Actions for Design and administration of the WestInvest program

Design and administration of the WestInvest program

Premier and Cabinet
Treasury
Infrastructure
Management and administration

What this report is about

WestInvest is a $5 billion funding program announced in September 2021 to provide ‘local infrastructure to help communities hit hard by COVID-19’ in 15 local government areas (LGAs) selected by the government. It was divided into three parts: $3 billion for NSW government agency projects; $1.6 billion for competitive grants to councils and community groups; and $400 million for non-competitive grants to councils.

Following the change of government at the 2023 election, the program was renamed the Western Sydney Infrastructure Grants Program. Funding decisions made for the community and local government grants were retained, but multiple funding decisions for the NSW government projects were changed.

The audit objective was to assess the integrity of the design and implementation of the program and the award of program funding.

Findings

The design of the program lacked integrity because it was not informed by robust research or analysis to justify the commitment of public money to a program of this scale.

The then government did not have sufficient regard to the implications for the state's credit rating. A risk to the credit rating arose because the government may have been perceived to be using proceeds from major asset sales to fund new expenditure, rather than pay down its debt.

Decisions about program design were made by the then Treasurer's office without consultation with affected communities. The rationale for these decisions was not documented or made public.

For the NSW government projects, funding allocations did not follow advice from departments. Many funded projects did not meet the objectives of the program.

The two other rounds of the program were administered effectively, except for some gaps in documentation and quality assurance. The program guidelines did not require an equitable or needs-based distribution of funding across LGAs and there was a significant imbalance in funding between the 15 LGAs.

Recommendations

Our recommendations for the administration of future funding programs included:

  • considering whether competitive grants are the best way to achieve the program's purpose
  • completing program design and guidelines before announcements
  • ensuring adequate quality assurance.

We also recommended that when providing advice for submissions by Ministers to Cabinet, agencies should ensure that departmental advice is clearly identified and is distinct from other advice or political considerations. 

 

WestInvest is a $5 billion funding program that was announced in September 2021. The program was established with the stated aim of building ‘new and improved facilities and local infrastructure to help communities hit hard by COVID-19’.

WestInvest was divided into three funding streams:

  • $3 billion NSW government projects round open to NSW government agencies
  • $1.6 billion community projects competitive round administered as a competitive grant program that was open to local councils, non-government organisations, Local Aboriginal Land Councils, and educational institutions in the 15 eligible LGAs
  • $400 million local government projects round administered as a non-competitive grant round only open to the 15 eligible councils, with each council receiving a pre-determined share of the $400 million.

The WestInvest program was administered by NSW Treasury and the Premier's Department (previously the Department of Premier and Cabinet). Decisions about funding allocations were made by the former Treasurer in his role as the statutory decision-maker and announced by the former government in the lead up to the March 2023 NSW State election, but no funding was paid prior to the election.

Following the change of government, the funding decisions for the community projects competitive round and local government projects round were confirmed and negotiation of funding deeds commenced. The current government reviewed the decisions for the NSW government projects round and made changes to multiple decisions as part of the 2023–24 NSW Budget process. The current government has also changed the name of the program to the Western Sydney Infrastructure Grants Program.

The objective of the audit was to assess the integrity of the design and administration of the WestInvest program. This included assessing the processes used in the design and implementation of the program and award of funding.

The audit did not re-assess the merits of individual projects that were submitted for funding consideration and did not examine the implementation of projects that were allocated funding.

Decisions about the objectives and focus areas for the program were made without advice or analysis from the agencies that administered the program

The WestInvest program involved the commitment of $5 billion as a stimulus measure linked to economic recovery from the COVID-19 pandemic. However, there was no business case or other economic analysis conducted to support consideration of the potential benefits and costs of the program. Media releases and the public guidelines for WestInvest stated that western Sydney was affected by the COVID-19 pandemic more severely than other parts of Sydney and regional NSW. These assertions were not supported by evidence or analysis.

