Actions for Sydney Road Maintenance Contracts
Sydney Road Maintenance Contracts
In November 2013, Roads and Maritime Services (RMS) outsourced the maintenance of State roads in the Sydney region south and west zones using an innovative contracting approach called the Stewardship Maintenance Contract (SMC). The SMC links risk to reward, and uses a performance framework where outcomes should drive improved performance over time.
WA | VIC | QLD | NSW | |
---|---|---|---|---|
Roads managed (lane kms) | 52,659 | 50,510 | 71,353 | 80,348 |
Estimated spend ($/lane km) | 5,000 | 4,500 | 6,000 | 7,000 |
Road quality measure (%) | 99 | 99 | 94 | 91 |
Parliamentary reference - Report number #288 - released 15 June 2017
Actions for NorthConnex
NorthConnex
The processes used to assess NorthConnex adequately considered value for money for taxpayers.This report also found that the impact of tolling concessions on road users and the motorway network was consistent with policy objectives described in the 2012 NSW Long Term Transport Master Plan.
Parliamentary reference - Report number #287 - released 8 June 2017
Actions for Improving the Performance of Metropolitan Bus Services
Improving the Performance of Metropolitan Bus Services
The 2004 Review of Bus Services in NSW always envisaged that there would be a transition period as the new bus contracts were introduced. NSWTI has developed and implemented the new arrangements, and pursued a range of new initiatives including the network improvement program, strategic corridors and uniform bus fares and concessions. The new contracts provided for a performance management regime to hold operators accountable. But this is still being developed four years after the bus contracts came into effect and it remains unproven as a basis for ensuring value for money from the contracts - each of which guarantees monopoly rights to the operators.
Parliamentary reference - Report number #198 - released 10 March 2010
Actions for Follow-up of Performance Audit: Bus Maintenance and Bus Contracts
Follow-up of Performance Audit: Bus Maintenance and Bus Contracts
Periodically we review the extent to which agencies have implemented the recommendations they accepted from our earlier audits.
This gives Parliament and the public an update on the extent of progress made.
In this follow-up audit, we examine changes following our May 2002 report on how well the:
- State Transit Authority maintained its buses
- Ministry of Transport administered contracts for the provision of regular passenger bus services.
Parliamentary reference - Report number #138 - released 14 June 2005