Actions for Handback of the M4 Tollway
Handback of the M4 Tollway
This audit focuses on the M4 handback. It looks at whether the road will be in good condition when the State gets it back, and whether it will cope with the extra traffic after the toll is removed. These are critical issues for taxpayers and motorists. Taxpayers don’t want to be responsible for a large repair bill and motorists don’t want to be stuck in traffic jams.
To ensure that future private sector partnerships (PPP) deal adequately with handback, we recommend that the Roads and Traffic Authority (RTA):
- ensure deeds spell out an appropriate inspection and testing program to determine repairs required to bring roads up to a satisfactory condition at handback (p.11)
- ensure deeds link condition standards and maintenance approaches to changing industry standards and approaches over the life of the PPP (p.11)
- consider including in deeds a requirement that operators provide a performance bond or similar security over the cost of handback repairs (p.11)
- review the lessons learnt from the M4 tollway handback and determine whether it should seek to negotiate changes to existing tollway deeds to better deal with handback, by June 2010 (p.11)
Parliamentary reference - Report number #193 - released 27 October 2009
Actions for Environmental Grants Administration
Environmental Grants Administration
We found many aspects of good grants management, particularly in the Trust. All of the programs we looked at are clearly aligned to the Government’s objective to improve environmental outcomes. The Trust also has good practices for allocating grants. Performance in respect of results was mixed although many grants delivered tangible benefits - homes were protected from floods, degraded waterways restored and endangered habitats protected.
Generally we found that while both Department of Environment, Climate Change and Water and the NSW Environmental Trust had a range of strategies to monitor grants these were not always applied consistently or effectively. Grant programs need to be regularly evaluated to see what is working and what can be done better.
Parliamentary reference - Report number #190 - released 26 August 2009