Actions for Machinery of government changes

Machinery of government changes

Premier and Cabinet
Treasury
Whole of Government
Management and administration
Project management

What the report is about

The term ‘machinery of government’ refers to the way government functions and responsibilities are organised.

The decision to make machinery of government changes is made by the Premier. Changes may be made for a range of reasons, including to support the policy and/or political objectives of the government of the day.

Larger machinery of government changes typically occur after an election or a change of Premier.

This report assessed how effectively the Department of Planning, Industry and Environment (DPIE) and the Department of Regional NSW (DRNSW) managed their 2019 and 2020 machinery of government changes, respectively. It also considered the role of the Department of Premier and Cabinet (DPC) and NSW Treasury in overseeing machinery of government changes.

What we found

The anticipated benefits of the changes were not articulated in sufficient detail and the achievement of benefits has not been monitored. The costs of the changes were not tracked or reported.

DPC and NSW Treasury provided principles to guide implementation but did not require departments to collect or report information about the benefits or costs of the changes.

The implementation of the machinery of government changes was completed within the set timeframes, and operations for the new departments commenced as scheduled.

Major implementation challenges included negotiation about the allocation of corporate support staff and the integration of complex corporate and ICT systems.

What we recommended

DPC and NSW Treasury should:

  • consolidate existing guidance on machinery of government changes into a single document that is available to all departments and agencies
  • provide guidance for departments and agencies to use when negotiating corporate services staff transfers as a part of machinery of government changes, including a standard rate for calculating corporate services requirements
  • progress work to develop and implement common processes and systems for corporate services in order to support more efficient movement of staff between departments and agencies.

Fast facts

  • $23.7m is the estimated minimum direct cost of the 2019 DPIE changes to date, noting additional ICT costs will be incurred
  • $4.0m is the estimated minimum direct cost of the 2020 DRNSW changes, with an estimated $2.7 million ongoing annual cost
  • 40+ NSW Government entities affected by the 2019 machinery of government changes

The term ‘machinery of government’ refers to the way government functions and responsibilities are allocated and structured across government departments and agencies. A machinery of government change is the reorganisation of these structures. This can involve establishing, merging or abolishing departments and agencies and transferring functions and responsibilities from one department or agency to another.

The decision to make machinery of government changes is made by the Premier. These changes may be made for a range of reasons, including to support the policy and/or political objectives of the government of the day. Machinery of government changes are formally set out in Administrative Arrangements Orders, which are prepared by the Department of Premier and Cabinet, as instructed by the Premier, and issued as legislative instruments under the Constitution Act 1902.

The heads of agencies subject to machinery of government changes are responsible for implementing them. For more complex changes, central agencies are also involved in providing guidance and monitoring progress.

The NSW Government announced major machinery of government changes after the 2019 state government election. These changes took place between April and June 2019 and involved abolishing five departments (Industry; Planning and Environment; Family and Community Services; Justice; and Finance, Services and Innovation) and creating three new departments (Planning, Industry and Environment; Communities and Justice; and Customer Service). This also resulted in changes to the 'clusters' associated with departments. The NSW Government uses clusters to group certain agencies and entities with related departments for administrative and financial management. Clusters do not have legal status. Most other departments that were not abolished had some functions added or removed as a part of these machinery of government changes. For example, the functions relating to regional policy and service delivery in the Department of Premier and Cabinet were moved to the new Department of Planning, Industry and Environment.

Our Report on State Finances 2019, tabled in October 2019, outlined these changes and identified several issues that can arise from machinery of government changes if risks are not identified early and properly managed. These include: challenges measuring the costs and benefits of machinery of government changes; disruption to services due to unclear roles and responsibilities; and disruption to control environments due to staff, system and process changes.

In April 2020, the Department of Regional NSW was created in a separate machinery of government change. This involved moving functions and agencies related to regional policy and service delivery from the Department of Planning, Industry and Environment into a standalone department.

