This report analyses the results of our audits of the Planning, Industry and Environment cluster agencies for the year ended 30 June 2021.

Our preferred approach is to table the ‘Report on State Finances’ in Parliament before any other cluster report. This is because the 'Report on State Finances' focuses on the audit results and observations relating to the Total State Sector Accounts, in effect a consolidation of all government agencies. This year the 'Report on State Finances' has been delayed due to significant accounting issues being considered in the Total State Sector Accounts and which may impact the Treasury and Transport clusters.

As there are no outstanding matters relating to audits in the Planning, Industry and Environment cluster impacting the Total State Sector Accounts we have decided to break with normal practice and table this cluster report ahead of the ‘Report on State Finances’.

What the report is about

The results of the Planning, Industry and Environment cluster agencies' financial statements audits for the year ended 30 June 2021.

What we found

Unmodified audit opinions were issued for all completed 30 June 2021 financial statements audits of cluster agencies. Three audits are ongoing.

An 'Other Matter' paragraph was included in the Independent Planning Commission's (the IPC) audit opinion because the prior year comparative figures were not audited. Prior to 2020–21, the IPC was not required to prepare separate financial statements under the Public Finance and Audit Act 1983 (PF&A Act). The financial reporting provisions of the Government Sector Finance Act 2018 now require the IPC to prepare financial statements.

The number of identified misstatements increased from 51 in 2019–20 to 54 in 2020–21.

The 2010–11 to 2019–20 audits of the Water Administration Ministerial Corporation’s (the Corporation) financial statements are incomplete due to insufficient records and evidence to support the transactions of the Corporation, particularly for the earlier years. Management has commenced actions to improve the governance and financial management of the Corporation. These audits are currently in progress and the 2020–21 audit will commence shortly.

There are 609 State controlled Crown land managers (CLMs) across New South Wales that predominantly manage small parcels of Crown land.

Eight CLMs prepared and submitted 2019–20 financial statements by the revised deadline of 30 June 2021. A further 24 CLMs did not prepare financial statements in accordance with the PF&A Act. The remaining CLMs were not required to prepare 2019–20 financial statements as they met NSW Treasury's financial reporting exemption criteria.

The Department of Planning, Industry and Environment's (the department) preliminary assessment indicates that 60 CLMs are required to prepare financial statements in 2020–21. To date, no CLMs have prepared and submitted financial statements for audit in 2020–21.

There are also 120 common trusts that have never submitted financial statements for audit. Common trusts are responsible for the care, control and management of land that has been set aside for specific use in a certain locality, such as grazing, camping or bushwalking.

What the key issues were

The number of matters we reported to management increased from 135 in 2019–20 to 180 in 2020–21, of which 40 per cent were repeat findings.

Seven high-risk issues were identified in 2020–21:

  • system control deficiencies at the department relating to user access to HR and payroll management systems, vendor master data management and journal processing, which require manual reviews to mitigate risks
  • deficiencies related to the Centennial Park and Moore Park Trust's tree assets valuation methodology
  • the Lord Howe Island Board did not regularly review and monitor privileged user access rights to key information systems
  • the Natural Resources Access Regulator identified and adjusted three prior period errors retrospectively, which indicate deficiencies within the financial reporting processes
  • deficiencies relating to the Parramatta Park Trust's tree assets valuation methodology
  • lease arrangements have not been confirmed between the Planning Ministerial Corporation and Office of Sport regarding the Sydney International Regatta Centre
  • the Wentworth Park Sporting Complex land manager (the land manager) has a $6.5 million loan with Greyhound Racing NSW (GRNSW). GRNSW requested the land manager to repay the loan. However, the land manager subsequently requested GRNSW to convert the loan to a grant. Should this request be denied, the land manager would not be able to continue as a going concern without financial support. This matter remains unresolved for many years.

There continues to be significant deficiencies in Crown land records. The department uses the Crown Land Information Database (CLID) to record key information relating to Crown land in New South Wales that are managed and controlled by the department and land managers (including councils and land managers controlled by the state). The CLID system was not designed to facilitate financial reporting and the department is required to conduct extensive adjustments and reconciliations to produce accurate information for the financial statements.

The department is implementing a new system to record Crown land (the CrownTracker project). The department advised that the project completion date will be confirmed by June 2022.

What we recommended

The department should ensure CLMs and common trusts meet their statutory reporting obligations.

Cluster agencies should prioritise and action recommendations to address internal control deficiencies, with a focus on addressing high-risk and repeat issues.

The department should prioritise action to ensure the Crown land database is complete and accurate. This will allow the department and CLMs to be better informed about the Crown land they control.

Fast facts

The Planning, Industry and Environment cluster aims to make the lives of people in New South Wales better by developing well-connected communities, preserving the environment, supporting industries and contributing to a strong economy.

There are 54 agencies, 609 State controlled Crown land managers that predominantly manage small parcels of Crown land and 120 common trusts in the cluster.

  • 42% of the area of NSW is Crown land
  • $33.2b water and electricity infrastructure as at 30 June 2021
  • 100% unqualified audit opinions were issued for all completed 30 June 2021 financial statements audits
  • 7 high-risk management letter findings were identified
  • 54 monetary misstatements were reported in 2020–21
  • 40% of reported issues were repeat issues

This report provides parliament and other users of the Planning, Industry and Environment cluster (the cluster) agencies’ financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision-making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Planning, Industry and Environment cluster (the cluster) for 2021.

