Reports
Actions for Planning and Environment 2016
Planning and Environment 2016
Auditor-General, Margaret Crawford released a report on the planning and environment cluster today, concluding that the quality of financial reporting is improving. However, the cluster can improve its financial controls and governance framework.
Actions for Transport 2016
Transport 2016
Financial reporting within the Transport Cluster continues to improve with reported misstatements down 96 per cent since 2011-12 to just three in 2015-16, according to a report released today by the NSW Auditor-General, Margaret Crawford.
Actions for Volume Twelve 2015 Part Two Water
Volume Twelve 2015 Part Two Water
The distributions to the NSW Government increased from $690 million in 2013-14 to $1.0 billion in 2014-15. The increase was largely due to a higher dividend from Sydney Water Corporation.
Actions for Volume Nine 2015 Planning and Environment
Volume Nine 2015 Planning and Environment
The NSW Environment Protection Authority has reduced the average time to assess contaminated sites from 203 days in 2013-14 to 73 days in 2014-15. It is also improving transparency by making more information on its performance publicly available.
In 2014-15, the Department of Planning and Environment increased new housing approvals across New South Wales by 12 per cent to 58,252, exceeding the State priority target of 50,000. It also reduced the time taken to assess major projects from about three years in 2013-14 to four months in 2014-15.
Actions for Volume Six 2015 Transport
Volume Six 2015 Transport
Public transport revenue decreased by 2.7 per cent despite a fare increase and increased patronage. Twenty-five per cent of all Opal trips (over 74 million) were free, including 47 per cent of trips on ferries, according to a report released today by the New South Wales Acting Auditor-General, Tony Whitfield. These trips were valued at $189 million.
Actions for Areas of focus from 2014
Areas of focus from 2014
Actions for Volume Eight 2012 focusing on Transport and Ports
Volume Eight 2012 focusing on Transport and Ports
We issued unqualified audit opinions on the transport entities’ 30 June 2012 financial statements.
Some of the findings of the report include:
-
government funding to the public transport operators totalled $4.4 billion in 2011-12 ($3.7 billion in 2010-11)
-
passenger services revenue only covered 20 per cent of RailCorp's operating costs
-
Transport for NSW has formalised a protocol to mitigate the risk of potential conflicts of interests
-
At present, no sustainability framework exists for the transport agencies around environment and sustainability. Transport for NSW should complete its Environment and Sustainability Policy Framework by June 2013 and should publicly report its results annually
-
Transport patronage continued to grow with 510 million journeys on train, bus and ferry services
-
CityRail had two peak hour periods where only 36 per cent and 39 per cent of services were on time
-
On-time running performance for Sydney Ferries was above the NSW 2021 plan target of 98.5 per cent for most routes in 2011-12
-
Customer surveys by transport agencies no longer specifically address crowding on public transport. Transport for NSW should observe and report on crowding on all transport modes
-
Over 2,500 transport staff, or 8.3 per cent of the workforce, have excessive leave balances. All transport entities should do more to reduce excessive annual leave balances to ensure they will comply with new targets set by the Premier.
Actions for Volume Six 2012 focusing on Environment, Water and Regional Infrastructure
Volume Six 2012 focusing on Environment, Water and Regional Infrastructure
Last year it was reported that the cost to remediate contaminated sites in New South Wales is largely unknown and that remains the case today. It is noted that this is unlikely to change because parties responsible for contaminated sites can choose not to provide remediation costs, for sites regulated by EPA. The complexity and uniqueness of each contaminated site adds to the difficulty of accurately estimating costs.