What this report is about

In this report, we present findings and recommendations relevant to regulation from selected reports between 2018 and 2024.

This analysis includes performance audits, compliance audits and the outcomes of financial audits.

Effective regulation is necessary to ensure compliance with the law as well as to promote positive social and economic outcomes and minimise risks with certain activities.

The report is a resource for public sector leaders. It provides insights into the challenges and opportunities for more effective regulation.

Audit findings

The analysis of findings and recommendations is structured around four key themes related to effective regulation:

  • governance and accountability
  • processes and procedures
  • data and information management
  • support and guidance.

The report draws from this analysis to present insights for agencies to promote effective regulation. It also includes relevant examples from recent audit reports.

In this report, we also draw out insights for agencies that provide a public sector stewardship role.

The report highlights the need for agencies to communicate a clear regulatory approach. It also emphasises the need to have a consistent regulatory approach, supported by robust information about risks and accompanied with timely and proportionate responses.

The report highlights the need to provide relevant support to regulated parties to facilitate compliance and the importance of transparency through reporting of meaningful regulatory information.

 

Read the PDF report

Published

Actions for State Finances 2023

State Finances 2023

Treasury
Whole of Government
Asset valuation
Compliance
Cyber security
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Regulation

What this report is about

Results of the audit of the Consolidated State Financial Statements of the New South Wales General Government Sector (GGS) and Total State Sector (TSS) for the year ended 30 June 2023.

Findings

The audit opinion on the 2022–23 Consolidated State Financial Statements was qualified in relation to two issues and included an emphasis of matter.

The first qualification matter is a continuation of the prior year limitation of scope on the audit relating to the Catholic Metropolitan Cemeteries Trust (CMCT), a controlled state entity, who continued to deny access to its management, books and records for the purposes of a financial audit. As a result, the Audit Office was unable to obtain sufficient appropriate audit evidence to support the assets, liabilities, income and expenses relating to CMCT recorded in the TSS and the equity investment recognised in the GGS relating to the net assets of CMCT.

The second qualification matter relates to the limitations on the accuracy and reliability of financial information relating to Statutory Land Managers (SLMs) and Common Trust entities (CTs) controlled by the State and were either exempted from requirements to prepare financial reports, or who were required to submit financial reports and have not done so. The Audit Office was unable to obtain sufficient appropriate audit evidence to determine the impact on the value of non-land assets and liabilities, income and expenses that should be recognised in the 2022–23 Consolidated State Financial Statements and which have not been recorded in the Consolidated State Financial Statements.

The independent audit opinion also includes an emphasis of matter drawing attention to key decisions made by the NSW Government regarding the future of the Transport Asset Holding Entity of New South Wales (TAHE).

Recommendations

The report includes recommendations for NSW Treasury to address several high-risk findings, including:

  • ensuring accurate and reliable financial information is available to recognise the non-land balances of SLMs and CTs
  • ensuring the CMCT, SLMs and CTs meet their statutory reporting obligations
  • conducting a broader review of the financial reporting exemption framework
  • continued monitoring of TAHE's control over its assets
  • providing timely guidance to the sector relating to legislative or policy changes that impact financial reporting
  • developing an accounting policy for the reimbursement of unsuccessful tender bid cost contributions.

 

Read the PDF report

Published

Actions for Internal controls and governance 2023

Internal controls and governance 2023

Whole of Government
Compliance
Cyber security
Information technology
Internal controls and governance
Management and administration
Regulation
Workforce and capability

What this report is about

This report analyses the internal controls and governance of the 25 largest agencies in the NSW public sector, excluding state owned corporations and public financial corporations, for the year ended 30 June 2023.

Findings

Internal control trends

The proportion of control deficiencies identified as high-risk this year decreased to 4.5% (8.2% in 2022).

Repeat findings of control deficiencies represent 38% of all findings (48% in 2022). 

Information technology

Over half of the agencies reviewed have deficiencies in managing user access to their information systems. Over a third of agencies had deficiencies in their controls over privileged user accounts within their information technology environments. 

Cyber security

Over 80% of assessments for maturity levels against the NSW Cyber Security Policy have reported one or more self-assessed Mandatory Requirements are not practiced on a consistent and regular basis.

Essential Eight cyber controls have not improved, and they need to. 

Governance framework

Deficiencies were noted in agencies' governance and risk management frameworks, namely: outdated risk management policies, lack of risk appetite statements, and internal audit functions not being externally evaluated.  

Payroll and work health and safety (WHS)

Overtime expenses increased by 40% between 2020 and 2023, compared to salaries and wages which increased by 16% over the same period.

Five agencies have WHS policies that do not reflect current WHS regulations.

Recommendations

Several important recommendations were made for agencies to prioritise efforts to improve cyber security controls and cyber resilience measures.

It was also recommended that agencies periodically review their risk management maturity and implement action plans, and ensure their WHS policies and procedures reflect current legislation requirements including the need to manage psychosocial risks.

 

Internal controls are processes, policies and procedures that help agencies to:

  • operate effectively and efficiently
  • produce reliable financial reports
  • comply with laws and regulations
  • support ethical government.

This chapter outlines the overall trends for agency controls and governance issues, including the number of audit findings, the degree of risk those deficiencies pose to the agency, and a summary of the most common deficiencies found across agencies.

For consistency and comparability, we have adjusted the 2022 results to incorporate additional audit findings that were reported after the date of the Internal controls and governance 2022 report. Therefore, the 2022 figures will not necessarily align with those reported in our 2022 report.

Section highlights

  • The Audit Office identified 12 high-risk findings, compared to 23 last year, with eight repeated from last year. Eleven of the high-risk findings related to financial controls while one related to other (governance) controls.
  • The proportion of repeat deficiencies has decreased from 48% in 2021–22 to 38% in 2022–23. 

 

This chapter outlines our audit observations, conclusions and recommendations arising from our review of agency controls to manage key financial systems.

Section highlights

  • Over half of the agencies reviewed have deficiencies in managing user access.
  • Thirty-six per cent of agencies had deficiencies in their controls over privileged accounts.
  • Weaknesses were identified in how agencies manage service providers or other organisations which have access to their systems and data.
  • Inadequate records were kept to demonstrate approvals for key system implementation milestones, including successful data migration testing and approval for go-live.
  • Thirty-two per cent of agencies had not implemented segregations of duties over key payroll functions. 

 

This chapter outlines our audit observations, conclusions and recommendations arising from our review of agencies' cyber security.

