Refine search Expand filter

Reports

Published

Actions for Education 2018

Education 2018

Education
Asset valuation
Financial reporting
Information technology
Infrastructure
Service delivery
Shared services and collaboration
Workforce and capability

The Auditor-General for New South Wales, Margaret Crawford, released her report today on the results of the financial audits of agencies in the Education cluster. The report focuses on key observations and findings from the most recent financial audits of these agencies. 'I am pleased to report that unqualified audit opinions were issued on the financial statements of both agencies in the Education cluster', the Auditor-General said. Statements were submitted and audited within statutory deadlines.

This report analyses the results of our audits of financial statements of the Education cluster for the year ended 30 June 2018. The table below summarises our key observations.

This report provides parliament and other users of the Education cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations
  • service delivery.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Education cluster for 2017–18.

Observation Conclusions and recommendations
2.1 Quality of financial reporting
Unqualified audit opinions were issued on the financial statements of both cluster agencies. Sufficient audit evidence was obtained to conclude the financial statements were free of material misstatement.
2.2 Timeliness of financial reporting
Both cluster agencies met the statutory deadlines for completing early close procedures and submitting financial statements. Early close procedures continue to facilitate the timely preparation of cluster agencies’ financial statements and completion of audits, but scope exists to improve outcomes by resolving issues and supplying supporting documentation earlier.
2.3 Key issues from financial audits
Inconsistencies in the Department’s annual leave and long service leave data, identified over the past three audits, remain unresolved. This issue impacts the Department’s liability estimates for annual leave and long service leave, including associated on-costs. It also on-flows to the Crown Entity, which assumes the Department's liability for long service leave. Recommendation: The Department should confirm leave data and review assumptions following deployment of the new HR/Payroll system to better estimate the liability for employee benefits and the amount to be assumed by the Crown Entity.
2.4 Key financial information
Cluster agencies recorded net deficits in 2017–18.

The Department recorded a net deficit of $30.7 million in 2017–18 against a budgeted surplus of $122 million.

The NSW Education Standards Authority recorded a net deficit of $4.1 million against a budgeted deficit of $4.7 million.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from:

  • our financial statement audits of agencies in the Education cluster for 2018
  • the areas of focus identified in the Audit Office work program.

The Audit Office Annual Work Program provides a summary of all audits to be conducted within the proposed time period as well as detailed information on the areas of focus for each of the NSW Government clusters.

Observation Conclusions and recommendations
3.1  Internal controls
Twenty internal control deficiencies were identified during our audits of cluster agencies. We assessed one as a high risk finding.  
Eight internal control weaknesses were repeat issues from previous financial audits that had not been fully addressed by management. Recommendation: Management should prioritise and action recommendations to address internal control weaknesses.
3.2 Information technology
Delivery of the Learning Management and Business Reform (LMBR) program is complete.

The LMBR program has been a major project for the Department since it was established in 2006.

A staged approach was adopted for implementing the Department’s new HR/Payroll system to manage the risks associated with this large-scale roll-out.

3.3 Valuation of the Department’s land and buildings
The Department completed a revaluation of land and building assets during 2017–18.

A market approach was used to revalue the Department’s land, resulting in a revaluation increment of $2.3 billion.

A current replacement cost approach was used to revalue the Department’s school buildings, resulting in an increment of $6.2 billion.

3.4 Maintenance of school facilities
The Department regularly assesses the condition of school buildings and uses Life Cycle Costing to predict maintenance and capital renewal, and to prioritise maintenance activities. The Life Cycle Costing assessment conducted by the Department in 2017–18 rated 70 per cent of school buildings as being in either as new or good condition. No school buildings were rated as being in end-of-life condition.
3.4 School asset delivery
The Department’s School Assets Strategic Plan is designed to ensure that there are sufficient fit-for-purpose places for students up to 2031. The Department created a new division, School Infrastructure NSW, to oversee the planning, supply and maintenance of schools and implement major school infrastructure projects.

This chapter provides service delivery outcomes for the Education cluster for 2017–18. It provides important contextual information about the cluster's operation, but the data on achievement of these outcomes is not audited. The Audit Office does not have a specific mandate to audit performance information.

Published

Actions for Family and Community Services 2018

Family and Community Services 2018

Community Services
Compliance
Financial reporting
Information technology
Management and administration
Project management
Risk
Service delivery
Workforce and capability

The Auditor-General for New South Wales, Margaret Crawford released her report today on the Family and Community Services cluster. The report focuses on key observations and findings from the most recent financial audits of agencies in the cluster. Cluster entities received unqualified audit opinions for their 30 June 2018 financial statements. Opportunities to improve the quality of financial reporting were identified and reported to management.

This report analyses the results of our audits of financial statements of the Family and Community Services cluster for the year ended 30 June 2018. The table below summarises our key observations.

This report provides NSW Parliament and other users of the financial statements of Family and Community Services' agencies with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations
  • service delivery.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Family and Community Services cluster for 2018.

Observation Conclusions and recommendations
2.1 Quality of financial reporting
Unqualified audit opinions were issued for all cluster agencies' financial statements. Conclusion: Sufficient audit evidence was obtained to conclude the financial statements were free of material misstatement.
Agencies complied with NSW Treasury’s mandatory early close requirements.

Completing other early close procedures was inconsistent and not always supported by adequate evidence.
Conclusion: There are opportunities for agencies to improve the quality of financial reporting by:
  • documenting all significant judgements and assumptions used when preparing the financial statements
  • regularly reconciling inter-agency balances and transactions
  • reconciling key account balances on a timely basis
  • quantifying the impact of new and revised accounting standards.
2.2 Timeliness of financial reporting
Agencies completed revaluations of property, plant and equipment and submitted 31 March 2018 financial statements by the due date as required by NSW Treasury.

Agencies submitted year-end financial statements by the statutory deadline.
Conclusion: Early revaluations of property, plant and equipment contributes to agencies meeting the year-end statutory reporting deadline.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from:

  • our financial statement audits of agencies in the Family and Community Services cluster for 2018
  • the areas of focus identified in the Audit Office annual work program.

The Audit Office Annual Work Program provides a summary of all audits to be conducted within the proposed time period as well as detailed information on the areas of focus for each NSW Government cluster.

Observation Conclusions and recommendations
3.1 Internal controls
The 2017–18 audits reported 47 internal control weaknesses. While none were high risk, there were 15 repeat issues.

Conclusion: Management accepted audit findings and advised they are actioning recommendations. Timely action is important to ensure internal controls operate effectively.

