Actions for Design and administration of the WestInvest program

Design and administration of the WestInvest program

Premier and Cabinet
Treasury
Infrastructure
Management and administration

What this report is about

WestInvest is a $5 billion funding program announced in September 2021 to provide ‘local infrastructure to help communities hit hard by COVID-19’ in 15 local government areas (LGAs) selected by the government. It was divided into three parts: $3 billion for NSW government agency projects; $1.6 billion for competitive grants to councils and community groups; and $400 million for non-competitive grants to councils.

Following the change of government at the 2023 election, the program was renamed the Western Sydney Infrastructure Grants Program. Funding decisions made for the community and local government grants were retained, but multiple funding decisions for the NSW government projects were changed.

The audit objective was to assess the integrity of the design and implementation of the program and the award of program funding.

Findings

The design of the program lacked integrity because it was not informed by robust research or analysis to justify the commitment of public money to a program of this scale.

The then government did not have sufficient regard to the implications for the state's credit rating. A risk to the credit rating arose because the government may have been perceived to be using proceeds from major asset sales to fund new expenditure, rather than pay down its debt.

Decisions about program design were made by the then Treasurer's office without consultation with affected communities. The rationale for these decisions was not documented or made public.

For the NSW government projects, funding allocations did not follow advice from departments. Many funded projects did not meet the objectives of the program.

The two other rounds of the program were administered effectively, except for some gaps in documentation and quality assurance. The program guidelines did not require an equitable or needs-based distribution of funding across LGAs and there was a significant imbalance in funding between the 15 LGAs.

Recommendations

Our recommendations for the administration of future funding programs included:

  • considering whether competitive grants are the best way to achieve the program's purpose
  • completing program design and guidelines before announcements
  • ensuring adequate quality assurance.

We also recommended that when providing advice for submissions by Ministers to Cabinet, agencies should ensure that departmental advice is clearly identified and is distinct from other advice or political considerations.

 

Read the PDF report

Parliamentary reference - Report number #391 - released 28 February 2024

Published

Actions for Flood housing response

Flood housing response

Planning
Whole of Government
Community Services
Premier and Cabinet
Internal controls and governance
Management and administration
Procurement
Project management
Risk
Service delivery
Shared services and collaboration

What this report is about

Extreme rainfall across eastern Australia in 2021 and 2022 led to a series of major flood events in New South Wales.

This audit assessed how effectively the NSW Government provided emergency accommodation and temporary housing in response to the early 2022 Northern Rivers and late 2022 Central West flood events.

Responsible agencies included in this audit were the Department of Communities and Justice, NSW Reconstruction Authority, the former Department of Planning and Environment, the Department of Regional NSW and the Premier’s Department.

Findings

The Department of Communities and Justice rapidly provided emergency accommodation to displaced persons immediately following these flood events.

There was no plan in place to guide a temporary housing response and agencies did not have agency-level plans for implementing their responsibilities.

The NSW Government rapidly procured and constructed temporary housing villages. However, the amount of temporary housing provided did not meet the demand.

There is an extensive waitlist for temporary housing and the remaining demand in the Northern Rivers is unlikely to be met. The NSW Reconstruction Authority has not reviewed this list to confirm its accuracy.

Demobilisation plans for the temporary housing villages have been developed, but there are no long-term plans in place for the transition of tenants out of the temporary housing.

Agencies are in the process of evaluating the provision of emergency accommodation and temporary housing.

The findings from the 2022 State-wide lessons process largely relate to response activities.

Audit recommendations

The NSW Reconstruction Authority should:

  • Develop a plan for the provision of temporary housing.
  • Review the temporary housing waitlist.
  • Determine a timeline for demobilising the temporary housing villages.
  • Develop a strategy to manage the transition of people into long-term accommodation.
  • Develop a process for state-wide recovery lessons learned.

All audited agencies should:

  • Finalise evaluations of their role in the provision of emergency accommodation and temporary housing.
  • Develop internal plans for implementing their roles under state-wide plans.

Read the PDF report

Parliamentary reference - Report number #389 - released 22 February 2024

Published

Actions for Management of the Critical Communications Enhancement Program

Management of the Critical Communications Enhancement Program

Finance
Health
Justice
Whole of Government
Cyber security
Information technology
Infrastructure
Internal controls and governance
Project management
Risk
Service delivery
Shared services and collaboration

What the report is about

Effective radio communications are crucial to NSW's emergency services organisations.

The Critical Communications Enhancement Program (CCEP) aims to deliver an enhanced public safety radio network to serve the five emergency services organisations (ESOs), as well as a range of other users.

This report assesses whether the NSW Telco Authority is effectively managing the CCEP.

What we found

Where it has already been delivered (about 50% of the state), the enhanced network meets most of the requirements of ESOs.

The CCEP will provide additional infrastructure for public safety radio coverage in existing buildings agreed to with ESOs. However, radio coverage inside buildings constructed after the CCEP concludes will be at risk because building and fire regulations do not address the need for in-building public safety radio coverage.

Around 98% of radios connected to the network can be authenticated to protect against cloning, though only 42% are.

The NSW Telco Authority has not settled with ESOs on how call encryption will be used across the network. This creates the risk that radio interoperability between ESOs will not be maximised.

When completed, the public safety radio network will be the only mission critical radio network for ESOs. It is unclear whether governance for the ongoing running of the network will allow ESOs to participate in future network operational decisions.

The current estimated capital cost for the NSW Telco Authority to complete the CCEP is $1.293 billion. This is up from an estimated cost of $400 million in 2016. The estimated capital cost was not publicly disclosed until $1.325 billion was shown in the 2021–22 NSW Budget Papers.

We estimate that the full cost to government, including costs to the ESOs, of implementing the enhanced network is likely to exceed $2 billion.

We made recommendations about

  • The governance of the enhanced Public Safety Network (PSN) to support agency relationships.
  • The need to finalise a Traffic Mitigation Plan for when the network is congested.
  • The need to provide advice to the NSW Government about the regulatory gap for ensuring adequate network reach in future buildings.
  • The need to clarify how encryption and interoperability will work on the enhanced network.
  • The need for the NSW Telco Authority to comply with its policy on Infrastructure Capacity Reservation.
  • Expediting measures to protect against the risk of cloning by unauthenticated radios.

Public safety radio networks are critical for operational communications among Emergency Services Organisations (ESOs), which in New South Wales include:

  • NSW Ambulance
  • Fire and Rescue NSW
  • NSW Police Force
  • NSW Rural Fire Service
  • NSW State Emergency Service.1

Since 1993, these five ESOs have had access to a NSW Government owned and operated radio communications network, the Public Safety Network (PSN), to support their operational communications. Around 60 to 70 other entities also have access to this network, including other NSW government entities, Commonwealth government entities, local councils, community organisations, and utility companies.

Pursuant to the Government Telecommunications Act 2018 ('the Act'), the New South Wales Government Telecommunications Authority ('NSW Telco Authority') is responsible for the establishment, control, management, maintenance and operation of the PSN.2

Separate to the PSN, all ESOs and other government entities have historically maintained their own radio communication capabilities and networks. Accordingly, the PSN has been a supplementary source of operational radio communications for these entities.

These other radio networks maintained by ESOs and other entities are of varying size and capability, with many ageing and nearing their end-of-life. There was generally little or no interoperability between networks, infrastructure was often co-located and duplicative, and there were large gaps in geographic coverage.

In 2016, the NSW Telco Authority received dedicated NSW Government funding to commence the Critical Communications Enhancement Program (CCEP).

According to NSW Telco Authority's 2021–22 annual report, the CCEP is a transformation program for operational communications for NSW government agencies. The CCEP '…aims to deliver greater access to public safety standard radio communications for the State’s first responders and essential service agencies'. The objective of CCEP is to consolidate the large number of separate radio networks that are owned and operated by various NSW government entities and to enhance the state’s existing shared PSN. The program also aims to deliver increased PSN coverage throughout New South Wales.

The former NSW Government intended that as the enhanced PSN was progressively rolled-out across NSW, ESOs would migrate their radio communications to the enhanced network, before closing and decommissioning their own networks.

About this Audit

This audit assessed whether the CCEP is being effectively managed by the NSW Telco Authority to deliver an enhanced PSN that meets ESOs' requirements for operational communications.

We addressed the audit objective by answering the following two questions:

  1. Have agreed ESO user requirements for the enhanced PSN been met under day-to-day and emergency operational conditions?
  2. Has there been adequate transparency to the NSW Government and other stakeholders regarding whole-of-government costs related to the CCEP?

In answering the first question, we also considered how the agreed user requirements were determined. This included whether they were supported by evidence, whether they were sufficient to meet the intent of the CCEP (including in considering any role for new or alternative technologies), and whether they met any relevant technical standards and compliance obligations (including for cyber security resilience).

While other NSW government agencies and entities use the PSN, we focused on the experience of the five primary ESOs because these will be the largest users of the enhanced PSN.

Both the cost and time required to complete the CCEP roll-out have increased since 2016. While it was originally intended to be completed in 2020, this is now forecast to be 2027. Infrastructure NSW has previously assessed the reasons for the increases in time and cost. A summary of the findings made by Infrastructure NSW is presented in Chapter 1 of this report. Accordingly, as these matters had already been assessed, we did not re-examine them in this performance audit.

The auditee for this performance audit is the NSW Telco Authority, which is a statutory authority within the Department of Customer Service portfolio.

In addition to being responsible for the operation of the PSN, section 5 of the Act also prescribes that the NSW Telco Authority is:

  • to identify, develop and deliver upgrades and enhancements to the government telecommunications network to improve operational communications for government sector agencies
  • to develop policies, standards and guidelines for operational communications using telecommunications networks.

The NSW Telco Authority Advisory Board is established under section 10 of the Act. The role of the board is to advise the NSW Telco Authority and the minister on any matter relating to the telecommunications requirements of government sector agencies and on any other matter relating to the functions of the Authority. As of 2 June 2023, the responsible minister is the Minister for Customer Service and Digital Government.

The five identified ESOs are critical stakeholders of the CCEP and therefore they were consulted during this audit. However, the ESOs were not auditees for this performance audit.

Conclusion

In areas of New South Wales where the enhanced Public Safety Network has been implemented under the Critical Communications Enhancement Program, the NSW Telco Authority has delivered a radio network that meets most of the agreed requirements of Emergency Services Organisations for routine and emergency operations.
In April 2023, the enhanced Public Safety Network (PSN) was approximately 50% completed. In areas where it is used by Emergency Services Organisations (ESOs), the PSN generally meets agreed user requirements. This is demonstrated through extensive performance monitoring and reporting, which shows that agreed performance standards are generally achieved. Reviews by the NSW Government and the NSW Telco Authority found that the PSN performed effectively during major flood events in 2021 and 2022.

Where it is completed, PSN coverage is generally equal to or better than each ESO's individual pre-existing coverage. The NSW Telco Authority has a dedicated work program to address localised coverage gaps (or 'blackspots') in those areas where coverage has otherwise been substantively delivered. Available call capacity on the network far exceeds demand in everyday use. Any operational issues that may occur with the PSN are transparent to ESOs in real time.

The NSW Telco Authority consulted extensively with ESOs on requirements for the enhanced PSN, with relatively few ESO requirements not being included in the specifications for the enhanced PSN. Lessons from previous events, including the 2019–20 summer bushfires, have informed the design and implementation of the enhanced PSN (such as the need to ensure adequate backup power supply to inaccessible sites). The network is based on the Project 25 technical standards for mission-critical radio communications, which is widely-accepted in the public safety radio community throughout Australia and internationally.