Section highlights

  • Eighty-three per cent of maturity assessments have reported one or more Mandatory Requirements below level three, which is the level at which the requirement is self-assessed and considered to be practiced on a consistent and regular basis.
  • Essential Eight maturity levels have remained unchanged or have declined, and may not be suitable for the level of risk agencies face.
  • All 25 agencies reviewed have a cyber incident response plan and all but two newly created agencies tested their plan.
  • Systems to detect cyber incidents across agencies could improve.
  • There is a risk of under reporting cyber incidents at six agencies that kept insufficient records to support their cyber incident classifications.
  • Overall, agencies need to increase their focus and prioritise efforts to ensure effective cyber security and resilience measures are in place. 

 

Governance in the context of the NSW public service refers to the structures, processes, and mechanisms by which government departments and agencies are held to account when they make decisions and implement policies and programs in the service of the public interest. It also includes the principles and practices that guide how these agencies work together.

This chapter outlines our audit observations, conclusions and recommendations from our review of agencies' governance frameworks and practices, with consideration of NSW Treasury issued policies and best practices. It focuses on two key areas: governance arrangements and risk management.

Section highlights

  • Whilst agencies have generally adopted governance and risk management frameworks that align with Treasury issued policies and best practices, we noted deficiencies, including:
    • 20% of governing boards operated without a board charter
    • 16% of agencies had risk management policies that were beyond their scheduled review date
    • 16% of agencies did not have a risk appetite statement
    • 28% of agency internal audit functions have not been externally evaluated in the last five years.
  • Agencies should perform periodic assessments/reviews of their risk maturity and implement action plans where required. 

 

This chapter outlines our audit observations, conclusions and recommendations arising from our review of agencies' payroll controls and management of work health and safety (WHS).

Section highlights

  • Agencies should improve their controls around payroll masterfile maintenance, such as enforcing segregation of duties in system access levels and ensuring changes to data are reviewed by an independent officer.
  • On average, overtime expenses represented three per cent of total salaries and wages in 2023 and have increased by 40.2% since 2020, compared to salaries and wages which increased by 16.3% over the same period.
  • Five agencies have outdated WHS policies, which do not reflect changes to WHS regulations. Sixteen per cent of agencies have not included psychosocial hazards in their WHS procedures or risk assessment process. 

 

Published

Actions for Health 2023

Health 2023

Health
Whole of Government
Asset valuation
Compliance
Financial reporting
Information technology
Internal controls and governance
Project management
Regulation
Risk
Shared services and collaboration
Workforce and capability

What this report is about

Results of the Health portfolio of agencies' financial statement audits for the year ended 30 June 2023.

The audit found

Unmodified audit opinions were issued for all Health portfolio agencies' financial statements. 

The number of monetary misstatements increased in 2022–23, driven by key accounting issues, including the first-time recognition of paid parental leave and plant and equipment fair value adjustments. 

The key audit issues were 

NSW Health identified errors regarding the recognition and calculation of long service leave entitlements for employees with ten or more years of service that had periods of part time service in the first ten years, resulting in prior period restatements. 

Comprehensive revaluation of buildings at the Graythwaite Charitable Trust found errors in the previous year's valuation, resulting in prior period restatements. 

New parental leave legislation increased employee liabilities for portfolio agencies. The Ministry of Health corrected the consolidated financial statements to record parental leave liabilities for all agencies within the Health portfolio.   

A repeat high-risk issue relates to processing time records by administrators that have not been reviewed prior to running the pay cycle.   

Thirty per cent of reported issues were repeat issues. 

The audit recommended 

Portfolio agencies should ensure any changes to employee entitlements are assessed for their potential financial statements impact under the relevant Australian Accounting Standards. 

Portfolio agencies should address deficiencies that resulted in qualified reports on:   

  • the design and operation of shared service controls
  • prudential non-compliance at residential aged care facilities.

 

This report provides Parliament and other users of the Health portfolio of agencies’ financial statements with the results of our audits, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision-making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Health portfolio of agencies (the portfolio) for 2023.

Section highlights

  • Unqualified audit opinions were issued for all portfolio agencies required to prepare general purpose financial statements.
  • The total number of errors (including corrected and uncorrected) in the financial statements increased compared to the prior year.
  • The Ministry of Health retrospectively corrected an $18.9 million adjustment in its financial statements relating to long service leave entitlements for certain employees.
  • Graythwaite Charitable Trust retrospectively corrected a $4.2 million adjustment in its financial statements related to prior period valuations. 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision-making.

This chapter outlines observations and insights from our financial statement audits of agencies in the Health portfolio.  

 Section highlights 

  • The 2022–23 audits identified one high-risk and 57 moderate risk issues across the portfolio.
  • The high-risk matter related to the forced-finalisation of time records.
  • The total number of findings increased from 67 to 111 in 2022–23.
  • Thirty per cent of the issues were repeat issues. Most repeat issues related to internal control deficiencies or non-compliance with key legislation and/or central agency policies.
  • Forced-finalisation of time records, accounting for the new paid parental leave provision and user access review deficiencies were the most commonly reported issues.
  • Qualified Assurance Practitioner's reports were issued on:
    • the design and operation of controls as documented by HealthShare NSW
    • the Ministry's Annual Prudential Compliance Statements in relation to residential aged care facilities.

Appendix one – Misstatements in financial statements submitted for audit

Appendix two – Early close procedures

Appendix three – Timeliness of financial reporting

Appendix four – Financial data

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

 

Published

Actions for Transport 2023

Transport 2023

Transport
Whole of Government
Asset valuation
Compliance
Financial reporting
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Risk

What this report is about

Result of the Transport portfolio of agencies' financial statement audits for the year ended 30 June 2023.

The audit found

Unqualified audit opinions were issued for all Transport portfolio agencies.

An 'emphasis of matter' paragraph was included in the Transport Asset Holding Entity of New South Wales' (TAHE) independent auditor's report, which draws attention to management's disclosure regarding proposed changes to TAHE's operating model.

Government's decision to convert TAHE into a non-commercial Public Non-Financial Corporation may impact the future valuation and the control of TAHE's assets.

Transport for NSW's valuation of roads and bridges resulted in a net increase to its asset value by $15.7 billion.

Transport for NSW and Sydney Metro have capitalised over $300 million of tender bid costs paid to unsuccessful tender bidders relating to significant infrastructure projects. Whilst NSW Treasury policy provides clarity on the reimbursement of unsuccessful bidders' costs, clearer guidance on how to account for these costs in agency's financial statements is required.

The key audit issues were

The number of issues reported to management decreased from 53 in 2021–22 to 49 in 2022–23.

High-risk findings include:

  • gaps in how Sydney Metro manages its contractors and how conflicts of interest are recorded and managed
  • future financial reporting implications to account for government's proposed changes to TAHE's future operating model, including asset valuations and control assessments of assets and operations
  • Parramatta Park Trust's tree assets' valuation methodology needs to be addressed.