Twenty-two of these internal control weaknesses related to information technology processes and control environment. Conclusion: Control weaknesses in information systems may compromise the integrity and security of financial data used for decision making and financial reporting.

Recommendation: Agencies should strengthen user access administration to prevent inappropriate access to key IT systems by:
  • ensuring privileged user access is limited to those requiring access to maintain the IT systems
  • monitoring privileged user access to address risks from unauthorised activity
  • ensuring IT password settings comply with password policies
  • ensuring timely removal of access to business systems for terminated and casual employees.
The Department, NSW Land and Housing Corporation (LAHC) and three other cluster agencies’ contract registers are incomplete and/or inaccurate. Recommendation: Agencies should ensure their contract registers are complete and accurate so they can more effectively govern contracts and manage compliance obligations.
3.2 Audit Office annual work program
Financial impact of the commissioning approach.

The transfer of disability services to the National Disability Insurance Scheme and other commissioning of service delivery has contributed to a 36 per cent decrease in frontline employee numbers since 2015–16. Similarly, corporate services’ employee numbers reduced by 34 per cent.

The Department’s salary costs have reduced by $232 million or 18 per cent from 2016–17.
Conclusion: The ratio of corporate services employee numbers to support frontline and support services has remained at 1:10 since 2015–16, which indicates restructures have been planned to align with the transfer of disability services.
Impact of the new social housing maintenance contract

Maintenance expenses have increased by about 40 per cent since the new maintenance contract commenced in April 2016. LAHC measures the benefits of the new maintenance contract such as improved tenant satisfaction.
Conclusion: The new maintenance contract has contributed to some positive social outcomes such as tenants being employed by the contractors to conduct maintenance, as call centre operators and in administration. However, more can be done to ensure value for money is being achieved.
ChildStory IT Project

Whilst phase one of the ChildStory IT project went 'live' in 2017–18, the planned timetable has not been met and the revised date for full implementation is end of 2018.

According to the 2014–15 NSW Budget, the budget for ChildStory was $100 million over a four-year period. During the design and implementation stage, this amount was revised to $128 million, with approval of the Expenditure Review Committee. The actual cost incurred over the four years until 30 June 2018, is approximately $131 million.

We identified issues with the data migration from the legacy systems to ChildStory.
Conclusion: To inform future IT projects, we understand the Department is capturing our findings, along with the findings from the Department of Finance, Services and Innovation’s ‘Healthchecks’.

This chapter outlines certain service delivery outcomes for 2017–18. The data on activity levels and performance is provided by Cluster agencies. The Audit Office does not have a specific mandate to audit performance information. Accordingly, the information in this chapter is unaudited.

In our recent performance audit, Progress and measurement of Premier's Priorities, we identified 12 limitations of performance measurement and performance data. We recommended that the Department of Premier and Cabinet ensure that processes to check and verify data are in place for all agency data sources.

Published

Actions for Internal Controls and Governance 2018

Internal Controls and Governance 2018

Education
Community Services
Finance
Health
Industry
Justice
Planning
Premier and Cabinet
Transport
Treasury
Whole of Government
Environment
Compliance
Cyber security
Financial reporting
Fraud
Information technology
Internal controls and governance
Management and administration
Procurement
Project management

The Auditor-General for New South Wales Margaret Crawford found that as NSW state government agencies’ digital footprint increases they need to do more to address new and emerging information technology (IT) risks. This is one of the key findings to emerge from the second stand-alone report on internal controls and governance of the 40 largest NSW state government agencies.

This report analyses the internal controls and governance of the 40 largest agencies in the NSW public sector for the year ended 30 June 2018.

This report covers the findings and recommendations from our 2017–18 financial audits that relate to internal controls and governance at the 40 largest agencies (refer to Appendix three) in the NSW public sector.

This report offers insights into internal controls and governance in the NSW public sector

This is our second report dedicated to internal controls and governance at NSW State Government agencies. The report provides insights into the effectiveness of controls and governance processes in the NSW public sector by:

  • highlighting the potential risks posed by weaknesses in controls and governance processes
  • helping agencies benchmark the adequacy of their processes against their peers
  • focusing on new and emerging risks, and the internal controls and governance processes that might address those risks.

Without strong governance systems and internal controls, agencies increase the risks associated with effectively managing their finances and delivering services to citizens. The way agencies deliver services increasingly relies on contracts and partnerships with the private sector. Many of these arrangements deliver front line services, but others provide less visible back office support. For example, an agency may rely on an IT service provider to manage a key system used to provide services to the community. The contract and service level agreements are only truly effective where they are actively managed to reduce risks to continuous quality service delivery, such as interruptions caused by system outages, cyber security attacks and data security breaches.

Our audits do not review all aspects of internal controls and governance every year. We select a range of measures, and report on those that present heightened risks for agencies to mitigate. This report divides these into the following five areas:

  1. Internal control trends
  2. Information technology (IT), including IT vendor management
  3. Transparency and performance reporting
  4. Management of purchasing cards and taxis
  5. Fraud and corruption control.

The findings in this report should not be used to draw conclusions on the effectiveness of individual agency control environments and governance arrangements. Specific financial reporting, controls and service delivery comments are included in the individual 2018 cluster financial audit reports, which will be tabled in Parliament from November to December 2018.

The focus of the report has changed since last year

Last year's report topics included asset management, ethics and conduct, and risk management. We are reporting on new topics this year. We plan to introduce new topics and re-visit our previous topics in subsequent reports on a cyclical basis. This will provide a baseline against which to measure the NSW public sectors’ progress in implementing appropriate internal controls and governance processes to mitigate existing, new and emerging risks in the public sector.

Agencies selected for the volume account for 95 per cent of the state's expenditure

While we have covered only 40 agencies in this report, those selected are a large enough group to identify common issues and insights. They represent about 95 per cent of total expenditure for all NSW public sector agencies.

Internal controls are processes, policies and procedures that help agencies to:

  • operate effectively and efficiently
  • produce reliable financial reports
  • comply with laws and regulations
  • support ethical government.

This chapter outlines the overall trends for agency controls and governance issues, including the number of findings, level of risk and the most common deficiencies we found across agencies. The rest of this volume presents this year’s controls and governance findings in more detail.

