Actions for CBD South East Sydney Light Rail: follow-up performance audit

CBD South East Sydney Light Rail: follow-up performance audit

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk
Service delivery

This is a follow-up to the Auditor-General's November 2016 report on the CBD South East Sydney Light Rail project. This follow-up report assessed whether Transport for NSW has updated and consolidated information about project costs and benefits.

The audit found that Transport for NSW has not consistently and accurately updated project costs, limiting the transparency of reporting to the public.

The Auditor-General reports that the total cost of the project will exceed $3.1 billion, which is above the revised cost of $2.9 billion published in November 2019. $153.84 million of additional costs are due to omitted costs for early enabling works, the small business assistance package and financing costs attributable to project delays.

The report makes four recommendations to Transport for NSW to publicly report on the final project cost, the updated expected project benefits, the benefits achieved in the first year of operations and the average weekly journey times.

Read full report (PDF)

The CBD and South East Light Rail is a 12 km light rail network for Sydney. It extends from Circular Quay along George Street to Central Station, through Surry Hills to Moore Park, then to Kensington and Kingsford via Anzac Parade and Randwick via Alison Road and High Street.

Transport for NSW (TfNSW) is responsible for planning, procuring and delivering the Central Business District and South East Light Rail (CSELR) project. In December 2014, TfNSW entered into a public private partnership with ALTRAC Light Rail as the operating company (OpCo) responsible for delivering, operating and maintaining the CSELR. OpCo engaged Alstom and Acciona, who together form its Design and Construct Contractor (D&C).

On 14 December 2019, passenger services started on the line between Circular Quay and Randwick. Passenger services on the line between Circular Quay and Kingsford commenced on 3 April 2020.

In November 2016, the Auditor-General published a performance audit report on the CSELR project. The audit found that TfNSW would deliver the CSELR at a higher cost with lower benefits than in the approved business case, and recommended that TfNSW update and consolidate information about project costs and benefits and ensure the information is readily accessible to the public.

In November 2018, the Public Accounts Committee (PAC) examined TfNSW's actions taken in response to our 2016 performance audit report on the CSELR project. The PAC recommended that the Auditor-General consider undertaking a follow-up audit on the CSELR project. The purpose of this follow-up performance audit is to assess whether TfNSW has effectively updated and consolidated information about project costs and benefits for the CSELR project.

Conclusion

Transport for NSW has not consistently and accurately updated CSLER project costs, limiting the transparency of reporting to the public. In line with the NSW Government Benefits Realisation Management Framework, TfNSW intends to measure benefits after the project is completed and has not updated the expected project benefits since April 2015.

Between February 2015 and December 2019, Transport for NSW (TfNSW) regularly updated capital expenditure costs for the CSELR in internal monthly financial performance and risk reports. These reports did not include all the costs incurred by TfNSW to manage and commission the CSELR project.

Omitted costs of $153.84 million for early enabling works, the small business assistance package and financing costs attributable to project delays will bring the current estimated total cost of the CSELR project to $3.147 billion.

From February 2015, TfNSW did not regularly provide the financial performance and risk reports to key CSELR project governance bodies. TfNSW publishes information on project costs and benefits on the Sydney Light Rail website. However, the information on project costs has not always been accurate or current.

TfNSW is working with OpCo partners to deliver the expected journey time benefits. A key benefit defined in the business plan was that bus services would be reduced owing to transfer of demand to the light rail - entailing a saving. However, TfNSW reports that the full expected benefit of changes to bus services will not be realised due to bus patronage increasing above forecasted levels.

Appendix one – Response from agency

Appendix two – Governance and reporting arrangements for the CSELR

Appendix three – 2018 CSELR governance changes

Appendix four – About the audit

Appendix five – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #335 - released 11 June 2020

Published

Actions for Newcastle Urban Transformation and Transport Program

Newcastle Urban Transformation and Transport Program

Transport
Planning
Compliance
Infrastructure
Management and administration
Procurement
Project management

The urban renewal projects on former railway land in the Newcastle city centre are well targeted to support the objectives of the Newcastle Urban Transformation and Transport Program (the Program), according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the government. However, the evidence that the cost of the light rail will be justified by its contribution to the Program is not convincing.

The Newcastle Urban Transformation and Transport Program (the Program) is an urban renewal and transport program in the Newcastle city centre. The Hunter and Central Coast Development Corporation (HCCDC) has led the Program since 2017. UrbanGrowth NSW led the Program from 2014 until 2017. Transport for NSW has been responsible for delivering the transport parts of the Program since the Program commenced. All references to HCCDC in this report relate to both HCCDC and its predecessor, the Hunter Development Corporation. All references to UrbanGrowth NSW in this report relate only to its Newcastle office from 2014 to 2017.

This audit had two objectives:

  1. To assess the economy of the approach chosen to achieve the objectives of the Program.
  2. To assess the effectiveness of the consultation and oversight of the Program.