Recommendations were made to address the identified deficiencies.

This report provides Parliament and other users of the Transport portfolio of agencies’ financial statements with the results of our audits, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Transport portfolio of agencies (the portfolio) for 2023.

Section highlights

  • Unqualified audit opinions were issued on all the portfolio agencies’ 30 June 2023 financial statements.
  • An 'Emphasis of Matter' paragraph was included in the Transport Asset Holding Entity of New South Wales’ (TAHE) Independent Auditor's Report to draw attention to management's disclosure regarding the proposed changes to TAHE's future operating model.
  • The total number of errors (including corrected and uncorrected) in the financial statements increased by 59% compared to the prior year.
  • The recent government's decision to convert TAHE into a non-commercial Public Non-Financial Corporation may impact the future valuation and the control of TAHE’s assets.
  • Transport for NSW needs to further improve its quality assurance processes over comprehensive valuations, in particular, ensuring key inputs used in the valuations are properly supported and verified.
  • Transport for NSW and Sydney Metro capitalised over $300 million of bid costs paid to unsuccessful bidders. NSW Treasury’s Bid Cost Contributions Policy does not contemplate how these costs should be recognised in agency’s financial statements. Transport agencies should work with NSW Treasury to develop an accounting policy for the bid cost contributions to ensure consistent application across the sector.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision-making.
This chapter outlines our observations and insights from our financial statement audits of agencies in the Transport portfolio.

Section highlights

  • The 2022–23 audits identified four high risks and 28 moderate risk issues across the portfolio. Thirty-nine per cent of issues were repeat findings.
  • Four high risk findings include:
    • TAHE’s asset valuations (new)
    • TAHE’s control of assets and operations (new)
    • Sydney Metro’s management of contractors and conflicts of interest (new)
    • Parramatta Park Trust’s valuation of trees (repeat).
  • The total number of findings decreased from 53 in 2021–22 to 49 in 2022–23. Many repeat findings related to control weaknesses over the asset valuation, payroll processes, conflicts of interest and information technology user access administration.


Appendix one – Misstatements in financial statements submitted for audit 

Appendix two – Early close procedures

Appendix three – Timeliness of financial reporting 

Appendix four – Financial data 

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Regional NSW 2023

Regional NSW 2023

Industry
Environment
Planning
Whole of Government
Asset valuation
Compliance
Cyber security
Financial reporting
Fraud
Information technology
Infrastructure
Procurement
Regulation
Risk
Service delivery
Shared services and collaboration

What this report is about

Results of the Regional NSW financial statements audits for the year ended 30 June 2023.

What we found

Unqualified audit opinions were issued on all completed audits in the Regional NSW portfolio agencies.

The number of monetary misstatements identified in our audits increased from 28 in 2021–22 to 30 in 2022–23.

What the key issues were

Effective 1 July 2023, staff employed in the Northern Rivers Reconstruction Corporation Division of the Department of Regional NSW transferred to the NSW Reconstruction Authority Staff Agency.

The Regional NSW portfolio agencies were migrated into a new government wide enterprise resourcing planning system.

The total number of audit management letter findings across the portfolio of agencies decreased from 36 to 23.

A high risk matter was raised for the NSW Food Authority to improve the internal controls in the information technology environment including monitoring and managing privilege user access.

What we recommended

Local Land Services should prioritise completing all mandatory early close procedures.

Portfolio agencies should:

  • ensure any changes to employee entitlements are assessed for their potential financial statements impact under the relevant Australian Accounting Standards
  • prioritise and address internal control deficiencies identified in audit management letters.

This report provides Parliament and other users of the Regional NSW portfolio of agencies financial statements with the results of our audits, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision-making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Regional NSW portfolio of agencies (the portfolio) for 2023.

Section highlights

  • Unqualified audit opinions were issued on all completed 30 June 2023 financial statements audits of the portfolio agencies. Two audits are ongoing.
  • The total number of errors (including corrected and uncorrected) in the financial statements increased compared to the prior year.
  • Portfolio agencies met the statutory deadline for submitting their 2022–23 early close financial statements and other mandatory procedures.
  • Portfolio agencies continue to provide financial assistance to communities affected by natural disasters.
  • A change to the NSW paid parental leave scheme, effective October 2023, created a new legal obligation that needed to be recognised by impacted government agencies. Impact to the agencies' financial statements were not material. 

 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision-making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the Regional NSW portfolio.

Section highlights

  • The 2022–23 audits identified one high risk and nine moderate risk issues across the portfolio. Of these, one was a moderate risk repeat issue.
  • The total number of findings decreased from 36 to 23 which mainly related to deficiencies in internal controls.
  • The high risk matter relates to the monitoring and managing of privilege user access at NSW Food Authority. 

 

Appendix one – Misstatements in financial statements submitted for audit

Appendix two – Early close procedures

Appendix three – Timeliness of financial reporting

Appendix four – Financial data

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Premier and Cabinet 2023

Premier and Cabinet 2023

Premier and Cabinet
Whole of Government
Asset valuation
Compliance
Cyber security
Financial reporting
Fraud
Information technology
Procurement
Regulation
Risk
Workforce and capability

What this report is about

Results of the Premier and Cabinet portfolio of agencies' financial statement audits for the year ended 30 June 2023.

What we found

Unqualified audit opinions were issued for all Premier and Cabinet portfolio agencies.

What the key issues were

The Administrative Arrangements Orders, effective 1 July 2023, changed the name of the Department of Premier and Cabinet to the Premier's Department and transferred parts of Department of Premier and Cabinet to The Cabinet Office.

The number of monetary misstatements identified in our audits decreased from 15 in 2021–22 to 12 in 2022–23.

The total number of management letter findings across the portfolio of agencies increased from ten in 2021–22 to 20 in 2022–23.

Thirty per cent of all issues were repeat issues. The most common repeat issues related to deficiencies in controls over financial reporting.

What we recommended

Portfolio agencies should:

  • ensure any changes to employee entitlements are assessed for their potential financial statements impact under the relevant Australian Accounting Standards
  • prioritise and address internal control deficiencies identified in Audit Office management letters.

This report provides Parliament and other users of the Premier and Cabinet portfolio of agencies’ financial statements with the results of our audits, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision-making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Premier and Cabinet portfolio of agencies (the portfolio) for 2023.

Section highlights

  • Unqualified audit opinions were issued on all the portfolio agencies 2022–23 financial statements.
  • The total number of errors (including corrected and uncorrected) in the financial statements decreased compared to the prior year. 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision-making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the Premier and Cabinet portfolio.