This audit assessed how effectively the Department of Planning, Industry and Environment (DPIE) and the Department of Regional NSW (DRNSW) managed their 2019 and 2020 machinery of government changes, respectively. It also considered the role of the Department of Premier and Cabinet and NSW Treasury in overseeing machinery of government changes. The audit investigated whether:

  • DPIE and DRNSW have integrated new responsibilities and functions in an effective and timely manner
  • DPIE and DRNSW can demonstrate the costs of the machinery of government changes
  • The machinery of government changes have achieved or are achieving intended outcomes and benefits.
Conclusion

It is unclear whether the benefits of the machinery of government changes that created the Department of Planning, Industry and Environment (DPIE) and the Department of Regional NSW (DRNSW) outweigh the costs. The anticipated benefits of the changes were not articulated in sufficient detail and the achievement of directly attributable benefits has not been monitored. The costs of the changes were not tracked or reported. The benefits and costs of the machinery of government changes were not tracked because the Department of Premier and Cabinet (DPC) and NSW Treasury did not require departments to collect or report this information. The implementation of the machinery of government changes was completed within the set timeframes, and operations for the new departments commenced as scheduled. This was achieved despite short timelines and no additional budget allocation for the implementation of the changes.

The rationale for establishing DPIE was not documented at the time of the 2019 machinery of government changes and the anticipated benefits of the change were not defined by the government or the department. For DRNSW, the government’s stated purpose was to provide better representation and support for regional areas, but no prior analysis was conducted to quantify any problems or set targets for improvement. Both departments reported some anecdotal benefits linked to the machinery of government changes. However, improvements in these areas are difficult to attribute because neither department set specific measures or targets to align with these intended benefits. Since the machinery of government changes were completed, limited data has been gathered to allow comparisons of performance before and after the changes.

DPC and NSW Treasury advised that they did not define the purpose and benefits of the machinery of government changes, or request affected departments to do so, because these were decisions of the government and the role of the public service was to implement the decisions.

We have attempted to quantify some of the costs of the DPIE and DRNSW changes based on the information the audited agencies could provide. This information does not capture the full costs of the changes because some costs, such as the impact of disruption on staff, are very difficult to quantify, and the costs of ICT separation and integration work may continue for several more years. Noting these limitations, we estimate the initial costs of these machinery of government changes are at least $23.7 million for DPIE and $4.0 million for DRNSW. For DPIE, this is predominantly made up of ICT costs and redundancy payments made around the time of the machinery of government change. For DRNSW it includes ICT costs and an increase in senior executive costs for a standalone department, which we estimate is an ongoing cost of at least $1.9 million per year.

For the DPIE machinery of government change, there were risks associated with placing functions and agencies that represent potentially competing policy interests within the same 'cluster', such as environment protection and industry. We did not see evidence of plans to manage these issues being considered by DPIE as a part of the machinery of government change process.

The efficiency of machinery of government changes could be improved in several ways. This includes providing additional standardised guidance on the allocation of corporate functions and resources when agencies are being merged or separated, and consolidating guidance on defining, measuring and monitoring the benefits and costs of machinery of government changes.

Appendix one – Response from agencies

Appendix two – About the audit

Appendix three – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #359 - released (17 December 2021).

Published

Actions for Compliance with the NSW Cyber Security Policy

Compliance with the NSW Cyber Security Policy

Whole of Government
Compliance
Cyber security
Information technology

What the report is about

This audit assessed nine agencies’ compliance with the NSW Cyber Security Policy (CSP) including whether, during the year to 30 June 2020, the participating agencies:

  • met their reporting obligations under the CSP
  • reported accurate self-assessments of their level of maturity implementing the CSP’s requirements including the Australian Cyber Security Centre’s (ACSC) Essential 8.

What we found

Key elements to strengthen cyber security governance, controls and culture are not sufficiently robust and not consistently applied. The CSP is not achieving the objectives of improved cyber governance, controls and culture because:

  • the CSP does not specify a minimum level for agencies to achieve in implementing the 'mandatory requirements' or the Essential 8
  • the CSP does not require agencies to report their target levels, nor does it require risk acceptance decisions to be documented or formally endorsed
  • each participating agency had implemented one or more of the mandatory requirements in an ad hoc or inconsistent basis
  • none of the participating agencies had implemented all of the Essential 8 controls
  • agencies tended to over-assess their cyber security maturity - all nine participating agencies were unable to support all of their self-assessments with evidence
  • there is no monitoring of the adequacy or accuracy of agencies' self-assessments.

What we recommended

In this report, we repeat recommendations made in the 2019 and 2020 Central Agencies reports, that Cyber Security NSW and NSW Government agencies need to prioritise improvements to cyber security resilience as a matter of urgency.

Cyber Security NSW should:

  • monitor and report compliance with the CSP
  • require agencies to report the target and achieved levels of maturity
  • require agencies to justify why it is appropriate to target a low level of maturity
  • require the agency head to formally accept the residual risk
  • challenge agencies' target maturity levels.