Observation Conclusions and recommendations
2.1 High risk findings
We found six high risk findings (seven in 2016–17), one of which was repeated from both last year and 2015–16. Recommendation: Agencies should reduce risk by addressing high risk internal control deficiencies as a priority.
2.2 Common findings
We found several internal controls and governance findings common to multiple agencies. Conclusion: Central agencies or the lead agency in a cluster can play a lead role in helping ensure agency responses to common findings are consistent, timely, efficient and effective.
2.3 New and repeat findings
Although internal control deficiencies decreased over the last four years, this year has seen a 42 per cent increase in internal control deficiencies. The increase in new IT control deficiencies and repeat IT control deficiencies signifies an emerging risk for agencies.
IT control deficiencies feature in this increase, having risen by 63 per cent since last year. The number of repeat IT control deficiencies has doubled and is driven by the increasing digital footprint left by agencies as government prioritises on-line interfaces with citizens, and the number of transactions conducted through digital channels increases

Recommendation: Agencies should reduce IT risks by:

  • assigning ownership of recommendations to address IT control deficiencies, with timeframes and actions plans for implementation
  • ensuring audit and risk committees and agency management regularly monitor the implementation status of recommendations.

 

Government agencies’ financial reporting is now heavily reliant on information technology (IT). IT is also increasingly important to the delivery of agency services. These systems often provide the data to help monitor the efficiency and effectiveness of agency processes and services they deliver. Our audits reviewed whether agencies have effective controls in place to manage both key financial systems and IT service contracts.

Observation Conclusions and recommendations
3.1 Management of IT vendors
Contract management framework 
Although 87 per cent of agencies have a contract management policy to manage IT vendors, one fifth require review.
 

Conclusion: Agencies can more effectively manage IT vendor contracts by developing policies and procedures to ensure vendor management frameworks are kept up to date, plans are in place to manage vendor performance and risk, and compliance with the framework is monitored by:

  • internal audit focusing on key contracting activities
  • experienced officers who are independent of contract administration performing spot checks or peer reviews
  • targeted analysis of data in contract registers.
Contract risk management
Forty-one per cent of agencies are not using contract management plans and do not assess contract risks. Half of the agencies that did assess contract risks, had not updated the risk assessments since the commencement of the contract.
 
Conclusion: Instead of applying a 'set and forget' approach in relation to management of contract risks, agencies should assess risk regularly and develop a plan to actively manage identified risks throughout the contract lifecycle - from negotiation and commencement, to termination.

Performance management
Eighty-six per cent of agencies meet with vendors to discuss performance. 

Only 24 per cent of agencies sought assurance about the accuracy of vendor reporting against KPIs, yet sixty-seven per cent of the IT contracts allow agencies to determine performance based payments and/or penalise underperformance.

Conclusion: Agencies are monitoring IT vendor performance, but could improve outcomes and more effectively manage under-performance by:

  • a more active, rigorous approach to both risk and performance management
  • checking the accuracy of vendor reporting against those KPIs and where appropriate seeking assurance over their accuracy
  • invoking performance based payments clauses in contracts when performance falls below agreed standards.

Transitioning services
Forty-three per cent of the IT vendor contracts did not contain transitioning-out provisions.

Where IT vendor contracts do make provision for transitioning-out, only 28 per cent of agencies have developed a transitioning-out plan with their IT vendor.

Conclusion: Contract transition/phase out clauses and plans can mitigate risks to service disruption, ensure internal controls remain in place, avoid unnecessary costs and reduce the risk of 'vendor lock-in'.
Contract Registers
Eleven out of forty agencies did not have a contract register, or have registers that are not accurate and/or complete.

Conclusion: A contract register helps to manage an agency’s compliance obligations under the Government Information (Public Access) Act 2009 (the GIPA Act). However, it also helps agencies more effectively manage IT vendors by:

  • monitoring contract end dates and contract extensions, and commence new procurements through their central procurement teams in a timely manner
  • managing their contractual commitments, budgeting and cash flow requirements.

Recommendation: Agencies should ensure their contract registers are complete and accurate so they can more effectively govern contracts and manage compliance obligations.

3.2 IT general controls
Governance
Ninety-five per cent of agencies have established policies to manage key IT processes and functions within the agency, with ten per cent of those due for review.
 
Conclusion: Regular review of IT policies ensures risks are considered and appropriate strategies and procedures are implemented to manage these risks on a consistent basis. An absence of policies can lead to ad-hoc responses to risks, and failure to consider emerging IT risks and changes to agency IT environments. 

User access administration
Seventy-two deficiencies were identified related to user access administration, including:

  • thirty issues related to granting user access across 43 per cent of agencies
  • sixteen issues related to removing user access across 30 per cent of agencies
  • twenty-six issues related to periodic reviews of user access across 50 per cent of agencies.
Recommendation: Agencies should strengthen the administration of user access to prevent inappropriate access to key systems.
Privileged access
Forty per cent of agencies do not periodically review logs of the activities of privileged users to identify suspicious or unauthorised activities.

Recommendation: Agencies should:

  • review the number of, and access granted to privileged users, and assess and document the risks associated with their activities
  • monitor user access to address risks from unauthorised activity.
Password controls
Twenty-three per cent of agencies did not comply with their own policy on password parameters.
Recommendation: Agencies should ensure IT password settings comply with their password policies.
Program changes
Fifteen per cent of agencies had deficient IT program change controls mainly related to segregation of duties and authorisation and testing of IT program changes prior to deployment.
Recommendation: Agencies should maintain appropriate segregation of duties in their IT functions and test system changes before they are deployed.

 

This chapter outlines our audit observations, conclusions and recommendations from our review of how agencies reported their performance in their 2016–17 annual reports. The Annual Reports (Statutory Bodies) Regulation 2015 and Annual Reports (Departments) Regulation 2015 (annual reports regulation) currently prescribes the minimum requirements for agency annual reports.

Observation Conclusion or recommendation
4.1 Reporting on performance

Only 57 per cent of agencies linked reporting on performance to their strategic objectives.

The use of targets and reporting performance over time was limited and applied inconsistently.

Conclusion: There is significant disparity in the quality and consistency of how agencies report on their performance in their annual reports. This limits the reliability and transparency of reported performance information.

Agencies could improve performance reporting by clearly linking strategic objectives to reported outcomes, and reporting on performance against targets over time. NSW Treasury may need to provide more guidance to agencies to support consistent and high-quality performance reporting in annual reports.

There is no independent assurance that the performance metrics agencies report in their annual reports are accurate.

Prior performance audits have noted issues related to the collection of performance information. For example, our 2016 Report on Red Tape Reduction highlighted inaccuracies in how the dollar-value of red tape reduction had been reported.

