Actions for CBD and South East Light Rail Project

CBD and South East Light Rail Project

Transport
Compliance
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk

Transport for NSW did not effectively plan and procure the CBD and South East Light Rail (CSELR) project to achieve best value for money according to a report released today by NSW Auditor-General, Margaret Crawford.

Transport for NSW is on track to deliver the project, but it will come at a higher cost with lower benefits than in the approved business case.

 

Parliamentary reference - Report number #278 - released 30 November 2016

Published

Actions for Fraud Survey

Fraud Survey

Education
Community Services
Finance
Health
Industry
Justice
Local Government
Planning
Premier and Cabinet
Transport
Treasury
Universities
Whole of Government
Environment
Fraud
Information technology
Internal controls and governance
Procurement
Risk

In a report released today, the NSW Auditor-General, Margaret Crawford provides a snapshot of reported fraud in the NSW public sector and an analysis of NSW Government agencies’ fraud controls based on a survey of 102 agencies.

Published

Actions for Finance, Services and Innovation 2016

Finance, Services and Innovation 2016

Finance
Asset valuation
Financial reporting
Information technology
Internal controls and governance
Project management
Risk

This report analyses the results of the financial statement audits of the Finance, Services and Innovation cluster entities for the year ended 30 June 2016.

Published

Actions for Red tape reduction

Red tape reduction

Premier and Cabinet
Finance
Financial reporting
Internal controls and governance
Management and administration
Project management
Regulation
Shared services and collaboration

Overall, NSW Government initiatives and processes to prevent and reduce red tape were not effective, according to a report released today by the NSW Auditor-General.

In 2015, the Government reported that its red tape reduction initiatives, implemented between 2011 and 2015, had resulted in $896 million in savings. While these initiatives resulted in some savings, the total value of savings is unknown because estimates for some initiatives were based on unverified assumptions, cost transfers or unrealised projections.

 

Parliamentary reference - Report number #272 - released 25 August 2016

Published

Actions for Early childhood education

Early childhood education

Education
Compliance
Information technology
Management and administration
Project management
Regulation
Risk
Service delivery
Workforce and capability

Enrolments in quality early childhood education programs in New South Wales are increasing but are below the national benchmark, according to a report released today by the NSW Auditor-General, Margaret Crawford.

Ninety-five per cent of children should be enrolled in at least 600 hours in the year before school, but according to the latest NSW figures 77 per cent of children were enrolled in quality early childhood education programs. This 2015 figure is below the benchmark, but is a significant improvement on 2013 when 59 per cent were enrolled.

 

Parliamentary reference - Report number #271 - released 26 May 2016

Published

Actions for Areas of focus in 2015

Areas of focus in 2015

Whole of Government
Asset valuation
Compliance
Financial reporting
Information technology
Internal controls and governance
Project management
Risk

This report focuses on key observations from financial and performance audits in 2015. The findings have been broadly classified into four themes, which has informed the focus of financial and performance audits for 2016.

Published

Actions for Realising the benefits of the Service NSW initiative

Realising the benefits of the Service NSW initiative

Whole of Government
Information technology
Internal controls and governance
Management and administration
Project management
Service delivery
Shared services and collaboration

The current benefits realisation approach for Service NSW needs to improve so benefits and savings can be effectively measured, reported and realised, according to a report released today by the NSW Acting Auditor-General, Tony Whitfield.

Customers are finding that Service NSW provides a convenient and practical way to access all government transaction services.

 

Parliamentary reference - Report number #266 - released 17 February 2016

Published

Actions for Volume Nine 2012 focusing on Education and Communities

Volume Nine 2012 focusing on Education and Communities

Education
Community Services
Asset valuation
Financial reporting
Management and administration
Project management
Risk
Workforce and capability

In New South Wales in 2011, around 20 per cent of public school teachers were under 35 and less than 10 per cent were under 30. Nothing has changed during 2012. We need to do more to attract and retain young teachers to a profession that is essential for our children and our future prosperity.

Published

Actions for Volume Eight 2012 focusing on Transport and Ports

Volume Eight 2012 focusing on Transport and Ports

Transport
Industry
Compliance
Financial reporting
Fraud
Information technology
Infrastructure
Management and administration
Procurement
Project management
Regulation
Risk
Workforce and capability

We issued unqualified audit opinions on the transport entities’ 30 June 2012 financial statements.

Some of the findings of the report include:

  • government funding to the public transport operators totalled $4.4 billion in 2011-12 ($3.7 billion in 2010-11)

  • passenger services revenue only covered 20 per cent of RailCorp's operating costs

  • Transport for NSW has formalised a protocol to mitigate the risk of potential conflicts of interests

  • At present, no sustainability framework exists for the transport agencies around environment and sustainability. Transport for NSW should complete its Environment and Sustainability Policy Framework by June 2013 and should publicly report its results annually

  • Transport patronage continued to grow with 510 million journeys on train, bus and ferry services

  • CityRail had two peak hour periods where only 36 per cent and 39 per cent of services were on time

  • On-time running performance for Sydney Ferries was above the NSW 2021 plan target of 98.5 per cent for most routes in 2011-12

  • Customer surveys by transport agencies no longer specifically address crowding on public transport. Transport for NSW should observe and report on crowding on all transport modes

  • Over 2,500 transport staff, or 8.3 per cent of the workforce, have excessive leave balances. All transport entities should do more to reduce excessive annual leave balances to ensure they will comply with new targets set by the Premier.

 

Published

Actions for Managing IT Services Contracts

Managing IT Services Contracts

Finance
Health
Justice
Compliance
Information technology
Internal controls and governance
Procurement
Project management
Risk

Neither agency (NSW Ministry of Health and NSW Police Force) demonstrated that they continued to get value for money over the life of these long term contracts or that they had effectively managed all critical elements of the three contracts we reviewed post award. This is because both agencies treated contract extensions or renewals as simply continuing previous contractual arrangements, rather than as establishing a new contract and financial commitment. Consequently, there was not a robust analysis of the continuing need for the mix and quantity of services being provided or an assessment of value for money in terms of the prices being paid.

 

Parliamentary reference - Report number #220 - released 1 February 2012