Agencies should resolve discrepancies between their reported level of maturity and the level they are able to support with evidence.

Separately, the agencies we audited requested that we not disclose our audit findings. We reluctantly agreed to anonymise our findings, even though they are more than 12 months old. We are of the view that transparency and accountability to the Parliament of New South Wales are part of the solution, not the problem.

The poor levels of agency cyber security maturity are a significant concern. Improvement requires leadership and resourcing.

Fast facts

The NSW Cyber Security Policy requires agencies to report their level of maturity implementing the mandatory requirements, which includes the ACSC's Essential 8.

  • 100% of audited agencies failed to reach level one maturity for at least three of the Essential 8 controls.

  • 53% of mandatory requirements implemented in an ad hoc or inconsistent manner, or not at all.

  • 89 of the 104 reporting agencies across government met the reporting deadline of 31 August.

This report assesses whether state government agencies are complying with the NSW Cyber Security Policy. The audit was based on the level of compliance reported at 30 June 2020.

Our audit identified non-compliance and significant weaknesses against the government’s policy.

Audited agencies have requested that we not report the findings of this audit to the Parliament of New South Wales, even though the findings are more than 12 months old, believing that the audit report would expose their weaknesses to threat actors.

I have reluctantly agreed to modify my report to anonymise agencies and their specific failings because the vulnerabilities identified have not yet been remedied. Time, leadership and prioritised action should have been sufficient for agencies to improve their cyber safeguards. I am of the view that transparency and accountability to the Parliament is part of the solution, not the problem.

The poor levels of cyber security maturity are a significant concern. Improvement requires dedicated leadership and resourcing. To comply with some elements of the government’s policy agencies will have to invest in technical uplift and some measures may take time to implement. However, other elements of the policy do not require any investment in technology. They simply require leadership and management commitment to improve cyber literacy and culture. And they require accountability and transparency. Transparent reporting of performance is a key means to improve performance.

Cyber security is increasingly a focus of governments around Australia. The Australian Cyber Security Centre (ACSC) is the Australian Government’s lead agency for cyber security and is part of the Australian Signals Directorate, a statutory authority within the Australian Government’s Defence portfolio. The ACSC has advised that government agencies at all levels, as well as individuals and other organisations were increasingly targeted over the 2021 financial year1. The ACSC received over 67,500 cybercrime reports, a 13 per cent increase on the previous year. This equates to one reported cyber attack every eight minutes. They also noted that attacks by cyber criminals and state actors are becoming increasingly sophisticated and complex and that the attacks are increasingly likely to be categorised as ‘substantial’ in impact.

High profile attacks in Australia and overseas have included a sustained malware campaign targeted at the health sector2, a phishing campaign deploying emotet malware, spear phishing campaigns targeting people with administrator or other high-level access, and denial of service attacks. The continuing trend towards digital delivery of government services has increased the vulnerability of organisations to cyber threats.

The COVID-19 pandemic has increased these risks. It has increased Australian dependence on the internet – to work remotely, to access services and information, and to communicate and continue our daily lives. Traditional security policies within an organisation’s perimeter are harder to enforce in networks made up of home and other private networks, and assets the organisation does not manage. This has increased the cyber risks for NSW Government agencies.

In March 2020, Service NSW suffered two cyber security incidents in short succession. Technical analysis undertaken by the Department of Customer Service (DCS) concluded that these cyber breaches resulted from a phishing exercise through which external threat actors gained access to the email accounts of 47 staff members. These attacks resulted in the breach of a large amount of personal customer information contained in these email accounts. These attacks were the subject of the Auditor-General's report on Service NSW's handling of personal information tabled on 18 December 2020.

This audit also follows two significant performance audits. Managing cyber risks, tabled on 13 July 2021 found Transport for NSW and Sydney Trains were not effectively managing their cyber security risks. Integrity of data in the Births, Deaths and Marriages Register, tabled 7 April 2020 found that although there are controls in place to prevent and detect unauthorised access to, and activity in the register, there were significant gaps in these controls.

The NSW Cyber Security Policy (CSP) was issued by Cyber Security NSW, a business unit within the Department of Customer Service, and took effect from 1 February 2019. It applies to all NSW Government departments and public service agencies, including statutory authorities. Of the 104 agencies in the NSW public sector that self-assessed their maturity implementing the mandatory requirements, only five assessed their maturity at level three or above (on the five point maturity scale). This means that, according to their own self-assessments, 99 agencies practiced requirements within the framework in what the CSP’s maturity model describes as an ad hoc manner, or they did not practice the requirement at all. Cyber Security NSW and NSW Government agencies need to prioritise improvements to their cybersecurity and resilience as a matter of priority.

