force to several investment priorities, including body-worn video (BWV) cameras, smart phone devices (MobiPOL), mobile fingerprint scanners and hand-held drug testing devices. Otherwise, the NSW Police Force was allowed flexibility in identifying and resourcing suitable projects.

This audit assessed whether the Policing for Tomorrow fund was effectively managed to improve policing in New South Wales. We addressed the audit objective with the following audit questions:

  • Did the NSW Police Force efficiently and effectively identify, acquire, implement and maintain technology resourced by the fund?
  • Did the NSW Police Force establish effective governance arrangements for administering the fund, and for monitoring expected benefits and unintended consequences?
  • Did technology implemented under the fund improve the efficiency and effectiveness of policing in New South Wales?

Conclusion

The NSW Police Force's management of the Policing for Tomorrow fund was mostly effective. There are measures in place to assess the impact of the technologies on the efficiency and effectiveness of policing in NSW. However, these measures are not in place for all technologies funded by Policing for Tomorrow. A strategic whole-of-organisation approach to identifying and filling technology capability gaps may have assisted in better targeting funds and managing expected benefits.

The NSW Police Force identified, acquired, implemented and maintained a range of technologies resourced by the fund in an efficient and effective way. The election announcement committed the NSW Police Force to four specific projects which made up over three quarters of the fund value. Investment decisions for remaining funds were driven by the availability of funding and individual technology requirements rather than targeting improved policing outcomes and the capability necessary to achieve these.

The NSW Police Force missed an opportunity to take a whole-of-organisation approach to selecting technology projects for the remainder of the funds where it had discretion. This may have included considering less obvious back office technology or making different investment decisions driven by gaps in the agency's technology capabilities.

The NSW Police Force used effective governance arrangements for administering the Policing for Tomorrow fund, including using its existing ICT Executive Board. The NSW Police Force has adequate processes in place to drive benefits and monitor the impact of technology on the efficiency and effectiveness of policing for the larger projects funded by Policing for Tomorrow. Further work is required to ensure this for smaller projects.

The NSW Police Force tends to consider only impacts on the organisation in managing benefits and identifying unintended consequences. It does not routinely engage proactively with stakeholders, including partner criminal justice agencies and members of the community, on new technology that changes how police interact with the public.

We examined how effectively the NSW Police Force governed the Policing for Tomorrow fund, to ensure that key accountability and decision-making arrangements were in place to direct the $100 million spend to appropriate technologies. We also assessed how the NSW Police Force acquired, implemented and maintained technology funded by Policing for Tomorrow to determine the effectiveness of the relevant asset management.

The Policing for Tomorrow election commitment aimed to invest in technology to ‘make police work safer and quicker – meaning more time on the street combatting crime’. We assessed whether the NSW Police Force ensured that funded technologies have improved policing efficiency and effectiveness. We did not seek to independently assure the benefits or outcomes resulting from the technologies.

Appendix one – Response from agency

Appendix two – Policing for Tomorrow projects and expenditure

Appendix three – About the audit

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #334 - released 2 June 2020

Published

Actions for Family and Community Services 2018

Family and Community Services 2018

Community Services
Compliance
Financial reporting
Information technology
Management and administration
Project management
Risk
Service delivery
Workforce and capability

The Auditor-General for New South Wales, Margaret Crawford released her report today on the Family and Community Services cluster. The report focuses on key observations and findings from the most recent financial audits of agencies in the cluster. Cluster entities received unqualified audit opinions for their 30 June 2018 financial statements. Opportunities to improve the quality of financial reporting were identified and reported to management.

This report analyses the results of our audits of financial statements of the Family and Community Services cluster for the year ended 30 June 2018. The table below summarises our key observations.

This report provides NSW Parliament and other users of the financial statements of Family and Community Services' agencies with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations
  • service delivery.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Family and Community Services cluster for 2018.

