Actions for WestConnex: changes since 2014

WestConnex: changes since 2014

Transport
Compliance
Infrastructure
Internal controls and governance
Management and administration
Project management
Risk

What the report is about

The report examined whether Transport for NSW (TfNSW) and Infrastructure NSW (INSW) effectively assessed and justified major scope changes to the WestConnex project since 2014.

What we found

NSW Government decisions to fund WestConnex-related projects outside WestConnex's $16.812 billion budget have reduced transparency and understate the full cost of WestConnex.

The NSW Government's decision to separate Sydney Gateway from WestConnex has reduced transparency over the cost of the road component of Sydney Gateway. $1.76 billion of the cost to complete Sydney Gateway is funded outside the WestConnex budget.

Network integration costs, currently estimated at $2.3 billion, are also funded outside the WestConnex budget. Many of these costs are directly attributable to WestConnex and ought to be included in the reported budget.

The Parramatta Road Urban Amenity Improvement Program, costing $198 million, should also be included as part of the WestConnex reported budget.

Decisions to exclude or remove these elements from WestConnex without justification have seen $4.26 billion of projects funded outside the $16.8 billion budget.

Positively, robust analysis was used to develop and incorporate design improvements into the 2015 WestConnex Updated Strategic Business Case.

The separate components of WestConnex underwent all required assurance reviews. However, the NSW Government's assurance framework does not require ongoing ‘whole-of-program’ assurance for large and complex projects like WestConnex. The absence of a holistic review of WestConnex allows for some costs and benefits to avoid scrutiny.

What we recommended

TfNSW should:

  • review the impact of scope changes on project objectives, costs and benefits for complex infrastructure projects
  • ensure that estimated costs and benefits of works which are reasonably required to meet consent conditions are included in business cases for complex large infrastructure projects
  • establish centralised and project specific record keeping for major infrastructure projects.

Infrastructure NSW should provide transparent whole of program assurance on total costs and benefits when complex projects are split into sub-projects.

Government should consider enhancing public transparency of existing infrastructure assurance processes by requiring that large complex infrastructure programs undergo periodic review at a whole-of-program level.

Fast facts

  • $16.812b 2015 WestConnex business case budget
  • $2.3b current estimated cost of network integration works to enable WestConnex, funded outside the WestConnex budget
  • $1.76b cost to complete Sydney Gateway to enable WestConnex and also funded outside the WestConnex budget
  • $198m Parramatta Road Urban Amenity Improvement Program, originally part of WestConnex but now funded outside the WestConnex budget

WestConnex

WestConnex is a 33 km motorway network that will link the western and south‑western suburbs with the Sydney CBD and the Airport and Port Botany precinct. It will also connect with proposed future motorway links to the north shore, northern beaches, and southern Sydney. The project is being delivered in three stages, with completion scheduled for 2023.

When first conceived by Infrastructure NSW (INSW) in 2012, WestConnex was described as a single integrated concept. In August 2013, government approved a business case for an integrated concept of WestConnex, with an estimated cost of $14.881 billion (in nominal outturn costs). Transport for NSW (TfNSW) is the government agency (sponsor agency) accountable for the delivery of WestConnex in accordance with the business case. In August 2014, the NSW Government established the Sydney Motorway Corporation to fund, deliver and operate WestConnex.

In November 2015, the NSW Government publicly released an updated WestConnex business case with greater detail and design enhancements, which increased the estimated cost to $16.812 billion.

Subsequent to this update, further changes were made to the design, including realignment of the M4 to M5 Link connection to the Western Harbour Tunnel project, an expanded interchange at Rozelle, the deletion of the Camperdown Intersection, and the addition of the Iron Cove Link. The reported budget for WestConnex was not changed as a result of these design updates.

To fund WestConnex, Sydney Motorway Corporation consolidated a concessional loan of $2 billion from the Australian Government, private sector debt and equity funding from the State. The Australian Government also provided a $1.5 billion contribution to the State to partially fund construction of WestConnex.

In August 2018, the NSW Government sold 51 per cent of its stake in Sydney Motorway Corporation for $9.26 billion. At the time of writing, the NSW Government is in the process of selling its remaining 49 per cent stake of Sydney Motorway Corporation.

About this audit

In the course of delivering a complex major infrastructure project, it is reasonable to expect changes to the original design and scope. Changes may occur as the design moves from a high‑level concept to a detailed design for project delivery, as new risks or issues are identified, as demands change, or as other interdependent projects are approved. Changes can also occur in response to potential cost or delivery overruns which arise as a result of planning deficiencies. Where design and scope changes significantly change the project costs and/or expected benefits, the justification for these changes should be robust and transparent.

Following our 2014 performance audit, 'WestConnex: Assurance to the government', the NSW Government established the Infrastructure Investor Assurance Framework (IIAF) to improve accountability and transparency over major projects that are developed, procured, or delivered by government agencies. Under the framework, TfNSW, as project sponsor, is responsible for ensuring the WestConnex project meets all IIAF requirements. These include ensuring the project remains strategically aligned and viable, and benefits are on track. INSW is responsible for coordinating the assurance review process and reporting directly to NSW Cabinet on project delivery against time, budget and risks to project delivery.

The objective of this performance audit is to assess whether TfNSW and INSW effectively assessed and justified major scope changes to the WestConnex project since 2014.

 

Conclusion

Government decisions to separate WestConnex related projects and deliver them outside WestConnex's 2015 business case budget of $16.812 billion has understated the total cost of WestConnex achieving its objectives. The rationale for separating these elements from the WestConnex project scope has not been transparent. Together, these projects represent costs of $4.26 billion funded outside the $16.812 billion WestConnex budget.

Since 2015, the NSW Government has removed several projects from the scope described in the 2015 WestConnex business case, and funded them separately:
  • In mid‑2017, the Sydney Gateway became a separate project outside WestConnex. This project, estimated in 2015 to cost $800 million, now has an estimated cost of $2.56 billion. The project remains partly funded by an $800 million contribution from the $16.812 billion WestConnex budget, with $1.76 billion funded outside the WestConnex budget.
  • In late 2018, the Parramatta Road Urban Amenity Improvement Program became a separate project outside the 2015 WestConnex budget. This project was part of the 2015 WestConnex Business Case and is intended to create urban renewal opportunities around Paramatta Road. It is estimated to cost $198 million.

Work required to integrate WestConnex with existing roads ('network integration') was funded outside the $16.812 billion budget for the November 2015 WestConnex business case. TfNSW is obliged to deliver network integration works to meet the conditions of planning approval for WestConnex. As such, these costs should be included in the WestConnex budget. The current estimated cost of these network integration works is $2.3 billion.

The rationale to exclude or remove each of these elements from the WestConnex project scope has not been transparent, nor supported by robust analysis and justification. These elements are required for WestConnex to achieve its objectives. The additional project costs will also deliver additional benefits not included in the 2015 WestConnex business case. Removing them understates the total cost of achieving the objectives set out in the 2013 and 2015 WestConnex business cases.

WestConnex's complex financing arrangements further reduce transparency on costs.

Transparency over the total cost of WestConnex – including elements funded from other project budgets – is further limited by the project's complex financing arrangements.

Prior to 2018, the Audit Office provided assurance on costs borne and levied by Sydney Motorway Corporation and its controlled entities. Since the NSW Government sold its majority stake in WestConnex in August 2018, the Auditor‑General no longer has the mandate to provide this assurance. Considering this, and the lack of transparency on the cost of projects removed from the WestConnex project scope, there is no transparent or comprehensive view of the total cost to deliver WestConnex – nor of how these cost would be offset by the sale of the government's remaining stake.

There is no 'whole‑of‑program' assurance over the WestConnex program of works. This limits transparency and confidence that WestConnex will meet intended objectives within its budget.

After INSW conducted a gateway review of a draft of the 2015 WestConnex Business Case under the IIAF, the project was broken up into separate components to support staged delivery. Each of these projects, including the Sydney Gateway, as well as the Network Integration Program, underwent the required assurance reviews under the IIAF. INSW also provided monthly progress updates to government. These individual projects are, in themselves, significant in scale and complexity. Addressing them as discrete components for the purposes of the assurance review process is justified and there is no requirement under the IIAF to holistically review projects which together deliver final benefits of the WestConnex program. However, whole‑of‑program review would improve transparency over total costs and benefits.

In 2016, TfNSW revised the design of the M4‑M5 Link and Rozelle to address traffic and integration issues.

TfNSW identified that the concept designs used for the M4‑M5 Link and Rozelle Interchange in the 2015 WestConnex Business Case would not integrate well with surface roads, including the proposed Bays Precinct, and would result in increased traffic on Victoria Road and the ANZAC Bridge. Following a comprehensive review conducted in mid‑2016, TfNSW refined the design of the M4‑M5 Link and Rozelle Interchange to address these limitations without increasing the cost of delivery. TfNSW documented the rationale for the design changes, including how the changes improved on the original design to increase capacity, improve traffic conditions and create more open space.

1. Key findings

Government decisions to fund WestConnex related projects outside of WestConnex's $16.812 billion reported budget have reduced transparency over costs and understate the full cost of WestConnex

In 2015, the work required to integrate WestConnex with existing roads ('network integration') was funded as a separate project with an estimated cost of $1.534 billion outside the 2015 WestConnex budget of $16.812 billion. TfNSW then created the Network Integration Program to respond to the conditions of planning approval for WestConnex. The current estimated cost to deliver all network integration works is $2.3 billion.

Since the 2015 WestConnex Business Case, the NSW Government has removed several elements from the scope of WestConnex and funded them as separate projects, while keeping the published WestConnex budget at an estimated $16.812 billion. Projects removed include:

  • Sydney Gateway, currently costed at $2.56 billion (with an $800 million contribution from WestConnex)
  • Parramatta Road Urban Amenity Improvement Program, costed at $198 million in late 2018 and funded though new funding to the Greater Sydney Commission.

Together, these projects represent costs of $4.26 billion that are not included in the WestConnex budget, but are required for WestConnex to achieve the objectives of the 2013 and 2015 WestConnex Business Cases. The costs of these elements in supporting the objectives of WestConnex is not tracked centrally, and there is no single point of oversight over them. Exhibit 1 compares total WestConnex forecast costs (including related projects) between November 2015 and April 2021.

 

November 2015
($ million)

April 2021
($ million)
WestConnex
Stage 1
Stage 1A (M4 Widening) 497 517
Stage 1B (M4 East) 3,802 3,782
Total 4,299 4,299
Stage 2
King Georges Road Interchange 131 131
New M5 4,335 4,335
Sydney Gateway Contribution 800 800
Total 5,266 5,266
Stage 3
M4‑M5 Link and Rozelle Interchange 7,049 7,049
Urban renewal (Parramatta Road) 198 ‑‑
Urban renewal (Rozelle) ‑‑ 198
Total 7,247 7,247
Total reportable WestConnex 16,812 16,812

Exhibit 1: WestConnex and related projects forecast costs
  November 2015
($ million)
April 2021
($ million)
Related projects
Network integration 1,534 2,300
Urban renewal (Parramatta Road) ‑‑ 198
Sydney Gateway Road Component ‑‑ 1,760
Total 1,534 4,258

Source: AO research.

Many network integration costs are directly attributable to WestConnex and ought to be included in the reported budget for WestConnex

Prior to 2015, the scope of WestConnex included enabling works needed before or during construction, as well as funding for future works to address any adverse traffic outcomes created by WestConnex which become apparent after its opening. These works are also known as network integration works.

When government approved the 2015 WestConnex Business Case, it noted that the project would require $1.534 billion for network integration works to address the impacts of WestConnex on the road network. However, the WestConnex project budget of $16.812 billion did not include funding for network integration works. Instead, Roads and Maritime Services (RMS, now TfNSW) was to fund network integration through its normal budget allocation.

It is important to recognise these costs as part of the total WestConnex project cost because:

  • TfNSW created the Network Integration Program to respond to network traffic and transport elements of the planning conditions of approval for WestConnex granted by the then NSW Department of Planning and Environment under the Environment, Planning and Assessment Act 1979.
  • NSW Treasury guidelines for business cases note that accurate cost estimates include assessment of the financial impact of meeting the conditions of planning approval.
  • Travel time and vehicle operating cost benefits attributed to the WestConnex project in the 2015 WestConnex Business Case assume that some network integration works, then costed at $373 million, were in place.

Refer to Appendix two for more detail on network integration works.

Some of the projects in the WestConnex Network Integration Program provide community and place benefits, such as parklands and cycleways. These benefits have not been attributed to WestConnex. Additionally, some network integration works are likely to deliver additional traffic related benefits to WestConnex. As the Network Integration Program’s primary purpose is to meet the conditions of planning approval for WestConnex, TfNSW should attribute all the costs and benefits of the program to WestConnex.

To September 2021, the total funded cost of the Network Integration Program is approximately $2.077 billion. TfNSW estimates that it will need a further $222 million to complete all expected network integration works.

The NSW Government's decision to separate Sydney Gateway from WestConnex has reduced transparency and accountability for TfNSW's underestimation of the cost of the road component of Sydney Gateway

Sydney Gateway is a high‑capacity connection between the new St Peters Interchange and the Sydney Airport and Port Botany precinct. It includes a road and rail components. The road component was included in the scope of WestConnex in the 2015 WestConnex Business Case. The November 2015 design, which TfNSW costed at $800 million, involved separate roadways from the St Peters Interchange to the International terminal, and to the domestic terminals and Mascot airport precinct.