This audit looks specifically at the compliance of nine key agencies with the CSP. It looks at their achievement implementing the requirements of the policy, the accuracy of their self-assessments and the attestations they made as to their compliance with the CSP.

The CSP outlines the mandatory requirements to which all NSW Government departments and public service agencies must adhere. It seeks to ensure cyber security risks to agencies’ information and systems are appropriately managed. The key areas of responsibility for agencies are:

  • Lead - Agencies must implement cyber security planning and governance and report against the requirements outlined in the CSP and other cyber security measures.
  • Prepare - Agencies must build and support a cyber security culture across their agency and NSW Government more broadly.
  • Prevent - Agencies must manage cyber security risks to safeguard and secure their information and systems.
  • Detect/Respond/Recover - Agencies must improve their resilience including their ability to rapidly detect cyber incidents and respond appropriately.
  • Report - Agencies must report against the requirements outlined in the CSP and other cyber security measures.

DCS has only recommended, but not mandated the CSP for state owned corporations, local councils and universities.

NSW Government agencies must include an attestation on cyber security in their annual report and provide a copy to Cyber Security NSW by 31 August each year stating whether, for the preceding financial year, the agency has:

  • assessed its cyber security risks
  • appropriately addressed cyber security at agency governance forums
  • a cyber incident response plan that is integrated with the security components of business continuity arrangements, and the response plan has been tested during the previous 12 months (involving senior business executives)
  • certified the agency’s Information Security Management System (ISMS) or confirmed the agency’s Cyber Security Framework (CSF)
  • a plan to continuously improve the management of cyber security governance and resilience.

The purpose of the attestation is to focus the agency's attention on its cyber risks and the mitigation of those risks.

Agencies assess their level of compliance in accordance with a maturity model. The CSP does not mandate a minimum maturity threshold for any requirement, including implementation of the Australian Cyber Security Centre's (ACSC) Essential 8 Strategies to Mitigate Cyber Security Incidents (Essential 8).

Agencies are required to set a target maturity level based on their risk appetite for each requirement, seek continual improvement in their maturity, and annually assess their maturity on an ascending scale of one to five for all requirements (refer to Appendix two for the maturity model). Each control within the Essential 8 is assessed on an ascending scale of zero to three reflecting the agency's level of alignment with the strategy (refer to Appendix three for the maturity model).

Scope of this audit

We assessed whether agencies had provided accurate reporting on their level of maturity implementing the requirements of the CSP in a documented way and covering all their systems.

The scope of this audit covered nine agencies (the participating agencies). These agencies were selected because they are the lead agency in their cluster, or have a significant digital presence within their respective cluster. The list of participating agencies is in section 1.2. The audit aimed to determine whether, during the year to 30th June 2020, the participating agencies:

  • met their reporting obligations under the CSP
  • provided accurate reporting in self-assessments against the CSP’s mandatory requirements, including their implementation of the Australian Cyber Security Centre’s (ACSC) Essential 8
  • achieved implementation of mandatory requirements at maturity levels which meet or exceed the ‘level three - defined’ threshold (i.e. are documented and practiced on a regular and consistent basis).

While the audit does assess the accuracy of agency self-assessed ratings, the audit did not assess the appropriateness of the maturity ratings.

Conclusion

Key elements to strengthen cyber security governance, controls and culture are not sufficiently robust and not consistently applied. There has been insufficient progress to improve cyber security safeguards across NSW Government agencies.
The NSW CSP replaced the NSW Digital Information Security Policy from 1 February 2019. New requirements of the CSP were, inter alia, to strengthen cyber security governance, strengthen cyber security controls and improve cyber security culture.
The CSP is not achieving the objective of improved cyber governance, controls and culture because:
  • The CSP does not specify a minimum level for agencies to achieve in implementing the 'mandatory requirements' or the Essential 8 Strategies to Mitigate Cyber Security Incidents.
  • The CSP does not require agencies to report their target levels, nor does it require risk acceptance decisions to be documented or formally endorsed.
  • All of the participating agencies had implemented one or more of the mandatory requirements in an ad hoc or inconsistent basis.
  • None of the participating agencies had implemented all of the Essential 8 controls to at least level one.
  • Agencies tended to over-assess their cyber security maturity, with all nine participating agencies unable to support some of their self-assessments of compliance with one or more mandatory criteria. Optimistic assessment of the current state of cyber resilience undermines effective decision making and risk management in responding to cyber risks.
  • There is no systematised and formal monitoring, by either Cyber Security NSW or another agency, of the adequacy or accuracy of agencies' cyber self-assessment processes.