Conclusion: The ability of Parliament and the public to rely on reported information as a relevant and accurate reflection of an agency's performance is limited.

The relevance and accuracy of performance information is enhanced when:

  • policies and guidance support the consistent and accurate collection of data
  • internal review processes and management oversight are effective
  • independent review processes are established to provide effective challenge to the assumptions, judgements and methodology used to collect the reported performance information.
4.2 Reporting on reports

Agency reporting on major projects does not meet the requirements of the annual reports regulation.

Forty-seven per cent of agencies did not report on costs to date and estimated completion dates for major works in progress. Of the 47 per cent of agencies that reported on major works, only one agency reported detail about significant cost overruns, delays, amendments, deferments or cancellations.

NSW Treasury produce an annual report checklist to help agencies comply with their annual report obligations.

Recommendation: Agencies should comply with the annual reports regulation and report on all mandatory fields, including significant cost overruns and delays, for their major works in progress.

The information the annual reports regulation requires agencies to report deals only with major works in progress. There is no requirement to report on completed works.

Sixteen of 30 agencies reported some information on completed major works.

Conclusion: Agencies could improve their transparency if they reported, or were required to report:

  • on both works in progress and projects completed during the year
  • actual costs and completion dates, and forecast completion dates for major works, against original and revised budgets and original expected completion dates
  • explanations for significant cost overruns, delays and key project performance metrics.

 

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency preventative and detective controls over purchasing card and taxi use for 2017–18.

Observation Conclusion or recommendation
5.1 Management of purchasing cards
Volume of credit card spend
Purchasing card expenditure has increased by 76 per cent over the last four years in response to a government review into the cost savings possible from using purchasing cards for low value, high volume procurement.
 
Conclusion: The increasing use of purchasing cards highlights the importance of an effective framework for the use and management of purchasing cards.
Policy framework
We found all agencies that held purchasing cards had a policy in place, but 26 per cent of agencies have not reviewed their purchasing card policy by the scheduled date, or do not have a scheduled revision date stated within their policy.
Recommendation: Agencies should mitigate the risks associated with increased purchasing card use by ensuring policies and purchasing card frameworks remain current and compliant with the core requirements of TPP 17–09 'Use and Management of NSW Government Purchasing Cards'.
Preventative controls
We found that:
  • all agencies maintained purchasing card registers
  • seventy-six per cent provided training to cardholders prior to being issued with a card
  • eighty-nine per cent appointed a program administrator, but only half of these had clearly defined roles and responsibilities
  • thirty-two per cent of agencies place merchant blocks on purchasing cards
  • forty-seven per cent of agencies place geographic restrictions on purchasing cards.

Agencies have designed and implemented preventative controls aimed at deterring the potential misuse of purchasing cards.

Conclusion: Further opportunities exist for agencies to better control the use of purchasing cards, such as:

  • updating purchasing card registers to contain all mandatory fields required by TPP17–09
  • appointing a program administrator for the agency's purchasing card framework and defining their role and responsibility for the function
  • strengthening preventive controls to prevent misuse.

Detective controls
Ninety-two per cent of agencies have designed and implemented at least one control to monitor purchasing card activity.

Major reviews, such as data analytics (29 per cent of agencies) and independent spot checks (49 per cent of agencies) are not widely used.

Agencies have designed and implemented detective controls aimed at identifying potential misuse of purchasing cards.

Conclusion: More effective monitoring using purchasing card data can provide better visibility over spending activity and can be used to:

  • detect misuse and investigate exceptions
  • analyse trends to highlight cost saving opportunities.
5.2 Management of taxis
Policy framework
Thirteen per cent of agencies have not developed and implemented a policy to manage taxi use. In addition:
  • a further 41 per cent of agencies have not reviewed their policies by the scheduled revision date, or do not have a scheduled revision date
  • more than half of all agencies’ policies do not offer alternative travel options. For example, only 36 per cent of policies promoted the use of general Opal cards.
Conclusion: Agencies can promote savings and provide more options to staff where their taxi use policies:
  • limit the circumstances where taxi use is appropriate
  • offer alternate, lower cost options to using taxis, such as general Opal cards and rideshare.
Detective controls
All agencies approve taxi expenditure by expense reimbursement, purchasing card and Cabcharge, and have implemented controls around this approval process. However, beyond this there is minimal monitoring and review activity, such as data monitoring, independent spot checks or internal audit reviews.
Conclusion: Taxi spend at agencies is not significant in terms of its dollar value, but it is significant from a probity perspective. Agencies can better address the probity risk by incorporating taxi use into a broader purchasing card or fraud monitoring program.

 

Fraud and corruption control is one of the 17 key elements of our governance lighthouse. Recent reports from ICAC into state agencies and local government councils highlight the need for effective fraud control and ethical frameworks. Effective frameworks can help protect an agency from events that risk serious reputational damage and financial loss.

Our 2016 Fraud Survey found the NSW Government agencies we surveyed reported 1,077 frauds over the three year period to 30 June 2015. For those frauds where an estimate of losses was made, the reported value exceeded $10.0 million. The report also highlighted that the full extent of fraud in the NSW public sector could be higher than reported because:

  • unreported frauds in organisations can be almost three times the number of reported frauds
  • our 2015 survey did not include all NSW public sector agencies, nor did it include any NSW universities or local councils
  • fraud committed by citizens such as fare evasion and fraudulent state tax self-assessments was not within the scope of our 2015 survey
  • agencies did not estimate a value for 599 of the 1,077 (56 per cent) reported frauds.

Commissioning and outsourcing of services to the private sector and the advancement of digital technology are changing the fraud and corruption risks agencies face. Fraud risk assessments should be updated regularly and in particular where there are changes in agency business models. NSW Treasury Circular TC18-02 NSW Fraud and Corruption Control Policy now requires agencies develop, implement and maintain a fraud and corruption control framework, effective from 1 July 2018. 

Our Fraud Control Improvement Kit provides guidance and practical advice to help organisations implement an effective fraud control framework. The kit is divided into ten attributes. Three key attributes have been assessed below; prevention, detection and notification systems.

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency fraud and corruption controls for 2017–18.

Observation Conclusion or recommendation
6.1 Prevention systems

Prevention systems
Ninety-two per cent of agencies have a fraud control plan in place, 81 per cent maintain a fraud database and 79 per cent report fraud and corruption matters as a standing item on audit and risk committee agendas.

Only 54 per cent of agencies have an employment screening policy and all agencies have IT security policies, but gaps in IT security controls could undermine their policies.

