Refine search Expand filter

Reports

Published

Actions for One TAFE NSW modernisation program

One TAFE NSW modernisation program

Education
Finance
Management and administration
Project management
Shared services and collaboration

The Auditor-General for New South Wales, Margaret Crawford, released a report today examining the management of the One TAFE NSW modernisation program.

In 2016, the Government released 'A Vision for TAFE NSW' which stated that TAFE NSW needed to become more flexible, efficient and competitive. It set out the need to progressively reduce significant cost inefficiencies, including by moving away from separate institutes to a single institute model. TAFE NSW established the One TAFE NSW modernisation program to deliver on that vision.

The Auditor General found that the One TAFE NSW modernisation program did not deliver against its key objectives within planned timeframes. The modernisation program originally aimed to realise $250 million in annual savings from 2018–19. Because of project delays and higher than expected transition costs, TAFE NSW did not meet the original savings target. TAFE NSW has made progress on key elements of the program and anticipates that savings will be realised in coming years.

The report makes two recommendations to improve governance arrangements for delivering on commercial objectives and increasing transparency of non commercial activities. 

The report also identifies a series of lessons for future government transformation programs.

TAFE NSW is the public provider of Vocational Education and Training (VET) in New South Wales. In 2018, TAFE NSW enrolled 436,000 students in more than 1,200 courses at around 130 locations across the State.

There have been major policy changes impacting TAFE NSW over the past decade. Under the Smart and Skilled reform, TAFE NSW started to compete with other Registered Training Organisations (RTOs) for a share of the student market.

In 2016, the NSW Government released 'A Vision for TAFE NSW'. The Vision stated that a failure to adapt to market circumstances had left TAFE NSW with unsustainable costs and inefficiencies. To address this, TAFE NSW needed to become more flexible, efficient and competitive. It set out that TAFE NSW must progressively reduce significant cost inefficiencies, including by moving away from a model of separate institutes to a One  TAFE NSW model. The NSW Government set TAFE NSW a target to achieve savings through implementing the Vision.

TAFE NSW established the One TAFE NSW modernisation program to deliver on that vision. The program initially aimed to deliver savings of $250 million per year from 2018–19, but this target was reviewed and updated as the program was being delivered.

This audit assessed whether TAFE NSW effectively managed the One TAFE NSW modernisation program to deliver on the NSW Government's vision for TAFE NSW. In making this assessment, the audit examined whether:

  • delivery of the program was well planned
  • the program was driven by sound governance arrangements
  • TAFE NSW is making progress against the intended outcomes of the program.

The audit focused on the effectiveness of planning, governance and reporting arrangements. It examined five projects within the overall modernisation program as case studies.

Conclusion

The One TAFE NSW modernisation program was an ambitious plan to deliver on the NSW Government’s vision for TAFE NSW, while achieving ongoing savings. Several factors contributed to TAFE NSW not effectively managing the program to deliver on planned timeframes and objectives. These factors include unclear expectations of the primary role of TAFE NSW, unrealistic timeframes, undertaking a large number of complex projects concurrently, governance arrangements that were not fit-for-purpose and poor-quality data.

Planning for the modernisation program and its projects was driven by top-down savings targets and pre-determined timeframes. This led to TAFE NSW attempting to deliver a large number of programs concurrently within tight timeframes. Program management capability was underdeveloped at the commencement of the program and this affected the quality of planning for delivery.

There was a lack of clarity around TAFE NSW's primary purpose. Part of the NSW Government's vision for TAFE NSW was for it to be more commercial, competitive and efficient. These objectives were not fully supported by existing legislation. The commercial objectives of the modernisation program conflicted with legislated social objectives for TAFE NSW. TAFE NSW did not have the autonomy to operate like a government-owned business in a market environment. And while TAFE NSW received separate funding to support students facing disadvantage this did not cover the costs of other non-commercial activities undertaken for social purposes, such as delivering uneconomic courses. The role of the TAFE Commission Board was ambiguous during the initial years of the program, which increased reporting requirements and blurred accountabilities for decision-making.

TAFE NSW's Strategic Plan 2016-22 nominated ten key milestones for delivery by January 2019. TAFE NSW has made progress against several important milestones, including that TAFE ‘is a single TAFE NSW brand’ and has 'industry specific TAFE NSW SkillsPoints'. Other key elements have yet to be delivered, including that TAFE NSW achieves 'integrated enterprise-wide business systems'. Because of delays to projects and higher than expected transition costs, TAFE NSW reported that it did not meet the originally targeted $250 million in annual savings for 2018–19 (which was reviewed and updated as the program was being delivered). 

Appendix one – Response from agency

Appendix two – About the audit

Appendix three – Performance auditing

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #346 - released 17 December 2020

Published

Actions for Waste levy and grants for waste infrastructure

Waste levy and grants for waste infrastructure

Planning
Environment
Management and administration
Regulation
Risk
Service delivery

The Auditor-General for New South Wales, Margaret Crawford, released a report today that examined the effectiveness of the waste levy and grants for waste infrastructure in minimising the amount of waste sent to landfill and increasing recycling rates.  

The audit found that the waste levy has a positive impact on diverting waste from landfill. However, while the levy rates increase each year in line with the consumer price index, the EPA has not conducted a review since 2009 to confirm whether they are set at the optimal level. The audit also found that there were no objective and transparent criteria for which local government areas should pay the levy, and the list of levied local government areas has not been reviewed since 2014. 

Grant funding programs for waste infrastructure administered by the EPA and the Environmental Trust have supported increases in recycling capacity. However, these grant programs are not guided by a clear strategy for investment in waste infrastructure. 

The Auditor-General made six recommendations aimed at ensuring the waste levy is as effective as possible at meeting its objectives and ensuring funding for waste infrastructure is contributing effectively to recycling and waste diversion targets.

 

Overall, waste generation in New South Wales (NSW) is increasing. This leads to an increasing need to manage waste in ways that reduce the environmental impact of waste and promote the efficient use of resources. In 2014, the NSW Government set targets relating to recycling rates and diversion of waste from landfill, to be achieved by 2021–22. The NSW Waste and Resource Recovery (WARR) Strategy 2014–21 identifies the waste levy, a strong compliance regime, and investment in recycling infrastructure as key tools for achieving these waste targets.

This audit assessed the effectiveness of the NSW Government in minimising waste sent to landfill and increasing recycling rates. The audit focused on the waste levy, which is paid by waste facility operators when waste is sent to landfill, and grant programs that fund infrastructure for waste reuse and recycling.

The waste levy is regulated by the Environment Protection Authority (EPA) and is generally paid when waste is disposed in landfill. The waste levy rates are set by the NSW Government and prescribed in the Protection of Environment Operations (Waste) Regulation 2014. As part of its broader role in reviewing the regulatory framework for managing waste and recycling, the EPA can provide advice to the government on the operation of the waste levy.

The purpose of the waste levy is to act as an incentive for waste generators to reduce, re-use or recycle waste by increasing the cost of sending waste to landfill. In 2019–20, around $750 million was collected through the waste levy in NSW. The government spends approximately one third of the revenue raised through the waste levy on waste and environmental programs.

One of the waste programs funded through the one third allocation of the waste levy is Waste Less, Recycle More (WLRM). This initiative funds smaller grant programs that focus on specific aspects of waste management. This audit focused on five grant programs that fund projects that provide new or enhanced waste infrastructure such as recycling facilities. Four of these programs were administered by the Environmental Trust and one by the EPA.

Conclusion

The waste levy has a positive impact on diverting waste from landfill. However, aspects of the EPA's administration of the waste levy could be improved, including the frequency of its modelling of the waste levy impact and coverage, and the timeliness of reporting. Grant funding programs have supported increases in recycling capacity but are not guided by a clear strategy for investment in waste infrastructure which would help effectively target them to where waste infrastructure is most needed. Data published by the EPA indicates that the NSW Government is on track to meet the recycling target for construction and demolition waste, but recycling targets for municipal solid waste and commercial and industrial waste are unlikely to be met.

Waste levy

The waste levy rate, including a schedule of annual increases to 2016, was set by the NSW Government in 2009. Since 2016, the waste levy rate has increased in line with the consumer price index (CPI). The EPA has not conducted recent modelling to test whether the waste levy is set at the optimal level to achieve its objectives. The waste levy operation was last reviewed in 2012, although some specific aspects of the waste levy have been reviewed more recently, including reviews of waste levy rates for two types of waste. The waste levy is applied at different rates across the state. Decisions about which local government areas (LGAs) are subject to the levy, and which rate each LGA pays, were made in 2009 and potential changes were considered but not implemented in 2014. Currently, there are no objective and transparent criteria for determining which LGAs pay the levy. The EPA collects waste data from waste operators. This data has improved since 2015, but published data is at least one year out of date which limits its usefulness to stakeholders when making decisions relating to waste management.

Grants for waste infrastructure

All state funding for new and enhanced waste infrastructure in NSW is administered through grants to councils and commercial waste operators. The government's Waste and Resource Recovery (WARR) Strategy 2014–21 includes few priorities for waste infrastructure and there is no other waste infrastructure strategy in place to guide investment. The absence of a formal strategy to guide infrastructure investment in NSW limits the ability of the State Government to develop a shared understanding between planners, councils and the waste industry about waste infrastructure requirements and priorities. The Department of Planning, Industry and Environment is currently developing a 20-year waste strategy and there is an opportunity for the government to take a more direct role in planning the type, location and timing of waste infrastructure needed in NSW.

The grants administration procedures used for the grant programs reviewed in this audit were well designed. However, we identified some gaps in risk management, record-keeping and consistency of information provided to applicants and assessment teams. In four of the five programs we examined, there was no direct alignment between program objectives and the NSW Government's overall waste targets.