 

1. Key findings

The CSP allows agencies to determine their own level of maturity to implement the 'mandatory requirements', which can include not practicing a policy requirement or implementing a policy requirement on an ad hoc basis. These determinations do not need to be justified

Agencies can decide not to implement requirements of the CSP, or they can decide to implement them only in an informal or ad-hoc manner. The CSP allows agencies to determine their desired level of maturity in implementing the requirements on a scale of one to five - level one being 'initial – not practiced' and level five being 'optimised'. The desired level of maturity is determined by the agency based on their own assessment of the risk of the services they provide and the information they hold.

The reporting template for the 2019 version of the CSP stated that level three maturity - where a policy requirement is practiced on a regular and consistent basis and its processes are documented - was required for compliance with the CSP. This requirement was removed in the 2020 revision of the reporting template.

This CSP does not require the decisions on risk tolerance, or the timeframes agencies have set to implement requirements to be documented or formally endorsed by the agency head. There is no requirement to report these decisions to Cyber Security NSW.

Some comparable jurisdictions require formal risk acceptance decisions where requirements are not implemented. The NSW CSP does not have a similar formal requirement

Some jurisdictions, with a similar policy framework to NSW, require agencies to demonstrate reasons for not implementing requirements, and require agency heads to formally acknowledge the residual risk. The NSW CSP does not require these considerations to be documented, nor does it require an explicit acknowledgement and acceptance of the residual risk by the agency head or Cyber Security NSW. The NSW CSP does not require that the records of how agencies considered and decided which measures to adopt to be documented and auditable, limiting transparency and accountability of decisions made.

All of the participating agencies had implemented one or more of the mandatory requirements in an ad hoc or inconsistent basis

All of the participating agencies had implemented one or more of the mandatory requirements at level one or two. Maturity below level three typically means not all elements of the requirement have been implemented, or the requirements have been implemented on an ad-hoc or inconsistent basis.

None of the participating agencies has implemented all of the Essential 8 controls at level one – that is, only partly aligned with the intent of the mitigation strategy

Eight of the nine agencies we audited had not implemented any of the Essential 8 strategies to level three – that is, fully aligned with the intent of the mitigation strategy. At the time of this audit the ACSC advised that:

as a baseline organisations should aim to reach to reach Maturity Level Three for each mitigation strategy3.

The Australian Signals Directorate4 currently advises that, with respect to the Essential 8:

[even] level three maturity will not stop adversaries willing and able to invest enough time, money and effort to compromise a target. As such, organisations still need to consider the remainder of the mitigation strategies from the Strategies to Mitigate Cyber Security Incidents and the Australian Government Information Security Manual

All agencies failed to reach even level one maturity for at least three of the Essential 8.

Cyber Security NSW modified the ACSC model for implementation of the Essential 8

The NSW maturity model used for the Essential 8 does not fully align with the ACSC’s model. At the time of this audit the major difference was the inclusion of level zero in the NSW CSP maturity scale. Level zero broadly means that the relevant cyber mitigation strategy is not implemented or is not applied consistently. Level zero had been removed by the ACSC in February 2019 and was not part of the framework at the time of this audit. It was re-introduced in July 2021 when the ACSC revised the detailed criteria for each element of the essential 8 maturity model. The indicators to reach level one on the new ACSC model are more detailed, specific and rigorous than those currently prescribed for NSW Government agencies. Cyber Security NSW asserted the level zero on the CSP maturity scale:

is not identical to the level zero of the ACSC’s previous Essential 8 maturity model, but is a NSW-specific inclusion designed to prevent agencies incorrectly assessing as level one when they have not achieved that level.

Attestations did not accurately reflect whether agencies implemented the requirements

Of the nine participating agencies, seven did not modify the proforma wording in their attestation to reflect their actual situation. Despite known gaps in their implementation of mandatory requirements, these agencies stated that they had 'managed cyber security risks in a manner consistent with the Mandatory Requirements set out in the NSW Government Cyber Security Policy'. Only two agencies modified the wording of the attestation to reflect their actual situation.

