Actions for State Finances 2022

State Finances 2022

Treasury
Whole of Government
Asset valuation
Compliance
Cyber security
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Regulation
Risk

What the report is about

Results of the 2021–22 consolidated General Government Sector (GGS) and Total State Sector (TSS) financial statements audits.

What we found

The Independent Auditor’s Report on the 2021–22 GGS and TSS financial statements was modified with a limitation of scope and also contained an emphasis of matter.

The opinion in the TSS Independent Auditor’s Report was modified with a limitation of scope on certain balances consolidated in the TSS financial statements because the Catholic Metropolitan Cemeteries Trust (CMCT) denied access to its management, books and records for the purpose of conducting a financial audit.

The Independent Auditor’s Report also includes an emphasis of matter drawing attention to the significant uncertainties associated with the GGS’s equity investment in Transport Asset Holding Entity (TAHE). The significant uncertainty relates to key assumptions and estimates used to forecast a 2.5% return from GGS investments into TAHE that supports the accounting treatment as an equity injection, including:

  • funding to support the Rail Operators to pay TAHE’s contracted and forecast access and licence fees up until 2045–46. The Rail Operators are dependent on funding from the GGS to pay access and licence fees. Forecast modelling notes a requirement of a further $10.2 billion in budget funding to pay TAHE to the end of the ten-year contract period in 2030–31, in addition to the $5.5 billion allocated in the forward estimates and up to $50.8 billion for the period 2032 to 2046
  • a significant portion of the projected returns are earnt outside of the ten-year contract period and there is a risk that TAHE may not be able to recontract fees at levels consistent with current projections.

What we recommended

The report includes a number of recommendations including:

  • continued monitoring that TAHE controls the reported assets ensuring the CMCT, Category 2 Statutory Land Managers (SLM) and Commons Trusts meet their statutory reporting obligations
  • ensuring accounting and audit position papers are sufficiently consulted with key stakeholders and are concluded on a timely basis
  • ensuring agencies support the timely conclusion of audits by bringing to the auditors' attention key Cabinet records and identifying references relating to accounting issues impacting the financial statements
  • for Special Deposit Accounts (SDA) responsible managers should ensure amounts appropriated under any Act or law for payment into the account are appropriately recorded, ensuring payments from SDAs are allowable and made in accordance with Treasurer's delegations and standing authorisation.
Image
Margaret Crawford, Auditor-General for New South Wales

Pursuant to section 52A of the Government Sector Audit Act 1983 I am pleased to present my Auditor-General’s Report on State Finances 2022.

Once again this year has presented considerable challenges for the state sector and my Office as we collectively grapple with uncertainties related to COVID-19 and the disruption of emergency events impacting New South Wales. In addition, there were many recommendations arising from last year’s audit to be addressed.

While there is more to do to ensure good financial stewardship of the State, resolution of matters was helped by constructive engagement with the NSW Treasury at the most senior levels. Personally I wish to thank the Treasurer and Secretary for their commitment to instilling integrity in financial management systems and processes. The support Treasury provided for recent amendments to the Government Sector Audit Act 1983 to provide ‘follow the dollar’ powers and other changes recommended by the Public Accounts Committee quadrennial review of my Office is also acknowledged.

Finally I want to thank the teams that contributed to this year’s audit of the Total State Accounts for their diligence, professionalism and commitment. I am very proud of your work.

Margaret Crawford

Auditor-General for New South Wales

The Independent Auditor's Report was qualified and also included an emphasis of matter

The audit opinion on the State's 2021–22 financial statements was modified. The delayed signing of the NSW Total State Sector Accounts (TSSA) by NSW Treasury was in order to resolve significant accounting issues that were material to the TSSA. The key areas requiring significant audit effort included reviewing the State's accounting for TCorp Investment Management (IM) Funds and responding to the risks related to the Catholic Metropolitan Cemeteries Trust (CMCT) denying access to its management and books and records, which is detailed in this Report.

NSW Treasury aimed to sign the TSSA by 19 October 2022. This was delayed by nearly six weeks and the TSSA audit opinion was subsequently signed on the statutory deadline imposed on the Treasurer for tabling of the TSSA in the Legislative Assembly of 30 November 2022.

The Independent Auditor’s Report was modified due to a limitation of scope on the balances consolidated in the TSSA relating to the CMCT

The opinion in the Independent Auditor’s Report was modified with a limitation of scope due to the inability to access management, books and records of a controlled entity, the CMCT.

This year, NSW Treasury, after reconsidering all facts and the perspectives of the CMCT, reconfirmed that the CMCT is a controlled entity of the State for financial reporting purposes. This means CMCT is a GSF agency under the provisions of the Government Sector Finance Act 2018 (GSF Act). As such NSW Treasury is required by Australian Accounting Standards to consolidate the CMCT into the Total State Sector Accounts (TSSA). The value of assets and liabilities of CMCT consolidated into the TSSA is $310.3 million and $15.1 million, respectively, and the loss of CMCT consolidated into the TSSA for the year is $2.4 million.

To date, CMCT has not met its statutory obligations to prepare financial statements under the GSF Act and give them to the Auditor-General. CMCT has not submitted its financial statements to the Auditor-General for audit as required despite repeated requests and has not provided access to its books and records for the purposes of a financial audit. The Secretary of the Department of Planning and Environment wrote to CMCT to request it work with, and offer full assistance to, the Auditor-General in the exercise of her duties.

NSW Treasury has met with and considered CMCT's perspectives. NSW Treasury’s position remains that CMCT is a controlled entity of the State for financial reporting purposes. Consequently, CMCT has not met its statutory obligations as a controlled entity to submit its financial statements for audit and provide access to its books and records. Therefore, the Audit Office was unable to obtain sufficient appropriate audit evidence about the carrying amount of assets and liabilities consolidated into the Total State Sector Accounts as at 30 June 2022 and of the amount of income and expenses for the year then ended. Accordingly a modified audit opinion was issued on the NSW Government's 2021–22 consolidated financial statements.

Section 3 of this report titled 'Limitation of Scope relating to CMCT' discusses this matter in further detail.

An emphasis of matter drawing attention to uncertainty relating to the General Government Sector's investment in the Transport Asset Holding Entity (TAHE) remains

The Independent Auditor’s Report also includes an emphasis of matter, drawing attention to the significant uncertainties associated with the General Government Sector's (GGS) equity investment in TAHE. The significant uncertainty relates to key assumptions used to forecast returns from investments into TAHE in order to support the recognition of the government's funding of TAHE as an equity injection.

At the time of signing the Independent Auditor's Report, there was significant uncertainty with regards to assumptions and estimates used to forecast a return from the GGS investment into TAHE, which supports the recognition of an equity injection. There is significant uncertainty relating to:

  • the 2022–23 Budget committed $5.5 billion to fund TAHE's key customers, Sydney Trains and NSW Trains (the operators), to support their payment of access and licence fees agreed on 23 June 2022. However, this funding only extends out to the end of the forward estimates period in 2025–26, which falls short of the ten-year contractual periods to 2030–31 and the projected period to 2045–46 to achieve a 2.5% return from the government's equity investment. The government will need to fund the operators an additional $10.2 billion in Budget funding so that they can meet their contractual obligations to TAHE from 2026–27 to 2030–31, and a further projected funding of $50.8 billion from 2031 to 2046. This additional funding is not within the government's published Budget figures, leading to uncertainty on whether the government-funded operators can pay access and licence fees beyond the forward estimates period of 2025–26
  • a significant portion of the projected returns are earnt outside the ten-year contract period (terminating 30 June 2031) and there is a risk that TAHE will not be able to recontract for access and licence fees at a level that is consistent with current projections. There is also a risk that funding for TAHE's key customers will not be sufficient to fund payment of access and licence fees at a level that is consistent with current projections.

The 'State Finances 2021' report made recommendations regarding the significant accounting issues relating to TAHE. The State's response to these recommendations are detailed in Section 4 of this report titled ‘Investment in the Transport Asset Holding Entity’. Other significant matters related to the TSSA audit are covered in Section 8 titled ‘Key audit findings’.

Other financial reporting matters

All government agencies were granted an extra week to submit financial statements for audit

A one-week extension provided agencies across the sector with additional time to resolve key accounting issues and submit financial statements for audit by 1 August 2022.

Further extensions were approved for the following seven agencies (ten in 2020–21):

  • State Insurance Regulatory Authority (3 August 2022)
  • Dams Safety NSW (8 August 2022)
  • Jenolan Caves Reserve Trust (8 August 2022)
  • Transport for NSW (8 August 2022)
  • Department of Enterprise, Investment and Trade (22 August 2022)
  • Transport Asset Holding Entity (22 August 2022)
  • Department of Transport (26 August 2022).

Additional extensions provided agencies with more time to complete:

  • asset valuations
  • valuations of actuarially assessed liabilities.

An initial draft of the TSSA was provided to audit on 15 September 2022. This version was incomplete and excluded the impact of consolidating the State's TCorp IM funds under the correct Australian Accounting Standards. An additional three versions of the draft TSSA were provided to audit progressively to update the TCorp IM fund consolidated balances. The final complete version of the TSSA was submitted on 27 October 2022 which included all adjustments relating to the TCorp IM fund consolidation. Refer to section 8.1 for more details on the material restatements relating to the consolidation of the TCorp IM funds.

In 2021–22, agency financial statements presented for audit contained 20 errors exceeding $20 million (24 in 2020–21). The total value of these errors was $973 million, a decrease from the previous year ($6.6 billion in 2020–21).

The graph below shows the number of reported errors exceeding $20 million over the past five years in agencies’ financial statements presented for audit.

The errors resulted from:

  • incorrect application of Australian Accounting Standards and NSW Treasury policies
  • incorrect judgements and assumptions when valuing non-current physical assets and liabilities.

NSW Treasury concluded CMCT is a controlled entity of the State

In response to our recommendation in the ‘State Finances 2021’ report, NSW Treasury reconfirmed that the Catholic Metropolitan Cemeteries Trust (CMCT) is a controlled entity of the State. The Audit Office accepted the position of NSW Treasury.

The reaffirmation of this position means CMCT is a GSF agency under the provisions of the Government Sector Finance Act 2018 (GSF Act). Section 7.6 of the GSF Act places an obligation on CMCT to prepare financial statements and give them to the Auditor-General. Further, section 34 of the Government Sector Audit Act 1983 (the GSA Act) requires the Auditor-General to furnish an audit report on these financial statements.

To date, CMCT has not met its statutory obligations to prepare financial statements under the GSF Act and give them to the Auditor-General. CMCT has not submitted their financial statements to the Auditor-General for audit despite repeated requests and has not provided access to its books and records for the purposes of a financial audit. There was extensive correspondence between the Audit Office of NSW, CMCT, NSW Treasury and the Department of Planning and Environment in 2022 regarding this matter.

Recommendation

NSW Treasury and the Department of Planning and Environment should ensure the Catholic Metropolitan Cemeteries Trust meets its statutory reporting obligations.

In addition, on 10 December 2021, the then Minister for Water, Property and Housing wrote to the Auditor-General requesting a financial and performance audit be performed pursuant to section 27B(3)(c) of the GSA Act. The audit would cover the financial affairs of CMCT, including whether funds have been used for the proper purpose. The Audit Office of New South Wales has written to CMCT on a number of occasions to request the provision of documentation and access to management in order to conduct the performance audit. CMCT has not provided the Audit Office of New South Wales access to its management, books and records for the purpose of the required performance audit.

NSW Treasury has met with and considered CMCT's perspectives. NSW Treasury’s position remains that CMCT is a controlled entity of the State for financial reporting purposes. Consequently, CMCT did not meet its statutory obligations as a controlled entity to submit its financial statements for audit and provide access to its books and records.

The TSSA audit opinion included a limitation of scope

The opinion in the TSSA Independent Auditor’s Report was modified with a limitation of scope due to an inability to access management and the books and records of CMCT. This limitation was appropriately disclosed in Note 1 'Statement of Significant Accounting Policies' of the TSSA. The Statement of Compliance signed by the Secretary of Treasury and the Treasurer on 29 November 2022 was also updated to acknowledge the disclosure in Note 1 regarding CMCT.

The Audit Office was unable to obtain sufficient appropriate audit evidence about the carrying amount of assets and liabilities consolidated into the Total State Sector Accounts as at 30 June 2022 and of the amount of income and expenses for the year then ended. Accordingly a modified audit opinion was issued on the NSW Government's 2021–22 consolidated financial statements.

The process of information sharing by NSW Treasury continues to require improvement

In last year’s ‘State Finances 2021’ report an extreme risk management letter finding was reported for NSW Treasury to ensure it significantly improve its processes so that all relevant information is identified and shared with the Audit Office to support material transactions and balances of the State.

A number of events reconfirmed that NSW Treasury needs to continue improving its process with respect to information sharing with the Audit Office. Notably, NSW Treasury’s finance team had not demonstrated that all available information (on their systems) was considered by them when assessing the State’s control over CMCT.

