Actions for Sydney Road Maintenance Contracts
Sydney Road Maintenance Contracts
In November 2013, Roads and Maritime Services (RMS) outsourced the maintenance of State roads in the Sydney region south and west zones using an innovative contracting approach called the Stewardship Maintenance Contract (SMC). The SMC links risk to reward, and uses a performance framework where outcomes should drive improved performance over time.
WA | VIC | QLD | NSW | |
---|---|---|---|---|
Roads managed (lane kms) | 52,659 | 50,510 | 71,353 | 80,348 |
Estimated spend ($/lane km) | 5,000 | 4,500 | 6,000 | 7,000 |
Road quality measure (%) | 99 | 99 | 94 | 91 |
Parliamentary reference - Report number #288 - released 15 June 2017
Actions for NorthConnex
NorthConnex
The processes used to assess NorthConnex adequately considered value for money for taxpayers.This report also found that the impact of tolling concessions on road users and the motorway network was consistent with policy objectives described in the 2012 NSW Long Term Transport Master Plan.
Parliamentary reference - Report number #287 - released 8 June 2017
Actions for Passenger Rail Punctuality
Passenger Rail Punctuality
Rail agencies are well placed to manage the forecast increase in passengers up to 2019, including joining the Sydney Metro Northwest to the network at Chatswood. Their plans and strategies are evidence-based, and mechanisms to assure effective implementation are sound.
Appendix one - Response from the agencies
Appendix two - Response from Audit Office
Appendix three - About the audit
Appendix four - Accuracy of punctuality measurement
Appendix five - Train and customer punctuality
Parliamentary reference - Report number #281 - released 11 April 2017
Actions for Signal failures on the metropolitan rail network
Signal failures on the metropolitan rail network
Between 2004 and 2006, the number of signalling failures, signalling downtime and the number of trains delayed as a result of signal failures all fell. RailCorp’s on-time running performance improved over the same period. The fall in failures is a clear indication of improved performance. Changes in the definition of on-time and to the timetable during 2005 and 2006 however make it difficult to determine whether improvements in response downtime and signalling delays are due to a true performance improvement. To build upon this strong base, RailCorp needs to determine with more confidence the number and duration of signalling failures the network can tolerate without impacting on service levels.
Parliamentary reference - Report number #170 - released 15 August 2007
Actions for Connecting with public transport
Connecting with public transport
We see considerable potential for the Ministry of Transport to plan and manage interchanges more effectively, so as to make better use of our public transport network. We believe that the Ministry now needs to focus more on multi-modal transport planning and interchange performance. It needs to assign responsibility for the coordination and oversight of inter-modal operations to an entity resourced for the purpose. Without this it will continue to be very difficult to identify and address unmet needs, seek and secure stakeholder funding, and monitor and evaluate system performance.
Parliamentary reference - Report number #168 - released 6 June 2007