By October 2016, TfNSW was aware that the $800 million budget for Sydney Gateway was insufficient and revised the forecast cost for the road component to $1.8 billion. The original cost estimate did not sufficiently consider the cost of:

  • constructing a complex design adjacent to the airport precinct
  • obtaining access to land required for the project
  • managing environmental contamination.

On 9 August 2017, the then Minister for WestConnex announced that the Sydney Gateway project was not part of WestConnex.

The 2015 WestConnex Business Case notes that material changes to the WestConnex budget, funding, scope, or timeframe are subject to Cabinet approval processes. It states that, when seeking approval for material changes, the portfolio Minister will make a submission to the relevant Cabinet Committee. Changes in project scope required the approval of the then Cabinet Committee on Infrastructure and should have been endorsed by the WestConnex Interdepartmental Steering Committee.

TfNSW and the NSW Department of Premier and Cabinet (DPC) assert that there is no documentation to support the government’s decision to separate Sydney Gateway from the WestConnex Program, or the WestConnex Interdepartmental Steering Committee's endorsement of a submission to Cabinet seeking approval for the separation.

The established governance processes for major scope changes were not followed in this instance. The lack of transparency regarding government's decision to separate Sydney Gateway from WestConnex also reduces visibility of TfNSW's underestimation of the cost of delivering the road component of Sydney Gateway.

The November 2018 Final Business Case for Sydney Gateway, which was approved by the government, included an estimate of $2.45 billion (nominal outturn cost) for the road component. This estimate included an $800 million contribution from WestConnex. A more recent estimate (late 2020) for this project is $2.56 billion (nominal outturn cost).

The Parramatta Road Urban Amenity Improvement Program should be included as part of the WestConnex budget

A specific objective of the 2015 WestConnex Business Case was the creation of opportunities for urban renewal along and around Parramatta Road. The business case included an allocation of $198 million in the $16.812 billion WestConnex budget for the Parramatta Road Urban Amenity Improvement program, designed to implement aspects of the objective. In November 2018, the NSW Government removed the Parramatta Road Urban Amenity Improvement Program from the WestConnex program of works and reallocated the $198 million (inside the $16.812 billion WestConnex budget) for urban renewal works around the Rozelle Interchange. As part of this decision, government approved new funding of $198 million to the Greater Sydney Commission for the urban amenity program, outside the $16.812 billion WestConnex budget. This understates the cost of WestConnex meeting its objectives by $198 million.

There is no requirement for ongoing ‘whole‑of‑program’ assurance of the WestConnex program of works, including related projects

In August 2015, INSW conducted its first Gateway Review of WestConnex as a program consisting of composite projects. Following that review, TfNSW registered each of the components of WestConnex with INSW as individual projects, rather than keeping WestConnex registered as a program or mega‑project. This is not inconsistent with the IIAF and all WestConnex related projects, including Sydney Gateway and the Network Integration Program, have undergone independent assurance reviews as individual projects under the IIAF.

Once a program like WestConnex is broken down into its composite parts, there is no requirement for the sponsor agency (TfNSW) or INSW to provide independent assurance on the program as a whole until it is completed. This is then done as part of the Gateway review for benefits realisation, which examines whether project benefits are being measured and meet expectations. These individual projects are, in themselves, significant in scale and complexity. While addressing them as discrete components for the purposes of the assurance review process can be justified, the absence of strategic, holistic reviews of WestConnex allows for total costs and benefits to become opaque and avoid scrutiny. Programs of this scale require greater ongoing transparency on total costs and benefits in order to ensure confidence they will meet intended objectives within budget.

There is a lack of public transparency on the total costs and benefits of the WestConnex project

Prior to 2018, the Audit Office provided assurance on costs borne and levied by Sydney Motorway Corporation and its controlled entities. Since the NSW Government sold 51 per cent of its stake in WestConnex in August 2018, the Auditor‑General no longer has the mandate to provide this assurance. The Audit Office is also unable to provide any assurance regarding the performance of tolling concessions.

This means that the total costs of WestConnex, including those levied on road users through tolling, are not reported alongside the full cost of delivering the project. This information, and independent assurance over that information, would provide transparency and context to the outcome of government's sale of its interest in WestConnex.

To enhance the transparency of existing infrastructure assurance processes, government could consider requiring large and complex infrastructure programs to undergo periodic review at a whole‑of‑program level. This could take the form of annual reports to Parliament on the total costs and benefits of selected large and complex projects by the responsible agency. The reports could include an assessment of the cost to government and cost to the community of funding and financing. Independent assurance of the agency report would provide Parliament with greater confidence that infrastructure is delivered economically and providing value for money for the people of NSW.

The Australian National Audit Office provides similar assurance on selected Department of Defence acquisition projects as part of its annual Major Projects Report.

Design enhancements included in the 2015 WestConnex Updated Strategic Business Case were supported by robust analysis

The 2015 WestConnex Business Case contained more detail than the 2013 WestConnex business case. Design enhancements were made as a result of modelling analysis conducted over the two years since the 2013 business case. Enhancements included a full underground link between Kingsgrove and St Peters as part of the New M5 and re‑alignment of the M4‑M5 link tunnel (Stage 3) to include the Rozelle Interchange. The Rozelle Interchange will provide a direct connection to the Anzac Bridge and Victoria Road, and will enable a connection to the proposed Western Harbour Tunnel and Beaches Link. A map and description of these elements can be found at Exhibits 2 and 3 of this report.

In 2016, TfNSW revised the design of the M4‑M5 Link and Rozelle to address traffic and integration issues

As part of preparing the 2015 WestConnex Business Case, TfNSW prepared a Project Definition and Delivery Report (PDDR) for the M4‑M5 Link. This report describes the scope of the project, including a high‑level concept design. TfNSW identified limitations with the proposed design of the M4‑M5 in the PDDR, which it would need to address as the project moved to a detailed design stage. In particular, these limitations included:

  • poor integration with the Bays Precinct masterplan
  • traffic capacity constraints on Victoria Road and Anzac Bridge
  • construction complexity.

Following a comprehensive review in mid‑2016, TfNSW changed the design of the M4‑M5 Link and Rozelle Interchange to address these limitations. These changes included:

  • deletion of the Camperdown intersection to improve traffic conditions on Parramatta Road
  • a fully underground and larger Rozelle Interchange with 10‑hectare dedicated parklands
  • a toll‑free tunnel link from Iron Cove Bridge to Anzac Bridge
  • increasing the lanes in the dual tunnels from three to four each way.

TfNSW documented, but did not publish, the rationale for the design changes, including how the changes addressed the limitations of the previous design while providing increased community benefit through the creation of open space. TfNSW undertook cost comparison studies which estimated that these changes would have a neutral impact on the estimated project cost while achieving the same or improved benefits.

TfNSW's record‑keeping systems for large infrastructure investments negatively impact accountability and transparency

In response to our formal requests for relevant information, made during the conduct of this audit, TfNSW advised that complete and valid records of key decision‑making processes, analysis and advice were unavailable. Additionally, TfNSW often provided information that was incomplete or unverifiable (for instance, unsigned briefing notes). This is not consistent with accepted governance practices and does not comply with the requirements of the State Records Act 1998.

We also requested that TfNSW provide a list of relevant documents held by the Sydney Motorway Corporation (SMC). While TfNSW acknowledged that SMC may hold material relevant to the audit, TfNSW did not have a list or description of these documents. As SMC is now a majority privately held entity, both the Audit Office and TfNSW have limited power to require SMC to provide documentation.

The delivery timeframe for large and complex infrastructure projects such as WestConnex frequently exceeds five years, and some projects can take over a decade to deliver. These projects represent a significant investment of public resources and government agencies should expect independent review and assurance activities such as performance audits. The establishment of dedicated record keeping facilities for major infrastructure projects, such as data rooms, would improve transparency and accountability. This would ensure that the use of public resources is fully auditable in line with public expectations and the requirements of the Government Sector Finance Act 2018, the State Records Act 1998 and the Public Finance and Audit Act 1983.

2. Recommendations

By December 2021, TfNSW should:

1. review the impact of scope changes on project objectives, costs and benefits for complex infrastructure projects

2. when preparing business cases for complex large infrastructure projects, ensure that the estimated costs and benefits of works which are reasonably expected to meet consent conditions are included in the overall project cost and its benefits (as per Treasury guidelines)

3. establish and maintain centralised and project‑specific record keeping, including through dedicated project data rooms, to ensure major infrastructure projects can readily be subject to external oversight and assurance.

By June 2022, INSW should:

4. provide transparent whole‑of‑program assurance on total costs and benefits throughout the project life‑cycle when complex projects are split into sub‑projects.

By June 2022, NSW Government should:

5. consider enhancing the public transparency of existing infrastructure assurance processes by requiring that large complex infrastructure programs undergo periodic review at a whole‑of‑program level. This could take the form of reports to Parliament on the total costs and benefits on selected large and complex projects by the responsible agency, including cost to government and cost to community of funding and financing, as well as an accompanying independent assessment of the agency report.

Following our 2014 performance audit report 'WestConnex: Assurance to the government', the NSW Government established the Infrastructure Investor Assurance Framework (IIAF). INSW is responsible for the development, implementation and administration of the IIAF. The assurance framework involves gateway reviews, health checks, deep dive reviews, and project monitoring and reporting at various stages in the lifecycle of a project. The main aims of the IIAF are to help ensure major infrastructure projects are delivered on time and on budget, and to ensure that reports are regularly monitored by the Cabinet of the NSW Government. The IIAF gateway review process is compulsory for all significant investments and expenditure under the NSW Treasury Gateway Policy.

In accordance with the IIAF, INSW is responsible for the following:

  • providing a dedicated Assurance Team including Gateway Review Managers to coordinate Reviews
  • determining appropriate expert reviewers, and manages scheduling, commissioning and administration of Assurance Review reports. Infrastructure NSW is independent of the Expert Review Team
  • monitoring Tier 1 – High Profile/High Risk projects, Tier 2 and Tier 3 (if required) project performance through independent Assurance Reviews
  • providing independent analysis and advice on key risks and any corrective actions recommended for Tier 1 – High Profile/High Risk, Tier 2 and Tier 3 projects
  • escalating projects to Infrastructure Investor Assurance Committee (IIAC) and Cabinet where projects present ‘red flag issues’ and where corrective action is needed
  • working with delivery agencies to register all capital projects with an estimated cost greater than $10.0 million and ensures they are risk profiled and assigned a risk‑based project tier with an endorsed IIAF Project Registration report
  • preparing forward looking annual Cluster Assurance Plans
  • maintaining and continuously improves the IIAF process
  • reporting to the IIAC, Cabinet and Infrastructure NSW Board
  • regularly report to NSW Treasury on the performance of the IIAF.

In relation to WestConnex, TfNSW is the sponsor agency responsible for meeting relevant IIAF requirements, including:

  • registering and risk profiling projects
  • IIAF gateway, health check, and deep dive assurance reviews
  • regular reporting.

Under the IIAF, it is mandatory for all capital projects valued over $10.0 million to be registered with INSW. Capital projects can be registered either as a program (comprising of a group of related projects or activities) or as a project (which may or may not be part of a program).

According to the IIAF, programs tend to have a lifespan of several years and aim to deliver outcomes and benefits related to an organisation's strategic objectives. Projects tend to have a shorter lifespan, and deal with outputs. Projects can, however, be grouped under a single program if they are similar in nature or if they are aimed at collectively achieving a strategic objective. Complex projects can be delivered in multiple stages, under different contracts, and across different time periods.

The last assurance review of the entire WestConnex program of works as a whole was in 2015

INSW conducted the first IIAF gateway review of WestConnex in August 2015. TfNSW developed a draft WestConnex Updated Strategic Business Case to consolidate the latest analysis on WestConnex, and to confirm that the project remained fit for purpose, economically viable, and financially deliverable. The review followed a recommendation in our 2014 performance audit report that business cases be thoroughly revisited.

During September 2015, INSW conducted additional informal reviews to identify strategic risks associated with public release of the WestConnex business case. Subsequently, INSW gave the Premier of NSW its views on the draft business case, including the following points:

  • The $398 million budget for Sydney Gateway was insufficient to meet the benefits claimed in the business case for a ‘functional’ connection to Sydney Airport and Port Botany. INSW studies indicate a future‑proof solution would require a minimum spend of $755 million.
  • Enabling works for WestConnex estimated at $1.534 billion were excluded from the cost of WestConnex. Significant work remained for RMS to identify mitigation measures to address planning approvals and network performance issues.
  • Enabling works (a Southern Connector), an access ramp and surface road improvements within St Peters were excluded from the draft 2015 business case despite their inclusion in the WestConnex scope in the 2014–15 State Budget.
  • The overall cost of works not funded within the WestConnex budget ranged from $2.011 billion to $2.196 billion. This included the enabling works, access ramp and surface road improvements and the shortfall for Sydney Gateway.

All WestConnex related projects, including Sydney Gateway have undergone independent assurance reviews under the IIAF

Since INSW submitted the first WestConnex progress update report to Cabinet in June 2015, INSW has been reporting monthly on the different stages of the WestConnex Program, including Sydney Gateway, as the projects were registered with INSW as High‑Profile, High‑Risk projects. Separate reporting enabled INSW to report and review each stage with more detailed scrutiny, compared to the reporting and reviewing at a program level.