Section highlights

  • Unmodified audit opinions were issued for all completed 30 June 2021 financial statements audits of cluster agencies. Three audits are ongoing.
  • An 'Other Matter' paragraph was included in the Independent Planning Commission’s (the IPC) audit opinion because the prior year comparative figures were not audited. Prior to 2020–21, the IPC was not required to prepare separate financial statements under the Public Finance and Audit Act 1983. From 2020–21, the IPC is required to prepare financial statements under the Government Sector Finance Act 2018.
  • The 2010–11 to 2019–20 audits of the Water Administration Ministerial Corporation’s (the Corporation) financial statements were incomplete due to insufficient records and evidence to support the transactions of the Corporation, particularly for the earlier years. These audits are currently underway, and the 2020–21 audit will commence shortly.
  • The Department of Planning, Industry and Environment's (the department) preliminary assessment indicates that 60 State controlled Crown land managers (CLMs) are required to prepare financial statements in 2020–21. To date, no CLMs have prepared and submitted financial statements for audit in 2020–21. All 120 common trusts have never submitted their financial statements for audit. The department needs to do more to ensure that the CLMs and common trusts meet their statutory reporting obligations.
  • Nine agencies that were required to perform early close procedures did not complete a total of 20 mandatory procedures. The most common incomplete early close procedures include the revaluation of property, plant and equipment, documenting all significant management judgments and assumptions, and the implementation of new and updated accounting standards.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision-making.

This chapter outlines our observations and insights from our financial statements audits of agencies in the Planning, Industry and Environment cluster.

Section highlights

  • The number of findings reported to management has increased from 135 in 2019–20 to 180 in 2020–21, and 40 per cent were repeat issues.
  • Seven high-risk issues were identified in 2020–21, and three high-risk findings were repeat issues.
  • There continues to be significant deficiencies in Crown land records. The department should prioritise action to ensure the Crown land database is complete and accurate.

Appendix one - Misstatements in financial statements submitted for audit

Appendix two – Early close procedures

Appendix three – Timeliness of financial reporting

Appendix four – Financial data

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Premier and Cabinet 2021

Premier and Cabinet 2021

Premier and Cabinet
Whole of Government
Asset valuation
Financial reporting
Infrastructure
Internal controls and governance
Shared services and collaboration

This report analyses the results of our audits of the Premier and Cabinet cluster agencies for the year ended 30 June 2021.

Our preferred approach is to table the ‘Report on State Finances’ in Parliament before any other cluster report. This is because the 'Report on State Finances' focuses on the audit results and observations relating to the Total State Sector Accounts, in effect a consolidation of all government agencies. This year the 'Report on State Finances' has been delayed due to significant accounting issues being considered in the Total State Sector Accounts and which may impact the Treasury and Transport clusters.

As there are no outstanding matters relating to audits in the Premier and Cabinet cluster impacting the Total State Sector Accounts we have decided to break with normal practice and table this cluster report ahead of the ‘Report on State Finances’.

What the report is about

The results of the Premier and Cabinet cluster (the cluster) agencies' financial statement audits for the year ended 30 June 2021.

What we found

Unmodified audit opinions were issued for all Premier and Cabinet cluster agencies.

The number of monetary misstatements decreased from 49 in 2019–20 to 38 in 2020–21.

The Library Council of New South Wales corrected a prior period error of $325 million. In 2017, the council split its collection assets into six asset classes, but not the related asset revaluation reserves. To correct this error, some revaluation decrements previously recognised in asset revaluation reserves were reclassified to accumulated funds.

Eight agencies did not complete all of the mandatory early close procedures.

What the key issues were

The Premier and Cabinet cluster was impacted by three Machinery of Government (MoG) changes during 2020–21.

The changes resulted in the transfer of activities and functions in and out of the cluster and the creation of a new entity - Investment NSW.

The transferor entities continued to provide services to Investment NSW subsequent to 30 June 2021. There were no formal service level agreements in place for the provision of these services.

The New South Wales Electoral Commission (the Commission) and Sydney Opera House Trust obtained letters of financial support from their relevant Minister and/or NSW Treasury in 2020–21. The postponement of local government elections impacted the Commission's operations due to increased planned expenditure to support a COVID-safe election. Sydney Opera House Trust's ability to generate revenue was impacted due to the closure of the Concert Hall partly due to COVID-19 and planned renovations.

The number of repeated audit issues raised with management and those charged with governance increased from 22 in 2019–20 to 24 in 2020–21.

There were 47 moderate risk and 28 low risk findings identified. Of the total findings there were 24 repeat issues.

What we recommended

Investment NSW should ensure services received from other agencies are governed by service level agreements.

Fast facts

The Department of Premier and Cabinet supports the Premier and Cabinet to deliver the government's objectives, infrastructure, preparedness for disaster, incident recovery, arts and culture.

  • $11.9b of property, plant and equipment as at 30 June 2021
  • $4.4b total expenditure incurred in 2020-21
  • 100% unqualified audit opinions were issued on agencies' 30 June 2021 financial statements
  • 47 moderate risk findings were reported to management 
  • 38 monetary misstatements were reported in 2020-21
  • 32% of all reported issues were repeat issues.

This report provides Parliament and other users of the Premier and Cabinet’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Premier and Cabinet cluster (the cluster) for 2021.

Section highlights

  • Unqualified audit opinions were issued on all completed cluster agencies' 2020–21 financial statements.
  • Monetary misstatements decreased from 49 in 2019–20 to 38 in 2020–21.
  • Thirteen agencies were exempt from financial reporting in 2020–21. 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the Premier and Cabinet cluster.

Section highlights

  • The 2020–21 audits identified 47 moderate risk issues across the cluster. Sixteen of the moderate risk issues were repeat issues. Many repeat issues related to governance and oversight and information technology.
  • The number of moderate risk findings increased by 42 per cent in 2020–21.
  • The moderate risk issues included information technology improvements, lack of service level agreements, risk management, contract and procurement and asset management improvements.