Achievement of the 2014–21 state targets for waste and resource recovery (WARR targets) is reliant in part on the availability of infrastructure that supports waste diversion and recycling. The state WARR targets dependent on waste infrastructure are:

  • Increase recycling rates to 70 per cent for municipal solid waste and commercial and industrial waste, and 80 per cent for construction and demolition waste.
  • Increase waste diverted from landfill to 75 per cent.

A further target — manage problem waste better by establishing or upgrading 86 drop-off facilities or services for managing household problem wastes state-wide — is dependent on accessible community waste drop-off facilities across NSW.

Exhibit 7 identifies the five grant programs that provide funding for new or enhanced waste infrastructure to increase capacity for reuse or recycling of waste. All five of these programs were examined in the audit.
In addition to the grant programs shown in Exhibit 7, other programs provide funding for infrastructure, but at a smaller scale. Examples of these include:

  • Bin Trim which provides rebates to small businesses for small scale recycling equipment such as cardboard and soft plastic balers.
  • Litter grants which provide funding for litter bins.
  • Weighbridges grants for installation of a weighbridge at waste facilities.
  • Landfill consolidation and environmental improvement grants for rural councils to replace old landfills with transfer stations or to improve the infrastructure at landfill sites.

Appendix one – Responses from audited agencies

Appendix two – About the audit

Appendix three – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #343 - released 26 November 2020

Published

Actions for Internal controls and governance 2020

Internal controls and governance 2020

Education
Environment
Community Services
Finance
Health
Industry
Justice
Premier and Cabinet
Transport
Treasury
Compliance
Cyber security
Information technology
Internal controls and governance
Management and administration
Procurement

The Auditor-General for New South Wales, Margaret Crawford today released her report on the findings and recommendations from the 2019–20 financial audits that relate to internal controls and governance at 40 of the largest agencies in the NSW public sector.

The bushfire and flood emergencies and the COVID‑19 pandemic continue to have a significant impact on the people and public sector of New South Wales. The scale of the government response to these events has been significant. The report focuses on the effectiveness of internal controls and governance processes, including relevant agencies’ response to the emergencies. In particular, the report focuses on:

  • financial and information technology controls
  • business continuity and disaster recovery planning arrangements
  • procurement, including emergency procurement
  • delegations that support timely and effective decision-making.

Due to the ongoing impact of COVID‑19 agencies have not yet returned to a business‑as‑usual environment. ‘Agencies will need to assess their response to the recent emergencies and update their business continuity, disaster recovery and other business resilience frameworks to reflect the lessons learnt from these events’ the Auditor-General said.

The report noted that special procurement provisions were put in place to allow agencies to better respond to the COVID-19 pandemic. The Auditor-General recommended agencies update their procurement policies to reflect the current requirements of the NSW Procurement Framework and the emergency procurement requirements.

Read the PDF report

This report analyses the internal controls and governance of 40 of the largest agencies in the NSW public sector for the year ended 30 June 2020. These 40 agencies constitute an estimated 85 per cent of total expenditure for all NSW public sector agencies.

1. Internal control trends
New, repeat and high risk findings

Internal control deficiencies increased by 13 per cent compared to last year. This is predominately due to a seven per cent increase in new internal control deficiencies and 24 per cent increase in repeat internal control deficiencies. There were ten high risk findings compared to four last year.

The recent emergencies have consumed agency time and resources and may have contributed to the increase in internal control deficiencies, particularly repeat deficiencies.

Agencies should:

  • prioritise addressing high-risk findings
  • address repeat internal control deficiencies by re-setting action plans and timeframes and monitoring the implementation status of recommendations.
Common findings

A number of findings remain common across multiple agencies over the last four years, including:

  • out of date or missing policies to guide appropriate decisions
  • poor record keeping and document retention
  • incomplete or inaccurate centralised registers or gaps in these registers.
2. Information technology controls
IT general controls

We found deficiencies in information security controls over key financial systems including:

  • user access administration deficiencies relating to inadequate oversight of the granting, review and removal of user access at 53 per cent of agencies
  • privileged users were not appropriately monitored at 43 per cent of agencies
  • deficient password controls that did not align to the agency's own password policies at 25 per cent of agencies.

The deficiencies above increase the risk of non-compliance with the NSW Cyber Security Policy, which requires agencies to have processes in place to manage user access, including privileged user access to sensitive information or systems and remove that access once it is not required or employment is terminated.

3. Business continuity and disaster recovery planning
Assessing risks to business continuity and Scenario testing

The response to the recent emergencies and the COVID-19 pandemic has encompassed a wide range of activities, including policy setting, on-going service delivery, safety and availability of staff, availability of IT and other systems and financial management. Agencies were required to activate their business continuity plans in response, and with the continued impact of COVID-19 have not yet returned to a business-as-usual environment.

Our audits focused on the preparedness of agency business continuity and disaster recovery planning arrangements prior to the onset of the COVID-19 pandemic.

We identified deficiencies in agency business continuity and disaster recovery planning arrangements. Twenty-three per cent of agencies had not conducted a business impact analysis (BIA) to identify critical business functions and determine business continuity priorities. Agencies can also improve the content of their BIA. For example, ten per cent of agencies' BIAs did not include recovery time objectives and six per cent of agencies did not identify key IT systems that support critical business functions. Scenario testing improves the effectiveness with which a live crisis is handled, but 40 per cent of agencies had not conducted a business continuity scenario testing exercise in the period from 1 January 2019 to 31 December 2019. There were also opportunities to improve the effectiveness of scenario testing exercises by:

  • involving key dependent or inter-dependent third parties who support or deliver critical business functions
  • testing one or more high impact scenarios identified in their business continuity plan
  • preparing a formalpost-exercise report documenting the outcome of their scenario testing.

Agencies have responded to the recent emergencies but addressing deficiencies will ensure agencies have adequate safeguards in their processes to again respond in the future, if required.

During 2020–21 we plan to conduct a performance audit on 'Business continuity and disaster recovery planning'. This audit will consider the effectiveness of agency business continuity planning arrangements to maintain business continuity through the recent emergencies and/or COVID-19 pandemic and return to a business-as-usual environment. We also plan to conduct a performance audit on whole-of-government 'Coordination of emergency responses'.

Responding to disruptions

We found agencies' governance functions could have been better informed about responses to disruptive incidents that had activated a business continuity or disaster recovery response between 1 January 2019 to 31 December 2019. For instance:

in 89 per cent of instances where a business continuity response was activated, a post-incident review had been performed. In 82 per cent of these instances, the outcomes were reported to a relevant governance or executive management committee

in 95 per cent of instances where a disaster recovery response was activated, a post incident review had been performed. In 86 per cent of these instances, the outcomes were reported to a relevant governance committee or executive management committee.

Examples of recorded incidents included extensive air quality issues and power outages due to bushfires, system and network outages, and infected and hijacked servers.

Agencies should assess their response to the recent emergencies and the COVID-19 pandemic and update business continuity, disaster recovery and other business resilience frameworks to incorporate lessons learned. Agencies should report to those charged with governance on the results and planned actions.

Management review and oversight Eighty-two per cent and 86 per cent of agencies report to their audit and risk committees (ARC) on their business continuity and disaster recovery planning arrangements, respectively. Only 18 per cent and five per cent of ARCs are briefed on the results of respective scenario testing. Briefing ARCs on the results of scenario testing exercises helps inform their decisions about whether sound and effective business continuity and disaster recovery arrangements have been established.
4. Procurement, including emergency procurement
Policy framework

Agency procurement policies did not capture the requirements of several key NSW Procurement Board Directions (the Directions), increasing the risk of non-compliance with the Directions. We noted: 

  • 67 per cent of agencies did specify that procurement above $650,000 must be open to market unless exempt or procured through an existing Whole of Government Scheme or contract
  • 36 per cent of agencies did specify that procurements above $500,000 payable in foreign currencies must be hedged
  • 69 per cent of agencies' policies did specify that the agency head or cluster CFO must authorise the engagement of consultants where the engagement of the supplier does not comply with the standard commercial framework.

Recommendation: Agencies should review their procurement policies and guidelines to ensure they capture the key requirements of the NSW Government Procurement Policy Framework, including NSW Procurement Board Directions.

Managing contracts

Eighty-eight per cent of agencies maintain a central contract register to record all details of contracts above $150,000, which is a requirement of GIPA legislation. Of the agencies that maintained registers, 13 per cent did not capture all contracts and eight per cent did not include all relevant contract details.

Sixteen per cent of agencies did not periodically review their contract register. Timely review increases compliance with GIPA legislation, and enhances the effectiveness with which procurement business units monitor contract end dates, contract extensions and commence new procurement.

Training and support

Ninety-three per cent of agencies provide training to staff involved in procurement processes, and a further 77 per cent of agencies provide this training on an on-going basis. Of the seven per cent of agencies that had not provided training to staff, we noted gaps in aspects of their procurement activity, including:

  • not conducting value for money assessments prior to renewing or extending the contract with their existing supplier
  • not obtaining approval from a delegated authority to commence the procurement process
  • procurement documentation not specifying certain key details such as the conditions for participation including any financial guarantees and dates for the delivery of goods or supply of services.

Training on procurement activities ensures there is effective management of procurement processes to support operational requirements, and compliance with procurement directions.

Procurement activities While agencies had implemented controls for tender activities above $650,000, 43 per cent of unaccredited agencies did not comply with the NSW Procurement Policy Framework because they had not had their procurement endorsed by an accredited agency within the cluster or by NSW Procurement. This endorsement aims to ensure the procurement is properly planned to deliver a value for money outcome before it commences.
Emergency procurement

As at 30 June 2020, agencies within the scope of this report reported conducting 32,239 emergency procurements with a total contract value of $316,908,485. Emergency procurement activities included the purchase of COVID-19 cleaning and hygiene supplies.