Observation Conclusions and recommendations
2.1 Quality of financial reporting
Unqualified audit opinions were issued for all cluster agencies' financial statements. Conclusion: Sufficient audit evidence was obtained to conclude the financial statements were free of material misstatement.
Agencies complied with NSW Treasury’s mandatory early close requirements.

Completing other early close procedures was inconsistent and not always supported by adequate evidence.
Conclusion: There are opportunities for agencies to improve the quality of financial reporting by:
  • documenting all significant judgements and assumptions used when preparing the financial statements
  • regularly reconciling inter-agency balances and transactions
  • reconciling key account balances on a timely basis
  • quantifying the impact of new and revised accounting standards.
2.2 Timeliness of financial reporting
Agencies completed revaluations of property, plant and equipment and submitted 31 March 2018 financial statements by the due date as required by NSW Treasury.

Agencies submitted year-end financial statements by the statutory deadline.
Conclusion: Early revaluations of property, plant and equipment contributes to agencies meeting the year-end statutory reporting deadline.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from:

  • our financial statement audits of agencies in the Family and Community Services cluster for 2018
  • the areas of focus identified in the Audit Office annual work program.

The Audit Office Annual Work Program provides a summary of all audits to be conducted within the proposed time period as well as detailed information on the areas of focus for each NSW Government cluster.

Observation Conclusions and recommendations
3.1 Internal controls
The 2017–18 audits reported 47 internal control weaknesses. While none were high risk, there were 15 repeat issues.

Conclusion: Management accepted audit findings and advised they are actioning recommendations. Timely action is important to ensure internal controls operate effectively.

Twenty-two of these internal control weaknesses related to information technology processes and control environment. Conclusion: Control weaknesses in information systems may compromise the integrity and security of financial data used for decision making and financial reporting.

Recommendation: Agencies should strengthen user access administration to prevent inappropriate access to key IT systems by:
  • ensuring privileged user access is limited to those requiring access to maintain the IT systems
  • monitoring privileged user access to address risks from unauthorised activity
  • ensuring IT password settings comply with password policies
  • ensuring timely removal of access to business systems for terminated and casual employees.
The Department, NSW Land and Housing Corporation (LAHC) and three other cluster agencies’ contract registers are incomplete and/or inaccurate. Recommendation: Agencies should ensure their contract registers are complete and accurate so they can more effectively govern contracts and manage compliance obligations.
3.2 Audit Office annual work program
Financial impact of the commissioning approach.

The transfer of disability services to the National Disability Insurance Scheme and other commissioning of service delivery has contributed to a 36 per cent decrease in frontline employee numbers since 2015–16. Similarly, corporate services’ employee numbers reduced by 34 per cent.

The Department’s salary costs have reduced by $232 million or 18 per cent from 2016–17.
Conclusion: The ratio of corporate services employee numbers to support frontline and support services has remained at 1:10 since 2015–16, which indicates restructures have been planned to align with the transfer of disability services.
Impact of the new social housing maintenance contract

Maintenance expenses have increased by about 40 per cent since the new maintenance contract commenced in April 2016. LAHC measures the benefits of the new maintenance contract such as improved tenant satisfaction.
Conclusion: The new maintenance contract has contributed to some positive social outcomes such as tenants being employed by the contractors to conduct maintenance, as call centre operators and in administration. However, more can be done to ensure value for money is being achieved.
ChildStory IT Project

Whilst phase one of the ChildStory IT project went 'live' in 2017–18, the planned timetable has not been met and the revised date for full implementation is end of 2018.

According to the 2014–15 NSW Budget, the budget for ChildStory was $100 million over a four-year period. During the design and implementation stage, this amount was revised to $128 million, with approval of the Expenditure Review Committee. The actual cost incurred over the four years until 30 June 2018, is approximately $131 million.

We identified issues with the data migration from the legacy systems to ChildStory.
Conclusion: To inform future IT projects, we understand the Department is capturing our findings, along with the findings from the Department of Finance, Services and Innovation’s ‘Healthchecks’.