There is no mechanism to ensure adequate radio coverage within new building infrastructure after the CCEP concludes, but the NSW Telco Authority and ESOs have agreed an approach to prioritise existing in-building sites for coverage for the duration of the CCEP.
The extent to which the PSN works within buildings and other built structures (such as railway tunnels) is of crucial importance to ESOs, especially the NSW Police Force, NSW Ambulance, and Fire and Rescue NSW. This is because a large proportion of their operational communications occurs within buildings.

There is no mechanism to ensure the adequacy of future in-building coverage for the PSN in new or refurbished buildings after the CCEP concludes. Planning, building, and fire regulations are silent on this issue. We note there are examples in the United States of how in-building coverage for public safety radio networks can be incorporated into building or fire safety codes.

In regard to existing buildings, it is not possible to know whether a building requires its own in-building PSN infrastructure until nearby outside radio sites, including towers and antennae, have been commissioned into the network. Only then can it be determined whether their radio transmissions are capable of penetrating inside nearby buildings. Accordingly, much of this work for in-building coverage cannot be done until outside radio sites are finished and operating.

In March 2023, the NSW Telco Authority and ESOs agreed on a list of 906 mandatory and 7,086

non-mandatory sites for in-building PSN coverage. Most of these sites will likely be able to receive radio coverage via external antennae and towers, however this cannot be confirmed until those nearby external PSN sites are completed. The parties also agreed on an approach to prioritising those sites where coverage is needed but not provided by antennae and towers. Available funding will likely only extend to ensuring coverage in sites deemed mandatory, which is nonetheless expected to meet the overall benchmark of achieving 'same or better' coverage than what ESOs had previously.

There is a risk that radio interoperability between ESOs will not be maximised because the NSW Telco Authority has not settled with ESOs how encryption will be used across the enhanced PSN.
End-to-end encryption of radio transmissions is a security feature that prevents radio transmissions being intercepted or listened to by people who are not meant to. The ability of the PSN to provide end-to-end encryption of operational communications is of critical importance to the two largest prospective users of the PSN: the NSW Police Force and NSW Ambulance. Given that encryption excludes other parties that do not have the requisite encryption keys, its use creates an obstacle to achieving a key intended benefit of the CCEP, that is a more interoperable PSN, where first responders are better able to communicate with other ESOs.

Further planning and collaboration between PSN participants are necessary to consider how these dual benefits can be achieved, including in what operational circumstances encrypted interoperability is necessary or appropriate.

The capital cost to the NSW Telco Authority of the CCEP, originally estimated at $400 million in 2016, was not made public until the 2021–22 NSW Budget disclosed an estimate of $1.325 billon.
The estimated capital cost to complete all stages of the CCEP increased over time. This increasing cost was progressively disclosed to the NSW Government through Cabinet processes between 2015–16 and 2021–22.

In 2016, the full capital cost to the NSW Telco Authority of completing the CCEP was estimated to be $400 million. This estimated cost was not publicly disclosed, nor were subsequent increases, until the cost of $1.325 billion was publicly disclosed in the 2021–22 NSW Budget (revised down in the 2022–23 NSW Budget to $1.293 billion).

There has been no transparency about the whole-of-government cost of implementing the enhanced PSN through the CCEP.
In addition to the capital costs incurred directly by the NSW Telco Authority for the CCEP, ESOs have incurred costs to maintain their own networks due to the delay in implementing the CCEP. The ESOs will continue to incur these costs until they are able to fully migrate to the enhanced PSN, which is expected to be in 2027. These costs have not been tracked or reported as part of transparently accounting for the whole-of-government cost of the enhanced PSN. This is despite Infrastructure NSW in 2019 recommending to the NSW Telco Authority that it conduct a stocktake of such costs so that a whole-of-government cost impact is available to the NSW Government.

1 The definition of 'emergency services organisation' is set out in the State Emergency and Rescue Management Act 1989 (NSW). In addition to the five ESOs discussed in this report, the definition also includes: Surf Life Saving New South Wales; New South Wales Volunteer Rescue Association Inc; Volunteer Marine Rescue NSW; an agency that manages or controls an accredited rescue unit; and a non-government agency that is prescribed by the regulations for the purposes of this definition.
2 Section 15(1) of the Government Telecommunications Act 2018 (NSW).

The NSW Telco Authority established and tracked its own costs for the CCEP

Over the course of the program from 2016, the NSW Telco Authority prepared a series of business cases and program reviews that estimated its cost of implementing the program in full, including those shown in Exhibit 6 below.

Exhibit 6: Estimated costs to fully implement the CCEP
Source Capital cost ($ million) Operating cost
($ million)
Completion date
March 2016 business case 400 37.3 2020
November 2017 internal review 476.7 41.7 2022
March 2020 business case 950–1,050 -- 2025
October 2020 business case 1,263.1 56.1 2026

Source: CCEP business cases as identified.

In response to the 2016 CCEP business case, the then NSW Government approved the NSW Telco Authority implementing the CCEP in full, with funding provided in stages. The NSW Telco Authority tracked its costs against approved funding, with monthly reports provided to the multi-agency Program Steering Committee

Throughout the program, the NSW Government was informed of increasing costs being incurred by the NSW Telco Authority for the CCEP

The various business cases, program updates, and program reviews prepared by the NSW Telco Authority were provided to the NSW Government through the required Cabinet process when seeking approval for the program proceeding and requests for both capital and operational funding. These provided clear indication of the changing overall cost of the CCEP to the NSW Telco Authority, as well as the delays that were being experienced.

There was no transparency to the Parliament and community about changes in the capital cost of the CCEP until the 2021–22 NSW Budget

As the business cases for the CCEP were not publicly available, the only sources of information about capital cost were NSW Budget papers and media releases. The information provided in the annual Budget papers prior to the 2021–22 NSW Budget provided no visibility of the estimated full capital cost to complete all stages of the CCEP. As shown in Exhibit 7 below, this information was fragmented and complex.

Media releases about the progress of the CCEP did not provide the estimated total cost to the NSW Telco Authority of $1.325 billion to complete all stages of the CCEP until June 2021. Prior to this date, media releases only provided funding for the initial stages of the program or for the stages subject to a funding announcement.

Even during the September 2019 and March 2020 Parliamentary Estimate Committee hearings where the costings and delays to the CCEP were raised, the estimated full cost of the CCEP was not revealed.

Exhibit 7: CCEP funding in NSW Budget papers from 2015–16 to 2022–23
Financial year Type of major work Description of expenditure Forecast estimate to complete ($ million) Estimated duration
2015–16 New work Infrastructure Rationalisation Program: Planning and Pilot 18.3 2015–16
2016–17 Work in progress CCEP Planning and Pilot 18.3 2015–17
New work CCEP 45 2016–17
2017–18 New work CCEP 190.75 2017–21
2018–19 Work in progress CCEP North Coast and State-wide Detailed Design 190.75 2017–21
New work CCEP Greater Metropolitan Area 236 2018–22
2019–20 Work in progress CCEP 426.9 2018–22
2020–21 Work in progress CCEP 664.8 2018–22
2021–22 Work in progress CCEP 1,325 2018–26
2022–23 Work in progress CCEP 1,292.8 2018–26

Source: NSW Treasury, Annual State Budget Papers.

The original business case for the CCEP included estimated ESO costs, though these costs were not tracked throughout the program

Estimates for ESO costs for operating and maintaining their own radio networks over the four years from 2016–17 were included in the original March 2016 business case. They included $75.2 million for capital expenditure and $95 million for one-off operating costs. These costs, as well as costs incurred by ESOs due to the delay in the program, were not subsequently tracked by the NSW Telco Authority.

In January 2017, Infrastructure NSW reviewed the CCEP business case of March 2016. In this review, Infrastructure NSW recommended that the NSW Telco Authority identify combined and apportioned costs and cashflow for all ESOs over the CCEP funding period reflecting all associated costs to deliver the CCEP. These to include additional incidental capital costs accruing to ESOs, transition and migration to the new network and the cost (capital and operational) of maintaining existing networks. This recommendation was implemented in the November 2017 program review, with ESO capital costs estimated as $183 million.

In 2019, Infrastructure NSW conducted a Deep Dive Review on the progress of the CCEP. In this review, Infrastructure NSW made what it described as a 'critical recommendation' that the NSW Telco Authority:

…coordinate a stocktake of the costs of operational bridging solutions implemented by PSAs [ESOs] as a result of the 18-month delay, so that a whole-of-government cost impact is available to the NSW Government.  

It should be noted that the delay to CCEP completion now is seven years and that further ‘operational bridging solutions’ have been needed by the ESOs.

'Stay Safe and Keep Operational' costs incurred by ESOs will be significantly higher than originally estimated

Stay Safe and Keep Operational (SSKO) funding was established to provide funding to ESOs to maintain their legacy networks while the CCEP was refreshing and enhancing the PSN. This recognised that much of the network infrastructure relied on by ESOs had reached – or was reaching – obsolescence and would either require extensive maintenance or replacement before the PSN was available for ESOs to migrate to it. ESOs may apply to NSW Treasury for SSKO funding, with their specific proposals being reviewed (and endorsed, where appropriate) by the NSW Telco Authority. Accordingly, SSKO expenditure does not fall within the CCEP budget allocation.

As shown in the table below, extracted from the March 2016 CCEP business case, the total expected cost for SSKO purposes over the course of the CCEP was originally $40 million, assuming the enhanced PSN would be fully available by 2020.

Exhibit 8: Stay Safe and Keep Operational forecast costs, 2017 to 2020
Year 2017 2018 2019 2020 Total
SSKO forecast ($ million) 12.5 15 10 2.5 40

Source: March 2016 CCEP business case.

In October 2022, the expected completion date for the CCEP was re-baselined to August 2027. Accordingly, ESOs will be required to continue to maintain their radio networks using legacy equipment for seven years longer than the original 2020 forecast. This will likely become progressively more expensive and require additional SSKO funding. For example, NSW Telco Authority endorsed SSKO bids for 2022–23 exceeded $35 million for that year alone.

Compared to the original forecast made in the March 2016 CCEP business case of $40 million, we found ESOs had estimated SSKO spending to 2027 will be $292.5 million.

A refresh of paging network used by ESOs and the decommissioning of redundant sites were both removed from the original 2016 scope of the CCEP

Paging

A paging network is considered an important user requirement by the Fire and Rescue NSW, NSW Rural Fire Service, and NSW State Emergency Service. The 2016 CCEP business case included a paging network refresh within the program scope of works. This was reiterated in the November 2017 internal review of the program. These documents did not estimate a cost for this refresh. The March 2020 and October 2020 business cases excluded paging from the program scope. The audit is unable to identify when, why or by whom the decision was made to remove paging from the program scope, something that was also not well communicated to the affected ESOs.

In 2021, after representations from the affected ESOs, the NSW Telco Authority prepared a separate business case for a refresh of the paging network at an estimated capital cost of $60.31 million. This program was subsequently approved by the NSW Government and included in the 2022–23 NSW Budget.

In determining an estimated full whole-of-government cost of delivering the enhanced PSN, we have included the budgeted cost of the paging network refresh on the basis that:

  • it was expressly included in the original approved March 2016 business case
  • the capability is deemed essential to the needs of three ESOs.

Decommissioning costs

The 2016 CCEP business case included cost estimates for decommissioning surplus sites (whether ‘old’ GRN sites or sites belonging to ESOs’ own networks). These estimates were provided for both the NSW Telco Authority ($38 million) and for the ESOs ($55 million). However, while these estimates were described, they were not included as part of the NSW Telco Authority's estimated capital cost ($400 million) or (more relevantly) operating cost ($37.3 million) for the CCEP. This is despite decommissioning being included as one of eight planned activities for the rollout of the program.