The government, through NSW Procurement released the 'COVID-19 Emergency procurement procedure', which relaxed procurement requirements to allow agencies to make COVID-19 emergency procurements. Our review against the emergency procurement measures found most agencies complied with requirements. For example:

  • 95 per cent of agencies documented an assessment of the need for the emergency procurement for the good and/or service
  • 86 per cent of agencies obtained authorisation of the emergency procurement by the agency head or the nominated employee under Public Works and Procurement Regulation 2019
  • 76 per cent of agencies reported the emergency procurement to the NSW Procurement Board.

Complying with the procedure helps to ensure government resources are being efficiently, effectively, economically and in accordance with the law.

Recommendation: Agency procurement frameworks should be reviewed and updated so they can respond effectively to emergency situations that may arise in the future. This includes:

  • updating procurement policies and guidelines to define an emergency situation, specify who can approve emergency procurement and capture other key requirements
  • using standard templates and documentation to prompt users to capture key requirements, such as needs analysis, supplier selection criteria, price assessment criteria, licence and insurance checks
  • having processes for reporting on emergency procurements to those charged with governance and NSW Procurement.
5. Delegations
Instruments of delegation

We found that agencies have established financial and human resources delegations, but some had not revisited their delegation manuals following the legislative and machinery of government changes. For those agencies impacted by machinery of government changes we noted:

  • 16 per cent of agencies had not updated their financial delegations to reflect the changes
  • 16 per cent of agencies did not update their human resources delegations to reflect the changes.

Delegations manuals are not always complete; 16 per cent of agencies had no delegation for writing off bad debts and 26 per cent of agencies had no delegation for writing off capital assets.

Recommendation: Agencies should ensure their financial and human resources delegation manuals contain regular set review dates and are updated to reflect the Government Sector Finance Act 2018, machinery of government changes and their current organisational structure and roles and responsibilities.

Compliance with delegations

Agencies did not understand or correctly apply the requirements of the Government Sector Finance Act 2018 (GSF Act), resulting in non-compliance with the Act. We found that 18 per cent of agencies spent deemed appropriations without obtaining an authorised delegation from the relevant Minister(s), as required by sections 4.6(1) and 5.5(3) of the GSF Act.

Further detail on this issue will be included in our Auditor-General's Reports to Parliament on Central Agencies, Education, Health and Stronger Communities, which will be tabled throughout December 2020.

Recommendation: Agencies should review financial and human resources delegations to ensure they capture all key functions of laws and regulations, and clearly specify the relevant power or function being conferred on the officer.

6. Status of 2019 recommendations
Progress implementing last year's recommendations

Recommendations were made last year to improve transparency over reporting on gifts and benefits and improve the visibility management and those charged with governance had over actions taken to address conflicts of interest that may arise. This year, we continue to note:

  • 38 per cent of agencies have not updated their gifts and benefits register to include all the key fields required under the minimum standards set by the Public Service Commission
  • 56 per cent of agencies have not provided training to staff and 63 per cent of agencies have not implemented an annual attestation process for senior management
  • 97 per cent of agencies have not published their gifts and benefits register on their website and 41 per cent of agencies are not reporting on trends in the gifts and benefits register to those charged with governance.

While we acknowledge the significance of the recent emergencies, which have consumed agency time and resources, we note limited progress has been made implementing these recommendations. Further detail on the status of implementing all recommendations is in Appendix 2.

Recommendation: Agencies should re-visit the recommendations made in last year's report on internal controls and governance and action these recommendations.

Internal controls are processes, policies and procedures that help agencies to:

  • operate effectively and efficiently
  • produce reliable financial reports
  • comply with laws and regulations
  • support ethical government.

This chapter outlines the overall trends for agency controls and governance issues, including the number of audit findings, the degree of risk those deficiencies pose to the agency, and a summary of the most common deficiencies we found across agencies. The rest of this report presents this year’s controls and governance findings in more detail.

Section highlights

We identified ten high risk findings, compared to four last year with two findings repeated from the previous year. There was an overall increase of 13 per cent in the number of internal control deficiencies compared to last year due to a seven per cent increase in new internal control deficiencies, and a 24 per cent increase in repeat internal control deficiencies. The recent emergencies have consumed agency time and resources and may have contributed to the increase in internal control deficiencies, particularly repeat deficiencies.

We identified a number of findings that remain common across multiple agencies over the last four years. Some of these findings related to areas that are fundamental to good internal control environments and effective organisational governance. Examples include:

  • out of date or missing policies to guide appropriate decisions
  • poor record keeping and document retention
  • incomplete or inaccurate centralised registers, or gaps in these registers.

Policies, procedures and internal controls should be properly designed, be appropriate for the current organisational structure and its business activities, and work effectively.

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency controls to manage key financial systems.

Section highlights

Government agencies’ financial reporting is heavily reliant on information technology (IT). We continue to see a high number of deficiencies related to IT general controls, particularly those related to user access administration. These controls are key in adequately protecting IT systems from inappropriate access and misuse.

IT is also important to the delivery of agency services. These systems often provide the data to help monitor the efficiency and effectiveness of agency processes and services they deliver. Our financial audits do not review all agency IT systems. For example, IT systems used to support agency service delivery are generally outside the scope of our financial audit. However, agencies should also consider the relevance of our findings to these systems.

Agencies need to continue to focus on assessing the risks of inappropriate access and misuse and the implementation of controls to adequately protect their systems, focussing on the processes in place to grant, remove and monitor user access, particularly privileged user access.

 

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency business continuity and disaster recovery planning arrangements.

Section highlights

We identified deficiencies in agency business continuity and disaster recovery planning arrangements and opportunities for agencies to enhance their business continuity management and disaster recovery planning arrangements. This will better prepare them to respond to a disruption to their critical functions, resulting from an emergency or other serious event. Twenty-three per cent of agencies had not conducted a business impact analysis (BIA) to identify critical business functions and determine business continuity priorities and 40 per cent of agencies had not conducted a business continuity scenario testing exercise in the period from 1 January 2019 to 31 December 2019. Scenario testing improves the effectiveness with which a live crisis is handled.

This section focusses on the preparedness of agency business continuity and disaster recovery planning arrangements prior to the onset of the COVID-19 pandemic. While agencies have responded to the recent emergencies, proactively addressing deficiencies will ensure agencies have adequate safeguards in their processes to again respond in the future, if required.

During 2020–21 we plan to conduct a performance audit on 'Business continuity and disaster recovery planning'. This audit will consider the effectiveness of agency business continuity planning arrangements to maintain business continuity through the recent emergencies and/or COVID-19 pandemic and return to a business-as-usual environment. We also plan to conduct a performance audit on whole-of-government 'Coordination of emergency responses'.

 

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of procurement agency procurement policies and procurement activity.

Section highlights

We found agencies have procurement policies in place to manage procurement activity, but the content of these policies was not sufficiently detailed to ensure compliance with NSW Procurement Board Directions (the Directions). The Directions aim to ensure procurement activity achieves value for money and meets the principles of probity and fairness.

Agencies have generally implemented controls over their procurement process. In relation to emergency procurement activity, agencies reported conducting 32,239 emergency procurements with a total contract value of $316,908,485 up to 30 June 2020. Our review of emergency procurement activity conducted during 2019–20 identified areas where some agencies did not fully comply with the 'COVID-19 Emergency procurement procedure'.

We also found not all agencies are maintaining complete and accurate contract registers. This not only increases the risk of non-compliance with GIPA legislation, but also limits the effectiveness of procurement business units to monitor contract end dates, contract extensions and commence new procurement in a timely manner. We noted instances where agencies renewed or extended contracts without going through a competitive tender process during the year.

 

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency compliance with financial and human resources delegations.

Section highlights
We found that agencies are not always regularly reviewing and updating their financial and human resources delegations when there are changes to legislation or other organisational changes within the agency or from machinery of government changes. For example, agencies did not understand or correctly apply the requirements of the GSF Act, resulting in non-compliance with the Act. We found that 18 per cent of agencies spent deemed appropriations without obtaining an authorised delegation from the relevant Minister(s), as required by sections 4.6(1) and 5.5(3) of the GSF Act.
In order for agencies to operate efficiently, make necessary expenditure and human resource decisions quickly and lawfully, particularly in emergency situations, it is important that delegations are kept up to date, provide clear authority to decision makers and are widely communicated.

Appendix one – List of 2020 recommendations 

Appendix two – Status of 2019 recommendations

Appendix three – Cluster agencies

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Their Futures Matter

Their Futures Matter

Justice
Community Services
Education
Health
Whole of Government
Cross-agency collaboration
Internal controls and governance
Management and administration
Project management

The Auditor-General for New South Wales, Margaret Crawford, released a report today examining whether the Department of Communities and Justice had effective governance and partnership arrangements in place to deliver ‘Their Futures Matter’.

Their Futures Matter was intended to place vulnerable children and families at the heart of services, and direct investment to where funding and programs deliver the greatest social and economic benefits. It was a four-year whole-of-government reform in response to the 2015 Tune Review of out-of-home care.

The Auditor-General found that while important foundations were put in place, and new programs trialled, the key objective to establish an evidence-based whole-of-government early intervention approach for vulnerable children and families in NSW was not achieved.

Governance and cross-agency partnership arrangements to deliver Their Futures Matter were found to be ineffective. 'Their Futures Matter lacked mechanisms to secure cross portfolio buy‑in and did not have authority to drive reprioritisation of government investment', the Auditor-General said.