This chapter outlines certain service delivery outcomes for 2017–18. The data on activity levels and performance is provided by Cluster agencies. The Audit Office does not have a specific mandate to audit performance information. Accordingly, the information in this chapter is unaudited.

In our recent performance audit, Progress and measurement of Premier's Priorities, we identified 12 limitations of performance measurement and performance data. We recommended that the Department of Premier and Cabinet ensure that processes to check and verify data are in place for all agency data sources.

Published

Actions for Internal Controls and Governance 2018

Internal Controls and Governance 2018

Education
Community Services
Finance
Health
Industry
Justice
Planning
Premier and Cabinet
Transport
Treasury
Whole of Government
Environment
Compliance
Cyber security
Financial reporting
Fraud
Information technology
Internal controls and governance
Management and administration
Procurement
Project management

The Auditor-General for New South Wales Margaret Crawford found that as NSW state government agencies’ digital footprint increases they need to do more to address new and emerging information technology (IT) risks. This is one of the key findings to emerge from the second stand-alone report on internal controls and governance of the 40 largest NSW state government agencies.

This report analyses the internal controls and governance of the 40 largest agencies in the NSW public sector for the year ended 30 June 2018.

This report covers the findings and recommendations from our 2017–18 financial audits that relate to internal controls and governance at the 40 largest agencies (refer to Appendix three) in the NSW public sector.

This report offers insights into internal controls and governance in the NSW public sector

This is our second report dedicated to internal controls and governance at NSW State Government agencies. The report provides insights into the effectiveness of controls and governance processes in the NSW public sector by:

  • highlighting the potential risks posed by weaknesses in controls and governance processes
  • helping agencies benchmark the adequacy of their processes against their peers
  • focusing on new and emerging risks, and the internal controls and governance processes that might address those risks.

Without strong governance systems and internal controls, agencies increase the risks associated with effectively managing their finances and delivering services to citizens. The way agencies deliver services increasingly relies on contracts and partnerships with the private sector. Many of these arrangements deliver front line services, but others provide less visible back office support. For example, an agency may rely on an IT service provider to manage a key system used to provide services to the community. The contract and service level agreements are only truly effective where they are actively managed to reduce risks to continuous quality service delivery, such as interruptions caused by system outages, cyber security attacks and data security breaches.

Our audits do not review all aspects of internal controls and governance every year. We select a range of measures, and report on those that present heightened risks for agencies to mitigate. This report divides these into the following five areas:

  1. Internal control trends
  2. Information technology (IT), including IT vendor management
  3. Transparency and performance reporting
  4. Management of purchasing cards and taxis
  5. Fraud and corruption control.

The findings in this report should not be used to draw conclusions on the effectiveness of individual agency control environments and governance arrangements. Specific financial reporting, controls and service delivery comments are included in the individual 2018 cluster financial audit reports, which will be tabled in Parliament from November to December 2018.

The focus of the report has changed since last year

Last year's report topics included asset management, ethics and conduct, and risk management. We are reporting on new topics this year. We plan to introduce new topics and re-visit our previous topics in subsequent reports on a cyclical basis. This will provide a baseline against which to measure the NSW public sectors’ progress in implementing appropriate internal controls and governance processes to mitigate existing, new and emerging risks in the public sector.

Agencies selected for the volume account for 95 per cent of the state's expenditure

While we have covered only 40 agencies in this report, those selected are a large enough group to identify common issues and insights. They represent about 95 per cent of total expenditure for all NSW public sector agencies.

Internal controls are processes, policies and procedures that help agencies to:

  • operate effectively and efficiently
  • produce reliable financial reports
  • comply with laws and regulations
  • support ethical government.

This chapter outlines the overall trends for agency controls and governance issues, including the number of findings, level of risk and the most common deficiencies we found across agencies. The rest of this volume presents this year’s controls and governance findings in more detail.

