Actions for WestConnex: Assurance to the Government
WestConnex: Assurance to the Government
This audit assesses the assurance provided to the NSW Government for the initial stages of the WestConnex project.
The audit examined the WestConnex project from concept development to the pre-tender phase for Stage 1A – M4 (Parramatta to Homebush Bay). It did not examine the merit of the project or whether it represented value-for-money.
This audit found a number of shortcomings with the governance of the WestConnex project during its early stages and makes recommendations on how to better govern the remainder of the project to minimise the risk of failure.
Parliamentary reference - Report number #247 - released 18 December 2014
Actions for Volume One 2014 - Areas of focus from 2013
Volume One 2014 - Areas of focus from 2013
Today the Auditor-General of New South Wales, Grant Hehir, released his Volume One Report to Parliament for 2014. The observations included in this report are designed to inform readers of common findings from the 2013 financial and performance audits so agencies and audit committees can use them to identify issues that may be relevant to their organisations.
Actions for Handback of the M4 Tollway
Handback of the M4 Tollway
This audit focuses on the M4 handback. It looks at whether the road will be in good condition when the State gets it back, and whether it will cope with the extra traffic after the toll is removed. These are critical issues for taxpayers and motorists. Taxpayers don’t want to be responsible for a large repair bill and motorists don’t want to be stuck in traffic jams.
To ensure that future private sector partnerships (PPP) deal adequately with handback, we recommend that the Roads and Traffic Authority (RTA):
- ensure deeds spell out an appropriate inspection and testing program to determine repairs required to bring roads up to a satisfactory condition at handback (p.11)
- ensure deeds link condition standards and maintenance approaches to changing industry standards and approaches over the life of the PPP (p.11)
- consider including in deeds a requirement that operators provide a performance bond or similar security over the cost of handback repairs (p.11)
- review the lessons learnt from the M4 tollway handback and determine whether it should seek to negotiate changes to existing tollway deeds to better deal with handback, by June 2010 (p.11)
Parliamentary reference - Report number #193 - released 27 October 2009
Actions for Bus Maintenance and Bus Contracts
Bus Maintenance and Bus Contracts
State Transit has developed fleet management plans and maintenance standards that meet its regulatory and contractual obligations as a bus operator and are consistent with vehicle manufacturers’ standards and best practice. However, assumptions used in fleet management plans to forecast fleet growth may not result in the most efficient and effective outcome for State Transit. Forecasts fail to take account of opportunities to redesign or reduce services where they exceed contract requirements and are difficult to justify on a commercial basis. Of greater concern are the consequences arising from bus maintenance practices not meeting State Transit’s own standards.
Parliamentary reference - Report number #97 - released 29 May 2002
Actions for Planning for road maintenance
Planning for road maintenance
The Audit Office is of the opinion that the RTA is taking positive steps in planning for road maintenance and in many instances follows better practice. There are, however, some important improvements which need to be implemented in order to enhance the efficiency and effectiveness of that function.
Parliamentary reference - Report number #69 - released 1 December 1999