Actions for Albert 'Tibby' Cotter Walkway

Albert 'Tibby' Cotter Walkway

Transport
Internal controls and governance
Procurement
Project management

On 17 September 2015, the Acting Auditor-General of New South Wales, Tony Whitfield, released a report on the Albert ‘Tibby’ Cotter Walkway which crosses over Anzac Parade in Moore Park. The Walkway’s primary function is to cater for event patrons in the precinct. Moore Park is listed on the State Heritage Register and is an open space specifically established to cater for public recreation.   Roads and Maritime Services (RMS) delivered the Walkway

Published

Actions for Sydney metropolitan bus contracts

Sydney metropolitan bus contracts

Transport
Internal controls and governance
Management and administration
Procurement
Project management
Service delivery

On 9 September 2015, the Acting Auditor-General of New South Wales, Tony Whitfield, released a report on Sydney Metropolitan Bus Service Contracts.   All scheduled bus services in the Sydney metropolitan area are provided under contracts with the public and private operators. The contracts allow Transport for NSW (TfNSW) to determine what bus services are provided and to whom. This audit assessed the effectiveness of TfNSW’s design and management of

Published

Actions for Identifying productivity in the public sector

Identifying productivity in the public sector

Health
Education
Community Services
Transport
Justice
Treasury
Whole of Government
Internal controls and governance
Management and administration

This report examines selected areas of government activity to see if sufficient information was available to identify and assess changes in productivity. The areas examined were primary and secondary school public education, acute inpatient care in NSW public hospitals, CityRail, the NSW Police Force, and the NSW Local Court. Productivity is commonly defined as the amount of output per unit of input.   Parliamentary reference - Report number #256

Published

Actions for Implementing performance audit recommendations

Implementing performance audit recommendations

Premier and Cabinet
Treasury
Whole of Government
Health
Education
Community Services
Transport
Justice
Compliance
Internal controls and governance
Management and administration

NSW Government agencies have sound processes for implementing performance audit recommendations in Auditor-General’s Reports to Parliament. There are many cases of good practice. For example, some agencies formed a steering committee and developed a detailed plan to implement recommendations. Another incorporated the implementation of recommendations into both its business plan and the work plans of individual officers who were managing projects. Most ag

Published

Actions for Government advertising 2015

Government advertising 2015

Premier and Cabinet
Environment
Whole of Government
Compliance
Internal controls and governance
Procurement
Project management

The Government Advertising Act 2011 requires the Auditor-General to conduct an annual performance audit to check NSW Government agency compliance with the Act. This audit focused on the Department of Premier and Cabinet’s (DPC) role in monitoring government agencies compliance with government advertising requirements, and examined advertising campaigns run by Destination NSW and the Sydney Opera House.   Parliamentary reference - Report number #2

Published

Actions for Large construction projects

Large construction projects

Treasury
Transport
Health
Industry
Planning
Premier and Cabinet
Whole of Government
Compliance
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management

The independent assurance given to the NSW Government and sponsor agencies on the viability of large capital projects throughout their lifecycle is inadequate. Government policy is regularly not followed and not properly communicated to those responsible for implementing such policy.   This audit sought to test the effectiveness of the NSW capital project assurance system - which includes gateway reviews and reporting - but significant levels of non

Published

Actions for Security of critical IT infrastructure

Security of critical IT infrastructure

Transport
Planning
Compliance
Information technology
Internal controls and governance
Management and administration
Risk

Roads and Maritime Services and Transport for NSW have deployed many controls to protect traffic management systems but these would have been only partially effective in detecting and preventing incidents and unlikely to support a timely response. There was a potential for unauthorised access to sensitive information and systems that could have disrupted traffic.   Until Roads and Maritime Services’ IT disaster recovery site is fully commissioned, a

Published

Actions for The Millennium Train Project

The Millennium Train Project

Transport
Infrastructure
Procurement
Project management
Service delivery

State Rail has made significant improvements since the purchase of the Tangara. It improved measures necessary for handling contracts dealing with technically complex and innovative projects, although some other problems have been encountered, with new lessons to learn. The design and manufacture of new trains requires a significant investment in both time and cost. The Millennium Train has come at a considerably higher price than originally expected. An

Published

Actions for Delivering Services Online

Delivering Services Online

Transport
Information technology
Internal controls and governance
Service delivery
Shared services and collaboration

A staged, systematic and careful approach and extensive business re-engineering effort underpinned the Roads and Traffic Authority's (RTA) steady progress in providing customers with a range of reliable and secure online registration services. The RTA’s consistent and disciplined pursuit of new and challenging e-business opportunities is commendable.   Parliamentary reference - Report number #111 - released 11 June 2003

Published

Actions for Outsourcing Information Technology

Outsourcing Information Technology

Whole of Government
Information technology
Management and administration
Procurement

Agencies have managed the planning of outsourcing in a competent way. All agencies satisfactorily managed the contractual aspects of outsourcing. The Audit Office is of the opinion, however, that there is no objective evidence to demonstrate that agencies have achieved their goals in outsourcing IT. Most agencies had identified the current and expected costs and risks of outsourcing. Agencies were not able to demonstrate that the actual costs of outsourc