At the reform’s close, the majority of around $380 million in investment funding remains tied to existing agency programs, with limited evidence of their comparative effectiveness or alignment with Their Futures Matter policy objectives. The reform concluded on 30 June 2020 without a strategy or plan in place to achieve its intent.

The Auditor-General made four recommendations to the Department of Communities and Justice, aimed at improving implementation of outstanding objectives, revising governance arrangements, and utilising the new human services data set to address the intent of the reform. However, these recommendations respond only in part to the findings of the audit.

According to the Auditor-General, ‘Cross-portfolio leadership and action is required to ensure a whole-of-government response to delivering the objectives of Their Futures Matter to improve outcomes for vulnerable children, young people and their families in New South Wales.’

Read full report (PDF)

In 2016, the NSW Government launched 'Their Futures Matter' (TFM) - a whole-of-government reform aimed at delivering improved outcomes for vulnerable children, young people and their families. TFM was the government's key response to the 2015 Independent Review of Out of Home Care in New South Wales (known as 'the Tune Review').

The Tune Review found that, despite previous child protection reforms, the out of home care system was ineffective and unsustainable. It highlighted that the system was not client-centred and was failing to improve the long-term outcomes for vulnerable children and families. The review found that the greatest proportion of relevant expenditure was made in out of home care service delivery rather than in evidence-based early intervention strategies to support children and families when vulnerabilities first become evident to government services (such as missed school days or presentations to health services).

The then Department of Family and Community Services (FACS) designed the TFM reform initiatives, in consultation with central and human services agencies. A cross-agency board, senior officers group, and a new unit in the FACS cluster were established to drive the implementation of TFM. In the 2016–17 Budget, the government allocated $190 million over four years (2016–17 to 2019–20) to the reform. This resourced the design and commissioning of evidence-based pilots, data analytics work, staffing for the implementation unit and secretariat support for the board and cross-agency collaboration.

As part of the TFM reform, the Department of Premier and Cabinet, NSW Treasury and partnering agencies (NSW Health, Department of Education and Department of Justice) identified various existing programs that targeted vulnerable children and families (such as the preceding whole-of-government ‘Keep Them Safe’ reform coming to an end in June 2020). Funding for these programs, totalling $381 million in 2019–20, was combined to form a nominal ‘investment pool’. The government intended that the TFM Implementation Board would use this pool to direct and prioritise resource allocation to evidence-based interventions for vulnerable children and families in NSW.

This audit assessed whether TFM had effective governance and partnership arrangements in place to enable an evidence-based early intervention investment approach for vulnerable children and families in NSW. We addressed the audit objective with the following audit questions:

  • Was the TFM reform driven by effective governance arrangements?
  • Was the TFM reform supported by effective cross-agency collaboration?
  • Has the TFM reform generated an evidence base to inform a cross-agency investment approach in the future?

The audit did not seek to assess the outcomes for children, young people and families achieved by TFM programs and projects.

Conclusion

The governance and cross-agency partnership arrangements used to deliver the Their Futures Matter reform were ineffective. Important foundations were put in place, and new programs trialled over the reform's four years. However, an evidence-based whole-of-government early intervention approach for vulnerable children and families in NSW − the key objective of the reform − was not established. The reform concluded in June 2020 without a strategy or plan in place to achieve its intent.

The governance arrangements established for the Their Futures Matter (TFM) reform did not provide sufficient independence, authority and cross-agency clout to deliver on the reform’s intent. This hindered delivery of the reform's key elements, particularly the redirection of funding to evidence-based earlier intervention supports, and limited the impact that TFM could have on driving system change.

TFM increased focus on the contribution that other agencies outside of the former Family and Community Services portfolio could make in responding to the needs of vulnerable children and families, and in reducing the demand costs of related government service delivery. Despite being a whole-of-government reform, TFM lacked mechanisms to secure cross-portfolio buy-in and lacked the powers to drive reprioritisation of government investment in evidence-based and earlier intervention supports across agencies. At the reform’s close, the majority of the reform's investment pool funding remained tied to existing agency programs, with limited evidence of their comparative effectiveness or alignment with Their Futures Matter policy objectives.

TFM began building an evidence base about ‘what works’, including piloting programs and creating a new dataset to identify risk factors for vulnerability and future costs to government. However, this evidence base does not yet comprehensively map how existing services meet needs, identify system duplications or gaps, nor demonstrate which government funded supports and interventions are most effective to make a difference to life outcomes for vulnerable children and families in NSW.
Despite these issues, the need, intent and vision for Their Futures Matter remains relevant and urgent, as issues identified in the Tune Review remain pertinent.

Their Futures Matter (TFM) is a whole-of-government reform to deliver improved outcomes for vulnerable children, young people and their families.

Supported by a cross-agency TFM Board, and the TFM Unit in the then Department of Family and Community Services (FACS), the reform aimed to develop whole-of-government evidence-based early intervention investment approaches for vulnerable children and families in NSW.

Governance refers to the structures, systems and practices that an organisation has in place to:

  • assign decision-making authorities and establish the organisation's strategic direction
  • oversee the delivery of its services, the implementation of its policies, and the monitoring and mitigation of its key risks
  • report on its performance in achieving intended results, and drive ongoing improvements.

We examined whether the TFM reform was driven by effective governance arrangements and cross-agency collaboration.

The reform agenda and timeframe set down for Their Futures Matter (TFM) were ambitious. This chapter assesses whether the TFM Board and TFM Unit had the capability, capacity and clout within government to deliver the reform agenda.

Creating a robust evidence base was important for Their Futures Matter, in order to:

  • identify effective intervention strategies to improve supports and outcomes for vulnerable children and families
  • make efficient use of taxpayer money to assist the maximum number of vulnerable children and families
  • inform the investment-based approach for future funding allocation.

This chapter assesses whether the TFM reform has developed an evidence base to inform cross-agency investment decisions.

Appendix one – Response from agency

Appendix two – TFM governance entities

Appendix three – TFM Human Services Data Set

Appendix four – TFM pilot programs

Appendix five – About the audit

Appendix six – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #337 - released 24 July 2020

Published

Actions for Universities 2019 audits

Universities 2019 audits

Universities
Cyber security
Financial reporting
Internal controls and governance
Procurement

This report contains findings on the results of financial audits of NSW universities for the year ended 31 December 2019.

All ten NSW universities received unqualified audit opinions. The 2019 financial results for universities are reported as at 31 December and reflect results from operations before the impact of the COVID‑19 pandemic.

The combined revenues for all NSW universities increased by $381 million to $11.4 billion in 2019, driven by increases in student revenues. Revenue from overseas students continued to grow faster than that from domestic students and contributed $3.6 billion in course fees to NSW universities in 2019.

Overseas students from the top three countries of origin, being China, India and Nepal, represented 72.4 per cent of all enrolments of overseas students and 65.4 per cent of all overseas student revenues for 2019. Revenue from students from these three countries comprised 40.9 per cent of total student revenues for all NSW universities, creating a considerable concentration risk for NSW universities.

The COVID‑19 pandemic may significantly impact the financial results of NSW universities in 2020. NSW universities provided data on COVID‑19 impacted student enrolments for semester one 2020. Overall numbers of student enrolments in semester one 2020 were 5.8 per cent beneath projections. Overseas student enrolments were 13.8 per cent beneath expectations and domestic student enrolments were 2.4 per cent below expectations.

The report makes recommendations to the NSW universities, aimed at strengthening controls over information technology, cyber security, validating published performance information, procurement practices and the oversight of their overseas controlled entities' legal and policy compliance functions.

Read full report (PDF)

This report analyses the results of our audits of the financial statements of the ten NSW universities for the year ended 31 December 2019. The table below summarises our key observations.

1. Financial reporting

Financial reporting

The 2019 financial statements of all ten NSW universities received unmodified audit opinions.

One controlled entity of the Western Sydney University received a qualified audit opinion.

Five NSW universities finalised their audited financial statements this year on or before the date they did last year.

New accounting standards, which changed how universities report income and treat operating leases, became effective from 1 January 2019.

Sources of revenue from operations

Government grants as a proportion of the total income of NSW universities continued to decrease.

Fee revenue from overseas students continued to grow faster than fees from domestic students. Forty-one per cent of NSW universities' total student revenue came from overseas students from three countries.

Five NSW universities increased the proportion of revenue they receive from overseas students from a single country. Two universities sourced over 73 per cent of their total overseas student revenue from students from a single country of origin in 2019.

Other revenues Two universities attracted over 69.5 per cent of the total philanthropic revenue of $174 million received by all NSW universities in 2019.
Operating expenditures Combined total operating expenditure for NSW universities increased to $9.9 billion in 2019, a rise of 5.2 per cent from 2018.
Current ratio At 31 December 2019, five NSW universities had a current ratio of less than one, meaning those universities need to actively manage their cash to meet current obligations.
Controlled entities

All six NSW universities with overseas controlled entities have devolved responsibility for governance and legislative compliance to their overseas controlled entities.

Recommendation (repeat issue): NSW universities should strengthen their governance arrangements to oversight their overseas controlled entities' legal and policy compliance functions.

COVID-19 impacts and responses

The 2019 financial results for universities are reported as at 31 December. Consequently, the results for the 2019 year were unaffected by the impact of the COVID-19 pandemic.

NSW universities provided data on the COVID-19 impacted student enrolments for semester one 2020. Overall numbers of student enrolments were 5.8 per cent beneath projections. Overseas student enrolments were 13.8 per cent beneath expectations and domestic student enrolments were 2.4 per cent beneath expectations.

NSW universities are responding to the challenges presented by COVID-19 by moving course delivery online, expanding student support and introducing cost saving measures.