Conclusion: Most agencies have implemented fraud prevention systems to reduce the risk of fraud. However poor IT security along with other gaps in agency prevention systems, such as employment screening practices heightens the risk of fraud and inappropriate use of data.

Agencies can improve their fraud prevention systems by:

  • completing regular fraud risk assessments, embedding fraud risk assessment into their enterprise risk management process and reporting the results of the assessment to the audit and risk committee
  • maintaining a fraud database and reviewing it regularly for systemic issues and reporting a redacted version of the database on the agency's website to inform corruption prevention networks
  • developing policies and procedures for employee screening and benchmarking their current processes against ICAC's publication ‘Strengthening Employment Screening Practices in the NSW Public Sector’
  • developing and maintaining up to date IT security policies and monitoring compliance with the policy.
Twenty-three per cent of agencies were not performing fraud risk assessments and some agency fraud risk assessments may not be as robust as they could be.  Conclusion: Agencies' systems of internal controls may be less effective where new and emerging fraud risks have been overlooked, or known weaknesses have not been rectified.
6.2 Detection systems
Detection systems
Several agencies reported they were developing a data monitoring program, but only 38 per cent of agencies had already implemented a program.
 

Studies have shown data monitoring, whereby entire populations of transactional data are analysed for indicators of fraudulent activity, is one of the most effective methods of early detection. Early detection decreases the duration a fraud remains undetected thereby limiting the extent of losses.

Conclusion: Data monitoring is an effective tool for early detection of fraud and is more effective when informed by a comprehensive fraud risk assessment.

6.3 Notification systems
Notification system
All agencies have notification systems for reporting actual or suspected fraud and corruption. Most agencies provide multiple reporting lines, provide training and publicise options for staff to report actual or suspected fraud and corruption.
Conclusion: Training staff about their obligations and the use of fraud notification systems promotes a fraud-aware culture

 

Published

Actions for Procurement and reporting of consultancy services

Procurement and reporting of consultancy services

Finance
Education
Community Services
Industry
Justice
Planning
Premier and Cabinet
Health
Treasury
Transport
Environment
Information technology

Agencies need to improve their compliance with requirements governing the procurement of consultancy services. These requirements help agencies access procurement savings. Also, some agencies have under-reported consultancy fees in their annual reports for the 2016-17 financial year, according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. The report examined twelve agencies' compliance with procurement and reporting obligations for consultancy services. It notes that it is difficult to quantify total government expenditure on consultants as agencies define ‘consultants’ differently.

NSW Government agencies engage consultants to provide professional advice to inform their decision‑making. The spend on consultants is measured and reported in different ways for different purposes and the absence of a consistently applied definition makes quantification difficult.

The NSW Government’s procurement principles aim to help agencies obtain value for money and be fair, ethical and transparent in their procurement activities. All NSW Government agencies, with the exception of State Owned Corporations, must comply with the NSW Procurement Board’s Direction when engaging suppliers of business advisory services. Business advisory services include consultancy services. NSW Government agencies must disclose certain information about their use of consultants in their annual reports. The table below illustrates the detailed procurement and reporting requirements.

  Relevant guidance Requirements
Procurement of consultancy services PBD 2015 04 Engagement of major suppliers of consultancy and other services (the Direction) including the Standard Commercial Framework
(revised on 31 January 2018, shortly before it was superseded by 'PBD 2018 01')
 
Required agencies to seek the Agency Head or Chief Financial Officer's approval for engagements over $50,000 and report the engagements in the Major Suppliers' Portal (the Portal). 
  PBD 2018 01 Engagement of professional services suppliers
(replaced 'PBD 2015 04' in May 2018)
Requires agencies to seek the Agency Head or Chief Financial Officer's approval for engagements that depart from the Standard Commercial Framework and report the engagements in the Portal. Exhibit 3 in the report includes the key requirements of these three Directions.
 
Reporting of consultancy expenditure Annual Reports (Departments) Regulation 2015 and Annual Reports (Statutory Bodies) Regulation 2015 Requires agencies to disclose, in their annual reports, details of consultants engaged in a reporting year.
  Premier's Memorandum 
'M2002 07 Engagement and Use of Consultants'
 
Outlines additional reporting requirements for agencies to describe the nature and purpose of consultancies in their annual reports.

We examined how 12 agencies complied with their procurement and reporting obligations for consultancy services between 1 July 2016 and 31 March 2018. Participating agencies are listed in Appendix two. We also examined how NSW Procurement supports the functions of the NSW Procurement Board within the Department of Finance, Services and Innovation.

This audit assessed:

  • agency compliance with relevant procurement requirements for their use of consultants
  • agency compliance with disclosure requirements about consultancy expenditure in their annual reports 
  • the effectiveness of the NSW Procurement Board (the Board) in fulfilling its functions to oversee and support agency procurement of consultancy services. 
Conclusion
No participating agency materially complied with procurement requirements when engaging consultancy services. Eight participating agencies under reported consultant fees in their annual reports. The NSW Procurement Board is not fully effective in overseeing and supporting agencies' procurement of consultancy services.
All 12 agencies that we examined did not materially comply with the NSW Procurement Board Direction for the use of consultants between 1 July 2016 and 31 March 2018. 
Eight agencies did not comply with annual reporting requirements in the 2016–17 financial reporting year. Three agencies did not report expenditure on consultants that had been capitalised as part of asset costs, and one agency did not disclose consultancy fees incurred by its subsidiaries. Agencies also defined ‘consultants’ inconsistently.
The NSW Procurement Board's Direction was revised in January 2018, and mandates the use of the Standard Commercial Framework. The Direction aims to drive value for money, reduce administrative costs and simplify the procurement process. In practice, agencies found the Framework challenging to use. To better achieve the Direction’s intent, the Board needs to simplify procurement and compliance processes. 
The Board is yet to publish any statistics or analysis of agencies’ procurement of business advisory services due to issues with the quality of data and systems limitations. Also, the Board’s oversight of agency and supplier compliance with the Framework is limited as it relies on self reporting, and the information provided is insufficient to properly monitor compliance. NSW Procurement is yet to develop an effective procurement and business intelligence system for use by government agencies. Better procurement support, benefit realisation monitoring and reporting by NSW Procurement will help promote value for money in the engagement of consultants.