Appendix one – Misstatements in financial statements submitted for audit

Appendix two – Early close procedures

Appendix three – Timeliness of financial reporting

Appendix four – Financial data

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Regional NSW 2021

Regional NSW 2021

Environment
Industry
Asset valuation
Compliance
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Service delivery

This report analyses the results of our audits of the Regional NSW cluster agencies for the year ended 30 June 2021.

Our preferred approach is to table the ‘Report on State Finances’ in Parliament before any other cluster report. This is because the 'Report on State Finances' focuses on the audit results and observations relating to the Total State Sector Accounts, in effect a consolidation of all government agencies. This year the 'Report on State Finances' has been delayed due to significant accounting issues being considered in the Total State Sector Accounts and which may impact the Treasury and Transport clusters.

As there are no outstanding matters relating to audits in the Regional NSW cluster impacting the Total State Sector Accounts we have decided to break with normal practice and table this cluster report ahead of the ‘Report on State Finances’.

What the report is about

The results of the Regional NSW cluster (the cluster) agencies’ financial statement audits for the year ended 30 June 2021.

What we found

Unmodified audit opinions were issued for all completed 30 June 2021 financial statement audits of cluster agencies. Four audits are ongoing.

The number of misstatements identified in the financial statements of cluster agencies decreased from 27 in 2019–20 to seven in 2020–21.

The Department corrected an understatement of $82.2 million in prepaid income related to the Bushfire Clean-up Program.

What the key issues were

Local Land Services (LLS) undertook a comprehensive revaluation of asset improvements on land reserves used for moving stock (travelling stock reserves).

The revaluation process identified that improvements on land reserves, with a value of $93.0 million, had not been previously recognised in the financial statements. LLS corrected this error by restating the 2019–20 comparative balances in its 2020–21 financial statements.

The Forestry Corporation of NSW revalued its biological assets that comprise approximately 225,000 hectares of softwood plantations and 34,000 hectares of hardwood forests. The current year valuation resulted in $71.4 million decrement in the total biological assets from $824.9 million in 2019–20 to $753.5 million in 2020–21.

The number of matters reported to management decreased from 36 in 2019–20 to 19 in 2020–21. Twelve moderate risk issues were identified and 47 per cent of reported issues were repeat issues.

What we recommended

Cluster agencies should prioritise and action recommendations to address internal control deficiencies.

 

Fast facts

The Regional NSW cluster plans and delivers regional programs and infrastructure to respond to regional issues, creating and preserving regional jobs, driving regional economy, growing existing and supporting emerging industries. There are 31 agencies in the cluster.

  • $2.3b of regional land and buildings as at 30 June 2021.

  • 100% unqualified audit opinions were issued for all completed 30 June 2021 financial statements audits.

  • monetary misstatements were reported in 2020–21.

  • $603m of grants and subsidies administered to the regional community in 2020–21.

  • 12 moderate risk management letter findings were identified and reported to management.

  • 47% of reported issues were repeat issues. 

This report provides Parliament and other users of the Regional NSW cluster agencies’ financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Regional NSW cluster for 2021.

Section highlights

  • Unqualified audit opinions were issued for all completed 30 June 2021 financial statements audits of cluster agencies. Four audits are ongoing.
  • The number of monetary misstatements identified during the audit decreased from 27 in 2019–20 to seven in 2020–21.
  • Three cluster agencies could improve their early close process by completing all required procedures.
  • Local Land Services disclosed a prior period error relating to the completeness of asset improvements on travelling stock reserves.

 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the Regional NSW cluster.

Section highlights

  • The number of findings reported to management decreased from 36 in 2019–20 to 19 in 2020–21, and 47 per cent were repeat findings.
  • The 2020–21 audits identified 12 moderate risk and seven low risk issues across the cluster.
  • Four moderate risk issues and five low risk issues were repeat findings from
    2019–20.

 

Appendix one - Misstatements in financial statements submitted for audit

Appendix two - Early close procedures

Appendix three - Financial data

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Central Agencies 2020

Central Agencies 2020

Premier and Cabinet
Treasury
Financial reporting
Internal controls and governance
Management and administration
Risk

This report analyses the results of our audits of the financial statements of the Treasury, Premier and Cabinet, Customer Service cluster agencies (central agencies), and the Legislature for the year ended 30 June 2020. The table below summarises our key observations.

1. Financial reporting

Audit opinions and timeliness of reporting

Unqualified audit opinions were issued on the 2019–20 financial statements of central agencies and the Legislature.

The audit opinion on the Social and Affordable Housing NSW Fund's compliance with the payment requirements of the Social and Affordable Housing NSW Fund Act 2016 was qualified.

All agencies met statutory deadlines for submitting
financial statements. 

Agencies were financially impacted by recent emergency events The NSW Government allocated $1.4 billion to provide small business support and bushfire recovery relief, support COVID-19 quarantine compliance management, recruit more staff to respond to increased customer demand, and meet additional COVID-19 cleaning requirements. Agencies spent $901 million (64 per cent of the allocated funding) for the financial year ended 30 June 2020. NSW Self Insurance Corporation reported an increase of $850 million in its liability for claims related to emergency events.
AASB 16 'Leases' resulted in significant changes to agencies' financial position The implementation of new accounting standards was challenging for many agencies. The New South Wales Government Telecommunications Authority was not well-prepared to implement AASB 16 'Leases' and had not completely assessed contracts that contained leases. This resulted in understatements of leased assets and liabilities by $56 million which were subsequently corrected.
Implementation of new revenue standards NSW Treasury did not adequately implement the new revenue standard AASB 1058 ‘Income of Not-for-Profit Entities’ for the Crown Entity. This resulted in understatements of $274 million in opening equity and $254 million to current year revenue, which have been corrected in the final financial statements.