2. Internal controls and governance

Internal control findings

Our audits identified 108 internal control deficiencies in 2019 (99 in 2018).

Gaps in information technology (IT) controls comprised the majority of these deficiencies. Deficiencies included a lack of sufficient user access reviews, inadequate review and approval of change management processes, and issues with password settings.

We identified one high risk financial control deficiency at the University of New South Wales, which resulted in the University providing for a potential underpayment of casual staff salaries.

NSW universities continue to implement recommendations arising from 35 findings raised in previous years.

Performance reporting

Five NSW universities still do not have formal processes to internally review and validate performance information published in their annual reports.

Recommendation (repeat issue): NSW universities should strengthen processes to review and validate published performance information.

Cyber security

Two universities have not yet implemented a cyber risk policy and three universities have not formally trained staff in cyber awareness.

Recommendation (repeat issue): NSW universities should strengthen cyber security frameworks and controls to protect sensitive data and prevent financial and reputational losses.

Management of IT service providers NSW universities have contracts with vendors to support their computer systems. Five universities have not formally established frameworks to manage these contracts. Poor contract management can compound risks associated with IT control deficiencies.
Data breach management Universities are required to maintain the privacy of sensitive data which, if disclosed or used inappropriately, could result in harm to individuals, financial loss, or loss of intellectual property. Two NSW universities have not established formal policies to manage data breaches.
Procurement

All universities have a procurement policy. Most universities have a documented procurement manual and contact management policy.

Recommendation: NSW universities should review their procurement and contract management policies and procedures to ensure that they are relevant and effective in reducing risk and improving purchasing outcomes.

3. Teaching and research

Graduate employment outcomes Eight out of ten NSW universities exceeded the national average for full-time employment rates of their undergraduates in 2019. Six universities performed better than the national average for full-time employment outcomes of their postgraduates in 2019.
Student enrolments by field of education Enrolments at NSW universities increased the most in Management and Commerce courses in 2019.
Achieving diversity outcomes

Five universities in 2018 (five in 2017) met the target enrolment rate for students from low socio-economic status (SES) backgrounds.

Eight universities increased enrolments of students from Aboriginal and Torres Strait Islander backgrounds in 2018.

 

This report provides Parliament with the results of our financial audits of New South Wales universities and their controlled entities in 2019, including our analysis, observations and recommendations in the following areas:

  • financial reporting
  • internal controls and governance
  • teaching and research.

Financial reporting is an important element of governance. Confidence and transparency in university sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations on the financial reporting of NSW universities for 2019.

Appropriate and robust internal controls help reduce risks associated with managing finances, compliance and administration of NSW universities.

This chapter outlines the internal controls related observations and insights across NSW universities for 2019, including overall trends in findings, level of risk and implications.

Our audits do not review all aspects of internal controls and governance every year. The more significant issues and risks are included in this chapter. These along with the less significant ones are reported to universities for them to address.

Universities' primary objectives are teaching and research. They invest most of their resources to achieve quality outcomes in academia and student experience. Universities have committed to achieving certain government targets and compete to advance their reputation and international and Australian rankings.

This chapter outlines teaching and research outcomes for NSW universities for 2019.

Appendix one – List of 2019 recommendations

Appendix two – Status of 2018 recommendations

Appendix three – NSW universities’ controlled entities and associated entities

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Internal Controls and Governance 2017

Internal Controls and Governance 2017

Finance
Education
Community Services
Health
Justice
Whole of Government
Asset valuation
Compliance
Cyber security
Information technology
Internal controls and governance
Project management
Risk

Agencies need to do more to address risks posed by information technology (IT).

Effective internal controls and governance systems help agencies to operate efficiently and effectively and comply with relevant laws, standards and policies. We assessed how well agencies are implementing these systems, and highlighted opportunities for improvement.
 

1. Overall trends

New and repeat findings

The number of reported financial and IT control deficiencies has fallen, but many previously reported findings remain unresolved.

High risk findings

Poor systems implementations contributed to the seven high risk internal control deficiencies that could affect agencies.

Common findings

Poor IT controls are the most commonly reported deficiency across agencies, followed by governance issues relating to cyber security, capital projects, continuous disclosure, shared services, ethics and risk management maturity.

2. Information Technology

IT security

Only two-thirds of agencies are complying with their own policies on IT security. Agencies need to tighten user access and password controls.

Cyber security

Agencies do not have a common view on what constitutes a cyber attack, which limits understanding the extent of the cyber security threat.

Other IT systems

Agencies can improve their disaster recovery plans and the change control processes they use when updating IT systems.

3. Asset Management

Capital investment

Agencies report delays delivering against the significant increase in their budgets for capital projects.

Capital projects

Agencies are underspending their capital budgets and some can improve capital project governance.

Asset disposals

Eleven per cent of agencies were required to sell their real property through Property NSW but didn’t. And eight per cent of agencies can improve their asset disposal processes.

4. Governance

Governance arrangements

Sixty-four per cent of agencies’ disclosure policies support communication of key performance information and prompt public reporting of significant issues.

Shared services

Fifty-nine per cent of agencies use shared services, yet 14 per cent do not have service level agreements in place and 20 per cent can strengthen the performance standards they set.

5. Ethics and Conduct

Ethical framework

Agencies can reinforce their ethical frameworks by updating code‑of‑conduct policies and publishing a Statement of Business Ethics.

Conflicts of interest

All agencies we reviewed have a code of conduct, but they can still improve the way they update and manage their codes to reduce the risk of fraud and unethical behaviour.

6. Risk Management 

Risk management maturity

All agencies have implemented risk management frameworks, but with varying levels of maturity.

Risk management elements

Many agencies can improve risk registers and strengthen their risk culture, particularly in the way that they report risks to their lead agency.

This report covers the findings and recommendations from our 2016–17 financial audits related to the internal controls and governance of the 39 largest agencies (refer to Appendix three) in the NSW public sector. These agencies represent about 95 per cent of total expenditure for all NSW agencies and were considered to be a large enough group to identify common issues and insights.

The findings in this report should not be used to draw conclusions on the effectiveness of individual agency control environments and governance arrangements. Specific financial reporting, controls and service delivery comments are included in the individual 2017 cluster financial audit reports tabled in Parliament from October to December 2017.

This new report offers strategic insight on the public sector as a whole

In previous years, we have commented on internal control and governance issues in the volumes we published on each ‘cluster’ or agency sector, generally between October and December. To add further value, we then commented more broadly about the issues identified for the public sector as a whole at the start of the following year.

This year, we have created this report dedicated to internal controls and governance. This will help Parliament to understand broad issues affecting the public sector, and help agencies to compare their own performance against that of their peers.

Without strong control measures and governance systems, agencies face increased risks in their financial management and service delivery. If they do not, for example, properly authorise payments or manage conflicts of interest, they are at greater risk of fraud. If they do not have strong information technology (IT) systems, sensitive and trusted information may be at risk of unauthorised access and misuse.

These problems can in turn reduce the efficiency of agency operations, increase their costs and reduce the quality of the services they deliver.

Our audits do not review every control or governance measure every year. We select a range of measures, and report on those that present the most significant risks that agencies should mitigate. This report divides these into the following six areas:

  1. Overall trends
  2. Information technology
  3. Asset management
  4. Governance
  5. Ethics and conduct
  6. Risk management.

Internal controls are processes, policies and procedures that help agencies to:

  • operate effectively and efficiently
  • produce reliable financial reports
  • comply with laws and regulations.

This chapter outlines the overall trends for agency controls and governance issues, including the number of findings, level of risk and the most common deficiencies we found across agencies. The rest of this volume then illustrates this year’s controls and governance findings in more detail.

Issues

Recommendations

1.1 New and repeat findings

The number of internal control deficiencies reduced over the past three years, but new higher-risk information technology (IT) control deficiencies were reported in 2016–17.

Deficiencies repeated from previous years still make up a sizeable proportion of all internal control deficiencies.

Recommendation

Agencies should focus on emerging IT risks, but also manage new IT risks, reduce existing IT control deficiencies, and address repeat internal control deficiencies on a more timely basis.

1.2 High risk findings

We found seven high risk internal control deficiencies, which might significantly affect agencies.

Recommendation

Agencies should rectify high risk internal control deficiencies as a priority

1.3 Common findings

The most common internal control deficiencies related to poor or absent IT controls.

We found some common governance deficiencies across multiple agencies.

Recommendation

Agencies should coordinate actions and resources to help rectify common IT control and governance deficiencies.

Information technology (IT) has become increasingly important for government agencies’ financial reporting and to deliver their services efficiently and effectively. Our audits reviewed whether agencies have effective controls in place over their IT systems. We found that IT security remains the source of many control weakness in agencies.

Issues Recommendations

2.1 IT security

User access administration

While 95 per cent of agencies have policies about user access, about two-thirds were compliant with these policies. Agencies can improve how they grant, change and end user access to their systems.

Recommendation

Agencies should strengthen user access administration to prevent inappropriate access to sensitive systems. Agencies should:

  • establish and enforce clear policies and procedures
  • review user access regularly
  • remove user access for terminated staff promptly
  • change user access for transferred staff promptly.

Privileged access

Sixty-eight per cent of agencies do not adequately manage who can access their information systems, and many do not sufficiently monitor or restrict privileged access.

Recommendation

Agencies should tighten privileged user access to protect their information systems and reduce the risks of data misuse and fraud. Agencies should ensure they:

  • only grant privileged access in line with the responsibilities of a position
  • review the level of access regularly
  • limit privileged access to necessary functions and data
  • monitor privileged user account activity on a regular basis.

Password controls

Forty-one per cent of agencies did not meet either their own standards or minimum standards for password controls.

