Refine search Expand filter

Reports

Published

Actions for Credit card management in Local Government

Credit card management in Local Government

Local Government
Internal controls and governance
Management and administration
Procurement
Risk

The Auditor-General for New South Wales, Margaret Crawford, released a report today examining credit card management in Local Government.

The audit was in response to a letter from the then Minister for Local Government in November 2018. The audit assessed the effectiveness of credit card management practices in six councils, including in the areas of policies, procedures, compliance and monitoring.

The audit found that all six councils had gaps in their credit card policies and procedures. The Auditor-General recommended that the Department of Planning, Industry and Environment publish guidelines on credit card management for the Local Government sector. The report also generated insights for the Local Government sector with respect to credit card management.

Read full report (PDF)

In 2018–19, all councils responding to an Audit Office survey (representing over 90 per cent of the sector) indicated they issued credit cards to staff members to make work-related purchases. As there are no sector-wide requirements or policies for credit card use and management in Local Government, councils have developed their credit card management frameworks to suit their own needs. The quality of credit card policies and procedures may therefore vary across the sector.

Credit cards are an efficient means of payment, especially for low-value purchases. Compared to the use of petty cash, credit card transactions provide better transparency and accountability for expenditure. By using credit cards, councils only need to make one payment each month, which can reduce the time spent on paying separate vendors, as in the case of purchase orders.

This audit assessed the effectiveness of credit card management practices in six councils: Dubbo Regional Council, Junee Shire Council, Lane Cove Council, Nambucca Valley Council, Penrith City Council and Shellharbour City Council. The councils selected represent a mix of rural, regional and metropolitan councils. They were also among the top ten users of credit cards within their geographical classification, in terms of the number of credit cards issued or the number of transactions per credit card.

This audit referenced the NSW Treasury's Policy and Guidelines Paper TPP17–09 'Use and Management of NSW Government Purchasing Cards', as its principles and recommendations for NSW Government agencies are relevant for councils.

The Audit Office of New South Wales Report on Local Government 2019 provided a high-level overview of credit card management across the sector. While over 90 per cent of councils reported that they had a credit card policy and a credit card acquittal process, the quality of these policies and procedures may vary across the sector as there is no standardised or recommended approach to credit card management for Local Government. This audit complements the Report on Local Government 2019 by providing a detailed discussion of the effectiveness of credit card management practices in councils.

Audit conclusion

All six audited councils had important gaps in their credit card policies and procedures. Their reconciliation of credit card transactions needs to be enhanced to enable detection of potential misuse or fraud.
 
The audit found important gaps in each of the six audited councils' credit card management practices. Their policies and procedures covered the essential aspects of credit card use and management, but a lack of coverage or clarity in some areas could lead to inconsistent and inappropriate use of credit cards. These areas included: eligibility to hold a credit card, aligning credit card limits with financial delegations, and the reconciliation procedures.
 
While all six councils conducted reconciliations of credit card transactions, the processes need to be enhanced to enable detection of potential misuse or fraud. Reconciliations had focused solely on verifying receipts, and did not require evidence of business-related purposes, even for transactions such as alcohol purchases or spending at entertainment venues. Five of the six councils also did not include compliance checks in their reconciliation process, such as checking that purchases were not for restricted items.
 
The level of senior management involvement in monitoring credit card use varied across the six councils. Three of the six councils did not generate regular reports for management oversight. Five of the six councils had no plans for internal audits or targeted reviews of credit card management and use.

Council staff provided with a credit card can purchase from a wide range of businesses, including online transactions with overseas vendors. However, councils may limit the types of purchases that staff can make through their policies and procedures or by setting controls that block certain transaction types such as cash advances. To examine credit card usage, the audit obtained credit card transaction data from 1 July 2016 to 30 June 2019 for the six councils in this review. The data included:

  • transaction date
  • amount
  • merchant category code (MCC)
  • merchant name.

The audit analysed the number and value of transactions by each council, and the types of purchases made using credit cards.

The existence of a documented approach to managing credit cards ensures transparency and consistency of use within the council. A credit card management framework that contains preventative and detective controls can also minimise risks of fraud, misuse and wastage.

There is no prescribed credit card management framework for Local Government, but typical components of a credit card management framework include:

  • policies and procedures
  • guidance for staff
  • monitoring and reporting.

With no detailed guidance notes similar to those in TPP17–09 for NSW Government, councils have developed their own credit card management framework based on their size, structure, resources and intended credit card usage. For instance, the size of a council has implications for the number of credit cards issued, which in turn influences the arrangements for training and guidance provided to cardholders and approvers.

The intended level of credit card usage may determine whether a council adopts a manual or electronic credit card management system and councils should identify the system that best meets their needs. For instance, a council with few credit cards may not be able to justify investment in an electronic system. On the other hand, a manual system may only be viable for councils with a low number of credit cards and a low number of transactions.

Among the six councils audited, the three councils with fewer cards and a lower number of transactions had a manual credit card management system, while the three councils with more cards and a higher number of transactions used an electronic system.

Exhibit 10 summarises the six councils' policies on use of credit cards.

Exhibit 10: Overview of the six councils' policies on credit card use
Council Audit Office classification Number of staff (full-time equivalent) Number of credit cards issued (current at August 2019) Policy on credit card use
Dubbo Regional Council Regional 453 77 Purchase cards are used for official council business up to $5,000 and the policy allows cardholders to delegate the use of their purchase cards to other staff members.
Junee Shire Council Rural 71 1 Corporate credit cards are for council business activities and minor purchases where a purchase order is not accepted. Items that can be purchased via a purchase order should not be purchased on a corporate credit card.
Lane Cove Council Metropolitan 192 6 Corporate credit cards are for official council business, but should not be used when there is an alternative form of payment that aligns with the council's purchasing process.
Nambucca Valley Council Rural 110 37 Purchase cards are used for the payment of goods and services associated with council businesses.
Penrith City Council Metropolitan 1,031 167 Purchase cards are used for ‘low value and low risk procurement of goods and services’, while corporate cards are held by senior staff for ‘non-routine low value work related purchases’.
Shellharbour City Council Regional 372 65 Credit cards are for purchases up to $9,999 and the preferred payment method for transactions under $1,000.
Source: Audit Office of New South Wales analysis of council credit card registers, policies and procedures 2020; staff numbers from Office of Local Government's 'Your Council' website, except for Junee Shire Council which comes from their Workforce Plan 2020–24.

While it is important for councils to have an established credit card management framework, it is equally important that they ensure compliance in practice. This chapter examines councils' credit card management practices – how well staff members were complying with policies and procedures, and how effective their credit card controls were. The chapter is structured to cover:

  • preventative controls (embedded in the issuance, use and cancellation of cards) that prevent fraud and misuse
  • detective controls (embedded in reconciliation and record keeping) that assist in detecting fraud and misuse.

Where ineffective credit card management practices are identified, councils should reflect on whether they need to more closely monitor compliance, or whether there are fundamental deficiencies in their policies and procedures that need to be refined.

Dubbo Regional Council had gaps in its credit card policy and procedures. It allowed cardholders to share their credit card with other staff members, which complicated credit card management, increased the risk of misuse and fraud, and breached its agreement with the credit card issuer. The council's reconciliation of credit card transactions needs to be enhanced to ensure it can review compliance with policy and detect potential misuse or fraud.

Dubbo Regional Council had 77 credit cards at the time of the audit. The council's policy on credit card sharing violated its agreement with the card issuer that each credit card should be for the respective cardholder's use only. Credit card sharing also increases the risk of misuse and fraud.

The council's credit card policy and procedures lacked clarity in several areas. The eligibility criteria were broad and there was a risk of inconsistency in granting approvals, especially since the council gave approval delegations to multiple senior staff members. The policy and procedures also lacked guidance on the reconciliation of the general manager's credit card and the management of Cabcharge.

The audit identified gaps in the council's credit card management practices. While the council had a clear policy on financial delegations, there was no evidence that credit card limits were monitored in line with financial delegations. The credit card register contained inaccurate information, and the council was also unable to provide records of certain transactions requested for review by the audit.

The council's credit card reconciliation process needs to be enhanced to enable detection of potential misuse or fraud. It did not include compliance checks or reviewing the business-related purpose of transactions. Purchases of restricted items such as fuel, meals and entertainment were not accompanied by evidence of need or exemption. Travel expenses were not checked against travel pre-approval forms. The audit also identified instances of split transactions. The council provided no evidence of the finance team's involvement in the reconciliation of credit card transactions.

Senior management oversight of credit card use was lacking, as the council did not produce reports on credit card use. There was also no evidence that the internal auditor had undertaken monitoring activities as required in the credit card policy.

Recommendations

Dubbo Regional Council should immediately:

1. amend its credit card policy to prevent cardholders from sharing their credit card with other staff.

By December 2020, Dubbo Regional Council should:

2. clarify in the credit card policy and procedures:

  • eligibility criteria for a credit card
  • reconciliation arrangements for the general manager’s credit card
  • Cabcharge management policy and procedures

3. ensure that credit card management practices include:

  • monitoring credit card limits in line with financial delegations
  • considering the use of credit card blocks
  • keeping the credit card register are up-to-date, accurate and complete
  • maintaining complete and accurate records

4. ensure reconciliation involves:

  • scrutinising business-related purposes and incident details of transactions
  • keeping a record of the finance team's review of transactions
  • reviewing transactions against travel pre-approval forms (where applicable)
  • recording vehicle details and mileage when credit cards are used in place of fuel cards
  • checking that there are no split transactions

5. ensure there is ongoing senior management oversight of credit card use

6. ensure the internal auditor undertakes monitoring activities as specified in the credit card policy.

 

Junee Shire Council had gaps in its credit card policy and procedures. The council's reconciliation of credit card transactions needs to be enhanced to ensure it can review compliance with policy and detect potential misuse or fraud.

Junee Shire Council had only one credit card, held by the general manager, at the time of the audit. Staff members could seek approval from the general manager to purchase using the credit card. This raises concerns of credit card sharing, which would be a violation of the council's agreement with its credit card issuer. Credit card sharing also increases the risk of misuse and fraud.

The council had fuel cards and store cards for use by staff members. However, its credit card policy and procedures did not cover the management of these types of cards. The lack of documented rules and guidance increases the risk of misuse and fraud.

The audit identified other gaps in the council's credit card management practices:

  • the credit card limit was not monitored in line with financial delegation
  • there was a lack of targeted guidance for the approver (the mayor) in reconciliation
  • the council was unable to provide records of certain transactions requested for review by the audit
  • the council did not review its credit card policy according to schedule.

The council's credit card reconciliation process needs to be enhanced to enable detection of potential misuse or fraud. It did not include reviewing the business-related purpose of transactions. The council also provided no evidence of the finance team's involvement in the reconciliation of credit card transactions.