WestConnex Stage 2 (New M5) underwent both mandatory and non‑mandatory reviews at key points in the project lifecycle. Three mandatory gateway reviews – at Gate 2 (Final business case), Gate 3 (Readiness for market), and Gate 4 (Tender evaluation) – were conducted by TfNSW before the introduction of IIAF. Four non‑mandatory health check reviews and one non‑mandatory deep dive review were conducted after the introduction of the IIAF managed by INSW.

Similarly, WestConnex Stage 3 projects – M4‑M5 link, M4‑M5 Tunnels, and Rozelle Interchange – also underwent mandatory and non‑mandatory reviews at key points in their lifecycle under IIAF.

The M4‑M5 Link had two mandatory gateway reviews and one non‑mandatory health check review under IIAF. These reviews were conducted before Stage 3 was split into two stages, due to major design changes to the Rozelle Interchange and the M4‑M5 tunnels.

The M4‑M5 tunnels had two mandatory gateway reviews (at Gates 3 and 4), one non‑mandatory health check review, and one non‑mandatory deep dive review under IIAF.

Rozelle Interchange also underwent three mandatory gateway reviews at Gate 3 (part 1), Gate 3 (part 2), and Gate 4, two non‑mandatory health check reviews, and one non‑mandatory deep dive review under IIAF.

Since mid‑2017, the Sydney Gateway project has undergone required independent assurance reviews, as well as a number of optional assurance reviews

In November 2016, INSW conducted a mandatory Gate 1 gateway review on a strategic business case for the Sydney Gateway Project. TfNSW did not proceed with this business case. Following the separation of Sydney Gateway from WestConnex in mid‑2017, TfNSW developed a new business case for Sydney Gateway. It has undergone the required Gate 1, Gate 2, and Gate 3 gateway reviews, as well as two non‑mandatory health check reviews, and three non‑mandatory deep dive reviews under IIAF.

Network integration works have undergone all IIAF required assurance reviews

TfNSW completed a strategic business case for the Network Integration Program in August 2020, and INSW completed a gateway review in November 2020. This is despite network integration projects starting as early as 2015, with $645 million having been spent by June 2020. The strategic business case included a prioritisation process for completing remaining works in the program. Prior to November 2020, TfNSW registered individual network integration projects with INSW, and these projects have undergone gateway reviews where required.

The Network Integration Program strategic business case does not include Rozelle interchange network integration works ($353 million) and additional network integration works to settle a contractor claim adjacent to St Peters Interchange ($190 million). These were excluded from the business case on the basis they had already been approved by government, and as such were not subject to the prioritisation elements of the business case. TfNSW has not developed separate business cases for these works, although the scope of the St Peters Interchange works was developed through a negotiated process.

TfNSW did not prepare business cases for some network integration works which have commenced, including the $323 million Campbell Road/Euston Road works

Prior to its development of the August 2020 strategic business case, TfNSW did not prepare business cases for many network integration works that have commenced, and in some instances were completed, before 2019. Significantly, TfNSW did not prepare a business case for the Campbell Road/Euston Road works, which cost $323 million and have been completed.

In 2016, TfNSW’s Business Case Policy requires the creation of business cases for capital projects costing over $1.0 million. At the time of writing this report, TfNSW’s draft policy requires full business cases for capital projects costing $10.0 million or more.

There is no requirement for ongoing ‘whole‑of‑program’ assurance of the WestConnex program of works, including related projects

INSW conducted its first gateway review of WestConnex (as a program, which consisted of composite projects) in August 2015. Following that review, TfNSW registered each of the components of WestConnex with INSW as individual projects, rather than keeping WestConnex registered as a program or complex project. The IIAF allows this to occur.

Separate registration enabled INSW to report and review each stage with more scrutiny compared to whole‑of‑program level review.

Such an approach has merit, considering the individual stages (and components of these stages) are multi‑million dollar works in their own right. Each project has its own timing for gateway reviews at stages such as 'Readiness for Market' and 'Tender Evaluation'.

Once a program such as WestConnex is broken down into its composite parts, there is no requirement for the sponsor agency (TfNSW) or INSW to conduct independent assurance on the program of works as a whole until the whole program is completed as part of the Benefits Realisation (Gate 6) gateway review. The absence of strategic, holistic reviews of projects of the scale and complexity such as WestConnex during their delivery allows for total costs and benefits to become opaque and avoid scrutiny. Projects of this scale require greater ongoing transparency on total costs and benefits in order to ensure confidence they will meet intended objectives within budget.

INSW has advised us that it has prepared a proposal to expand its assurance function to include whole‑of‑program review of inter‑related infrastructure projects.

Appendix one – Responses from agencies

Appendix two – Network integration works

Appendix three – About the audit

Appendix four – Performance auditing

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #351 - released (17 June 2021).

Published

Actions for Acquisition of 4–6 Grand Avenue, Camellia

Acquisition of 4–6 Grand Avenue, Camellia

Transport
Asset valuation
Compliance
Fraud
Infrastructure
Internal controls and governance
Management and administration
Procurement
Risk

The Auditor-General for New South Wales, Margaret Crawford, has today released a report on Transport for NSW’s (TfNSW) acquisition of 4–6 Grand Avenue in Camellia.

This audit, which was requested on 17 November 2020 by the Hon. Andrew Constance MP, the Minister for Transport and Roads, examined:

  • whether TfNSW conducted an effective process to purchase 4–6 Grand Avenue, Camellia
  • whether TfNSW has effective processes and procedures to identify and acquire property required to deliver the NSW Government’s major infrastructure projects.

The audit found that TfNSW conducted an ineffective process when it purchased 4–6 Grand Avenue, Camellia. The audit also found that TfNSW’s internal policies and procedures to guide the transaction were, and continue to be, insufficient.

The Auditor-General has made seven recommendations to address the issues identified in the report.

On 17 November 2020, the Hon. Andrew Constance MP, the Minister for Transport and Roads, requested this audit under section 27B(3)(c) of the Public Finance and Audit Act 1983.

On 15 June 2016, Transport for New South Wales (TfNSW) acquired 6.3 hectares of land at 4–6 Grand Avenue, Camellia, by agreement from Grand 4 Investments Pty Ltd. Grand 4 Investments was a business entity established by the owners of Billbergia Pty Ltd, a property development and investment company.

TfNSW paid Grand 4 Investments $53.5 million and assumed liability for addressing environmental issues and contamination associated with the site. This took place seven months after the vendor acquired the land as part of a competitive Expression of Interest process, in which TfNSW also participated, for $38.15 million.

TfNSW is the NSW Government agency responsible for most major transport infrastructure projects in New South Wales. TfNSW acquired the Camellia site for use as a stabling and maintenance depot to support the Parramatta Light Rail (PLR) project.

Consistent with the minister’s request, this audit assessed:

  • whether TfNSW conducted an effective process to purchase 4–6 Grand Avenue, Camellia
  • whether TfNSW has effective processes and procedures to identify and acquire property required to deliver the NSW Government’s major infrastructure projects.

In considering the effectiveness of the processes for this purchase, the audit considered:

  • the requirements of the Land Acquisition (Just Terms Compensation) Act 1991 (the Act)
  • the application of sound processes to manage risk to the NSW Government and to achieve value for money
  • the application of disciplines associated with complex procurement, such as probity, in a NSW Government context.
The acquisition of the 4–6 Grand Avenue site in Camellia was consistent with a 2014 feasibility study for the PLR, but occurred before the completion of detailed project planning or an acquisition strategy.

TfNSW made two attempts to acquire the 4–6 Grand Avenue site in Camellia, and was successful on the second attempt. TfNSW recognised the risks associated with early acquisition and had high-level strategies in place should the site not be required.

The specific site had been identified in a feasibility study for the PLR commissioned by TfNSW in 2014 as one of several options in Camellia for a stabling and maintenance depot. However, TfNSW had not done any substantive analysis of the various options to identify a preferred location before the two opportunities to acquire 4–6 Grand Avenue were brought to TfNSW’s attention by the landowners (or their agents). On both occasions, TfNSW chose to actively pursue acquisition in advance of any such analysis.

The acquisition was also not informed by a Property Acquisition Strategy, which TfNSW policy recommends in order to guide the process and manage acquisition specific risks.

In 2015, TfNSW identified that it would require a stabling and maintenance depot in the Camellia area for the Parramatta Light Rail

In 2014, TfNSW commissioned an external engineering consultancy to undertake a feasibility design study for the Parramatta Light Rail - the Parramatta Transport Corridor Strategy Feasibility Design study (herein referred to as ‘the feasibility study’). In early 2015, TfNSW received the feasibility study, which was one of several key sources that informed the development of business cases for the PLR.

The feasibility study recommended that TfNSW should consolidate the maintenance and cleaning operations with overnight stabling facilities on one site. The study noted that the optimal location for any such site would be in close proximity to the proposed network, and noted that the site must have access to road connections to accommodate access for cars and trucks.

The study found that a centrally located stabling and maintenance facility would be required for all routes serving the Parramatta CBD, and that the Camellia industrial area was a preferred location for such a facility. The study noted that the Camellia area was contaminated.

The feasibility study notes that its conclusions were based on assumptions about the light rail system adopted and decisions made by the future operator of the system, who had not yet been selected or appointed.

TfNSW's decision to progress a potential acquisition in 2015 considered the risk that the site may not be required

TfNSW's FIC was responsible for making decisions on funding allocations at a whole of program level within TfNSW. FIC was also responsible for approving ‘high-risk/high-value’ variations to program budgets. Members of the FIC included:

  • Secretary of Transport for NSW
  • Deputy Secretary, Infrastructure and Services
  • Deputy Secretary, Freight, Strategy and Planning
  • Deputy Secretary, Customer Services
  • Deputy Secretary Finance and Investment
  • Deputy Secretary People and Corporate Services.

An April 2015 submission, from the then Deputy Director-General to the agency’s FIC, sought authorisation and funding approval to participate in an Expression of Interest sale process. It noted the risk that the project may not go ahead. The submission advised that:

By acquiring a strategic site now, it reduces the risk of having to pay an improved value or a value that may be subject to rapidly improving land values due to changes in land use and rezoning.

The property can be acquired for the project, held strategically and income generated by leasing the site as hardstand 1 space until the project requires the land for the Parramatta Light Rail project.

If the project does not proceed in the medium to longer term, the property can be sold at a premium to what has been paid today as property fundamentals improve.

This submission acknowledged the risks associated with environmental contamination and proposed that these risks would be managed by negotiating a contract where the remediation and associated expenses would be at the landowner’s cost. 

TfNSW assessed the 4–6 Grand Avenue site as one of several sites in Camellia that was a feasible location for a stabling and maintenance facility

The Departmental feasibility study assessed six potential sites for a stabling and maintenance facility, including 4–6 Grand Avenue, noting strengths and weaknesses of each site. A different site on Grand Avenue was assessed as the ‘base case’ option (1 Grand Avenue). The study’s comments on the 4–6 Grand Avenue site included the following:

With an area of approximately 63,000m2, this site has sufficient space for a depot with the required stabling yard and maintenance facilities. The location allows for good road access and LRT [light rail transit] access would be from Grand Avenue, which may require a road crossing or signalised intersection. The site has been used for general industrial uses; however the land has been cleared and is currently undergoing remediation 2. The site is not affected by flooding based on one in 100-year flood data.

In early 2015, once the opportunity to acquire 4–6 Grand Avenue emerged, TfNSW commissioned a specific feasibility study of the 4–6 Grand Avenue site. The feasibility studies clearly documented the existence of environmental contamination. In April 2015, the report concluded:

Given the limitations of this report and within the parameters that have been set it is concluded that from a spatial and geographic perspective the site at 6 Grand Avenue would be suitable as a stabling and maintenance depot for the Parramatta light rail project. There are few engineering and environmental constraints that would affect the feasibility level analysis of this site and all issues identified, within this desk study, are considered to be resolvable. However this being said there is a significant amount of work necessary to reach the final layout and definition of the stabling and maintenance depot. There are numerous items which require further consideration and conformation; planning approvals could impose restrictions on building heights, noise mitigation measures, light and visual impact requirements all of which can have significant impacts on the spatial requirements of any stabling and maintenance depot. 

The acquisition of 4–6 Grand Avenue was not informed by a Property Acquisition Strategy

For major projects, TfNSW typically requires the project team to complete a Property Acquisition Strategy, which is intended to guide both process as well as specific acquisition issues expected to be faced during the project. The Property Acquisition Strategy is not a mandated document but is a recommended tool to support property acquisition as part of major projects.

TfNSW did not have a Property Acquisition Strategy in place to guide the 2015 Expression of Interest process. On 6 November 2015, the then Project Director for the PLR project emailed the property team, noting a need to develop a Property Acquisition Strategy to close off the scoping design and preliminary business case.

In January 2016, TfNSW developed a draft Property Acquisition Strategy for the Parramatta Light Rail Project, although it was silent on the potential sites for the stabling and maintenance facility.

TfNSW focussed on 4–6 Grand Avenue because it was available and aligned to TfNSW's strategic interests

In early 2015, officials commenced monitoring the market for industrial real estate in the Camellia area and surrounds for possible sites for a stabling and maintenance facility.

In March 2015, then owner of the site, Akzo Nobel Pty Limited released the 4–6 Grand Avenue site through an Expression of Interest process managed by CBRE.