Section highlights

  • The 2022–23 audits identified eight moderate risk issues across the portfolio of agencies. Of these, two were repeat issues, and related to password and security configuration and management of excessive annual leave.
  • The total number of findings increased from ten to 20, which mainly related to deficiencies in controls over financial reporting and governance and oversight.
  • The most common repeat issues related to weaknesses in controls over financial reporting.

Appendix one – Early close procedures

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Stronger Communities 2023

Stronger Communities 2023

Community Services
Whole of Government
Asset valuation
Compliance
Cyber security
Financial reporting
Information technology
Internal controls and governance
Management and administration
Procurement
Project management
Shared services and collaboration

What this report is about

Results of the Stronger Communities financial statement audits for the year ended 30 June 2023.

What we found

Unqualified audit opinions were issued on all completed Stronger Communities portfolio agencies.

Machinery of government changes during the year returned the sports-related agencies to the Stronger Communities portfolio.

Resilience NSW was abolished on 16 December 2022 with most of its functions transferred to the newly created NSW Reconstruction Authority.

The Trustee for the First Australian Mortgage Acceptance Corporation (FANMAC) is a prescribed entity under the Government Sector Finance Regulation 2018. The Trustee should have presented the FANMAC's financial statements for audit after it became a GSF agency on 1 July 2020.

The number of monetary misstatements identified in our audits decreased from 42 in 2021–22 to 29 in 2022–23.

What the key issues were

In 2022–23, agencies in the portfolio recorded net revaluation uplifts to land and buildings totalling $643 million.

Out of home care and permanency support grant expenditure has increased by 27% since 2019–20. An upcoming performance audit report will focus on the timeliness and quality of the child protection services provided by the department and its non-government service providers.

A high-risk matter was raised for the department over segregation of duties deficiencies in the Justice Link system.

Four high-risk matters reported in 2021–22 have been resolved.

Thirty-three agencies were onboarded into a new government-wide enterprise resource planning system. Additional agencies will be onboarded in three tranches from April 2024 through to October 2024.

What we recommended

Portfolio agencies should:

  • ensure any changes to employee entitlements are assessed for their financial statement impact under the relevant Australian Accounting Standards
  • prioritise and address internal control deficiencies identified in our management letters.

This report provides Parliament and other users of the Stronger Communities portfolio of agencies’ financial statements with the results of our audits, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision-making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Stronger Communities portfolio of agencies (the portfolio) for 2023.

Section highlights

  • Unqualified audit opinions were issued on all completed 30 June 2023 financial statements audits of portfolio agencies, including the audit of the Crown Solicitor's Office's Trust Account for compliance with clause 14 of the Legal Profession Uniform Law Application Regulation 2015.
  • The financial statement audits of the NSW Trustee and Guardian Common Funds (the common funds) – year ended 30 June 2022 were certified by management on 6 December 2022 and independent auditor's reports issued 21 December 2022. The 30 June 2023 financial statements audits of the common funds are ongoing.
  • A variation to an agreement between the Commonwealth Attorney-General and the Legal Aid Commission of New South Wales for legal services to support the Royal Commission into Violence, Neglect and Exploitation of people with disability program extended the reporting period from 30 June 2023 to 29 September 2023 – the conclusion of the Royal Commission. The audit of the financial report acquitting expenditure under the agreement is expected to be completed before 28 February 2024.
  • The audit of the Home Purchase Assistance Fund's (the fund) 30 June 2022 financial statements remains incomplete. Those charged with governance of the fund have not provided sufficient and appropriate evidence to support the carrying value of material investments reported in the fund's financial statements. The financial audit of the fund's 2023 financial statements remain incomplete as a result.
  • The Trustee for the First Australian Mortgage Acceptance Corporation Master and Pooled Super Trusts had not prepared general purpose financial statements since 30 June 2021 when the financial reporting provisions of the Government Finance Sector Act 2018 were enacted and the Trustee was prescribed as a GSF agency under the regulations. The audits of these financial statements are ongoing.
  • Reported corrected misstatements decreased from 28 in 2021–22 to six with a gross value of $8.8 million in 2022–23 ($277 million in 2021–22).
  • Portfolio agencies met the statutory deadline for submitting their 2022–23 early close financial statements and other mandatory procedures.
  • In 2022–23, portfolio agencies collectively recorded net revaluation uplifts to the carrying values of land and buildings totalling $643 million (2021–22: $993 million) initiated through a combination of comprehensive and desktop valuations.
  • The Department of Communities and Justice (the department) had previously deferred performing a comprehensive revaluation of its land and building portfolio relating to the Corrective Services and Youth Justice functions. The deferral was due to the challenges in providing valuers sufficient access to the facilities due to the pandemic. The department is scheduled to perform a comprehensive revaluation of its full land and building portfolio in 2023–24. 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision-making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the Stronger Communities portfolio.

Section highlights

  • The number of findings reported to management has decreased from 142 in 2021–22, to 71 in 2022–23, and 35% were repeat issues (36% in 2021–22). Repeat issues related to non-compliance with key legislation and/or agency policies, information technology and internal control deficiencies.
  • A long-standing issue about segregation of duties over the JusticeLink system managed by the department has been elevated from moderate to high risk.
  • Four out of six high-risk issues reported in the prior year have been addressed.
  • Of the 15 newly identified moderate risk issues, 11 related to information technology and internal control deficiencies. 

Appendix one – Misstatements in financial statements submitted for audit

Appendix two – Early close procedures

Appendix three – Timeliness of financial reporting

Appendix four – Financial data

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Education 2023

Education 2023

Education
Whole of Government
Asset valuation
Compliance
Cyber security
Financial reporting
Information technology
Internal controls and governance
Procurement
Project management
Risk

What this report is about

Results of the Education portfolio of agencies’ financial statements audits for the year ended 30 June 2023.

What we found

Unqualified audit opinions were issued for all Education portfolio agencies.

An ‘other matter’ paragraph was included in the TAFE Commission’s independent auditor’s report as it did not have a delegation or sub-delegation from the Minister for Education and Early Learning to incur expenditure on grants from other portfolio agencies.

What the key issues were

Comprehensive valuations of buildings at the Department of Education (the department) and at the TAFE Commission found that certain assumptions applied in previous years needed to be updated, resulting in prior period restatements.

The department prepaid a building contractor for early works on a project and some of the prepayment is in legal dispute.

The department duplicated a claim for project funding from Restart NSW in 2021.

New parental leave legislation increased employee liabilities for portfolio agencies. The department and the NSW Education Standards Authority (the Authority) updated their financial statements to record parental leave liabilities.

A high risk matter was raised for the Authority to improve the quality and timeliness of information to support their financial statement close process.

What we recommended

Portfolio agencies should ensure any changes to employee entitlements are assessed for their potential financial statements impact under the relevant Australian Accounting Standards.