As the cardholder, the general manager reviewed all transactions every month. As the approver, the mayor (or deputy mayor) had to sign off on these transactions. Hence, there was sufficient management oversight of the council's credit card use. However, there was a lack of periodic review of the council's credit card use, as it was not included in the council's forward program of internal audits.

Recommendations

Junee Shire Council should immediately:

1. amend its credit card policy to prevent cardholders from sharing their credit card with other staff.

By December 2020, Junee Shire Council should:

2. clarify in the credit card policy and procedures:

  • fuel card management policy and procedures
  • store card management policy and procedures

3. ensure that credit card management practices include:

  • monitoring credit card limits in line with financial delegations
  • considering the use of credit card blocks
  • providing approvers with targeted guidance
  • maintaining complete and accurate records

4. ensure reconciliation involves:

  • scrutinising business-related purposes and incident details of transactions
  • keeping a record of the finance team's review of transactions
  • checking travel pre-approval forms (where applicable)
  • recording vehicle details and mileage when credit cards are used in place of fuel cards
  • checking that there are no split transactions

5. develop a plan for periodic reviews (e.g. internal audit) of credit card use and management

6. ensure its credit card policy and procedures are reviewed according to schedule.

 

Lane Cove Council had gaps in its credit card policy and procedures. The council's reconciliation of credit card transactions needs to be enhanced to ensure it can review compliance with policy and detect potential misuse or fraud.

Lane Cove Council had six credit cards, held by the most senior staff members, at the time of the audit. During our interviews, cardholders advised that they had shared their credit card with reporting staff. Credit card sharing is a violation of the council's agreement with its credit card issuer, and it also increases the risk of misuse and fraud.

The council's credit card policy lacked clarity in several areas. While the general manager had delegation to authorise the issue of credit cards, the policy did not specify any eligibility criteria. The policy and procedures also lacked guidance on the reconciliation of the general manager's credit card and the management of fuel cards and store cards.

The audit identified gaps in the council's credit card management practices. There was no evidence that credit card limits were monitored in line with financial delegations. The credit card register contained inaccurate information, and the council was also unable to provide records of certain transactions requested for review by the audit.

The council's credit card reconciliation process needs to be enhanced to enable detection of potential misuse or fraud. The process also did not include compliance checks or reviewing the business-related purpose of transactions. Purchases of restricted items such as fuel and fine payments were not accompanied by adequate justification. There was a lack of targeted guidance for approvers in reconciliation, and the council only evidenced the finance team's involvement in an administrative capacity (i.e. entering data into the journals).

Senior management oversight of credit card use was lacking. Although the credit card policy referred to management reporting, the council had not been producing such reports at the time of the audit. Management reporting was implemented in December 2019 following our discussions. There was a lack of periodic review of the council's credit card use, as it was not included in the council's forward program of internal audits.

The council has adopted a new Management Directive in January 2020, which has clarified the eligibility criteria for credit cards.

Recommendations

Lane Cove Council should immediately:

1. amend its credit card policy to prevent cardholders from sharing their credit card with other staff.

By December 2020, Lane Cove Council should:

2. clarify in the credit card policy and procedures:

  • reconciliation arrangements for the general manager’s credit card
  • fuel card management policy and procedures
  • store card management policy and procedures

3. ensure that credit card management practices include:

  • monitoring credit card limits in line with financial delegations
  • considering the use of credit card blocks
  • providing approvers with targeted guidance
  • keeping the credit card register up-to-date, accurate and complete
  • maintaining complete and accurate records

4. ensure reconciliation involves:

  • scrutinising business-related purposes and incident details of transactions
  • keeping a record of the finance team's review of transactions
  • checking travel pre-approval forms (where applicable)
  • recording vehicle details and mileage when credit cards are used in place of fuel cards

5. develop a plan for periodic reviews (e.g. internal audit) of credit card use and management.

 

Nambucca Valley Council had gaps in its credit card policy and procedures. The council's reconciliation of credit card transactions needs to be enhanced to ensure it can review compliance with policy and detect potential misuse or fraud.

Nambucca Valley Council had 37 credit cards at the time of the audit. During our interviews, cardholders described instances of credit card sharing within the council. Credit card sharing is a violation of the council's agreement with its credit card issuer, and it also increases the risk of misuse and fraud.

The council's credit card policy lacked clarity in several areas. While the general manager had delegation to authorise the issue of credit cards, the policy did not specify any eligibility criteria. The policy and procedures lacked guidance on the management of fuel cards, store cards and Cabcharge. The policy also lacked coverage of the reconciliation arrangements for the general manager's credit card as the general manager did not hold a credit card. While the policy did not preclude the mayor and the general manager from holding a credit card, both opted not to do so.

The audit identified gaps in the council's credit card management practices. There was no evidence that credit card limits were monitored in line with financial delegations. The credit card register contained inaccurate information, and there was insufficient control in handling staff departures, as the audit identified one incident where a credit card was returned after the staff member's last day.

The council's credit card reconciliation process needs to be enhanced to enable detection of potential misuse or fraud. The process also did not include adequate compliance checks or reviewing the business-related purpose of transactions. Purchases of restricted items such as fuel and the use of third-party travel websites were not accompanied by adequate justification. Travel expenses were not checked against travel pre-approval forms. The audit also identified instances of split transactions.

Senior management oversight of credit card use was insufficient, as the council had been producing reports for only one manager for his department at the time of the audit. Management reporting for the Chief Finance Officer was implemented following our discussions. There was a lack of periodic review of the council's credit card use, as it was not included in the council's forward program of internal audits.

The audit acknowledges that the council had revised its credit card procedures following our discussions to address our preliminary findings. The council has also set additional credit card blocks in response to this audit. The recommendations below contain only the outstanding items.

Recommendations

Nambucca Valley Council should immediately:

1. ensure cardholders stop sharing their credit card with other staff.

By December 2020, Nambucca Valley Council should:

2. clarify in the credit card policy and procedures:

  • reconciliation arrangements for the general manager’s credit card (should the policy continue to allow the general manager to have one)
  • fuel card management policy and procedures

3. ensure that credit card management practices include:

  • monitoring credit card limits in line with financial delegations
  • keeping the credit card register up-to-date, accurate and complete

4. ensure reconciliation involves:

  • scrutinising business-related purposes and incident details of transactions
  • checking travel pre-approval forms (where applicable)
  • recording vehicle details and mileage when credit cards are used in place of fuel cards
  • checking that there are no split transactions

5. develop a plan for periodic reviews (e.g. internal audit) of credit card use and management.

 

Penrith City Council had gaps in its credit card policy and procedures. The council's reconciliation of credit card transactions needs to be enhanced to ensure it can review compliance with policy and detect potential misuse or fraud.

Penrith City Council had 167 credit cards at the time of the audit. During our interviews, cardholders described instances of credit card sharing within the council. Credit card sharing is a violation of the council's agreement with its credit card issuer, and it also increases the risk of misuse and fraud.

The audit identified gaps in the council's credit card policy and procedures. There was no documented arrangement for the reconciliation of the general manager's credit card. There was also no guidance on the management of Cabcharge. The credit card register contained inaccurate information, and the council was also unable to provide records of certain transactions requested for review by the audit.

The council's credit card reconciliation process needs to be enhanced to enable detection of potential misuse or fraud. The process did not include adequate compliance checks or reviewing the business-related purpose of transactions. The council's policy required prior approval for conferences, accommodation or meal expenses. However, there was no evidence that such approvals were checked during credit card reconciliation. The audit also identified instances of split transactions.

The council implemented monthly reporting for managers in July 2019.

There was a lack of periodic review of the council's credit card use, as it was not included in the council's forward program of internal audits.

Recommendations

Penrith City Council should immediately:

1. ensure cardholders stop sharing their credit card with other staff.

By December 2020, Penrith City Council should:

2. clarify in the credit card policy and procedures

  • reconciliation arrangements for the general manager’s credit card
  • Cabcharge management policy and procedures

3. ensure that credit card management practices include:

  • considering the use of credit card blocks
  • keeping the credit card register up-to-date, accurate and complete
  • maintaining complete and accurate records

4. ensure reconciliation involves:

  • scrutinising business-related purposes and incident details of transactions
  • keeping a record of the finance team's review of transactions
  • checking travel pre-approval forms (where applicable)
  • recording vehicle details and mileage when credit cards are used in place of fuel cards
  • checking that there are no split transactions

5. develop a plan for periodic reviews (e.g. internal audit) of credit card use and management.

 

Shellharbour City Council had gaps in its credit card policy and procedures. The council's reconciliation of credit card transactions needs to be enhanced to ensure it can review compliance with policy and detect potential misuse or fraud.

Shellharbour City Council had 65 credit cards at the time of the audit. During our interviews, cardholders described instances of credit card sharing within the council. Credit card sharing is a violation of the council's agreement with its credit card issuer, and it also increases the risk of misuse and fraud.

The council's credit card policy lacked clarity in several areas. While the general manager had delegation to authorise the issue of credit cards, the policy did not specify any eligibility criteria. The council did not align credit card limits with financial delegations, and while blocking codes were used, there was no explanation in the policy or procedures. Although the mayor and general manager's credit card transactions were reviewed during the council's monthly Executive Leadership Team meetings, the policy and procedures lacked guidance on the reconciliation of their credit cards. The council also did not have sufficiently detailed documentation for the management of fuel cards.

The audit identified gaps in the council's credit card management practices:

  • The council's training material had not been updated following the review of its credit card policy and procedures.
  • The credit card register contained inaccurate information.
  • The council was unable to provide records of certain transactions requested for review by the audit.
  • The council did not review its credit card policy according to schedule.

The council's credit card reconciliation process needs to be enhanced to enable detection of potential misuse or fraud. The process did not include compliance checks or reviewing the business-related purpose of transactions. Purchases of restricted items, such as fuel and fine payments, were not accompanied by adequate justification. The audit identified instances of split transactions, and travel or conference approval forms were also not checked during reconciliation. There was a lack of targeted guidance for approvers in reconciliation, and the council also provided no evidence of the finance team's involvement in the reconciliation of credit card transactions.

The council's Executive Leadership Team was involved in the monthly review of credit card transactions, hence there was management oversight of credit card use. However, there was a lack of periodic review of the council's credit card use, as it was not included in the council's forward program of internal audits.

Recommendations

Shellharbour City Council should immediately:

1. ensure cardholders stop sharing their credit card with other staff.

By December 2020, Shellharbour City Council should:

2. clarify in the credit card policy and procedures:

  • eligibility criteria for a credit card
  • the use of blocking codes
  • reconciliation arrangements for the general manager’s credit card
  • fuel card management policy and procedures (with more details)

3. ensure that credit card management practices include:

  • monitoring credit card limits in line with financial delegations
  • providing approvers with targeted guidance
  • keeping the credit card register up-to-date, accurate and complete
  • maintaining complete and accurate records
  • updating the training material to reflect the latest policy and procedures

4. ensure reconciliation involves:

  • scrutinising business-related purposes and incident details of transactions
  • keeping a record of the finance team's review of transactions
  • checking travel pre-approval forms (where applicable)
  • recording vehicle details and mileage when credit cards are used in place of fuel cards
  • ensuring no split transactions

5. develop a plan for periodic reviews (e.g. internal audit) of credit card use and management

6. ensure its credit card policy and procedures are reviewed according to schedule.

