Actions for Signal failures on the metropolitan rail network

Signal failures on the metropolitan rail network

Transport
Information technology
Infrastructure
Internal controls and governance
Project management
Risk
Service delivery

Between 2004 and 2006, the number of signalling failures, signalling downtime and the number of trains delayed as a result of signal failures all fell. RailCorp’s on-time running performance improved over the same period. The fall in failures is a clear indication of improved performance. Changes in the definition of on-time and to the timetable during 2005 and 2006 however make it difficult to determine whether improvements in response downtime and sign

Published

Actions for Connecting with public transport

Connecting with public transport

Transport
Information technology
Infrastructure
Internal controls and governance
Management and administration
Project management
Service delivery
Workforce and capability

We see considerable potential for the Ministry of Transport to plan and manage interchanges more effectively, so as to make better use of our public transport network. We believe that the Ministry now needs to focus more on multi-modal transport planning and interchange performance. It needs to assign responsibility for the coordination and oversight of inter-modal operations to an entity resourced for the purpose. Without this it will continue to be ver

Published

Actions for Responding to homelessness

Responding to homelessness

Health
Community Services
Internal controls and governance
Management and administration
Project management
Service delivery
Shared services and collaboration

Many projects, both Partnership Against Homelessness and by individual agencies, have shown good results or led to improvements. One example is helping mental health patients maintain stable housing. Another is providing street outreach services to homeless people in inner Sydney. Despite these efforts, we were unable to determine how well the government is responding to homelessness statewide. This is because there are no statewide performance measures

Published

Actions for Oversight of State Owned Electricity Corporations

Oversight of State Owned Electricity Corporations

Treasury
Asset valuation
Financial reporting
Management and administration
Service delivery

Issues of corporate governance have long been a matter for concern in the private sector. Following recent corporate collapses and scandals, legislators and regulators in a number of countries have focused on strengthening governance in publicly traded corporations. Considerable attention has been given to setting clear expectations for the performance of boards and for the disclosure of information to various stakeholders. Good governance is no less im

Published

Actions for Implementing Asset Management Reforms

Implementing Asset Management Reforms

Justice
Planning
Finance
Treasury
Asset valuation
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Project management

Hospitals, schools, public housing, roads, bridges, buses and trains are just some of the assets used by government in providing services to citizens. The NSW Government’s asset base is impressive in size - with a value of around $167 billion and with government plans to spend around $8 billion acquiring or replacing assets in the current year. Another $2 billion is spent each year on maintenance. Good asset management is very important to government;

Published

Actions for Follow-up of Performance Audit: Bus Maintenance and Bus Contracts

Follow-up of Performance Audit: Bus Maintenance and Bus Contracts

Transport
Asset valuation
Compliance
Financial reporting
Infrastructure
Management and administration
Procurement
Project management
Service delivery
Workforce and capability

Periodically we review the extent to which agencies have implemented the recommendations they accepted from our earlier audits. This gives Parliament and the public an update on the extent of progress made. In this follow-up audit, we examine changes following our May 2002 report on how well the: State Transit Authority maintained its buses Ministry of Transport administered contracts for the provision of regular passenger bus services.   Parliament

Published

Actions for Follow-up of Performance Audit: Maintenance of Public Housing

Follow-up of Performance Audit: Maintenance of Public Housing

Community Services
Compliance
Internal controls and governance
Management and administration
Regulation

Periodically we review the extent to which agencies have implemented the recommendations they accepted from our earlier audits. This gives Parliament and the public an update on the extent of progress made. Maintaining public infrastructure – whether social or economic – is a topic that is attracting significant attention. In this follow-up audit, we examine changes following our April 2001 report on how well the Department of Housing managed its publi

Published

Actions for Government office accommodation

Government office accommodation

Treasury
Finance
Asset valuation
Management and administration
Procurement

The Audit Office has undertaken an audit on Government Office Accommodation. The audit examined the cost effectiveness of long-term leasing versus ownership and the housing of agencies involved with the delivery of core government activities.  Core activities are those intrinsically linked to basic and ongoing functions of Government and Parliament. It recommends that: the Government consider owning office accommodation, as opposed to leasing, for it

Published

Actions for Review of Eastern Distributor

Review of Eastern Distributor

Transport
Infrastructure
Procurement
Project management

Following a resolution of the Legislative Council, the Audit Office has undertaken a performance audit of the Eastern Distributor. For a number of reasons, The Audit Office is not in the position to determine “whether the proposed toll and concession period represents the best deal”. In part this is the result of time constraints which do not allow a careful analysis of many toll and concession options. Similarly, the audit does not answer “whether the c

Published

Actions for Large residential centres for people with a disability in NSW

Large residential centres for people with a disability in NSW

Community Services
Compliance
Internal controls and governance
Management and administration
Service delivery

The audit reviewed policies and practices in large government and non-government residential centres to determine if policies and practices protected the human and legal rights, safety and dignity of residents. The report indicates that practices in both government and non-government centres fail to protect adequately the human and legal rights, safety and dignity of residents. Factors contributing to this situation are the absence of minimum criteria f