Published

Actions for HealthRoster benefits realisation

HealthRoster benefits realisation

Health
Compliance
Information technology
Management and administration
Project management
Workforce and capability

The HealthRoster system is delivering some business benefits but Local Health Districts are yet to use all of its features, according to a report released today by the Auditor-General for New South Wales,  Margaret Crawford. HealthRoster is an IT system designed to more effectively roster staff to meet the needs of Local Health Districts and other NSW health agencies.

The NSW public health system employs over 100,000 people in clinical and non-clinical roles across the state. With increasing demand for services, it is vital that NSW Health effectively rosters staff to ensure high quality and efficient patient care, while maintaining good workplace practices to support staff in demanding roles.

NSW Health is implementing HealthRoster as its single state-wide rostering system to more effectively roster staff according to the demands of each location. Between 2013–14 and 2016–17, our financial audits of individual LHDs had reported issues with rostering and payroll processes and systems.

NSW Health grouped all Local Health Districts (LHDs), and other NSW Health organisations, into four clusters to manage the implementation of HealthRoster over four years. Refer to Exhibit 4 for a list of the NSW Health entities in each cluster.

  • Cluster 1 implementation commenced in 2014–15 and was completed in 2015–16.
  • Cluster 2 implementation commenced in 2015–16 and was completed in 2016–17.
  • Cluster 3 began implementation in 2016–17 and was underway during the conduct of the audit.
  • Cluster 4 began planning for implementation in 2017–18.

Full implementation, including capability for centralised data and reporting, is planned for completion in 2019.

This audit assessed the effectiveness of the HealthRoster system in delivering business benefits. In making this assessment, we examined whether:

  • expected business benefits of HealthRoster were well-defined
  • HealthRoster is achieving business benefits where implemented.

The HealthRoster project has a timespan from 2009 to 2019. We examined the HealthRoster implementation in LHDs, and other NSW Health organisations, focusing on the period from 2014, when eHealth assumed responsibility for project implementation, to early 2018.

Conclusion
The HealthRoster system is realising functional business benefits in the LHDs where it has been implemented. In these LHDs, financial control of payroll expenditure and rostering compliance with employment award conditions has improved. However, these LHDs are not measuring the value of broader benefits such as better management of staff leave and overtime.
NSW Health has addressed the lessons learned from earlier implementations to improve later implementations. Business benefits identified in the business case were well defined and are consistent with business needs identified by NSW Health. Three of four cluster 1 LHDs have been able to reduce the number of issues with rostering and payroll processes. LHDs in earlier implementations need to use HealthRoster more effectively to ensure they are getting all available benefits from it.
HealthRoster is taking six years longer, and costing $37.2 million more, to fully implement than originally planned. NSW Health attributes the increased cost and extended timeframe to the large scale and complexity of the full implementation of HealthRoster.

Business benefits identified for HealthRoster accurately reflect business needs.

NSW Health has a good understanding of the issues in previous rostering systems and has designed HealthRoster to adequately address these issues. Interviews with frontline staff indicate that HealthRoster facilitates rostering which complies with industrial awards. This is a key business benefit that supports the provision of quality patient care. We saw no evidence that any major business needs or issues with the previous rostering systems are not being addressed by HealthRoster.

In the period examined in this audit since 2015, NSW Health has applied appropriate project management and governance structures to ensure that risks and issues are well managed during HealthRoster implementation.

HealthRoster has had two changes to its budget and timeline. Overall, the capital cost for the project has increased from $88.6 million to $125.6 million (42 per cent) and has delayed expected project completion by four years from 2015 to 2019. NSW Health attributes the increased cost and extended time frame to the large scale and complexity of the full implementation of HealthRoster.

NSW Health has established appropriate governance arrangements to ensure that HealthRoster is successfully implemented and that it will achieve business benefits in the long term. During implementation, local steering committees monitor risks and resolve implementation issues. Risks or issues that cannot be resolved locally are escalated to the state-wide steering committee.

NSW Health has grouped local health districts, and other NSW Health organisations, into four clusters for implementation. This has enabled NSW Health to apply lessons learnt from each implementation to improve future implementations.

NSW Health has a benefits realisation framework, but it is not fully applied to HealthRoster.

NSW Health can demonstrate that HealthRoster has delivered some functional business benefits, including rosters that comply with a wide variety of employment awards.

NSW Health is not yet measuring and tracking the value of business benefits achieved. NSW Health did not have benefits realisation plans with baseline measures defined for LHDs in cluster 1 and 2 before implementation. Without baseline measures NSW Health is unable to quantify business benefits achieved. However, analysis of post-implementation reviews and interviews with frontline staff indicate that benefits are being achieved. As a result, NSW Health now includes defining baseline measures and setting targets as part of LHD implementation planning. It has created a benefits realisation toolkit to assist this process from cluster 3 implementations onwards.

NSW Health conducted post-implementation reviews for clusters 1 and 2 and found that LHDs in these clusters were not using HealthRoster to realise all the benefits that HealthRoster could deliver.

By September 2018, NSW Health should:

  1. Ensure that Local Health Districts undertake benefits realisation planning according to the NSW Health benefits realisation framework
  2. Regularly measure benefits realised, at state and local health district levels, from the statewide implementation of HealthRoster
  3. Review the use of HealthRoster in Local Health Districts in clusters 1 and 2 and assist them to improve their HealthRoster related processes and practices.

By June 2019, NSW Health should:

  1. Ensure that all Local Health Districts are effectively using demand based rostering.

Appendix one - Response from agency

Appendix two - About the audit

Appendix three - Performance auditing

 

Parliamentary reference - Report number #301 - released 7 June 2018

Published

Actions for Grants to non-government schools

Grants to non-government schools

Education
Compliance
Internal controls and governance
Management and administration

The NSW Department of Education could strengthen its management of the $1.2 billion provided to non-government schools annually. This would provide greater accountability for the use of public funds, according to a report released today by the Auditor-General for New South Wales, Margaret Crawford.

Non‑government schools educate 418,000 school children each year, representing 35 per cent of all students in NSW. The NSW Department of Education administers several grant schemes to support these schools, with the aim of improving student learning outcomes and supporting parent choice. To be eligible for NSW Government funding, non‑government schools must be registered with the NSW Education Standards Authority (NESA) and not operate 'for profit' as per section 83C of the NSW Education Act 1990 (the Act). Non‑government schools can either be registered as independent or part of a System Authority.

In 2017–18, non‑government schools in NSW will receive over $1.2 billion from the NSW Government, as well as $3.4 billion from the Australian Government. Recently, the Australian Government has changed the way it funds schools. The NSW Government is assessing how these changes will impact State funding for non‑government schools.