Appendix one – Responses from councils and the Department of Planning, Industry and Environment

Appendix two – About the audit

Appendix three – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #340 - released 3 September 2020

Published

Actions for Governance and internal controls over local infrastructure contributions

Governance and internal controls over local infrastructure contributions

Local Government
Planning
Environment
Compliance
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Service delivery

The Auditor-General for New South Wales, Margaret Crawford, released a report today on how well four councils managed their local infrastructure contributions during the 2017-18 and 2018-19 financial years. 

Local infrastructure contributions, also known as developer contributions, are collected from developers to pay for local infrastructure such as drainage, local roads, open space and community facilities. Controls over local infrastructure contributions help to ensure that all contributions owed are collected, funds are spent as intended, and any contributions paid in the form of works-in-kind or dedicated land are correctly valued.

The audit found that Blacktown City Council and City of Sydney Council provided effective governance over their local infrastructure contributions whereas Central Coast and Liverpool City Councils’ governance arrangements require improvement.

The audit found that three councils had spent local infrastructure contributions in accordance with approved contributions plans. Central Coast Council and the former Gosford City Council had spent $13.2 million on administration costs in breach of the Environmental Planning and Assessment Act 1979. These funds were repaid into the council’s local infrastructure fund during the course of the audit.

The Auditor-General made a number of recommendations for each council relating to improving controls over contributions and increasing transparency. 

Read full report (PDF)
 

This audit examined the effectiveness of governance and internal controls over local infrastructure contributions, also known as developer contributions, held by four councils during the 2017–18 and 2018–19 financial years.

This performance audit was conducted with reference to the legislative and regulatory planning framework that was in place during that period.

Our work for this performance audit was completed at the end of March 2020 when we issued the final report to the four audited councils and the Department of Planning, Industry and Environment. We received their respective formal responses to the report’s recommendations during April and May 2020.

Concurrently to this audit, we sought Crown Solicitor’s advice (the ‘Advice’) regarding the use of local infrastructure contributions collected by local councils under the Environmental Planning and Assessment Act 1979 (‘the EPA Act’) for our financial audit work. The Advice clarified the applicable legislative requirements with reference to the application, investment and pooling of local infrastructure contributions. The Advice is included in Appendix 2 of this report. The Advice has not impacted on the findings and recommendations of this report.

Councils collect Local Infrastructure Contributions (LICs) from developers under the Environmental Planning and Assessment Act (1979), the Local Government Act (1993) and the City of Sydney Act (2000) (EP&A Act, LG Act and City of Sydney Act) to fund infrastructure required to service and support new development. At 30 June 2018, councils across NSW collectively held more than $3.0 billion in LICs collected from developers. Just over $1.37 billion in total was held by ten councils. Councils collecting LICs must prepare a contributions plan, which outlines how LICs will be calculated and apportioned across different types of infrastructure. Councils that deliver water and sewer services prepare a development servicing plan (DSP) which allows them to collect contributions for water and sewer infrastructure.

Development timeframes are such that there is often several years between when LICs are collected and the infrastructure is required. Good governance and internal controls are needed over these funds to ensure they are available when needed and spent appropriately.

This audit assessed the effectiveness of governance and internal controls over LICs collected by four councils during the 2017–18 and 2018–19 financial years: Blacktown City Council, Central Coast Council, City of Sydney Council and Liverpool City Council. As at June 2018 these councils held the four highest LIC balances, each in excess of $140 million.

Audit Conclusion

Three of the four councils audited were currently compliant with legislation, regulations and Ministerial Directions regarding LICs. All had gaps in governance and controls over LICs which limited effective oversight.

Three of the councils included in the audit complied with legislation, regulations and Ministerial Directions relating to LICs. Central Coast Council breached the EP&A Act between 2001 and 2019 when it used LICs for administration costs. These funds were repaid in late 2019.

While controls over the receipt and expenditure of contributions funds were largely in place at all councils, there were some exceptions relating to valuing work and land delivered in lieu of cash. Three councils do not provide probity guidance in policies relating to LICs delivered through works-in-kind. Three of the councils had contributions plans that were more than five years old.

Staff at all four councils are knowledgeable about LICs but not all councils keep procedures up to date. Three councils' governance frameworks operate effectively with senior officers from across the council involved in decisions about spending LICs, entering into voluntary planning agreements (VPAs) and reviewing contributions plans.

Transparency over key information relating to LICs is important for senior management so they can make informed decisions, and for the community who pay LICs and expect infrastructure to be provided. During the period of the audit, none of the councils included in the audit provided sufficient information to senior management or their councillors about the projected financial status of contributions plans. This information would be valuable when making broader strategic and financial decisions. Information about LIC levies and intended infrastructure is available to the community but not always easy to find.

A strong governance framework is important at each council to ensure that the funds are managed well, available when needed and spent as intended. The audit examined the following features of each council's governance framework as they apply to LICs:

  • decision-making by councillors and council officers relating to LICs
  • monitoring delivery of contributions plans and DSPs including:
    • reviewing assumptions underlying the plans
    • monitoring projected status of plans.

Internal controls over LICs are important to promote accountability, prevent fraud and deliver infrastructure to the required standard at the best possible price. If financial controls are weak or are not implemented well, there is a risk that LICs are misspent or that councils pay too much for infrastructure.

Not all councils' internal controls adequately addressed risks associated with the administration of LICs

The audit examined a number of internal controls that manage risks related to LICs. These included:

  • financial controls over receipt and expenditure of LIC funds
  • management of conflicts-of-interest when dealing with developers
  • independent valuations of works-in-kind and dedicated land
  • ensuring delivery and quality of works-in-kind, and obtaining security from developers in the event of non-delivery or poor quality work
  • management of variations to VPAs and works-in-kind agreements.

We reviewed controls included in policies and procedures and then checked samples of work to ensure that controls were implemented. We found variation in the controls that councils implemented, and some weaknesses in controls. It is a matter for each council to assess their financial risk and develop internal controls that support the collection, management, and expenditure of LICs. However, councils must be able to assure their communities and developers that they are doing everything possible to collect all LICs owing and that work conducted by developers in lieu of cash payments is properly valued and carried out to the required standard.

Further information about audit findings in relation to internal controls for each council are included in chapters five to eight. The exhibit below demonstrates variation in several controls implemented in the audited councils.

In a 2018 report, the Independent Commission Against Corruption noted that 'the appetite for transparency is expanding in both the public and private sectors'.

The Practice Note and S64 Guidance refer to transparency, including the importance of transparency over:

  • calculation and apportionment of LICs
  • funding of infrastructure, including where and when infrastructure is delivered
  • arrangements made with developers through VPAs.

The LIC system is largely transparent for community members who know where to look

Contributions plans and DSPs are public documents, exhibited to the public before being adopted by council. Councils included in the audit publish their contributions plans and DSPs on their websites and meet statutory requirements with regard to reporting and accessibility of information.

However, other public information relating to the LIC system is fragmented across different websites and reports and varies in detail across councils.

Exhibit 10: Published information about LICs at the four audited councils
  Blacktown City Council Central Coast Council City of Sydney Council Liverpool City Council
Financial details about contributions collected and spent Financial statements Financial statements Financial statements Financial statements
Implementation plans for spending LICs Contribution plans S64 implementation plans in DSPs. S7.11 & S7.12 implementation plans developed annually within capital works plan Contribution plans Developed annually within capital works plan
Capital works underway or completed, funded by LICs Capital works plan and annual report Not published Not published Capital works plan
Source: Audit Office analysis.

The Practice Note states that councils are accountable for providing the infrastructure for which contributions are collected. Demonstrating that infrastructure has been provided is difficult with fragmented information. As an example of transparent reporting, Blacktown City Council's 2018–19 annual report includes information about infrastructure that has been delivered for every contributions plan, providing transparency over how LICs have been spent.

Use of LICs collected under VPAs is not always transparent

Contributions collected under VPAs are not required to demonstrate the same relationship to a development as LICs collected under section 7.11 of the EP&A Act. VPAs are often negotiated because a developer requests a change to a planning instrument, and it is important that these arrangements, and their outcomes, are transparent to the community.

The EP&A Regulation includes mechanisms to ensure that VPAs are partially transparent. VPAs are exhibited to the public and approved by the elected council. Councils must maintain a VPA Register and make the VPA Deeds of Agreement available on request. However, there is no obligation on council to report on the outcomes or delivery of developers' obligations under VPAs. The four audited councils vary in transparency and accessibility of information available about VPAs.

Exhibit 11: Published information about VPAs at the four audited councils
  Blacktown City Council Central Coast Council City of Sydney Council Liverpool City Council
VPA Register Council website and annual report Annual report Annual report Council website and annual report
VPA Deeds of Agreement Council website Available on request Available on request Council website
Intended use of LICs collected under VPAs In Deeds of Agreement In Deeds of Agreement In VPA Register and most Deeds of Agreement In VPA Register and most Deeds of Agreement
Completion of work funded by cash collected under VPAs Not published Not published Not published Not published
Delivery of works-in-kind or land negotiated under VPAs Not published Not published In VPA Register Not published
Source: Audit Office analysis.

The Practice Note suggests that councils incorporate the intended use of LICs collected under VPAs in the Deed of Agreement, but there is no guidance relating to transparency over where and when funds have actually been spent. There is merit in councils providing greater transparency over public benefits delivered through VPAs to give communities confidence in VPAs as a planning tool.

Credit arrangements with developers are not always well documented or monitored

When levying LICs, section 7.11(6) of the EP&A Act requires councils to take into account land, money, or works-in-kind that the developer has contributed on other development sites over and above their LIC obligations. This section of the EP&A Act allows a developer to offset a LIC owed on one site against land or works contributed on another. This leads to some developers carrying 'credits' for work delivered to councils, to be paid back by reduced LICs on a future development. Blacktown City Council and Central Coast Council allow developers to carry credits. Liverpool City Council and City of Sydney Council do not permit credits and instead pay the developers for any additional work undertaken.

Councils should formally document credit arrangements and have a robust process to validate and keep track of credit balances and report on them. Central Coast Council does not keep good track of credit arrangements and neither Blacktown City Council or Central Coast Council aggregate or report on outstanding credit balances.

Blacktown City Council manages the largest LIC fund in NSW and negotiates more VPAs than any other council. Overall, Blacktown City Council demonstrates effective governance over the LIC funds but there is scope for improved oversight of the projected financial status of contributions plans and credit arrangements with developers. Blacktown City Council also needs to update its operating procedures relating to LICs and improve security over key information.