In the October 2020 business case, an estimate of $201 million was included for decommissioning agency networks based on a model whereby:

  • funding would be coordinated by the NSW Telco Authority
  • scheduling and reporting through an inter-agency working group and
  • where appropriate, agencies would be appointed as the most appropriate decommissioning party.

This estimated cost is not included in the CCEP budget.

In determining an estimated full whole-of-government cost of the enhanced PSN, we have included the estimated cost of decommissioning on the basis that:

  • decommissioning was included in the 2016 CCEP business case as one of eight 'planned activities for the rollout of the program'
  • effective decommissioning of surplus sites and equipment (including as described in the business case as incorporating asset decommissioning, asset re-use, and site make-good) is an inherent part of the program management for an enhanced PSN
  • costs incurred in decommissioning are entirely a consequence of the CCEP program.

The estimated minimum cost of building an enhanced PSN consistent with the original proposal is over $2 billion

We have derived two estimated minimum whole-of-government costs for delivering an enhanced PSN. These are:

  • $2.04 billion when calculated from NSW Telco Authority data – shown as estimate A in Exhibit 9 below.
  • $2.26 billion when calculated from ESO supplied data – shown as estimate B in Exhibit 9.

Both totals include:

  • budgeted amounts for both CCEP capital expenditure ($1,292.8 million) and operating expenditure ($139 million)
  • the NSW Telco Authority's 2020 estimated cost for decommissioning ($201 million)
  • the NSW Telco Authority's approved funding for paging refresh ($60.3 million).

The two estimated totals primarily vary around the capital expenditure of ESOs (particularly SSKO funding). To determine these costs, we used ESO provided actual SSKO costs to date, as well as their estimates for maintaining their legacy radio networks through to 2027.

The equivalent cost estimates from the NSW Telco Authority were sourced from the November 2017 internal review and the October 2020 business case for CCEP. It should be noted that the amounts for both estimates are not audited, or verified, but do provide an indication of how whole-of-government costs have grown over the course of the program.

The increase in and reasons for the increase in total CCEP costs (capital and one-off operating) incurred or forecast by the NSW Telco Authority (from $437.3 million in 2016 to $1,431.8 million in 2022) have been provided to the NSW Government through various business cases and reviews prepared by the NSW Telco Authority, as well as by reviews conducted by Infrastructure NSW as part of its project assurance responsibilities.

However, the growth in ESO costs and other consequential costs, such as paging and decommissioning, from around $263 million in the 2016 CCEP business case to between $600 million and $800 million, has to a large degree remained invisible and unexplained to the NSW Government and other stakeholders

Exhibit 9: Estimated whole-of-government costs of the enhanced PSN
  Estimated whole-of-government cost, over time
Cost type 20161 20172 20203 2023–Estimate A4 2023–Estimate B5
$ million $ million $ million $ million $ million
CCEP capital expenditure 400a 476.7b 1,263.1c 1,292.8d 1,292.8d
CCEP operating expenditure 37.3a 41.7b 41.5e 139d 139d
CCEP total 437.3 518.4 1,304.6 1,431.8 1,431.8
ESO capital expenditure 75.2a,f 183b,e 75.4e 258.4g 292.5
ESO one-off operating expenditure 93a n.a.l 86.5e 86.5h 273
ESO total 168.2 183 161.9 344.9 565.5
Paging n.a.i n.a.i n.a.j 60.3k 60.3k
Decommissioning 93 n.a.l 201.0 201h 201
Paging and decommissioning total 93 n.a. 201 261.3 261.3
Whole-of-government total 698.5 701.4 1,667.5 2,038 2,258.6

Notes:
  1. Financial year 2016 to Financial year 2020.
  2. Financial year 2016 to Financial year 2021.
  3. Financial year 2016 to Financial year 2025.
  4. Financial year 2016 to Financial year 2026.
  5. Financial year 2022 to Financial year 2025.
  6. Stay Safe and Keep Operational (SSKO) costs plus terminals costs.
  7. November 2017 internal review and October 2020 Business case.
  8. October 2020 Business case.
  9. Included in CCEP capital expenditure at that time.
  10. By 2020, a refresh of the paging network had been removed from the CCEP scope.
  11. A separate business case for a refresh of the paging network was approved by government in 2022.
  12. Figure not included in the source document.
Sources:
  1. March 2016 CCEP business case.
  2. November 2017 Internal Review conducted by the NSW Telco Authority.
  3. October 2020 CCEP business case.
  4. Derived from business cases, with ESO costs drawn from NSW Telco Authority data.
  5. Derived from business cases, with ESO costs based on data provided to the Audit Office of New South Wales by each of the five ESOs.

Appendix one – Response from agency

Appendix two – Trunked public safety radio networks

Appendix three – About the audit

Appendix four – Performance auditing

 

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #383 - released 23 June 2023

 

Published

Actions for NSW government agencies' use of consultants

NSW government agencies' use of consultants

Treasury
Whole of Government
Compliance
Internal controls and governance
Management and administration
Procurement
Workforce and capability

What the report is about

This audit assessed how effectively NSW government agencies procure and manage consultants. It examined the role of the NSW Procurement Board and NSW Procurement (a unit within NSW Treasury) in supporting and monitoring agency procurement and management of consultants.

The audit used four sources of data that contain information about spending on consultants by NSW government agencies, including annual report disclosures and the State's financial consolidation system (Prime). It also reviewed a sample of consulting engagements from ten NSW government agencies.

What we found

Our review of a selection of consulting engagements indicates that agencies do not procure and manage consultants effectively.

We found most agencies do not use consultants strategically and do not have systems for managing or evaluating consultant performance. We also found examples of non-compliance with procurement rules, including contract variations that exceeded procurement thresholds.

NSW Procurement has made improvements to the information available about spending on consultants, including additional analysis and reporting. However, there is no single data source that accurately captures spending on consultants.

Our analysis of data on whole-of-government spending on consultants, drawn from agency annual reports, indicates that four large professional services firms accounted for about a quarter of consultancy expenditure from 2017–18 to 2021–22. This concentration increases strategic risks, including over-reliance on a limited number of providers and potential reduction in the independence of advice.

It is also highly unlikely that NSW government agencies will meet the government's 2019 policy commitment to reduce consultancy expenses by 20% each year, over four years, from 2019–20. NSW Treasury advised that to implement this commitment, agency budgets were reduced in Prime in line with the savings targets. However, actual spending on consulting in NSW Treasury's Reports on State Finances 2020–21 and 2021–22 was almost $100 million higher than the savings targets over the first three years since 2019–20.

What we recommended

The report made seven recommendations which aim to improve:

  • the quality and transparency of data on spending on consultants
  • monitoring of strategic risks and agency compliance with procurement and recordkeeping rules
  • agencies' strategic use of consultants, including evaluation and knowledge retention.

Between 2017–18 and 2021–22, NSW government agency annual reports disclosed total spending of around $1 billion on consultants across more than 10,000 engagements. More than 1,000 consulting firms provided services to NSW government agencies during this period. Consulting is a classification of professional services that is characterised by giving advice or recommendations on a specific issue. The NSW Procurement Board Direction PBD-2021-03 defines a consultant as a person or organisation that provides 'recommendations or professional advice to assist decision-making by management'. PBD-2021-03 notes that the advisory nature of the work of consultants is the main factor that distinguishes them from other providers of professional services.

The NSW Procurement Board is responsible for setting procurement policy, issuing directions to support policies, and monitoring and reporting on agency compliance with policies and directions. NSW Procurement, a division within NSW Treasury, supports agencies to comply with the NSW Procurement Board’s policies and directions. A 'devolved governance model' is used for procurement in New South Wales. This means the heads of government entities that are covered by the NSW Procurement Board’s directions are responsible for managing the entity's procurement, including managing risks, reporting and ensuring compliance, in line with procurement laws and policies.

This audit assessed how effectively NSW government agencies procure and manage consultants. It assessed the role of the NSW Procurement Board and NSW Procurement in supporting and monitoring agency procurement and management of consultants. It also reviewed a sample of consulting engagements from ten NSW government agencies to examine how agencies procured, managed and reported on their use of consultants. The ten NSW government agencies were:

  • NSW Treasury
  • Department of Communities and Justice
  • Department of Customer Service
  • Department of Education
  • Department of Planning and Environment
  • Department of Premier and Cabinet
  • Department of Regional NSW
  • Infrastructure NSW
  • Sydney Metro
  • Transport for NSW

There are four different sources of data that contain information about spending on consultants by NSW government agencies: the State's financial consolidation system (Prime), disclosures of spending on consultants in agency annual reports, and two systems operated by NSW Procurement (the Business Advisory Services (BAS) dashboard and Spend Cube). Each of these data sources serves a different purpose, and collects and categorises information differently. None of these provide a complete source of data on spending on consultants, either in their own right or collectively.

NSW Treasury considers Prime to be the 'source of truth' on consulting expenditure across the NSW public sector. An account within Prime records recurrent spending on consultants, but this account does not include capital expenditure (that is, spending on consultants that has from a financial reporting perspective been 'capitalised' to a project on the balance sheet). As the State's financial consolidation system, Prime captures all financial information. However, capitalised consulting expenditure is recorded within various capital accounts, and is not identifiable within these accounts. While this is appropriate for accounting purposes, it means that the Prime account that records recurrent consulting expenditure does not reflect total spending on consultants by NSW government agencies. We used the data in Prime to assess whether NSW government agencies met the NSW Government's policy commitment—stated before the 2019 election and costed by the Parliamentary Budget Office—to reduce recurrent expenditure on consulting by 20% each year, over four years, from 2019–20. We did this because, while the Prime account for recurrent consulting expenditure does not reflect all spending on consultants, it does capture the recurrent spending that was subject to the policy commitment.

Most NSW government agencies are required by legislation to disclose spending on consultants (as defined in PBD-2021-03) in their annual reports. These disclosures include both recurrent and capital expenditure. For consulting engagements that cost more than $50,000, the disclosures also provide itemised information, including the names of the individual projects and the consultants used. While this data is more complete than Prime because it includes capital expenditure, it also has some gaps. Some entities are excluded from public reporting requirements on consultant use. For example, NSW Local Health Districts (LHD) are not required to produce annual reports, and the Ministry of Health does not include LHD consulting expenditure in its annual report.1 We used annual report disclosure data to report on total expenditure on consultants, and the concentration of suppliers of consulting services to NSW government agencies.

The BAS dashboard and Spend Cube are systems created by NSW Procurement to collect information about spending on suppliers of professional services. This includes consultants, but also includes other professional services providers. The systems were not designed for reporting on spending on consulting as defined in PBD-2021-03. However, we have used this data to assess specific aspects of NSW Procurement's monitoring of the use of consultants by NSW government agencies.

In 2018, we conducted an audit titled 'Procurement and reporting of consultancy services'. This assessed how 12 NSW government agencies complied with procurement requirements and how NSW Procurement supported the functions of the NSW Procurement Board. The 2018 audit found that none of the 12 agencies fully complied with NSW Procurement Board Directions on the use of consultants and that the NSW Procurement Board was not fully effective in overseeing and supporting agencies’ procurement of consultants. Specific findings from the 2018 audit included: 

  • Agencies applied the definition of consultant inconsistently, which affected the accuracy of reporting on consultancy expenditure.
  • There was inadequate guidance from NSW Procurement for agencies implementing the procurement framework, with a need for additional tools, automated processes, and other internal controls to improve compliance.
  • NSW Procurement had insufficient data for effective oversight of procurement and did not publish any data on the procurement of consultancy services by NSW government agencies.