Critical information relating to CMCT was in the possession of NSW Treasury since late October 2021 but not considered when reconfirming their accounting position on the State's control of CMCT this year. A further reconfirmation of the State's control over CMCT was needed by NSW Treasury to ensure this information was considered in their accounting assessment.

The above demonstrates that more effective consultation is required by NSW Treasury with key stakeholders to ensure all information relevant to forming an accounting position relating to the TSSA is captured. This will ensure new information is not identified late in the audit process and NSW Treasury considers all information when concluding on the accounting position of the State.

Recommendation

NSW Treasury should ensure when drafting position papers and concluding on accounting issues impacting the State, these are provided to audit on a timely basis and reflect a complete and accurate understanding of the key public sector issues being considered.

Last year's report highlighted that NSW Government actions avoided a qualified opinion in 2020–21 relating to the General Government Sector's $2.4 billion cash contribution to Transport Asset Holding Entity (TAHE). These actions included the NSW Government agreeing to provide additional future funding to TAHE's key government customers Sydney Trains and NSW Trains (the operators) to support increases in access and licence fees to be paid to TAHE.

The additional funding by the government was necessary to demonstrate that a reasonable expectation of a sufficient rate of return would be earned on its equity invested in TAHE. Last year, there was no government policy on what the minimum return should be on investments in other public sector entities, so the long-term inflation rate was used as a benchmark. A recommendation was made in last year's State Finances report that NSW Treasury establish a policy on the minimum expected return from its investments.

On 6 September 2022, NSW Treasury finalised its policy relating to the government’s returns on equity investments. The application of this policy is limited to State Owned Corporations and similar to the Commonwealth framework for commercial businesses, which requires the expected return be at least equal to the long-term inflation rate.

The government's commitment to additional funding was conveyed last year through revised shareholder expectations being published in the 2021–22 'NSW Budget-Half yearly Review' on 16 December 2021, increasing the expected returns on equity from 1.5% to the expected long-term inflation rate of 2.5%. On 18 December 2021, Transport for NSW (TfNSW) and the operators entered into a Heads of Agreement (HoA). This formed the basis of negotiations to revise the pricing within the existing ten-year contracts and deliver upon the shareholders’ expected return of 2.5% on contributed equity to be earned over the estimated weighted average remaining useful lives of TAHE's assets.

Further information on last year's audit of the government’s investment in TAHE can be found in our 'State Finances 2021' report.

Ten-year commercial agreements were signed between TAHE, operators and TfNSW

Last year's State Finances report recommended that NSW Treasury facilitate revised commercial agreements to reflect the access and licence fees detailed in the HoA. As these agreements were not executed by 30 June 2021, last year's audit opinion of the Total State Sector Accounts (TSSA) included an Emphasis of Matter drawing attention to the uncertainty that existed at balance date as these agreements were not finalised.

On 23 June 2022, commercial agreements were signed between TAHE, the operators and Transport for NSW through a deed of variation. The revised access and licence fees for the ten-year period 2021–22 to 2030–31 was $16.6 billion, which is $520 million less than the HoA fees of $17.1 billion.

Comparison FY22
$m
FY23
$m
FY24
$m
FY25
$m
FY26
$m
FY27
$m
FY28
$m
FY29
$m
FY30
$m
FY31
$m
Total
$m
Revised commercial agreements 641.1 911.8 1,298.1 1,585 1,807.3 1,921.8 1,992 2,065.4 2,139.1 2,252.8 16,614.4
HoA 679.9 1,081.4 1,236 1,398.9 1,645.8 1,826.1 2,023.3 2,209.4 2,404.5 2,629.2 17,134.6
Difference (38.8) (169.6) 62.1 186.1 161.5 95.7 (31.3) (144) (265.4) (376.4) (520.2)

TAHE's main customers principally rely on government funding to pay access and licence fees

Whilst TAHE has agreed ten-year access and licence fees of $16.6 billion with its two main customers Sydney Trains and NSW Trains, these two operators significantly rely on government funding when making these payments to TAHE. At 30 June 2022, TAHE's expected return of 2.5% is contingent upon the GGS funding the operators to support their payment of access and licence fees that have been agreed with TAHE for the ten-year contracted period and for non-contracted periods from 2031–32 to 2045–46.

The 2022–23 NSW Budget has allocated $5.5 billion to fund the operators, to support their payment of access and licence fees. However, this funding extends to the end of the forward estimates period in 2025–26, which falls short of the ten-year contractual period to 2030–2031 and the projected period to 2045–46 to achieve the 2.5% return.

  2022–261
$b
2027–20312
$b
2032–46
$b
Total
$b
Access and licence fees3 5.5 10.2 50.8 66.5

1 Represents the 2022–23 Budget year and three-year forward estimates which includes: FY2024–26.
2 Whilst excluded from the 2022–23 NSW Budget, these access and licence fees are included in the ten-year commercial agreement between TAHE, operators and TfNSW.
3 Represents cumulative access and licence fees for the period stated.

The government will need to fund the operators an additional $10.2 billion in budget funding to meet their contractual obligations to TAHE from 2026–27 to 2030–2031, and a further projected funding of $50.8 billion from 2032 to 2046. This is needed to ensure the government continues to demonstrate its expected return on investment of 2.5%. This additional funding is not within the government's published 2022–23 NSW Budget figures, leading to uncertainty on whether the government funded operators can pay access and licence fees beyond the forward estimate period of 2025–26.

Significant funding uncertainties remain

While the ten-year access and licence fee agreements were communicated to the NSW Government's Expenditure Review Committee, it is yet to be fully provided for in the government's budget figures. As TAHE's projections are highly dependent on the operators as its key customers, it remains critical that the government continue to provide sufficient funding to the operators so they can pay for access and use of TAHE assets. This means the significant funding uncertainties reported in last year's TSSA audit opinion remain for 2021–22.

The government has estimated $37.9 billion in returns (equivalent to 2.5% on contributed equity) is to be earned from its investment in TAHE over the period from 1 July 2022 to 30 June 2046. As previously reported, TAHE derives most of its revenue from access and licence fee agreements from the operators, who in turn are both funded by grants through TfNSW from the GGS. More than 95% of these returns are estimated to be earned outside of the ten-year contract period (terminating 30 June 2031).

  2022–261
$b
2027–20312
$b
2032–46
$b
Total
$b
Returns to GGS 1.8 4.7 31.5 37.9

1 Represents the 2022–23 budget year and three-year forward estimates which includes: 2023–24, 2024–25 and 2025–26.
2 Whilst excluded from the 2022–23 NSW Budget, these access and licence fees are included in the ten-year commercial agreement between TAHE, operators and TfNSW.

There remains risk that:

  • TAHE will not be able to recontract for access and licence fees at a level that is consistent with current projections
  • future governments' funding to TAHE's key customers will not be sufficient to fund payment of access and licence fees at a level that is consistent with current projections
  • TAHE will be unable to grow its non-government revenues.

This significant funding uncertainty was also reported in last year's TSSA audit opinion and will remain for 2021–22.

In 2021–22, TAHE and NSW Treasury prepared further modelling to support the Government's intent to earn a 2.5% return inclusive of recovering the holding (revaluation) loss of $20.3 billion on its investment in TAHE

Last year's State Finances report highlighted that NSW Treasury, with TAHE, should prepare robust projections and business plans to support the expected returns forecast beyond FY2031.

This year TAHE engaged an expert to help develop a model demonstrating the government's expected returns from its investment in TAHE. The model mathematically forecasts that returns of 2.5% will be achieved by 2046 and this will include recovery of the revaluation losses of $20.3 billion relating to 2020–21.

The current model includes some key assumptions:

  • The main source of revenue is the access and licence fees expected from the two public rail operators (Sydney Trains and NSW Trains) contributing to more than 80% of TAHE's projected revenue. The rail operators are largely funded by the government when paying access and licence fees to TAHE.
  • For the first ten years, the access and licence fees are based on the signed agreements between TAHE and the public rail operators.
  • Beyond the ten-year contracted period, the model assumes existing contractual terms for access and licence fees will continue unchanged allowing for an annual rise for inflation (2.5% per annum), and increased fees to enable a 7.62% return for renewed assets.
  • The capital expenditure included in the model is only the amounts approved by the Expenditure Review Committee (ERC) as part of the ten-year forecast. The model beyond ten years includes expected investment in renewed and replacement assets but excludes any forecasts relating to growth capex that is not approved by the ERC, and any related depreciation expenses for growth capex.

While management has developed a 35-year long term financial model to support the returns, we note this will need to be refined over the next few years. Furthermore, these are forecasted figures and we have not seen sufficient evidence of whether this reflects reality (that is, the achievement of dividends representing a return on equity) as it is still very early. Therefore, this will remain a high-risk matter until we have seen sufficient evidence of reality to the forecasted figures.

There is negative net impact on the budget after 2024–25 and this will grow in the future

There are some key points to highlight with this modelling and these are best conveyed with the graph below. This graph shows total cash injections made by the GGS since the government first announced the creation of TAHE as a for-profit entity in the 2015–16 NSW Budget. It also conveys the forecast returns from TAHE to the GGS and the level of funding operators will need from the GGS to pay TAHE's access and licence fees over the 30-year period. These cash flows are key inputs used in the modelling which calculates a 2.5% return from TAHE inclusive of recovering the holding (revaluation) loss of $20.3 billion.

The government continues to respond to the impact of the COVID-19 pandemic on New South Wales through its economic stimulus measures

The COVID-19 pandemic continued to significantly impact the State’s finances, reducing revenue and increasing expenses especially in sectors directly responsible for responding to the COVID-19 pandemic, such as Health. In October 2021, the government announced through the 'COVID-19 Economic Recovery Strategy' an additional $2.8 billion in economic stimulus and response measures following the conclusion of the three-month lockdown due to the Delta COVID-19 outbreak. Measures included:

  • $739 million in household and social support, including housing support for Aboriginal communities and survivors of domestic violence, and vouchers to thank parents for their efforts to support learning from home
  • $500 million to consumers and businesses including expansion of the 'Dine & Discover' and 'Stay & Rediscover' voucher programs
  • $495 million in education support addressing learning gaps for children and helping schools prepare for future learning disruptions
  • $487 million in combined funding for tourism, events, sports, and recreation throughout New South Wales
  • $130 million to fund mental health services for individuals whose mental health was impacted by the pandemic.

The 2021–22 financial year included $21.9 billion for pandemic response and economic stimulus measures. Of this, $17.9 billion was spent in 2021–22 while a further $1 billion of the budgeted amount from 2021–22 was carried forward into 2022–23. The graph below shows the total allocation and spend by cluster for 2022 compared to target spend.

There were 14 natural disaster declarations including four severe weather events in 2021–22

Natural disasters such as bushfires, storms, floods, and other adverse weather events can have a significant impact on the State's finances. Costs associated with natural disasters include direct response costs such as clean-up and recovery, temporary accommodation, and as well as financial assistance provided to impacted communities such as recovery and business support grants.

The NSW Government can make a natural disaster declaration allowing eligible individuals and communities from impacted Local Government Areas access to a range of special financial assistance measures.

In 2021–22, there were 14 natural disaster declarations announced comparable to 14 in the previous year. These natural disaster declarations largely related to storms and floods throughout the State. In 2021–22, there was a larger number of 'severe weather' events declared, with four in 2021–22 (nil in 2020–21).

Natural disaster expenses increased 143% to $1.4 billion in 2021–22, up from $569 million last year

Over 2021–22, the budgeted cost for declared natural disasters was $1.9 billion ($725 million in 2020–21). Actual expenditure by the State on disaster response increased by $815 million to $1.4 billion. The graph below shows the total allocation and spend by cluster for 2022 compared to their budget spend.

Deficit of $15.3 billion compared with a budgeted deficit of $8.6 billion

The outcomes of the government’s overall activity and policies are reflected in its net operating balance (budget result). This is the difference between the cost of general government service delivery and the revenue earned to fund these sectors.

The General Government Sector, which comprises 196 entities, generally provides goods and services funded centrally by the State.

In addition to the 196 entities within the General Government Sector, a further 85 government controlled businesses are included within the consolidated Total State Sector financial statements. These businesses generally provide goods and services, such as water, electricity and financial services for which consumers pay for directly, and form part of the PNFC (31) and PFC (54) sectors.

The budget result for the 2021–22 financial year was a deficit of $15.3 billion compared to an original forecast of a budget deficit of $8.6 billion.

Revenues increased $16.1 billion to $106.7 billion

The State’s total revenues increased $16.1 billion to $106.7 billion, an increase of 17.8% compared to the previous year. Total revenue growth in 2020–21 was 5.1%. The State's increase in revenue was mostly from $9.2 billion in grants and subsidies and $4.6 billion in taxation.

Taxation revenue increased by 13.3%

Taxation revenue increased by $4.6 billion, mainly due to the net of:

  • $4.9 billion higher stamp duties collected from property sales driven by growth in property transaction volumes and prices during 2021–22. This was growth was experienced across residential and commercial property markets
  • $296 million lower gambling and betting taxes compared to 2020–21. Decrease was primarily attributed to the ongoing effects of COVID-19 restrictions and venue closures within the first half of 2021–22.