The department should:

  • improve processes to ensure project claims are not duplicated
  • assess the risks associated with providing prepayments to contractors.

This report provides Parliament and other users of the Education portfolio of agencies’ financial statements with the results of our audits, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision-making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Education portfolio (the portfolio) for 2023.

Section highlights

  • Unqualified audit opinions were issued on all the portfolio agencies 2022–23 financial statements.
  • An ‘other matter’ paragraph was included in the independent auditor’s report for the Technical and Further Education Commission (the TAFE Commission) as it did not have a delegation or sub-delegation from the Minister for Education and Early Learning to incur expenditure on grants from other portfolio agencies.
  • Comprehensive valuations of buildings in the current year identified that certain assumptions applied in previous years were incorrect. The effects of these corrections are disclosed as prior period errors in the financial statements of the Department of Education (the department) and the TAFE Commission.
  • The department made corrections to its financial statements to reflect increases to NSW teachers’ wages announced post balance date. This impacted amounts recorded as liabilities for a range of employee benefits and entitlements totalling $225.4 million, of which $147.9 million is accepted by the Crown and $77.5 million is borne by the department.
  • A change to the NSW paid parental leave scheme, effective October 2022, created a new legal obligation that needed to be recognised by impacted government agencies. Of the three affected portfolio agencies, only the department and the NSW Education Standards Authority recognised a liability to account for this change. The aggregated unrecorded liabilities of other agencies in the portfolio totalled $2.4 million. The errors within the individual agencies’ financial statements were not material.
  • The total number of errors (including corrected and uncorrected) in the financial statements increased compared to the prior year.
  • The NSW Childcare and Economic Opportunity Fund should prepare financial statements unless NSW Treasury releases a Treasurer’s Direction under section 7.8 of the GSF Act that will exempt the SDA from financial reporting requirements. 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision-making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the Education portfolio.

Section highlights

  • The 2022–23 audits identified one high risk and 20 moderate risk issues across the portfolio. Of these, one was a high risk repeat issue and four were moderate risk repeat issues.
  • The total number of findings increased from 29 to 36, which mainly related to deficiencies in financial reporting, information technology, payroll and purchasing controls.
  • The high risk matter relates to the lack of quality and timely information to support the financial statement close process at the NSW Education Standards Authority. 

Appendix one – Early close procedures

Appendix two – Financial data

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Management of the Critical Communications Enhancement Program

Management of the Critical Communications Enhancement Program

Finance
Health
Justice
Whole of Government
Cyber security
Information technology
Infrastructure
Internal controls and governance
Project management
Risk
Service delivery
Shared services and collaboration

What the report is about

Effective radio communications are crucial to NSW's emergency services organisations.

The Critical Communications Enhancement Program (CCEP) aims to deliver an enhanced public safety radio network to serve the five emergency services organisations (ESOs), as well as a range of other users.

This report assesses whether the NSW Telco Authority is effectively managing the CCEP.

What we found

Where it has already been delivered (about 50% of the state), the enhanced network meets most of the requirements of ESOs.

The CCEP will provide additional infrastructure for public safety radio coverage in existing buildings agreed to with ESOs. However, radio coverage inside buildings constructed after the CCEP concludes will be at risk because building and fire regulations do not address the need for in-building public safety radio coverage.

Around 98% of radios connected to the network can be authenticated to protect against cloning, though only 42% are.

The NSW Telco Authority has not settled with ESOs on how call encryption will be used across the network. This creates the risk that radio interoperability between ESOs will not be maximised.

When completed, the public safety radio network will be the only mission critical radio network for ESOs. It is unclear whether governance for the ongoing running of the network will allow ESOs to participate in future network operational decisions.

The current estimated capital cost for the NSW Telco Authority to complete the CCEP is $1.293 billion. This is up from an estimated cost of $400 million in 2016. The estimated capital cost was not publicly disclosed until $1.325 billion was shown in the 2021–22 NSW Budget Papers.

We estimate that the full cost to government, including costs to the ESOs, of implementing the enhanced network is likely to exceed $2 billion.

We made recommendations about

  • The governance of the enhanced Public Safety Network (PSN) to support agency relationships.
  • The need to finalise a Traffic Mitigation Plan for when the network is congested.
  • The need to provide advice to the NSW Government about the regulatory gap for ensuring adequate network reach in future buildings.
  • The need to clarify how encryption and interoperability will work on the enhanced network.
  • The need for the NSW Telco Authority to comply with its policy on Infrastructure Capacity Reservation.
  • Expediting measures to protect against the risk of cloning by unauthenticated radios.

Public safety radio networks are critical for operational communications among Emergency Services Organisations (ESOs), which in New South Wales include:

  • NSW Ambulance
  • Fire and Rescue NSW
  • NSW Police Force
  • NSW Rural Fire Service
  • NSW State Emergency Service.1

Since 1993, these five ESOs have had access to a NSW Government owned and operated radio communications network, the Public Safety Network (PSN), to support their operational communications. Around 60 to 70 other entities also have access to this network, including other NSW government entities, Commonwealth government entities, local councils, community organisations, and utility companies.

Pursuant to the Government Telecommunications Act 2018 ('the Act'), the New South Wales Government Telecommunications Authority ('NSW Telco Authority') is responsible for the establishment, control, management, maintenance and operation of the PSN.2

Separate to the PSN, all ESOs and other government entities have historically maintained their own radio communication capabilities and networks. Accordingly, the PSN has been a supplementary source of operational radio communications for these entities.

These other radio networks maintained by ESOs and other entities are of varying size and capability, with many ageing and nearing their end-of-life. There was generally little or no interoperability between networks, infrastructure was often co-located and duplicative, and there were large gaps in geographic coverage.

In 2016, the NSW Telco Authority received dedicated NSW Government funding to commence the Critical Communications Enhancement Program (CCEP).

According to NSW Telco Authority's 2021–22 annual report, the CCEP is a transformation program for operational communications for NSW government agencies. The CCEP '…aims to deliver greater access to public safety standard radio communications for the State’s first responders and essential service agencies'. The objective of CCEP is to consolidate the large number of separate radio networks that are owned and operated by various NSW government entities and to enhance the state’s existing shared PSN. The program also aims to deliver increased PSN coverage throughout New South Wales.

The former NSW Government intended that as the enhanced PSN was progressively rolled-out across NSW, ESOs would migrate their radio communications to the enhanced network, before closing and decommissioning their own networks.

About this Audit

This audit assessed whether the CCEP is being effectively managed by the NSW Telco Authority to deliver an enhanced PSN that meets ESOs' requirements for operational communications.