Conclusion

Our review of a selection of consulting engagements from ten NSW government agencies indicates that these agencies do not procure and manage consultants effectively. We found that most agencies do not have a strategic approach to using consultants, or systems for managing or evaluating their performance. We also found examples of non-compliance with procurement rules, including contract variations that exceeded procurement thresholds. NSW Procurement, a division within NSW Treasury, provides frameworks and some guidance to agencies for procuring consultants. However, gaps in its data collection and analysis mean monitoring of strategic risks is limited and it does not respond to agency non-compliance consistently. There are limitations in ability of various data sources to accurately record spending on consultants. These limitations include incomplete recording of all spending, and different definitions of consulting for accounting and financial reporting purposes. Notwithstanding these limitations, and based on information in the State's financial consolidation system (Prime)—which records recurrent expenditure on consultants—it is highly unlikely that NSW government agencies will meet the government's 2019 policy commitment to reduce spending on consultants, as defined in the policy commitment and costed by the Parliamentary Budget Office. 

The use of a 'devolved governance model' for procurement means NSW government agencies are responsible for developing and implementing their own systems that align with the NSW Government Procurement Policy Framework. Agency heads are responsible for demonstrating compliance. Most agencies included in this audit did not have a clear strategic approach to how and when consultants should be used (for example, to seek advice and expertise not already available within the agency) and were using consultants in an ad hoc manner.

Our analysis of whole-of-government spending on consultants, drawn from agency annual reports, indicates that four large professional services firms account for around 27% of spending on consultants in the period from 2017–18 to 2021–22. The number of firms making up the top 50% of expenditure decreased from 11 to eight during this time, with the other 50% of expenditure spread across more than 1,000 firms. Concentration of consulting engagements within a small number of firms increases strategic risks, including that advice is not sufficiently objective and impartial, and that NSW government agencies become overly reliant on selected professional services firms.

Our review of a selection of consulting engagements by NSW government agencies found several examples of non-compliance with procurement policy. This included the use of variations to contract values which exceeded allowable limits. Record keeping was inadequate in many cases we reviewed, which limits transparency about government spending. Most agencies did not proactively manage their consulting engagements. The majority of consulting engagements that we reviewed were not evaluated or assessed by the agency for quality. Very few used any processes to ensure the transfer and retention of knowledge generated through consulting engagements. This means agencies miss opportunities to increase core staff skills and knowledge and to maximise value from these engagements.

NSW Procurement oversees a detailed policy framework that provides guidance and support to NSW government agencies when they are using consultants. The policy framework provides mandatory steps and some other guidance. Our audit on the procurement and reporting of consultancy services in 2018 found that agency reporting on the use of consultants was inconsistent and recommended that NSW Procurement should improve the quality, accuracy and completeness of data collection. NSW Procurement’s guidance on how agencies should classify and report on consulting engagements remains ambiguous. This contributes to continued inconsistent reporting by and across agencies, and reduces the quality of data on the use of consultants.

NSW Procurement has made some improvements to the information available about spending on consultants since our audit in 2018, including additional analysis and reporting that is available to agencies. However, there is still no single data source that accurately captures all spending on consultants. This is despite our recommendations in 2018 that NSW Procurement improve the quality of information collected from agencies and suppliers, which NSW Procurement accepted. This makes it harder for NSW Procurement or individual agencies to track trends and identify risks or improvement opportunities in the way consultants are used. 

In early 2019, the NSW Government made a policy commitment to reduce consultancy expenses by 20% each year, over four years, from 2019–20 (excluding capital-related consultancy expenses). This commitment was set out in the Parliamentary Budget Office's '2019 Coalition Election Policy Costings (Policy Costings)'. NSW Treasury subsequently advised that to implement this commitment, agency budgets were reduced in Prime in line with the savings targets. However, actual spending on consultants recorded in Prime in the first three years after the commitment was made was almost $100 million higher than the targets. We did not see any evidence that the financial data on actual expenditure was used to inform reporting on NSW government agencies' progress toward achieving the savings set out in the policy commitment.


1 The Government Sector Finance Legislation (Repeal and Amendment) Act 2018 No 70 will amend the Health Services Act 1997 to specify that annual reporting information for any or all NSW Health entities may be included in the annual reporting information prepared by the Ministry of Health under the Government Sector Finance Act 2018. This provision is expected to commence on 1 July 2023.

This chapter outlines our findings on the role of NSW Procurement in overseeing the use of consultants by NSW government agencies.

This chapter outlines our findings on the use of consultants by the ten NSW government agencies that were included in this audit.

Appendix one – Responses from auditees

Appendix two – About the audit

Appendix three – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #378 - released 2 March 2023

Published

Actions for Government's acquisition of private property: Sydney Metro project

Government's acquisition of private property: Sydney Metro project

Transport
Planning
Whole of Government
Compliance
Infrastructure
Internal controls and governance
Project management
Risk

What the report is about

Sydney Metro is Australia’s largest public transport project. It requires the acquisition of many private properties, including residential and business properties.

This audit assessed the effectiveness of the acquisition of private properties for the Sydney Metro project. The audited agencies were Sydney Metro, the Department of Planning and Environment (Valuer General NSW) and Transport for NSW (the Centre for Property Acquisition).

The audit assessed agencies against the framework for property acquisitions in New South Wales. It did not re-perform the valuations done for individual properties that were acquired by Sydney Metro.

What we found

Acquisitions of private property for the Sydney Metro project were mostly effective in the sample of acquisitions we assessed. We found Sydney Metro:

  • complied with legislative and policy requirements for compensation and communication with people subject to property acquisitions
  • kept accurate records of its acquisitions and applied probity controls consistently
  • did not complete detailed plans or negotiation strategies for the high-risk and high-value acquisitions we reviewed
  • did not comply with legislative timelines for most compulsory acquisitions because of delays in receiving the required information from the Valuer General in these cases.

The Centre for Property Acquisition has overseen the implementation of reforms to residential acquisition processes, but its assessment of the effectiveness of these reforms has not been comprehensive.

What we recommended

The audit made four recommendations to the audited agencies to improve:

  • plans and strategies for the acquisition of high-risk and high-value properties
  • timeliness of issuing compensation determinations for compulsory acquisitions
  • data quality on the experience of people subject to property acquisitions.

The NSW Government has the power to acquire land that is owned or leased by individuals or businesses, if it is needed for a public purpose. The power arises from the Land Acquisition (Just Terms Compensation) Act 1991 (the Just Terms Act). Government agencies that have the power to compulsorily acquire private property are referred to as ‘acquiring authorities’. People who are subject to acquisitions are referred to as ‘affected parties’ and include property owners (business or residential), businesses with a commercial lease on a property, or individuals with residential tenancy leases. In recent years, the vast majority of acquisitions by the NSW Government have been for public transport or road projects.

Sydney Metro is a NSW Government agency with responsibility for building the Sydney Metro railway project. Sydney Metro is Australia’s largest public transport project. The project requires the acquisition of a large number of private properties. Sydney Metro has been one of the largest acquirers of private property in recent years, completing over 500 acquisitions between 2020 and mid-2022, with a total acquisition value of over $2 billion. Other agencies and statutory officers involved in the acquisition of property for the Sydney Metro project include:

  • the Department of Planning and Environment (DPE), which supports the minister responsible for the Just Terms Act. DPE also provides staff to the Valuer General of NSW
  • the Valuer General of NSW, an independent statutory officer that determines compensation in cases where the acquiring authority and the affected party cannot agree on compensation for property that has been acquired
  • Transport for NSW, which includes the Centre for Property Acquisition (CPA). The CPA does not have a direct role in acquiring properties, but its responsibilities include developing guidance for acquiring agencies and monitoring and reporting on their activities.

About this audit

The objective of this audit was to assess the effectiveness of acquisitions of private properties for Sydney Metro projects. The audit assessed agencies against the legislative and policy requirements in place for government acquisitions of private property in New South Wales. In line with the Audit Office's legislative mandate, the audit does not comment on the merits of the policy objectives reflected in the Just Terms Act.

The audit examined a sample of 20 property acquisitions. This was not a statistically representative sample. While our report provides comments on Sydney Metro’s overall acquisition processes, it does not provide assurance regarding the acquisitions that were not examined for this audit.

The audit did not re-perform the valuations done for individual properties that were acquired by Sydney Metro. Affected parties who disagree with the valuation of their property have the right to seek independent assessment of this via the Valuer General and the Land and Environment Court.

Conclusion

Acquisitions of property for the Sydney Metro project were mostly effective in the sample of acquisitions we assessed. Sydney Metro followed requirements for communication with affected parties. Compensation processes were conducted in compliance with legislative requirements, but compensation determinations for compulsory acquisitions were not completed within legislated time frames due to delays in receiving these from the Valuer General. Governance and probity processes were followed consistently, with some relatively minor exceptions. 

Sydney Metro has detailed guidelines for acquisitions that are based on relevant legislation and government policy. In the 20 acquisitions we assessed for this audit, these procedures were followed consistently. This included adhering to minimum timelines for negotiation periods, engaging independent valuers and other experts when needed, and complying with governance and probity processes.

Sydney Metro staff followed requirements for communication and support for residential acquisitions by assigning ‘personal managers’ and providing additional support to affected parties when needed. The Centre for Property Acquisition (CPA) has overseen reforms to the residential property acquisition process in recent years. These reforms include the introduction of the NSW Property Acquisition Standards and the use of personal managers, in addition to the existing acquisition managers, for residential acquisitions. However, the CPA has not assessed the impact of these changes on the experiences on people affected by property acquisitions.

Sydney Metro did not comply with the legislative requirement to provide a formal compensation notice to the affected party within 45 days of a compulsory acquisition starting in any of the eight relevant acquisitions in our sample. This was because Sydney Metro must wait for the Valuer General to complete a compensation determination before Sydney Metro can send the compensation notice, and the Valuer General did not do this within 45 days. We acknowledge that Sydney Metro does not have full control over this process, and that it has taken steps to mitigate the impact of delays on affected parties. 

This chapter presents our findings on Sydney Metro's acquisition of industrial and commercial properties. Industrial properties include construction businesses and manufacturing facilities. Commercial properties were mostly properties such as shopping centres and office towers. Many of these acquisitions involve businesses and properties that are relatively complex and have high values. This means the valuation process can require multiple experts and can be lengthy and contested. Adherence to governance and probity requirements is important for these acquisitions in order to demonstrate that the acquiring authority has achieved value for money.

This chapter presents our findings on Sydney Metro's acquisition of residential properties, which include apartments and houses, and small business leases, which mostly affected businesses in small shopping centres or arcades. Most of these acquisitions were lower value compared to industrial and commercial property acquisitions and did not require as much expert advice on complex technical issues. However, residential property acquisitions can be personally distressing for the affected parties and require staff from the acquiring authority to provide support and show empathy while ensuring legislative compliance and value for money.

Appendix one – Responses from agencies

Appendix two – About the audit 

Appendix three – Performance auditing 

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #375 - released 9 February 2023

Published

Actions for Coordination of the response to COVID-19 (June to November 2021)

Coordination of the response to COVID-19 (June to November 2021)

Premier and Cabinet
Community Services
Health
Justice
Whole of Government
Internal controls and governance
Risk
Service delivery
Shared services and collaboration

What the report is about

This audit assessed the effectiveness of NSW Government agencies’ coordination of the response to COVID-19, with a focus on the Delta variant outbreak in the Dubbo and Fairfield Local Government Areas (LGA) between June and November 2021. We audited five agencies - the Department of Premier and Cabinet, NSW Health, the NSW Police Force, Resilience NSW and the Department of Customer Service.