2. Audit observations

Management letter findings and repeat issues Our 2019–20 audits identified nine high risk and 122 moderate risk issues across central agencies and the Legislature. The high risk issues were identified in the audits of:
  • Insurance and Care NSW
  • New South Wales Government Telecommunications Authority
  • Rental Bond Board
  • Independent Commission Against Corruption
  • NSW Treasury
  • Crown Entity
  • Department of Premier and Cabinet.

High risk findings include:

  • Insurance and Care NSW (icare) allocates service costs to the Workers Compensation Nominal Insurer, and the other schemes it supports. The documentation supporting cost allocations does not demonstrate how these allocations reflect actual costs. There is a risk of the Workers Compensation Nominal Insurer being overcharged.
  • New South Wales Government Telecommunications Authority's delay in capitalisation and valuation of material capital projects; and insufficient work performed to implement the new accounting standard AASB 16 ‘Leases’.
  • NSW Treasury's four-year plan to transition RailCorp to a for-profit State Owned Corporation called Transport Asset Holding Entity of New South Wales (TAHE) by 1 July 2019, remains to be implemented. On 1 July 2020, RailCorp converted to TAHE. A large portion of the planned arrangements are still to be implemented. As at the time of the audit, the TAHE operating model, Statement of Corporate Intent (SCI) and other key plans and commercial agreements were not finalised. In the absence of commercial arrangements with the public rail operators, there is a lack of evidence to demonstrate TAHE’s ability to create a commercial return in the long term. This matter has been included as a high risk finding in our management letter as there may be financial reporting implications to the State if TAHE does not generate a commercial return for its shareholders in line with the original intent. NSW Treasury and TAHE should ensure the commercial arrangements, operating model and SCI are finalised in 2020–21.

Of the 122 moderate risk issues, 36 per cent were repeat issues. The most common repeat issue related to weaknesses in controls over information technology user access administration, which increases the risk of inappropriate access to systems and records.

Grants administration for disaster relief Service NSW delivers grants responding to emergency events on behalf of other NSW Public Sector agencies. Since the first grant program commenced in January 2020, Service NSW processed approximately $791 million to NSW citizens and businesses impacted by emergency events for the financial year ended 30 June 2020. A performance audit of grants administration for disaster relief is planned for 2020–21. It will assess whether grants programs administered under the Small Business Support Fund were effectively designed and implemented to provide disaster relief.
Internal controls at GovConnect NSW service providers require enhancement

GovConnect NSW provides transactional and information technology services to central agencies. It engages an independent service auditor (service auditor) from the private sector to perform annual assurance reviews of controls at service providers, namely Infosys, Unisys and the Department of Customer Service (DCS). The service auditor issued:

  • unqualified opinions on information technology and business process controls at Infosys and Unisys, but there was an increase in control deficiencies identified in the user access controls at these service providers
  • a qualified opinion on DCS's information technology (IT) security monitoring controls because security tools were not implemented and monitored for the entire financial year. Responsibility for IT security monitoring transitioned from Unisys to DCS in 2019–20. These control deficiencies can increase the risk of fraud and inappropriate use of sensitive data.

These may impact on the ability of agencies to detect and respond to a cyber incident.

Recommendation:

We recommend DCS work with GovConnect service providers to resolve the identified control deficiencies as a matter of priority.

The NSW Public Sector's cyber security resilience needs to improve

The NSW Cyber Security Policy requires agencies to provide a maturity self-assessment against the Australian Cyber Security Centre (ACSC) Essential 8 to the head of the agency and Cyber Security NSW annually. Completed self-assessment returns highlighted limited progress in implementing the Essential 8.

Repeat recommendation:

Cyber Security NSW and NSW government agencies need to prioritise improvements to their cyber security resilience as a matter of urgency

Three Insurance and Care NSW (icare) entities had net asset deficiencies at 30 June 2020 The Workers Compensation Nominal Insurer, NSW Self Insurance Corporation and the Lifetime Care and Support Authority of NSW all had negative net assets at 30 June 2020. These icare entities did not hold sufficient assets to meet the estimated present value of all of their future payment obligations at 30 June 2020. The deterioration in net assets was largely due to increases in outstanding claims liabilities. Notwithstanding the overall net asset deficiencies, the financial statements for these entities were prepared on a going concern basis. This is because future payment obligations are not all due within the next 12 months. Settlement is instead expected to occur over years into the future, depending on the nature of the benefits provided by each scheme.
icare has not been able to demonstrate that its allocation of costs reflects the actual costs incurred by the Workers Compensation Nominal Insurer and other schemes

Costs are incurred by icare as the 'service entity' of the statutory scheme it administers, and then subsequently recovered from the schemes through 'service fees'. In the absence of documentation supported by robust supporting analysis, there is a risk of the schemes being overcharged, and the allocation of costs being in breach of legislative requirements.

Recommendation:

icare should ensure its approach to allocating service fees to the Workers Compensation Nominal Insurer and the other schemes it manages, is transparent and reflects actual costs.

icare did not comply with GIPA requirements icare did not comply with the Government Information (Public Access) Act 2009 (GIPA) contract disclosure requirements in 2019–20 and has not complied for several years. A total of 417 contracts were identified by management as not having been published on the NSW Government’s eTendering website. The final upload of these past contracts occurred on 20 August 2020.
Implementation of Machinery of Government (MoG) changes MoG changes impacted the governance and business processes of some agencies. Our audits identified and reported areas for improvement in the consolidation of corporate functions following MoG implementation processes at Infrastructure NSW and in the Customer Service cluster.