Stamp duties of $16.6 billion remains the largest source of taxation revenue, $7.7 billion higher than payroll tax of $8.9 billion, the second-largest source of taxation revenue.

Assets grew by $53 billion to $571 billion

The State’s assets include physical assets such as land, buildings and infrastructure, and financial assets such as cash, and other financial instruments and equity investments. The value of total assets increased by $53.2 billion or 10.3% to $571 billion. The increase was largely due to increases in the carrying value of land, buildings and infrastructure systems.

Valuing the State’s physical assets

State’s physical assets valued at $437 billion

The value of the State’s physical assets increased by $46.8 billion to $437 billion in 2021–22 ($724 million increase in 2020–21). The State’s physical assets include land and buildings ($198 billion), infrastructure systems ($221 billion), and plant and equipment ($18 billion).

The movement in physical asset values between years includes additions, disposals, depreciation and valuation adjustments. Other movements include assets reclassified to held for sale and other opening balance adjustments.

Appendix one – Prescribed entities

Appendix two – Legal opinions

Appendix three – TSS sectors and entities

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Coordination of the response to COVID-19 (June to November 2021)

Coordination of the response to COVID-19 (June to November 2021)

Premier and Cabinet
Community Services
Health
Justice
Whole of Government
Internal controls and governance
Risk
Service delivery
Shared services and collaboration

What the report is about

This audit assessed the effectiveness of NSW Government agencies’ coordination of the response to COVID-19, with a focus on the Delta variant outbreak in the Dubbo and Fairfield Local Government Areas (LGA) between June and November 2021. We audited five agencies - the Department of Premier and Cabinet, NSW Health, the NSW Police Force, Resilience NSW and the Department of Customer Service.

The audit also considered relevant planning and preparation activities that occurred prior to June 2021 to examine how emergency management and public health responses learned from previous events.

What we found

Prior to Delta, agencies developed capability to respond to COVID-19 related challenges.

However, lessons learned from prior reviews of emergency management arrangements, and from other jurisdictions, had not been implemented when Delta emerged in June 2021. As a result, agencies were not as fully prepared as they could have been to respond to the additional challenges presented by Delta.

Gaps in emergency management plans affected agencies' ability to support individuals, families and businesses impacted by restrictions to movement and gathering such as stay-at-home orders. In LGAs of concern, modest delays of a few days had a significant impact on people, especially those most vulnerable.

On 23 July 2021, the NSW Government established a cross-government coordinating approach, the Delta Microstrategy, which complemented existing emergency management arrangements, improved coordination between NSW Government agencies and led to more effective local responses.

Where possible, advice provided to government was supported by cross-government consultation, up-to-date evidence and insights. Public Health Orders were updated as the response to Delta intensified or to address unintended consequences of previous orders. The frequency of changes hampered agencies' ability to effectively communicate changes to frontline staff and the community in a rapidly evolving situation.

The NSW Government could provide greater transparency and accountability over decisions to apply Public Health Orders during a pandemic.

What we recommended

The audit made seven recommendations intended to improve transparency, accountability and preparedness for future emergency events.

This audit assessed the effectiveness of NSW Government agencies’ coordination (focused on the Department of Premier and Cabinet, NSW Health, the NSW Police Force, Resilience NSW and the Department of Customer Service) of the COVID-19 response in selected Local Government Areas (Fairfield City Council and Dubbo Regional Council) between June and November 2021.

As noted in this report, Resilience NSW was responsible for the coordination of welfare services as part of the emergency management arrangements. On 16 December 2022, the NSW Government abolished Resilience NSW.

During the audited period, Resilience NSW was tasked with supporting the needs of communities subject to stay-at-home orders or stricter restrictions and it provided secretariat support to the State Emergency Management Committee (SEMC). The SEMC was, and remains, responsible for the coordination and oversight of emergency management policy and preparedness.

Our work for this performance audit was completed on 15 November 2022, when we issued the final report to the five audited agencies. While the audit report does not make specific recommendations to Resilience NSW, it does include five recommendations to the State Emergency Management Committee. On 8 December 2022, the then Commissioner of Resilience NSW provided a response to the final report, which we include as it is the formal response from the audited entity at the time the audit was conducted.

The community of New South Wales has experienced significant emergency events during the past three years. COVID-19 first emerged in New South Wales after bushfire and flooding emergencies in 2019–20. The pandemic is now into its third year, and there have been further extreme weather and flooding events during 2021 and 2022.

Lessons taken from the experience of these events are important to informing future responses and reducing future risks to the community from emergencies.

This audit focuses on the NSW Government's response to the COVID-19 pandemic, and in particular, the Delta variant (Delta) that occurred between June and November 2021. The response to the Delta represents six months of heightened challenges for the NSW Government.

Government responses to emergencies are guided by legislation. The State Emergency and Rescue Management Act 1989 (SERM Act) establishes emergency management arrangements in New South Wales and covers:

  • coordination at state, regional and local levels through emergency management committees
  • emergency management plans, supporting plans and functional areas including the State Emergency Management Plan (EMPLAN)
  • operations centres and controllers at state, regional and local levels.

This audit focuses on the activities of five agencies during the audit period:

  • The NSW Police Force led the emergency management response and was responsible for coordinating agencies across government in providing the tactical and operational elements that supported and enhanced the health response to the pandemic. The NSW Police Force also led the compliance response which enforced Public Health Orders and included household checks on those required to isolate at home after testing positive to COVID-19. In some parts of NSW, they were supported by the Australian Defence Force in this role.
  • NSW Health was responsible for leading the health response which coordinated all parts of the health system, initially to prevent, and then to manage, the pandemic.
  • Resilience NSW coordinated welfare services as part of the emergency management arrangements and provided secretariat support to the State Emergency Management Committee (SEMC). The SEMC is responsible for the coordination and oversight of emergency management policy and preparedness. Resilience NSW was also tasked with supporting the needs of communities subject to stay-at-home orders or stricter restrictions.
  • The Department of Customer Service (DCS) was responsible for the statewide strategic communications response.
  • The Department of Premier and Cabinet (DPC) held a key role in providing policy and legal services, as well as supporting the coordination of activity across a range of functional areas and decision-making by our State’s leaders.

This audit assessed the effectiveness of NSW Government agencies’ coordination (focused on the Department of Premier and Cabinet, NSW Health, the NSW Police Force, Resilience NSW and the Department of Customer Service) of the COVID-19 response in selected Local Government Areas (LGA) (Fairfield City Council and Dubbo Regional Council) after June 2021.

The audit investigated whether:

  • government decisions to apply LGA-specific Public Health Orders were supported by effective crisis management governance and planning frameworks
  • agencies effectively coordinated in the communication (and enforcement) of Public Health Orders.

While focusing on the coordination of NSW Government agencies’ response to the Delta variant in June through to November 2021, the audit also considered relevant planning and preparation activities that occurred prior to June 2021 to examine how emergency management and public health responses learned from previous events.

This audit does not assess the effectiveness of other specific COVID-19 responses such as business support. It refers to the preparedness, planning and delivery of these activities in the context of supporting communities in selected LGAs. NSW Health's contribution to the Australian COVID-19 vaccine rollout was also subject to a separate audit titled 'New South Wales COVID-19 vaccine rollout' tabled in NSW Parliament on 7 December 2022. 

This audit is part of a series of audits which have been completed, or are in progress, regarding the New South Wales COVID-19 emergency response. The Audit Office of New South Wales '2022–2025 Annual Work Program' details the ongoing focus our audits will have on providing assurance on the effectiveness of emergency responses.

In this document Aboriginal refers to the First Nations peoples of the land and waters now called Australia, and includes Aboriginal and Torres Strait Islander peoples.

Conclusion

Prior to June 2021, agencies worked effectively together to adapt and refine pre-existing emergency management arrangements to respond to COVID-19. However, lessons learned from prior reviews of emergency management arrangements, and from other jurisdictions, had not been implemented when Delta emerged in June 2021. As a result, agencies were not as fully prepared as they could have been to respond to the additional challenges presented by Delta.

In the period March 2020 to June 2021, the State's Emergency Management (EM) arrangements coordinated the New South Wales emergency response to COVID-19 with support from the Department of Premier and Cabinet (DPC) which led the cross-government COVID-19 Taskforce. NSW Government agencies enhanced the EM arrangements, which until then had typically been activated in response to natural disasters, to meet the specific circumstances of the pandemic.

However, the State Emergency Management Committee (SEMC), supported by Resilience NSW, did not address relevant recommendations arising from the 2020 Bushfires Inquiry before June 2021 and agencies did not always integrate lessons learned from other jurisdictions or scenario training exercises into emergency management plans or strategies before Delta. As a result, deficiencies in the EM arrangements, including representation of vulnerable communities on EM bodies, well-being support for multicultural communities in locked down environments and cross-agency information sharing, persisted when Delta emerged in June 2021.

It should be noted that for the purposes of this audit there is no benchmark, informed by precedent, that articulates what level of preparation would have been sufficient or proportionate. However, the steps required to address these gaps were reasonable and achievable, and the failure to do so meant that agencies were not as fully prepared as they could have been for the scale and escalation of Delta’s spread across the State.

The Delta Microstrategy complemented the EM arrangements to support greater coordination and agencies are working to improve their capability for future events

The Delta Microstrategy (the Microstrategy) led to innovations in information sharing and collaboration across the public service. Agencies involved in the response have completed, or are completing, reviews of their contribution to the response. That said, none of these reviews includes a focus on whole-of-government coordination.

On 23 July 2021, the NSW Government approved the establishment of the Microstrategy to respond to the additional challenges presented by Delta including the need to support communities most impacted by restrictions to movement and gathering in the LGAs of concern. An extensive range of government agencies were represented across eight Microstrategy workstreams, which coordinated with the existing EM arrangements to deliver targeted strategies to communities in high-risk locations and improve data and information sharing across government. This enhanced the public health, compliance, income and food support, communications and community engagement aspects of the response.

Agencies also leveraged learnings from early weeks of the Delta wave and were able to replicate those lessons in other locations. The use of pre-staging hubs in Fairfield to support food and personal hamper distribution was used a month later in Dubbo which acted as a central hub for more remote parts of the State.

Emergency management plans did not enable government to respond immediately to support vulnerable communities in high-risk LGAs or regional NSW

There are gaps in the emergency management plans relating to the support for individuals, families and businesses impacted by the stay-at-home orders and other restrictions to movement and gathering. These gaps affected agencies' ability to respond immediately when the need arose during Delta.

Emergency management plans and supporting instruments did not include provision for immediate relief for households, which meant arrangements for isolation income support and food security measures had to be designed in the early stages of Delta before it could be approved and deployed.

There were delays – sometimes only days, on occasion, weeks - in providing support to affected communities. In particular, there were delays to the provision of income support and in scaling up efforts to coordinate food and grocery hampers to households in isolation. In LGAs of concern, modest delays of a few days had a significant impact on people, especially those most vulnerable.

Although government issued stricter restrictions for workers in the Fairfield LGA on 14 July 2021, it only approved targeted income support for people in LGAs of concern on 16 August 2021.

Overall, agencies coordinated effectively to provide advice to government but there are opportunities to learn lessons to improve preparedness for future events

Agencies coordinated in providing advice to government. The advice was supported by timely public health information, although this was in the context of a pandemic, where data and information about the virus and its variants was changing regularly. However, agencies did not always consider the impact on key industries or supply chains when they provided advice to government, which meant that Public Health Orders would sometimes need to be corrected.

Public Health Orders were also updated as the response to Delta intensified or to address unintended consequences of previous orders. The frequency of changes hampered agencies' ability to effectively communicate changes to frontline staff and the community in a rapidly evolving situation.

The audit identified several occasions where there were delays, ranging from three to 21 days, between the provision of advice to government and subsequent decision-making (which we have not detailed due to the confidentiality of Cabinet deliberations). Agency officers advised of instances where they were not provided sufficient notice of changes to Public Health Orders to organise local infrastructure (such as traffic support for testing clinics) to support compliance with new requirements.

The COVID-19 pandemic arrived in Australia in late January 2020 as the bushfire and localised flooding emergencies were in their final stages. Between 2020 and mid-2021, agencies responded to the initial variants of COVID-19, managed a border closure with Victoria that lasted nearly four months and dealt with localised ‘flare-ups’ that required postcode-based restrictions on mobility in northern parts of Sydney and regional New South Wales. During this period, New South Wales had the opportunity to learn from events in Victoria which imposed strict restrictions on mobility across the State and the growing emergence of the Delta variant (Delta) across the Asia Pacific.

This section of the report assesses how emergency management and public health responses adapted to these lessons and determined preparedness for, and responses to, widespread community transmission of Delta in New South Wales.

The previous chapter discusses how agencies had refined the existing emergency management arrangements to suit the needs of a pandemic and describes some gaps that were not addressed. This chapter explores the first month of Delta (mid-June to mid-July 2021). It explores the areas where agencies were prepared and responses in place for the outbreak. It also discusses the impact of the gaps that were not addressed in the period prior to Delta and other issues that emerged.