The audit also considered relevant planning and preparation activities that occurred prior to June 2021 to examine how emergency management and public health responses learned from previous events.

What we found

Prior to Delta, agencies developed capability to respond to COVID-19 related challenges.

However, lessons learned from prior reviews of emergency management arrangements, and from other jurisdictions, had not been implemented when Delta emerged in June 2021. As a result, agencies were not as fully prepared as they could have been to respond to the additional challenges presented by Delta.

Gaps in emergency management plans affected agencies' ability to support individuals, families and businesses impacted by restrictions to movement and gathering such as stay-at-home orders. In LGAs of concern, modest delays of a few days had a significant impact on people, especially those most vulnerable.

On 23 July 2021, the NSW Government established a cross-government coordinating approach, the Delta Microstrategy, which complemented existing emergency management arrangements, improved coordination between NSW Government agencies and led to more effective local responses.

Where possible, advice provided to government was supported by cross-government consultation, up-to-date evidence and insights. Public Health Orders were updated as the response to Delta intensified or to address unintended consequences of previous orders. The frequency of changes hampered agencies' ability to effectively communicate changes to frontline staff and the community in a rapidly evolving situation.

The NSW Government could provide greater transparency and accountability over decisions to apply Public Health Orders during a pandemic.

What we recommended

The audit made seven recommendations intended to improve transparency, accountability and preparedness for future emergency events.

This audit assessed the effectiveness of NSW Government agencies’ coordination (focused on the Department of Premier and Cabinet, NSW Health, the NSW Police Force, Resilience NSW and the Department of Customer Service) of the COVID-19 response in selected Local Government Areas (Fairfield City Council and Dubbo Regional Council) between June and November 2021.

As noted in this report, Resilience NSW was responsible for the coordination of welfare services as part of the emergency management arrangements. On 16 December 2022, the NSW Government abolished Resilience NSW.

During the audited period, Resilience NSW was tasked with supporting the needs of communities subject to stay-at-home orders or stricter restrictions and it provided secretariat support to the State Emergency Management Committee (SEMC). The SEMC was, and remains, responsible for the coordination and oversight of emergency management policy and preparedness.

Our work for this performance audit was completed on 15 November 2022, when we issued the final report to the five audited agencies. While the audit report does not make specific recommendations to Resilience NSW, it does include five recommendations to the State Emergency Management Committee. On 8 December 2022, the then Commissioner of Resilience NSW provided a response to the final report, which we include as it is the formal response from the audited entity at the time the audit was conducted.

The community of New South Wales has experienced significant emergency events during the past three years. COVID-19 first emerged in New South Wales after bushfire and flooding emergencies in 2019–20. The pandemic is now into its third year, and there have been further extreme weather and flooding events during 2021 and 2022.

Lessons taken from the experience of these events are important to informing future responses and reducing future risks to the community from emergencies.

This audit focuses on the NSW Government's response to the COVID-19 pandemic, and in particular, the Delta variant (Delta) that occurred between June and November 2021. The response to the Delta represents six months of heightened challenges for the NSW Government.

Government responses to emergencies are guided by legislation. The State Emergency and Rescue Management Act 1989 (SERM Act) establishes emergency management arrangements in New South Wales and covers:

  • coordination at state, regional and local levels through emergency management committees
  • emergency management plans, supporting plans and functional areas including the State Emergency Management Plan (EMPLAN)
  • operations centres and controllers at state, regional and local levels.

This audit focuses on the activities of five agencies during the audit period:

  • The NSW Police Force led the emergency management response and was responsible for coordinating agencies across government in providing the tactical and operational elements that supported and enhanced the health response to the pandemic. The NSW Police Force also led the compliance response which enforced Public Health Orders and included household checks on those required to isolate at home after testing positive to COVID-19. In some parts of NSW, they were supported by the Australian Defence Force in this role.
  • NSW Health was responsible for leading the health response which coordinated all parts of the health system, initially to prevent, and then to manage, the pandemic.
  • Resilience NSW coordinated welfare services as part of the emergency management arrangements and provided secretariat support to the State Emergency Management Committee (SEMC). The SEMC is responsible for the coordination and oversight of emergency management policy and preparedness. Resilience NSW was also tasked with supporting the needs of communities subject to stay-at-home orders or stricter restrictions.
  • The Department of Customer Service (DCS) was responsible for the statewide strategic communications response.
  • The Department of Premier and Cabinet (DPC) held a key role in providing policy and legal services, as well as supporting the coordination of activity across a range of functional areas and decision-making by our State’s leaders.

This audit assessed the effectiveness of NSW Government agencies’ coordination (focused on the Department of Premier and Cabinet, NSW Health, the NSW Police Force, Resilience NSW and the Department of Customer Service) of the COVID-19 response in selected Local Government Areas (LGA) (Fairfield City Council and Dubbo Regional Council) after June 2021.

The audit investigated whether:

  • government decisions to apply LGA-specific Public Health Orders were supported by effective crisis management governance and planning frameworks
  • agencies effectively coordinated in the communication (and enforcement) of Public Health Orders.

While focusing on the coordination of NSW Government agencies’ response to the Delta variant in June through to November 2021, the audit also considered relevant planning and preparation activities that occurred prior to June 2021 to examine how emergency management and public health responses learned from previous events.

This audit does not assess the effectiveness of other specific COVID-19 responses such as business support. It refers to the preparedness, planning and delivery of these activities in the context of supporting communities in selected LGAs. NSW Health's contribution to the Australian COVID-19 vaccine rollout was also subject to a separate audit titled 'New South Wales COVID-19 vaccine rollout' tabled in NSW Parliament on 7 December 2022. 

This audit is part of a series of audits which have been completed, or are in progress, regarding the New South Wales COVID-19 emergency response. The Audit Office of New South Wales '2022–2025 Annual Work Program' details the ongoing focus our audits will have on providing assurance on the effectiveness of emergency responses.

In this document Aboriginal refers to the First Nations peoples of the land and waters now called Australia, and includes Aboriginal and Torres Strait Islander peoples.

Conclusion

Prior to June 2021, agencies worked effectively together to adapt and refine pre-existing emergency management arrangements to respond to COVID-19. However, lessons learned from prior reviews of emergency management arrangements, and from other jurisdictions, had not been implemented when Delta emerged in June 2021. As a result, agencies were not as fully prepared as they could have been to respond to the additional challenges presented by Delta.

In the period March 2020 to June 2021, the State's Emergency Management (EM) arrangements coordinated the New South Wales emergency response to COVID-19 with support from the Department of Premier and Cabinet (DPC) which led the cross-government COVID-19 Taskforce. NSW Government agencies enhanced the EM arrangements, which until then had typically been activated in response to natural disasters, to meet the specific circumstances of the pandemic.

However, the State Emergency Management Committee (SEMC), supported by Resilience NSW, did not address relevant recommendations arising from the 2020 Bushfires Inquiry before June 2021 and agencies did not always integrate lessons learned from other jurisdictions or scenario training exercises into emergency management plans or strategies before Delta. As a result, deficiencies in the EM arrangements, including representation of vulnerable communities on EM bodies, well-being support for multicultural communities in locked down environments and cross-agency information sharing, persisted when Delta emerged in June 2021.

It should be noted that for the purposes of this audit there is no benchmark, informed by precedent, that articulates what level of preparation would have been sufficient or proportionate. However, the steps required to address these gaps were reasonable and achievable, and the failure to do so meant that agencies were not as fully prepared as they could have been for the scale and escalation of Delta’s spread across the State.

The Delta Microstrategy complemented the EM arrangements to support greater coordination and agencies are working to improve their capability for future events

The Delta Microstrategy (the Microstrategy) led to innovations in information sharing and collaboration across the public service. Agencies involved in the response have completed, or are completing, reviews of their contribution to the response. That said, none of these reviews includes a focus on whole-of-government coordination.

On 23 July 2021, the NSW Government approved the establishment of the Microstrategy to respond to the additional challenges presented by Delta including the need to support communities most impacted by restrictions to movement and gathering in the LGAs of concern. An extensive range of government agencies were represented across eight Microstrategy workstreams, which coordinated with the existing EM arrangements to deliver targeted strategies to communities in high-risk locations and improve data and information sharing across government. This enhanced the public health, compliance, income and food support, communications and community engagement aspects of the response.

Agencies also leveraged learnings from early weeks of the Delta wave and were able to replicate those lessons in other locations. The use of pre-staging hubs in Fairfield to support food and personal hamper distribution was used a month later in Dubbo which acted as a central hub for more remote parts of the State.

Emergency management plans did not enable government to respond immediately to support vulnerable communities in high-risk LGAs or regional NSW

There are gaps in the emergency management plans relating to the support for individuals, families and businesses impacted by the stay-at-home orders and other restrictions to movement and gathering. These gaps affected agencies' ability to respond immediately when the need arose during Delta.

Emergency management plans and supporting instruments did not include provision for immediate relief for households, which meant arrangements for isolation income support and food security measures had to be designed in the early stages of Delta before it could be approved and deployed.

There were delays – sometimes only days, on occasion, weeks - in providing support to affected communities. In particular, there were delays to the provision of income support and in scaling up efforts to coordinate food and grocery hampers to households in isolation. In LGAs of concern, modest delays of a few days had a significant impact on people, especially those most vulnerable.

Although government issued stricter restrictions for workers in the Fairfield LGA on 14 July 2021, it only approved targeted income support for people in LGAs of concern on 16 August 2021.

Overall, agencies coordinated effectively to provide advice to government but there are opportunities to learn lessons to improve preparedness for future events

Agencies coordinated in providing advice to government. The advice was supported by timely public health information, although this was in the context of a pandemic, where data and information about the virus and its variants was changing regularly. However, agencies did not always consider the impact on key industries or supply chains when they provided advice to government, which meant that Public Health Orders would sometimes need to be corrected.

Public Health Orders were also updated as the response to Delta intensified or to address unintended consequences of previous orders. The frequency of changes hampered agencies' ability to effectively communicate changes to frontline staff and the community in a rapidly evolving situation.

The audit identified several occasions where there were delays, ranging from three to 21 days, between the provision of advice to government and subsequent decision-making (which we have not detailed due to the confidentiality of Cabinet deliberations). Agency officers advised of instances where they were not provided sufficient notice of changes to Public Health Orders to organise local infrastructure (such as traffic support for testing clinics) to support compliance with new requirements.

The COVID-19 pandemic arrived in Australia in late January 2020 as the bushfire and localised flooding emergencies were in their final stages. Between 2020 and mid-2021, agencies responded to the initial variants of COVID-19, managed a border closure with Victoria that lasted nearly four months and dealt with localised ‘flare-ups’ that required postcode-based restrictions on mobility in northern parts of Sydney and regional New South Wales. During this period, New South Wales had the opportunity to learn from events in Victoria which imposed strict restrictions on mobility across the State and the growing emergence of the Delta variant (Delta) across the Asia Pacific.

This section of the report assesses how emergency management and public health responses adapted to these lessons and determined preparedness for, and responses to, widespread community transmission of Delta in New South Wales.

The previous chapter discusses how agencies had refined the existing emergency management arrangements to suit the needs of a pandemic and describes some gaps that were not addressed. This chapter explores the first month of Delta (mid-June to mid-July 2021). It explores the areas where agencies were prepared and responses in place for the outbreak. It also discusses the impact of the gaps that were not addressed in the period prior to Delta and other issues that emerged.