Attestations should be accurate so that agencies’ and the government’s response to the risk of cyber attack is properly informed by an understanding of the gaps in agency implementation of the policy requirements and the Essential 8. Without accurate information about these gaps, subsequent decisions as to prioritisation of effort and deployment of resources are unlikely to effectively mitigate the risks faced by NSW Government agencies.

Participating agencies were not able to support all of their self-assessments with evidence and had overstated their maturity assessments, limiting the effectiveness of agency risk management approaches

Seven of the nine participating agencies reported levels of maturity against both the mandatory requirements and the Essential 8 that were not supported by evidence.

Each of the nine participating agencies for this audit had overstated their level of maturity against at least one of the 20 mandatory requirements. Seven agencies were not able to provide evidence to support their self-assessed ratings for the Essential 8 controls.

Where agency staff over-assess the current state of their cyber resilience, it can undermine the effectiveness of subsequent decision making by Agency Heads and those charged with governance. It means that actions taken in mitigating cyber risks are less likely to be appropriate and that gaps in implementing cyber security measures will remain, exposing them to cyber attack.

Agencies' self-assessments across government exposed poor levels of maturity in implementing the mandatory requirements and the Essential 8 controls

We reviewed the data 104 NSW agencies provided to Cyber Security NSW. The 104 agencies includes nine audited agencies referred to in more detail in this report. Our review of the 104 agency self-assessment returns submitted to Cyber Security NSW highlighted that, consistent with previous years, there remains reported poor levels of cyber security maturity. We reported the previous years’ self-assessments in the Central Agencies 2019 Report to Parliament and the Central Agencies 2020 Report to Parliament.

Only five out of the 104 agencies self-assessed that they had implemented all of the mandatory requirements at level three or above (against the five point scale). Fourteen agencies self-assessed that they had implemented each of the Essential 8 controls at level one maturity or higher (using Cyber NSW’s four point scale). The remainder reported at level zero for implementation of one or more of the Essential 8 controls, meaning that for the majority of agencies the cyber mitigation strategy has not been implemented, or is applied inconsistently.

Where agencies had reported in both 2019 and 2020, agencies’ self-assessments showed little improvement over the previous year’s self-assessments:

  • 14 agencies reported improvement across both the Essential 8 and the mandatory requirements
  • 8 agencies reported a net decline in both the Essential 8 and the mandatory requirements.

The poor levels of maturity in implementing the Essential 8 over the last couple of years is an area of significant concern that requires better leadership and resourcing to prioritise the required significant improvement in agency cyber security measures.

2. Recommendations

Cyber Security NSW should:

1. monitor and report compliance with the CSP by:

  • obtaining objective assurance over the accuracy of self-assessments
  • requiring agencies to resolve inaccurate or anomalous self-assessments where these are apparent

2. require agencies to report:

  • the target level of maturity for each mandatory requirement they have determined appropriate for their agency
  • the agency head's acceptance of the residual risk where the target levels are low

3. identify and challenge discrepancies between agencies' target maturity levels and the risks of the information they hold and services they provide

4. more closely align their policy with the most current version of the ACSC model.

Participating agencies should:

5. resolve the discrepancies between their reported level of maturity and the level they are able to demonstrate with evidence, and:

  • compile and retain in accessible form the artefacts that demonstrate the basis of their self-assessments
  • refer to the CSP guidance when determining their current level of maturity
  • ensure the attestations they make refer to departures from the CSP
  • have processes whereby the agency head and those charged with governance formally accept the residual cyber risks.

Repeat recommendation from the 2019 Central Agencies report and the 2020 Central Agencies report

6. Cyber Security NSW and NSW Government agencies need to prioritise improvements to their cyber security and resilience as a matter of urgency.


The objective of the CSP is to ensure cyber security risks are appropriately managed. However, meeting this objective depends on the requirements being implemented at all agencies to a level of maturity that addresses their specific cyber security risks. Agency systems and data are increasingly interconnected. If an agency does not implement the requirements, or implements them only in an ad-hoc or informal way, an agency is more susceptible to their systems and data being compromised, which may affect the confidentiality of citizens' data and the reliability of services, including critical infrastructure services.

Agencies determine their own target level of maturity, which may mean the requirement is not addressed, or is addressed in an ad hoc or inconsistent way

While the CSP is mandatory for all agencies, it does not set a minimum maturity threshold for agencies to meet.