Recommendation

Agencies should review and enforce password controls to strengthen security over sensitive systems. As a minimum, password parameters should include:

  • minimum password lengths and complexity requirements
  • limits on the number of failed log-in attempts
  • password history (such as the number of passwords remembered)
  • maximum and minimum password ages.

2.2 Cyber Security

Cyber security framework

Agencies do not have a common view on what constitutes a cyber attack, which limits understanding the extent of the cyber security threat.

Recommendation

The Department of Finance, Services and Innovation should revisit its existing framework to develop a shared cyber security terminology and strengthen the current reporting requirements for cyber incidents.

Cyber security strategies

While 82 per cent of agencies have dedicated resources to address cyber security, they can strengthen their strategies, expertise and staff awareness.

Recommendations

The Department of Finance, Services and Innovation should:

  • mandate minimum standards and require agencies to regularly assess and report on how well they mitigate cyber security risks against these standards
  • develop a framework that provides for cyber security training.

Agencies should ensure they adequately resource staff dedicated to cyber security.

2.3 Other IT systems

Change control processes

Some agencies need to improve change control processes to avoid unauthorised or inaccurate system changes.

Recommendation

Agencies should consistently perform user acceptance testing before system upgrades and changes. They should also properly approve and document changes to IT systems.

Disaster recovery planning

Agencies can do more to adequately assess critical business systems to enforce effective disaster recovery plans. This includes reviewing and testing their plans on a timely basis.

Recommendation

Agencies should complete business impact analyses to strengthen disaster recovery plans, then regularly test and update their plans.

Agency service delivery relies on developing and renewing infrastructure assets such as schools, hospitals, roads, or public housing. Agencies are currently investing significantly in new assets. Agencies need to manage the scale and volume of current capital projects in order to deliver new infrastructure on time, on budget and realise the intended benefits. We found agencies can improve how they:

  • manage their major capital projects
  • dispose of existing assets.
Issues Recommendations or conclusions

3.1 Capital investment

Capital asset investment ratios

Most agencies report high capital investment ratios, but one-third of agencies’ capital investment ratios are less than one.

Recommendation

Agencies with high capital asset investment ratios should ensure their project management and delivery functions have the capacity to deliver their current and forward work programs.

Volume of capital spending

Most agencies have significant forward spending commitments for capital projects. However, agencies’ actual capital expenditure has been below budget for the last three years.

Conclusion

The significant increase in capital budget underspends warrant investigation, particularly where this has resulted from slower than expected delivery of projects from previous years.

3.2 Capital projects

Major capital projects

Agencies’ major capital projects were underspent by 13 percent against their budgets.

Conclusion

The causes of agency budget underspends warrant investigation to ensure the NSW Government’s infrastructure commitment is delivered on time.

Capital project governance

Agencies do not consistently prepare business cases or use project steering committees to oversee major capital projects.

Conclusion

Agencies that have project management processes that include robust business cases and regular updates to their steering committees (or equivalent) are better able to provide those projects with strategic direction and oversight.

3.3. Asset disposals

Asset disposal procedures

Agencies need to strengthen their asset disposal procedures.

Recommendations

Agencies should have formal processes for disposing of surplus properties.

Agencies should use Property NSW to manage real property sales unless, as in the case for State owned corporations, they have been granted an exemption.

Governance refers to the high-level frameworks, processes and behaviours that help an organisation to achieve its objectives, comply with legal and other requirements, and meet a high standard of probity, accountability and transparency.

This chapter sets out the governance lighthouse model the Audit Office developed to help agencies reach best practice. It then focuses on two key areas: continuous disclosure and shared services arrangements. The following two chapters look at findings related to ethics and risk management.

Issues Recommendations or conclusions

4.1 Governance arrangements

Continuous disclosure

Continuous disclosure promotes improved performance and public trust and aides better decision-making. Continuous disclosure is only mandatory for NSW Government Businesses such as State owned corporations.

Conclusion

Some agencies promote transparency and accountability by publishing on their websites a continuous disclosure policy that provides for, and encourages:

  • regular public disclosure of key performance information
  • disclosure of both positive and negative information
  • prompt reporting of significant issues.

4.2 Shared services

Service level agreements

Some agencies do not have service level agreements for their shared service arrangements.

Many of the agreements that do exist do not adequately specify controls, performance or reporting requirements. This reduces the effectiveness of shared services arrangements.

Conclusion

Agencies are better able to manage the quality and timeliness of shared service arrangements where they have a service level agreement in place. Ideally, the terms of service should be agreed before services are transferred to the service provider and:

  • specify the controls a provider must maintain
  • specify key performance targets
  • include penalties for non-compliance.

Shared service performance

Some agencies do not set performance standards for their shared service providers or regularly review performance results.

Conclusion

Agencies can achieve better results from shared service arrangements when they regularly monitor the performance of shared service providers using key measures for the benefits realised, costs saved and quality of services received.

Before agencies extend or renegotiate a contract, they should comprehensively assess the services received and test the market to maximise value for money.

All government sector employees must demonstrate the highest levels of ethical conduct, in line with standards set by The Code of Ethics and Conduct for NSW government sector employees.

This chapter looks at how well agencies are managing these requirements, and where they can improve their policies and processes.

We found that agencies mostly have the appropriate codes, frameworks and policies in place. But we have highlighted opportunities to improve the way they manage those systems to reduce the risks of unethical conduct.

Issues Recommendations or conclusions

5.1 Ethical framework

Code of conduct

All agencies we reviewed have a code of conduct, but they can still improve the way they update and manage their codes to reduce the risk of fraud and unethical behaviour.

Recommendation

Agencies should regularly review their code-of-conduct policies and ensure they keep their codes of conduct up-to-date.

Statement of business ethics

Most agencies maintain an ethical framework, but some can enhance their related processes, particularly when dealing with external clients, customers, suppliers and contractors.

Conclusion

Agencies can enhance their ethical frameworks by publishing a Statement of Business Ethics, which communicates their values and culture.

5.2 Potential conflicts of interest

Conflicts of interest

All agencies have a conflicts-of-interest policy, but most can improve how they identify, manage and avoid conflicts of interest.

Recommendation

Agencies should improve the way they manage conflicts of interest, particularly by:

  • requiring senior executives to make a conflict-of-interest declaration at least annually
  • implementing processes to identify and address outstanding declarations
  • providing annual training to staff
  • maintaining current registers of conflicts of interest.

Gifts and benefits

While all agencies already have a formal gifts-and-benefits policy, we found gaps in the management of gifts and benefits by some that increase the risk of unethical conduct.

Recommendation

Agencies should improve the way they manage gifts and benefits by promptly updating registers and providing annual training to staff.

Risk management is an integral part of effective corporate governance. It helps agencies to identify, assess and prioritise the risks they face and in turn minimise, monitor and control the impact of unforeseen events. It also means agencies can respond to opportunities that may emerge and improve their services and activities.

This year we looked at the overall maturity of the risk management frameworks that agencies use, along with two important risk management elements: risk culture and risk registers.

Issues Recommendations or conclusions

6.1 Risk management maturity

All agencies have implemented risk management frameworks, but with varying levels of maturity in their application.

Agencies’ averaged a score of 3.1 out of five across five critical assessment criteria for risk management. While strategy and governance fared best, the areas that most need to improve are risk culture, and systems and intelligence.

Conclusion

Agencies have introduced risk management frameworks and practices as required by the Treasury’s:

  • 'Risk Management Toolkit for the NSW Public Sector'
  • 'Internal Audit and Risk Management Policy for the NSW Public Sector'.

However, more can be done to progress risk management maturity and embed risk management in agency culture.

6.2 Risk management elements

Risk culture

Most agencies have started to embed risk management into the culture of their organisation. But only some have successfully done so, and most agencies can improve their risk culture.

 

 

Conclusion

Agencies can improve their risk culture by:

  • setting an appropriate tone from the top
  • training all staff in effective risk management
  • ensuring desired risk behaviours and culture are supported, monitored, and reinforced through business plans, or the equivalent and employees' performance assessments.

Risk registers and reporting

Some agencies do not report their significant risks to their lead agency, which may impair the way resources are allocated in their cluster. Some agencies do not integrate risk registers at a divisional and whole-of-enterprise level.

Conclusion

Agencies not reporting significant risks at the cluster level increases the likelihood that significant risks are not being mitigated appropriately.

Effective risk management can improve agency decision-making, protect reputations and lead to significant efficiencies and cost savings. By embedding risk management directly into their operations, agencies can also derive extra value for their activities and services.

Published

Actions for Planning and Environment 2017

Planning and Environment 2017

Planning
Environment
Asset valuation
Information technology
Internal controls and governance
Management and administration
Project management

The following report highlights results of financial audits of agencies in the Planning and Environment cluster. The report focuses on key observations and findings from the most recent audits of these agencies.

The audits were completed for most agencies in the cluster and unqualified audit opinions issued. Issues identified during the financial statement audits of seven small agencies delayed their finalisation beyond the statutory deadline, and six of these remain incomplete. Apart from these small agencies, the quality of financial reporting across the cluster remained at a high standard.

1. Financial reporting and controls

Financial reporting Unqualified audit opinions were issued for 39 of the 45 cluster agencies. Issues identified during the financial statement audits of seven small agencies delayed their finalisation beyond the statutory deadline. Six of these audits remain incomplete at the date of this report.
  Agencies completed early close procedures mandated by the Treasury. We noted opportunities for agencies to improve the effectiveness of these procedures.
Internal Controls One in six internal control weaknesses identified during the financial audits were repeat issues. Agencies should action audit recommendations promptly.
  User administration over financial systems needs to be strengthened to prevent inappropriate access to financial information.