Blacktown City Council is managing areas with high growth. There is a risk that Blacktown City Council will be unable to collect sufficient LICs to fund the infrastructure required to support that growth. However, Blacktown City Council does not assess and report to senior management or its Audit, Risk and Improvement Committee about the projected financial status of contributions plans.

Blacktown City Council has policies in place to guide the management of LICs although management of credit arrangements with developers requires greater oversight. Policies relating to works-in-kind agreements provide no guidance about probity in negotiations with developers and valuations of works-in-kind are not independent as they are paid for by the developer. Blacktown City Council's S7.11 committee structure could act as a model for other councils. Blacktown City Council is spending LICs according to its contributions plans. Staff managing LICs demonstrate good knowledge of the regulatory environment. However, a number of administrative processes need attention such as outdated procedures, lack of security over key spreadsheets, and inappropriate retention of sensitive personal data.

Recommendations

By December 2020, Blacktown City Council should:

  1. regularly report to senior management on the projected financial status of contributions plans
  2. update council's works-in-kind policy to address probity risks during negotiations with developers
  3. mitigate risks associated with lack of independence in valuations of works-in-kind
  4. improve public reporting about expenditure of cash collected under VPAs
  5. improve management oversight of credit arrangements with developers
  6. update procedures for managing LICs
  7. implement security measures over critical or personal information and spreadsheets. 

Central Coast Council's governance and internal controls over LICs were not fully effective. Between 2001 and 2019, more than $13.0 million in LICs was misspent on administration costs in breach of the EP&A Act. There is scope for improved oversight of the projected financial status of contributions plans and credit arrangements with developers. Policies and procedures from the two former councils are not aligned.

In May 2016, the newly amalgamated Central Coast Council inherited 53 contributions plans from the former Gosford City and Wyong Shire Councils. Managing this number of contributions plans fragments the available funds and increases complexity. Central Coast Council is currently working on consolidating these plans. Between June 2016 and June 2019, its LIC balance doubled from $90.0 million to $196 million. Central Coast Council does not assess and report to senior management or its Audit, Risk and Improvement Committee about the projected financial status of contributions plans. Central Coast Council has a LIC committee but it has no formal charter and senior officers do not regularly attend meetings. This limits the committee's effectiveness as a decision-making body. A draft policy relating to works-in-kind agreements provide no guidance about probity in negotiations with developers. Valuations of works-in-kind and land dedications are not independent as they are paid for by the developer.

Central Coast Council has adjusted its accounts in 2018–19 by $13.2 million to repay the LIC fund for administration expenses that were not provided for in 40 contributions plans.

Recommendations

By June 2020, Central Coast Council should:

1. obtain independent validation of the adjustment made to the restricted asset accounts and general fund to repay LICs spent on administration, and adjustments made to each infrastructure category within the contributions plans

2. publish current contributions plans from the former Gosford City Council on the Central Coast Council website.

By December 2020, Central Coast Council should:

3. regularly report to senior management on the projected financial status of contributions plans

4. increase transparency of information available to the public about LIC works planned and underway, including intended use of contributions collected under VPAs

5. consolidate existing plans, ensuring the new contributions plans includes a regular review cycle

6. develop a formal charter for the developer contributions committee and increase the seniority of membership

7. complete and adopt council's works-in-kind policy currently under development, ensuring it addresses probity risks during negotiations with developers

8. mitigate risks associated with lack of independence in valuations of works-in-kind and dedicated land

9. improve public reporting about expenditure of cash collected under VPAs

10. improve management oversight of credit arrangements with developers

11. implement security measures to ensure the integrity of key spreadsheets used to manage LICs

12. align policies and procedures relating to LICs across the amalgamated council including developing policies and procedures for the management of S64 LICs

13. update council's VPA policy to address increased or indexed bank guarantees to accommodate cost increases.

City of Sydney Council manages a complex development environment across the Sydney CBD and inner suburbs. Overall, governance and internal controls over LICs are effective although there is scope for improved oversight of the projected financial status of contributions plans.

City of Sydney Council maintains a large balance of LICs, although not excessive relative to the annual level of LIC expenditure. Unspent contributions are largely associated with open space infrastructure that cannot be delivered until suitable land is available. Thirty per cent of cash contributions are collected under VPAs and there is limited transparency over how these funds are spent. City of Sydney Council does not assess and report to management or its Audit, Risk and Compliance Committee about the projected financial status of contributions plans.

In 2017–18 and 2018–19, LICs were spent in accordance with the corresponding contributions plans. City of Sydney Council staff are knowledgeable about the regulatory environment and are supported by up-to-date policies and procedures.

Recommendations

By December 2020, City of Sydney Council should:

  1. regularly report to senior management on the projected financial status of contributions plans
  2. improve public reporting about expenditure of cash collected under VPAs
  3. periodically review the risk of unpaid LICs associated with complying development certificates and assess whether additional controls are required
  4. implement security measures to ensure the integrity of key spreadsheets used to manage LICs. 

During the audit period 2017–18 and 2018–19, Liverpool City Council did not have effective governance and internal controls over LICs. Liverpool City Council is addressing deficiencies and risks identified through an internal audit published in December 2018 although further work is required. There is scope for improved oversight of the projected financial status of contributions plans.

In the two years to 30 June 2019, the balance of unspent LICs increased by more than 60 per cent against a relatively low pattern of expenditure. Prior to an internal audit completed in late 2018, there was no regular reporting on the status of LICs and a lack of transparency when prioritising the expenditure of LIC funds. During 2019, and following the internal audit, Liverpool City Council engaged additional skilled resources to improve focus and accountability for LICs. A LIC committee has been established to manage contributions plans and support business units to initiate relevant infrastructure projects, although it is too early to assess whether this committee is operating effectively. From February 2019, Liverpool City Council commenced monthly reporting to its Chief Executive Officer (CEO) about the point-in-time status of LIC funds, and to its Audit, Risk and Improvement Committee about risks associated with LICs and the implementation of internal audit recommendations. There is limited reporting to senior management about the projected financial status of some contributions plans. Our audit found no evidence of misuse of funds during the audited period. Methods for valuing work and land are not aligned with policies and procedures and are implemented inconsistently. In addition, valuations of works-in-kind and land dedications are not independent as they are paid for by the developer. The policy relating to works-in-kind provides no guidance about managing probity risks when negotiating with developers.

Recommendations

By December 2020, Liverpool City Council should:

  1. regularly report to senior management on the projected financial status of contributions plans
  2. update council's policies and procedures to provide consistent guidance about how works and land offered by developers should be valued
  3. update council's Works-in-Kind and Land Acquisition Policy to address probity risks during negotiations with developers
  4. improve public reporting about expenditure of cash collected under VPAs
  5. mitigate risks associated with lack of independence in valuations of works-in-kind and dedicated land
  6. implement security measures over critical or private information. 

Appendix one – Responses from councils and the Department of Planning, Industry and Environment

Appendix two – Advice from the Crown Solicitor

Appendix three – About the audit

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #339 - released 17 August 2020

Published

Actions for Health capital works

Health capital works

Health
Compliance
Infrastructure
Procurement
Project management

This report examines whether NSW Health effectively planned and delivered major capital works to meet the demand for health services in New South Wales.

The report found that NSW Health has substantially expanded health infrastructure across New South Wales since 2015. However, the program was driven by Local Health District priorities without assessment of the State’s broader and future‑focussed health requirements.

The report found that unclear decision making roles and responsibilities between Health Infrastructure and the Ministry of Health limited the ability of NSW Health to effectively test and analyse investment options.

Project delays and budget overruns on some major projects indicate that Health Infrastructure's project governance, risk assessment and management systems could be improved.

The Auditor‑General recommends that NSW Health ensure its capital projects offer the greatest value to New South Wales by establishing effective policy guidance and enhancing project governance and management systems.

Read full report (PDF)

Since 2011–12, NSW Health has aimed to improve its facilities and build 'future focused' infrastructure. The NSW Government’s 2015–16 election commitments established a four-year $5.0 billion capital program for NSW Health to build and upgrade more than 60 hospitals and health services. The 2019–20 State Budget committed a further $10.1 billion over four years for another 29 projects. This is the largest investment to date on health capital works in New South Wales.

Recent reviews of infrastructure have recognised that population and demographic growth will require a change in the delivery and composition of health infrastructure, including considering greater use of non-traditional, non-capital health service options and assets.

To ensure that expenditure on capital works represents the best value for money, NSW Health's business cases need to be robust and supported by evidence that demonstrates they are worthy investments. The NSW Process of Facility Planning has been the main framework guiding the detailed planning and development of NSW Health's capital works proposals. This framework was developed by the then NSW Department of Health in 2010. Its aim is to ensure investment proposals are supported by rigorous planning processes that address health service needs and provide value for money.

Infrastructure projects of the complexity and scale being delivered by NSW Health carry inherent risks. For example, unplanned cost escalations can potentially impact on the State’s finances. Unforeseen delays can also reduce the intended benefits. The growth in the State’s health capital spend and project profile, means its exposure to such risks has increased over time.

The objective of this audit was to assess the effectiveness of planning and delivery of major capital works to meet demand for health services in New South Wales. To address this objective, the audit examined whether:

  • the Ministry of Health has effective procedures for planning and prioritising investments in major health capital works
  • Health Infrastructure develops robust business cases for initiated major capital works that reliably inform government decision making
  • Health Infrastructure has effective project governance and management systems that support delivering projects on-time, within budget and achievement of intended benefits.

The audit focused on the Ministry of Health and Health Infrastructure – being the lead agencies within NSW Health responsible for prioritising, planning and delivering major health capital works across the State. The audit examined 13 business cases for eight discrete projects over a ten-year period.

Conclusion

NSW Health has substantially expanded health infrastructure across New South Wales since 2015. However, its planning and prioritisation processes were not assessed against a long-term statewide health infrastructure plan and lacked rigorous assessment against non-capital options creating a risk that they do not maximise value for New South Wales.

The scale of NSW Health's capital investment is significant and has grown substantially in recent years. The NSW Government’s election commitments in 2015–16 and 2019–20 collectively set out a $15.0 billion capital program to build and upgrade 89 hospitals and health services. NSW Health developed this infrastructure program in the absence of a statewide health infrastructure strategy and investment framework to focus its planning and decisions on the types of capital investments required to meet the long-term needs of the NSW health system.

Consequently, locally focused priorities of the State’s 17 Local Health Districts have been the primary drivers of NSW Health’s capital investments since 2015–16. Local Health District investment proposals for hospitals were developed without consideration of alternative health options such as community health service models, technology-driven eHealth care, or private sector options. Without rigorous assessment against a range of potential health service options, there is a risk that selected projects do not maximise value for New South Wales.

In recognition of the need for a statewide approach to infrastructure planning, the Ministry of Health recently developed a 20-year Health Infrastructure Strategy and prioritisation framework in 2019. The strategy was approved by the NSW Government in April 2020.