We addressed the audit objectives by answering the following questions:

a) Was the decision to build light rail an economical option for achieving Program objectives?
b) Has the best value been obtained for the use of the former railway land?
c) Was good practice used in consultation on key Program decisions?
d) Did governance arrangements support delivery of the program?

Conclusion
1. The urban renewal projects on the former railway land are well targeted to support the objectives of the Program. However, there is insufficient evidence that the cost of the light rail will be justified by its contribution to Program objectives.

The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the Government. HCCDC, and previously UrbanGrowth NSW, identified and considered options for land use that would best meet Program objectives. Required probity processes were followed for developments that involved financial transactions. Our audit did not assess the achievement of these objectives because none of the projects have been completed yet.

Analysis presented in the Program business case and other planning documents showed that the light rail would have small transport benefits and was expected to make a modest contribution to broader Program objectives. Analysis in the Program business case argued that despite this, the light rail was justified because it would attract investment and promote economic development around the route. The Program business case referred to several international examples to support this argument, but did not make a convincing case that these examples were comparable to the proposed light rail in Newcastle.

The audited agencies argue that the contribution of light rail cannot be assessed separately because it is a part of a broader Program. The cost of the light rail makes up around 53 per cent of the total Program funding. Given the cost of the light rail, agencies need to be able to demonstrate that this investment provides value for money by making a measurable contribution to the Program objectives.

2. Consultation and oversight were mostly effective during the implementation stages of the Program. There were weaknesses in both areas in the planning stages.

Consultations about the urban renewal activities from around 2015 onward followed good practice standards. These consultations were based on an internationally accepted framework and met their stated objectives. Community consultations on the decision to close the train line were held in 2006 and 2009. However, the final decision in 2012 was made without a specific community consultation. There was no community consultation on the decision to build a light rail.

The governance arrangements that were in place during the planning stages of the Program did not provide effective oversight. This meant there was not a single agreed set of Program objectives until 2016 and roles and responsibilities for the Program were not clear. Leadership and oversight improved during the implementation phase of the Program. Roles and responsibilities were clarified and a multi-agency steering committee was established to resolve issues that needed multi-agency coordination.
The light rail is not justified by conventional cost-benefit analysis and there is insufficient evidence that the indirect contribution of light rail to achieving the economic development objectives of the Program will justify the cost.
Analysis presented in Program business cases and other planning documents showed that the light rail would have small transport benefits and was expected to make a modest contribution to broader Program objectives. Analysis in the Program business case argued that despite this, the light rail was justified because it would attract investment and promote economic development around the route. The Program business case referred to several international examples to support this argument, but did not make a convincing case that these examples were comparable to the proposed light rail in Newcastle.
The business case analysis of the benefits and costs of light rail was prepared after the decision to build light rail had been made and announced. Our previous reports, and recent reports by others, have emphasised the importance of completing thorough analysis before announcing infrastructure projects. Some advice provided after the initial light rail decision was announced was overly optimistic. It included benefits that cannot reasonably be attributed to light rail and underestimated the scope and cost of the project.
The audited agencies argue that the contribution of light rail cannot be assessed separately because it is part of a broader Program. The cost of the light rail makes up around 53 per cent of the total Program funding. Given the high cost of the light rail, we believe agencies need to be able to demonstrate that this investment provides value for money by making a measurable contribution to the Program objectives.

Recommendations
For future infrastructure programs, NSW Government agencies should support economical decision-making on infrastructure projects by:
  • providing balanced advice to decision makers on the benefits and risks of large infrastructure investments at all stages of the decision-making process
  • providing scope and cost estimates that are as accurate and complete as possible when initial funding decisions are being made
  • making business cases available to the public.​​​​​​
The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the government.

The planned uses of the former railway land align with the objectives of encouraging people to visit and live in the city centre, creating attractive public spaces, and supporting growth in employment in the city. The transport benefits of the activities are less clear, because the light rail is the major transport project and this will not make significant improvements to transport in Newcastle.

The processes used for selling and leasing parts of the former railway land followed industry standards. Options for the former railway land were identified and assessed systematically. Competitive processes were used for most transactions and the required assessment and approval processes were followed. The sale of land to the University of Newcastle did not use a competitive process, but required processes for direct negotiations were followed.

Recommendation
By March 2019, the Hunter and Central Coast Development Corporation should:
  • work with relevant stakeholders to explore options for increasing the focus on the heritage objective of the Program in projects on the former railway land. This could include projects that recognise the cultural and industrial heritage of Newcastle.
Consultations about the urban renewal activities followed good practice standards, but consultation on transport decisions for the Program did not.

Consultations focusing on urban renewal options for the Program included a range of stakeholders and provided opportunities for input into decisions about the use of the former railway land. These consultations received mostly positive feedback from participants. Changes and additions were made to the objectives of the Program and specific projects in response to feedback received. 