Observation Conclusions and recommendations
2.1 High risk findings
We found six high risk findings (seven in 2016–17), one of which was repeated from both last year and 2015–16. Recommendation: Agencies should reduce risk by addressing high risk internal control deficiencies as a priority.
2.2 Common findings
We found several internal controls and governance findings common to multiple agencies. Conclusion: Central agencies or the lead agency in a cluster can play a lead role in helping ensure agency responses to common findings are consistent, timely, efficient and effective.
2.3 New and repeat findings
Although internal control deficiencies decreased over the last four years, this year has seen a 42 per cent increase in internal control deficiencies. The increase in new IT control deficiencies and repeat IT control deficiencies signifies an emerging risk for agencies.
IT control deficiencies feature in this increase, having risen by 63 per cent since last year. The number of repeat IT control deficiencies has doubled and is driven by the increasing digital footprint left by agencies as government prioritises on-line interfaces with citizens, and the number of transactions conducted through digital channels increases

Recommendation: Agencies should reduce IT risks by:

  • assigning ownership of recommendations to address IT control deficiencies, with timeframes and actions plans for implementation
  • ensuring audit and risk committees and agency management regularly monitor the implementation status of recommendations.

 

Government agencies’ financial reporting is now heavily reliant on information technology (IT). IT is also increasingly important to the delivery of agency services. These systems often provide the data to help monitor the efficiency and effectiveness of agency processes and services they deliver. Our audits reviewed whether agencies have effective controls in place to manage both key financial systems and IT service contracts.

Observation Conclusions and recommendations
3.1 Management of IT vendors
Contract management framework 
Although 87 per cent of agencies have a contract management policy to manage IT vendors, one fifth require review.
 

Conclusion: Agencies can more effectively manage IT vendor contracts by developing policies and procedures to ensure vendor management frameworks are kept up to date, plans are in place to manage vendor performance and risk, and compliance with the framework is monitored by:

  • internal audit focusing on key contracting activities
  • experienced officers who are independent of contract administration performing spot checks or peer reviews
  • targeted analysis of data in contract registers.
Contract risk management
Forty-one per cent of agencies are not using contract management plans and do not assess contract risks. Half of the agencies that did assess contract risks, had not updated the risk assessments since the commencement of the contract.
 
Conclusion: Instead of applying a 'set and forget' approach in relation to management of contract risks, agencies should assess risk regularly and develop a plan to actively manage identified risks throughout the contract lifecycle - from negotiation and commencement, to termination.

Performance management
Eighty-six per cent of agencies meet with vendors to discuss performance. 

Only 24 per cent of agencies sought assurance about the accuracy of vendor reporting against KPIs, yet sixty-seven per cent of the IT contracts allow agencies to determine performance based payments and/or penalise underperformance.

Conclusion: Agencies are monitoring IT vendor performance, but could improve outcomes and more effectively manage under-performance by:

  • a more active, rigorous approach to both risk and performance management
  • checking the accuracy of vendor reporting against those KPIs and where appropriate seeking assurance over their accuracy
  • invoking performance based payments clauses in contracts when performance falls below agreed standards.

Transitioning services
Forty-three per cent of the IT vendor contracts did not contain transitioning-out provisions.

Where IT vendor contracts do make provision for transitioning-out, only 28 per cent of agencies have developed a transitioning-out plan with their IT vendor.

Conclusion: Contract transition/phase out clauses and plans can mitigate risks to service disruption, ensure internal controls remain in place, avoid unnecessary costs and reduce the risk of 'vendor lock-in'.
Contract Registers
Eleven out of forty agencies did not have a contract register, or have registers that are not accurate and/or complete.

Conclusion: A contract register helps to manage an agency’s compliance obligations under the Government Information (Public Access) Act 2009 (the GIPA Act). However, it also helps agencies more effectively manage IT vendors by:

  • monitoring contract end dates and contract extensions, and commence new procurements through their central procurement teams in a timely manner
  • managing their contractual commitments, budgeting and cash flow requirements.