Evidence from NSW Treasury provided for this audit indicates that it was asked to prepare the initial proposal for the WestInvest program within a very short timeframe. This limited its ability to conduct research, analysis and consultation that could have informed the development of the program. This is particularly important for the integrity of decisions involving large-scale spending. Staff from NSW Treasury and the Premier's Department advised the audit team that the areas of focus for WestInvest were decided by Ministers and their staff without advice from the audited agencies. There is no documented analysis justifying the decision to focus the program on community infrastructure, or the six ‘areas of focus’ that were selected. The Premier's Department commissioned research from Western Sydney University after the areas of focus for the program had been decided. This did not inform decisions about the program focus but aimed to provide baseline information about community infrastructure in the 15 eligible LGAs which could be used in program evaluation.

The rationale for making 15 LGAs eligible for the program was not clear

It is not clear how the government decided which LGAs would be eligible for WestInvest funding. Public communication about the program referred to the western Sydney region and commented on areas that had been ‘hit hard’ by the COVID-19 pandemic. The specific factors that were used to decide which LGAs were eligible were not explained publicly or documented.

In the 2019–20 NSW Budget papers, "western Sydney" was defined as 12 LGAs. All of these were included as eligible for the WestInvest program. The additional three LGAs that were made eligible for the WestInvest program (Burwood, Canterbury-Bankstown, and Strathfield) were not within the NSW Budget papers definition but were designated "areas of concern" during the COVID-19 pandemic, which meant they were subject to more restrictions than other LGAs at certain points.

Georges River and Bayside LGAs both made public statements that drew attention to the fact that they were not made eligible for the WestInvest program despite being designated areas of concern. Several of the 15 LGAs that were made eligible for WestInvest had not been designated areas of concern during the pandemic, including Penrith, The Hills, and Blue Mountains. 

There was no consultation with eligible councils or other key stakeholders before the program design was decide

The program design had not been subject to consultation with councils or other relevant organisations in western Sydney. This meant that the views of eligible councils and community organisations on strategic priorities in their respective communities were not considered before decisions on program design were made.

Staff from some councils interviewed by the audit team indicated that while funding for community infrastructure is welcome, some councils had other priority areas for infrastructure development that were at least as high as new community infrastructure. As independent entities, each council has its own strategic planning processes to identify and plan for infrastructure projects and other areas of need. These were not considered in the design of the WestInvest program.

Staff at several councils we spoke to highlighted delivery risks to the projects for which they had been allocated funding. These included:

  • the short timetable set by the then government (considering the amount of funding available and the requirements for applications) meant that full project development and assurance processes were not completed for most applications when they were submitted
  • difficulty complying with the government’s administrative and assurance requirements for funding recipients, such as detailed planning and reporting.

When early planning for WestInvest was being done, both NSW Treasury and the Premier's Department identified the risk that applicants may not be able to deliver funded projects on time or within budget. The absence of consultation, research and analysis before the program design was finalised meant that these factors were not considered before the government had committed to the program. We did not see evidence that the then government had considered the cumulative impact of an additional $5 billion in infrastructure projects on the costs of materials and skilled labour concentrated in the eligible LGAs.

The Premier's Department conducted an online survey (WestInvest 'Have Your Say'), between 23 February 2022 and 31 March 2022. This was open to the public and asked questions about which of the six ‘areas of focus’ were most important to them and what type of community infrastructure projects they would like to see. This found higher levels of community support for two of the six areas (community infrastructure and green and open space).

On 18 April 2022, the Premier's Department released a summary report on the findings of the WestInvest ‘Have Your Say’ Survey. The Premier's Department noted that the survey was for consultation purposes only and did not form part of the application process for the WestInvest program. The Premier's Department stated in its summary report that the survey results 'will feed into the assessment process across the WestInvest Program'.

However, the Premier's Department staff interviewed by the audit team told us that the survey results did not play any formal role in the assessment process or funding recommendations for projects. The survey did not provide data that could be used to inform assessment decisions because:

  • responses could be submitted by any member of the public who accessed the survey, not just those living in the LGAs that were eligible for the program, so the data could not be taken as representative of the views of the residents of eligible LGAs
  • many survey responses were ruled ineligible as they were deemed to be associated with a community campaign that related to projects outside the focus areas of WestInvest.