NSW Health provided advice on the removal of restrictions based on up-to-date advice

The NSW Government discussed the gradual process for removing restrictions using the Doherty Institute modelling provided to National Cabinet on 10 August 2021. NSW Health highlighted the importance of maintaining a level of public health and safety measure bundles to further suppress case numbers. This was based on additional modelling from the Doherty Institute.

The Department of Regional NSW led discussion and planning around reopening with a range of proposal through August and September 2021. The Department of Premier and Cabinet and NSW Health jointly developed a paper to provide options on the restrictions when the State reached a level of 70% double dose vaccinations.

The roadmap to reopening was originally published on 9 September 2021. However, by 11 October 2021, the restrictions were relaxed when the 70% double dose threshold was reached to allow:

  • up to ten fully vaccinated visitors to a home (increased from five)
  • up to 30 fully vaccinated people attending outdoor gatherings (increased from 20)
  • weddings and funerals limits increased to 100 people (from 50)
  • the reopening of indoor pools for training, exercise and learning purposes only.

On the same day, the NSW Government announced further relaxation of restrictions once the 80% double dose threshold was reached. These restrictions were further relaxed on 8 November 2021. This included the removal of capacity restrictions to the number of visitors to a private residence, indoor pools to reopen for all purposes and density limits of one person for every two square metres, dancing allowed in nightclubs and 100% capacity in major stadia.

The NSW Government allowed workers in regional areas who received one vaccination dose to return to their workplace from 11 October 2021.

The Premier extended the date of easing of restrictions for unvaccinated people aged over 16 from 1 December to 15 December 2021.

Many agencies have undertaken reviews of their response to the Delta outbreak but a whole-of-government review has yet to be conducted

Various agencies and entities associated with the response to the Delta outbreak conducted after-action review processes. These processes assessed the achievements delivered, lessons learned and opportunities for improvement. However, a whole-of-government level review has not been conducted. This limits the New South Wales public service's ability to improve how it coordinates responses in future emergencies.

The agencies/entities that conducted reviews included:

  • South West Metropolitan region, Western NSW region, Fairfield Local Emergency Management Committee (LEMC), Dubbo Local Emergency Operations Controller (LEOCON), which were collated centrally by the State Emergency Operations Centre (SEOC)
  • Aboriginal Affairs NSW assessed representation and relevance of the emergency management arrangements for Aboriginal communities following the 2019 bushfires
  • Resilience NSW developed case studies to capture improved practice with regard to food security and supply chains
  • a community support and empowerment-focused after-action review undertaken by the Pillar 5 workstream of the Microstrategy.

Key lessons collated from the after-action reviews include:

  • the impact of variation in capability across agencies on the management of key aspects of the response including welfare support and logistics
  • issues with boundary differences between NSW Police Force regions, local government areas (LGA and local health districts (LHD) caused issues in delivering and coordinating services in an emergency situation 
  • the need to improve relationships between state and local Government outside of acute emergency responses to improve service delivery 
  • issues arising from impediments to information sharing between agencies and jurisdictions, such as:
    • timeliness and accuracy of data used to direct compliance activities
    • the impact of insufficient advance notice on changes to Public Health Orders
    • timely access to data across public sector agencies and other jurisdictions to inform decision-making, analysis and communications
    • gaps in data around ethnicity, geolocation of recent positive cases and infection/vaccination rates in Aboriginal communities.
  • the lack of Aboriginal community representation on many LEMCs
  • compared with the response to COVID-19 in 2020, improved coordination of communications with Culturally and Linguistically Diverse (CALD) populations with a reduction in overlapping messages and over-communication
  • improved attendance from agency representatives in LEMCs, and regional emergency operations centres (REOC) to improve interagency communications, planning, capability development and community engagement issues
  • deficiencies in succession planning and fatigue management practices
  • the potential for REOC Welfare/Well-being subgroups to be included as part of the wider efforts to community needs during emergencies.

NSW Health commenced a whole of system review of its COVID-19 response in May 2022. At the time of writing, the completion due date for the debrief is 7 November 2022. This debrief is expected to explore:

  • governance
  • engagement 
  • innovation and technology 
  • community impact 
  • workforce impact
  • system impact and performance.

NSW Health is also undertaking a parallel Intra-Action Review that is focused on the public health aspects of the response with finalisation estimated for the end of November 2022. At the time of completing this performance audit report, NSW Health had not finalised these reviews and, as a result, we cannot validate their findings against our own observations.

Recent inquiries are likely to impact the governance of emergency management in New South Wales

In March 2022, the NSW Government established an independent inquiry to examine and report on the causes of, preparedness for, response to and recovery from the 2022 floods. The Flood Inquiry report made 28 recommendations, which the NSW Government supported in full or in principle. Some of the recommendations relate directly to the governance and leadership of emergency management arrangements in New South Wales. 

The State Emergency Management Committee (SEMC) will likely be involved in, and impacted by, the recommendations arising from the Flood Inquiry with potential changes to its membership and reshaping of functional areas and agencies. At the same time, the SEMC may have a role in overseeing the changes that emerge from the SEOC consolidated after-action reviews. This can also extend to ensuring local and regional bodies have incorporated the required actions. There is a risk that the recommendations from the pandemic-based after-action reviews may not be considered due to the priority of action resulting from the Flood Inquiry.

Furthermore, there is potential for the SEMC to work with NSW Health during its system-wide review. Such an approach is likely to improve preparedness for future events.

Appendix one – Response from agencies

Appendix two – Chronology 2020–2021

Appendix three – About the audit

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #371 - released 20 December 2022

Published

Actions for Internal controls and governance 2022

Internal controls and governance 2022

Whole of Government
Compliance
Cyber security
Financial reporting
Fraud
Information technology
Internal controls and governance
Procurement
Risk

What the report is about

This report analyses the internal controls and governance of the 25 largest agencies in the NSW public sector, excluding state-owned corporations and public financial corporations, for the year ended 30 June 2022.

What we found

Internal control trends

The proportion of control deficiencies identified as high-risk this year increased to 8.2% (5.9% in 2020–21). Sixteen of the 23 high-risk findings related to financial controls while seven related to IT controls.

Repeat findings of control deficiencies now represent 48% of all findings (47% in 2020–21).

Information technology

There continues to be a high number of deficiencies relating to IT general controls, particularly around user access reviews, which affected 56% of agencies.

Cyber security

Agencies' self-assessed maturity levels against the NSW Cyber Security Policy mandatory requirements are lower than target levels. Overall, maturity levels against the Australian Cyber Security Centre's Essential Eight controls have not improved since last year.

Management of cyber risks relating to third party IT service providers should be improved. IT service providers may pose risks to the agency if the provider's cyber security controls have weaknesses.

Consultants and contractors

Agencies risk over-reliance on the same consultants and contractors. A quarter of agencies have re-engaged the same contractor over the past five years.

Employment screening Twenty-four per cent of agencies have not complied with the employment screening requirements of the Government Sector Employment Act 2013 with regard to citizenship or residency. Screening and induction practices for non-permanent workers are often less stringent than for permanent employees. This can pose increased risks to an entity of not detecting applicants with false credentials or a history of corrupt conduct.

Contract management

Half of all agencies' procurement contract registers are incomplete, which is non-compliant with the Government Information (Public Access) Act 2009.

What we recommended

Agencies should:

  • prioritise actions to address repeat control deficiencies
  • prioritise improvements to their cyber security and resilience
  • reinforce mandatory cyber training to all staff and improve completion rates
  • ensure that contractor engagements that have been renewed over multiple years are periodically reassessed against the market.

Internal controls are processes, policies and procedures that help agencies to:

  • operate effectively and efficiently
  • produce reliable financial reports
  • comply with laws and regulations
  • support ethical government.

This chapter outlines the overall trends for agency controls and governance issues, including the number of audit findings, the degree of risk those deficiencies pose to the agency, and a summary of the most common deficiencies we found across agencies. The rest of this report presents this year's controls and governance findings in more detail.

For consistency and comparability, we have adjusted the 2021 results to incorporate additional audit findings that were reported after the date of the 'Internal controls and governance 2021' report. Therefore, the 2021 figures will not necessarily align with those reported in our 2021 report.

This section also covers how agencies have complied with TD 21-04 during 2021–22.

Section highlights

We identified 23 high-risk findings, compared to 20 last year, with ten repeated from last year. Sixteen of the 23 findings related to financial controls and seven related to IT controls.

  • The proportion of repeat deficiencies has increased from 47% in 2020–21 to 48% in 2021–22.
  • We identified a low level of compliance with TD 21-04 during 2021–22. Most agencies do not have a policy on gifts of government property, and did not annually certify their register of gifts of government property or attest that the agency has not made any gifts.

This chapter outlines our audit observations, conclusions and recommendations arising from our review of agency controls to manage key financial systems.

Section highlights

  • We continue to see a high number of deficiencies related to IT General Controls, particularly those related to user access administration and privileged user access.
  • We identified deficiencies within IT governance related to IT policies and procedures not effective in managing IT risks. We also identified weaknesses in arrangements with third-party IT service providers which can increase cyber security risk.

This chapter outlines our audit observations, conclusions and recommendations arising from our review of agencies' cyber security planning and governance arrangements.

Section highlights

  • Only 80% of agencies specify how they monitor or ensure that third-party IT service providers comply with the agencies' cyber security policies. IT service providers may pose certain risks to the agency if the provider's cyber security controls have weaknesses.
  • There are inconsistent practices and definitions of cyber security incidents across agencies with respect to maintaining incident registers. Five agencies reported nil incidents in their registers for 2021–22, while other agencies recorded up to 1,913 incidents.
  • Agencies' self-assessed maturity levels against the NSW Cyber Security Policy mandatory requirements are lower than their target levels in at least one requirement. Maturity levels against the Australian Cyber Security Centre's Essential Eight controls have not improved since last year. 

This chapter outlines our audit observations, conclusions and recommendations arising from our review of agencies' practices in engaging external experts, such as consultants and contractors.

Section highlights

  • Agencies risk over-reliance on the same consultants, as some firms continue to be the highest paid consultants at 60% of agencies for at least three of the past five years.
  • Agencies could improve their policies on engaging consultants to include consideration of:
    • probity requirements/conflict of interests
    • rotation of independent consultants from time-to-time
    • additional review where multiple consultants are engaged on the same topic to address the risk of opinion shopping.
  • A quarter of agencies have re-engaged the same contractor over the past five years, with one contractor engaged for 19 years. Long-term engagements without reassessment against market increase the risk of dependency on the contractor.

This chapter outlines our audit observations, conclusions and recommendations arising from our review of agencies' employment screening practices.

Section highlights

  • We identified that most agencies do not include the risk of employment application fraud in their risk registers.
    Post-employment screening has an important role in preventing fraud and managing risk as roles often change and the initial employment screening procedures may not be sufficient to control risk over time. Only 57% of agencies that have an employment screening policy include post-employment screening guidance.
  • Screening and induction practices for non-permanent workers are often less stringent than for permanent employees. There is an increased risk that agencies will:
    • fail to identify an applicant with a past history of corrupt or criminal conduct
    • not identify applications with false credentials
    • hire a worker with unsuitable qualifications, skills or experience.

This chapter outlines our audit observations, conclusions and recommendations arising from our review of agencies' contract management processes.

Section highlights

  • All agencies maintain a central contract register but 40% are incomplete, risking non-compliance with the Government Information (Public Access) Act 2009 (GIPA Act).
  • The contract renewal process could be improved. We identified only 76% of agencies assessed value for money before deciding to renew/extend the contract.
  • Most agencies provide some training and support to staff on procurement procedures. Ongoing training and awareness programs allow agencies to communicate to all staff their responsibilities and obligations in relation to procurement activities. 

Published

Actions for Planning and Environment 2022

Planning and Environment 2022

Environment
Industry
Local Government
Planning
Asset valuation
Compliance
Financial reporting
Information technology
Infrastructure
Internal controls and governance
Management and administration
Risk

What the report is about

Result of the Planning and Environment cluster agencies' financial statements audits for the year ended 30 June 2022.

What we found

Unmodified audit opinions were issued for all completed 30 June 2022 financial statements audits of cluster agencies. Seven audits are ongoing.

Disclaimed audit opinions were issued for the 2010–11 to 2015–16 financial statements of the Water Administration Ministerial Corporation (WAMC), as management was unable to certify that the financial statements exhibit a true and fair view of WAMC's financial position and financial performance.

Qualified audit opinions were issued for WAMC's 2016–17 and 2017–18 financial statements due to insufficient evidence to support the completeness and valuation of water meters infrastructure assets, the impairment of water meters, and the completeness of buildings at Nimmie Caira.

Unqualified audit opinions were issued for WAMC's 2018–19 and 2019–20 financial statements.