This audit assessed how effectively and efficiently NSW Government grants to non‑government schools are allocated and managed. This audit did not assess the use of NSW Government grants by individual non‑government schools or System Authorities because the Auditor‑General of New South Wales does not have the mandate to assess how government funds are spent by non‑government entities.

Conclusion

The Department of Education effectively and efficiently allocates grants to non‑government schools. Clarifying the objectives of grants, monitoring progress towards these objectives, and improving oversight, would strengthen accountability for the use of public funds by non‑government schools.

We tested a sample of grants provided to non‑government schools under all major schemes, and found that the Department of Education consistently allocates and distributes grants in line with its methodology. The Department has clear processes and procedures to efficiently collect data from schools, calculate the level of funding each school or System should receive, obtain appropriate approvals, and make payments.

We identified three areas where the Department could strengthen its management of grants to provide greater accountability for the use of public funds. First, the Department’s objectives for providing grants to non‑government schools are covered by legislation, intergovernmental agreements and grant guidelines. The Department could consolidate these objectives to allow for more consistent monitoring. Second, the Department relies on schools or System Authorities to engage a registered auditor to certify the accuracy of information on their enrolments and usage of grants. Greater scrutiny of the registration and independence of the auditors would increase confidence in the accuracy of this information. Third, the Department does not monitor how System Authorities reallocate grant funding to their member schools. Further oversight in this area would increase accountability for the use of public funds.

The Department effectively and efficiently allocates grants to non‑government schools. Strengthening its processes would provide greater assurance that the information it collects is accurate.

The Department provides clear guidelines to assist schools to provide the necessary census information to calculate per capita grants. Schools must get an independent external auditor, registered with ASIC, to certify their enrolment figures. The Department checks a sample of the auditors to ensure that they are registered with ASIC. Some other jurisdictions perform additional procedures to increase confidence in the accuracy of the census (for example, independently checking a sample of schools’ census data).

The Department accurately calculates and distributes per capita grants in accordance with its methodology. The previous methodology, used prior to 2018, was not updated frequently enough to reflect changes in schools' circumstances. Over 2014 to 2017, the Department provided additional grants to non‑government schools under the National Education Reform Agreement (NERA), to bring funding more closely in line with the Australian Department of Education and Training's Schooling Resource Standard (SRS). From 2018, the Department has changed the way it calculates per capita grants to more closely align with the Australian Department of Education and Training's approach.

The Department determines eligibility for grants by checking a school's registration status with NESA. However, NESA's approach to monitoring compliance with the registration requirements prioritises student learning and wellbeing requirements over the requirement for policies and procedures for proper governance. Given their importance to the appropriate use of government funding, NESA could increase its monitoring of policies and procedures for proper governance through its program of random inspections. Further, the Department and NESA should enter into a formal agreement to share information to more accurately determine the level of risk of non‑compliance at each school. This may help both agencies more effectively target their monitoring to higher‑risk schools.

By December 2018, the NSW Department of Education should:

  1. Strengthen its processes to provide greater assurance that the enrolment and expenditure information it collects from non‑government schools is accurate. This should build on the work the Australian Government already does in this area.
  2. Establish formal information‑sharing arrangements with the NSW Education Standards Authority to more effectively monitor schools' eligibility to receive funding.
     

By December 2018, the NSW Education Standards Authority should:

  1. Extend its inspection practices to increase coverage of the registration requirement for policies and procedures for the proper governance of schools.
  2. Establish formal information‑sharing arrangements with the NSW Department of Education to more effectively monitor schools' continued compliance with the registration requirements.

The Department’s current approach to managing grants to non‑government schools could be improved to provide greater confidence that funds are being spent in line with the objectives of the grant schemes.

The NSW Government provides funding to non‑government schools to improve student learning outcomes, and to support schooling choices by parents, but does not monitor whether these grants are achieving this. In addition, each grant program has specific objectives. The main objectives for the per capita grant program is to increase the rate of students completing Year 12 (or equivalent), and to improve education outcomes for students. While non‑government schools publicly report on some educational measures via the MySchool website, these measures do not address all the objectives. Strengthened monitoring and reporting of progress towards objectives, at a school level, would increase accountability for public funding. This may require the Department to formalise its access to student level information.

The Department has listed five broad categories of acceptable use for per capita grants, however, provides no further guidance on what expenditure would fit into these categories. Clarifying the appropriate use of grants would increase confidence that funding is being used as intended. Schools must engage an independent auditor, registered with ASIC, to certify that the funding has been spent. The Department could strengthen this approach by improving its processes to check the registration of the auditor, and to verify their independence.

The Department has limited oversight of funding provided to System Authorities (Systems). The Department provides grants to Systems for all their member schools. The Systems can distribute the grants to their schools according to their own methodology. Systems are not required to report to the Department how much of their grant was retained for administrative or centralised expenses. Increased oversight over how the Systems distribute this grant could provide increased transparency for the use of public funds by systems.

By December 2018, the NSW Department of Education should:

  1. Establish and communicate funding conditions that require funded schools to:
    • adhere to conditions of funding, such as the acceptable use of grants, and accounting requirements to demonstrate compliance
    • report their progress towards the objectives of the scheme or wider Government initiatives
    • allow the Department to conduct investigations to verify enrolment and expenditure of funds
    • provide the Department with access to existing student level data to inform policy development and analysis.
  1. Increase its oversight of System Authorities by requiring them to:
    • re‑allocate funds across their system on a needs basis, and report to the Department on this
    • provide a yearly submission with enough detail to demonstrate that each System school has spent their State funding in line with the Department's requirements.

Published

Actions for Managing risks in the NSW public sector: risk culture and capability

Managing risks in the NSW public sector: risk culture and capability

Finance
Health
Justice
Treasury
Internal controls and governance
Management and administration
Risk
Workforce and capability

The Ministry of Health, NSW Fair Trading, NSW Police Force, and NSW Treasury Corporation are taking steps to strengthen their risk culture, according to a report released today by the Auditor-General, Margaret Crawford. 'Senior management communicates the importance of managing risk to their staff, and there are many examples of risk management being integrated into daily activities', the Auditor-General said.

We did find that three of the agencies we examined could strengthen their culture so that all employees feel comfortable speaking openly about risks. To support innovation, senior management could also do better at communicating to their staff the levels of risk they are willing to accept.

Effective risk management is essential to good governance, and supports staff at all levels to make informed judgements and decisions. At a time when government is encouraging innovation and exploring new service delivery models, effective risk management is about seizing opportunities as well as managing threats.

