Reports
Actions for Managing native vegetation
Managing native vegetation
The report found the clearing of native vegetation on rural land is not effectively regulated and managed. The processes supporting the regulatory framework are weak and there is no evidence-based assurance that clearing of native vegetation is carried out in accordance with approvals.
In 2014 an expert panel completed a review of biodiversity legislation in NSW. The panel’s recommendations included repealing the Native Vegetation Act 2003, proposing a new Act with the goal of maintaining a healthy, productive and resilient environment for the greatest wellbeing of the community, and recommending that management of native vegetation in the context of existing agricultural management would be assisted and supervised by Local Land Services (LLS).
Following the panel report, the NSW Government undertook major biodiversity conservation and land management reforms which saw the introduction of the Biodiversity Conservation Act 2016 (NSW) and the Local Land Services Amendment Act 2016 (NSW). The reforms commenced in August 2017. The Native Vegetation Act 2003, the Threatened Species Conservation Act 1995, the Nature Conservation Trust Act 2001, and parts of the National Parks and Wildlife Act 1974 were repealed.
Under the legislative reforms, the Biodiversity Conservation Act 2016 and Local Land Services Amendment Act 2016, which amended the Local Land Services Act 2013, aim to ensure a balanced approach to land management and biodiversity conservation in NSW.
A core objective of the Biodiversity Conservation Act 2016 is to conserve biodiversity at bioregional and state scales. A core objective of the Local Land Service Act 2013 is to ensure the proper management of natural resources in the social, economic and environmental interests of the state, consistently with the principles of ecologically sustainable development.
The integrated package of reforms included:
- new arrangements that allow land owners to improve productivity while responding to environmental risks
- new ways to assess and manage the biodiversity impacts of development
- a new state Environmental Planning Policy for managing impacts on native vegetation in urban areas
- significant investment in conservation of private land
- a risk-based system for regulating human and business interactions with native plants and animals
- streamlined approvals and dedicated resources to help reduce the regulatory burden.
Transition to this land management framework began on 25 August 2017 with the commencement of the Land Management (Native Vegetation) Code.
The overall objectives of the reforms are:
- to arrest and ultimately reverse the current decline in the state’s biodiversity while facilitating ecologically sustainable development, in particular efficient and sustainable agricultural development
- enable landholders to improve the efficiency of their agricultural systems and take a more active role in providing incentive and supporting landholders to improve the condition and function of their ecological systems.
The objective of this audit is to assess whether the clearing of native vegetation in rural areas is effectively regulated and managed by the Office of Environment and Heritage (OEH) and LLS under these legislative frameworks. The audit also examined the progress of the Biodiversity Conservation Trust in implementing the Biodiversity Conservation Investment Strategy as a counterbalance to rural land clearing.
At the time of this audit OEH was responsible for preparing the Native Vegetation Regulatory map and for compliance enforcement in relation to unlawful land clearing. Post 1 July 2019, under machinery of government changes, OEH will be abolished and its activities relevant to this audit will be moved to the new Department of Planning, Industry and Environment. For the purposes of this audit we will continue to refer to it as OEH.
Conclusion
The clearing of native vegetation on rural land is not effectively regulated and managed because the processes in place to support the regulatory framework are weak. There is no evidence-based assurance that clearing of native vegetation is being carried out in accordance with approvals. Responses to incidents of unlawful clearing are slow, with few tangible outcomes. Enforcement action is rarely taken against landholders who unlawfully clear native vegetation. There are processes in place for approving land clearing but there is limited follow-up to ensure approvals are complied with. Procedures and systems are in place for assessing applications and issuing approvals for land clearing. Approvals contain conditions for managing clearing and setting aside land for conservation as a counterbalance to permitted clearing.
There is limited follow-up or capacity to gauge whether landholders are complying with the conditions of approvals and effectively managing areas of their land that have been set aside for conservation (i.e. 'set asides').
Certificate assessments are used to grant landholders permission to clear. All assessments we reviewed generally complied with the Land Management (Native Vegetation) Code 2018 (the Code).
The rules around land clearing may not be responding adequately to environmental risks.