We addressed the audit objective by answering the following two questions:

  1. Have agreed ESO user requirements for the enhanced PSN been met under day-to-day and emergency operational conditions?
  2. Has there been adequate transparency to the NSW Government and other stakeholders regarding whole-of-government costs related to the CCEP?

In answering the first question, we also considered how the agreed user requirements were determined. This included whether they were supported by evidence, whether they were sufficient to meet the intent of the CCEP (including in considering any role for new or alternative technologies), and whether they met any relevant technical standards and compliance obligations (including for cyber security resilience).

While other NSW government agencies and entities use the PSN, we focused on the experience of the five primary ESOs because these will be the largest users of the enhanced PSN.

Both the cost and time required to complete the CCEP roll-out have increased since 2016. While it was originally intended to be completed in 2020, this is now forecast to be 2027. Infrastructure NSW has previously assessed the reasons for the increases in time and cost. A summary of the findings made by Infrastructure NSW is presented in Chapter 1 of this report. Accordingly, as these matters had already been assessed, we did not re-examine them in this performance audit.

The auditee for this performance audit is the NSW Telco Authority, which is a statutory authority within the Department of Customer Service portfolio.

In addition to being responsible for the operation of the PSN, section 5 of the Act also prescribes that the NSW Telco Authority is:

  • to identify, develop and deliver upgrades and enhancements to the government telecommunications network to improve operational communications for government sector agencies
  • to develop policies, standards and guidelines for operational communications using telecommunications networks.

The NSW Telco Authority Advisory Board is established under section 10 of the Act. The role of the board is to advise the NSW Telco Authority and the minister on any matter relating to the telecommunications requirements of government sector agencies and on any other matter relating to the functions of the Authority. As of 2 June 2023, the responsible minister is the Minister for Customer Service and Digital Government.

The five identified ESOs are critical stakeholders of the CCEP and therefore they were consulted during this audit. However, the ESOs were not auditees for this performance audit.

Conclusion

In areas of New South Wales where the enhanced Public Safety Network has been implemented under the Critical Communications Enhancement Program, the NSW Telco Authority has delivered a radio network that meets most of the agreed requirements of Emergency Services Organisations for routine and emergency operations.
In April 2023, the enhanced Public Safety Network (PSN) was approximately 50% completed. In areas where it is used by Emergency Services Organisations (ESOs), the PSN generally meets agreed user requirements. This is demonstrated through extensive performance monitoring and reporting, which shows that agreed performance standards are generally achieved. Reviews by the NSW Government and the NSW Telco Authority found that the PSN performed effectively during major flood events in 2021 and 2022.

Where it is completed, PSN coverage is generally equal to or better than each ESO's individual pre-existing coverage. The NSW Telco Authority has a dedicated work program to address localised coverage gaps (or 'blackspots') in those areas where coverage has otherwise been substantively delivered. Available call capacity on the network far exceeds demand in everyday use. Any operational issues that may occur with the PSN are transparent to ESOs in real time.

The NSW Telco Authority consulted extensively with ESOs on requirements for the enhanced PSN, with relatively few ESO requirements not being included in the specifications for the enhanced PSN. Lessons from previous events, including the 2019–20 summer bushfires, have informed the design and implementation of the enhanced PSN (such as the need to ensure adequate backup power supply to inaccessible sites). The network is based on the Project 25 technical standards for mission-critical radio communications, which is widely-accepted in the public safety radio community throughout Australia and internationally.

There is no mechanism to ensure adequate radio coverage within new building infrastructure after the CCEP concludes, but the NSW Telco Authority and ESOs have agreed an approach to prioritise existing in-building sites for coverage for the duration of the CCEP.
The extent to which the PSN works within buildings and other built structures (such as railway tunnels) is of crucial importance to ESOs, especially the NSW Police Force, NSW Ambulance, and Fire and Rescue NSW. This is because a large proportion of their operational communications occurs within buildings.

There is no mechanism to ensure the adequacy of future in-building coverage for the PSN in new or refurbished buildings after the CCEP concludes. Planning, building, and fire regulations are silent on this issue. We note there are examples in the United States of how in-building coverage for public safety radio networks can be incorporated into building or fire safety codes.

In regard to existing buildings, it is not possible to know whether a building requires its own in-building PSN infrastructure until nearby outside radio sites, including towers and antennae, have been commissioned into the network. Only then can it be determined whether their radio transmissions are capable of penetrating inside nearby buildings. Accordingly, much of this work for in-building coverage cannot be done until outside radio sites are finished and operating.

In March 2023, the NSW Telco Authority and ESOs agreed on a list of 906 mandatory and 7,086

non-mandatory sites for in-building PSN coverage. Most of these sites will likely be able to receive radio coverage via external antennae and towers, however this cannot be confirmed until those nearby external PSN sites are completed. The parties also agreed on an approach to prioritising those sites where coverage is needed but not provided by antennae and towers. Available funding will likely only extend to ensuring coverage in sites deemed mandatory, which is nonetheless expected to meet the overall benchmark of achieving 'same or better' coverage than what ESOs had previously.

There is a risk that radio interoperability between ESOs will not be maximised because the NSW Telco Authority has not settled with ESOs how encryption will be used across the enhanced PSN.
End-to-end encryption of radio transmissions is a security feature that prevents radio transmissions being intercepted or listened to by people who are not meant to. The ability of the PSN to provide end-to-end encryption of operational communications is of critical importance to the two largest prospective users of the PSN: the NSW Police Force and NSW Ambulance. Given that encryption excludes other parties that do not have the requisite encryption keys, its use creates an obstacle to achieving a key intended benefit of the CCEP, that is a more interoperable PSN, where first responders are better able to communicate with other ESOs.

Further planning and collaboration between PSN participants are necessary to consider how these dual benefits can be achieved, including in what operational circumstances encrypted interoperability is necessary or appropriate.

The capital cost to the NSW Telco Authority of the CCEP, originally estimated at $400 million in 2016, was not made public until the 2021–22 NSW Budget disclosed an estimate of $1.325 billon.
The estimated capital cost to complete all stages of the CCEP increased over time. This increasing cost was progressively disclosed to the NSW Government through Cabinet processes between 2015–16 and 2021–22.

In 2016, the full capital cost to the NSW Telco Authority of completing the CCEP was estimated to be $400 million. This estimated cost was not publicly disclosed, nor were subsequent increases, until the cost of $1.325 billion was publicly disclosed in the 2021–22 NSW Budget (revised down in the 2022–23 NSW Budget to $1.293 billion).