The reporting template issued in 2019 stated that agencies were required to reach level three maturity in order to comply with the CSP. The 2020 revision6 of the CSP and guidance indicates that level three maturity may not be sufficient to mitigate risks. It advises the agency may determine the level to which it believes it is suitable to implement the requirements, and allows for an agency to aim for a target level of maturity less than level three. The agency can set its optimal maturity level with reference to its risk tolerance with the objective that that aim ‘to be as high as possible’. However, ‘as high as possible’ does not necessarily mean ‘fully implemented’. The CSP contemplates that a lower level of maturity is sufficient if it aligns with the agency's risk tolerance.

2019 reporting template 2020 reporting template
‘A Mandatory Requirement is considered met if a maturity level of three is achieved. The Agency may choose to pursue a higher maturity level if required.

There is no mandated level for the Essential 8 Maturity reporting’.

‘There is no mandated maturity level for either the Mandatory Requirement reporting or Essential 8 reporting. Agencies need to risk-assess their optimal maturity and aim to be 'as high as possible’.
Source: Maturity Reporting Template v4.0, February 2019.
Source: CSP Reporting Template 2020, May 2020.

The Department of Customer Service asserts that while the quotes above were part of their annual templates and policy documents, their documents were incorrect. They assert that the policy has never required a minimum level of maturity to be reached. They have responded to our enquiries that:

…a level three maturity was not a requirement of the Policy or Maturity Model’ and ‘it is misleading to suggest it was a requirement of the Policy.

This audit found that, based on the 2020 reporting template there is no established minimum baseline. Consequently, because the Department of Customer Service had not established a minimum baseline agencies are able to target lower levels (providing they were within the agency’s own risk appetite), which includes targeting to not practice a CSP policy requirement, or to practice a CSP policy requirement on an ad hoc basis.

Where requirements are not implemented, documentation of formal acceptance of the residual risks by the agency head is not required

The New Zealand Government has an approach that is not dissimilar to NSW, in that it also identifies 20 mandatory requirements and allows for a risk based approach to implementation. However, the New Zealand approach puts more rigor around risk acceptance decisions.

The New Zealand Government requires that agencies that do not implement the requirements must demonstrate that a measure is not relevant for them. It requires agencies to document the rationale for not implementing the measure, including explicit acknowledgement of the residual risk by the agency head. They require these records to be auditable.

A security measure with a ‘must’ or ‘must not’ compliance requirement is mandatory. You must implement or follow mandatory security measures unless you can demonstrate that a measure is not relevant in your context.

Not using a security measure without due consideration may increase residual risk for your organisation. This residual risk needs to be agreed and acknowledged by your organisation head.

A formal auditable record of how you considered and decided which measures to adopt is required as part of the governance and assurance processes within your organisation.

Source: Overview of Protective Security Requirements, New Zealand Government (PSR-Overview-booklet.pdf (protectivesecurity.govt.nz).

The NSW CSP does not require these considerations to be documented or auditable and does not require an explicit acknowledgement or acceptance of the residual risk by the agency head.

None of the participating agencies achieved level three implementation for all mandatory risk prevention and mitigation requirements

Maturity level three is the minimum level whereby an agency has implemented documented processes that are practiced on a regular basis across their environment. An agency has not reached level three if the requirement is implemented on an ad-hoc or inconsistent basis, or if not all elements of the requirement have been implemented.

None of the participating agencies achieved level three implementation for all mandatory requirements.

The requirements of the CSP are organised into five sections. Agency implementation of these requirements is discussed in the next five sections of this report.

  • Lead: Planning and governance requirements. Section 2.1
  • Prepare: Cyber security culture requirements. Section 2.2
  • Prevent: Managing cyber incident prevention requirements. Section 2.3
  • Detect/Respond/Recover: Resilience requirements. Section 2.4
  • Report: Reporting requirements. Section 2.5.

 


6The reporting template issued in 2019 required agencies to reach level three, but that guidance was removed in the 2020 revision.

Appendix one – Response from agencies

Appendix two – The maturity model for the mandatory requirements

Appendix three – Essential 8 maturity model

Appendix four – About the audit

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Fast-tracked Assessment Program

Fast-tracked Assessment Program

Planning
Industry
Environment
Compliance
Internal controls and governance
Management and administration
Service delivery

What the report is about

This report examines the effectiveness of the Fast-tracked Assessment Program, administered by the Department of Planning, Industry and Environment (DPIE) between April 2020 and October 2020. 

The program aimed to support the construction industry during the COVID-19 crisis by accelerating the final assessment stages for planning proposals and development applications. 