Recommendation: Agencies should ensure their contract registers are complete and accurate so they can more effectively govern contracts and manage compliance obligations.

3.2 IT general controls
Governance
Ninety-five per cent of agencies have established policies to manage key IT processes and functions within the agency, with ten per cent of those due for review.
 
Conclusion: Regular review of IT policies ensures risks are considered and appropriate strategies and procedures are implemented to manage these risks on a consistent basis. An absence of policies can lead to ad-hoc responses to risks, and failure to consider emerging IT risks and changes to agency IT environments. 

User access administration
Seventy-two deficiencies were identified related to user access administration, including:

  • thirty issues related to granting user access across 43 per cent of agencies
  • sixteen issues related to removing user access across 30 per cent of agencies
  • twenty-six issues related to periodic reviews of user access across 50 per cent of agencies.
Recommendation: Agencies should strengthen the administration of user access to prevent inappropriate access to key systems.
Privileged access
Forty per cent of agencies do not periodically review logs of the activities of privileged users to identify suspicious or unauthorised activities.

Recommendation: Agencies should:

  • review the number of, and access granted to privileged users, and assess and document the risks associated with their activities
  • monitor user access to address risks from unauthorised activity.
Password controls
Twenty-three per cent of agencies did not comply with their own policy on password parameters.
Recommendation: Agencies should ensure IT password settings comply with their password policies.
Program changes
Fifteen per cent of agencies had deficient IT program change controls mainly related to segregation of duties and authorisation and testing of IT program changes prior to deployment.
Recommendation: Agencies should maintain appropriate segregation of duties in their IT functions and test system changes before they are deployed.

 

This chapter outlines our audit observations, conclusions and recommendations from our review of how agencies reported their performance in their 2016–17 annual reports. The Annual Reports (Statutory Bodies) Regulation 2015 and Annual Reports (Departments) Regulation 2015 (annual reports regulation) currently prescribes the minimum requirements for agency annual reports.

Observation Conclusion or recommendation
4.1 Reporting on performance

Only 57 per cent of agencies linked reporting on performance to their strategic objectives.

The use of targets and reporting performance over time was limited and applied inconsistently.

Conclusion: There is significant disparity in the quality and consistency of how agencies report on their performance in their annual reports. This limits the reliability and transparency of reported performance information.

Agencies could improve performance reporting by clearly linking strategic objectives to reported outcomes, and reporting on performance against targets over time. NSW Treasury may need to provide more guidance to agencies to support consistent and high-quality performance reporting in annual reports.

There is no independent assurance that the performance metrics agencies report in their annual reports are accurate.

Prior performance audits have noted issues related to the collection of performance information. For example, our 2016 Report on Red Tape Reduction highlighted inaccuracies in how the dollar-value of red tape reduction had been reported.

Conclusion: The ability of Parliament and the public to rely on reported information as a relevant and accurate reflection of an agency's performance is limited.

The relevance and accuracy of performance information is enhanced when:

  • policies and guidance support the consistent and accurate collection of data
  • internal review processes and management oversight are effective
  • independent review processes are established to provide effective challenge to the assumptions, judgements and methodology used to collect the reported performance information.
4.2 Reporting on reports

Agency reporting on major projects does not meet the requirements of the annual reports regulation.

Forty-seven per cent of agencies did not report on costs to date and estimated completion dates for major works in progress. Of the 47 per cent of agencies that reported on major works, only one agency reported detail about significant cost overruns, delays, amendments, deferments or cancellations.

NSW Treasury produce an annual report checklist to help agencies comply with their annual report obligations.

Recommendation: Agencies should comply with the annual reports regulation and report on all mandatory fields, including significant cost overruns and delays, for their major works in progress.

The information the annual reports regulation requires agencies to report deals only with major works in progress. There is no requirement to report on completed works.

Sixteen of 30 agencies reported some information on completed major works.