The government did not have sufficient regard to risks to the State's credit rating when establishing the WestInvest program

The NSW Government has a policy of maintaining a AAA credit rating for the State of New South Wales. This is codified in the Fiscal Responsibility Act 2012. The NSW Government did not have sufficient regard to the implications and risks of committing $5 billion of funding to the WestInvest program to its credit rating. A risk to the State's credit rating arose because the government may have been perceived to be using proceeds from major asset sales to fund new expenditure, rather than paying down State debt.

The $3 billion NSW government projects round was open to NSW government agencies and administration of the round was led by NSW Treasury. Funding allocated through this round was not subject to the NSW Grants Administration Guide. This is because the funding was awarded to NSW government agencies rather than organisations external to government, so it did not meet the definition of a grant program. Projects were submitted by NSW government agencies to NSW Treasury and were assessed against program criteria by staff from NSW Treasury and the Premier's Department. Each project received a score and advice on whether it was suitable for funding or not. The WestInvest steering committee considered these and provided advice to the then Treasurer.

NSW Treasury prepared guidelines for the $3 billion NSW government projects round, but these were not approved by the then Treasurer until after the program assessment had commenced

NSW Treasury prepared guidelines for the NSW government projects round in September 2021. These were submitted to the then Treasurer for approval in December 2021 but were not approved. This meant that the process for assessing applications for NSW government projects was not agreed between government agencies and the then Treasurer, who was the statutory decision-maker of the allocations of funding. NSW Treasury subsequently prepared an assessment plan based on the unapproved guidelines, which set out more details about the process to be used for assessing applications for the NSW government projects round. The program guidelines were not published, which meant there was no public information about the process for assessing the largest component of the WestInvest program.

In May 2022, the then Treasurer’s Office requested that NSW Treasury make changes to the unapproved guidelines so that projects that delivered 'business as usual' state government infrastructure such as schools, roads, and health infrastructure were no longer considered ineligible for the program. These revised guidelines were approved in June 2022, but were not published. The changes were not consistent with the initial purpose of the WestInvest program which was to fund ‘transformational’ community infrastructure.

The funding advice from the WestInvest steering committee was not followed by the then Treasurer and the justifications for the funding allocation decisions were not documented

One-third of the projects that were allocated funding (9 out of 27) had been assessed by the WestInvest steering committee as having low or moderate merit. These projects were allocated combined funding of $1.1 billion. Reasons that the steering committee gave for assessing these projects as not suitable for funding through the WestInvest program included the absence of completed business cases, incomplete project development, and poor alignment to the objectives and criteria for the WestInvest program as outlined in the original program guidelines.

Staff from NSW Treasury and the Premier's Department put considerable resources into preparing guidelines and assessing and providing advice on the merits and eligibility of applications against these guidelines, but in most cases the advice was not followed by the then Treasurer. There was no documentation of reasons for the departures from steering committee advice. The NSW government projects round was not subject to the NSW Grants Administration Guide, so the requirement under those guidelines for documenting reasons for departures from advice on funding decisions did not apply. However, when the WestInvest program was established, it was noted that any departures from the funding advice from the steering committee would be documented by the then Treasurer. This applied to the entire WestInvest program. None of the projects that were allocated funding through the NSW government projects round were actually given funding, as only allocations of funding were approved by the then Treasurer.

Most of the funding was allocated to projects that did not align with the purpose of WestInvest or meet the assurance requirements of the program

Of the 27 projects that were allocated funding (Exhibit 3), 12 were from the Department of Education and seven from Transport for NSW. This resulted in over $2 billion, or 69% of the funding available through the NSW government projects round, being allocated to state school and road projects. Most of these projects were not aligned with any of the six focus areas of the WestInvest program. In addition, these projects were examples of ‘business as usual’ activities of NSW government agencies that did not clearly align with the initial purpose of the program to deliver transformational community infrastructure that would improve liveability in the 15 eligible LGAs.