There had been several decades of debate about the potential closure of the train line, including community consultations in 2006 and 2009. However, the final decision to close the train line was made and announced in 2012 without a specific community consultation. HCCDC states that consultation with industry and business representatives constitutes community consultation because industry representatives are also members of the community. This does not meet good practice standards because it is not a representative sample of the community.

There was no community consultation on the decision to build a light rail. There were subsequent opportunities for members of the community to comment on the implementation options, but the decision to build it had already been made. A community and industry consultation was held on which route the light rail should use, but the results of this were not made public. 

Recommendation
For future infrastructure programs, NSW Government agencies should consult with a wide range of stakeholders before major decisions are made and announced, and report publicly on the results and outcomes of consultations. 

The governance arrangements that were in place during the planning stages of the Program did not provide effective oversight. Project leadership and oversight improved during the implementation phase of the Program.

Multi-agency coordination and oversight were ineffective during the planning stages of the Program. Examples include: multiple versions of Program objectives being in circulation; unclear reporting lines for project management groups; and poor role definition for the initial advisory board. Program ownership was clarified in mid-2016 with the appointment of a new Program Director with clear accountability for the delivery of the Program. This was supported by the creation of a multi-agency steering committee that was more effective than previous oversight bodies.

The limitations that existed in multi-agency coordination and oversight had some negative consequences in important aspects of project management for the Program. This included whole-of-government benefits management and the coordination of work to mitigate impacts of the Program on small businesses.

Recommendations
For future infrastructure programs, NSW Government agencies should: 

  • develop and implement a benefits management approach from the beginning of a program to ensure responsibility for defining benefits and measuring their achievement is clear
  • establish whole-of-government oversight early in the program to guide major decisions. This should include:
    • agreeing on objectives and ensuring all agencies understand these
    • clearly defining roles and responsibilities for all agencies
    • establishing whole-of-government coordination for the assessment and mitigation of the impact of major construction projects on businesses and the community.

By March 2019, the Hunter and Central Coast Development Corporation should update and implement the Program Benefits Realisation Plan. This should include:

  • setting measurable targets for the desired benefits
  • clearly allocating ownership for achieving the desired benefits
  • monitoring progress toward achieving the desired benefits and reporting publicly on the results.

Appendix one - Response from agencies    

Appendix two - About the audit

Appendix three - Performance auditing

 

Parliamentary reference - Report number #310 - released 12 December 2018

Published

Actions for Condition of State Roads

Condition of State Roads

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Service delivery

The Roads and Traffic Authority (RTA) has improved the overall surface condition of State Roads in the last decade. Country road surfaces are now generally much better. Ride quality has improved and cracking has been reduced. The RTA has also achieved a substantial reduction in the number of structurally deficient bridges over the same period. 

Despite a significant increase in the State’s contribution to maintenance since 1999-2000, the RTA has deferred road rebuilding projects. The RTA is rebuilding at less than half its long term target, and has not met this target at any time this decade. The RTA has not identified how it will address deferred rebuilding, although it advises it is developing a new road network management plan which will address this.

 

Parliamentary reference - Report number #157 - released 16 August 2006

Published

Actions for The Cross City Tunnel Project

The Cross City Tunnel Project

Transport
Treasury
Premier and Cabinet
Planning
Environment
Infrastructure
Management and administration
Procurement
Project management
Risk

In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs. Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate.

In our opinion, however, the Government, Treasury and the RTA did not sufficiently consider the implications of an upfront payment involving more than simple project cost reimbursement (i.e. the ‘Business Consideration Fee’ component). In addition, the RTA was wrong to change the toll escalation factor late in 2002 to compensate the tunnel operator, Cross City Motorway Pty Ltd, for additional costs.

 

Parliamentary reference - Report number #152 - released 31 May 2006

Published

Actions for Review of Eastern Distributor

Review of Eastern Distributor

Transport
Infrastructure
Procurement
Project management

Following a resolution of the Legislative Council, the Audit Office has undertaken a performance audit of the Eastern Distributor. For a number of reasons, The Audit Office is not in the position to determine “whether the proposed toll and concession period represents the best deal”. In part this is the result of time constraints which do not allow a careful analysis of many toll and concession options. Similarly, the audit does not answer “whether the current proposal represents the best environmental outcome”. But each of these issues (toll and concession and environmental consequences) is discussed in the audit report.

The Audit Office recommends that the Roads and Traffic Authority (RTA), for any further major project of this type, ensures that it establishes a process which allows all decision makers to have a thorough understanding of the reasonableness of the proponents’ offers and their implications for the State and for the public. The Audit Office also recommends that the RTA should at the outset consult with TCorp in respect of each major project put to tender.

 

Parliamentary reference - Report number #42 - released 31 July 1997