Conclusion: Agencies could improve their transparency if they reported, or were required to report:

  • on both works in progress and projects completed during the year
  • actual costs and completion dates, and forecast completion dates for major works, against original and revised budgets and original expected completion dates
  • explanations for significant cost overruns, delays and key project performance metrics.

 

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency preventative and detective controls over purchasing card and taxi use for 2017–18.

Observation Conclusion or recommendation
5.1 Management of purchasing cards
Volume of credit card spend
Purchasing card expenditure has increased by 76 per cent over the last four years in response to a government review into the cost savings possible from using purchasing cards for low value, high volume procurement.
 
Conclusion: The increasing use of purchasing cards highlights the importance of an effective framework for the use and management of purchasing cards.
Policy framework
We found all agencies that held purchasing cards had a policy in place, but 26 per cent of agencies have not reviewed their purchasing card policy by the scheduled date, or do not have a scheduled revision date stated within their policy.
Recommendation: Agencies should mitigate the risks associated with increased purchasing card use by ensuring policies and purchasing card frameworks remain current and compliant with the core requirements of TPP 17–09 'Use and Management of NSW Government Purchasing Cards'.
Preventative controls
We found that:
  • all agencies maintained purchasing card registers
  • seventy-six per cent provided training to cardholders prior to being issued with a card
  • eighty-nine per cent appointed a program administrator, but only half of these had clearly defined roles and responsibilities
  • thirty-two per cent of agencies place merchant blocks on purchasing cards
  • forty-seven per cent of agencies place geographic restrictions on purchasing cards.

Agencies have designed and implemented preventative controls aimed at deterring the potential misuse of purchasing cards.

Conclusion: Further opportunities exist for agencies to better control the use of purchasing cards, such as:

  • updating purchasing card registers to contain all mandatory fields required by TPP17–09
  • appointing a program administrator for the agency's purchasing card framework and defining their role and responsibility for the function
  • strengthening preventive controls to prevent misuse.

Detective controls
Ninety-two per cent of agencies have designed and implemented at least one control to monitor purchasing card activity.

Major reviews, such as data analytics (29 per cent of agencies) and independent spot checks (49 per cent of agencies) are not widely used.

Agencies have designed and implemented detective controls aimed at identifying potential misuse of purchasing cards.

Conclusion: More effective monitoring using purchasing card data can provide better visibility over spending activity and can be used to:

  • detect misuse and investigate exceptions
  • analyse trends to highlight cost saving opportunities.
5.2 Management of taxis
Policy framework
Thirteen per cent of agencies have not developed and implemented a policy to manage taxi use. In addition:
  • a further 41 per cent of agencies have not reviewed their policies by the scheduled revision date, or do not have a scheduled revision date
  • more than half of all agencies’ policies do not offer alternative travel options. For example, only 36 per cent of policies promoted the use of general Opal cards.
Conclusion: Agencies can promote savings and provide more options to staff where their taxi use policies:
  • limit the circumstances where taxi use is appropriate
  • offer alternate, lower cost options to using taxis, such as general Opal cards and rideshare.
Detective controls
All agencies approve taxi expenditure by expense reimbursement, purchasing card and Cabcharge, and have implemented controls around this approval process. However, beyond this there is minimal monitoring and review activity, such as data monitoring, independent spot checks or internal audit reviews.
Conclusion: Taxi spend at agencies is not significant in terms of its dollar value, but it is significant from a probity perspective. Agencies can better address the probity risk by incorporating taxi use into a broader purchasing card or fraud monitoring program.

 

Fraud and corruption control is one of the 17 key elements of our governance lighthouse. Recent reports from ICAC into state agencies and local government councils highlight the need for effective fraud control and ethical frameworks. Effective frameworks can help protect an agency from events that risk serious reputational damage and financial loss.