2. Service Delivery

 
Housing completions Australian Bureau of Statistics data indicates the Department of Planning and Environment achieved the Premier's priority for housing completions in 2016–17. 
Increasing housing supply Australian Bureau of Statistics data shows the Department of Planning and Environment achieved the annual target of delivering over 50,000 housing approvals over the past three years.
Major project assessment Progress against the State priority target to reduce time taken to assess planning applications for State significant developments is difficult to determine as the measure is unclear.
Litter management The Environment Protection Authority's data indicates that progress towards the Premier's priority target for litter reduction slowed in 2016–17.
Cultural participation The Department of Planning and Environment’s data indicates overall attendance at cultural venues and events in New South Wales increased by 16 per cent in 2015–16.

This report provides Parliament and others with the audit results, observations and recommendations for Planning and Environment cluster agencies. The report has been structured into two chapters focussing on financial reporting and controls and service delivery.

The Planning and Environment cluster plays a role in ensuring each community across New South Wales receives the services and infrastructure it needs.

This chapter outlines our audit observations and recommendations related to financial reporting and controls of Planning and Environment cluster agencies for 2016–17.

Observation Conclusion or recommendation

2.1 Quality of financial reporting

Unqualified audit opinions were issued for 39 of the 45 cluster agencies' financial statements.

Issues identified during the financial statement audits of seven smaller agencies delayed their completion. Six audits remain incomplete at the date of this report.

Apart from these seven small agency audits, the quality of financial reporting across the cluster remained at a high standard.

2.2 Timeliness of financial reporting

Seven agencies' financial statement audits were not completed by the statutory deadline with six audits incomplete at the date of this report.

Issues identified during the financial statement audits of seven smaller agencies delayed their finalisation beyond the statutory deadline. These agencies would benefit from performing additional early close procedures in future reporting periods.

2.3 Financial and sustainability analysis

Water and Electricity utility agencies continue to operate with low liquidity ratios.

A liquidity ratio below one is an indicator that an entity may not be able to pay its debts as and when they fall due.

Whilst liquidity ratios were below one, utility agencies demonstrated they can continue to support ongoing operations due to:

  • access to regulated revenue streams

  • assets with long useful lives to generate revenue

  • debt funding limits approved by the NSW Treasurer under the Public Authorities (Financial Arrangements) Act 1987.

2.5 Internal controls

One in six internal control weaknesses reported in 2016–17 were repeat issues.

Delays in implementing audit recommendations can prolong the risk of fraud and error.

Recommendation (repeat issue): anagement letter recommendations to address internal control weaknesses should be actioned promptly, with a focus on addressing repeat issues.

Nine of these internal control weaknesses related to the creation, modification, deletion and review of user access to financial systems.

These control weaknesses may compromise the integrity and security of financial data.

Recommendation (repeat issue): Management of user administration over financial systems should be strengthened to prevent inappropriate access to financial information.

This chapter outlines our audit observations, conclusions and recommendations relating to service delivery for 2016–17.

Observation Conclusion or recommendation

3.1 Premier's and State priorities

The Planning and Environment cluster is responsible for delivering five Premier's and State priorities.

One priority target was achieved in 2016–17, two targets are on track to be achieved and progress towards one target slowed.

Progress against one target cannot be determined.

3.2 Planning

Housing Completion

 
There were 63,506 housing completions in
2016–17. This was 4.1 per cent above the Premier’s priority target of delivering 61,000 housing completions per year.
The Australian Bureau of Statistics data shows the housing completions target was achieved in
2016–17.

Housing supply

The number of approvals for new houses in
2016–17 was 72,472 against the State priority target of more than 50,000 approvals per year.
The Australian Bureau of Statistics data indicates the housing approvals target was achieved in
2016–17.

Major project assessment

 
State significant developments are not clearly defined for the purposes of reporting against the State priority target. The Department of Planning and Environment will clarify with the Department of Premier and Cabinet which developments are captured by the State priority target.
The Department of Planning and Environment’s data shows the time taken to assess complex State significant developments increased by 16 per cent in 2016–17 while the time taken to assess less complex developments reduced by 20 per cent. The Department of Planning and Environment considers it is on track to meet the State priority target of halving the time taken to assess State significant developments, despite uncertainty over the target measure.

Housing acceleration fund

 

Program business cases were not developed for projects in Housing Acceleration Fund Rounds 1 to 4.

The Department advised a program business case will be developed for Housing Acceleration Fund Round 5 projects.

A program business case is necessary to ensure related projects are evaluated, managed and coordinated effectively.
 

A benefit realisation review process has not yet been approved for Housing Acceleration Fund projects.

The Department of Planning and Environment advised it is developing a benefit realisation review process.

A benefit realisation review process is necessary to determine whether funded projects achieved intended outcomes.

Greater Sydney Commission

 
The Greater Sydney Commission forecasts a further 725,000 dwellings in the greater Sydney region will be required up to 2036 to meet housing demand. In response to population growth, the Commission has set a five-year housing supply target of 189,100 houses across the five Greater Sydney Commission districts.

ePlanning system

 
The Department of Planning and Environment did not perform a benefit realisation review for phase one of the ePlanning project. It has committed to performing a benefit realisation review after completion of phase two in 2018. It cannot be determined if phase one of the project delivered expected outcomes as a benefit realisation review was not performed.

3.3. Environment and Heritage

Litter volume in New South Wales was 6.6 litres per 1,000 square metres in 2016–17, an increase of 16 per cent from the prior year. This is above the Premier's priority litter volume target of 4.2 litres per 1,000 square metres by 2020. The Environment Protection Authority's data indicates the progress towards the target of reducing the volume of litter by 40 per cent by 2020 has slowed.
The NSW Government plans to invest $240 million to facilitate strategic biodiversity conservation on private land. Performance measures have not yet been developed for the private land conservation program.

3.4 Water

IPART reduced water usage charges for most Sydney Water Corporation customers in 2016–17. Water usage prices in New South Wales compare favourably to larger water utilities in other jurisdictions.

Hunter Water Corporation's water recycling and water conservation performance has been stable over recent years.

The volume of Sydney Water Corporation’s recycled water reduced by 12 per cent in 2016–17 compared to the previous year.

Sydney Water Corporation experienced reduced industry demand for recycled water. Several large industrial customers relocated away from Sydney.

3.5 Arts and culture

A State priority target is to increase overall attendance at cultural venues and events in New South Wales by 15 per cent from 2014–15 levels by 2019. The Department of Planning and Environment's data indicates overall attendance increased by 16 per cent in 2015–16, although attendance fluctuated across individual venues and events. This indicates progress towards achieving the overall target by 2019.

Published

Actions for Report on Education 2017

Report on Education 2017

Education
Financial reporting
Internal controls and governance
Management and administration
Procurement
Project management
Workforce and capability

The Auditor-General, Margaret Crawford released her report on the results of the financial audits of agencies in the Education cluster. The report focuses on key observations and findings from the most recent audits of these agencies.

'I am pleased to report that unqualified audit opinions were issued on the financial statements for all agencies in the Education cluster', the Auditor-General said. 'The quality and timeliness of financial reporting remains strong'.

Published

Actions for Universities 2016 Audits

Universities 2016 Audits

Universities
Asset valuation
Compliance
Cyber security
Financial reporting
Fraud
Information technology
Internal controls and governance
Procurement

No qualified opinions were issued on the universities’ financial statements and the quality and timeliness of financial reporting continued to improve. The report found that all NSW universities recorded a surplus in 2016 with combined revenue growth exceeding expense growth by 1.1 per cent. Universities have diversified revenue sources and are now less reliant on government grants. Combined overseas student income exceeded domestic student income for the first time in 2016.

This report analyses the results of the financial statement audits of the ten NSW universities and their controlled entities for the year ended 31 December 2016. The table below summarises key observations.  

This report focuses on key observations and common issues identified from our financial audits of the ten NSW universities and their controlled entities in 2016. The universities are listed in Appendix Three.

In this report, parliament and other users of universities’ financial statements are provided with an analysis of universities’ results and key observations in the following areas:

  • Financial Performance and Reporting
  • Financial Controls
  • Governance
  • Teaching and Research.

Snapshot of NSW universities

A snapshot of NSW universities for the year ended 31 December 2016 is shown below.

Financial performance and reporting are important elements of good governance. Confidence in public sector decision making and transparency is enhanced when financial reporting is accurate and timely.

This chapter outlines audit findings on financial performance and reporting of NSW universities for 2016. 

Appropriate financial controls help ensure the efficient and effective use of resources and the implementation and administration of university policies. They are essential for quality and timely decision making.

In 2016, our audit teams made the following key observations on the financial controls of NSW universities.

Governance refers to the high-level frameworks, processes and behaviours that ensure universities meet their intended purpose, conform with legislative requirements, and meet expectations of probity, accountability and transparency.

This chapter outlines audit findings on the governance of NSW universities and their controlled entities. 

Teaching and research are core activities of universities. The quality of teaching is a key driver for growth and attracting students. Through research, universities contribute to economic growth, lead innovation and improve their global rankings.  

This chapter reports on teaching and research in NSW universities for 2016.

Published

Actions for Mining Rehabilitation Security Deposits

Mining Rehabilitation Security Deposits

Planning
Industry
Environment
Infrastructure
Management and administration
Project management

The Department of Planning and Environment requires mining companies to rehabilitate sites according to conditions set in the mining development approval. The Department holds mining rehabilitation security deposits that are meant to cover the full cost of rehabilitation if a mining company defaults on its rehabilitation obligations.

The total value of security deposits held has increased from $500 million in 2005 to around $2.2 billion in 2016, covering around 450 mine sites in New South Wales.