NSW Health's ability to effectively test and analyse its capital investment options has been compromised by unclear decision-making roles and responsibilities between its Health Infrastructure and the Ministry of Health agencies.

While both Health Infrastructure and the Ministry of Health have responsibilities for the assessment of business cases for proposed infrastructure projects, confusion about the roles of each agency at key steps compromised the efficacy of the process. Health Infrastructure and the Ministry of Health have differing views about which agency is responsible for testing business case inputs and conducting comprehensive options appraisals.

As a result of this confusion, Health Infrastructure and the Ministry of Health did not rigorously test Local Health District capital investment proposals against defined statewide health infrastructure investment priorities. The NSW Process of Facility Planning does not clarify the responsibilities of all parties in validating and prioritising Local Health District's Clinical Service Plans and progressing them to business cases.

NSW Health's infrastructure priorities are not sufficiently supported by transparent documentation of selection methodology and the rationale for decisions. Consequently, there is a risk that recommended options, whilst having some economic and health service merit, do not represent the greatest value.

Substantial delays and budget overruns on some major projects indicate that Health Infrastructure's project governance, risk assessment and management systems could be improved.

Health Infrastructure did not fully comply with NSW Government guidelines for developing business cases and making economic appraisals for proposed capital investments. These weaknesses, along with delays and budget overruns on some projects, demonstrate a need for Health Infrastructure to strengthen its project governance, management and quality control systems.

 

Over the period of review, NSW Government policies for business case development and submission have emphasised that effective governance arrangements are critical to a proposal's successful implementation.

NSW Health's Process of Facility Planning similarly highlights the importance of effective governance and project management for achieving good outcomes. It prescribes a general governance structure managed by Health Infrastructure that can be tailored to the planning and delivery of health infrastructure projects greater than $10.0 million.

Project challenges indicate opportunities for strengthening governance and project management

The three major hospital redevelopments examined in metropolitan, regional and rural areas had a combined Estimated Total Cost of more than $1.2 billion and comprised eight discrete projects and 13 separate business cases.

Almost all these projects experienced delivery challenges which impacted achievement of their original objectives and intended benefits. This is expected in complex and large-scale health infrastructure programs. However, in some projects the impacts were significant and resulted in substantial delays, unforeseen costs, and diversion of resources from other priority areas.

Our review of the selected case studies highlighted opportunities for enhancing governance and project management. Specifically, it indicates a need for improving transparency in the management of contingencies, risk management and assessments particularly relating to adverse site conditions and the selection of contractors. There is also a need to strengthen forward planning for options to address unfunded priorities within business cases that risk complicating the delivery of future project stages resulting in unforeseen costs and potentially avoidable budget overruns.

Need for increased transparency and accountability in the management of contingency funds

In February 2017, the Ministry's Capital Strategy Group approved the use of surplus funds of $13.76 million from Stage 1 of the Hornsby Ku-ring-gai Hospital Redevelopment for new works deemed needed to support Stage 2. Following this decision, Health Infrastructure finalised and submitted a business case addendum for Stage 1 to the Ministry in March 2017, addressing the new works comprising a two-storey building for medical imaging and paediatric floors. The business case addendum also addressed options to fit out and procure major medical imaging equipment. The Ministry approved the Stage 1 business case in July 2017, noting the Ministry's Capital Strategy Group had already approved the use of remaining Stage 1 funds to deliver the new works.

Stage 1 was completed in 2015, almost two years before the Stage 1 business case addendum was prepared in February 2017.

The Ministry's decision to approve the new works using $13.76 million of surplus Stage 1 funds did not comply with the NSW Treasury Circular TC 12/20. This policy establishes the Treasurer's approval must be sought and received before a new capital project with an Estimated Total Cost of $5.0 million or more can be approved by NSW Health. The Ministry therefore exceeded its delegated authority in making this decision, as it was not evident it had sought and received the Treasurer's approval prior to doing so.

Consequently, the surplus Stage 1 funds should not have been used by the Ministry to deliver new works in the circumstances. Instead, they should have been released from the Stage 1 project in accordance with established NSW Health procedures, and the Stage 1 Estimated Total Cost revised down accordingly. This did not occur, and NSW Health ultimately directed $11.0 million in surplus Stage 1 funds to the new works.

These circumstances indicate a need to strengthen transparency and accountability within NSW Health for the approval of new projects, and how contingency funds are used in the management of major health capital works. They also demonstrate the impact of weaknesses with options appraisal as the initial Stage 1 business case did not consider alternative options for addressing the initially unfunded works later covered by the Stage 1 business case addendum and ultimately funded from the Stage 1 contingency provision.

Weaknesses in service delivery planning resulted in unaccounted-for costs

In addition to proposing the above-noted new works, the 2017 Stage 1 Business Case Addendum for the Hornsby-Ku-ring-gai development sought to retrospectively address the estimated funding gap of around $14.0 million for the internal fit out, supply of major medical imaging equipment, and cost to operate the medical imaging service at Hornsby Ku-ring-gai Hospital also not addressed in the originally Stage 1 business case.

The Stage 1 business case addendum considered various procurement options to purchase and run the medical imaging services ranging from State operation purchase options to private operation purchase options.

It recommended outsourcing the operation and provision of equipment to the private sector based on estimated savings to the public sector initially of around $650,000 per annum reducing over time to $270,000. The Ministry endorsed this option in June 2017, but it did not ultimately proceed.

A July 2018 report to the Executive Steering Committee on the project shows NSW Health later decided to deliver operation of the medical imaging unit 'traditionally' with an updated estimate of the cost at approximately $16.4 million. The report also shows the Ministry supported the costs now being met by the Northern Sydney Local Health District.

This means the funding gap previously identified in the Stage 1 business case addendum for fitting out the medical imaging building and supply of major medical equipment would need to be met fully by the State, representing a $16.4 million cost overrun for the project.

Examined reports to the Executive Steering Committee show this was largely funded by the Northern Sydney Local Health District via the disposal of land realising approximately $15.0 million in proceeds.

This initially unforeseen cost, along with the additional $11.0 million for the new works approved under the Stage 1 business case addendum, were ultimately merged with the Stage 2 project initially approved in 2017–18 with an Estimated Total Cost of $200 million.

The extent of budget variation on the Hornsby Kur-ring-gai development has not been transparent

The 2019–20 State Budget provided an additional $65.0 million for a further Stage 2A to deliver additional built capacity to support outpatient services, enhanced allied health services, re-housed community health services and the delivery of prioritised clinical services unfunded as part of Stage 2. The funds were approved based on an Investment Decision Template (IDT) that examined two options in addition to the base case representing scoping alternatives to the preferred master planned capital solution.

However, we found the IDT showed around 23 per cent of the $65.0 million sought (i.e. $15.0 million) was to be allocated to fund the deficit in Stage 2, which had arisen as a result of project delays due to adverse site conditions. This was not discussed in the IDT.

The February 2020 report to the Executive Steering Committee shows a combined Stage 2 and 2A final forecast cost of $292.6 million against a potential budget of $290.7 million representing an overall deficit for the project of around 0.6 per cent.

However, this favourable final budget position does not transparently show the funding challenges experienced over the project's implementation to-date. The three major budget issues include:

  • inappropriate use of around $11.0 million in Stage 1 contingency for originally unfunded works contrary to Treasury policy
  • the additional $16.4 million cost unforeseen in the Stage 1 business case for delivering medical imaging services mostly funded through the sale of land
  • an additional $15.0 million from Stage 2A to cover the budget overrun in Stage 2 due to adverse site conditions.

The cumulative impact of these events is that Stages 1 and 2 of the Hornsby project cost approximately $42.4 million than it should have in the circumstances around 14 per cent more than what the revised combined Estimated Total Cost for both stages should have been after releasing the $11.0 million in surplus Stage 1 funds, with Stage 2 delayed by around 14 months.

Opportunity for strengthening risk management for adverse site conditions

Major construction projects often experience adverse site conditions which can be difficult to fully detect in advance. However, we found this was a common occurrence in the projects we examined sometimes with significant time and/or budget impacts indicating scope to enhance related risk and cost assessments. Specifically:

  • Hornsby Ku-ring-gai Hospital Redevelopment Stage 2: adverse site conditions during demolition works resulted in an 11-month delay for delivering the medical imaging unit and 14-month delay completing Stage 2 main works including need for additional $15.0 million in funds to cover the resultant budget deficit for the project.
  • Blacktown Mt Druitt Hospital Redevelopment Stage 2: adverse site conditions combined with project complexity delayed completion of the early works by approximately five months. This contributed to the delay in completing the main construction works which occurred around nine months later than planned in the business case.
  • Dubbo Health Service Redevelopment Stages 3 and 4: Health Infrastructure advised adverse site conditions including asbestos containing materials and ground conditions delayed works for the main building with completion forecast for March 2021, around 21 months later than planned in the final business case. This resulted in the need for additional $13.5 million to cover increased construction costs and risks, increasing the Stage 3 and 4 forecast final cost from $150 million to $163.5 million as at February 2020.

These examples indicate a risk the cumulative impact of adverse site conditions may be substantial when measured across both time and Health Infrastructure's full delivery program. They also point to potential for Health Infrastructure to achieve efficiencies and improved outcomes from strengthening its approach to assessing and mitigating the risks from adverse site conditions.

Limited due diligence with prospective contractors risks avoidable delays and costs

Main construction works on Stage 1 of the Dubbo Health Service Redevelopment were completed in October 2015, approximately 13 months later than planned in the final business case. Delays were mainly due to insolvency of the early works contractor resulting in their departure from the project. The ensuing 11-month delay in completing the early works significantly impacted the overall schedule and delivery of main construction works.

The insolvency event was significant as it affected nine separate Health Infrastructure projects – three of which had yet to reach practical completion. It also affected state-funded projects in other sectors. It resulted in the need for additional funding of $11.5 million that was provided in the 2014–15 State Budget increasing the total Stage 1 and 2 budget from $79.8 million to $91.3 million.

Health Infrastructure’s analysis of lessons learned shows it worked actively to mitigate the impacts of the insolvency event across all affected projects. However, it also indicates a risk the lessons were mainly focused on mitigating the impacts after an insolvency event occurred rather than on prevention.

Although Health Infrastructure initially commissioned a financial assessment of the now insolvent early works contractor before engagement, it did not detect any risks of the impending insolvency and instead concluded the contractor was in a strong financial position. However, the contractor became insolvent shortly after commencement approximately seven months later. This indicates a risk of weaknesses in the assessment performed that was not explicitly addressed by the lessons learned.

Delivery of the main construction works were further impacted by disputes with the main works contractor over the scope of works for the renal unit resulting in Health Infrastructure terminating the contract in November 2016 following lengthy negotiations over several months.

The scope of works relating to the renal unit were ultimately transferred to Stages 3 and 4 and were delivered in December 2019, around five years later than originally planned in the business case.