NSW Health provided advice on the removal of restrictions based on up-to-date advice

The NSW Government discussed the gradual process for removing restrictions using the Doherty Institute modelling provided to National Cabinet on 10 August 2021. NSW Health highlighted the importance of maintaining a level of public health and safety measure bundles to further suppress case numbers. This was based on additional modelling from the Doherty Institute.

The Department of Regional NSW led discussion and planning around reopening with a range of proposal through August and September 2021. The Department of Premier and Cabinet and NSW Health jointly developed a paper to provide options on the restrictions when the State reached a level of 70% double dose vaccinations.

The roadmap to reopening was originally published on 9 September 2021. However, by 11 October 2021, the restrictions were relaxed when the 70% double dose threshold was reached to allow:

  • up to ten fully vaccinated visitors to a home (increased from five)
  • up to 30 fully vaccinated people attending outdoor gatherings (increased from 20)
  • weddings and funerals limits increased to 100 people (from 50)
  • the reopening of indoor pools for training, exercise and learning purposes only.

On the same day, the NSW Government announced further relaxation of restrictions once the 80% double dose threshold was reached. These restrictions were further relaxed on 8 November 2021. This included the removal of capacity restrictions to the number of visitors to a private residence, indoor pools to reopen for all purposes and density limits of one person for every two square metres, dancing allowed in nightclubs and 100% capacity in major stadia.

The NSW Government allowed workers in regional areas who received one vaccination dose to return to their workplace from 11 October 2021.

The Premier extended the date of easing of restrictions for unvaccinated people aged over 16 from 1 December to 15 December 2021.

Many agencies have undertaken reviews of their response to the Delta outbreak but a whole-of-government review has yet to be conducted

Various agencies and entities associated with the response to the Delta outbreak conducted after-action review processes. These processes assessed the achievements delivered, lessons learned and opportunities for improvement. However, a whole-of-government level review has not been conducted. This limits the New South Wales public service's ability to improve how it coordinates responses in future emergencies.

The agencies/entities that conducted reviews included:

  • South West Metropolitan region, Western NSW region, Fairfield Local Emergency Management Committee (LEMC), Dubbo Local Emergency Operations Controller (LEOCON), which were collated centrally by the State Emergency Operations Centre (SEOC)
  • Aboriginal Affairs NSW assessed representation and relevance of the emergency management arrangements for Aboriginal communities following the 2019 bushfires
  • Resilience NSW developed case studies to capture improved practice with regard to food security and supply chains
  • a community support and empowerment-focused after-action review undertaken by the Pillar 5 workstream of the Microstrategy.

Key lessons collated from the after-action reviews include:

  • the impact of variation in capability across agencies on the management of key aspects of the response including welfare support and logistics
  • issues with boundary differences between NSW Police Force regions, local government areas (LGA and local health districts (LHD) caused issues in delivering and coordinating services in an emergency situation 
  • the need to improve relationships between state and local Government outside of acute emergency responses to improve service delivery 
  • issues arising from impediments to information sharing between agencies and jurisdictions, such as:
    • timeliness and accuracy of data used to direct compliance activities
    • the impact of insufficient advance notice on changes to Public Health Orders
    • timely access to data across public sector agencies and other jurisdictions to inform decision-making, analysis and communications
    • gaps in data around ethnicity, geolocation of recent positive cases and infection/vaccination rates in Aboriginal communities.
  • the lack of Aboriginal community representation on many LEMCs
  • compared with the response to COVID-19 in 2020, improved coordination of communications with Culturally and Linguistically Diverse (CALD) populations with a reduction in overlapping messages and over-communication
  • improved attendance from agency representatives in LEMCs, and regional emergency operations centres (REOC) to improve interagency communications, planning, capability development and community engagement issues
  • deficiencies in succession planning and fatigue management practices
  • the potential for REOC Welfare/Well-being subgroups to be included as part of the wider efforts to community needs during emergencies.

NSW Health commenced a whole of system review of its COVID-19 response in May 2022. At the time of writing, the completion due date for the debrief is 7 November 2022. This debrief is expected to explore:

  • governance
  • engagement 
  • innovation and technology 
  • community impact 
  • workforce impact
  • system impact and performance.

NSW Health is also undertaking a parallel Intra-Action Review that is focused on the public health aspects of the response with finalisation estimated for the end of November 2022. At the time of completing this performance audit report, NSW Health had not finalised these reviews and, as a result, we cannot validate their findings against our own observations.

Recent inquiries are likely to impact the governance of emergency management in New South Wales

In March 2022, the NSW Government established an independent inquiry to examine and report on the causes of, preparedness for, response to and recovery from the 2022 floods. The Flood Inquiry report made 28 recommendations, which the NSW Government supported in full or in principle. Some of the recommendations relate directly to the governance and leadership of emergency management arrangements in New South Wales. 

The State Emergency Management Committee (SEMC) will likely be involved in, and impacted by, the recommendations arising from the Flood Inquiry with potential changes to its membership and reshaping of functional areas and agencies. At the same time, the SEMC may have a role in overseeing the changes that emerge from the SEOC consolidated after-action reviews. This can also extend to ensuring local and regional bodies have incorporated the required actions. There is a risk that the recommendations from the pandemic-based after-action reviews may not be considered due to the priority of action resulting from the Flood Inquiry.

Furthermore, there is potential for the SEMC to work with NSW Health during its system-wide review. Such an approach is likely to improve preparedness for future events.

Appendix one – Response from agencies

Appendix two – Chronology 2020–2021

Appendix three – About the audit

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #371 - released 20 December 2022

Published

Actions for Machinery of government changes

Machinery of government changes

Premier and Cabinet
Treasury
Whole of Government
Management and administration
Project management

What the report is about

The term ‘machinery of government’ refers to the way government functions and responsibilities are organised.

The decision to make machinery of government changes is made by the Premier. Changes may be made for a range of reasons, including to support the policy and/or political objectives of the government of the day.

Larger machinery of government changes typically occur after an election or a change of Premier.

This report assessed how effectively the Department of Planning, Industry and Environment (DPIE) and the Department of Regional NSW (DRNSW) managed their 2019 and 2020 machinery of government changes, respectively. It also considered the role of the Department of Premier and Cabinet (DPC) and NSW Treasury in overseeing machinery of government changes.

What we found

The anticipated benefits of the changes were not articulated in sufficient detail and the achievement of benefits has not been monitored. The costs of the changes were not tracked or reported.

DPC and NSW Treasury provided principles to guide implementation but did not require departments to collect or report information about the benefits or costs of the changes.

The implementation of the machinery of government changes was completed within the set timeframes, and operations for the new departments commenced as scheduled.

Major implementation challenges included negotiation about the allocation of corporate support staff and the integration of complex corporate and ICT systems.

What we recommended

DPC and NSW Treasury should:

  • consolidate existing guidance on machinery of government changes into a single document that is available to all departments and agencies
  • provide guidance for departments and agencies to use when negotiating corporate services staff transfers as a part of machinery of government changes, including a standard rate for calculating corporate services requirements
  • progress work to develop and implement common processes and systems for corporate services in order to support more efficient movement of staff between departments and agencies.

Fast facts

  • $23.7m is the estimated minimum direct cost of the 2019 DPIE changes to date, noting additional ICT costs will be incurred
  • $4.0m is the estimated minimum direct cost of the 2020 DRNSW changes, with an estimated $2.7 million ongoing annual cost
  • 40+ NSW Government entities affected by the 2019 machinery of government changes

The term ‘machinery of government’ refers to the way government functions and responsibilities are allocated and structured across government departments and agencies. A machinery of government change is the reorganisation of these structures. This can involve establishing, merging or abolishing departments and agencies and transferring functions and responsibilities from one department or agency to another.

The decision to make machinery of government changes is made by the Premier. These changes may be made for a range of reasons, including to support the policy and/or political objectives of the government of the day. Machinery of government changes are formally set out in Administrative Arrangements Orders, which are prepared by the Department of Premier and Cabinet, as instructed by the Premier, and issued as legislative instruments under the Constitution Act 1902.

The heads of agencies subject to machinery of government changes are responsible for implementing them. For more complex changes, central agencies are also involved in providing guidance and monitoring progress.

The NSW Government announced major machinery of government changes after the 2019 state government election. These changes took place between April and June 2019 and involved abolishing five departments (Industry; Planning and Environment; Family and Community Services; Justice; and Finance, Services and Innovation) and creating three new departments (Planning, Industry and Environment; Communities and Justice; and Customer Service). This also resulted in changes to the 'clusters' associated with departments. The NSW Government uses clusters to group certain agencies and entities with related departments for administrative and financial management. Clusters do not have legal status. Most other departments that were not abolished had some functions added or removed as a part of these machinery of government changes. For example, the functions relating to regional policy and service delivery in the Department of Premier and Cabinet were moved to the new Department of Planning, Industry and Environment.

Our Report on State Finances 2019, tabled in October 2019, outlined these changes and identified several issues that can arise from machinery of government changes if risks are not identified early and properly managed. These include: challenges measuring the costs and benefits of machinery of government changes; disruption to services due to unclear roles and responsibilities; and disruption to control environments due to staff, system and process changes.

In April 2020, the Department of Regional NSW was created in a separate machinery of government change. This involved moving functions and agencies related to regional policy and service delivery from the Department of Planning, Industry and Environment into a standalone department.

This audit assessed how effectively the Department of Planning, Industry and Environment (DPIE) and the Department of Regional NSW (DRNSW) managed their 2019 and 2020 machinery of government changes, respectively. It also considered the role of the Department of Premier and Cabinet and NSW Treasury in overseeing machinery of government changes. The audit investigated whether:

  • DPIE and DRNSW have integrated new responsibilities and functions in an effective and timely manner
  • DPIE and DRNSW can demonstrate the costs of the machinery of government changes
  • The machinery of government changes have achieved or are achieving intended outcomes and benefits.
Conclusion

It is unclear whether the benefits of the machinery of government changes that created the Department of Planning, Industry and Environment (DPIE) and the Department of Regional NSW (DRNSW) outweigh the costs. The anticipated benefits of the changes were not articulated in sufficient detail and the achievement of directly attributable benefits has not been monitored. The costs of the changes were not tracked or reported. The benefits and costs of the machinery of government changes were not tracked because the Department of Premier and Cabinet (DPC) and NSW Treasury did not require departments to collect or report this information. The implementation of the machinery of government changes was completed within the set timeframes, and operations for the new departments commenced as scheduled. This was achieved despite short timelines and no additional budget allocation for the implementation of the changes.

The rationale for establishing DPIE was not documented at the time of the 2019 machinery of government changes and the anticipated benefits of the change were not defined by the government or the department. For DRNSW, the government’s stated purpose was to provide better representation and support for regional areas, but no prior analysis was conducted to quantify any problems or set targets for improvement. Both departments reported some anecdotal benefits linked to the machinery of government changes. However, improvements in these areas are difficult to attribute because neither department set specific measures or targets to align with these intended benefits. Since the machinery of government changes were completed, limited data has been gathered to allow comparisons of performance before and after the changes.

DPC and NSW Treasury advised that they did not define the purpose and benefits of the machinery of government changes, or request affected departments to do so, because these were decisions of the government and the role of the public service was to implement the decisions.