The Code, which contains conditions under which the thinning or clearing of native vegetation can be approved on regulated land, is intended to allow landholders to improve productivity while responding to environmental risks. That said, it may not be achieving this balance. For example, the Code allows some native species to be treated as ‘invasive’ when they may not be invading an area, provides little protection for groundcover and limited management requirements for set asides. There is also limited ability under the Code to reject applications for higher risk clearing proposals. The release of the Native Vegetation Regulatory (NVR) map has been delayed, limiting landholders' ability to determine if their plans for clearing are lawful.
OEH has applied significant effort in developing a native vegetation regulatory map to guide landholders on which land they can and can’t clear without approval. However, in November 2016 the then Minister for Primary Industries advised Parliament that the two largest land categories of the NVR map will not come into effect until the relevant Ministers are satisfied stakeholders have sufficient confidence in the maps’ accuracy. Not releasing the map has made it harder for landholders to identify the portions of their land that are regulated and ensure they comply with land clearing rules. It has also limited OEH’s ability to consult on and improve the accuracy of the map. There are significant delays in identifying unlawful clearing and few penalties imposed.
Unexplained land clearing can take over two years to identify and analyse, making it difficult to minimise environmental harm or gather evidence to prosecute unlawful clearing. Despite around 1,000 instances of unexplained clearing identified by OEH and over 500 reports to the environmental hotline each year, with around 300 investigations in progress at any one time, there are only two to three prosecutions, three to five remediation orders and around ten penalty notices issued each year for unlawful clearing. Further, OEH is yet to commence any prosecutions under the current legislation which commenced in August 2017. Land clearing and private land conservation investment have both increased.
Clearing of native vegetation has increased in recent years. At the same time, the government is also investing in properties with high environmental value with a focus on improving the mix of endangered ecological communities conserved in perpetuity. Processes are in place for identifying and prioritising areas of land for investment but the funding provided to each region is not always consistent with these priorities. |
Local Land Services (LLS) is responsible for processing notifications and issuing certificates to landholders for managing the thinning or clearing of native vegetation on rural land through the ‘Land Management (Native Vegetation) Code 2018’ (the Code). This work includes monitoring and reporting on the implementation of the Code, including the establishment and management of set asides.
OEH is responsible for compliance and enforcement in relation to unlawful land clearing. It is also responsible for producing the NVR map, designed to show landholders where land clearing can occur without approval, where approval is required, and where land clearing is not permitted. Post 1 July 2019, under machinery of government changes, OEH will be abolished and its activities relevant to this audit will be moved to the new Department of Planning, Industry and Environment.
Appendix one - Response from agencies
Appendix three - About the audit
Appendix four - Performance auditing
Parliamentary Reference: Report number #324 - released 27 June 2019
Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.
Actions for Transport Access Program
Transport Access Program
The following report is available in an Easy English version that is intended to meet the needs of some people with lower literacy skills, some people with an intellectual disability and some people from different cultural backgrounds.
View the Easy English version of the Transport Access Program report
Transport for NSW’s process for selecting and prioritising projects for the third stage of its Transport Access Program balanced compliance with national disability standards with broader customer outcomes. Demographics, deliverability and value for money were also considered. However, Transport for NSW does not know the complete scope of work required for full compliance, limiting its ability to demonstrate that its approach is effective, according to a report released today by the Auditor-General for New South Wales, Margaret Crawford.
Access to transport is critical to ensuring that people can engage in all aspects of community life, including education, employment and recreation. People with disability can encounter barriers when accessing public transport services. In 2015, there were 1.37 million people living with disability in New South Wales.
Accessible public transport is about more than physical accessibility. It also means barrier-free access for people who have vision, hearing or cognitive impairments. All users, not just people with disability, benefit from improvements to the accessibility and inclusiveness of transport services.
Transport for NSW has an obligation under Australian Government legislation to provide accessible services to people with disabilities in a manner which is not discriminatory. Under the Disability Standards for Accessible Public Transport 2002 (the DSAPT - an instrument of the Disability Discrimination Act 1992 (the Act) (Commonwealth)), there is a requirement to modify and develop new infrastructure, means of transport and services to provide access for people with disabilities. All public transport operators are required to ensure that at least 90 per cent of their networks met DSAPT by December 2017 and the networks will need to be 100 per cent compliant with all parts of the standards by 31 December 2022. Trains are not required to be fully compliant with DSAPT until December 2032.