Our 2016 Fraud Survey found the NSW Government agencies we surveyed reported 1,077 frauds over the three year period to 30 June 2015. For those frauds where an estimate of losses was made, the reported value exceeded $10.0 million. The report also highlighted that the full extent of fraud in the NSW public sector could be higher than reported because:

  • unreported frauds in organisations can be almost three times the number of reported frauds
  • our 2015 survey did not include all NSW public sector agencies, nor did it include any NSW universities or local councils
  • fraud committed by citizens such as fare evasion and fraudulent state tax self-assessments was not within the scope of our 2015 survey
  • agencies did not estimate a value for 599 of the 1,077 (56 per cent) reported frauds.

Commissioning and outsourcing of services to the private sector and the advancement of digital technology are changing the fraud and corruption risks agencies face. Fraud risk assessments should be updated regularly and in particular where there are changes in agency business models. NSW Treasury Circular TC18-02 NSW Fraud and Corruption Control Policy now requires agencies develop, implement and maintain a fraud and corruption control framework, effective from 1 July 2018. 

Our Fraud Control Improvement Kit provides guidance and practical advice to help organisations implement an effective fraud control framework. The kit is divided into ten attributes. Three key attributes have been assessed below; prevention, detection and notification systems.

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency fraud and corruption controls for 2017–18.

Observation Conclusion or recommendation
6.1 Prevention systems

Prevention systems
Ninety-two per cent of agencies have a fraud control plan in place, 81 per cent maintain a fraud database and 79 per cent report fraud and corruption matters as a standing item on audit and risk committee agendas.

Only 54 per cent of agencies have an employment screening policy and all agencies have IT security policies, but gaps in IT security controls could undermine their policies.

Conclusion: Most agencies have implemented fraud prevention systems to reduce the risk of fraud. However poor IT security along with other gaps in agency prevention systems, such as employment screening practices heightens the risk of fraud and inappropriate use of data.

Agencies can improve their fraud prevention systems by:

  • completing regular fraud risk assessments, embedding fraud risk assessment into their enterprise risk management process and reporting the results of the assessment to the audit and risk committee
  • maintaining a fraud database and reviewing it regularly for systemic issues and reporting a redacted version of the database on the agency's website to inform corruption prevention networks
  • developing policies and procedures for employee screening and benchmarking their current processes against ICAC's publication ‘Strengthening Employment Screening Practices in the NSW Public Sector’
  • developing and maintaining up to date IT security policies and monitoring compliance with the policy.
Twenty-three per cent of agencies were not performing fraud risk assessments and some agency fraud risk assessments may not be as robust as they could be.  Conclusion: Agencies' systems of internal controls may be less effective where new and emerging fraud risks have been overlooked, or known weaknesses have not been rectified.
6.2 Detection systems
Detection systems
Several agencies reported they were developing a data monitoring program, but only 38 per cent of agencies had already implemented a program.
 

Studies have shown data monitoring, whereby entire populations of transactional data are analysed for indicators of fraudulent activity, is one of the most effective methods of early detection. Early detection decreases the duration a fraud remains undetected thereby limiting the extent of losses.

Conclusion: Data monitoring is an effective tool for early detection of fraud and is more effective when informed by a comprehensive fraud risk assessment.

6.3 Notification systems
Notification system
All agencies have notification systems for reporting actual or suspected fraud and corruption. Most agencies provide multiple reporting lines, provide training and publicise options for staff to report actual or suspected fraud and corruption.
Conclusion: Training staff about their obligations and the use of fraud notification systems promotes a fraud-aware culture

 

Published

Actions for Procurement and reporting of consultancy services

Procurement and reporting of consultancy services

Finance
Education
Community Services
Industry
Justice
Planning
Premier and Cabinet
Health
Treasury
Transport
Environment
Information technology

Agencies need to improve their compliance with requirements governing the procurement of consultancy services. These requirements help agencies access procurement savings. Also, some agencies have under-reported consultancy fees in their annual reports for the 2016-17 financial year, according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. The report examined twelve agencies' compliance with procurement and reporting obligations for consultancy services. It notes that it is difficult to quantify total government expenditure on consultants as agencies define ‘consultants’ differently.