We have attempted to quantify some of the costs of the DPIE and DRNSW changes based on the information the audited agencies could provide. This information does not capture the full costs of the changes because some costs, such as the impact of disruption on staff, are very difficult to quantify, and the costs of ICT separation and integration work may continue for several more years. Noting these limitations, we estimate the initial costs of these machinery of government changes are at least $23.7 million for DPIE and $4.0 million for DRNSW. For DPIE, this is predominantly made up of ICT costs and redundancy payments made around the time of the machinery of government change. For DRNSW it includes ICT costs and an increase in senior executive costs for a standalone department, which we estimate is an ongoing cost of at least $1.9 million per year.

For the DPIE machinery of government change, there were risks associated with placing functions and agencies that represent potentially competing policy interests within the same 'cluster', such as environment protection and industry. We did not see evidence of plans to manage these issues being considered by DPIE as a part of the machinery of government change process.

The efficiency of machinery of government changes could be improved in several ways. This includes providing additional standardised guidance on the allocation of corporate functions and resources when agencies are being merged or separated, and consolidating guidance on defining, measuring and monitoring the benefits and costs of machinery of government changes.

Appendix one – Response from agencies

Appendix two – About the audit

Appendix three – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #359 - released (17 December 2021).

Published

Actions for Their Futures Matter

Their Futures Matter

Justice
Community Services
Education
Health
Whole of Government
Cross-agency collaboration
Internal controls and governance
Management and administration
Project management

The Auditor-General for New South Wales, Margaret Crawford, released a report today examining whether the Department of Communities and Justice had effective governance and partnership arrangements in place to deliver ‘Their Futures Matter’.

Their Futures Matter was intended to place vulnerable children and families at the heart of services, and direct investment to where funding and programs deliver the greatest social and economic benefits. It was a four-year whole-of-government reform in response to the 2015 Tune Review of out-of-home care.

The Auditor-General found that while important foundations were put in place, and new programs trialled, the key objective to establish an evidence-based whole-of-government early intervention approach for vulnerable children and families in NSW was not achieved.

Governance and cross-agency partnership arrangements to deliver Their Futures Matter were found to be ineffective. 'Their Futures Matter lacked mechanisms to secure cross portfolio buy‑in and did not have authority to drive reprioritisation of government investment', the Auditor-General said.

At the reform’s close, the majority of around $380 million in investment funding remains tied to existing agency programs, with limited evidence of their comparative effectiveness or alignment with Their Futures Matter policy objectives. The reform concluded on 30 June 2020 without a strategy or plan in place to achieve its intent.

The Auditor-General made four recommendations to the Department of Communities and Justice, aimed at improving implementation of outstanding objectives, revising governance arrangements, and utilising the new human services data set to address the intent of the reform. However, these recommendations respond only in part to the findings of the audit.

According to the Auditor-General, ‘Cross-portfolio leadership and action is required to ensure a whole-of-government response to delivering the objectives of Their Futures Matter to improve outcomes for vulnerable children, young people and their families in New South Wales.’

Read full report (PDF)

In 2016, the NSW Government launched 'Their Futures Matter' (TFM) - a whole-of-government reform aimed at delivering improved outcomes for vulnerable children, young people and their families. TFM was the government's key response to the 2015 Independent Review of Out of Home Care in New South Wales (known as 'the Tune Review').

The Tune Review found that, despite previous child protection reforms, the out of home care system was ineffective and unsustainable. It highlighted that the system was not client-centred and was failing to improve the long-term outcomes for vulnerable children and families. The review found that the greatest proportion of relevant expenditure was made in out of home care service delivery rather than in evidence-based early intervention strategies to support children and families when vulnerabilities first become evident to government services (such as missed school days or presentations to health services).

The then Department of Family and Community Services (FACS) designed the TFM reform initiatives, in consultation with central and human services agencies. A cross-agency board, senior officers group, and a new unit in the FACS cluster were established to drive the implementation of TFM. In the 2016–17 Budget, the government allocated $190 million over four years (2016–17 to 2019–20) to the reform. This resourced the design and commissioning of evidence-based pilots, data analytics work, staffing for the implementation unit and secretariat support for the board and cross-agency collaboration.

As part of the TFM reform, the Department of Premier and Cabinet, NSW Treasury and partnering agencies (NSW Health, Department of Education and Department of Justice) identified various existing programs that targeted vulnerable children and families (such as the preceding whole-of-government ‘Keep Them Safe’ reform coming to an end in June 2020). Funding for these programs, totalling $381 million in 2019–20, was combined to form a nominal ‘investment pool’. The government intended that the TFM Implementation Board would use this pool to direct and prioritise resource allocation to evidence-based interventions for vulnerable children and families in NSW.

This audit assessed whether TFM had effective governance and partnership arrangements in place to enable an evidence-based early intervention investment approach for vulnerable children and families in NSW. We addressed the audit objective with the following audit questions:

  • Was the TFM reform driven by effective governance arrangements?
  • Was the TFM reform supported by effective cross-agency collaboration?
  • Has the TFM reform generated an evidence base to inform a cross-agency investment approach in the future?

The audit did not seek to assess the outcomes for children, young people and families achieved by TFM programs and projects.

Conclusion

The governance and cross-agency partnership arrangements used to deliver the Their Futures Matter reform were ineffective. Important foundations were put in place, and new programs trialled over the reform's four years. However, an evidence-based whole-of-government early intervention approach for vulnerable children and families in NSW − the key objective of the reform − was not established. The reform concluded in June 2020 without a strategy or plan in place to achieve its intent.

The governance arrangements established for the Their Futures Matter (TFM) reform did not provide sufficient independence, authority and cross-agency clout to deliver on the reform’s intent. This hindered delivery of the reform's key elements, particularly the redirection of funding to evidence-based earlier intervention supports, and limited the impact that TFM could have on driving system change.

TFM increased focus on the contribution that other agencies outside of the former Family and Community Services portfolio could make in responding to the needs of vulnerable children and families, and in reducing the demand costs of related government service delivery. Despite being a whole-of-government reform, TFM lacked mechanisms to secure cross-portfolio buy-in and lacked the powers to drive reprioritisation of government investment in evidence-based and earlier intervention supports across agencies. At the reform’s close, the majority of the reform's investment pool funding remained tied to existing agency programs, with limited evidence of their comparative effectiveness or alignment with Their Futures Matter policy objectives.

TFM began building an evidence base about ‘what works’, including piloting programs and creating a new dataset to identify risk factors for vulnerability and future costs to government. However, this evidence base does not yet comprehensively map how existing services meet needs, identify system duplications or gaps, nor demonstrate which government funded supports and interventions are most effective to make a difference to life outcomes for vulnerable children and families in NSW.
Despite these issues, the need, intent and vision for Their Futures Matter remains relevant and urgent, as issues identified in the Tune Review remain pertinent.

Their Futures Matter (TFM) is a whole-of-government reform to deliver improved outcomes for vulnerable children, young people and their families.

Supported by a cross-agency TFM Board, and the TFM Unit in the then Department of Family and Community Services (FACS), the reform aimed to develop whole-of-government evidence-based early intervention investment approaches for vulnerable children and families in NSW.

Governance refers to the structures, systems and practices that an organisation has in place to:

  • assign decision-making authorities and establish the organisation's strategic direction
  • oversee the delivery of its services, the implementation of its policies, and the monitoring and mitigation of its key risks
  • report on its performance in achieving intended results, and drive ongoing improvements.

We examined whether the TFM reform was driven by effective governance arrangements and cross-agency collaboration.

The reform agenda and timeframe set down for Their Futures Matter (TFM) were ambitious. This chapter assesses whether the TFM Board and TFM Unit had the capability, capacity and clout within government to deliver the reform agenda.

Creating a robust evidence base was important for Their Futures Matter, in order to:

  • identify effective intervention strategies to improve supports and outcomes for vulnerable children and families
  • make efficient use of taxpayer money to assist the maximum number of vulnerable children and families
  • inform the investment-based approach for future funding allocation.

This chapter assesses whether the TFM reform has developed an evidence base to inform cross-agency investment decisions.

Appendix one – Response from agency

Appendix two – TFM governance entities

Appendix three – TFM Human Services Data Set

Appendix four – TFM pilot programs

Appendix five – About the audit

Appendix six – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #337 - released 24 July 2020

Published

Actions for Unsolicited proposal process for the lease of Ausgrid

Unsolicited proposal process for the lease of Ausgrid

Premier and Cabinet
Asset valuation
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Service delivery
Shared services and collaboration

In October 2016, the NSW Government accepted an unsolicited proposal from IFM Investors and AustralianSuper to lease 50.4 per cent of Ausgrid for 99 years. The deal followed the Federal Government’s rejection of two bids from foreign investors, for national security reasons.

A performance audit of the lease of Ausgrid has found shortcomings in the unsolicited proposal process. Releasing the audit findings today, the Auditor-General for New South Wales, Margaret Crawford said ‘this transaction involved a $20 billion asset owned by the people of New South Wales. As such, it warranted strict adherence to established guidelines’.

Ausgrid is a distributor of electricity to eastern parts of Sydney, the Central Coast, Newcastle and the Hunter Region.

In June 2014, the then government announced its commitment to lease components of the state's electricity network as part of the Rebuilding NSW plan. Implementation of the policy began after the government was re-elected in 2015. Between November 2015 and August 2016, the NSW Government held a competitive tender process to lease 50.4 per cent of Ausgrid for 99 years. The NSW Government abandoned the process on 19 August 2016 after the Australian Treasurer rejected two bids from foreign investors, for national security reasons. That day, the Premier and Treasurer released a media statement clarifying the government's objective to complete the transaction via a competitive process in time to include the proceeds in the 2017–18 budget.

On 31 August 2016, the state received an unsolicited proposal from IFM Investors and AustralianSuper to acquire an interest in Ausgrid under the same terms proposed by the state during the tender process. In October 2016, the government accepted the unsolicited proposal. 

This audit examined whether the unsolicited proposal process for the partial long-term lease of Ausgrid was effectively conducted and in compliance with the government’s 2014 Unsolicited Proposals: Guide for Submission and Assessment (Unsolicited Proposals Guide or the Guide). 

The audit focused on how the government-appointed Assessment Panel and Proposal Specific Steering Committee assessed key requirements in the Guide that unsolicited proposals must be demonstrably unique and represent value for money. 

Conclusion

The evidence available does not conclusively demonstrate the unsolicited proposal was unique, and there were some shortcomings in the negotiation process, documentation and segregation of duties. That said, before the final commitment to proceed with the lease, the state obtained assurance that the proposal delivered value for money. 

It is particularly important to demonstrate unsolicited proposals are unique, in order to justify the departure from other transaction processes that offer greater competition, transparency and certainty about value for money.

The Assessment Panel and the Proposal Specific Steering Committee determined the Ausgrid unsolicited proposal was unique, primarily on the basis that the proponent did not require foreign investment approval from the Australian Treasurer, and the lease transaction could be concluded earlier than through a second tender process. However, the evidence that persuaded the Panel and Committee did not demonstrate that no other proponent could conclude the transaction in time to meet the government’s deadline. 

It is not appropriate to determine an unsolicited proposal is unique because it delivers an earlier outcome than possible through a tender process. The Panel and Committee did not contend, and it is not evident, that the unsolicited proposal was the only way to meet the government’s transaction deadline.

The evidence does not demonstrate that the proponent was the only party that would not have needed foreign investment approval to participate in the transaction. It also does not demonstrate that the requirement for foreign investment approval would have reduced the pool of foreign buyers to the degree that it would be reasonable to assume none would emerge. 

The Panel, Committee and financial advisers determined that the final price represented value for money, and that retendering offered a material risk of a worse financial outcome. However, an acceptable price was revealed early in the negotiation process, and doing so made it highly unlikely that the proponent would offer a higher price than that disclosed. The Department of Premier and Cabinet (DPC) and NSW Treasury were not able to provide a documented reserve price, bargaining strategy or similar which put the negotiations in context. It is not evident that the Panel or Committee authorised, justified or endorsed negotiations in advance. 