This report provides Parliament and other users of NSW Government central agencies' financial statements and the Legislature's financial statements with the results of our financial audits, observations, analyses, conclusions and recommendations.

Emergency events, such as bushfires, floods and the COVID-19 pandemic significantly impacted agencies in 2019–20. Our findings on nine agencies that were most impacted by recent emergency events are included throughout this report.

Refer to Appendix one for the names of all central agencies and Appendix four for the nine agencies most impacted by emergency events.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely. This chapter outlines our audit observations on the financial reporting of central agencies and the Legislature for 2020, including the financial implications from recent emergency events.

Section highlights

  • Unqualified audit opinions were issued on the 2019–20 financial statements of central agencies and the Legislature. All agencies met the statutory deadlines for submitting their financial statements.
  • The audit opinion on the Social and Affordable Housing NSW Fund's compliance with the payment requirements of the Social and Affordable Housing NSW Fund Act 2016 was qualified as a result of a payment made without a Treasurer's delegation.
  • Agencies were impacted by emergency events during 2019–20. This included additional grants to fund specific deliverables.
  • The implementation of new accounting standards was challenging for many agencies. The New South Wales Government Telecommunications Authority was not well-prepared to implement AASB 16 'Leases' and had not completely assessed contracts that contained leases. This resulted in understatements of leased assets and liabilities by $56 million which were subsequently corrected.
  • NSW Treasury did not adequately implement the new revenue standard AASB 1058 ‘Income of Not-for-Profit Entities’ for the Crown Entity. This resulted in understatements of $274 million in opening equity and $254 million to current year revenue in the financial statements. These misstatements were due to incorrect revenue calculations performed by the Transport agencies. The Crown Entity relies on information from Transport agencies as they are responsible for carrying out the State’s contractual obligations for Commonwealth funded transport projects. The extent of misstatements could have been reduced with more robust quality review processes in place by Treasury and Transport.

 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines:

  • our observations and insights from the financial statement audits of agencies in the central agencies and the Legislature
  • our assessment of how well agencies adapted their systems, policies, procedures and governance arrangements in response to recent emergencies.

Section highlights

  • The 2019–20 audits identified nine high risk and 122 moderate risk issues across the agencies. Of the 122 moderate risk issues, 44 (36 per cent) were repeat issues. The most common repeat issue relates to weaknesses in controls over information technology user access administration.
  • Service NSW delivers grants responding to emergency events on behalf of other NSW Public Sector agencies. Since the first grant program commenced in January 2020, Service NSW processed approximately $791 million to NSW citizens and businesses impacted by these emergency events for the financial year ended 30 June 2020.
  • GovConnect NSW engaged an independent auditor (the service auditor) from the private sector to evaluate the internal controls of its service providers. DCS's information technology security monitoring controls were qualified by the service auditor because security tools were not implemented and monitored for the entire financial year. These may impact on the ability of agencies to detect and respond to a cyber incident.
  • NSW Government agency self-assessment results show that the NSW Public Sector's cyber security resilience needs urgent attention.
  • The Workers Compensation Nominal Insurer, NSW Self Insurance Corporation and the Lifetime Care and Support Authority of NSW all had negative net assets at 30 June 2020. The financial statements for these entities continued to be prepared on a going concern basis as their liabilities are not all due for settlement within the next 12 months.
  • icare did not comply with the Government Information (Public Access) Act 2009 (GIPA) contract disclosure requirements in 2019–20, and has not complied for several years. A total of 417 contracts were identified by management as not having been published on the NSW Government’s eTendering website. The final upload of these past contracts occurred on 20 August 2020.
  • Machinery of Government (MoG) changes impacted the governance and business processes of affected agencies. Our audits identified and reported areas for improvement in the consolidation of corporate functions following MoG changes at Infrastructure NSW and in the Customer Service cluster.

 

Published

Actions for Transport 2020

Transport 2020

Transport
Asset valuation
Cyber security
Financial reporting
Information technology
Infrastructure
Project management

1. Financial Reporting

Audit opinion Unmodified audit opinions issued for the financial statements of all Transport cluster entities.
Quality and timeliness of financial reporting All cluster agencies met the statutory deadlines for completing the early close and submitting the financial statements.

Transport cluster agencies continued to experience some challenges with accounting for land and infrastructure assets. The former Roads and Maritime Services and Sydney Metro recorded prior period corrections to property, plant and equipment balances.
Impact of COVID-19 on passenger revenue and patronage Total patronage and revenue for public transport decreased by approximately 18 per cent in 2019–20 due to COVID-19.

The Transport cluster received additional funding from NSW Treasury during the year to support the reduced revenue and additional costs incurred such as cleaning on all modes of public transport and additional staff to manage physical distancing.
Completion of the CBD and South East Light Rail The CBD and South East Light Rail project was completed and commenced operations in this financial year. At 30 June 2020, the total cost of the project related to the CBD and South East Light Rail was $3.3 billion. Of this total cost, $2.6 billion was recorded as assets, whilst $700 million was expensed.

2. Audit Observations

Internal control While internal controls issues raised in management letters in the Transport cluster have decreased compared to the prior year, control weaknesses continue to exist in access security for financial systems. We identified 56 management letter findings across the cluster and 43 per cent of all issues were repeat issues. The majority of the repeat issues relate to information technology controls around user access management.