Health Infrastructure advised the delay was ultimately beneficial to the project because the refurbishment works for the renal unit, initially scheduled for Stages 1 and 2, would have been demolished to accommodate the new Western Cancer Centre proposed after Stages 1 and 2 and currently being delivered in parallel with Stages 3 and 4.

Health Infrastructure advised the actual cost of Stages 1 and 2 was $84.7 million against the budget of $91.3 million. The residual $6.6 million relates to the renal works not delivered during Stage 1 and 2 and transferred to Stage 3 and 4.

Health Infrastructure advised the contractual provisions for mitigating insolvency events 'in-flight' are limited highlighting the importance of proactive and effective due diligence prior to engaging contractors for significant construction projects.

Need for a quality framework linked to staff training and capability development

Health Infrastructure's 2017-20 Corporate Plan identifies the development of a quality framework to support delivery of future-focused outcomes as a key organisational priority. Related initiatives within the Corporate Plan describe a framework underpinned by a Quality Committee providing advice on:

  • records management, to meet the requirements of the State Records Act 1998
  • project assurance, to ensure future focused outcomes and enhance Health Infrastructure's Standards, Policies, Procedures and Guidelines, Templates and Design Guidance Notes
  • knowledge management and library services, to promote and leverage from project learnings.

Although Health Infrastructure has some elements of a quality framework it is not yet fully in place. Health Infrastructure advised it had yet to establish the quality framework and related committee described in its Corporate Plan due in part to its focus on responding to the growth of its capital program.

Health Infrastructure's Development and Innovation team has been active in supporting continuous improvement in knowledge and project management including development of business cases. Although useful, these initiatives have relied heavily on leveraging and disseminating insights from Gateway reviews and have not formed part of a systematic quality and continuous improvement framework.

The limited focus on the quality of business cases is reflected in internal performance monitoring and reporting which focuses mainly on tracking the delivery of projects against internal benchmarks, often revised from the baselines in the business case, and expenditure against cashflow targets. There is no evident internal monitoring and/or reporting to the Chief Executive and Board on defined quality metrics linked to business case development and staff capability.

Performance reporting on balanced scorecard metrics has similarly focused mainly on process rather than quality and has been inconsistent in recent years.

Appendix one – Response from agency

Appendix two – About the audit

Appendix three – Performance auditing

Appendix four – Ministry of Health planning tools and guidelines

Appendix five – Streamlined investment decision process for Health Capital Projects

Appendix six – Timeline of business cases and relevant policy guidelines

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #338 - released 12 August 2020

Published

Actions for Their Futures Matter

Their Futures Matter

Justice
Community Services
Education
Health
Whole of Government
Cross-agency collaboration
Internal controls and governance
Management and administration
Project management

The Auditor-General for New South Wales, Margaret Crawford, released a report today examining whether the Department of Communities and Justice had effective governance and partnership arrangements in place to deliver ‘Their Futures Matter’.

Their Futures Matter was intended to place vulnerable children and families at the heart of services, and direct investment to where funding and programs deliver the greatest social and economic benefits. It was a four-year whole-of-government reform in response to the 2015 Tune Review of out-of-home care.

The Auditor-General found that while important foundations were put in place, and new programs trialled, the key objective to establish an evidence-based whole-of-government early intervention approach for vulnerable children and families in NSW was not achieved.

Governance and cross-agency partnership arrangements to deliver Their Futures Matter were found to be ineffective. 'Their Futures Matter lacked mechanisms to secure cross portfolio buy‑in and did not have authority to drive reprioritisation of government investment', the Auditor-General said.

At the reform’s close, the majority of around $380 million in investment funding remains tied to existing agency programs, with limited evidence of their comparative effectiveness or alignment with Their Futures Matter policy objectives. The reform concluded on 30 June 2020 without a strategy or plan in place to achieve its intent.

The Auditor-General made four recommendations to the Department of Communities and Justice, aimed at improving implementation of outstanding objectives, revising governance arrangements, and utilising the new human services data set to address the intent of the reform. However, these recommendations respond only in part to the findings of the audit.

According to the Auditor-General, ‘Cross-portfolio leadership and action is required to ensure a whole-of-government response to delivering the objectives of Their Futures Matter to improve outcomes for vulnerable children, young people and their families in New South Wales.’

Read full report (PDF)

In 2016, the NSW Government launched 'Their Futures Matter' (TFM) - a whole-of-government reform aimed at delivering improved outcomes for vulnerable children, young people and their families. TFM was the government's key response to the 2015 Independent Review of Out of Home Care in New South Wales (known as 'the Tune Review').

The Tune Review found that, despite previous child protection reforms, the out of home care system was ineffective and unsustainable. It highlighted that the system was not client-centred and was failing to improve the long-term outcomes for vulnerable children and families. The review found that the greatest proportion of relevant expenditure was made in out of home care service delivery rather than in evidence-based early intervention strategies to support children and families when vulnerabilities first become evident to government services (such as missed school days or presentations to health services).

The then Department of Family and Community Services (FACS) designed the TFM reform initiatives, in consultation with central and human services agencies. A cross-agency board, senior officers group, and a new unit in the FACS cluster were established to drive the implementation of TFM. In the 2016–17 Budget, the government allocated $190 million over four years (2016–17 to 2019–20) to the reform. This resourced the design and commissioning of evidence-based pilots, data analytics work, staffing for the implementation unit and secretariat support for the board and cross-agency collaboration.

As part of the TFM reform, the Department of Premier and Cabinet, NSW Treasury and partnering agencies (NSW Health, Department of Education and Department of Justice) identified various existing programs that targeted vulnerable children and families (such as the preceding whole-of-government ‘Keep Them Safe’ reform coming to an end in June 2020). Funding for these programs, totalling $381 million in 2019–20, was combined to form a nominal ‘investment pool’. The government intended that the TFM Implementation Board would use this pool to direct and prioritise resource allocation to evidence-based interventions for vulnerable children and families in NSW.

This audit assessed whether TFM had effective governance and partnership arrangements in place to enable an evidence-based early intervention investment approach for vulnerable children and families in NSW. We addressed the audit objective with the following audit questions:

  • Was the TFM reform driven by effective governance arrangements?
  • Was the TFM reform supported by effective cross-agency collaboration?
  • Has the TFM reform generated an evidence base to inform a cross-agency investment approach in the future?

The audit did not seek to assess the outcomes for children, young people and families achieved by TFM programs and projects.

Conclusion

The governance and cross-agency partnership arrangements used to deliver the Their Futures Matter reform were ineffective. Important foundations were put in place, and new programs trialled over the reform's four years. However, an evidence-based whole-of-government early intervention approach for vulnerable children and families in NSW − the key objective of the reform − was not established. The reform concluded in June 2020 without a strategy or plan in place to achieve its intent.

The governance arrangements established for the Their Futures Matter (TFM) reform did not provide sufficient independence, authority and cross-agency clout to deliver on the reform’s intent. This hindered delivery of the reform's key elements, particularly the redirection of funding to evidence-based earlier intervention supports, and limited the impact that TFM could have on driving system change.

TFM increased focus on the contribution that other agencies outside of the former Family and Community Services portfolio could make in responding to the needs of vulnerable children and families, and in reducing the demand costs of related government service delivery. Despite being a whole-of-government reform, TFM lacked mechanisms to secure cross-portfolio buy-in and lacked the powers to drive reprioritisation of government investment in evidence-based and earlier intervention supports across agencies. At the reform’s close, the majority of the reform's investment pool funding remained tied to existing agency programs, with limited evidence of their comparative effectiveness or alignment with Their Futures Matter policy objectives.

TFM began building an evidence base about ‘what works’, including piloting programs and creating a new dataset to identify risk factors for vulnerability and future costs to government. However, this evidence base does not yet comprehensively map how existing services meet needs, identify system duplications or gaps, nor demonstrate which government funded supports and interventions are most effective to make a difference to life outcomes for vulnerable children and families in NSW.
Despite these issues, the need, intent and vision for Their Futures Matter remains relevant and urgent, as issues identified in the Tune Review remain pertinent.

Their Futures Matter (TFM) is a whole-of-government reform to deliver improved outcomes for vulnerable children, young people and their families.

Supported by a cross-agency TFM Board, and the TFM Unit in the then Department of Family and Community Services (FACS), the reform aimed to develop whole-of-government evidence-based early intervention investment approaches for vulnerable children and families in NSW.

Governance refers to the structures, systems and practices that an organisation has in place to:

  • assign decision-making authorities and establish the organisation's strategic direction
  • oversee the delivery of its services, the implementation of its policies, and the monitoring and mitigation of its key risks
  • report on its performance in achieving intended results, and drive ongoing improvements.

We examined whether the TFM reform was driven by effective governance arrangements and cross-agency collaboration.

The reform agenda and timeframe set down for Their Futures Matter (TFM) were ambitious. This chapter assesses whether the TFM Board and TFM Unit had the capability, capacity and clout within government to deliver the reform agenda.

Creating a robust evidence base was important for Their Futures Matter, in order to:

  • identify effective intervention strategies to improve supports and outcomes for vulnerable children and families
  • make efficient use of taxpayer money to assist the maximum number of vulnerable children and families
  • inform the investment-based approach for future funding allocation.

This chapter assesses whether the TFM reform has developed an evidence base to inform cross-agency investment decisions.

Appendix one – Response from agency

Appendix two – TFM governance entities

Appendix three – TFM Human Services Data Set

Appendix four – TFM pilot programs

Appendix five – About the audit

Appendix six – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #337 - released 24 July 2020

Published

Actions for CBD South East Sydney Light Rail: follow-up performance audit

CBD South East Sydney Light Rail: follow-up performance audit

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk
Service delivery

This is a follow-up to the Auditor-General's November 2016 report on the CBD South East Sydney Light Rail project. This follow-up report assessed whether Transport for NSW has updated and consolidated information about project costs and benefits.

The audit found that Transport for NSW has not consistently and accurately updated project costs, limiting the transparency of reporting to the public.

The Auditor-General reports that the total cost of the project will exceed $3.1 billion, which is above the revised cost of $2.9 billion published in November 2019. $153.84 million of additional costs are due to omitted costs for early enabling works, the small business assistance package and financing costs attributable to project delays.

The report makes four recommendations to Transport for NSW to publicly report on the final project cost, the updated expected project benefits, the benefits achieved in the first year of operations and the average weekly journey times.

Read full report (PDF)

The CBD and South East Light Rail is a 12 km light rail network for Sydney. It extends from Circular Quay along George Street to Central Station, through Surry Hills to Moore Park, then to Kensington and Kingsford via Anzac Parade and Randwick via Alison Road and High Street.

Transport for NSW (TfNSW) is responsible for planning, procuring and delivering the Central Business District and South East Light Rail (CSELR) project. In December 2014, TfNSW entered into a public private partnership with ALTRAC Light Rail as the operating company (OpCo) responsible for delivering, operating and maintaining the CSELR. OpCo engaged Alstom and Acciona, who together form its Design and Construct Contractor (D&C).