TfNSW’s then Deputy Director-General, Planning, sought approval from FIC to lodge an Expression of Interest up to $30.0 million. Approval was sought on the basis that it would ‘provide certainty for the Parramatta Light Rail project by allowing for a depot site in a suitable location and potentially avoid higher costs or longer timeframes associated with compulsory acquisition following completion of the project’s business case’. FIC approved the request at its meeting on 9 April 2015.

At this time, TfNSW had not conducted any analysis of financial or operational benefits and costs of the potential sites identified in earlier feasibility studies. TfNSW staff advised us that the decision to participate in the Expression of Interest process for 4–6 Grand Avenue was because it was available. There is no documentation substantiating this statement, which TfNSW staff provided verbally as part of this audit.

In November 2015, TfNSW was advised that it was unsuccessful in the Expression of Interest process and that Grand 4 Investments (a related entity of Billbergia) had purchased 4–6 Grand Avenue. TfNSW did not conduct any further analysis of alternative potential sites in Camellia between this date and commencing discussions with Grand 4 Investments in April 2016. In that time there had been some movement on other properties that were included in the feasibility study, including 37–39a Grand Avenue being under offer in September 2015.

In March 2016, TfNSW approached CBRE to organise a meeting with Grand 4 Investments. On 1 April 2016, TfNSW met with Grand 4 Investments.

TfNSW advises that a perceived benefit of the 4–6 Grand Avenue site was that it was not subject to other uses or leaseholds that would increase the cost of compulsory acquisition. Officers involved in the acquisition advised that other nominated sites in the feasibility study were subject to other uses or leaseholds. 


1  A hardstand space is a large, paved area to store cars, heavy vehicles and machinery.
2  Officers familiar with the acquisition could not confirm the nature of remediation being undertaken, but noted that the previous landowner had cleared buildings from the site, which may have been considered part of remediation.
TfNSW's independent valuation, which it commissioned and received after the acquisition, specifically excluded consideration of environmental contamination risk. As a result, TfNSW is exposed to the risk that the acquisition was not fully compliant with the Land Acquisition (Just Terms Compensation) Act 1991 (the Act) because it did not use an accurate estimate of market value during negotiations. That said, the acquisition of 4–6 Grand Avenue by agreement was consistent with preferred processes described in the Act.

TfNSW acquired the site from the landowner by agreement, and this is consistent with provisions in the Act. Obtaining approval for compulsory acquisition should negotiations for agreement break down is also consistent with the Act. That said, TfNSW did not at any time assess whether a compulsory acquisition could have resulted in acquisition at a lower cost than what was negotiated by agreement.

Despite the high risks associated with the acquisition, TfNSW did not commission a formal valuation in time to inform the negotiation and purchase. Instead, TfNSW relied on internal advice to estimate market value, but did not obtain a formal valuation from those advisors. For high-risk transactions, the greater expertise and arm's-length independence of an external specialist valuer should be preferred over an agency's own staff.

On 15 June 2016, the settlement date for the acquisition, TfNSW commissioned a formal independent valuation of the site. On 23 November 2016, TfNSW received the final formal valuation report. By not obtaining a formal independent valuation of the property in advance of acquisition to inform the acquisition value, TfNSW exposed itself to non-compliance with the Act by not establishing the market value as the basis for the acquisition price. TfNSW also breached its own internal policies.

TfNSW instructed the valuer to conduct its valuation within the following parameters:

  • Market valuation on an ‘as is’ basis – market value based on the methodology described in the Act. This approach valued the site at $25.0 million.
  • Market valuation on a speculative development basis – market value based on the financial value of the vendor's intended use of the site which, in this case, involved leasing the site for industrial use. This approach valued the site at $52.0 million, and TfNSW advised us this valuation supported the purchase price.
  • Disregard the impact of environmental contamination – TfNSW specifically instructed the independent valuer to disregard any known (or unknown) site contamination. As TfNSW knew of the significant environmental contamination affecting the site, this parameter resulted in a valuation that overstated the value of the site as it did not consider the cost of environmental remediation. The valuer applied this assumption for both market valuation approaches.

Additionally, as the independent valuer completed the valuation after the purchase was finalised, there is a risk that the valuation may have been influenced by the known purchase price.

TfNSW's failure to acquire a formal valuation and an assessment of the financial impact of environmental remediation before it purchased 4–6 Grand Avenue represents ineffective administration and governance.
TfNSW acquired the site at a time when there was demand and increasing prices for industrial property in the area. However, TfNSW did not effectively assess and manage the risks associated with the acquisition, and gaps in process led to increased risk. Briefings to decision-makers did not contain important information, and we found no evidence that gaps in advice were queried or explored by decision-makers.

TfNSW did not have plans or advice in place to assist in managing risk, such as:

  • a property acquisition plan
  • a comprehensive and up-to-date risk management plan
  • a negotiation strategy, or any authorisation limit or minimal acceptable position
  • an independent professional evaluation
  • external expert advice (with the exception of legal advice relating to the contract of sale).

TfNSW was aware of contamination issues affecting the land and had access to considerable information about the environmental conditions, such as site environmental audit reports and information on the NSW Environment Protection Authority's contaminated land register. However, TfNSW had not analysed specific technical information about the contamination and therefore was not aware of the risk implications and cost for remediation. Despite this, TfNSW changed its position from not accepting the risks and costs of contamination, to acquiring the site unconditionally. The basis for this decision is unclear and undocumented.

Briefing to senior leaders on the acquisition was silent on a number of important matters that would have been important for approvers to consider, including:

  • an explanation of the 40 per cent increase in purchase price between November 2015 and May 2016, and a 165 per cent increase from TfNSW’s offer in April 2015
  • the contamination risks associated with the site and an evidence-based estimate of potential costs to remediate the site
  • advice that an independent valuation had not been obtained, inconsistent with TfNSW policy.

Consideration of the acquisition by FIC was based on a summary business paper and was managed out-of-session, thereby removing the ability for comprehensive consideration of the acquisition proposal and its risks.

The probity management controls and assurances in place for the acquisition of the 4–6 Grand Avenue site were insufficient. These insufficiencies were exacerbated by the probity risk profile of the transaction.

The 4–6 Grand Avenue acquisition was a high-risk/high-value transaction, undertaken in a volatile property market in a short timeframe under pressure from Grand 4 Investments. TfNSW was engaging in a direct negotiation in advance of detailed planning for the acquisition, or the PLR as a whole. These circumstances contribute to heightened probity risk.

TfNSW did not establish a probity plan and sought no probity support throughout the acquisition. Also, with one exception, the staff involved in the acquisition did not complete conflict of interest declarations.

TfNSW was aware of the potential for probity or integrity issues with the transaction when it commissioned an internal audit in connection with the transaction in 2019. Internal discussions considered whether a misconduct investigation may be more appropriate, however no such investigation was undertaken.

TfNSW's insufficient probity practices, in addition to its failure to keep complete or comprehensive records of negotiations or decisions, reduce transparency of the process and its outcome and expose TfNSW to a greater risk of misconduct, corruption and maladministration.

At the time of the transaction, the TfNSW policy framework was not sufficiently risk-focussed and did not provide clarity on when officers ought to apply specific guidance or procedures. TfNSW's policies and procedures are more focussed on acquiring land to meet project needs and timeframes, and less on assuring value for money and managing risks.

At the time of its acquisition of 4–6 Grand Avenue, TfNSW had property acquisitions policies and procedures in place. Each of these were broadly sound in their content and intent. However, they lacked specificity on how or when to apply guidance, and when risk levels should elevate the importance of recommended guidance.

TfNSW's key guidance was principles based and relied on agency staff using their experience and expertise to apply guidance according to the circumstances of an individual transaction. This guidance was not duly applied in the acquisition of 4–6 Grand Avenue, Camellia. In addition, TfNSW does not have quality or control assurance to identify when TfNSW officers did not apply important policies or processes.

The primary focus of the TfNSW’s property acquisition guidance is to achieve vacant possession of land in a timeframe that meets the need of the relevant transport project. There is less specific focus on the need to meet the requirements of the NSW Government financial management framework.

Appendix one – Response from agency 

Appendix two – About the audit 

Appendix three – Performance auditing

 

Copyright Notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #349 - released (18 May 2021).

Published

Actions for Central Agencies 2020

Central Agencies 2020

Premier and Cabinet
Treasury
Financial reporting
Internal controls and governance
Management and administration
Risk

This report analyses the results of our audits of the financial statements of the Treasury, Premier and Cabinet, Customer Service cluster agencies (central agencies), and the Legislature for the year ended 30 June 2020. The table below summarises our key observations.

1. Financial reporting

Audit opinions and timeliness of reporting

Unqualified audit opinions were issued on the 2019–20 financial statements of central agencies and the Legislature.

The audit opinion on the Social and Affordable Housing NSW Fund's compliance with the payment requirements of the Social and Affordable Housing NSW Fund Act 2016 was qualified.

All agencies met statutory deadlines for submitting
financial statements. 

Agencies were financially impacted by recent emergency events The NSW Government allocated $1.4 billion to provide small business support and bushfire recovery relief, support COVID-19 quarantine compliance management, recruit more staff to respond to increased customer demand, and meet additional COVID-19 cleaning requirements. Agencies spent $901 million (64 per cent of the allocated funding) for the financial year ended 30 June 2020. NSW Self Insurance Corporation reported an increase of $850 million in its liability for claims related to emergency events.
AASB 16 'Leases' resulted in significant changes to agencies' financial position The implementation of new accounting standards was challenging for many agencies. The New South Wales Government Telecommunications Authority was not well-prepared to implement AASB 16 'Leases' and had not completely assessed contracts that contained leases. This resulted in understatements of leased assets and liabilities by $56 million which were subsequently corrected.
Implementation of new revenue standards NSW Treasury did not adequately implement the new revenue standard AASB 1058 ‘Income of Not-for-Profit Entities’ for the Crown Entity. This resulted in understatements of $274 million in opening equity and $254 million to current year revenue, which have been corrected in the final financial statements.

2. Audit observations

Management letter findings and repeat issues Our 2019–20 audits identified nine high risk and 122 moderate risk issues across central agencies and the Legislature. The high risk issues were identified in the audits of:
  • Insurance and Care NSW
  • New South Wales Government Telecommunications Authority
  • Rental Bond Board
  • Independent Commission Against Corruption
  • NSW Treasury
  • Crown Entity
  • Department of Premier and Cabinet.

High risk findings include:

  • Insurance and Care NSW (icare) allocates service costs to the Workers Compensation Nominal Insurer, and the other schemes it supports. The documentation supporting cost allocations does not demonstrate how these allocations reflect actual costs. There is a risk of the Workers Compensation Nominal Insurer being overcharged.
  • New South Wales Government Telecommunications Authority's delay in capitalisation and valuation of material capital projects; and insufficient work performed to implement the new accounting standard AASB 16 ‘Leases’.
  • NSW Treasury's four-year plan to transition RailCorp to a for-profit State Owned Corporation called Transport Asset Holding Entity of New South Wales (TAHE) by 1 July 2019, remains to be implemented. On 1 July 2020, RailCorp converted to TAHE. A large portion of the planned arrangements are still to be implemented. As at the time of the audit, the TAHE operating model, Statement of Corporate Intent (SCI) and other key plans and commercial agreements were not finalised. In the absence of commercial arrangements with the public rail operators, there is a lack of evidence to demonstrate TAHE’s ability to create a commercial return in the long term. This matter has been included as a high risk finding in our management letter as there may be financial reporting implications to the State if TAHE does not generate a commercial return for its shareholders in line with the original intent. NSW Treasury and TAHE should ensure the commercial arrangements, operating model and SCI are finalised in 2020–21.

Of the 122 moderate risk issues, 36 per cent were repeat issues. The most common repeat issue related to weaknesses in controls over information technology user access administration, which increases the risk of inappropriate access to systems and records.

Grants administration for disaster relief Service NSW delivers grants responding to emergency events on behalf of other NSW Public Sector agencies. Since the first grant program commenced in January 2020, Service NSW processed approximately $791 million to NSW citizens and businesses impacted by emergency events for the financial year ended 30 June 2020. A performance audit of grants administration for disaster relief is planned for 2020–21. It will assess whether grants programs administered under the Small Business Support Fund were effectively designed and implemented to provide disaster relief.
Internal controls at GovConnect NSW service providers require enhancement

GovConnect NSW provides transactional and information technology services to central agencies. It engages an independent service auditor (service auditor) from the private sector to perform annual assurance reviews of controls at service providers, namely Infosys, Unisys and the Department of Customer Service (DCS). The service auditor issued:

  • unqualified opinions on information technology and business process controls at Infosys and Unisys, but there was an increase in control deficiencies identified in the user access controls at these service providers
  • a qualified opinion on DCS's information technology (IT) security monitoring controls because security tools were not implemented and monitored for the entire financial year. Responsibility for IT security monitoring transitioned from Unisys to DCS in 2019–20. These control deficiencies can increase the risk of fraud and inappropriate use of sensitive data.

These may impact on the ability of agencies to detect and respond to a cyber incident.

Recommendation:

We recommend DCS work with GovConnect service providers to resolve the identified control deficiencies as a matter of priority.