There were three high risk issues identified - two related to financial reporting of assets and one for implementation of TAHE (see below).
Agency responses to emergency events Transport for NSW established the COVID-19 Taskforce in March 2020 to take responsibility for the overall response of planning and coordination for the Transport cluster. It also implemented the COVIDSafe Transport Plan which incorporates guidance on physical distancing, increasing services to support social distancing and cleaning.
RailCorp transition to TAHE On 1 July 2020, RailCorp was renamed Transport Asset Holding Entity of New South Wales (TAHE) and converted to a for-profit statutory State-Owned Corporation. TAHE is a commercial for-profit Public Trading Entity with the intent to provide a commercial return to its shareholders.

A plan was established by NSW Treasury to transition RailCorp to TAHE which covered the period 1 July 2015 to 1 July 2019. A large portion of the planned arrangements were not implemented by 1 July 2020. As at the time of this report, the TAHE operating model, Statement of Corporate Intent (SCI) and other key plans and commercial agreements are not finalised. The State Owned Corporations Act 1989 generally requires finalisation of an SCI three months after the commencement of each financial year. However, under the Transport Administration Act 1988, TAHE received an extension from the voting shareholders, the Treasurer and Minister for Finance and Small Business, to submit its first SCI by 31 December 2020. In accordance with the original plan, interim commercial access arrangements were supposed to be in place with RailCorp prior to commencement of TAHE.

Under the transitional arrangements, TAHE is continuing to operate in accordance with the asset and safety management plans of RailCorp. The final operating model is expected to include considerations of safety, operational, financial and fiscal risks. This should include a consideration of the potential conflicting objectives of a commercial return, and maintenance and safety measures.

This matter has been included as a high risk finding in our management letter due to the significance of the financial reporting impacts and business risks for TAHE.

Recommendation: TAHE management should:
  • establish an operating model in line with the original intent of a commercial return
  • finalise commercial agreements with the public rail operators
  • confirm forecast financial information to assess valuation of TAHE infrastructure
  • finalise asset and safety management plans.

Resolution of the above matters are critical as they may significantly impact the financial reporting arrangements for TAHE for 2020–21, in particular, accounting policies adopted as well as measurement principles of its significant infrastructure asset base.

Completeness and accuracy of contracts registers Across the Transport cluster, contracts and agreements are maintained by the transport agencies using disparate registers.

Recommendation (repeat): Transport agencies should continue to implement a process to centrally capture all contracts and agreements entered. This will ensure:
  • agencies are fully aware of contractual and other obligations
  • appropriate assessment of financial reporting implications
  • ongoing assessments of accounting standards, in particular AASB 16 ‘Leases’, AASB 15 'Revenue from Contract with Customers', AASB 1058 'Income of Not-for-Profit Entities' and new accounting standard AASB 1059 'Service Concession Arrangements: Grantors' are accurate and complete.

 

This report provides parliament and other users of the Transport cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations
  • the impact of emergencies and the pandemic.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Transport cluster for 2020, including any financial implications from the recent emergency events.

Section highlights

  • Total patronage and revenue for public transport decreased by approximately 18 per cent in 2019–20 due to COVID-19.
  • Unqualified audit opinions were issued on all Transport agencies' financial statements.
  • Transport cluster agencies continued to experience challenges with accounting of land and infrastructure assets.

 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our:

  • observations and insights from our financial statement audits of agencies in the Transport cluster
  • assessment of how well cluster agencies adapted their systems, policies and procedures, and governance arrangements in response to recent emergencies.

Section highlights

  • While there was a decrease in findings on internal controls across the Transport cluster, 43 per cent of all issues were repeat issues. Many repeat issues related to information technology controls around user access management.
  • RailCorp transitioned to TAHE on 1 July 2020. TAHE's operating model and commercial arrangements with public rail operators has not been finalised despite government original plans to be operating from 1 July 2019. TAHE management should finalise its operating model and commercial agreements with public rail operators as they may significantly impact the financial reporting arrangements for TAHE for 2020–21.
  • Completeness and accuracy of contracts registers remains an ongoing issue for the Transport cluster.

Appendix one – List of 2020 recommendations

Appendix two – Status of 2019, 2018 and 2017 recommendations

Appendix three – Management letter findings

Appendix four – Financial data

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Regional NSW 2020

Regional NSW 2020

Environment
Industry
Compliance
Financial reporting
Information technology
Management and administration
Risk

This report analyses the results of our audits of financial statements of entities within the Regional NSW cluster for the year ended 30 June 2020. The table below summarises our key observations and recommendations.

1. Machinery of Government (MoG) changes

Creation of Regional NSW cluster MoG changes on 2 April 2020 created the Department of Regional NSW (the Department). The Department of Planning, Industry and Environment (DPIE) staff employed in the Regions, Industry, Agriculture and Resources Group, together with associated functions, assets and liabilities were transferred to the new Department. A number of agencies moved from the Planning, Industry and Environment cluster to the new Regional NSW cluster. The Department deals with major issues affecting regional communities, including the coordination of support for people, businesses and farmers who have faced drought, bushfires, flood and the COVID-19 pandemic.
The Department is still in the process of implementing changes The Department continues to receive corporate services support from DPIE. The Department has indicated it will transition to its own policies and procedures by June 2021.

2. Financial reporting

Audit opinions Unqualified audit opinions were issued for all cluster agencies' 30 June 2020 financial statements audits.
Timeliness of financial reporting Nine of the ten cluster agencies subject to statutory reporting deadlines met the revised timeline for submitting the financial statements. The Department and a number of cluster agencies obtained NSW Treasury’s approval to delay submission of their 30 June 2020 financial statements due to delays resulting from accounting and administrative complexities created by the Machinery of Government changes that separated the Department from DPIE. The deadlines were moved from 5 August 2020 to either 10 August 2020 or 12 August 2020. New South Wales Rural Assistance Authority missed the revised deadline by one day. All agencies that were required to perform early close procedures had met the revised timeline. Due to issues identified during audit, four financial statements audit were not completed and audit opinions issued by the statutory deadline.
New accounting standards

Agencies implemented three new accounting standards during the year. Our audit of the Department identified there was a lack of quality assurance over the accuracy of lease information provided by Property NSW.