There has been no transparency about the whole-of-government cost of implementing the enhanced PSN through the CCEP.
In addition to the capital costs incurred directly by the NSW Telco Authority for the CCEP, ESOs have incurred costs to maintain their own networks due to the delay in implementing the CCEP. The ESOs will continue to incur these costs until they are able to fully migrate to the enhanced PSN, which is expected to be in 2027. These costs have not been tracked or reported as part of transparently accounting for the whole-of-government cost of the enhanced PSN. This is despite Infrastructure NSW in 2019 recommending to the NSW Telco Authority that it conduct a stocktake of such costs so that a whole-of-government cost impact is available to the NSW Government.

1 The definition of 'emergency services organisation' is set out in the State Emergency and Rescue Management Act 1989 (NSW). In addition to the five ESOs discussed in this report, the definition also includes: Surf Life Saving New South Wales; New South Wales Volunteer Rescue Association Inc; Volunteer Marine Rescue NSW; an agency that manages or controls an accredited rescue unit; and a non-government agency that is prescribed by the regulations for the purposes of this definition.
2 Section 15(1) of the Government Telecommunications Act 2018 (NSW).

The NSW Telco Authority established and tracked its own costs for the CCEP

Over the course of the program from 2016, the NSW Telco Authority prepared a series of business cases and program reviews that estimated its cost of implementing the program in full, including those shown in Exhibit 6 below.

Exhibit 6: Estimated costs to fully implement the CCEP
Source Capital cost ($ million) Operating cost
($ million)
Completion date
March 2016 business case 400 37.3 2020
November 2017 internal review 476.7 41.7 2022
March 2020 business case 950–1,050 -- 2025
October 2020 business case 1,263.1 56.1 2026

Source: CCEP business cases as identified.

In response to the 2016 CCEP business case, the then NSW Government approved the NSW Telco Authority implementing the CCEP in full, with funding provided in stages. The NSW Telco Authority tracked its costs against approved funding, with monthly reports provided to the multi-agency Program Steering Committee

Throughout the program, the NSW Government was informed of increasing costs being incurred by the NSW Telco Authority for the CCEP

The various business cases, program updates, and program reviews prepared by the NSW Telco Authority were provided to the NSW Government through the required Cabinet process when seeking approval for the program proceeding and requests for both capital and operational funding. These provided clear indication of the changing overall cost of the CCEP to the NSW Telco Authority, as well as the delays that were being experienced.

There was no transparency to the Parliament and community about changes in the capital cost of the CCEP until the 2021–22 NSW Budget

As the business cases for the CCEP were not publicly available, the only sources of information about capital cost were NSW Budget papers and media releases. The information provided in the annual Budget papers prior to the 2021–22 NSW Budget provided no visibility of the estimated full capital cost to complete all stages of the CCEP. As shown in Exhibit 7 below, this information was fragmented and complex.

Media releases about the progress of the CCEP did not provide the estimated total cost to the NSW Telco Authority of $1.325 billion to complete all stages of the CCEP until June 2021. Prior to this date, media releases only provided funding for the initial stages of the program or for the stages subject to a funding announcement.

Even during the September 2019 and March 2020 Parliamentary Estimate Committee hearings where the costings and delays to the CCEP were raised, the estimated full cost of the CCEP was not revealed.

Exhibit 7: CCEP funding in NSW Budget papers from 2015–16 to 2022–23
Financial year Type of major work Description of expenditure Forecast estimate to complete ($ million) Estimated duration
2015–16 New work Infrastructure Rationalisation Program: Planning and Pilot 18.3 2015–16
2016–17 Work in progress CCEP Planning and Pilot 18.3 2015–17
New work CCEP 45 2016–17
2017–18 New work CCEP 190.75 2017–21
2018–19 Work in progress CCEP North Coast and State-wide Detailed Design 190.75 2017–21
New work CCEP Greater Metropolitan Area 236 2018–22
2019–20 Work in progress CCEP 426.9 2018–22
2020–21 Work in progress CCEP 664.8 2018–22
2021–22 Work in progress CCEP 1,325 2018–26
2022–23 Work in progress CCEP 1,292.8 2018–26

Source: NSW Treasury, Annual State Budget Papers.

The original business case for the CCEP included estimated ESO costs, though these costs were not tracked throughout the program

Estimates for ESO costs for operating and maintaining their own radio networks over the four years from 2016–17 were included in the original March 2016 business case. They included $75.2 million for capital expenditure and $95 million for one-off operating costs. These costs, as well as costs incurred by ESOs due to the delay in the program, were not subsequently tracked by the NSW Telco Authority.

In January 2017, Infrastructure NSW reviewed the CCEP business case of March 2016. In this review, Infrastructure NSW recommended that the NSW Telco Authority identify combined and apportioned costs and cashflow for all ESOs over the CCEP funding period reflecting all associated costs to deliver the CCEP. These to include additional incidental capital costs accruing to ESOs, transition and migration to the new network and the cost (capital and operational) of maintaining existing networks. This recommendation was implemented in the November 2017 program review, with ESO capital costs estimated as $183 million.

In 2019, Infrastructure NSW conducted a Deep Dive Review on the progress of the CCEP. In this review, Infrastructure NSW made what it described as a 'critical recommendation' that the NSW Telco Authority:

…coordinate a stocktake of the costs of operational bridging solutions implemented by PSAs [ESOs] as a result of the 18-month delay, so that a whole-of-government cost impact is available to the NSW Government.  

It should be noted that the delay to CCEP completion now is seven years and that further ‘operational bridging solutions’ have been needed by the ESOs.

'Stay Safe and Keep Operational' costs incurred by ESOs will be significantly higher than originally estimated

Stay Safe and Keep Operational (SSKO) funding was established to provide funding to ESOs to maintain their legacy networks while the CCEP was refreshing and enhancing the PSN. This recognised that much of the network infrastructure relied on by ESOs had reached – or was reaching – obsolescence and would either require extensive maintenance or replacement before the PSN was available for ESOs to migrate to it. ESOs may apply to NSW Treasury for SSKO funding, with their specific proposals being reviewed (and endorsed, where appropriate) by the NSW Telco Authority. Accordingly, SSKO expenditure does not fall within the CCEP budget allocation.

As shown in the table below, extracted from the March 2016 CCEP business case, the total expected cost for SSKO purposes over the course of the CCEP was originally $40 million, assuming the enhanced PSN would be fully available by 2020.

Exhibit 8: Stay Safe and Keep Operational forecast costs, 2017 to 2020
Year 2017 2018 2019 2020 Total
SSKO forecast ($ million) 12.5 15 10 2.5 40

Source: March 2016 CCEP business case.

In October 2022, the expected completion date for the CCEP was re-baselined to August 2027. Accordingly, ESOs will be required to continue to maintain their radio networks using legacy equipment for seven years longer than the original 2020 forecast. This will likely become progressively more expensive and require additional SSKO funding. For example, NSW Telco Authority endorsed SSKO bids for 2022–23 exceeded $35 million for that year alone.