Exhibit 3: NSW government projects round funding allocations announced prior to the 2023 NSW State election

State schools

  • Upgrade nine public schools across western Sydney ($478 million)
  • Improve cooling in 84 public schools across western Sydney ($131 million
  • Westmead Education Campus ($308 million)
  • Box Hill (Terry Road) new school ($112 million)

State roads

  • M7 Motorway connections - Townson Road and Richmond Road ($285 million)
  • Elizabeth Drive upgrade ($200 million)
  • Henry Lawson Drive stage 1B ($200 million)
  • Richmond Road Marsden Park ($100 million)
  • Garfield Road east ($100 million)
  • Pitt Town bypass ($100 million)
  • Londonderry Road flood evacuation improvements ($15 million)

Health

  • Integrated community health hubs in Liverpool and Glenfield ($243 million)

Open spaces

  • Australian Botanic Garden Mount Annan masterplan stage 1 ($204 million)
  • Salt Pan Creek parklands ($86 million)
  • Fernhill Estate transformation ($65 million)
  • The People's Loop Parramatta ($56 million)
  • Penrith Lakes parkland ($15 million)

Arts and community infrastructure

  • Transforming Parramatta's Roxy Theatre ($122 million)
  • Western Sydney Stadium precinct community-based asset ($111 million).

Source: NSW Treasury documents.

Conditions were attached to the approval of funding allocations for 21 of the 27 projects. Most of these conditions related to the completion of a business case and other project assurance requirements, which were required under the program guidelines.

Projects approved through the WestInvest program were to receive funding from the Community Services and Facilities Fund (CSFF), which is a legislative fund created under the NSW Generations Funds Act 2018 (the Act). The Act states that the purpose of the CSFF is to provide funding for ‘cost-effective facilities and services’ (s.12(1)). The absence of business cases and other assurance requirements from most of the projects approved created the risk of legislative non-compliance, as many of the projects that had been allocated funding could not clearly demonstrate that they would be cost-effective.

NSW Treasury and the Premier's Department’s assessment of the first group of projects submitted for the NSW government projects round indicated that agencies applying for funding did not understand the purpose or requirements of the program. NSW Treasury and the Premier's Department received 153 applications after the first call for proposals. Most did not align with the stated purpose of WestInvest or meet the assurance requirements that had been set for the program. For example:

  • 90 project proposals (59% of those submitted) were assessed as ineligible. Thirty-five of the 90 did not include any infrastructure, which was the main purpose of the WestInvest program. The other 55 proposed infrastructure projects were not consistent with any of six areas of focus for the program.
  • 118 proposals (77% of proposals submitted) did not have a business case, which was a requirement of the WestInvest program guidelines.

As the first request for project proposals did not generate enough suitable applications, the then Treasurer made a second request to NSW government agencies in August 2022 seeking additional project proposals. This occurred after the guidelines for the NSW government projects round had been broadened to allow more projects to be considered for funding (discussed above).

Multiple state school projects were allocated funding after being assessed by the WestInvest steering committee as ineligible or unsuitable for funding

The Westmead Education Campus project, valued at $308 million, was rated as ineligible by NSW Treasury and the Premier's Department because it did not address any of the six specified focus areas for the WestInvest program. This meant it did not go through a full assessment against the program criteria and was not submitted to the then Treasurer for funding consideration.

The project was later re-submitted and the then Treasurer subsequently approved it for funding allocation. This occurred after the guidelines for the NSW government projects round had been broadened (discussed above). NSW Treasury's advice on this submission noted that the project had not been fully developed, with key decisions about the delivery model not made, and it did not have a final business case.

The Box Hill (Terry Road) new school project, valued at $112 million was rated as ‘moderate – not suitable for funding consideration at this time’ by the WestInvest steering committee. It was subsequently approved for funding by the then Treasurer.

Nine school upgrade projects with a total value of $478 million were allocated funding by the then Treasurer. Each of these had been assessed as ineligible by NSW Treasury and the Premier's Department against the original program guidelines because they did not meet any of the WestInvest focus areas and were not considered 'transformational'. There were a further 14 similar proposals for school upgrades that were also assessed as ineligible but were not allocated funding.

Funding allocations from the WestInvest program were changed after the 2023 NSW State election

Following the change of government at the 2023 NSW state election, most of the funding decisions announced by the former government were changed. The new government had announced during the election campaign that, if elected, it would redirect some WestInvest funding 'to rebuild Western Sydney schools and Western Sydney hospitals'. Eleven of the 27 projects that had been announced by the former government were not funded by the new government. The combined value of these projects was at around $1.5 billion (Exhibit 4). The seven roads projects that had been allocated funding through WestInvest, valued at $1 billion, were also removed from the WestInvest funding allocation but these still received funding from a different source.