The Transport Access Program (TAP) is Transport for NSW's largest program with a specific focus on improving access to public transport for people with disability. The TAP is a series of projects to upgrade existing public transport infrastructure across four networks: Sydney Trains, Intercity Trains, Regional Trains and Sydney Ferries. Transport for NSW established the TAP as a rolling program and, to date, it has delivered the first tranche of TAP (TAP 1) and is completing the final projects for the second tranche (TAP 2). NSW budget papers estimate that by 30 June 2018, Transport for NSW had spent $1.2 billion in the TAP since its commencement in 2011-12.
After the completion of TAP 1 and TAP 2 (as well as through other transport infrastructure programs), Transport for NSW estimates that 58.5 per cent of the Sydney Trains, Regional Trains and Intercity Trains networks, and 66 per cent of the Sydney Ferries network, will be accessible. To close the significant gap in compliance with the DSAPT target, the objective for TAP 3 is ‘to contribute to Disability Discrimination Act 1992 related targets through DSAPT compliance upgrades’.
The audit assessed whether Transport for NSW has an effective process to select and prioritise projects as part of the TAP, with a specific focus on the third tranche of TAP funding.
In August 2018, at the commencement of this audit, Transport for NSW intended to complete the selection of projects for the TAP 3 final business case in December 2018. Transport for NSW advise that it now intends to complete the development stage and final business case in the first quarter of 2019, prior to the final investment decision of the TAP program. This report is based on the TAP 3 strategic business case and information provided by Transport for NSW up to December 2018.
Transport for NSW’s process for selecting and prioritising projects for TAP 3 balanced DSAPT compliance goals with broader customer outcomes. It also considered demographics, deliverability and value for money. However, Transport for NSW does not know the complete scope of work required for full DSAPT compliance, and this limits its ability to demonstrate that its approach is effective.
In 2015, there were 1.37 million people living with disability in New South Wales. Access to transport is critical to ensuring that people can engage in all aspects of community life, including education, employment and recreation. People with disability can encounter barriers when accessing public transport services.
The social model of disability, outlined in the United Nations Convention on the Rights of Persons with Disabilities, views people with disability as not disabled by their impairment but by the barriers in the community and environment that restrict their full and effective participation in society on an equal basis with others.
Accessible public transport is more than the provision of physical access to premises and conveyances, it provides barrier-free access for people who have vision, hearing or cognitive impairments. All users, not just people with disability, benefit from improvements to the accessibility and inclusiveness of transport services.
According to the Australian Bureau of Statistics, the main types of difficulties experienced by people with disability when using public transport relate to steps (39.9 per cent), difficulty getting to stops and stations (25 per cent), fear and anxiety (23.3 per cent) and lack of seating or difficulty standing (20.7 per cent).
Transport for NSW has a Disability Inclusion Action Plan (the Action Plan) 2018-2022 that sets an overall framework for planning, delivering and reporting on initiatives to increase accessibility of the transport network. It covers all elements of the journey experienced when using public transport, including journey planning, staff training, customer services and interaction between the physical environment and modes of transport. Appendix five outlines the guiding principles of the Action Plan.
Transport for NSW's Transport Social Policy branch developed the Action Plan in consultation with internal and external stakeholders. The director of the Transport Social Policy branch is a member of the TAP executive steering committee, which supports alignment between the Action Plan and TAP.
Transport for NSW's Disability Inclusion Action Plan describes a customer focussed approach to accessibility
One of the guiding principles of the Action Plan is ‘intelligent compliance’. Transport for NSW describes this as compliance that prioritises customer-focused outcomes over a narrow focus on legal compliance with accessibility standards. As well as being compliant, infrastructure should be practical, usable, fit for purpose and convenient.
The TAP prioritisation and selection methodology reflects Transport for NSW’s focus on intelligent compliance. We consider this a reasonable approach as had Transport for NSW focussed exclusively on achieving compliance with the DSAPT targets by upgrading the most affordable infrastructure, some locations, that are used by more customers, would remain inaccessible to people with disability. However, this approach should not be seen as an alternative to Transport for NSW meeting its DSAPT compliance obligations.
TAP program staff consult with the Accessible Transport Advisory Committee
The Accessible Transport Advisory Committee (ATAC) has representatives from disability and ageing organisations, who provide expert guidance to Transport for NSW on access and inclusion. The ATAC provide guidance and feedback on projects and project solutions, including user testing where appropriate. TAP program staff provide regular updates at ATAC meetings, which include briefings on progress. The ATAC also provides feedback and suggestions to TAP program staff, which is considered and sometimes included in current and future projects.For example, in March 2017 the TAP program team briefed the ATAC on the challenges with respect to a number of ferry wharves and sought support for DSAPT exemptions proposed in the TAP 3 strategic business case.
