Reports
Actions for Volume Eight 2015 Family and Community Services
Volume Eight 2015 Family and Community Services
Placement reviews are not undertaken for all children and young people in statutory care. Caseworkers are required to review placements annually to assess the health, wellbeing, education and social life of the child. Over three-quarters of children and young people received placement reviews in 2014-15 compared to about half of them in the previous twelve months.
Actions for Albert 'Tibby' Cotter Walkway
Albert 'Tibby' Cotter Walkway
On 17 September 2015, the Acting Auditor-General of New South Wales, Tony Whitfield, released a report on the Albert ‘Tibby’ Cotter Walkway which crosses over Anzac Parade in Moore Park. The Walkway’s primary function is to cater for event patrons in the precinct. Moore Park is listed on the State Heritage Register and is an open space specifically established to cater for public recreation.
Roads and Maritime Services (RMS) delivered the Walkway to an extremely tight timeframe. It was operational for the 2015 Cricket World Cup at the Sydney Cricket Ground as promised by the government. However, the World Cup deadline added substantially to the total cost of the Walkway, which is projected to be $38 million.
Transport for NSW and RMS could not provide evidence of a compelling economic or financial argument to support the construction of the Walkway or for the tight deadline. Also, the processes they adopted to provide assurance of the project’s value for money were not adequate.
Parliamentary reference - Report number #260 - released 17 September 2015
Actions for Community Housing
Community Housing
On 16 September 2015 the NSW Acting Auditor-General, Tony Whitfield, released a report on community housing. The audit examines the Department of Family and Community Services’ transfer of public housing to non-government community housing providers.
The Department has worked collaboratively with community housing providers and industry groups to develop the community housing sector. Although there have been some delays, it has managed the transfer of public housing reasonably well and has improved the sustainability of the sector.
Parliamentary reference - Report number #259 - released 16 September 2015
Actions for Sydney metropolitan bus contracts
Sydney metropolitan bus contracts
On 9 September 2015, the Acting Auditor-General of New South Wales, Tony Whitfield, released a report on Sydney Metropolitan Bus Service Contracts.
All scheduled bus services in the Sydney metropolitan area are provided under contracts with the public and private operators. The contracts allow Transport for NSW (TfNSW) to determine what bus services are provided and to whom. This audit assessed the effectiveness of TfNSW’s design and management of these contracts.
Bus services provided under the Sydney Metropolitan Bus Service Contracts have largely been effective and efficient. Operators are mostly meeting their key performance indicators. Customer satisfaction is better than under the previous contracts and improving, patronage is increasing, and the unit costs of providing services are now lower than under the previous contracts.
However, punctuality remains a problem. Private operators are mostly starting their trips on time, but rarely meeting their mid and end-of-trip targets. State Transit Authority’s (STA) punctuality is improving but is worse than private operators, and other areas of performance are generally below private operators.
The current situation is a substantial improvement over what we found in our 2010 audit on the previous contracts.
Parliamentary reference - Report number #258 - released 9 September 2015
Actions for Transferring out-of-home care to non-government organisations
Transferring out-of-home care to non-government organisations
The audit assessed how well the Department of Family and Community Services has transferred the management of children in out-of-home care to non-government organisations (NGOs).
The Department has put considerable effort into developing the out-of-home care sector and is progressing well towards its goal of transferring all children in statutory care to NGOs. Since 2011, the number of children with an accredited NGO has more than doubled. This is a positive outcome as children are more likely to receive quality care because these providers meet NSW standards for outof-home care.
However, it is difficult to assess whether overall outcomes for children in care have improved. This is because the Department has yet to determine what wellbeing outcomes it wants to achieve, such as improvements in a child’s health, education and welfare. The Department is currently developing a quality assurance framework which will include such outcomes. We also found that the number of children in care returned to their birth family has declined, and the number of adoptions has remained relatively unchanged.
Parliamentary reference - Report number #257 - released 2 September 2015
Actions for Large construction projects
Large construction projects
The independent assurance given to the NSW Government and sponsor agencies on the viability of large capital projects throughout their lifecycle is inadequate. Government policy is regularly not followed and not properly communicated to those responsible for implementing such policy.
This audit sought to test the effectiveness of the NSW capital project assurance system - which includes gateway reviews and reporting - but significant levels of non-compliance identified in our case studies prevented this. The NSW Commission of Audit also identified this issue in 2012. Gateway reviews are conducted by independent reviewers at key stages of a project’s life cycle and provide an independent assessment on a project’s readiness to proceed to the next stage.
Parliamentary reference - Report number #252 - released 7 May 2015
Actions for Areas of focus from 2014
Areas of focus from 2014