NSW Government agencies engage consultants to provide professional advice to inform their decision‑making. The spend on consultants is measured and reported in different ways for different purposes and the absence of a consistently applied definition makes quantification difficult.

The NSW Government’s procurement principles aim to help agencies obtain value for money and be fair, ethical and transparent in their procurement activities. All NSW Government agencies, with the exception of State Owned Corporations, must comply with the NSW Procurement Board’s Direction when engaging suppliers of business advisory services. Business advisory services include consultancy services. NSW Government agencies must disclose certain information about their use of consultants in their annual reports. The table below illustrates the detailed procurement and reporting requirements.

  Relevant guidance Requirements
Procurement of consultancy services PBD 2015 04 Engagement of major suppliers of consultancy and other services (the Direction) including the Standard Commercial Framework
(revised on 31 January 2018, shortly before it was superseded by 'PBD 2018 01')
 
Required agencies to seek the Agency Head or Chief Financial Officer's approval for engagements over $50,000 and report the engagements in the Major Suppliers' Portal (the Portal). 
  PBD 2018 01 Engagement of professional services suppliers
(replaced 'PBD 2015 04' in May 2018)
Requires agencies to seek the Agency Head or Chief Financial Officer's approval for engagements that depart from the Standard Commercial Framework and report the engagements in the Portal. Exhibit 3 in the report includes the key requirements of these three Directions.
 
Reporting of consultancy expenditure Annual Reports (Departments) Regulation 2015 and Annual Reports (Statutory Bodies) Regulation 2015 Requires agencies to disclose, in their annual reports, details of consultants engaged in a reporting year.
  Premier's Memorandum 
'M2002 07 Engagement and Use of Consultants'
 
Outlines additional reporting requirements for agencies to describe the nature and purpose of consultancies in their annual reports.

We examined how 12 agencies complied with their procurement and reporting obligations for consultancy services between 1 July 2016 and 31 March 2018. Participating agencies are listed in Appendix two. We also examined how NSW Procurement supports the functions of the NSW Procurement Board within the Department of Finance, Services and Innovation.

This audit assessed:

  • agency compliance with relevant procurement requirements for their use of consultants
  • agency compliance with disclosure requirements about consultancy expenditure in their annual reports 
  • the effectiveness of the NSW Procurement Board (the Board) in fulfilling its functions to oversee and support agency procurement of consultancy services. 
Conclusion
No participating agency materially complied with procurement requirements when engaging consultancy services. Eight participating agencies under reported consultant fees in their annual reports. The NSW Procurement Board is not fully effective in overseeing and supporting agencies' procurement of consultancy services.
All 12 agencies that we examined did not materially comply with the NSW Procurement Board Direction for the use of consultants between 1 July 2016 and 31 March 2018. 
Eight agencies did not comply with annual reporting requirements in the 2016–17 financial reporting year. Three agencies did not report expenditure on consultants that had been capitalised as part of asset costs, and one agency did not disclose consultancy fees incurred by its subsidiaries. Agencies also defined ‘consultants’ inconsistently.
The NSW Procurement Board's Direction was revised in January 2018, and mandates the use of the Standard Commercial Framework. The Direction aims to drive value for money, reduce administrative costs and simplify the procurement process. In practice, agencies found the Framework challenging to use. To better achieve the Direction’s intent, the Board needs to simplify procurement and compliance processes. 
The Board is yet to publish any statistics or analysis of agencies’ procurement of business advisory services due to issues with the quality of data and systems limitations. Also, the Board’s oversight of agency and supplier compliance with the Framework is limited as it relies on self reporting, and the information provided is insufficient to properly monitor compliance. NSW Procurement is yet to develop an effective procurement and business intelligence system for use by government agencies. Better procurement support, benefit realisation monitoring and reporting by NSW Procurement will help promote value for money in the engagement of consultants.