On 14 December 2019, passenger services started on the line between Circular Quay and Randwick. Passenger services on the line between Circular Quay and Kingsford commenced on 3 April 2020.

In November 2016, the Auditor-General published a performance audit report on the CSELR project. The audit found that TfNSW would deliver the CSELR at a higher cost with lower benefits than in the approved business case, and recommended that TfNSW update and consolidate information about project costs and benefits and ensure the information is readily accessible to the public.

In November 2018, the Public Accounts Committee (PAC) examined TfNSW's actions taken in response to our 2016 performance audit report on the CSELR project. The PAC recommended that the Auditor-General consider undertaking a follow-up audit on the CSELR project. The purpose of this follow-up performance audit is to assess whether TfNSW has effectively updated and consolidated information about project costs and benefits for the CSELR project.

Conclusion

Transport for NSW has not consistently and accurately updated CSLER project costs, limiting the transparency of reporting to the public. In line with the NSW Government Benefits Realisation Management Framework, TfNSW intends to measure benefits after the project is completed and has not updated the expected project benefits since April 2015.

Between February 2015 and December 2019, Transport for NSW (TfNSW) regularly updated capital expenditure costs for the CSELR in internal monthly financial performance and risk reports. These reports did not include all the costs incurred by TfNSW to manage and commission the CSELR project.

Omitted costs of $153.84 million for early enabling works, the small business assistance package and financing costs attributable to project delays will bring the current estimated total cost of the CSELR project to $3.147 billion.

From February 2015, TfNSW did not regularly provide the financial performance and risk reports to key CSELR project governance bodies. TfNSW publishes information on project costs and benefits on the Sydney Light Rail website. However, the information on project costs has not always been accurate or current.

TfNSW is working with OpCo partners to deliver the expected journey time benefits. A key benefit defined in the business plan was that bus services would be reduced owing to transfer of demand to the light rail - entailing a saving. However, TfNSW reports that the full expected benefit of changes to bus services will not be realised due to bus patronage increasing above forecasted levels.

Appendix one – Response from agency

Appendix two – Governance and reporting arrangements for the CSELR

Appendix three – 2018 CSELR governance changes

Appendix four – About the audit

Appendix five – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #335 - released 11 June 2020

Published

Actions for Train station crowding

Train station crowding

Transport
Management and administration
Risk
Service delivery
Workforce and capability

This report focuses on how Transport for NSW and Sydney Trains manage crowding at selected metropolitan train stations.

The audit found that while Sydney Trains has identified platform crowding as a key strategic risk, it does not have an overarching strategy to manage crowding in the short to medium term. Sydney Trains 'do not have sufficient oversight to know if crowding is being effectively managed’, the Auditor-General said.

Sydney Trains' operational response to crowding involves restricting customer access to platforms or station entries before crowding reaches unsafe levels or when it impacts on-time running. Assuming rail patronage increases, it is likely that Sydney Trains will restrict more customers from accessing platforms or station entries, causing customer delay. ‘Restricting customer access to platforms or station entries is not a sustainable approach to manage station crowding’, said the Auditor-General.

The Auditor-General made seven recommendations to improve Transport for NSW and Sydney Trains' management of station crowding. Transport for NSW have accepted these recommendations on behalf of the Transport cluster.

Public transport patronage has been impacted by COVID-19. This audit was conducted before these impacts occurred.

Read full report (PDF)

Sydney Trains patronage has increased by close to 34 per cent over the last five years, and Transport for NSW (TfNSW) expects the growth in patronage to continue over the next 30 years. As patronage increases there are more passengers entering and exiting stations, moving within stations to change services, and waiting on platforms. As a result, some Sydney metropolitan train stations are becoming increasingly crowded.

There are three main causes of station crowding:

  • patronage growth exceeding the current capacity limits of the rail network
  • service disruptions
  • special events.

Crowds can inhibit movement, cause discomfort and can lead to increased health and safety risks to customers. In the context of a train service, unmanaged crowds can affect service operation as trains spend longer at platforms waiting for customers to alight and board services which can cause service delays. Crowding can also prevent customers from accessing services.

Our 2017 performance audit, ‘Passenger Rail Punctuality’, found that rail agencies would find it hard to maintain train punctuality after 2019 unless they significantly increased the capacity of the network to carry trains and people. TfNSW and Sydney Trains have plans to improve the network to move more passengers. These plans are set out in strategies such as More Trains, More Services and in the continued implementation of new infrastructure such as the Sydney Metro. Since 2017, TfNSW and Sydney Trains have introduced 1,500 more weekly services to increase capacity. Additional network capacity improvements are in progress for delivery from 2022 onwards.

In the meantime, TfNSW and Sydney Trains need to use other ways of managing crowding at train stations until increased capacity comes on line.

This audit examined how effectively TfNSW and Sydney Trains are managing crowding at selected metropolitan train stations in the short and medium term. In doing so, the audit examined how TfNSW and Sydney Trains know whether there is a crowding problem at stations and how they manage that crowding.

TfNSW is the lead agency for transport in NSW. TfNSW is responsible for setting the standard working timetable that Sydney Trains must implement. Sydney Trains is responsible for operating and maintaining the Sydney metropolitan heavy rail passenger service. This includes operating, staffing and maintaining most metropolitan stations. Sydney Trains’ overall responsibility is to run a safe rail network to timetable.

Conclusion

Sydney Trains has identified platform crowding as a key strategic risk, but does not have an overarching strategy to manage crowding in the short to medium term. TfNSW and Sydney Trains devolve responsibility for managing crowding at stations to Customer Area Managers, but do not have sufficient oversight to know if crowding is being effectively managed. TfNSW is delivering a program to influence demand for transport in key precincts but the effectiveness of this program and its impact on station crowding is unclear as Transport for NSW has not evaluated the outcomes of the program.

TfNSW and Sydney Trains do not directly measure or collect data on station crowding. Data and observation on dwell time, which is the time a train waits at a platform for customers to get on and off trains, inform the development of operational approaches to manage crowding at stations. Sydney Trains has KPIs on reliability, punctuality and customer experience and use these to indirectly assess the impact of station crowding. TfNSW and Sydney Trains only formally assess station crowding as part of planning for major projects, developments or events.

Sydney Trains devolve responsibility for crowd management to Customer Area Managers, who rely on frontline Sydney Trains staff to understand how crowding affects individual stations. Station staff at identified key metropolitan train stations have developed customer management plans (also known as crowd management plans). However, Sydney Trains does not have policies to support the creation, monitoring and evaluation of these plans and does not systematically collect data on when station staff activate crowding interventions under these plans.

Sydney Trains stated focus is on providing a safe and reliable rail service. As such, management of station crowding is a by-product of its strategies to manage customer safety and ensure on-time running of services. Sydney Trains' operational response to crowding involves restricting customer access to platforms or stations before crowding reaches unsafe levels, or when it impacts on-time running. As rail patronage increases, it is likely that Sydney Trains will need to increase its use of interventions to manage crowding. As Sydney Trains restrict more customers from accessing platforms or station entries, it is likely these customers will experience delays caused by these interventions.

Since 2015, TfNSW has been delivering the 'Travel Choices' program which aims to influence customer behaviour and to manage the demand for public transport services in key precincts. TfNSW is unable to provide data demonstrating the overall effectiveness of this program and the impact the program has on distributing public transport usage out of peak AM and PM times. TfNSW and Sydney Trains continue to explore initiatives to specifically address crowd management.

Conclusion

TfNSW and Sydney Trains do not directly measure or collect data on station crowding. There are no key performance indicators directly related to station crowding. Sydney Trains uses performance indicators on reliability, punctuality and customer experience to indirectly assess the impact of station crowding. Sydney Trains does not have a routine process for identifying whether crowding contributed to minor safety incidents. TfNSW and Sydney Trains formally assess station crowding as part of planning for major projects, developments or events.

 

Conclusion

Sydney Trains has identified platform crowding as a strategic risk but does not have an overarching strategy to manage station crowding. Sydney Trains' stated focus is on providing a safe and reliable rail service. As such, management of station crowding is a by-product of its strategies to manage customer safety and ensure on-time running of services.

Sydney Trains devolve responsibility for managing crowding at stations to Customer Area Managers but does not have sufficient oversight to know that station crowding is effectively managed. Sydney Trains does not have policies to support the creation, monitoring or evaluation of crowd management plans at key metropolitan train stations. The use of crowding interventions is likely to increase due to increasing patronage, causing more customers to experience delays directly caused by these activities.

TfNSW and Sydney Trains have developed interventions to influence customer behaviour and to manage the demand for public transport services but are yet to evaluate these interventions. As such, their impact on managing station crowding is unclear.

Appendix one – Response from agency

Appendix two – Sydney rail network

Appendix three – Rail services contract

Appendix four – Crowding pedestrian modelling

Appendix five – Airport Link stations case study

Appendix six – About the audit

Appendix seven – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #333 - released 30 April 2020

 

Published

Actions for Destination NSW's support for major events

Destination NSW's support for major events

Treasury
Financial reporting
Management and administration
Procurement
Project management
Service delivery

This report focuses on whether Destination NSW (DNSW) can demonstrate that its support for major events achieves value for money.

The audit found that DNSW’s processes for assessing and evaluating the major events it funds are mostly effective, but its public reporting does not provide enough transparency.

DNSW provides clear information to event organisers seeking funding and has a comprehensive methodology for conducting detailed event assessments. However, the reasons for decisions to progress events from the initial assessment to the detailed assessment stage are not documented in sufficient detail.

DNSW does not publish detailed information about the events it funds or the outcomes of these events. This means that members of the public are unable to see whether its activities achieve value for money. However, DNSW’s internal reporting to its key decision‑makers, including the CEO, the Board and the Minister is appropriate.

The Auditor-General made four recommendations to DNSW, aimed at improving the transparency of its activities, improving the documentation of decisions and certain compliance matters, and streamlining its approach to assessing and evaluating events that receive smaller amounts of funding.

Read full report (PDF)

Destination NSW (DNSW) provides funding to attract a range of major events to New South Wales, including high-profile professional sports matches and tournaments, musicals, art and museum exhibitions, and participation-focused events such as festivals and sports events that members of the public can enter. The NSW Government's rationale for providing funding is to encourage event organisers to hold events in New South Wales, and to ensure that events held in New South Wales maximise the potential for attracting overseas and interstate visitors.

This audit assessed whether DNSW can demonstrate that its support for major events achieves value for money. In making this assessment, the audit examined whether:

  • DNSW effectively assesses proposals to support major events
  • DNSW effectively evaluates the impact of its support for major events.

This audit focused on DNSW's work to attract major events to New South Wales. It did not assess DNSW's tourism promotion or development work, which includes developing tourism strategies, marketing and advertising campaigns, national and international partnerships, and regional programs.