The NSW Public Sector's cyber security resilience needs to improve

The NSW Cyber Security Policy requires agencies to provide a maturity self-assessment against the Australian Cyber Security Centre (ACSC) Essential 8 to the head of the agency and Cyber Security NSW annually. Completed self-assessment returns highlighted limited progress in implementing the Essential 8.

Repeat recommendation:

Cyber Security NSW and NSW government agencies need to prioritise improvements to their cyber security resilience as a matter of urgency

Three Insurance and Care NSW (icare) entities had net asset deficiencies at 30 June 2020 The Workers Compensation Nominal Insurer, NSW Self Insurance Corporation and the Lifetime Care and Support Authority of NSW all had negative net assets at 30 June 2020. These icare entities did not hold sufficient assets to meet the estimated present value of all of their future payment obligations at 30 June 2020. The deterioration in net assets was largely due to increases in outstanding claims liabilities. Notwithstanding the overall net asset deficiencies, the financial statements for these entities were prepared on a going concern basis. This is because future payment obligations are not all due within the next 12 months. Settlement is instead expected to occur over years into the future, depending on the nature of the benefits provided by each scheme.
icare has not been able to demonstrate that its allocation of costs reflects the actual costs incurred by the Workers Compensation Nominal Insurer and other schemes

Costs are incurred by icare as the 'service entity' of the statutory scheme it administers, and then subsequently recovered from the schemes through 'service fees'. In the absence of documentation supported by robust supporting analysis, there is a risk of the schemes being overcharged, and the allocation of costs being in breach of legislative requirements.

Recommendation:

icare should ensure its approach to allocating service fees to the Workers Compensation Nominal Insurer and the other schemes it manages, is transparent and reflects actual costs.

icare did not comply with GIPA requirements icare did not comply with the Government Information (Public Access) Act 2009 (GIPA) contract disclosure requirements in 2019–20 and has not complied for several years. A total of 417 contracts were identified by management as not having been published on the NSW Government’s eTendering website. The final upload of these past contracts occurred on 20 August 2020.
Implementation of Machinery of Government (MoG) changes MoG changes impacted the governance and business processes of some agencies. Our audits identified and reported areas for improvement in the consolidation of corporate functions following MoG implementation processes at Infrastructure NSW and in the Customer Service cluster.

This report provides Parliament and other users of NSW Government central agencies' financial statements and the Legislature's financial statements with the results of our financial audits, observations, analyses, conclusions and recommendations.

Emergency events, such as bushfires, floods and the COVID-19 pandemic significantly impacted agencies in 2019–20. Our findings on nine agencies that were most impacted by recent emergency events are included throughout this report.

Refer to Appendix one for the names of all central agencies and Appendix four for the nine agencies most impacted by emergency events.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely. This chapter outlines our audit observations on the financial reporting of central agencies and the Legislature for 2020, including the financial implications from recent emergency events.

Section highlights

  • Unqualified audit opinions were issued on the 2019–20 financial statements of central agencies and the Legislature. All agencies met the statutory deadlines for submitting their financial statements.
  • The audit opinion on the Social and Affordable Housing NSW Fund's compliance with the payment requirements of the Social and Affordable Housing NSW Fund Act 2016 was qualified as a result of a payment made without a Treasurer's delegation.
  • Agencies were impacted by emergency events during 2019–20. This included additional grants to fund specific deliverables.
  • The implementation of new accounting standards was challenging for many agencies. The New South Wales Government Telecommunications Authority was not well-prepared to implement AASB 16 'Leases' and had not completely assessed contracts that contained leases. This resulted in understatements of leased assets and liabilities by $56 million which were subsequently corrected.
  • NSW Treasury did not adequately implement the new revenue standard AASB 1058 ‘Income of Not-for-Profit Entities’ for the Crown Entity. This resulted in understatements of $274 million in opening equity and $254 million to current year revenue in the financial statements. These misstatements were due to incorrect revenue calculations performed by the Transport agencies. The Crown Entity relies on information from Transport agencies as they are responsible for carrying out the State’s contractual obligations for Commonwealth funded transport projects. The extent of misstatements could have been reduced with more robust quality review processes in place by Treasury and Transport.

 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines:

  • our observations and insights from the financial statement audits of agencies in the central agencies and the Legislature
  • our assessment of how well agencies adapted their systems, policies, procedures and governance arrangements in response to recent emergencies.

Section highlights

  • The 2019–20 audits identified nine high risk and 122 moderate risk issues across the agencies. Of the 122 moderate risk issues, 44 (36 per cent) were repeat issues. The most common repeat issue relates to weaknesses in controls over information technology user access administration.
  • Service NSW delivers grants responding to emergency events on behalf of other NSW Public Sector agencies. Since the first grant program commenced in January 2020, Service NSW processed approximately $791 million to NSW citizens and businesses impacted by these emergency events for the financial year ended 30 June 2020.
  • GovConnect NSW engaged an independent auditor (the service auditor) from the private sector to evaluate the internal controls of its service providers. DCS's information technology security monitoring controls were qualified by the service auditor because security tools were not implemented and monitored for the entire financial year. These may impact on the ability of agencies to detect and respond to a cyber incident.
  • NSW Government agency self-assessment results show that the NSW Public Sector's cyber security resilience needs urgent attention.
  • The Workers Compensation Nominal Insurer, NSW Self Insurance Corporation and the Lifetime Care and Support Authority of NSW all had negative net assets at 30 June 2020. The financial statements for these entities continued to be prepared on a going concern basis as their liabilities are not all due for settlement within the next 12 months.
  • icare did not comply with the Government Information (Public Access) Act 2009 (GIPA) contract disclosure requirements in 2019–20, and has not complied for several years. A total of 417 contracts were identified by management as not having been published on the NSW Government’s eTendering website. The final upload of these past contracts occurred on 20 August 2020.
  • Machinery of Government (MoG) changes impacted the governance and business processes of affected agencies. Our audits identified and reported areas for improvement in the consolidation of corporate functions following MoG changes at Infrastructure NSW and in the Customer Service cluster.

 

Published

Actions for Transport 2020

Transport 2020

Transport
Asset valuation
Cyber security
Financial reporting
Information technology
Infrastructure
Project management

1. Financial Reporting

Audit opinion Unmodified audit opinions issued for the financial statements of all Transport cluster entities.
Quality and timeliness of financial reporting All cluster agencies met the statutory deadlines for completing the early close and submitting the financial statements.

Transport cluster agencies continued to experience some challenges with accounting for land and infrastructure assets. The former Roads and Maritime Services and Sydney Metro recorded prior period corrections to property, plant and equipment balances.
Impact of COVID-19 on passenger revenue and patronage Total patronage and revenue for public transport decreased by approximately 18 per cent in 2019–20 due to COVID-19.

The Transport cluster received additional funding from NSW Treasury during the year to support the reduced revenue and additional costs incurred such as cleaning on all modes of public transport and additional staff to manage physical distancing.
Completion of the CBD and South East Light Rail The CBD and South East Light Rail project was completed and commenced operations in this financial year. At 30 June 2020, the total cost of the project related to the CBD and South East Light Rail was $3.3 billion. Of this total cost, $2.6 billion was recorded as assets, whilst $700 million was expensed.

2. Audit Observations

Internal control While internal controls issues raised in management letters in the Transport cluster have decreased compared to the prior year, control weaknesses continue to exist in access security for financial systems. We identified 56 management letter findings across the cluster and 43 per cent of all issues were repeat issues. The majority of the repeat issues relate to information technology controls around user access management.

There were three high risk issues identified - two related to financial reporting of assets and one for implementation of TAHE (see below).
Agency responses to emergency events Transport for NSW established the COVID-19 Taskforce in March 2020 to take responsibility for the overall response of planning and coordination for the Transport cluster. It also implemented the COVIDSafe Transport Plan which incorporates guidance on physical distancing, increasing services to support social distancing and cleaning.
RailCorp transition to TAHE On 1 July 2020, RailCorp was renamed Transport Asset Holding Entity of New South Wales (TAHE) and converted to a for-profit statutory State-Owned Corporation. TAHE is a commercial for-profit Public Trading Entity with the intent to provide a commercial return to its shareholders.

A plan was established by NSW Treasury to transition RailCorp to TAHE which covered the period 1 July 2015 to 1 July 2019. A large portion of the planned arrangements were not implemented by 1 July 2020. As at the time of this report, the TAHE operating model, Statement of Corporate Intent (SCI) and other key plans and commercial agreements are not finalised. The State Owned Corporations Act 1989 generally requires finalisation of an SCI three months after the commencement of each financial year. However, under the Transport Administration Act 1988, TAHE received an extension from the voting shareholders, the Treasurer and Minister for Finance and Small Business, to submit its first SCI by 31 December 2020. In accordance with the original plan, interim commercial access arrangements were supposed to be in place with RailCorp prior to commencement of TAHE.

Under the transitional arrangements, TAHE is continuing to operate in accordance with the asset and safety management plans of RailCorp. The final operating model is expected to include considerations of safety, operational, financial and fiscal risks. This should include a consideration of the potential conflicting objectives of a commercial return, and maintenance and safety measures.

This matter has been included as a high risk finding in our management letter due to the significance of the financial reporting impacts and business risks for TAHE.

Recommendation: TAHE management should:
  • establish an operating model in line with the original intent of a commercial return
  • finalise commercial agreements with the public rail operators
  • confirm forecast financial information to assess valuation of TAHE infrastructure
  • finalise asset and safety management plans.

Resolution of the above matters are critical as they may significantly impact the financial reporting arrangements for TAHE for 2020–21, in particular, accounting policies adopted as well as measurement principles of its significant infrastructure asset base.

Completeness and accuracy of contracts registers Across the Transport cluster, contracts and agreements are maintained by the transport agencies using disparate registers.

Recommendation (repeat): Transport agencies should continue to implement a process to centrally capture all contracts and agreements entered. This will ensure:
  • agencies are fully aware of contractual and other obligations
  • appropriate assessment of financial reporting implications
  • ongoing assessments of accounting standards, in particular AASB 16 ‘Leases’, AASB 15 'Revenue from Contract with Customers', AASB 1058 'Income of Not-for-Profit Entities' and new accounting standard AASB 1059 'Service Concession Arrangements: Grantors' are accurate and complete.

 

This report provides parliament and other users of the Transport cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations
  • the impact of emergencies and the pandemic.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Transport cluster for 2020, including any financial implications from the recent emergency events.

Section highlights

  • Total patronage and revenue for public transport decreased by approximately 18 per cent in 2019–20 due to COVID-19.
  • Unqualified audit opinions were issued on all Transport agencies' financial statements.
  • Transport cluster agencies continued to experience challenges with accounting of land and infrastructure assets.

 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our:

  • observations and insights from our financial statement audits of agencies in the Transport cluster
  • assessment of how well cluster agencies adapted their systems, policies and procedures, and governance arrangements in response to recent emergencies.

Section highlights

  • While there was a decrease in findings on internal controls across the Transport cluster, 43 per cent of all issues were repeat issues. Many repeat issues related to information technology controls around user access management.
  • RailCorp transitioned to TAHE on 1 July 2020. TAHE's operating model and commercial arrangements with public rail operators has not been finalised despite government original plans to be operating from 1 July 2019. TAHE management should finalise its operating model and commercial agreements with public rail operators as they may significantly impact the financial reporting arrangements for TAHE for 2020–21.
  • Completeness and accuracy of contracts registers remains an ongoing issue for the Transport cluster.

Appendix one – List of 2020 recommendations

Appendix two – Status of 2019, 2018 and 2017 recommendations

Appendix three – Management letter findings

Appendix four – Financial data

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for State Finances 2020

State Finances 2020

Education
Finance
Community Services
Health
Justice
Industry
Planning
Environment
Premier and Cabinet
Transport
Treasury
Whole of Government
Financial reporting

The Auditor-General for New South Wales, Margaret Crawford, released her report today on State Finances for the year ended 30 June 2020.

‘I am pleased to once again report that I issued an unmodified audit opinion on the State’s consolidated financial statements,’ the Auditor-General said.

The report acknowledges this has been a challenging year, with New South Wales impacted by natural disasters and the COVID-19 pandemic.

The State’s Budget Result, reported in the financial statements, was a deficit of $6.9 billion. This is different to the 2019-20 budget forecast surplus of $1.0 billion and is an outcome of the government’s significant response to bushfires and COVID-19.

The report summarises a number of audit and accounting matters arising from the audit of the Total State Sector Accounts, a sector that comprises 291 entities controlled by the NSW Government with total assets of $495 billion and total liabilities of $256 billion.

Read full report (PDF)

Our audit opinion on the State’s 2019–20 financial statements was unmodified

An unmodified audit opinion was issued on the State’s 2019–20 consolidated financial statements.

The State extended signing its financial statements by six weeks.

Natural disasters, the COVID-19 pandemic and other factors impacted the State’s 2019–20 reporting timetable. The State extended signing its financial statements by six weeks, compared with 2018–19.

All agencies were also given a two-week extension to prepare their financial statements compared with 2018–19. Further extensions beyond two weeks were subsequently approved for the following 11 agencies (7 in 2018–19) to submit completed financial statements for audit:

  • Department of Communities and Justice
  • Department of Customer Service
  • Department of Planning, Industry and Environment
  • Department of Regional NSW
  • Department of Transport
  • Environment Protection Authority
  • Infrastructure NSW
  • Lord Howe Island Board
  • NSW Crown Holiday Parks Land Manager
  • Service NSW
  • Water Administration Ministerial Corporation.