Compared to the original forecast made in the March 2016 CCEP business case of $40 million, we found ESOs had estimated SSKO spending to 2027 will be $292.5 million.

A refresh of paging network used by ESOs and the decommissioning of redundant sites were both removed from the original 2016 scope of the CCEP

Paging

A paging network is considered an important user requirement by the Fire and Rescue NSW, NSW Rural Fire Service, and NSW State Emergency Service. The 2016 CCEP business case included a paging network refresh within the program scope of works. This was reiterated in the November 2017 internal review of the program. These documents did not estimate a cost for this refresh. The March 2020 and October 2020 business cases excluded paging from the program scope. The audit is unable to identify when, why or by whom the decision was made to remove paging from the program scope, something that was also not well communicated to the affected ESOs.

In 2021, after representations from the affected ESOs, the NSW Telco Authority prepared a separate business case for a refresh of the paging network at an estimated capital cost of $60.31 million. This program was subsequently approved by the NSW Government and included in the 2022–23 NSW Budget.

In determining an estimated full whole-of-government cost of delivering the enhanced PSN, we have included the budgeted cost of the paging network refresh on the basis that:

  • it was expressly included in the original approved March 2016 business case
  • the capability is deemed essential to the needs of three ESOs.

Decommissioning costs

The 2016 CCEP business case included cost estimates for decommissioning surplus sites (whether ‘old’ GRN sites or sites belonging to ESOs’ own networks). These estimates were provided for both the NSW Telco Authority ($38 million) and for the ESOs ($55 million). However, while these estimates were described, they were not included as part of the NSW Telco Authority's estimated capital cost ($400 million) or (more relevantly) operating cost ($37.3 million) for the CCEP. This is despite decommissioning being included as one of eight planned activities for the rollout of the program.

In the October 2020 business case, an estimate of $201 million was included for decommissioning agency networks based on a model whereby:

  • funding would be coordinated by the NSW Telco Authority
  • scheduling and reporting through an inter-agency working group and
  • where appropriate, agencies would be appointed as the most appropriate decommissioning party.

This estimated cost is not included in the CCEP budget.

In determining an estimated full whole-of-government cost of the enhanced PSN, we have included the estimated cost of decommissioning on the basis that:

  • decommissioning was included in the 2016 CCEP business case as one of eight 'planned activities for the rollout of the program'
  • effective decommissioning of surplus sites and equipment (including as described in the business case as incorporating asset decommissioning, asset re-use, and site make-good) is an inherent part of the program management for an enhanced PSN
  • costs incurred in decommissioning are entirely a consequence of the CCEP program.

The estimated minimum cost of building an enhanced PSN consistent with the original proposal is over $2 billion

We have derived two estimated minimum whole-of-government costs for delivering an enhanced PSN. These are:

  • $2.04 billion when calculated from NSW Telco Authority data – shown as estimate A in Exhibit 9 below.
  • $2.26 billion when calculated from ESO supplied data – shown as estimate B in Exhibit 9.

Both totals include:

  • budgeted amounts for both CCEP capital expenditure ($1,292.8 million) and operating expenditure ($139 million)
  • the NSW Telco Authority's 2020 estimated cost for decommissioning ($201 million)
  • the NSW Telco Authority's approved funding for paging refresh ($60.3 million).

The two estimated totals primarily vary around the capital expenditure of ESOs (particularly SSKO funding). To determine these costs, we used ESO provided actual SSKO costs to date, as well as their estimates for maintaining their legacy radio networks through to 2027.

The equivalent cost estimates from the NSW Telco Authority were sourced from the November 2017 internal review and the October 2020 business case for CCEP. It should be noted that the amounts for both estimates are not audited, or verified, but do provide an indication of how whole-of-government costs have grown over the course of the program.

The increase in and reasons for the increase in total CCEP costs (capital and one-off operating) incurred or forecast by the NSW Telco Authority (from $437.3 million in 2016 to $1,431.8 million in 2022) have been provided to the NSW Government through various business cases and reviews prepared by the NSW Telco Authority, as well as by reviews conducted by Infrastructure NSW as part of its project assurance responsibilities.

However, the growth in ESO costs and other consequential costs, such as paging and decommissioning, from around $263 million in the 2016 CCEP business case to between $600 million and $800 million, has to a large degree remained invisible and unexplained to the NSW Government and other stakeholders

Exhibit 9: Estimated whole-of-government costs of the enhanced PSN
  Estimated whole-of-government cost, over time
Cost type 20161 20172 20203 2023–Estimate A4 2023–Estimate B5
$ million $ million $ million $ million $ million
CCEP capital expenditure 400a 476.7b 1,263.1c 1,292.8d 1,292.8d
CCEP operating expenditure 37.3a 41.7b 41.5e 139d 139d
CCEP total 437.3 518.4 1,304.6 1,431.8 1,431.8
ESO capital expenditure 75.2a,f 183b,e 75.4e 258.4g 292.5
ESO one-off operating expenditure 93a n.a.l 86.5e 86.5h 273
ESO total 168.2 183 161.9 344.9 565.5
Paging n.a.i n.a.i n.a.j 60.3k 60.3k
Decommissioning 93 n.a.l 201.0 201h 201
Paging and decommissioning total 93 n.a. 201 261.3 261.3
Whole-of-government total 698.5 701.4 1,667.5 2,038 2,258.6

Notes:
  1. Financial year 2016 to Financial year 2020.
  2. Financial year 2016 to Financial year 2021.
  3. Financial year 2016 to Financial year 2025.
  4. Financial year 2016 to Financial year 2026.
  5. Financial year 2022 to Financial year 2025.
  6. Stay Safe and Keep Operational (SSKO) costs plus terminals costs.
  7. November 2017 internal review and October 2020 Business case.
  8. October 2020 Business case.
  9. Included in CCEP capital expenditure at that time.
  10. By 2020, a refresh of the paging network had been removed from the CCEP scope.
  11. A separate business case for a refresh of the paging network was approved by government in 2022.
  12. Figure not included in the source document.
Sources:
  1. March 2016 CCEP business case.
  2. November 2017 Internal Review conducted by the NSW Telco Authority.
  3. October 2020 CCEP business case.
  4. Derived from business cases, with ESO costs drawn from NSW Telco Authority data.
  5. Derived from business cases, with ESO costs based on data provided to the Audit Office of New South Wales by each of the five ESOs.

Appendix one – Response from agency

Appendix two – Trunked public safety radio networks

Appendix three – About the audit

Appendix four – Performance auditing

 

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #383 - released 23 June 2023