Refine search Expand filter

Reports

Published

Actions for Health 2019

Health 2019

Health
Asset valuation
Compliance
Financial reporting
Fraud
Information technology
Internal controls and governance
Management and administration
Procurement
Project management

This report focuses on key observations and findings from the most recent financial audits of the Ministry of Health, local health districts, specialty health networks, health corporations and independent health agencies in New South Wales. The report also summarises self-reported performance measures across the network. The number and value of adjustments to financial statements of entities in the Health Cluster decreased from the prior year. And unqua

Published

Actions for Internal Controls and Governance 2019

Internal Controls and Governance 2019

Education
Community Services
Finance
Health
Industry
Justice
Planning
Premier and Cabinet
Transport
Treasury
Whole of Government
Compliance
Cyber security
Fraud
Information technology
Internal controls and governance
Management and administration
Procurement
Project management

This report covers the findings and recommendations from the 2018–19 financial audits that relate to internal controls and governance at 40 of the largest agencies in the NSW public sector. The 40 agencies selected for this report constitute around 84 per cent of total expenditure for all NSW public sector agencies. The report provides insights into the effectiveness of controls and governance processes across the NSW public sector. It ev

Published

Actions for Ensuring contract management capability in government - HealthShare NSW

Ensuring contract management capability in government - HealthShare NSW

Health
Management and administration
Procurement
Project management

This report examined whether HealthShare NSW, a part of NSW Health, has the required contract management capability to effectively manage goods and services contracts valued over $250,000.  The report found that HealthShare has a procurement framework that should support effective contract management, but it is not applying it consistently. In particular, the audit found that HealthShare was not applying key contract management elements to over 80

Published

Actions for Ensuring contract management capability in government - Department of Education

Ensuring contract management capability in government - Department of Education

Education
Compliance
Internal controls and governance
Management and administration
Procurement
Workforce and capability

This report examines whether the Department of Education has the required contract management capability to effectively manage high-value goods and services contracts (over $250,000). In 2017–18, the department managed high-value goods and services contracts worth $3.08 billion, with most of the contracts running over multiple years. NSW government agencies are increasingly delivering se

Published

Actions for Engagement of probity advisers and probity auditors

Engagement of probity advisers and probity auditors

Transport
Education
Health
Compliance
Internal controls and governance
Procurement
Project management
Workforce and capability

Three key agencies are not fully complying with the NSW Procurement Board’s Direction for engaging probity practitioners, according to a report released today by the Acting Auditor-General for New South Wales, Ian Goodwin. They also do not have effective processes to achieve compliance or assure that probity engagements achieved value for money. Probity is defined as the quality of having s

Published

Actions for Volume Eleven 2012 focusing on Health

Volume Eleven 2012 focusing on Health

Health
Compliance
Financial reporting
Fraud
Information technology
Internal controls and governance
Management and administration
Procurement
Project management
Workforce and capability

One in three ambulance crews were delayed for longer than 30 minutes at hospital. Over the year these delays totalled 84,680 hours of lost time, up from 78,224 last year and 58,399 the year before. The longer ambulance crews are at hospitals the less time they are available to respond to the next emergency.

Published

Actions for Volume Eight 2012 focusing on Transport and Ports

Volume Eight 2012 focusing on Transport and Ports

Transport
Industry
Compliance
Financial reporting
Fraud
Information technology
Infrastructure
Management and administration
Procurement
Project management
Regulation
Risk
Workforce and capability

We issued unqualified audit opinions on the transport entities’ 30 June 2012 financial statements. Some of the findings of the report include: government funding to the public transport operators totalled $4.4 billion in 2011-12 ($3.7 billion in 2010-11) passenger services revenue only covered 20 per cent of RailCorp's operating costs Transport for NSW has formalised a protocol to mitigate the risk of potential conflicts of interests

Published

Actions for Volume One 2012 focusing on themes from 2011

Volume One 2012 focusing on themes from 2011

Health
Industry
Premier and Cabinet
Asset valuation
Compliance
Financial reporting
Fraud
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Regulation
Risk
Shared services and collaboration

The following overview of audits from 2011 found agency restructures significantly impacted agency financial reporting processes, agencies are having difficulty establishing and enforcing compliance with their own policies and procedures, agencies experienced problems complying with regulations and providing adequate documentation to support their financial statements, the poor quality of some financial statements with 1,256 misstatements identified

Published

Actions for Managing IT Services Contracts

Managing IT Services Contracts

Finance
Health
Justice
Compliance
Information technology
Internal controls and governance
Procurement
Project management
Risk

Neither agency (NSW Ministry of Health and NSW Police Force) demonstrated that they continued to get value for money over the life of these long term contracts or that they had effectively managed all critical elements of the three contracts we reviewed post award. This is because both agencies treated contract extensions or renewals as simply continuing previous contractual arrangements, rather than as establishing a new contract and financial comm

Published

Actions for Volume Ten 2010 focus on Education and Communities

Volume Ten 2010 focus on Education and Communities

Education
Community Services
Asset valuation
Compliance
Financial reporting
Internal controls and governance
Management and administration
Procurement
Project management
Workforce and capability

The report includes a review on the Building the Education Revolution and outcomes of his financial audits on NSW Government agencies for Education and Communities 2009-10. Whilst the Department of Education appears to have achieved its key objective of rapidly constructing school facilities, costs were higher than business as usual and the preferences of local communities were not always met.