The Department of Planning and Environment (the department) assessed 45 Category 2 Statutory Land Managers (SLM) did not meet the reporting exemption criteria and therefore were required to prepare 2021–22 financial statements. None of these 45 Category 2 SLMs prepared and submitted their 30 June 2022 financial statements by the statutory reporting deadline.

All 119 Commons Trusts have never submitted their financial statements for audit as required by the Government Sector Finance Act 2018 (GSF Act).

NSW Treasury has confirmed that the Catholic Metropolitan Cemeteries Trust (CMCT) is a controlled entity of the State. To date, CMCT has not met its obligations to prepare financial statements under the GSF Act and it has not submitted financial statements to the Auditor-General for audit.

What the key issues were

Since 2017, the Audit Office has recommended the department address the different practices across the local government sector in accounting for rural firefighting equipment. Despite repeated recommendations, the department did little to resolve this issue. At the time of writing, 32 of 118 completed council audits received qualified audit opinions on their 30 June 2022 financial statements.

There continues to be significant deficiencies in Crown land records. The department uses the Crown Land Information Database (CLID) to record key information relating to Crown land in New South Wales that is managed and controlled by the department and land managers. The CLID system was not designed to facilitate financial reporting, and the department is required to conduct extensive adjustments and reconciliations to produce accurate information for the financial statements.

The department implemented the CrownTracker system as a replacement for CLID. The project was finalised in June 2022, but it has not achieved the intended outcomes.

Nine high-risk issues were identified across the cluster related to the findings outlined above and weaknesses in IT general controls, financial reporting, governance processes and internal controls.

Recommendations were made to address these deficiencies.

This report provides Parliament and other users of the Planning and Environment cluster’s financial statements with the results of our audits, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision-making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Planning and Environment cluster (the cluster) for 2022.

Section highlights

  • Unqualified audit opinions were issued for all completed 30 June 2022 financial statements audits of cluster agencies. Seven audits are ongoing. The audit of the Catholic Metropolitan Cemeteries Trust(CMCT) has not been able to commence, despite repeated requests to do so.
     
  • The audits of the Water Administration Ministerial Corporation's (WAMC) financial statements for the years ended 30 June 2011 to 30 June 2020 were completed in November 2022. These audits had been long outstanding due to insufficient records and evidence to support the transactions and balances of WAMC, particularly for the earlier years. In recent years, management commenced actions to improve WAMC's governance and financial management, and finalise the outstanding audits.

    Disclaimed audit opinions were issued on the 2010–11 to 2015–16 financial statements as management was unable to certify that the financial statements exhibit a true and fair view of WAMC's financial position and financial performance.

    Qualified audit opinions were issued for the 2016–17 and 2017–18 financial statements due to insufficient evidence to support the completeness and valuation of water meters infrastructure assets, the impairment of water meters, and the completeness of buildings at Nimmie Caira.

    Unqualified audit opinions were issued for the 2018–19 and 2019–20 financial statements.

    The 2020–21 and 2021–22 WAMC audits are in progress.
     
  • The Department of Planning and Environment (the department) assessed 45 Category 2 Statutory Land Managers (SLM) did not meet the reporting exemption criteria and therefore were required to prepare 2021–22 financial statements. None of these 45 Category 2 SLMs prepared and submitted their 30 June 2022 financial statements by the statutory reporting deadline.

    All 119 Commons Trusts have never submitted their financial statements for audit as required by the Government Sector Finance Act 2018 (GSF Act).

    The department needs to do more to ensure Category 2 SLMs and Commons Trusts meet their statutory reporting obligations.

    The department and Category 2 SLMs should finalise their reporting exemption assessments earlier to allow sufficient time for the non-exempted SLMs to prepare and submit annual financial statements by the statutory reporting deadline.
     
  • NSW Treasury has met with the Catholic Metropolitan Cemeteries Trust (CMCT) to consider their perspective as part of confirming CMCT is a controlled entity of the State for the purposes of financial reporting. NSW Treasury has confirmed that the CMCT is a controlled entity of the State. This means that the CMCT is statutorily obliged under section 7.6 of the GSF Act to prepare financial statements in accordance with the GSF Act and Treasurer's Directions, and give them to the Auditor-General for audit pursuant to the Government Sector Audit Act 1983 (GSA Act). Section 34 of the GSA Act requires the Auditor-General to furnish an audit report on these financial statements.

    The department wrote to CMCT to request it work with, and offer full assistance to, the Auditor-General in the exercise of her duties. To date, the CMCT has not met its obligations to prepare financial statements under the GSF Act as it has not submitted its financial statements to the Auditor-General for audit despite repeated requests, and has not provided access to its books and records for the purposes of a financial audit. The CMCT contends that they are not a GSF agency as defined by the GSF Act and therefore not a controlled entity of the State.
     
  • Six agencies required to perform early close procedures did not complete a total of 11 mandatory procedures. Incomplete procedures included the delayed resolution of matters raised in prior years and two agencies did not record movements in the fair value of physical assets in the financial statements.

 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision-making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the Planning and Environment cluster.

Section highlights

  • Since 2017, the Audit Office of New South Wales has recommended that the Department of Planning and Environment (the department) address the different practices across the local government sector in accounting for rural firefighting equipment. Despite repeated recommendations, the department did little to resolve this issue, and in 2022, 32 of 118 completed audits of councils received qualified audit opinions on their 2022 financial statements.
    Consistent with the department’s role to assess councils' compliance with legislative responsibilities, standards or guidelines, the department should intervene where councils do not recognise rural firefighting equipment.
  • There continues to be significant deficiencies in Crown land records. The department should implement an action plan to ensure the Crown land database is complete and accurate.
  • The number of findings reported to management decreased from 161 in 2020–21 to 132 in 2021–22. Eight high-risk findings were identified during 2021–22, of which six were repeat issues. One new high-risk finding related to deficiencies in governance processes and internal controls identified as a part of the Water Administration Ministerial Corporation's 2011–2020 financial statements audits.
  • The department and NSW Treasury did not comply with section 35 of the Energy and Utilities Administration Act 1987 (EUA Act). However, complying with the EUA Act could create non-compliance with other pieces of legislation. Amendments to the EUA Act have been made to resolve this inconsistency. The amendment took effect from April 1999.

 

Appendix one – Misstatements in financial statements submitted for audit

Appendix two – Early close procedures

Appendix three – Timeliness of financial reporting

Appendix four – Financial data

Appendix five – Councils received qualified audit opinions 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Development applications: assessment and determination stages

Development applications: assessment and determination stages

Planning
Local Government
Internal controls and governance
Management and administration
Service delivery

What the report is about

Local councils in New South Wales are responsible for assessing local and regional development applications.

Most development applications are assessed and determined by council staff under delegated authority. However, some development applications must be referred to independent local planning panels or Sydney and regional planning panels for determination.

Councils provide support to local planning panels. The Department of Planning and Environment provides support to Sydney and regional planning panels.

This audit assessed whether Byron Shire Council, Northern Beaches Council and The Hills Shire Council had effectively assessed and determined development applications in compliance with legislative and other requirements.

It also assessed whether The Hills Shire Council, Northern Beaches Council and the Department of Planning and Environment had provided effective support to relevant independent planning panels.

What we found

All councils had established clear roles, responsibilities and delegations for assessment and determination of development applications and had also established processes to ensure quality of assessment reports.

Northern Beaches Council and The Hills Shire Council have established comprehensive approaches to considering and managing risks related to development assessment.

Northern Beaches Council's approach to publishing its assessment reports promotes transparency.

Across a sample of development applications assessed and determined between 2020–22:

  • Northern Beaches Council and The Hills Shire Council had assessed and determined applications in compliance with legislative and other requirements. However, The Hills Shire Council could do more to transparently document any conflicts of interest within assessment reports.
  • Byron Shire Council had assessed most applications in compliance with legislative and other requirements. However, we found opportunities for the Council to:
    • ensure determinations were made in line with delegations
    • strengthen its approach to transparent management of conflicts of interest and quality review of assessments.

The Hills Shire Council and Northern Beaches Council had effectively supported their respective local planning panels.

The Department of Planning and Environment had processes that meet requirements for supporting regional planning panels but could do more to promote consistency in approach, share information across panels and measure the effectiveness of its support.

What we recommended

We made recommendations to Byron Shire Council, The Hills Shire Council and the Department of Planning and Environment to address the gaps identified and improve the transparency of processes.

Local councils in New South Wales are responsible for assessing local and regional development applications under the Environmental Planning and Assessment Act 1979 (EP&A Act).

In assessing development applications, councils consider:

  • whether the proposed development application is compliant with legislation and environmental planning instruments
  • whether the proposed development meets local planning controls and objectives
  • any environmental, social and economic impacts
  • any submissions from impacted properties, neighbours and interested parties
  • the public interest.

Once assessed, a development application will be determined by council staff under delegated authority, the elected council, or an independent planning panel.1 

The involvement of a particular independent planning panel is established under legislative and policy instruments, and depends on the type and value of the proposed development. Most development applications are assessed and determined by council staff under delegated authority.

In determining development applications, independent planning panels must manage any potential, real or perceived conflicts of interest of panel members for a given development application, meet and vote on development applications, and publish their decisions and reasons.

Under the EP&A Act, and as required by statutory instruments and procedures, councils and the Department of Planning and Environment (DPE) must provide secretariat and other support functions to independent planning panels.

Previous reviews and inquiries have identified several significant risks that are present within the processes involved in the assessment and determination of development applications. These risks include possible non-compliance with complex legal and policy requirements, potential improper influence from developers and other stakeholders, and a perceived lack of transparency within the planning system and planning outcomes.

There are several planning pathways for development in New South Wales. This audit focuses on local and regional development that requires assessment and determination by a local council and/or an independent local planning panel or Sydney or regional planning panel in three Local Government Areas (LGAs): Byron Shire Council, Northern Beaches Council, The Hills Shire Council.

Audited councils were selected from a range of criteria, including:

  • the number, value and types of development applications determined in 2018–19
  • average determination timeframes
  • appeals against determinations and Land and Environment Court outcomes
  • LGA demographics.

The audit also avoided councils that had previously been subject to a performance audit.

The objective of this audit was to assess whether:

  • selected councils have effectively assessed and determined development applications in compliance with relevant legislation, regulations and government guidance
  • selected councils and DPE effectively support independent planning panels to determine development applications in compliance with relevant legislation, regulations and government guidance.

Conclusion – Byron Shire Council

Byron Shire Council has established clear roles, responsibilities and delegations for assessment and determination of development applications. However, the effectiveness of the Council's approach is limited by gaps in governance, risk management and internal controls.

Byron Shire Council has established clear roles, responsibilities and delegations for assessment and determination of development applications. However, the Council does not have a consolidated policy and procedure for development assessment, has not adequately followed up on the outcomes of internal reviews that identified opportunities to strengthen its assessment and determination procedures and approach, and has not demonstrated that it has managed relevant risks effectively.

The Council has not ensured that delegations have been consistently followed in the assessment of development applications.

Byron Shire Council's approach to managing conflicts of interest in development assessments does not provide transparency over potential conflicts of interest.

Byron Shire Council manages the risk of conflicts of interest for development assessment under its Code of Conduct. The Council has also implemented a separate policy that details additional requirements for managing conflicts of interest relevant to the development assessment process, but has not regularly updated this policy and requirements between it and the Code of Conduct have not been aligned. This creates a risk that planning staff may be following inconsistent or outdated advice in managing conflicts of interest.

Across the period of review, the Council did not require staff to provide a disclosure of interest for individual development applications to be contained within assessment reports. Including these disclosures would increase transparency and ensure that staff are sufficiently considering any conflicts of interest relevant to each separate assessment process.

Byron Shire Council has processes that promote compliance with legislation, regulation and government policy, but can improve how it undertakes some aspects of these that would ensure transparency, quality and consistency.

Our review of a sample of completed development applications from the Council indicated that most assessments were completed in compliance with relevant legislation, regulations and government guidance, but that there were some opportunities to improve elements of the assessment process, including: transparency of any conflicts of interest involved in the assessment process, ensuring compliance with delegated authority limits, and consideration of modification application provisions.

The Council has established templates to guide planners through relevant assessment considerations required by legislation, regulations and other guidance. However, it could do more to strengthen its approach to peer or manager review, monitoring legislative changes, and how it monitors the completion of relevant training by planning staff. 

 

Conclusion – Northern Beaches Council

Northern Beaches Council has established processes to support compliant and effective assessment and determination of development applications.

The Council has a clear governance and risk management framework for development assessment that sets out roles, responsibilities and delegations.

Northern Beaches Council has established clear roles, responsibilities and delegations for development application assessment and determination. The Council has identified development assessment related risks, and has put in place controls and mitigating actions to manage the risks to within risk tolerances.

Northern Beaches Council's approach to managing conflicts of interest promotes transparency.

Northern Beaches Council manages the risk of conflicts of interest for development assessment under its Code of Conduct. The Council has implemented an additional framework for planning staff to respond to the risk of conflicts of interest in development assessment processes. This framework requires its staff to disclose any conflicts of interest as a formal step in assessing development applications and includes declarations of any interests within assessment reports or planning panel minutes.