Key aspects of governance recommended by the Guide were in place. Some shortcomings relating to role segregation, record keeping and probity assurance weakened the effectiveness of the unsolicited proposal process adopted for Ausgrid.

The reasons for accepting that the proposal and proponent were unique are not compelling.

The Unsolicited Proposals Guide says the 'unique benefits of the proposal and the unique ability of the proponent to deliver the proposal' must be demonstrated. 

The conclusion reached by the Panel and Committee that the proposal offered a ‘unique ability to deliver (a) strategic outcome’ was primarily based on the proponent not requiring foreign investment approval from the Australian Treasurer, and allowing the government to complete the lease transaction earlier than by going through a second tender process. 

It is not appropriate to determine an unsolicited proposal is unique because it delivers an earlier outcome than possible through a tender process. The Panel and Committee did not contend, and it is not evident, that the unsolicited proposal was the only way to meet the government’s transaction deadline.

The evidence does not demonstrate that the proponent was the only party that would not have needed foreign investment approval to participate in the transaction. Nor does it demonstrate that the requirement for foreign investment approval would have reduced the pool of foreign buyers to the degree that it would be reasonable to assume none would emerge. 

That said, the Australian Treasurer’s decision to reject the two bids from the previous tender process created uncertainty about the conditions under which he would approve international bids. The financial advisers engaged for the Ausgrid transaction informed the Panel and Committee that:

  • it was not likely another viable proponent would emerge soon enough to meet the government’s transaction deadline
  • the market would be unlikely to deliver a better result than offered by the proponent
  • going to tender presented a material risk of a worse financial result. 

The Unsolicited Proposals Guide says that a proposal to directly purchase or acquire a government-owned entity or property will generally not be unique. The Ausgrid unsolicited proposal fell into this category. 

Recommendations:
DPC should ensure future Assessment Panels and Steering Committees considering a proposal to acquire a government business or asset:

  • recognise that when considering uniqueness they should: 
    • require very strong evidence to decide that both the proponent and proposal are the only ones of their kind that could meet the government’s objectives 
    • give thorough consideration to any reasonable counter-arguments against uniqueness.
  • rigorously consider all elements of the Unsolicited Proposals Guide when determining whether a proposal should be dealt with as an unsolicited proposal, and document these deliberations and all relevant evidence
  • do not use speed of transaction compared to a market process as justification for uniqueness.
The process to obtain assurance that the final price represented value for money was adequate. However, the negotiation approach reduced assurance that the bid price was maximised. 

The Panel and Committee concluded the price represented value for money, based on peer-reviewed advice from their financial advisers and knowledge acquired from previous tenders. The financial advisers also told the Panel and Committee that there was a material risk the state would receive a lower price than offered by the unsolicited proposal if it immediately proceeded with a second market transaction. 

The state commenced negotiations on price earlier than the Guide says they should have. Early disclosure of a price that the state would accept reduced the likelihood of achieving a price greater than this. DPC says the intent of this meeting was to quickly establish whether the proponents could meet the state’s benchmark rather than spending more time and resources on a proposal which had no prospect of proceeding.

DPC and NSW Treasury were not able to provide a documented reserve price, negotiation strategy or similar which put the negotiations and price achieved in context. It was not evident that the Panel or Committee authorised, justified or endorsed negotiations in advance. However, the Panel and Committee endorsed the outcomes of the negotiations. 

The negotiations were informed by the range of prices achieved for similar assets and the specific bids for Ausgrid from the earlier market process.

Recommendations:
DPC should ensure any future Assessment Panels and Steering Committees considering a proposal to acquire a government business or asset:

  • document a minimum acceptable price, and a negotiating strategy designed to maximise price, before commencing negotiations
  • do not communicate an acceptable price to the proponent, before the negotiation stage of the process, and then only as part of a documented bargaining strategy.
Key aspects of governance recommended by the Guide were in place, but there were some shortcomings around role segregation, record keeping and probity assurance.

The state established a governance structure in accordance with the Unsolicited Proposals Guide, including an Assessment Panel and Proposal Specific Steering Committee. The members of the Panel and Steering Committee were senior and experienced officers, as befitted the size and nature of the unsolicited proposal. 

The separation of negotiation, assessment and review envisaged by the Guide was not maintained fully. The Chair of the Assessment Panel and a member of the Steering Committee were involved in negotiations with the proponent. 

DPC could not provide comprehensive records of some key interactions with the proponent or a documented negotiation strategy. The absence of such records means the Department cannot demonstrate engagement and negotiation processes were authorised and rigorous. 

The probity adviser reported there were no material probity issues with the transaction. The probity adviser also provided audit services. This is not good practice. The same party should not provide both advisory and audit services on the same transaction.

Recommendations:
DPC should ensure any future Assessment Panels and Steering Committees considering a proposal to acquire a government entity or asset:
•    maintain separation between negotiation, assessment and review in line with the Unsolicited Proposals Guide
•    keep an auditable trail of documentation relating to the negotiation process
•    maintain separation between any probity audit services engaged and the probity advisory and reporting services recommended in the current Guide.

Published

Actions for Progress and measurement of the Premier's Priorities

Progress and measurement of the Premier's Priorities

Premier and Cabinet
Compliance
Internal controls and governance
Management and administration
Project management
Risk
Service delivery
Shared services and collaboration
Workforce and capability

The Premier’s Implementation Unit uses a systematic approach to measuring and reporting progress towards the Premier’s Priorities performance targets, but public reporting needed to improve, according to a report released today by the Auditor-General of NSW, Margaret Crawford.

The Premier of New South Wales has established 12 Premier’s Priorities. These are key performance targets for government.

The 12 Premier's Priorities
  • 150,000 new jobs by 2019

  • Reduce the volume of litter by 40 per cent by 2020

  • 10 key projects in metro and regional areas to be delivered on time and on budget, and nearly 90 local infrastructure projects to be delivered on time

  • Increase the proportion of NSW students in the top two NAPLAN bands by eight per cent by 2019

  • Increase the proportion of women in senior leadership roles in the NSW Government sector from 33 to 50 per cent by 2025 and double the number of Aboriginal and Torres Strait Islander people in senior leadership roles in the NSW Government sector, from 57 to 114

  • Increase the proportion of young people who successfully move from Specialist Homelessness Services to long-term accommodation to more than 34 per cent by 2019

  • 61,000 housing completions on average per year to 2021

  • Reduce the proportion of domestic violence perpetrators reoffending by 25 per cent by 2021

  • Improve customer satisfaction with key government services every year, this term of government to 2019

  • Decrease the percentage of children and young people re-reported at risk of significant harm by 15 per cent by 2020

  • 81 per cent of patients through emergency departments within four hours by 2019

  • Reduce overweight and obesity rates of children by five percentage points by 2025


Source: Department of Premier and Cabinet, Premier’s Priorities website.

Each Premier’s Priority has a lead agency and minister responsible for achieving the performance target.

The Premier’s Implementation Unit (PIU) was established within the Department of Premier and Cabinet (DPC) in 2015. The PIU is a delivery unit that supports agencies to measure and monitor performance, make progress toward the Premier’s Priorities targets, and report progress to the Premier, key ministers and the public.

This audit assessed how effectively the NSW Government is progressing and reporting on the Premier's Priorities.

 


The Premier’s Implementation Unit (PIU) is effective in assisting agencies to make progress against the Premier’s Priorities targets. Progress reporting is regular but transparency to the public is weakened by the lack of information about specific measurement limitations and lack of clarity about the relationship of the targets to broader government objectives.The PIU promotes a systematic approach to measuring performance and reporting progress towards the Premier’s Priorities’ performance targets. Public reporting would be improved with additional information about the rationale for choosing specific targets to report on broader government objectives.

The PIU provides a systematic approach to measuring performance and reporting progress towards the Premier's Priorities performance targets. Public reporting would be improved with additional information about the rationale for choosing specific targets to report on broader government objectives. The data used to measure the Premier’s Priorities comes from a variety of government and external datasets, some of which have known limitations. These limitations are not revealed in public reporting, and only some are revealed in progress reported to the Premier and ministers. This limits the transparency of reporting.

The PIU assists agencies to avoid unintended outcomes that can arise from prioritising particular performance measures over other areas of activity. The PIU has adopted a collaborative approach to assisting agencies to analyse performance using data, and helping them work across organisational silos to achieve the Premier’s Priorities targets.


 


Data used to measure progress for some of the Premier’s Priorities has limitations which are not made clear when progress is reported. This reduces transparency about the reported progress. Public reporting would also be improved with additional information about the relationship between specific performance measures and broader government objectives.

The PIU is responsible for reporting progress to the Premier, key ministers and the public. Agencies provide performance data and some play a role in preparing progress reports for the Premier and ministers. For 11 of the Premier's Priorities, progress is reported against measurable and time-related performance targets. For the infrastructure priority, progress is reported against project milestones.

Progress of some Priorities is measured using data that has known limitations, which should be noted wherever progress is reported. For example, the data used to report on housing completions does not take housing demolitions into account, and is therefore overstating the contribution of this performance measure to housing supply. This known limitation is not explained in progress reports or on the public website.

Data used to measure progress is sourced from a mix of government and external datasets. Updated progress data for most Premier’s Priorities is published on the Premier’s Priorities website annually, although reported to the Premier and key ministers more frequently. The PIU reviews the data and validates it through fieldwork with front line agencies. The PIU also assists agencies to avoid unintended outcomes that can arise from prioritising single performance measures. Most, but not all, agencies use additional indicators to check for misuse of data or perverse outcomes.

We examined the reporting processes and controls for five of the Premier’s Priorities. We found that there is insufficient assurance over the accuracy of the data on housing approvals.

The relationships between performance measures and broader government objectives is not always clearly explained on the Premier’s Priority website, which is the key source of public information about the Premier’s Priorities. For example, the Premier’s Priority to reduce litter volumes is communicated as “Keeping our Environment Clean.” While the website explains why reducing litter is important, it does not clearly explain why that particular target has been chosen to measure progress in keeping the environment clean.

By December 2018, the Department of Premier and Cabinet should:

  1. improve transparency of public reporting by:
    • providing information about limitations of reported data and associated performance
    • clarifying the relationship between the Premier’s Priorities performance targets and broader government objectives.
  2. ensure that processes to check and verify data are in place for all agency data sources
  3. encourage agencies to develop and implement additional supporting indicators for all Premier’s Priority performance measures to prevent and detect unintended consequences or misuse of data.

 


The Premier's Implementation Unit is effective in supporting agencies to deliver progress towards the Premier’s Priority targets.

The PIU promotes a systematic approach to monitoring and reporting progress against a target, based on a methodology used in delivery units elsewhere in the world. The PIU undertakes internal self-evaluation, and commissions regular reviews of methodology implementation from the consultancy that owns the methodology and helped to establish the PIU. However, the unit lacks periodic independent reviews of their overall effectiveness. The PIU has adopted a collaborative approach and assists agencies to analyse performance using data, and work across organisational silos to achieve the Premier’s Priorities targets.

Agency representatives recognise the benefits of being responsible for a Premier's Priority and speak of the value of being held to account and having the attention of the Premier and senior ministers.

By June 2019, the Department of Premier and Cabinet should:

  1. establish routine collection of feedback about PIU performance including:
    • independent assurance of PIU performance
    • opportunity for agencies to provide confidential feedback.