Recommendation:

The Department should:

  • quality assure and validate the leasing information provided by Property NSW
  • ensure changes made by Property NSW to lease data are supported and that assumptions and judgements applied are appropriate
  • document their review of the data supplied.

3. Audit observations

Internal control deficiencies

We identified 30 internal control issues, including 16 findings that were raised with former agencies in previous years. Two matters from previous years have been elevated to high risk during 2019–20. Both matters related to Local Land Services:

  • not completing all mandatory requirements as part of its early close procedures at 31 March 2020
  • not performing annual fair value assessment of asset improvements on land reserves used for moving livestock.

Recommendation:

Management letter recommendations to address internal control weaknesses should be actioned promptly, with a focus on addressing high-risk and repeat issues.

Agency responses to emergency events The Department's executive leadership committee along with support from DPIE crisis management team managed the recovery from the bushfires and impact of COVID-19. Social distancing and other infection control measures were put in place. The Forestry Corporation of New South Wales accelerated a fire salvage timber program in response to the bushfire emergency. The Department and cluster agencies received additional funding for bushfire recovery and COVID-19 pandemic response.

The Regional NSW cluster aims to respond to regional issues, creating and preserving regional jobs, driving regional economy, growing existing and supporting emerging industries. The key areas of focus across the New South Wales (NSW) State is shown below:

MoG changes impact on Department of Regional NSW

The Department was created as result of the MoG changes during 2019–20. The Administrative Arrangements Order 2020, effective on 2 April 2020 created the Department of Regional NSW. These changes had a significant administrative impact on the cluster agencies. The MoG change resulted in a transfer of net assets ($446 million) and budget ($284 million) from DPIE to the newly created Department of Regional NSW on 2 April 2020. A summary of the MoG impacts on the Regional NSW cluster is shown below.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

The COVID-19 Legislation Amendment (Emergency Measures–Treasurer) Act 2020 amended legislation administered by the Treasurer to implement further emergency measures as a result of the COVID-19 pandemic. These amendments:

  • allowed the Treasurer to authorise payments from the consolidated fund until the enactment of the 2020–21 budget – impacting the going concern assessments of cluster agencies
  • revised budgetary and financial and annual reporting time frames – impacting the timeliness of financial reporting
  • exempted certain statutory bodies and departments from preparing financial statements.

This chapter outlines our audit observations related to the financial reporting of agencies in the Regional NSW cluster for 2020, including any financial implications from the recent emergency events.

Section highlights

  • Unqualified audit opinions were issued for all cluster agencies' 30 June 2020 financial statements audits.
  • Nine of the ten cluster agencies subject to statutory reporting deadlines met the revised timeline for submitting the financial statements. New South Wales Rural Assistance Authority missed the revised deadline by one day.
  • Due to issues identified during audit, four financial statements audit were not completed and audit opinions issued by the statutory deadline.
  • Emergency legislation allowing the Treasurer to continue authorising payments from the consolidated fund under the existing Appropriations Act enabled cluster agencies to prepare financial statements on a going concern basis.

 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our:

  • observations and insights from our financial statement audits of agencies in the Regional NSW cluster
  • assessment of how well cluster agencies adapted their systems, policies and procedures, and governance arrangements in response to recent emergencies.

Section highlights

  • Two high-risk issues were identified during our audits. Both related to Local Land Services for:
    − not completing all mandatory requirements as part of its early close procedures at 31 March 2020
    − not performing annual fair value assessment of asset improvements on land reserves used for moving livestock
  • More than one in two issues identified and reported to management in 2019–20 were raised in the former agencies.

Appendix one - List of 2020 recommendations

Appendix two - Financial data

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Planning, Industry and Environment 2020

Planning, Industry and Environment 2020

Planning
Environment
Industry
Asset valuation
Compliance
Financial reporting
Internal controls and governance
Management and administration

This report analyses the results of our audits of financial statements of the Planning, Industry and Environment cluster agencies for the year ended 30 June 2020. The table below summarises our key observations.

1. Financial reporting

Audit opinions

There are 45 separate entities in the cluster. Unqualified audit opinions were issued for 38 cluster agencies' 30 June 2020 financial statements audits. Four financial statements audits are still ongoing, and three agencies were not subject to audit due to NSW Treasury reporting exemptions.

Timeliness of financial reporting

The majority of cluster agencies subject to statutory reporting deadlines met the revised timeline for submitting financial statements. Twenty‑four of the 26 cluster agencies required to submit early close financial statements met the revised timeframe.

Due to issues identified during the audit, 13 financial statements audits were not completed and audit opinions not issued by the statutory deadline.

Implementation of AASB 16 'Leases'

Significant deficiencies were identified in Property NSW's lease data maintenance and lease calculations.

Recommendation (partially repeat):

Property NSW should:

  • review and document the accounting implications for each lease
  • ensure the accuracy and validity of lease data used for the lease calculations
  • review user access to the leasing system, including privileged users.

Our audits of the cluster agencies identified there was a lack of thorough quality assurance over the accuracy of lease information provided by Property NSW.

Recommendation:

The Department and cluster agencies should:

  • quality assure and validate the information provided by Property NSW
  • ensure changes made by Property NSW on lease data are supported and that assumptions and judgements applied are appropriate
  • document their review of the data supplied.