Conclusion

Destination NSW's processes for assessing event applications and evaluating its support for major events are mostly effective. DNSW's internal systems allow it to know whether its decisions are achieving value for money. Its public reporting does not provide enough information about its activities and their outcomes, although it is consistent with that of equivalent organisations in other Australian jurisdictions.

DNSW's process for assessing applications for funding from organisers of major events is mostly effective. Clear information is provided to event organisers seeking funding, and DNSW has a comprehensive methodology for conducting detailed event assessments. However, the reasons for decisions to progress events from the initial assessment to the detailed assessment stage are not documented in sufficient detail.

DNSW has a framework for disclosure and monitoring staff conflicts of interest. However, its forms for staff to disclose conflicts of interest on specific events they are working on are ambiguous. DNSW's management of gifts and benefits broadly complies with the minimum standards set by the Public Service Commission, but there are some gaps in its implementation of these.

DNSW conducts an evaluation of each major event it supports. DNSW articulates expected outcomes in contracts with event organisers and uses a sound methodology to evaluate events. Internal reporting to its key decision-makers, including the CEO, the Board and the Minister is appropriate. However, DNSW does not publish detailed information about the events it funds or the outcomes of these events. This means that members of the public are unable to see whether its activities achieve value for money.

Appendix one – Response from Destination NSW

Appendix two – About the audit 

Appendix three – Performance auditing

 

Copyright Notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #332 - released 9 April 2020.

Published

Actions for Integrity of data in the Births, Deaths and Marriages Register

Integrity of data in the Births, Deaths and Marriages Register

Justice
Premier and Cabinet
Whole of Government
Cyber security
Fraud
Information technology
Internal controls and governance
Management and administration

This report outlines whether the Department of Customer Service (the department) has effective controls in place to ensure the integrity of data in the Births, Deaths and Marriages Register (the register), and to prevent unauthorised access and misuse.

The audit found that the department has processes in place to ensure that the information entered in the register is accurate and that any changes to it are validated. Although there are controls in place to prevent and detect unauthorised access to, and activity in the register, there were significant gaps in these controls. Addressing these gaps is necessary to ensure the integrity of information in the register.

The Auditor-General made nine recommendations to the department, aimed at strengthening controls to prevent and detect unauthorised access to, and activity in the register. These included increased monitoring of individuals who have access to the register and strengthening security controls around the databases that contain the information in the register.

The NSW Registry of Births Deaths and Marriages is responsible for maintaining registers of births, deaths and marriages in New South Wales as well as registering adoptions, changes of names, changes of sex and relationships. Maintaining the integrity of this information is important as it is used to confirm people’s identity and unauthorised access to it can lead to fraud or identity theft.

Read full report (PDF)

The NSW Registry of Births Deaths and Marriages (BD&M) is responsible for maintaining registers of births, deaths and marriages in New South Wales. BD&M is also responsible for registering adoptions, changes of name, changes of sex and relationships. These records are collectively referred to as 'the Register'. The Births, Deaths and Marriages Registration Act 1995 (the BD&M Act) makes the Registrar (the head of BD&M) responsible for maintaining the integrity of the Register and preventing fraud associated with the Register. Maintaining the integrity of the information held in the Register is important as it is used to confirm people's identity. Unauthorised access to, or misuse of the information in the Register can lead to fraud or identity theft. For these reasons it is important that there are sufficient controls in place to protect the information.

BD&M staff access, add to and amend the Register through the LifeLink application. While BD&M is part of the Department of Customer Service, the Department of Communities and Justice (DCJ) manages the databases that contain the Register and sit behind LifeLink and is responsible for the security of these databases.

This audit assessed whether BD&M has effective controls in place to ensure the integrity of data in the Births, Deaths and Marriages Register, and to prevent unauthorised access and misuse. It addressed the following:

  • Are relevant process and IT controls in place and effective to ensure the integrity of data in the Register and the authenticity of records and documents?
  • Are security controls in place and effective to prevent unauthorised access to, and modification of, data in the Register?

Conclusion

BD&M has processes and controls in place to ensure that the information entered in the Register is accurate and that amendments to the Register are validated. BD&M also has controls in place to prevent and detect unauthorised access to, and activity in the Register. However, there are significant gaps in these controls. Addressing these gaps is necessary to ensure the integrity of the information in the Register.

BD&M has detailed procedures for all registrations and amendments to the Register, which include processes for entering, assessing and checking the validity and adequacy of source documents. Where BD&M staff have directly input all the data and for amendments to the Register, a second person is required to check all information that has been input before an event can be registered or an amendment can be made. BD&M carries out regular internal audits of all registration processes to check whether procedures are being followed and to address non-compliance where required.

BD&M authorises access to the Register and carries out regular access reviews to ensure that users are current and have the appropriate level of access. There are audit trails of all user activity, but BD&M does not routinely monitor these. At the time of the audit, BD&M also did not monitor activity by privileged users who could make unauthorised changes to the Register. Not monitoring this activity created a risk that unauthorised activity in the Register would not be detected.

BD&M has no direct oversight of the database environment which houses the Register and relies on DCJ's management of a third-party vendor to provide the assurance it needs over database security. The vendor operates an Information Security Management System that complies with international standards, but neither BD&M nor DCJ has undertaken independent assurance of the effectiveness of the vendor's IT controls.

Appendix one – Response from agency

Appendix two – About the audit

Appendix three – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #330 - released 7 April 2020.

Published

Actions for Report on Local Government 2019

Report on Local Government 2019

Local Government
Asset valuation
Cyber security
Financial reporting
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Service delivery
Shared services and collaboration
Workforce and capability

I am pleased to present my third report to the Parliament on the 2019 audits of local government councils in New South Wales.

This report notes that unqualified audit opinions were issued on the 2018–19 financial statements of 134 councils and 11 joint organisations. The opinion for one council was disclaimed and three audits are yet to complete.

The report also highlights improvements I have seen in financial reporting and governance arrangements across councils. Fewer errors were identified. More councils have audit, risk and improvement committees and internal audit functions. Risk management practices, including fraud control systems, have also improved.

These are very pleasing indicators of the gradual strengthening of governance and financial oversight of the sector. I want to acknowledge the investment councils have made in working with the Audit Office to improve consistency of practice and accountability generally.

Of course there is more work to do, particularly to prepare for new accounting standards and to strengthen controls over information technology and cyber security management. Asset management practices can also be improved. This report provides some guidance to council on these matters and we will continue to partner with the Office of Local Government in the Department of Planning, Industry and Environment to support good practice.

Margaret Crawford

Auditor-General
5 March 2020

This report focuses on key observations and findings from the 2018–19 financial audits of councils and joint organisations.

Unqualified audit opinions were issued on the financial statements for 134 councils and 11 joint organisations. The audit opinion for Bayside’s 2017–18 and 2018–19 financial statements were disclaimed. Three audits are still in progress and will be included in next year’s report.

The report highlights a number of areas where there has been improvement. There was a reduction in errors identified in council financial statements and high risk issues reported in audit management letters. More councils have audit, risk and improvement committees and internal audit functions. Risk management practices and fraud control systems have also improved.

The report also found that councils could do more to be better prepared for the new accounting standards, asset management practices could be strengthened, and information technology controls and cyber security management could be improved.

The Auditor-General recommended that the Office of Local Government within the Department of Planning, Industry and Environment develop a cyber security policy by 30 June 2021 to ensure a consistent response to cyber security risks across councils.

Read the PDF Report

Financial reporting is an important element of good governance. Confidence in and transparency of public sector decision making is enhanced when financial reporting is accurate and timely. Strong financial performance provides the platform for councils to deliver services and respond to community needs.

This chapter outlines our audit observations on the financial reporting and performance of councils and joint organisations.

Section highlights
  • There was a reduction in the number and dollar value of errors identified in councils' financial statements.
  • We continue to identify prior period errors, which are predominantly asset-related.
  • Unqualified audit opinions were issued for 99 per cent of completed audits for councils and joint organisations.
  • Three audits remain outstanding, with the outcomes to be reported in next year's Report to Parliament.
  • Seventy-nine per cent of councils and joint organisations lodged their financial reports by 31 October 2019.
  • Councils that performed some early reporting procedures achieved better outcomes in terms of the quality and timeliness of financial reporting.
  • Councils are at various levels of preparedness to implement the new accounting standards for the 2019–20 financial year. Some have made the necessary modifications to systems and processes, but others are still assessing impacts.
  • Most councils met the prescribed benchmarks for the liquidity and working capital performance measures over the past three years.
  • More councils reported negative operating performance compared with the prior year, meaning their operating expenditure exceeded their operating revenue.

Strong governance systems and internal controls help councils to operate effectively and efficiently, produce reliable financial reports, comply with laws and regulations and support ethical government.

This chapter outlines the overall trends related to governance and internal control issues across councils and joint organisations for 2018–19.

Section highlights
  • While the total number of issues reported in our management letters increased compared with the prior year, the total number of high risk issues have decreased. Of the high-risk issues, 41 per cent were deficiencies in information technology controls.
  • More councils have established audit, risk and improvement committees and internal audit functions.
  • Councils have improved risk management practices, with over 75 per cent of councils now having a risk management policy and register.
  • While most councils have policies and processes to manage gifts and benefits, we identified some instances of non-compliance with the Model Code of Conduct.
  • Most councils have policies and processes to manage the use of credit cards.
  • Councils can strengthen policies and practices for managing fraud controls and legislative compliance.
  • There are further opportunities for councils to improve internal controls over revenue, purchasing, payroll, cash, financial accounting and governance processes.

Councils rely on information technology (IT) to deliver services and manage information. While IT delivers considerable benefits, it also presents risks that council needs to address.

In prior years, we reported that councils need to improve IT governance and controls to manage key financial systems. This chapter outlines the progress made by councils in the management of key IT risks and controls, with an added focus on cyber security.

Section highlights
  • We continue to report deficiencies in information technology controls, particularly around user access management. These controls are key to ensuring IT systems are protected from inappropriate access and misuse.
  • Many councils do not have IT policies and procedures and others do not identify, monitor or report on IT risks.
  • Cyber security management requires improvement, with some basic elements of governance not yet in place for many councils.

Councils are responsible for managing a significant range of assets to deliver services on behalf of the community.

This chapter outlines our asset management observations across councils and joint organisations.

Section highlights
  • There was an increase in the total number of issues reported in our management letters for asset management processes.
  • There were less high-risk issues reported compared to the previous year.
  • We continue to identify discrepancies between the council's Crown land asset records and the Crown Land Information Database (CLID) managed by the former Department of Industry (DOI).
  • Inconsistent practices remain across the Local Government sector in accounting for landfill sites.

Appendix one – Response from the Office of Local Government within the Department of Planning, Industry and Environment

Appendix two – Status of 2018 recommendations

Appendix three – Status of audits 

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.