Our review of a sample of completed development applications indicated that the assessment reports had been compliant with the Council's approach to transparently documenting conflicts of interest.

Northern Beaches Council has established processes to deliver consistent, quality assessment of development applications.

Northern Beaches Council staff use an electronic development assessment tool that provides guidance, links to legislative and policy instruments and other applications that support assessment and drive consistency in approach. The Council applies a peer review process in which a manager or team member in a more senior position reviews an assessment report prior to determination to ensure that expected standards of quality and consistency have been met.

Our review of a sample of completed development applications indicated that assessments were undertaken in compliance with relevant legislation, regulations and government guidance.

Northern Beaches Council transparently documents assessment reports, supporting information and determination outcomes.

Northern Beaches Council has implemented a transparent approach to how it assesses and determines development applications. The Council publishes assessment reports, supporting technical reports, plans and submissions for all development applications. Notices of determination and final plans are also published alongside the assessment reports, allowing for greater transparency to the public.

Northern Beaches Council has established processes to effectively support the Northern Beaches Local Planning Panel.

Northern Beaches Council has established processes to support the Northern Beaches Local Planning Panel as required under legislative and policy instruments. The Council has processes to ensure that development applications required to be referred to a planning panel are identified and monitored, supports identification and documentation of any conflicts of interest, and transparently documents decisions of the panel.

Our review of a sample of meeting records held across the audit period of review indicated that these requirements were met and were transparently documented. 

 

Conclusion – The Hills Shire Council

The Hills Shire Council has established processes to support compliant and effective assessment and determination of development applications.

The Council has established a comprehensive governance and risk management framework for development assessment that sets out clear roles, responsibilities and delegations.

The Hills Shire Council has established a comprehensive framework for managing risks related to development assessment. Such risks are clearly identified and associated controls are in place to reduce or mitigate the risks. The Council has undertaken regular internal audits of development assessments, including reviewing completed applications to ensure compliance with relevant legislative and policy requirements.

The Council has established clear roles, responsibilities and delegations, and its staff assessing and determining development applications are supported by a standard set of policies and procedures for undertaking assessment and determination of applications.

The Hills Shire Council is managing conflicts of interest in line with Code of Conduct requirements but could more transparently document these.

The Hills Shire Council manages conflicts of interest for those involved in development application processes through provisions under its Code of Conduct. Under this Code of Conduct, staff must declare any conflicts of interest to their manager. However, the Council does not require staff to disclose any conflicts of interest in development application assessment reports which limits transparency to reviewing managers or any other determination bodies.

The Hills Shire Council has established processes to deliver consistent, quality assessment of development applications.

The Hills Shire Council has established templates to guide planners through relevant development assessment and determination considerations required by legislation, regulations and other guidance. The Council requires a peer review to occur prior to any determination which ensures a check on the compliance and quality of the assessment report prepared.

Our review of a sample of completed development applications from the Council indicated that assessments were performed in compliance with relevant legislation, regulations and government guidance.

The Hills Shire Council has established processes to effectively support The Hills Shire Local Planning Panel.

The Hills Shire Council has met requirements to provide secretariat and other support to The Hills Shire Local Planning Panel as required under legislative and policy instruments. It has processes to ensure that development applications required to be referred to a planning panel are identified and monitored, supports identification and documentation of any conflicts of interest, and transparently documents decisions of the panel.

Our review of a sample of meeting records held across the audit period of review indicated that these requirements were met and were transparently documented. 

 

Conclusion – Department of Planning and Environment

The Department of Planning and Environment (DPE) has established processes that meet its statutory and policy requirements to support Sydney and regional planning panels.

DPE has established processes to provide secretariat and other support to planning panels. It has met requirements to provide administrative support to the panels through its planning panels secretariat including undertaking administrative functions, supporting recruitment of panel members, and addressing complaints about the panel processes.

DPE has not ensured collection of annual pecuniary interest declarations for all panel members for the three Sydney and regional planning panels in scope for this audit. DPE could not provide annual pecuniary interest declarations for part of the audit period for three of the 47 members of these panels, as is required by DPE's Code of Conduct for Regional Planning Panels.

DPE does not formally measure its effectiveness in providing support to panels, but panel chairs consulted as part of this audit advised that they had no concerns with the level of secretariat support provided by DPE.

DPE could do more to facilitate information sharing between panels and could formalise how it provides comparative information to panels to improve consistency and standardisation in approach and share good practice. DPE has identified these gaps in reviews of its services and functions and has a plan in place to address them.

DPE has effectively documented planning panel decisions and made them available to all stakeholders. It also effectively documented interests declared as part of consideration of development applications for in-scope panels. 


1 Prescribed councils within designated Sydney districts are required to refer contentious development applications to local planning panels for determination. If the proposed development is above a threshold for estimated cost of works, or meets other prescribed criteria, the EP&A Act may require it to be referred to a Sydney or regional planning panel.

This audit continues a series of audits examining the development assessment process in NSW local councils and is focused on the assessment and determination stages.

The Audit Office of New South Wales previously considered local government development assessments in our 2019 performance audit: 'Development assessment: pre-lodgement and lodgement in Camden Council and Randwick City Council'.

Appendix one – Response from agencies

Appendix two – Council profile: Byron Shire Council

Appendix three – Council profile: Northern Beaches Council

Appendix four – Council profile: The Hills Shire Council

Appendix five – About the audit 

Appendix six – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #370 - released 12 December 2022

 

Published

Actions for Regional NSW 2022

Regional NSW 2022

Environment
Industry
Planning
Asset valuation
Compliance
Financial reporting
Fraud
Information technology
Infrastructure
Internal controls and governance
Management and administration
Regulation
Risk
Shared services and collaboration

What the report is about

Result of the Regional NSW cluster agencies' financial statement audits for the year ended 30 June 2022.

What we found

Unmodified audit opinions were issued for Regional NSW cluster agencies. Two audits are ongoing.

What the key issues were

The Department of Regional NSW (the department) and Local Land Services (LLS) accepted changes to their office leasing arrangements managed by Property NSW.

These changes resulted in the collective derecognition of $100.6 million of rights-of-use-assets and $110.4 million of lease liabilities.

In 2021–22, the cluster agencies continued to assist communities in their recovery from recent weather emergencies, including significant flooding in New South Wales.

The Northern Rivers Reconstruction Corporation was established in May 2022 to rebuild communities in the Lismore and Northern Rivers region impacted by floods.

The number of matters reported to management decreased from 36 in 2020–21 to 14 in 2021–22.

Five moderate risk issues were identified and 14% of reported issues were repeat issues.

One moderate risk issue was a repeat issue related to Local Land Services' annual fair value assessment of the asset improvements on land reserves used for moving stock.

This report provides Parliament and other users of the Regional NSW cluster financial statements with the results of our audits, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision-making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Regional NSW cluster (the cluster) for 2022.

Section highlights

  • Unqualified audit opinions were issued on the financial statements of cluster agencies. Two audits are ongoing.
  • Cluster agencies completed all required early close procedures.
  • Changes to accommodation arrangements managed by Property NSW on behalf of the department and cluster agencies resulted in the collective derecognition of approximately $100.6 million in right-of-use assets and corresponding lease liabilities totalling $110.4 million from the balance sheets of these agencies.
  • Cluster agencies continue to provide financial assistance to communities affected by natural disasters.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision-making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the Regional NSW cluster.

Section highlights

  • The 2021–22 audits identified five moderate issues across the cluster. One moderate risk issue was a repeat issue related to Local Land Services' annual fair value assessment of the asset improvements on land reserves used for moving stock.
  • Of the four newly identified moderate rated issues, one related to internal control deficiencies and improvements and three related to financial reporting.
  • The number of findings reported to management has decreased from 36 in 2020–21 to 14 in 2021–22.

Published

Actions for Health 2022

Health 2022

Health
Whole of Government
Asset valuation
Compliance
Cyber security
Financial reporting
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Risk
Service delivery
Shared services and collaboration
Workforce and capability

What the report is about

Result of Health cluster (the cluster) agencies' financial statement audits for the year ended 30 June 2022.

What we found

Unmodified audit opinions were issued for the financial statements for all Health cluster agencies.

The COVID-19 pandemic continued to increase the complexity and number of accounting matters faced by the cluster. The total gross value of corrected misstatements in 2021–22 was $353.3 million, of which $186.7 million related to an increase in the impairment provision for Rapid Antigen Tests (RATs).

A qualified audit opinion was issued on the Annual Prudential Compliance Statement related to five residential aged care facilities. There were 20 instances (19 in 2020–21) of non-compliance with the prudential responsibilities within the Aged Care Act 1997.

What the key issues were

The total number of matters we reported to management across the cluster decreased from 116 in 2020–21 to 67 in 2021–22. Of the 67 issues raised, four were high risk (three in 2020-21) and 37 were moderate risk (57 in 2020–21). Nearly half of all control deficiencies reported in 2021–22 were repeat issues.

Three unresolved high-risk issues were:

  • COVID-19 inventories impairment – we continued to identify issues relating to management’s impairment model which relies on anticipated future consumption patterns. RATs had not been assessed for impairment.

  • Asset capitalisation threshold – management has not reviewed the appropriateness of the asset capitalisation threshold since 2006.

  • Forced-finalisation of HealthRoster time records – we continued to observe unapproved rosters being finalised by system administrators so payroll can be processed on time. 2.6 million time records were processed in this way in 2021–22.

What we recommended

  • COVID-19 inventories impairment – ensure consumption patterns are supported by relevant data and plans.

  • Assets capitalisation threshold – undertake further review of the appropriateness of applying a $10,000 threshold before capitalising expenditure on property, plant and equipment.

  • Forced-finalisation of HealthRoster time records – develop a methodology to quantify the potential monetary value of unapproved rosters being finalised.

This report provides Parliament and other users of Health cluster (the cluster) agencies' financial statements with the results of our audits, analysis, conclusions and recommendations in the following areas:

  • financial reporting

  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision-making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Health cluster (the cluster) for 2022.

Section highlights

  • Unqualified audit opinions were issued for all cluster agencies required to prepare general purpose financial statements.

  • The total gross value of corrected monetary misstatements for 2021–22 was $353.3 million, of which, $186.7 million related to an increase in the impairment provision for Rapid Antigen Tests.

  • A qualified audit opinion was issued on the ministry's Annual Prudential Compliance Statements.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision-making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the cluster.

Section highlights

  • The total number of internal control deficiencies has decreased from 116 in 2020–21 to 67 in 2021–22. Of the 67 issues raised in 2021–22, four were high (2020–21: 3) and 37 were moderate (2020–21: 57); with nearly half of all control deficiencies reported in 2021–22 being repeat issues.

  • The following four issues were reported in 2021–22 as high risk:

    • impairment of COVID-19 inventories

    • inadequate review over the appropriateness of asset capitalisation threshold

    • forced-finalisation of HealthRoster time records

    • COVID-19 vaccination inventories – data quality issue at 31 March 2022.

  • Management of excessive leave balances and poor quality or lack of documentation supporting key agreements continued to be the key repeat issues observed in the 2021–22 financial reporting period.

Appendix one – Misstatements in financial statements submitted for audit

Appendix two – Early close procedures

Appendix three – Timeliness of financial reporting

Appendix four – Financial data

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Premier and Cabinet 2022

Premier and Cabinet 2022

Whole of Government
Premier and Cabinet
Compliance
Cyber security
Financial reporting
Information technology
Internal controls and governance
Management and administration
Procurement
Risk

What the report is about

Result of the Premier and Cabinet cluster financial statement audits for the year ended 30 June 2022. 

What we found

Unmodified audit opinions were issued for all Premier and Cabinet cluster agencies.

The machinery of government changes within the Premier and Cabinet cluster resulted in the transfer of net assets of $1 billion from the Department of Premier and Cabinet.

The Department of Premier and Cabinet, Public Service Commission and Parliamentary Counsel's Office accepted changes to their office leasing arrangements managed by Property NSW. These changes resulted in the collective de-recognition of $167.3 million of right-of-use assets, $225.1 million in lease liabilities and recognition of $47.8 million of other gains/losses. 

What the key issues were

The number of issues we reported to management decreased. 

Forty per cent of issues were repeated from the prior year.

Four moderate risk issues were reported in the management letters for Department of Premier and Cabinet and New South Wales Electoral Commission. Three out of the four moderate risk issues were repeat issues. 

The repeat issues related to internal control deficiencies in agencies' including lack of updated procurement policies and procedures and information technology general controls.

Fast facts 

The Premier and Cabinet cluster comprises seven agencies, delivering the government's objectives and facilitating stewardship of the public service.

  • $0.2b property, plant and equipment as at 30 June 2022
  • $3b total expenditure incurred in 2021–22
  • 100% unqualified audit opinions issued on agencies’ 30 June 2022 financial statements
  • moderate risk findings identified
  • 15 monetary misstatements reported in 2021–22
  • 40% of reported issues were repeat issues

This report provides Parliament and other users of the Premier and Cabinet’s financial statements with the results of our audits, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision-making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Premier and Cabinet cluster for 2022.