The extensions reflected that the COVID-19 pandemic impacted agencies’ work environments during the first six months of 2020. This was at a time when many were still implementing machinery of government changes and preparing to implement three significant new accounting standards:

  • AASB 15 Revenue from Contracts with Customers (issued December 2014, effective 1 July 2019)
  • AASB 16 Leases (issued February 2016, effective 1 July 2019)
  • AASB 1058 Income of Not-for-profit entities (issued December 2016, effective 1 July 2019).

These new accounting standards were issued some years before they became effective, to allow reporting entities sufficient time to prepare for implementation. Notwithstanding this, some agencies had not fully implemented the new accounting standards in time for early close procedures, and the unforeseen impact of COVID-19 further complicated the year-end financial reporting processes for the State and its agencies.

The graph below shows the number of reported errors exceeding $20 million over the past five years in agencies’ financial statements presented for audit.

In 2019–20, agency financial statements presented for audit contained 19 errors exceeding $20 million (six in 2018–19). The total value of these errors increased to $1.4 billion ($927 million in 2018–19).

The errors resulted from:

  • incorrectly applying Australian Accounting Standards and Treasury Policies
  • incorrect judgements and assumptions when valuing noncurrent physical assets and liabilities
  • incorrectly interpreting the accounting treatment for unspent stimulus funding.

Errors in agency financial statements exceeding $20m (2016–2020)

$4.1 billion in stimulus funding was allocated in 2019–20

The government implemented an economic stimulus package primarily to mitigate the impacts of the COVID-19 pandemic on New South Wales.

The COVID-19 pandemic and bushfires had a significant impact on the State’s finances, reducing its revenue and increasing its expenses especially in sectors directly responsible for responding to the COVID-19 pandemic, such as Health.

The government announced a $4.1 billion health and economic stimulus package in 2019–20. This primarily included:

  • $2.2 billion in health measures including purchases of essential medical equipment and increasing clinical health capacity (like intensive care spaces)
  • $1.0 billion in small business and land tax relief
  • $355 million in extra cleaning services and quarantine costs.

Cluster agencies had spent $3.0 billion (just under 75 per cent) of the COVID-19 stimulus package by 30 June 2020.

The Health cluster incurred most of this expenditure.

Total spend relating to bushfires was $1.3 billion in 2019–20.

The graph below shows the total allocation and spend by cluster to 30 June 2020.

Economic stimulus allocation and spend by cluster to 30 June 2020

Deficit of $6.9 billion compared with a budgeted surplus of $1.0 billion

An outcome of the government’s overall activity and policies is its net operating balance (Budget Result). This is the difference between the cost of general government service delivery and the revenue earned to fund these sectors.

The General Government Sector, which comprises 199 entities, generally provides goods and services funded centrally by the State.

The Non-General Government Sector, which comprises 92 government businesses, generally provides goods and services, such as water, electricity and financial services that consumers pay for directly.

The Budget Result for the 2019–20 financial year was a deficit of $6.9 billion. The original budget forecast, set before the COVID-19 pandemic and bushfires, was a $1.0 billion surplus. The main driver of the change in result was:

  • $1.3 billion of higher employee costs, mainly due to:
    • increased workers compensation claims
    • additional personnel required (mainly in the Health sector) to respond to the COVID-19 pandemic
  • $2.3 billion of higher operating expenses, mainly due to:
    • $828 million from first time recognition of a child abuse claim liability
    • $507 million from additional insurance claims from the NSW bushfires
    • $343 million from COVID-19 claims by agencies for loss of revenue.
  • $1.8 billion in higher grants and subsidy expenses, mainly due to:
    • small business grants
    • COVID-19 quarantine compliance measures
    • costs incurred in response to the 2019–20 bushfires, drought and disaster relief payments
    • third party-controlled assets that were subsequently transferred to councils and utility providers, mainly arising from construction of the CBD and South East Light Rail.

The deficit was further driven by:

  • $1.9 billion less taxation revenue, mainly resulting from:
    • $1.3 billion less in payroll tax due to relief measures introduced by the government as part of its COVID-19 economic stimulus
    • $424 million less in gambling and betting taxes, due to venue closures required by COVID-19 public health orders
  • $523 million less in dividends and income tax revenue from the Non-General Government Sector, due to lower dividends received from NSW Treasury Corporation and from the State’s other commercial government businesses
  • lower fines, regulatory fees and other revenue, due to a $305 million decrease in mining royalties, largely driven by lower coal prices.

Main drivers of the 2019–20 actual vs. budget variance

Revenues increased $209 million to $86.3 billion

In 2019–20, the State’s total revenues increased by $209 million to $86.3 billion, 0.2 per cent higher than in 2018–19. COVID-19 impacted taxation revenue, which fell by $1.1 billion and revenue from the sale of goods and services, which fell by $1.1 billion. These falls were offset by a $2.5 billion (7.7 per cent) increase in grants and subsidies from the Australian Government, mainly in the form of additional stimulus funding.

Taxation revenue fell 3.5 per cent

Taxation revenue fell by $1.1 billion, mainly due to a:

  • $861 million fall in payroll tax as a result of COVID-19 relief (reduced payroll tax payments for eligible small businesses)
  • $430 million fall in stamp duty collections, driven by lower than expected growth in the property market
  • $427 million decline in gambling and betting taxes, mainly due to venue closures driven by COVID-19 public health orders.

Stamp duties of $8.8 billion were the largest source of taxation revenue, $473 million higher than payroll tax, the second-largest source of taxation revenue.

Australian Government grants and subsidies

The State received $34.2 billion in grants and subsides which are mainly from the Australian Government, $2.4 billion more than in 2018–19.

The increase was driven by a $1.1 billion increase in Commonwealth Specific Purpose Payments to support the Health cluster respond to the COVID-19 pandemic. Commonwealth National Partnership Payments increased by a similar amount to provide the State with Natural Disaster relief.

Sales of goods and services

In 2019–20, sales of goods and services fell $1.1 billion. This was due to the COVID-19 pandemic reducing:

  • patronage and related transport passenger revenue
  • health billing activities with elective surgery being put on hold
Fines, regulatory fees and other revenues

Fines, regulatory fees and other revenues fell $505 million. This was mainly due to a $409 million decrease in mining royalties attributed to a drop in thermal coal prices during 2019–20.

Other dividends and distributions

Other dividends and distributions rose by $616 million due to higher distributions received from the State’s investments. This was due to an additional $1.3 billion held in the State’s investment portfolio compared with last year.

Expenses increased $8.2 billion to $96.0 billion

The State’s expenses increased 9.3 per cent compared with 2018–19. Most of the increase was due to higher employee expenses, other operating costs and grants and subsidies.

Employee expenses, including superannuation, increased 5.7 per cent to $42.6 billion.

Salaries and wages increased to $42.6 billion from $40.3 billion in 2018–19. This was mainly due to increases in staff numbers and a 2.5 per cent increase in pay rates across the sector. Salaries and wages for the Education and Health sectors increased by $659 million and $732 million in each sector respectively.

The Health sector employed an additional 2,763 full time staff in 2019–20. It also incurred more overtime in response to COVID-19. Education increased staff numbers by 4,866 full time equivalents and paid a one off 11 per cent pay rise to school administration staff in 2019–20. Historically, the government wages policy aims to limit growth in employee remuneration and other employee related costs to no more than 2.5 per cent per annum.

Operating expenses increased 8.7 per cent to $27.0 billion.

Operating expenses increased to $27.0 billion in 2019–20 ($24.8 billion in 2018–19) due to higher operating activities in Health. The higher level of activities and related costs is attributed to a full year of operations at the Northern Beaches Hospital (opened November 2018), and responding to COVID-19. The response to COVID-19 involved the State providing viability payments to private hospitals, higher visiting medical officer costs due to additional overtime hours and spending more on equipment to set up COVID-19 testing clinics.

Insurance claims increased by $2.0 billion. This was mainly due to NSW Self Insurance Corporation (SiCorp) recognising a liability for child abuse claims incurred but not reported for the first time, and claims for the 2019–20 bushfires, floods and COVID-19.

Health costs remain the State’s highest expense.

Total expenses of the State were $96 billion ($87.8 billion in 2018–19). Traditionally, the following clusters have the highest expenses as a percentage of total government expenses:

  • Health – 24.3 per cent (25.8 per cent in 2018–19)
  • Education – 17.6 per cent (19.3 per cent in 2018–19)
  • Transport - 12.8 per cent (12.6 per cent in 2018–19).

General public service expenses as a percentage of total State expenses is higher due to a $2.0 billion increase in SiCorp’s accrued claim expenses.

Other expenses increased due to additional grant funding by the State for drought relief and COVID-19 stimulus spend.

Health expenses increased by $632 million compared with 2018–19 but fell as a proportion of total State expenses.

Education expenses remained stable compared with last year due to savings in student transportation costs primarily driven by COVID-19. This led to a decrease in the proportion of the State’s costs relating to education activities.

Grants and subsidies increased $2.5 billion to $14.1 billion.

The increase in grants and subsidies was due to payments the State made to support businesses and local communities in the face of COVID-19 and bushfires. In addition, the State transferred CBD and South East Light Rail assets to councils and utility providers during 2019–20 as it no longer controlled these.

Depreciation expense increased $1.0 billion to $9.2 billion.

Depreciation increased to $9.2 billion from $8.0 billion in 2018–19. At 1 July 2019, the State implemented the new leases standard recognising a right of use (ROU) asset and related lease liability in its financial statements. The value of ROU assets are amortised over the term of the lease. This contributed to $980 million of the increase in 2019–20 depreciation expense. Last year, these costs were previously reported within other operating expenses.

Assets grew by $28.0 billion to $495 billion

The State’s assets primarily include physical assets such as land, buildings and infrastructure, and financial assets such as cash, and other financial instruments and equity investments. The value of total assets increased by $28.0 billion to $495 billion. This was a six per cent increase compared with 2018–19, mostly due to changes in asset carrying values.

Of the State’s $28.0 billion increase in asset values, $9.3 billion was due to a new accounting standard requirement for operating leases to be valued and recorded on balance sheet for the first time.

AASB 16 Leases requires entities recognise values for right-ofuse assets (ROU) for the first time. An ROU asset is a lessee’s right to use an asset, the value of which is amortised over the term of the lease. This standard came into effect from 1 July 2019.

Valuing the State’s physical assets

State’s physical assets valued at $365 billion.

The value of the State’s physical assets increased by $14.1 billion to $365 billion in 2019–20. The assets include land and buildings ($168 billion), infrastructure ($180 billion) and plant and equipment ($16.7 billion). A prior period error relating to the valuation of RMS infrastructure assets reduced the reported values by $1.0 billion from $352 billion to $351 billion at 30 June 2019.

The movement in physical asset values between years includes additions, disposals, depreciation and valuation adjustments. Other movements include reclassification of physical assets leased under finance leases to right of use assets upon adoption of AASB 16 Leases on 1 July 2019.

Movements in physical asset values

Liabilities increased $38.4 billion to $256 billion

The State borrowed additional funds in response to natural disasters and COVID-19.

The State’s borrowings rose by $33.9 billion to $113.8 billion at 30 June 2020. This accounted for most of the increase in the State’s total liabilities.

The value of TCorp bonds on issue increased by $25.2 billion to $97.0 billion to largely fund capital expenditure and costs associated with the bushfires, drought and COVID-19.

TCorp bonds are actively traded in financial markets and are guaranteed by the NSW Government.

Over 2019–20, TCorp continued to take advantage of lower interest rates, buying back short-term bonds and replacing them with longer dated debt. This lengthens the portfolio matching liabilities with the funding requirements for infrastructure assets.

With effect from 1 July 2019, AASB 16 Leases required the State to recognise liabilities for operating leases for the first time. This increased total lease liabilities from $5.3 billion at 30 June 2019 to $11.8 billion at 30 June 2020.

More than a third of the State’s liabilities relate to its employees. They include unfunded superannuation and employee benefits, such as long service and recreation leave.

Valuing these obligations involves complex estimation techniques and significant judgements. Small changes in assumptions and other variables, such as a lower discount rate, can materially impact the valuation of liability balances in the financial statements.

The State’s unfunded superannuation liability rose $300 million from $70.7 billion to $71.0 billion at 30 June 2020. This was mainly due to a lower discount rate of 0.87 per cent (1.32 per cent in 2018–19). The State’s unfunded superannuation liability represents the value of its obligations to past and present employees less the value of assets set aside to fund those obligations.

 

The State maintained its AAA credit rating

The object of the Fiscal Responsibility Act 2012 is to maintain the State’s AAA credit rating.

The government manages New South Wales’ finances in accordance with the Fiscal Responsibility Act 2012 (the Act).

The Act establishes the framework for fiscal responsibility and the strategy to maintain the State’s AAA credit rating and service delivery to the people of New South Wales.

The legislation sets out targets and principles for financial management to achieve this.

This year, the State’s credit rating from Standard & Poor’s changed from AAA/Stable to AAA/Negative. Moody’s Investors Service credit rating of Aaa/Stable did not change from the previous year.

The fiscal target for achieving this objective is that General Government annual expenditure growth should be lower than long term average revenue growth.

The State did not achieve its fiscal target of maintaining annual expenditure growth below the long-term revenue growth rate target of 5.6 per cent.