Unprocessed Aboriginal land claims continued to increase

In 2019–20, the Department resolved an additional 468 Aboriginal land claims compared to the prior year. However, the total number of unprocessed Aboriginal land claims increased by 914 to 36,769 at 30 June 2020. The number of claims remaining unprocessed for more than ten years after lodgement increased by 10.9 per cent from last year. Until claims are resolved, there is an uncertainty over who is entitled to the land and the uses and activities that can be carried out on the land.

Auditor-General's Reports to Parliament since 2007 have recommended action to address the increasing number of unprocessed claims. To date, the Department has not been able to resolve this issue.

During 2020–21, a performance audit will assess the effectiveness and efficiency of the administration of Aboriginal land claims.

Financial reporting of Crown land managers

The Department will need to provide additional support and guidance to help Crown land managers (CLMs) meet their financial reporting obligations.

Recommendation:

The Department should:

  • in consultation with NSW Treasury, develop an appropriate statutory reporting framework for CLMs
  • ensure sufficient resources are available to help CLMs meet their reporting obligations.

During 2019–20, NSW Treasury established the reporting exemption criteria for the CLMs. Based on available information, the Department determined 31 CLMs would not meet the exemption criteria and therefore are required to prepare annual financial statements.

2. Audit observations

Internal controls

Six high‑risk issues were identified across the cluster in 2019–20:

  • 5 of those were related to financial reporting issues identified in Property NSW, Wentworth Park Sporting Complex Land Manager, Lord Howe Island Board, Planning Ministerial Corporation and Hunter and Central Coast Development Corporation
  • 1 issue was related to Lord Howe Island Board's outdated business continuity plan.

One in three internal control issues identified and reported to management in 2019–20 were repeat issues.

Recommendation:

Management letter recommendations to address internal control weaknesses should be actioned promptly, with a focus on addressing high‑risk and repeat issues.

Agencies response to recent emergencies

The unprecedented bushfires and COVID‑19 pandemic presented challenges for the cluster. Agencies established taskforces or response teams to respond to these emergencies.

With more staff working from home, agencies implemented protocols and procedures to manage risks associated with the remote working arrangements, and also needed to address certain technology issues.

The Department is responsible for the new Planning System Acceleration Program, which aims to fast‑track planning assessments, boost the State's economy and keep people in jobs during COVID‑19 pandemic. Between April and October 2020, the Department announced and determined 101 major projects and planning proposals.

Recognition of Crown land

Crown land is an important asset of the State. Management and recognition of Crown land assets is weakened when there is confusion over who is responsible for a particular Crown land parcel.

Auditor-General's Reports to Parliament since 2017 have recommended that the Department should ensure the database of Crown land is complete and accurate. Whilst the Department has commenced actions to improve the database, this remained an issue in 2019–20.

Recommendation (repeat issue):

The Department should prioritise action to ensure the Crown land database is complete and accurate. This allows state agencies and local councils to be better informed about the Crown land they control.

Implementation of Machinery of Government (MoG) changes

Since its creation on 1 July 2019, the Department has largely established its governance arrangements, including setting up the Audit and Risk Committee and internal audit function for the Department and relevant cluster agencies.

The Department still operated three main financial reporting systems in 2019–20, and has commenced the process to consolidate some of the systems.

The recent Regional NSW MoG change led to the transfer of $446 million net assets and $284 million 2019–20 budget from the Department to the newly created Department of Regional NSW on 2 April 2020.

 

This report provides parliament and other users of the Planning, Industry and Environment cluster agencies’ financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations
  • the impact of emergencies and the pandemic.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

The COVID‑19 Legislation Amendment (Emergency Measures–Treasurer) Act 2020 amended legislation administered by the Treasurer to implement further emergency measures as a result of the COVID‑19 pandemic. These amendments:

  • allowed the Treasurer to authorise payments from the Consolidated fund until the enactment of the 2020–21 budget – impacting the going concern assessments of cluster agencies
  • revised budgetary, financial and annual reporting time frames – impacting the timeliness of financial reporting
  • exempted certain statutory bodies and departments from preparing financial statements.

This chapter outlines our audit observations related to the financial reporting of agencies in the Planning, Industry and Environment cluster for 2020, including any financial implications from the recent emergency events.

Section highlights

  • Unqualified audit opinions were issued for all completed 30 June 2020 financial statements audits. Timeliness of financial reporting remains an issue for 13 agencies.
  • Significant deficiencies were identified in Property NSW's lease data maintenance and lease calculations. Cluster agencies can also improve their management of lease information provided by Property NSW.
  • The number of unprocessed Aboriginal land claims continued to increase. During 2020–21, a performance audit will assess the effectiveness and efficiency of the administration of Aboriginal land claims.

The Department has not yet developed a statutory reporting framework for Crown land managers and will need to provide additional resources to help Crown land managers meet their financial reporting obligations.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our:

  • observations and insights from our financial statements audits of agencies in the Planning, Industry and Environment cluster
  • assessment of how well cluster agencies adapted their systems, policies and procedures, and governance arrangements in response to recent emergencies
  • review of how the cluster agencies managed the increased risks associated with new programs aimed at stemming the spread of COVID-19 and stimulating the economy.

Cluster agencies experienced a range of control and governance related issues in recent years. An increased number of high risk issues and greater proportion of repeat issues were identified as part of our audits. It is important for cluster agencies to promptly address these issues.

Section highlights

  • Six high risk issues were identified during 2019–20 audits. One in three issues identified and reported to management in 2019–20 were repeat issues.
  • The Department has fast tracked the assessment and determination of 101 projects as a part of the Planning System Acceleration Program.
  • There continues to be significant deficiencies in Crown land records. The Department should ensure the Crown land database is complete and accurate.