Section highlights

  • Unqualified audit opinions were issued on all the cluster agencies 2021–22 financial statements.
  • There were two corrected misstatements greater than $5 million.
  • Changes to accommodation arrangements managed by Property NSW on behalf of the department resulted in the collective derecognition of approximately $167.3 million in right of use assets and corresponding lease liabilities totalling $225.1 million from the balance sheets of these agencies.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the Premier and Cabinet cluster.

Section highlights

  • The 2021–22 audits identified four moderate risk issues across the cluster.
  • Three out of the four moderate risk issues were repeat issues.
  • The repeat issues related to password and security configuration and a lack of updated procurement policies and procedures.

Appendix one – Early close procedures

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Effectiveness of the Biodiversity Offsets Scheme

Effectiveness of the Biodiversity Offsets Scheme

Planning
Environment
Infrastructure
Internal controls and governance
Management and administration
Regulation

What the report is about

This audit examined whether the Department of Planning and Environment (DPE) and the Biodiversity Conservation Trust (BCT) have effectively designed and implemented the Biodiversity Offsets Scheme (‘the Scheme’) to compensate for the loss of biodiversity due to development.

Under the Biodiversity Conservation Act 2016, the Scheme enables landholders to establish in-perpetuity Biodiversity Stewardship Agreements on sites to generate credits for the unique biodiversity on that land. These credits can be sold to offset the negative impact of development on biodiversity.

What we found

DPE has not effectively designed core elements of the Scheme. DPE did not establish a clear strategic plan to guide the implementation of the Scheme.

The BCT has various roles in the Scheme but lacked safeguards against potential conflicts, creating risks to credit supply.

The effectiveness of its implementation has also been limited. Key concerns around the Scheme’s transparency, sustainability and integrity are yet to be fully resolved.

A market-based approach to biodiversity offsetting is central to the Scheme's operation but credit supply is lacking and poorly matched to growing demand. DPE has not established a clear, resourced plan to manage the shortage in credit supply. Data about the market, published by the DPE and the BCT, does not provide an adequate picture of credit supply, demand and price to readily support market participation.

These factors create a risk that biodiversity gains made through the Scheme will not be sufficient to offset losses resulting from development, and that the DPE will not be able to assess the Scheme’s overall effectiveness.

DPE is leading work with the BCT to improve the Scheme, but this is not yet guided by a long-term strategy with clear goals.

What we recommended

The audit made 11 recommendations to DPE and the BCT, focusing on:

  • a long-term strategic plan for the Scheme
  • improvements to the operation and transparency of the market and credit supply
  • frameworks to ensure the financial and ecological sustainability of biodiversity stewardship sites
  • enhanced public reporting and data management
  • resolving issues in conflicting governance and oversight.

 

 Fast facts

  • 96% –  proportion of developer demand for species credits not met by current supply
  • 97% – proportion of species credits that have never been traded on the biodiversity market
  • 60% – proportion of the 226 Biodiversity Stewardship sites under active land management
  • $90m – value of developers’ obligations paid directly into the Biodiversity Conservation Fund
  • 20% – proportion of developer obligations transferred to the BCT that have been acquitted.

The NSW Government's Biodiversity Outlook Report 2020 estimates that, without effective management, only 50% of species and 59% of ecological communities that are listed as threatened in New South Wales will still exist in 100 years. The NSW State of the Environment 2021 report identifies habitat destruction and native vegetation clearing as presenting the single greatest threat to biodiversity in the State.

According to the Organisation for Economic Co-operation and Development (OECD), biodiversity offsets are 'measurable conservation outcomes that result from actions designed to compensate for significant, residual biodiversity loss from development projects'. The OECD states that a feature of such schemes is that biodiversity offsets are intended to be implemented as the 'final step of a mitigation hierarchy' whereby reasonable first steps are taken to avoid and minimise the negative impacts.

The NSW Biodiversity Offsets Scheme was established in 2017 under the Biodiversity Conservation Act 2016 (the Act). The purpose of the Act is to 'maintain a healthy, productive and resilient environment for the greatest well-being of the community, now and into the future, consistent with the principles of ecologically sustainable development'.

The Department of Planning and Environment (DPE) designed and manages this Scheme. Under the Act, a feature of the Scheme is a 'market-based conservation mechanism through which the impacts to biodiversity can be offset.' The Scheme enables landholders to establish in-perpetuity Biodiversity Stewardship Agreements (BSAs) on sites to generate biodiversity credits, which can be sold to offset the negative impact of development on biodiversity. BSA sites are intended to be managed over the long term to generate the biodiversity gains required to offset the impact.

The Biodiversity Conservation Trust (BCT) monitors and supports landholders to manage BSA sites under the Scheme. This includes making payments to landholders from funds held in the Biodiversity Stewardship Payments Fund for undertaking the required biodiversity management actions.

This Scheme was preceded by several other offsetting schemes in New South Wales, including the BioBanking scheme that started in 2008. DPE has arrangements to transition sites, credits, and offset obligations from this and other previous schemes.

The current biodiversity credit market in New South Wales consists of 1394 different types of ecosystem credits, which are approved to be traded in 364 different offset trading groups, and 867 different species credits. Trading rules, set out in the Biodiversity Conservation Regulation 2017 (the Regulation), prioritise offsetting the obligations of a development with like-for-like ecosystem or species credits.

The Scheme is implemented through the planning system in New South Wales. Proposed development that involves the clearing of native vegetation, and meets certain thresholds, is required to undertake a Biodiversity Development Assessment Report. These reports determine an offset obligation, in biodiversity credits, to compensate for the biodiversity loss proposed. These reports are considered by consent authorities (such as a council, for local development, or by the Minister for Planning for major projects). An offset obligation is then included in the conditions of development approval.

In addition to establishing a market for trading between developers, with offset obligations, and landholders, who sell credits from their BSA sites, the Scheme allows developers to pay into the Biodiversity Conservation Fund and transfer their obligations to the BCT. This allows the developer to proceed with their project. The BCT must then meet these acquired obligations by buying the required credits, or by undertaking other approved activities set out in the Regulation. The BCT has more options than developers on how and when it acquits its obligations.

This audit examined whether DPE and the BCT have effectively designed and implemented the Biodiversity Offsets Scheme to compensate for the loss of biodiversity due to development.

Conclusion

The Department of Planning and Environment (DPE) has not effectively designed core elements of the NSW Biodiversity Offsets Scheme. DPE did not establish a clear strategy to develop the biodiversity credit market or determine whether the Scheme’s operation and outcomes are consistent with the purposes of the Biodiversity Conservation Act 2016.

The effectiveness of the Scheme's implementation by DPE and the BCT has been limited. A market-based approach to biodiversity offsetting is central to the Scheme's operation but credit supply is lacking and poorly matched to growing demand: this includes a potential undersupply of in-demand credits for numerous endangered species. Key concerns around the Scheme’s integrity, transparency, and sustainability are also yet to be fully resolved. As such, there is a risk that biodiversity gains made through the Scheme will not be sufficient to offset losses resulting from the impacts of development, and that DPE will not be able to assess the Scheme’s overall effectiveness.

DPE developed the Scheme following a 2014 review of the State's biodiversity legislation and building on previous offsetting arrangements in New South Wales. At the time the Scheme commenced in 2017, DPE lacked a strategic plan to guide its implementation, set clear outcomes and performance measures, and respond effectively to risks. DPE did establish a detailed scientific method for assessing biodiversity impacts under the Scheme and a system for accrediting assessors to undertake this technical work. These are important foundations for the robustness of the Scheme.

The Scheme has been in place for five years, but the biodiversity credit market is not well developed. Most credit types have never been traded. Also, according to DPE data, around 90% of demand cannot be matched to credit supply – and there is likely to be a substantial credit undersupply for at least seven endangered flora species, three endangered fauna species, and eight threatened ecological communities. Credit demand is projected to grow – especially in relation to the NSW Government’s $112.7 billion four-year infrastructure pipeline.

As with any market, potential participants need information about demand and price in order to understand risks and opportunities. But information about the biodiversity credit market, published by DPE and the BCT, does not provide an adequate picture of credit supply, demand and price to support market participation. This can create uncertainty for landholders who may be weighing the costs and benefits of establishing Biodiversity Stewardship Agreement (BSA) sites, and for development proponents who need to know whether they can purchase sufficient credits and at what price. Development proponents who lack market information are being incentivised to meet their offset obligations by paying into the Biodiversity Conservation Fund, which is managed by the BCT. This option provides developers with more certainty that enables them to progress their projects, but does not result in the development being offset until the BCT later acquits the obligation.

The BCT has multiple roles in the Scheme. These include setting-up and administering BSAs which generate credits, acquiring offset obligations from developers who pay into the Biodiversity Conservation Fund, and purchasing credits to meet its acquired obligations. There have been inadequate safeguards to mitigate the potential for conflicts between these roles. As the BCT directs its efforts towards facilitating BSA sites and purchasing credits to meet its obligations, there is a risk that government is insufficiently focused on supporting overall credit supply.

DPE has begun developing a credit supply strategy. Its absence, and a lack of clarity around responsibility for credit supply under the Scheme, has contributed to the significant risk of insufficient and poorly matched credits to meet the growing demand. The BCT's acquired obligations from developers have been increasing year-on-year, and are likely to continue to grow. 

There is a risk that the BCT will not have sufficient funds to acquit its growing obligations with like-for-like credits, which could result in sub-optimal biodiversity outcomes. The Scheme rules allow the BCT to acquit its obligations with measures other than like-for-like credits. DPE has not provided clear guidance to the BCT on when or how to do so, or how this would fulfil the 'no net loss' of biodiversity standard.

There are transparency and integrity risks to the Scheme. DPE does not maintain a public register of biodiversity credits with complete information, including credits' transaction histories, consistent with the legislative intent for a single register. DPE also does not have ready access to information to check that developments have been acquitted with the required credits.

Risks to the sustainability of the Scheme and its outcomes remain. DPE and the BCT have not yet implemented a decision-making and intervention framework to ensure adequate initial and ongoing funding for the long-term management of new and existing BSA sites. DPE also did not collect ecological data from sites under previous schemes before they were transitioned, and BCT only introduced ecological monitoring requirements for new BSA sites in March 2021. The lack of monitoring requirements creates a risk that the biodiversity gains, which BSA sites are required to generate to offset biodiversity losses, will not be measured and achieved under the Scheme.

This section presents an overview of the status of the biodiversity credit market in New South Wales. It describes development of the market under the Scheme in the context of transitional arrangements from previous schemes, and the extent of market participation and transactions to date. It also presents information about emerging trends in credit demand and supply.

Background

A purpose of the Biodiversity Conservation Act 2016 (the Act) is to establish a market-based conservation mechanism through which impacts on biodiversity can be offset. Sufficient credits of appropriate types, which are well matched to demand, are necessary for enough transactions to inform prices and enable efficient like-for-like offsetting. For transactions to occur efficiently in the market, participants require reliable and easy-to-access information about supply, demand and price.

The Scheme was established in 2017 with an existing credit supply and offset obligations (credit demand) as regulations had been introduced to preserve and transition credits and obligations from previous schemes including the BioBanking Scheme, which started in 2008.

Credits under the BioBanking scheme are referred to as 'BBAM credits', and credits under the current Scheme are referred to as 'BAM credits'. BBAM credits are still available, and the transitional arrangements enable DPE to determine the 'reasonable equivalence' of these to the current Scheme's credit numbers and classes. DPE has stated that reasonable equivalence of credits is based on ecological not financial equivalence. 

This section assesses the clarity and alignment of the goals of the Scheme to key features of its design and operations. It also examines structural elements of the Scheme that aim to maintain integrity within administering agencies, and the status of actions to address risks or issues.

Background

The Biodiversity Conservation Act 2016 (the Act) sets out the legal framework for the Scheme. Given the complexities, financial interests, and range of stakeholders associated with the Scheme, it requires strong safeguards. Transparency and assurances around the Scheme's integrity are also relevant to participants' confidence in it, which in turn is important for market development.

Core components of the Scheme, identified in section 1.3 of the Act, are to be consistent with the ‘principles of ecologically sustainable development’.

The Act and other administrative arrangements of government allocate responsibility to DPE and the Minister for Environment and Heritage for the Scheme’s design and elements of its implementation. This includes responsibility for the Scheme’s policy, legislative and regulatory framework.

Responsibility is allocated to the BCT for implementing and operating certain elements of the Scheme. This includes administering Biodiversity Stewardship Agreements (which generate credits) and securing offsets on behalf of development proponents who pay into the Biodiversity Conservation Fund to meet their offset obligations.

This broad legislative framework is not intended to detail responsibilities for the full range of roles and activities that agencies need to take to implement and regulate the Scheme effectively, and ensure its good governance. Agencies should do this as part of sound and transparent public administration. 