In 2019–20, General Government expenditure grew by 9.7 per cent (5.5 per cent in 2018–19).

Expenditure items that contributed most to the growth rate include:

  • recurrent grants and subsidies (20.4 per cent)
  • other operating expenses (9.5 per cent)
  • employee costs (including superannuation) (5.6 per cent)

Recurrent grant and subsidy expenses increased by $2.8 billion in 2019–20 mainly due to the COVID-19 and natural disaster payments. Other operating expenses increased mainly due to a $2.0 billion increase in SiCorp insurance claims. This included the $828 million provision for child abuse claims incurred but not reported. The bushfires and COVID-19 pandemic also increased the number and cost of claims in 2019–20.

Superannuation funding position since inception of the Act - AASB 1056 Valuation

Published

Actions for CBD South East Sydney Light Rail: follow-up performance audit

CBD South East Sydney Light Rail: follow-up performance audit

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk
Service delivery

This is a follow-up to the Auditor-General's November 2016 report on the CBD South East Sydney Light Rail project. This follow-up report assessed whether Transport for NSW has updated and consolidated information about project costs and benefits.

The audit found that Transport for NSW has not consistently and accurately updated project costs, limiting the transparency of reporting to the public.

The Auditor-General reports that the total cost of the project will exceed $3.1 billion, which is above the revised cost of $2.9 billion published in November 2019. $153.84 million of additional costs are due to omitted costs for early enabling works, the small business assistance package and financing costs attributable to project delays.

The report makes four recommendations to Transport for NSW to publicly report on the final project cost, the updated expected project benefits, the benefits achieved in the first year of operations and the average weekly journey times.

Read full report (PDF)

The CBD and South East Light Rail is a 12 km light rail network for Sydney. It extends from Circular Quay along George Street to Central Station, through Surry Hills to Moore Park, then to Kensington and Kingsford via Anzac Parade and Randwick via Alison Road and High Street.

Transport for NSW (TfNSW) is responsible for planning, procuring and delivering the Central Business District and South East Light Rail (CSELR) project. In December 2014, TfNSW entered into a public private partnership with ALTRAC Light Rail as the operating company (OpCo) responsible for delivering, operating and maintaining the CSELR. OpCo engaged Alstom and Acciona, who together form its Design and Construct Contractor (D&C).

On 14 December 2019, passenger services started on the line between Circular Quay and Randwick. Passenger services on the line between Circular Quay and Kingsford commenced on 3 April 2020.

In November 2016, the Auditor-General published a performance audit report on the CSELR project. The audit found that TfNSW would deliver the CSELR at a higher cost with lower benefits than in the approved business case, and recommended that TfNSW update and consolidate information about project costs and benefits and ensure the information is readily accessible to the public.

In November 2018, the Public Accounts Committee (PAC) examined TfNSW's actions taken in response to our 2016 performance audit report on the CSELR project. The PAC recommended that the Auditor-General consider undertaking a follow-up audit on the CSELR project. The purpose of this follow-up performance audit is to assess whether TfNSW has effectively updated and consolidated information about project costs and benefits for the CSELR project.

Conclusion

Transport for NSW has not consistently and accurately updated CSLER project costs, limiting the transparency of reporting to the public. In line with the NSW Government Benefits Realisation Management Framework, TfNSW intends to measure benefits after the project is completed and has not updated the expected project benefits since April 2015.

Between February 2015 and December 2019, Transport for NSW (TfNSW) regularly updated capital expenditure costs for the CSELR in internal monthly financial performance and risk reports. These reports did not include all the costs incurred by TfNSW to manage and commission the CSELR project.

Omitted costs of $153.84 million for early enabling works, the small business assistance package and financing costs attributable to project delays will bring the current estimated total cost of the CSELR project to $3.147 billion.

From February 2015, TfNSW did not regularly provide the financial performance and risk reports to key CSELR project governance bodies. TfNSW publishes information on project costs and benefits on the Sydney Light Rail website. However, the information on project costs has not always been accurate or current.

TfNSW is working with OpCo partners to deliver the expected journey time benefits. A key benefit defined in the business plan was that bus services would be reduced owing to transfer of demand to the light rail - entailing a saving. However, TfNSW reports that the full expected benefit of changes to bus services will not be realised due to bus patronage increasing above forecasted levels.

Appendix one – Response from agency

Appendix two – Governance and reporting arrangements for the CSELR

Appendix three – 2018 CSELR governance changes

Appendix four – About the audit

Appendix five – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #335 - released 11 June 2020

Published

Actions for Universities 2019 audits

Universities 2019 audits

Universities
Cyber security
Financial reporting
Internal controls and governance
Procurement

This report contains findings on the results of financial audits of NSW universities for the year ended 31 December 2019.

All ten NSW universities received unqualified audit opinions. The 2019 financial results for universities are reported as at 31 December and reflect results from operations before the impact of the COVID‑19 pandemic.

The combined revenues for all NSW universities increased by $381 million to $11.4 billion in 2019, driven by increases in student revenues. Revenue from overseas students continued to grow faster than that from domestic students and contributed $3.6 billion in course fees to NSW universities in 2019.

Overseas students from the top three countries of origin, being China, India and Nepal, represented 72.4 per cent of all enrolments of overseas students and 65.4 per cent of all overseas student revenues for 2019. Revenue from students from these three countries comprised 40.9 per cent of total student revenues for all NSW universities, creating a considerable concentration risk for NSW universities.

The COVID‑19 pandemic may significantly impact the financial results of NSW universities in 2020. NSW universities provided data on COVID‑19 impacted student enrolments for semester one 2020. Overall numbers of student enrolments in semester one 2020 were 5.8 per cent beneath projections. Overseas student enrolments were 13.8 per cent beneath expectations and domestic student enrolments were 2.4 per cent below expectations.

The report makes recommendations to the NSW universities, aimed at strengthening controls over information technology, cyber security, validating published performance information, procurement practices and the oversight of their overseas controlled entities' legal and policy compliance functions.

Read full report (PDF)

This report analyses the results of our audits of the financial statements of the ten NSW universities for the year ended 31 December 2019. The table below summarises our key observations.

1. Financial reporting

Financial reporting

The 2019 financial statements of all ten NSW universities received unmodified audit opinions.

One controlled entity of the Western Sydney University received a qualified audit opinion.

Five NSW universities finalised their audited financial statements this year on or before the date they did last year.

New accounting standards, which changed how universities report income and treat operating leases, became effective from 1 January 2019.

Sources of revenue from operations

Government grants as a proportion of the total income of NSW universities continued to decrease.

Fee revenue from overseas students continued to grow faster than fees from domestic students. Forty-one per cent of NSW universities' total student revenue came from overseas students from three countries.

Five NSW universities increased the proportion of revenue they receive from overseas students from a single country. Two universities sourced over 73 per cent of their total overseas student revenue from students from a single country of origin in 2019.

Other revenues Two universities attracted over 69.5 per cent of the total philanthropic revenue of $174 million received by all NSW universities in 2019.
Operating expenditures Combined total operating expenditure for NSW universities increased to $9.9 billion in 2019, a rise of 5.2 per cent from 2018.
Current ratio At 31 December 2019, five NSW universities had a current ratio of less than one, meaning those universities need to actively manage their cash to meet current obligations.
Controlled entities

All six NSW universities with overseas controlled entities have devolved responsibility for governance and legislative compliance to their overseas controlled entities.

Recommendation (repeat issue): NSW universities should strengthen their governance arrangements to oversight their overseas controlled entities' legal and policy compliance functions.

COVID-19 impacts and responses

The 2019 financial results for universities are reported as at 31 December. Consequently, the results for the 2019 year were unaffected by the impact of the COVID-19 pandemic.

NSW universities provided data on the COVID-19 impacted student enrolments for semester one 2020. Overall numbers of student enrolments were 5.8 per cent beneath projections. Overseas student enrolments were 13.8 per cent beneath expectations and domestic student enrolments were 2.4 per cent beneath expectations.

NSW universities are responding to the challenges presented by COVID-19 by moving course delivery online, expanding student support and introducing cost saving measures.

2. Internal controls and governance

Internal control findings

Our audits identified 108 internal control deficiencies in 2019 (99 in 2018).

Gaps in information technology (IT) controls comprised the majority of these deficiencies. Deficiencies included a lack of sufficient user access reviews, inadequate review and approval of change management processes, and issues with password settings.

We identified one high risk financial control deficiency at the University of New South Wales, which resulted in the University providing for a potential underpayment of casual staff salaries.

NSW universities continue to implement recommendations arising from 35 findings raised in previous years.

Performance reporting

Five NSW universities still do not have formal processes to internally review and validate performance information published in their annual reports.

Recommendation (repeat issue): NSW universities should strengthen processes to review and validate published performance information.

Cyber security

Two universities have not yet implemented a cyber risk policy and three universities have not formally trained staff in cyber awareness.

Recommendation (repeat issue): NSW universities should strengthen cyber security frameworks and controls to protect sensitive data and prevent financial and reputational losses.

Management of IT service providers NSW universities have contracts with vendors to support their computer systems. Five universities have not formally established frameworks to manage these contracts. Poor contract management can compound risks associated with IT control deficiencies.
Data breach management Universities are required to maintain the privacy of sensitive data which, if disclosed or used inappropriately, could result in harm to individuals, financial loss, or loss of intellectual property. Two NSW universities have not established formal policies to manage data breaches.
Procurement

All universities have a procurement policy. Most universities have a documented procurement manual and contact management policy.

Recommendation: NSW universities should review their procurement and contract management policies and procedures to ensure that they are relevant and effective in reducing risk and improving purchasing outcomes.

3. Teaching and research

Graduate employment outcomes Eight out of ten NSW universities exceeded the national average for full-time employment rates of their undergraduates in 2019. Six universities performed better than the national average for full-time employment outcomes of their postgraduates in 2019.
Student enrolments by field of education Enrolments at NSW universities increased the most in Management and Commerce courses in 2019.
Achieving diversity outcomes

Five universities in 2018 (five in 2017) met the target enrolment rate for students from low socio-economic status (SES) backgrounds.

Eight universities increased enrolments of students from Aboriginal and Torres Strait Islander backgrounds in 2018.

 

This report provides Parliament with the results of our financial audits of New South Wales universities and their controlled entities in 2019, including our analysis, observations and recommendations in the following areas:

  • financial reporting
  • internal controls and governance
  • teaching and research.

Financial reporting is an important element of governance. Confidence and transparency in university sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations on the financial reporting of NSW universities for 2019.

Appropriate and robust internal controls help reduce risks associated with managing finances, compliance and administration of NSW universities.

This chapter outlines the internal controls related observations and insights across NSW universities for 2019, including overall trends in findings, level of risk and implications.

Our audits do not review all aspects of internal controls and governance every year. The more significant issues and risks are included in this chapter. These along with the less significant ones are reported to universities for them to address.

Universities' primary objectives are teaching and research. They invest most of their resources to achieve quality outcomes in academia and student experience. Universities have committed to achieving certain government targets and compete to advance their reputation and international and Australian rankings.

This chapter outlines teaching and research outcomes for NSW universities for 2019.

Appendix one – List of 2019 recommendations

Appendix two – Status of 2018 recommendations

Appendix three – NSW universities’ controlled entities and associated entities

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Train station crowding

Train station crowding

Transport
Management and administration
Risk
Service delivery
Workforce and capability

This report focuses on how Transport for NSW and Sydney Trains manage crowding at selected metropolitan train stations.

The audit found that while Sydney Trains has identified platform crowding as a key strategic risk, it does not have an overarching strategy to manage crowding in the short to medium term. Sydney Trains 'do not have sufficient oversight to know if crowding is being effectively managed’, the Auditor-General said.

Sydney Trains' operational response to crowding involves restricting customer access to platforms or station entries before crowding reaches unsafe levels or when it impacts on-time running. Assuming rail patronage increases, it is likely that Sydney Trains will restrict more customers from accessing platforms or station entries, causing customer delay. ‘Restricting customer access to platforms or station entries is not a sustainable approach to manage station crowding’, said the Auditor-General.

The Auditor-General made seven recommendations to improve Transport for NSW and Sydney Trains' management of station crowding. Transport for NSW have accepted these recommendations on behalf of the Transport cluster.

Public transport patronage has been impacted by COVID-19. This audit was conducted before these impacts occurred.

Read full report (PDF)

Sydney Trains patronage has increased by close to 34 per cent over the last five years, and Transport for NSW (TfNSW) expects the growth in patronage to continue over the next 30 years. As patronage increases there are more passengers entering and exiting stations, moving within stations to change services, and waiting on platforms. As a result, some Sydney metropolitan train stations are becoming increasingly crowded.

There are three main causes of station crowding:

  • patronage growth exceeding the current capacity limits of the rail network
  • service disruptions
  • special events.

Crowds can inhibit movement, cause discomfort and can lead to increased health and safety risks to customers. In the context of a train service, unmanaged crowds can affect service operation as trains spend longer at platforms waiting for customers to alight and board services which can cause service delays. Crowding can also prevent customers from accessing services.

Our 2017 performance audit, ‘Passenger Rail Punctuality’, found that rail agencies would find it hard to maintain train punctuality after 2019 unless they significantly increased the capacity of the network to carry trains and people. TfNSW and Sydney Trains have plans to improve the network to move more passengers. These plans are set out in strategies such as More Trains, More Services and in the continued implementation of new infrastructure such as the Sydney Metro. Since 2017, TfNSW and Sydney Trains have introduced 1,500 more weekly services to increase capacity. Additional network capacity improvements are in progress for delivery from 2022 onwards.