DPIE selected projects and planning proposals for fast tracked assessment that demonstrated the potential to:

  • deliver jobs
  • progress to the next stage of development within six months of determination
  • deliver public benefit.

The audit assessed whether the Fast-tracked Assessment Program achieved its objectives while complying with planning controls.

What we found

Through tranches three to six of the program, DPIE successfully accelerated the final stages of 53 assessments. DPIE reported that 89 per cent of these proceeded to the next stage of development within six months.

Assessment of projects and planning proposals was compliant with legislation and other requirements. However, the audit found gaps in DPIE's management of conflicts of interest.

DPIE has not evaluated or costed the program and is not able to demonstrate the extent to which it provided support to the construction industry during COVID-19. 

Aspects of the program have been incorporated into longer term reforms to create a new level of transparency over the progress and status of planning assessments. 

What we recommended

DPIE should:

  • strengthen controls over conflicts of interest 
  • evaluate the Fast-tracked Assessment Program.

Fast facts

Construction industry support 
  • The program aimed at providing immediate support to the construction industry during the COVID-19 crisis
59 fast-tracked projects 
  • 59 projects and 42 planning proposals projects were assessed in six tranches
89% of all fast-tracked assessments in tranches three to six progressed to the next stage of the planning process within six months of determination

In April 2020, the Department of Planning, Industry and Environment (DPIE) introduced programs aimed at providing immediate support to the construction industry during the COVID-19 crisis. One of these was the Fast-tracked Assessment Program. This program identified planning proposals and development applications (DAs), across six tranches, that were partially-assessed and could be accelerated to determination.

In accordance with the program objectives, the planning proposals and DAs selected for fast-tracked assessment had to:

  • deliver jobs – particularly in the construction industry
  • be capable of progressing to the next stage of development within six months of determination
  • deliver public benefit.

At the same time, the Fast-tracked Assessment Program was to lay a foundation for future reform of the planning system by piloting changes in the assessment process that could be adopted in the medium to long term.

This audit assessed whether the Fast-tracked Assessment Program achieved its objectives while complying with planning controls. The audit focused on tranches three to six of the program, which were determined between July 2020 and October 2020. The rationale for focusing on these four tranches was that the program design had been slightly modified after the first two tranches to address identified risks.

Conclusion

Through tranches three to six of the Fast-tracked Assessment Program, DPIE successfully accelerated the final stages of 53 assessments. DPIE’s internal monitoring indicates that 31 DAs and 16 planning proposals selected in these tranches proceeded to the next stage of development within six months of determination. DPIE achieved this while also successfully managing the risk of non-compliance with planning controls arising from the accelerated process. While DPIE has incorporated components of the Fast-tracked Assessment Program into other longer-term reforms, it has not evaluated the program and is not able to demonstrate the extent to which the program provided support to the construction industry during COVID-19.

Between April and October 2020, DPIE adopted a case management approach to accelerate the final stages of assessment for 42 planning proposals and 59 DAs in six tranches. Tranches three to six were the focus of this audit and included 22 planning proposals and 31 DAs. Applicants involved in the program were expected to progress their projects to the next stage of development within six months of determination. While DPIE had no way of compelling applicants to do this and relied on non-binding commitments obtained from applicants, DPIE’s internal monitoring indicates that 47 of the 53 applicants selected in tranches three to six honoured this commitment.

Fast-tracked assessment only applied to the final stages of assessment and required DPIE staff and other stakeholders to work towards a determination deadline. DPIE effectively used a case management approach to manage the risk that the accelerated timeframe could result in planning controls not being fully compliant with legislation. There is some room for improvement in the process, as four of 28 staff assessing planning proposals and DAs had not lodged current conflict of interest declarations.

Based on the results of and learnings from the Fast-tracked Assessment Program, DPIE has incorporated some elements of the program into other longer-term reforms. There is now increased transparency about when applicants can expect to receive a planning determination and DPIE has also introduced a case management approach for strategic and high priority planning applications. Applicants benefiting from case-managed assessment are now required to commit to a formal service charter that specifies the obligations of both DPIE and the applicant.

DPIE has not evaluated the Fast-tracked Assessment Program to understand the costs and benefits of the program, nor which aspects of the program were most effective as a basis for future reform.

Appendix one – Response from agency

Appendix two – Planning determination pathways

Appendix three – About the audit

Appendix four – Performance auditing

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #354 - released (27 July 2021).