In June 2018, the Program team sought feedback on a variety of lift button options to improve accessibility on future TAP projects. In September 2018, during the ATAC meeting attended by the Audit Office, the program team sought feedback on the standard designs for TAP 3. Some ATAC members noted that the standard design included Braille lettering on the lift buttons, and that this was not good practice because people can accidently press the button while reading it. As a result, Transport for NSW are incorporating this feedback into design requirements for the lifts for TAP 3, which will consider larger buttons, clearer Braille and Braille signage adjacent to the button. |
Transport for NSW has not briefed the Advisory Committee on the outcome of the prioritisation and selection process
TAP program staff briefed the Advisory Committee about the prioritisation and selection methodology, after the Minister approved it in 2016. However, Transport for NSW have not briefed or consulted the Advisory Committee on the outcome of the prioritisation process. Infrastructure NSW noted this issue during its review of the strategic business case.
Transport for NSW advised us that it established the ATAC as an advisory group, and that Transport for NSW does not disclose sensitive information to it. Transport for NSW intends to share the outcome of the prioritisation process following the completion of the TAP 3 development stage and final investment decision.
The TAP communication plan does not fully meet the requirements of the Disability Inclusion Action Plan
The Disability Inclusion Action Plan includes an action item to ‘provide a listing of stations and wharves to be upgraded with estimated time of construction as each new tranche of the Transport Access Program is announced’ The TAP Communication Plan that we reviewed does not include this provision instead focussing on communication on a per project basis. Given the long timeframes associated with improving transport infrastructure, this information is important as it allows people to make informed decisions about where they live, work or study.
Appendix one - Response from agency
Appendix two - Compliance requirements of Disability Standards for Accessible Public Transport
Appendix three - TAP 1 and TAP 2 sub-programs
Appendix four - Prioritisation Assessment for the TAP 3 Strategic Business Case
Appendix five - The guiding principles of Transport for NSW's Disability Inclusion Action Plan
Appendix six - Transport projects and programs that contribute to DSAPT compliance
Appendix seven - About the audit
Appendix eight - Performance auditing
Parliamentary Reference - Report number #314 - released 19 February 2019.
Actions for Mobile speed cameras
Mobile speed cameras
The primary goal of speed cameras is to reduce speeding and make the roads safer. Our 2011 performance audit on speed cameras found that, in general, speed cameras change driver behaviour and have a positive impact on road safety.
Transport for NSW published the NSW Speed Camera Strategy in June 2012 in response to our audit. According to the Strategy, the main purpose of mobile speed cameras is to reduce speeding across the road network by providing a general deterrence through anywhere, anytime enforcement and by creating a perceived risk of detection across the road network. Fixed and red-light speed cameras aim to reduce speeding at specific locations.
Roads and Maritime Services and Transport for NSW deploy mobile speed cameras (MSCs) in consultation with NSW Police. The cameras are operated by contractors authorised by Roads and Maritime Services. MSC locations are stretches of road that can be more than 20 kilometres long. MSC sites are specific places within these locations that meet the requirements for a MSC vehicle to be able to operate there.
This audit assessed whether the mobile speed camera program is effectively managed to maximise road safety benefits across the NSW road network.
The mobile speed camera program requires improvements to key aspects of its management to maximise road safety benefits. While camera locations have been selected based on crash history, the limited number of locations restricts network coverage. It also makes enforcement more predictable, reducing the ability to provide a general deterrence. Implementation of the program has been consistent with government decisions to limit its hours of operation and use multiple warning signs. These factors limit the ability of the mobile speed camera program to effectively deliver a broad general network deterrence from speeding.
Many locations are needed to enable network-wide coverage and ensure MSC sessions are randomised and not predictable. However, there are insufficient locations available to operate MSCs that meet strict criteria for crash history, operator safety, signage and technical requirements. MSC performance would be improved if there were more locations.
A scheduling system is meant to randomise MSC location visits to ensure they are not predictable. However, a relatively small number of locations have been visited many times making their deployment more predictable in these places. The allocation of MSCs across the time of day, day of week and across regions is prioritised based on crash history but the frequency of location visits does not correspond with the crash risk for each location.