This section assesses how effectively components of the Scheme have been designed and are being implemented to provide assurance that the impacts of development are being avoided and minimised such that only ‘unavoidable’ impacts remain to be offset. The section also assesses whether the Scheme and its market embeds the necessary controls to ensure that obligations are offset as required.

Background

The Biodiversity Assessment Method, and the quality of its application by DPE-Accredited Assessors, is critical to the robustness the Scheme. The method is designed to be applied to avoid and minimise impacts at proposed development sites before identifying offset obligations. The effectiveness of Scheme outcomes requires that obligations are offset with the retirement of the necessary and appropriate credits.

The Biodiversity Conservation Act 2016 (the Act) requires the relevant Minister (the current Minister for Environment and Heritage) to establish a method for the purpose of assessing the impacts of actions on threatened species and ecological communities.

The Act also specifies that this method must be applied by an accredited person. DPE is responsible for the design and implementation of this accreditation system, arrangements for which are set out in an instrument under the Act.

A Biodiversity Development Assessment Report is a report by a DPE-Accredited Assessor using the Biodiversity Assessment Method. These reports assess the biodiversity impacts of the proposed development and establish offset obligations as part of the development approval process. It is important that local councils and other development consent authorities understand and can assess the quality of these reports.

DPE manages the process of ‘retiring’ credits against the identified offset obligations. Once a credit is retired it cannot be reused to acquit another obligation, which is critical to Scheme outcomes. DPE is also responsible for maintaining records of credit transactions, which results in a legally binding transfer of credit ownership from seller to buyer. 

This section assesses how effectively the supply of biodiversity credits has been supported by encouraging and enabling landholders to participate in the Scheme. It also assesses whether sufficient action is underway to address issues and risks to the establishment of BSA sites, especially in the context of known credit supply issues (section 2).

Background

Credit supply is generated when a landholder establishes a Biodiversity Stewardship Agreement (BSA) on their land. Establishing a BSA site requires landholders agree to an in-perpetuity management plan, so it is important that they have sufficient support and access to relevant information about risks and opportunities when deciding to do so. Ensuring adequate credits supply underpins the Scheme's ability to deliver the intended biodiversity outcomes.

A landholder establishes an offset site through a BSA, which is a legal agreement with the Minister of Environment and Heritage (delegated to the Biodiversity Conservation Trust). The BSA is registered on the title of the land.

DPE-Accredited Assessors develop Biodiversity Stewardship Site Assessment Reports, which are submitted by landholders to the BCT as part of the BSA application. These reports apply the Biodiversity Assessment Method to detail the number and types of credits that a BSA site is expected to generate by implementing a 20-year management plan. The BCT issues credits to landholders on registration of the BSA.

Ensuring an adequate and appropriate supply of credits is important so that like-for-like matches between credits and obligations can be efficiently secured in a timely way. This minimises the use of offset variation rules, and can avoid potential delays in developers securing appropriate offsets to meet their offset obligations. It also makes it easier for the BCT to locate the necessary credits to acquit the obligations it acquires from developers. 

This section assesses how effectively BSA sites, which need to be managed by landholders to generate the biodiversity gains represented by credits, are regulated and supported by the Biodiversity Conservation Trust. It also assesses whether actions have been taken to address identified risks to the suitability of funds required to ensure long-term BSA site management.

Background

For Biodiversity Stewardship Agreement (BSA) sites to achieve the expected biodiversity gains to offset losses from development impact, they need sufficient funding for the required management actions, and to be effectively regulated and supported over the long-term. Funding for these sites is generated through the returns on landholders' initial investment (Total Fund Deposit). The BCT is required to monitor landholders' compliance with BSAs and should also ensure ecological outcomes on sites are measured.

DPE and the BCT are responsible for developing and implementing a system of oversight to ensure the implementation of management actions at BSA sites is delivering the intended outcomes in a financially and environmentally sustainable way. The agencies' key mechanisms for delivering this are:

  • calculating the costs of the required land management actions in perpetuity
  • annual reporting systems for monitoring compliance with land management requirements
  • reporting systems for monitoring ecological outcomes arising from land management actions.

Landholders are required to pay the required Total Fund Deposit amount for their BSA accounts into the Biodiversity Stewardship Payments Fund, which is held in trust and managed by the BCT. A costing tool is used by landholders to calculate the value of the deposit, based on the required management payments (in perpetuity), administrative fees, and the discount rate applied.

The Total Fund Deposit can be paid upfront but is usually paid from the proceeds of the sale of credits. Once this occurs the BSA site becomes 'active' and management payments commence to enable the landholder to undertake the required management actions. BSA sites that have not yet sold enough credits to make the deposit are 'passive' sites that do not require active land management.

Sites in passive management for an extended duration present risks to biodiversity outcomes, and potentially to Scheme integrity, if the quality of credits is undermined due to an absence of active site management. 

Appendix one – Response from agencies 

Appendix two – Like-for-like, variation and ancillary rules

Appendix three – Detail on progress of the IIAP

Appendix four – About the audit 

Appendix five – Performance auditing 

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #367 - released 30 August 2022

Published

Actions for Audit Insights 2018-2022

Audit Insights 2018-2022

Community Services
Education
Environment
Finance
Health
Industry
Justice
Local Government
Premier and Cabinet
Planning
Transport
Treasury
Universities
Whole of Government
Asset valuation
Cross-agency collaboration
Compliance
Cyber security
Financial reporting
Fraud
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Regulation
Risk
Service delivery
Shared services and collaboration
Workforce and capability

What the report is about

In this report, we have analysed the key findings and recommendations from our audit reports over the past four years.

This analysis includes financial audits, performance audits, and compliance audits of state and local government entities that were tabled in NSW Parliament between July 2018 and February 2022.

The report is framed by recognition that the past four years have seen significant challenges and emergency events.

The scale of government responses to these events has been wide-ranging, involving emergency response coordination, service delivery, governance and policy.

The report is a resource to support public sector agencies and local government to improve future programs and activities.

What we found

Our analysis of findings and recommendations is structured around six key themes:

  • Integrity and transparency
  • Performance and monitoring
  • Governance and oversight
  • Cyber security and data
  • System planning for disruption
  • Resource management.

The report draws from this analysis to present recommendations for elements of good practice that government agencies should consider in relation to these themes. It also includes relevant examples from recent audit reports.

In this report we particularly call out threats to the integrity of government systems, processes and governance arrangements.

The report highlights the need for balanced advice to government on options and risks, for transparent documentation and reporting of directions and decisions, and for early and open sharing of information with integrity bodies and audit.

A number of the matters highlighted in this report are similar to those described in our previous Insights Report, (Performance Audit Insights: key findings from 2014–2018) specifically in relation to cyber and information security, to performance measurement, reporting and evaluation, and system and workforce planning and capability.

Fast facts

  • 72 audits included in the Audit Insights 2018–2022 analysis
  • 4 years of audits tabled by the Auditor-General for New South Wales
  • 6 key themes for Audit Insights 2018–2022.

picture of Margaret Crawford Auditor-General for New South Wales in black dress with city skyline as backgroundI am pleased to present the Audit Insights 2018–2022 report. This report describes key findings, trends and lessons learned from the last four years of audit. It seeks to inform the New South Wales Parliament of key risks identified and to provide insights and suggestions to the agencies we audit to improve performance across the public sector.

The report is framed by a very clear recognition that governments have been responding to significant events, in number, character and scale, over recent years. Further, it acknowledges that public servants at both state and council levels generally bring their best selves to work and diligently strive to deliver great outcomes for citizens and communities. The role of audit in this context is to provide necessary assurance over government spending, programs and services, and make suggestions for continuous improvement.

A number of the matters highlighted in this report are similar to those described in our previous Insights Report, (Performance Audit Insights: key findings from 2014–2018) specifically in relation to cyber and information security, to performance measurement, reporting and evaluation, and system and workforce planning and capability.

However, in this report we particularly call out threats to the integrity of government systems, processes and governance arrangements. We highlight the need for balanced advice to government on options and risks, for transparent documentation and reporting of directions and decisions, and for early and open sharing of information with integrity bodies and audit. Arguably, these considerations are never more important than in an increasingly complex environment and in the face of significant emergency events and they will be key areas of focus in our future audit program.

While we have acknowledged the challenges of the last few years have required rapid responses to address the short-term impacts of emergency events, there is much to be learned to improve future programs. I trust that the insights developed in this report provide a helpful resource to public sector agencies and local government across New South Wales. I would be pleased to receive any feedback you may wish to offer.

Margaret Crawford
Auditor-General for New South Wales

Integrity and transparency Performance and monitoring Governance and oversight Cyber security and data System planning Resource management
Insufficient documentation of decisions reduces the ability to identify, or rule out, misconduct or corruption. Failure to apply lessons learned risks mistakes being repeated and undermines future decisions on the use of public funds. The control environment should be risk-based and keep pace with changes in the quantum and diversity of agency work. Building effective cyber resilience requires leadership and committed executive management, along with dedicated resourcing to build improvements in cyber security and culture. Priorities to meet forecast demand should incorporate regular assessment of need and any emerging risks or trends. Absence of an overarching strategy to guide decision-making results in project-by-project decisions lacking coordination. Governments must weigh up the cost of reliance on consultants at the expense of internal capability, and actively manage contracts and conflicts of interest.
Government entities should report to the public at both system and project level for transparency and accountability. Government activities benefit from a clear statement of objectives and associated performance measures to support systematic monitoring and reporting on outcomes and impact. Management of risk should include mechanisms to escalate risks, and action plans to mitigate risks with effective controls. In implementing strategies to mitigate cyber risk, agencies must set target cyber maturity levels, and document their acceptance of cyber risks consistent with their risk appetite. Service planning should establish future service offerings and service levels relative to current capacity, address risks to avoid or mitigate disruption of business and service delivery, and coordinate across other relevant plans and stakeholders. Negotiations on outsourced services and major transactions must maintain focus on integrity and seeking value for public funds.
Entities must provide balanced advice to decision-makers on the benefits and risks of investments. Benefits realisation should identify responsibility for benefits management, set baselines and targets for benefits, review during delivery, and evaluate costs and benefits post-delivery. Active review of policies and procedures in line with current business activities supports more effective risk management. Governments hold repositories of valuable data and data capabilities that should be leveraged and shared across government and non-government entities to improve strategic planning and forecasting. Formal structures and systems to facilitate coordination between agencies is critical to more efficient allocation of resources and to facilitate a timely response to unexpected events. Transformation programs can be improved by resourcing a program management office.
Clear guidelines and transparency of decisions are critical in distributing grant funding. Quality assurance should underpin key inputs that support performance monitoring and accounting judgements. Governance arrangements can enable input into key decisions from both government and non-government partners, and those with direct experience of complex issues.     Workforce planning should consider service continuity and ensure that specialist and targeted roles can be resourced and allocated to meet community need.
Governments must ensure timely and complete provision of information to support governance, integrity and audit processes.          
Read more Read more Read more Read more Read more Read more

 

This report brings together a summary of key findings arising from NSW Audit Office reports tabled in the New South Wales Parliament between July 2018 and February 2022. This includes analysis of financial audits, performance audits, and compliance audits tabled over this period.

  • Financial audits provide an independent opinion on the financial statements of NSW Government entities, universities and councils and identify whether they comply with accounting standards, relevant laws, regulations, and government directions.
  • Performance audits determine whether government entities carry out their activities effectively, are doing so economically and efficiently, and in accordance with relevant laws. The activities examined by a performance audit may include a selected program or service, all or part of an entity, or more than one government entity. Performance audits can consider issues which affect the whole state and/or the local government sectors.
  • Compliance audits and other assurance reviews are audits that assess whether specific legislation, directions, and regulations have been adhered to.

This report follows our earlier edition titled 'Performance Audit Insights: key findings from 2014–2018'. That report sought to highlight issues and themes emerging from performance audit findings, and to share lessons common across government. In this report, we have analysed the key findings and recommendations from our reports over the past four years. The full list of reports is included in Appendix 1. The analysis included findings and recommendations from 58 performance audits, as well as selected financial and compliance reports tabled between July 2018 and February 2022. The number of recommendations and key findings made across different areas of activity and the top issues are summarised at Exhibit 1.

The past four years have seen unprecedented challenges and several emergency events, and the scale of government responses to these events has been wide-ranging involving emergency response coordination, service delivery, governance and policy. While these emergencies are having a significant impact today, they are also likely to continue to have an impact into the future. There is much to learn from the response to those events that will help the government sector to prepare for and respond to future disruption. The following chapters bring together our recommendations for core elements of good practice across a number of areas of government activity, along with relevant examples from recent audit reports.

This 'Audit Insights 2018–2022' report does not make comparative analysis of trends in public sector performance since our 2018 Insights report, but instead highlights areas where government continues to face challenges, as well as new issues that our audits have identified since our 2018 report. We will continue to use the findings of our Insights analysis to shape our future audit priorities, in line with our purpose to help Parliament hold government accountable for its use of public resources in New South Wales.

Appendix one – Included reports, 2018–2022

Appendix two – About this report

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.