In the meantime, TfNSW and Sydney Trains need to use other ways of managing crowding at train stations until increased capacity comes on line.

This audit examined how effectively TfNSW and Sydney Trains are managing crowding at selected metropolitan train stations in the short and medium term. In doing so, the audit examined how TfNSW and Sydney Trains know whether there is a crowding problem at stations and how they manage that crowding.

TfNSW is the lead agency for transport in NSW. TfNSW is responsible for setting the standard working timetable that Sydney Trains must implement. Sydney Trains is responsible for operating and maintaining the Sydney metropolitan heavy rail passenger service. This includes operating, staffing and maintaining most metropolitan stations. Sydney Trains’ overall responsibility is to run a safe rail network to timetable.

Conclusion

Sydney Trains has identified platform crowding as a key strategic risk, but does not have an overarching strategy to manage crowding in the short to medium term. TfNSW and Sydney Trains devolve responsibility for managing crowding at stations to Customer Area Managers, but do not have sufficient oversight to know if crowding is being effectively managed. TfNSW is delivering a program to influence demand for transport in key precincts but the effectiveness of this program and its impact on station crowding is unclear as Transport for NSW has not evaluated the outcomes of the program.

TfNSW and Sydney Trains do not directly measure or collect data on station crowding. Data and observation on dwell time, which is the time a train waits at a platform for customers to get on and off trains, inform the development of operational approaches to manage crowding at stations. Sydney Trains has KPIs on reliability, punctuality and customer experience and use these to indirectly assess the impact of station crowding. TfNSW and Sydney Trains only formally assess station crowding as part of planning for major projects, developments or events.

Sydney Trains devolve responsibility for crowd management to Customer Area Managers, who rely on frontline Sydney Trains staff to understand how crowding affects individual stations. Station staff at identified key metropolitan train stations have developed customer management plans (also known as crowd management plans). However, Sydney Trains does not have policies to support the creation, monitoring and evaluation of these plans and does not systematically collect data on when station staff activate crowding interventions under these plans.

Sydney Trains stated focus is on providing a safe and reliable rail service. As such, management of station crowding is a by-product of its strategies to manage customer safety and ensure on-time running of services. Sydney Trains' operational response to crowding involves restricting customer access to platforms or stations before crowding reaches unsafe levels, or when it impacts on-time running. As rail patronage increases, it is likely that Sydney Trains will need to increase its use of interventions to manage crowding. As Sydney Trains restrict more customers from accessing platforms or station entries, it is likely these customers will experience delays caused by these interventions.

Since 2015, TfNSW has been delivering the 'Travel Choices' program which aims to influence customer behaviour and to manage the demand for public transport services in key precincts. TfNSW is unable to provide data demonstrating the overall effectiveness of this program and the impact the program has on distributing public transport usage out of peak AM and PM times. TfNSW and Sydney Trains continue to explore initiatives to specifically address crowd management.

Conclusion

TfNSW and Sydney Trains do not directly measure or collect data on station crowding. There are no key performance indicators directly related to station crowding. Sydney Trains uses performance indicators on reliability, punctuality and customer experience to indirectly assess the impact of station crowding. Sydney Trains does not have a routine process for identifying whether crowding contributed to minor safety incidents. TfNSW and Sydney Trains formally assess station crowding as part of planning for major projects, developments or events.

 

Conclusion

Sydney Trains has identified platform crowding as a strategic risk but does not have an overarching strategy to manage station crowding. Sydney Trains' stated focus is on providing a safe and reliable rail service. As such, management of station crowding is a by-product of its strategies to manage customer safety and ensure on-time running of services.

Sydney Trains devolve responsibility for managing crowding at stations to Customer Area Managers but does not have sufficient oversight to know that station crowding is effectively managed. Sydney Trains does not have policies to support the creation, monitoring or evaluation of crowd management plans at key metropolitan train stations. The use of crowding interventions is likely to increase due to increasing patronage, causing more customers to experience delays directly caused by these activities.

TfNSW and Sydney Trains have developed interventions to influence customer behaviour and to manage the demand for public transport services but are yet to evaluate these interventions. As such, their impact on managing station crowding is unclear.

Appendix one – Response from agency

Appendix two – Sydney rail network

Appendix three – Rail services contract

Appendix four – Crowding pedestrian modelling

Appendix five – Airport Link stations case study

Appendix six – About the audit

Appendix seven – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #333 - released 30 April 2020

 

Published

Actions for Destination NSW's support for major events

Destination NSW's support for major events

Treasury
Financial reporting
Management and administration
Procurement
Project management
Service delivery

This report focuses on whether Destination NSW (DNSW) can demonstrate that its support for major events achieves value for money.

The audit found that DNSW’s processes for assessing and evaluating the major events it funds are mostly effective, but its public reporting does not provide enough transparency.

DNSW provides clear information to event organisers seeking funding and has a comprehensive methodology for conducting detailed event assessments. However, the reasons for decisions to progress events from the initial assessment to the detailed assessment stage are not documented in sufficient detail.

DNSW does not publish detailed information about the events it funds or the outcomes of these events. This means that members of the public are unable to see whether its activities achieve value for money. However, DNSW’s internal reporting to its key decision‑makers, including the CEO, the Board and the Minister is appropriate.

The Auditor-General made four recommendations to DNSW, aimed at improving the transparency of its activities, improving the documentation of decisions and certain compliance matters, and streamlining its approach to assessing and evaluating events that receive smaller amounts of funding.

Read full report (PDF)

Destination NSW (DNSW) provides funding to attract a range of major events to New South Wales, including high-profile professional sports matches and tournaments, musicals, art and museum exhibitions, and participation-focused events such as festivals and sports events that members of the public can enter. The NSW Government's rationale for providing funding is to encourage event organisers to hold events in New South Wales, and to ensure that events held in New South Wales maximise the potential for attracting overseas and interstate visitors.

This audit assessed whether DNSW can demonstrate that its support for major events achieves value for money. In making this assessment, the audit examined whether:

  • DNSW effectively assesses proposals to support major events
  • DNSW effectively evaluates the impact of its support for major events.

This audit focused on DNSW's work to attract major events to New South Wales. It did not assess DNSW's tourism promotion or development work, which includes developing tourism strategies, marketing and advertising campaigns, national and international partnerships, and regional programs.

Conclusion

Destination NSW's processes for assessing event applications and evaluating its support for major events are mostly effective. DNSW's internal systems allow it to know whether its decisions are achieving value for money. Its public reporting does not provide enough information about its activities and their outcomes, although it is consistent with that of equivalent organisations in other Australian jurisdictions.

DNSW's process for assessing applications for funding from organisers of major events is mostly effective. Clear information is provided to event organisers seeking funding, and DNSW has a comprehensive methodology for conducting detailed event assessments. However, the reasons for decisions to progress events from the initial assessment to the detailed assessment stage are not documented in sufficient detail.

DNSW has a framework for disclosure and monitoring staff conflicts of interest. However, its forms for staff to disclose conflicts of interest on specific events they are working on are ambiguous. DNSW's management of gifts and benefits broadly complies with the minimum standards set by the Public Service Commission, but there are some gaps in its implementation of these.

DNSW conducts an evaluation of each major event it supports. DNSW articulates expected outcomes in contracts with event organisers and uses a sound methodology to evaluate events. Internal reporting to its key decision-makers, including the CEO, the Board and the Minister is appropriate. However, DNSW does not publish detailed information about the events it funds or the outcomes of these events. This means that members of the public are unable to see whether its activities achieve value for money.

Appendix one – Response from Destination NSW

Appendix two – About the audit 

Appendix three – Performance auditing

 

Copyright Notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #332 - released 9 April 2020.

Published

Actions for Central Agencies 2019

Central Agencies 2019

Treasury
Premier and Cabinet
Financial reporting
Internal controls and governance
Management and administration
Risk

The Auditor-General for New South Wales, Margaret Crawford, released her report today on the results of the financial audits of NSW Government central agencies, namely the Premier and Cabinet, Treasury and Customer Service clusters. There are 191 agencies in these clusters, including government financial, superannuation and insurance entities.

Unqualified audit opinions were issued on the financial statements for all agencies in the clusters. There were two high risk and 99 moderate risk audit findings on internal controls. Of these, 31 percent were repeat issues, and most related to weaknesses in information technology access controls.

The report notes a number of audit observations including:

  • a qualified opinion on information technology internal controls at an outsourced service provider
  • self-insurance losses of $1.4 billion partly due to unfavourable movements in the risk free discount rate, and increases in workers compensation claims, including psychological injury claims
  • a shortfall (unfunded liability) of $637 million at 30 June 2019 in the Home Building Compensation Fund, due to premiums not being sufficient to meet costs of the scheme
  • agencies self-assessed against the Australian Cyber Security Centre’s ‘Essential 8’ cyber risk mitigation strategies for the first time in 2018-19. Based on their own self assessments, more work needs to be done to improve cyber security resilience.

This report analyses the results of our financial statement audits of the Treasury, Premier and Cabinet and Customer Service clusters for the year ended 30 June 2019. Our key observations are summarised below.

This report provides parliament and other users of the NSW Government's central agencies and their cluster agencies financial statements with the results of our audits, observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations
  • government financial services.

Central agency clusters were significantly impacted by Machinery of Government changes which took effect on 1 July 2019. This report is focussed on agencies now in the Treasury, Premier and Cabinet and Customer Service clusters. Some of these agencies may have been in another cluster during 2018–19. Please refer to the section on Machinery of Government changes for more details.

Central agencies and their key responsibilities are set out below.

Machinery of Government (MoG) refers to how the government organises the structures and functions of the public service. MoG changes are where the government reorganises these structures and functions and they are given effect by Administrative orders.

The MoG changes announced following the NSW State election on 23 March 2019 significantly impacted Central Agencies’ clusters through Administrative Changes Orders issued on 2 April 2019 and 1 May 2019. These orders took effect on 1 July 2019.

Section highlights

Significant impacts of the 2019 MoG changes included:

  • abolishing the former Department of Finance, Services and Innovation, and creating the Department of Customer Service as the principal agency within the newly established Customer Service cluster
  • transferring Jobs for NSW, Destination NSW and the Western City and Aerotropolis Authority into the Treasury cluster
  • transferring Arts and Culture entities and Aboriginal Affairs NSW into the Premier and Cabinet cluster
  • new responsibilities, risks and challenges for each cluster

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations on the 2019 financial reporting of agencies in the Treasury, Premier and Cabinet, and Customer Service clusters.

Section highlights

  • Unqualified audit opinions were issued on the 30 June 2019 financial statements of all agencies within the three clusters, and the Legislature.
  • The NSW Self Insurance Corporation (Corporation) 2018–19 financial statements did not include an estimate of the liability for unreported incidents of abuse that have occurred within NSW Government institutions. This is because the Corporation’s financial exposure could not be reliably measured at 30 June 2019. The exposure was instead disclosed as an unquantified contingent liability in the financial statement notes. This liability may be material to the Corporation and the Total State Sector financial statements.
  • We recommend management and those charged with governance review instructions provided to management experts each year, along with other significant accounting judgements.
  • Agencies will be implementing the requirements of new accounting standards shortly. These could significantly impact their financial positions and operating results. We noted instances where agencies need to do more work on their impact assessments to minimise the risk of errors in the 2019–20 financial statements. 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the Treasury, Premier and Cabinet and Customer Service clusters.

Section highlights

  • The 2018–19 audits found two high risk and 99 moderate risk issues across the agencies. Of these, 31 per cent were repeat issues. The most common repeat issue related to weaknesses in controls over information technology user access administration.
  • NSW Government agency self-assessment results show that the NSW Public Sector's cyber security resilience needs urgent attention.
  • GovConnect received a qualified opinion from the auditor of their service provider, Unisys, over weaknesses in information technology controls.
  • Crown revenues from taxes, fines and fees continued to increase, but this was offset by decreases in stamp duty on property sales.
  • The CTP reform resulted in green slip refunds of $198 million to vehicle owners. Unclaimed refunds are to be returned to motorists through a reduction in green slip premiums.

Background

This chapter outlines our audit observations, conclusions and recommendations specific to NSW Government agencies providing financial services.

Section highlights

  • Last year's Auditor-General's Report to Parliament recommended Treasury consult with STC Pooled Fund and PCS Fund Trustees to prescribe prudential standards and requirements. Treasury has not taken specific action to address this recommendation.
    We recommend Treasury formally assess the merits of implementing prudential standards and supervision arrangements, after considering the risks, benefits and costs to scheme members.
  • The NSW Self Insurance Corporation did not include an estimate of the liability for unreported incidents of abuse that have occurred within NSW Government institutions because it could not be reliably measured at 30 June 2019. The amounts involved could be material to the Corporation's and Total State Sector's financial statements.
  • Insurance scheme liabilities were significantly impacted by unfavourable movements in economic assumptions, including a decrease in the risk free discount rate, and adverse changes in non-economic assumptions, such as higher medical costs. 

Appendix one – Timeliness of financial reporting by agency

Appendix two – Management letter findings by agency

Appendix three – Status of 2018 recommendations

Appendix four – Cluster agencies

Appendix five – Financial data

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.