While there have been substantial increases in total deposits held, mine rehabilitation security deposits are still not likely to be sufficient to cover the full costs of each mine's rehabilitation in the event of a default.

This audit was undertaken when the Department of Industry, Skills and Regional Development was responsible for ensuring land disturbed by mining activities is rehabilitated in accordance with the relevant development approval, including the administration of mining rehabilitation security deposits. On 1 April 2017, this responsibility was transferred to the Department of Planning and Environment (the Department).  

This audit assessed whether the Department maintains adequate security deposits to cover the liabilities associated with mine closures, including rehabilitation. Companies authorised by the Department to undertake mining activities must provide a security deposit to cover the full costs of rehabilitation in the event of default by the company. Rehabilitation is the treatment of disturbed land or water to establish a safe, stable, non-polluting and sustainable environment.

Mining companies must provide an estimate of rehabilitation costs for each site. The Department provides a Rehabilitation Cost Calculation tool to assist companies calculate the deposit amount. Companies are also required to ensure that the cost estimate is in accordance with the approved Mining Operations Plan (MOP). The MOP is intended to be a mine rehabilitation and closure plan, and forms the basis for the estimation of the security deposit. The Department reviews the estimates and determines the deposit for each site.  

Security deposits are an option of last resort. The Department has other legislative and regulatory tools which it normally uses to promote compliance with rehabilitation requirements before accessing a security deposit. It can direct action by the mining company, issue fines and even have the Minister revoke a mining lease. To date, the Department has never had to access a security deposit for a state significant development mine site.

Conclusion

The Department holds security deposits for mining rehabilitation consistent with the amounts it has requested from mining companies, and it should be able to claim on a deposit if a mining company defaults on its rehabilitation obligations. The total value of deposits has increased from $500 million in 2005 to around $2.2 billion in 2016, covering around 450 mine sites. The Department’s management of the security deposit process has improved in recent years, and it has well advanced plans for further improvement, including a revised cost calculation tool.

The Department’s policy is that each mine’s security deposit should cover the full costs of rehabilitation for that mine. The security deposits the Department holds are not likely to be sufficient to cover the full costs of each mine’s rehabilitation in the event of a default. The rates and allowances in the current cost calculation tool have not been updated since 2013 and some activities required for effective rehabilitation are not covered, or not covered adequately.

Security deposits also do not include sufficient contingency given the substantial risks and uncertainties associated with mine rehabilitation and closure, particularly in the absence of a detailed closure plan. This risk is exacerbated by the limited independent verification of mining company claims about the size of the outstanding rehabilitation task, which remains the case despite recent improvements to monitoring and review procedures and practices.  

There is also no financial assurance held over the risk of significant unexpected environmental degradation in the long-term after a mine is deemed to be rehabilitated and the security deposit is returned. A security deposit is not an appropriate vehicle for covering this risk.

Security deposits are close to calculated value and should be accessible if needed

The value of securities held by the Department aligns with the latest approved rehabilitation cost estimates. This contrasts with the situation found by investigations in Victoria and Queensland, where deposit amounts held fell below the calculated costs.

The security deposits are usually in the form of a bank guarantee or cash. The Department has obtained legal advice indicating that it should be able to claim on these bank guarantees if the need arises. As the guarantee is between the financial institution and the Department, if a mining company goes into liquidation the Department should still be able to access the funds.  

When the latest estimate of rehabilitation costs is higher than the existing deposit, the Department will request additional security. It has experienced extensive delays in obtaining additional security for some sites, increasing the risk that available funds will be insufficient if needed.

Rehabilitation cost estimates are not yet adequate, but improvements are planned

The Department’s policy is for security deposits to cover the full cost of rehabilitation. No discounts are provided to mining companies for past good behaviour or low likelihood of default, unlike in some other states. Discounting could undermine the policy position.  

Current security deposits are unlikely to cover the full cost of rehabilitation on each mine site. The Department provides a rehabilitation cost calculation tool to help mining companies calculate the cost of rehabilitation and the required deposit amount, but:

  • several activities required to effect closure are not included and others underestimated
  • it does not make provision for industry cost changes over time
  • the rates used in the tool have not been updated since 2013
  • it was not able to provide the basis for the rates and allowances in the tool.

The Department reviews cost estimates provided by mining companies, but its verification of the extent of rehabilitation work on which these estimates are based is limited. It relies instead on section 387C of the Mining Act 1992 which makes it an offence for mining companies to provide false or misleading information. It is not evident how the Department would establish that information provided was false or misleading without more verification work, and six of the 14 cost estimates we reviewed were not signed by the mine manager, making enforcement more difficult.  

The Department has developed a new calculation tool, and recently released it for industry consultation. The new tool should improve rehabilitation estimates. It updates rates and allowances, and includes additional items to better cover required rehabilitation tasks. While a substantial improvement, the new tool could be further improved by providing additional coverage for stakeholder engagement, additional planning approvals, insurance costs, and any additional design, research and verification work required for successful closure.

There is no financial assurance over long-term environmental risks

The Department does not hold any financial assurance to cover the costs associated with mitigating any future environmental degradation once a mine closes and the security deposit is relinquished to the mining company. Security deposits are probably not the appropriate mechanism to cover these long-term risks but the risk of potential post-closure environmental degradation still needs to be costed and covered. A fund to cover the state-wide risk, to which all mines would contribute, is a possible mechanism.

Rehabilitation and closure outcomes are vague, particularly for unplanned closure

Rehabilitation outcomes in the MOPs we reviewed were generally not specific. Any lack of specificity in MOPs translates into uncertainty about rehabilitation work required if a mining company defaults. Part of the problem is that rehabilitation outcomes established in planning approvals are usually not specific and may not address all closure requirements. The Department has recognised there is scope to improve the clarity and specificity of rehabilitation requirements in planning approvals, and has started a review focusing on open-cut mines.

Rehabilitation outcomes are even less specific in the event of an unexpected early closure because they will probably be different from that achievable from a planned closure.  

MOP guidelines do not cover management of some key closure matters, such as the requirements of environment protection licences issued by the Environment Protection Authority and the management of heritage sites during closure.

There were significant variations in quality of MOPs we reviewed and the way closure risks and uncertainties were identified and addressed. The Department plans to improve the quality of rehabilitation programs through enhanced guidance and oversight.

Monitoring is not adequate to effectively gauge rehabilitation progress

The Department was not able to show it has been monitoring operational mine sites effectively to gauge the progress of ongoing site rehabilitation and the management of closure risks. There was no protocol for site inspections and limited evidence of inspections for the sites we reviewed.

The Department receives annual environmental management reports from mining companies, with most describing the areas of disturbance and rehabilitation occurring at each mine site. The Department recently established procedures for reviewing these annual reports, and has developed a risk-based process for prioritising reviews.

Most annual reports we reviewed did not explain environmental changes over time, nor the risks to mine closure and the measures required to mitigate them. For example, analysis of changes to surface water and groundwater quality was limited despite its relevance for assessing future contamination risks.

The Department does not currently have adequate processes in place to effectively verify the reported areas of disturbance and rehabilitation. It is developing geographic information system-based tools to better measure areas of disturbance and rehabilitation, new rehabilitation guidelines, and a procedure for determining whether rehabilitation has been successful. These initiatives should improve the monitoring and reporting of rehabilitation progress at mine sites.

There is no mechanism to prevent a mine being in ‘care and maintenance’ indefinitely

The Department does not have a clear policy on the length of time and circumstances under which a mine can remain in ‘care and maintenance’. Indefinite postponement of rehabilitation and closure is therefore possible. 'Care and maintenance' is the period following temporary cessation of operations when infrastructure remains largely intact and the site continues to be managed. There are a range of valid reasons for a mining company to put a mine in ‘care and maintenance’, but it is also reasonable for the community to expect a limit to how long it has to wait for proper rehabilitation.

Mining operations make a significant contribution to the NSW economy, including over $1.3 billion in royalties each year. Around 400 mine sites throughout NSW provide over 40,000 jobs and are a major source of economic activity for many communities. Despite these benefits, it is important to ensure that mining companies fulfil their obligations to rehabilitate land disturbed as a result of mining activity.

We recommend that the Department should, by January 2018:

1. Improve the quality of rehabilitation and closure plans by:

  • ensuring plans submitted by mining companies include robust mine rehabilitation and closure risk assessments
  • clarifying the level of detail required in plans at each stage of a mine’s operation
  • specifying how requirements set under other legislative instruments (e.g. environment protection licences, heritage assets) should be addressed.

2. Improve assurance that security deposits are sufficient by:

  • ensuring its new cost calculation tool adequately covers all works needed for rehabilitation and closure
  • increasing the contingency for uncertainties associated with mine rehabilitation and closure, at least until the mining company provides a detailed closure plan
  • verifying the cost estimates for a sample of high risk sites annually
  • ensuring that when mining companies are required to provide increased security deposits, they do so with minimal delay.

3. Enhance oversight of mine rehabilitation by:

  • developing a protocol to ensure sufficient and adequate site inspections
  • ensuring mining companies report performance against rehabilitation targets and environmental changes clearly, including an analysis of long-term surface water and groundwater trends in terms of levels, flow and quality
  • improving how it determines the progress and success of mine rehabilitation
  • developing clear policy and procedures for ensuring a mine cannot be put into ‘care and maintenance’ indefinitely.

4. Collaborate with relevant agencies to establish a financial assurance mechanism, such as a sinking fund, to cover the risk of long-term environmental degradation after mines are closed and security deposits returned.

Appendix One - Response from the Department

Appendix Two - About the audit

 

Parliamentary reference - Report number #285 - released 11 May 2017