Over the past decade, governments and regulators around the world have increasingly turned their attention to risk culture. It is now widely accepted that organisational culture is a key element of risk management because it influences how people recognise and engage with risk. Neglecting this ‘soft’ side of risk management can prevent institutions from managing risks that threaten their success and lead to missed opportunities for change, improvement or innovation.

This audit assessed how effectively NSW Government agencies are building risk management capabilities and embedding a sound risk culture throughout their organisations. To do this we examined whether:

  • agencies can demonstrate that senior management is committed to risk management
  • information about risk is communicated effectively throughout agencies
  • agencies are building risk management capabilities.

The audit examined four agencies: the Ministry of Health, the NSW Fair Trading function within the Department of Finance, Services and Innovation, NSW Police Force and NSW Treasury Corporation (TCorp). NSW Treasury was also included as the agency responsible for the NSW Government's risk management framework.

Conclusion
All four agencies examined in the audit are taking steps to strengthen their risk culture. In these agencies, senior management communicates the importance of managing risk to their staff. They have risk management policies and funded central functions to oversee risk management. We also found many examples of risk management being integrated into daily activities.
That said, three of the four case study agencies could do more to understand their existing risk culture. As good practice, agencies should monitor their employees’ attitude to risk. Without a clear understanding of how employees identify and engage with risk, it is difficult to tell whether the 'tone' set by the executive and management is aligned with employee behaviours.
Our survey of risk culture found that three agencies could strengthen a culture of open communication, so that all employees feel comfortable speaking openly about risks. To support innovation, senior management could also do better at communicating to their staff the levels of risk they are willing to accept.
Some agencies are performing better than others in building their risk capabilities. Three case study agencies have reviewed the risk-related skills and knowledge of their workforce, but only one agency has addressed the gaps the review identified. In three agencies, staff also need more practical guidance on how to manage risks that are relevant to their day-to-day responsibilities.
NSW Treasury provides agencies with direction and guidance on risk management through policy and guidelines. Its principles-based approach to risk management is consistent with better practice. Nevertheless, there is scope for NSW Treasury to develop additional practical guidance and tools to support a better risk culture in the NSW public sector. NSW Treasury should encourage agency heads to form a view on the current risk culture in their agencies, identify desirable changes to that risk culture, and take steps to address those changes. 

In assessing an agency’s risk culture, we focused on four key areas:

Executive sponsorship (tone at the top)

In the four agencies we reviewed, senior management is communicating the importance of managing risk. They have endorsed risk management frameworks and funded central functions tasked with overseeing risk management within their agencies.

That said, we found that three case study agencies do not measure their existing risk culture. Without clear measures of how employees identify and engage with risk, it is difficult for agencies to tell whether employee's behaviours are aligned with the 'tone' set by the executive and management.

For example, in some agencies we examined we found a disconnect between risk tolerances espoused by senior management and how these concepts were understood by staff.

Employee perceptions of risk management

Our survey of staff indicated that while senior leaders have communicated the importance of managing risk, more could be done to strengthen a culture of open communication so that all employees feel comfortable speaking openly about risks. We found that senior management could better communicate to their staff the levels of risk they should be willing to accept.

Integration of risk management into daily activities and links to decision-making

We found examples of risk management being integrated into daily activities. On the other hand, we also identified areas where risk management deviated from good practice. For example, we found that corporate risk registers are not consistently used as a tool to support decision-making.

Support and guidance to help staff manage risks

Most case study agencies are monitoring risk-related skills and knowledge of their workforce, but only one agency has addressed the gaps it identified. While agencies are providing risk management training, surveyed staff in three case study agencies reported that risk management training is not adequate.

NSW Treasury provides agencies with direction and guidance on risk management through policy and guidelines. In line with better practice, NSW Treasury's principles-based policy acknowledges that individual agencies are in a better position to understand their own risks and design risk management frameworks that address those risks. Nevertheless, there is scope for NSW Treasury to refine its guidance material to support a better risk culture in the NSW public sector.

Recommendation

By May 2019, NSW Treasury should:

  • Review the scope of its risk management guidance, and identify additional guidance, training or activities to improve risk culture across the NSW public sector. This should focus on encouraging agency heads to form a view on the current risk culture in their agencies, identify desirable changes to that risk culture, and take steps to address those changes.

Published

Actions for Volume Ten 2013 focusing on Health

Volume Ten 2013 focusing on Health

Health
Asset valuation
Financial reporting
Information technology
Infrastructure
Internal controls and governance
Management and administration
Project management
Risk
Shared services and collaboration

Unqualified opinions were issued for all agencies audited in the following report.

Some of the reports findings include:

  • Most cultural bodies rely heavily on government grants to fund services

  • The Sydney Opera House Trust earns most of its revenue from commercial operations

  • Less than half of the 2014-16 service agreements between HealthShare NSW and its customers have been signed. HealthShare NSW and health entities should finalise their 2014-2016 service agreements by no later than 31 January 2014

  • Five service level agreements with NSW Health Pathology for 2012-13 were never signed. NSW Health Pathology and local health districts/speciality networks should finalise their 2013-14 service agreements by no later than 31 December 2013

  • HealthShare NSW is committed to sharing internal audit findings across NSW Health

  • The Ministry has started a long-term project to review its policy directives

  • A recent review concluded the health sector has mature risk management practices

  • When changes to the Aboriginal Land Rights Act 1983 occur, the Minister should identify and assess any risks from the changes and develop strategies to mitigate against them.

Published

Actions for Government Advertising 2012-13

Government Advertising 2012-13

Premier and Cabinet
Health
Transport
Compliance
Procurement

The following report assessed the activities of the two agencies in relation to their government advertising campaigns in 2012-13 and tested compliance by tracking a campaign through from development to dissemination.

 

Parliamentary reference - Report number #236 - released 23 September 2013

Published

Actions for Making the Best Use of Public Housing

Making the Best Use of Public Housing

Community Services
Internal controls and governance
Management and administration
Regulation

There are 55,000 eligible applicants on the social housing waiting list, with some people waiting for more than ten years to get a house. The waiting list could be more than 86,000 by 2016 unless things change.
 
Social housing only meets about 44 per cent of need in New South Wales even though we have the largest social housing portfolio in Australia. Social housing falls into three groups. About 80 per cent is public housing which is owned and operated by government. The remaining stock is community housing and Aboriginal housing.

 

Parliamentary reference - Report number #234 - released 30 July 2013