There is evidence of a reduction in fatal and serious crashes at the 30 best-performing MSC locations. However, there is limited evidence that the current MSC program in NSW has led to a behavioural change in drivers by creating a general network deterrence. While the overall reduction in serious injuries on roads has continued, fatalities have started to climb again. Compliance with speed limits has improved at the sites and locations that MSCs operate, but the results of overall network speed surveys vary, with recent improvements in some speed zones but not others.
There is no supporting justification for the number of hours of operation for the program. The rate of MSC enforcement (hours per capita) in NSW is less than Queensland and Victoria. The government decision to use multiple warning signs has made it harder to identify and maintain suitable MSC locations, and impeded their use for enforcement in both traffic directions and in school zones.
Appendix one - Response from agency
Appendix two - About the audit
Appendix three - Performance auditing
Parliamentary reference - Report number #308 - released 18 October 2018
Actions for Regulation of water pollution in drinking water catchments and illegal disposal of solid waste
Regulation of water pollution in drinking water catchments and illegal disposal of solid waste
There are important gaps in how the Environmental Protection Authority (EPA) implements its regulatory framework for water pollution in drinking water catchments and illegal solid waste disposal. This limits the effectiveness of its regulatory responses, according to a report released today by the Auditor-General for New South Wales, Margaret Crawford.
By 31 December 2018, to improve governance and oversight, the EPA should: | |
1. | implement a more effective performance framework with regular reports to the Chief Executive Officer and to the EPA Board on outcomes-based key result areas that assess its environmental and regulatory performance and trends over time |
By 30 June 2019, to improve consistency in its practices, the EPA should: | |
2. | progressively update and make accessible its policies and procedures for regulatory operations, and mandate procedures where necessary to ensure consistent application |
3. | implement internal controls to monitor the consistency and quality of its regulatory operations. |
By 30 June 2019, to address worsening water quality in Lake Burragorang, the EPA should: | |
4. | (a) review the impact of its licensed activities on water quality in Lake Burragorang, and |
(b) develop strategies relating to its licensed activities (in consultation with other relevant NSW Government agencies) to improve and maintain the lake's water quality. |
To improve compliance monitoring, the EPA should implement procedures to: | |
5. | by 30 June 2019, validate self-reported information, eliminate hardcopy submissions and require licensees to report on their breaches of the Act and associated regulations in their annual returns |
6. | by 31 December 2018, conduct mandatory site inspections under the risk-based licensing scheme to assess compliance with all regulatory requirements and licence conditions. |
By 31 December 2018 to improve enforcement, the EPA should: | |
7. | Implement procedures to systematically assess non-compliances with licence conditions and breaches of the Act and to implement appropriate and consistent regulatory actions. |
Appendix one – Response from agency
Appendix two – List of enforcement tools
Appendix three – The EPA's organisational structure
Appendix four – The EPA's regions and branches
Appendix five – About the audit
Appendix six – Performance auditing
Parliamentary reference - Report number #304 - released 28 June 2018
Actions for Signal failures on the metropolitan rail network
Signal failures on the metropolitan rail network
Between 2004 and 2006, the number of signalling failures, signalling downtime and the number of trains delayed as a result of signal failures all fell. RailCorp’s on-time running performance improved over the same period. The fall in failures is a clear indication of improved performance. Changes in the definition of on-time and to the timetable during 2005 and 2006 however make it difficult to determine whether improvements in response downtime and signalling delays are due to a true performance improvement. To build upon this strong base, RailCorp needs to determine with more confidence the number and duration of signalling failures the network can tolerate without impacting on service levels.
Parliamentary reference - Report number #170 - released 15 August 2007
Actions for Connecting with public transport
Connecting with public transport
We see considerable potential for the Ministry of Transport to plan and manage interchanges more effectively, so as to make better use of our public transport network. We believe that the Ministry now needs to focus more on multi-modal transport planning and interchange performance. It needs to assign responsibility for the coordination and oversight of inter-modal operations to an entity resourced for the purpose. Without this it will continue to be very difficult to identify and address unmet needs, seek and secure stakeholder funding, and monitor and evaluate system performance.
Parliamentary reference - Report number #168 - released 6 June 2007