Exhibit 4: Projects from the NSW government projects round not funded post-2023 NSW State election

State schools

  • Improve cooling in 84 public schools across western Sydney ($131 million)
  • Westmead Education Campus ($308 million)
  • Box Hill (Terry Road) new school ($112 million)

Health

  • Integrated community health hubs in Liverpool and Glenfield ($243 million)

Open spaces

  • Australian Botanic Garden Mount Annan masterplan stage 1 ($204 million)
  • Salt Pan Creek parklands ($86 million)
  • Fernhill Estate transformation ($65 million)
  • The People's Loop Parramatta ($56 million)
  • Penrith Lakes parkland ($15 million)

Arts and community infrastructure

  • Transforming Parramatta's Roxy Theatre ($122 million)
  • Western Sydney Stadium precinct community-based asset ($111 million).

Source: NSW Treasury documents.

The funding was reallocated to 17 projects that the new government had announced as election commitments during the 2023 State election campaign. This comprised ten school infrastructure projects, five health infrastructure projects, and two transport infrastructure projects. All of these projects had a cost of more than $10 million each, which means they are subject to NSW Government business case and gateway assurance requirements. Business cases had been completed for the two transport projects. The other 15 projects did not have business cases.

Exhibit 5: Election commitments funded through WestInvest, post-2023 NSW State election

State schools

  • New primary school near Sydney Olympic Park ($71 million)
  • New high school for Melrose Park ($98 million)
  • Convert Eagle Vale High School into a sports high school ($4 million)
  • Build new high school in Jordan Springs ($132 million)
  • Dundas Public School upgrade ($6 million)
  • New high school for Schofields and Tallawong ($130 million)
  • The Ponds High School upgrade ($15 million)
  • New public high school in Gledswood and Gregory Hills ($118 million)
  • New high school in Leppington/Denham Court ($125 million)
  • Kingswood Public School upgrades ($13 million)

Health

  • Additional beds at Mt Druitt Hospital ($60 million)
  • Additional beds at Blacktown Hospital ($60 million)
  • Expansion of Scope of new Rouse Hill Hospital ($400 million)
  • Canterbury Hospital extension and upgrade ($350 million)
  • Fairfield Hospital extension and upgrade ($350 million)

Transport

  • More accessible, safe and secure train stations ($300 million)
  • Active Transport ($60 million)

Source: NSW Treasury documents.

After these changes, the $3 billion NSW government projects round funding distribution was:

  • Nine school upgrades, valued at $478 million, that had been allocated funding by the former government (see Exhibit 3).
  • 17 new projects, with a total value of around $2.3 billion, that had been announced as election commitments by the new government (Exhibit 5). All of these are state school, health, or transport infrastructure.
  • Three projects that covered administrative costs associated with the WestInvest program, with a total value of around $230 million (not previously announced).

The $1.6 billion community project grants - competitive round was open to local councils, NGOs, Local Aboriginal Land Councils, and educational institutions, across 15 eligible LGAs in western Sydney. Exhibit 6 shows a timeline of key dates for the community project grants - competitive round.

The $400 million local government projects round was administered as a non-competitive grant round that was only open to the 15 eligible councils. Each council was allocated a portion of the $400 million funding via a formula that provided a base allocation and an additional amount based on the population of each LGA. Each council received between $21 million and $35 million.

Applications for funding were submitted to the Premier's Department for assessment. Proposed projects were required to be eligible for the program and be rated as having merit against the published program criteria, which were the same as those for the competitive round. Exhibit 12 shows a timeline of key dates for the Local government projects competitive round.

Appendix one – Responses from audited agencies

Appendix two – About the audit

Appendix three – Performance auditing

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #391 - released 28 February 2024.

 

 

Published

Actions for Transport 2023

Transport 2023

Transport
Whole of Government
Asset valuation
Compliance
Financial reporting
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Risk

What this report is about

Result of the Transport portfolio of agencies' financial statement audits for the year ended 30 June 2023.

The audit found

Unqualified audit opinions were issued for all Transport portfolio agencies.

An 'emphasis of matter' paragraph was included in the Transport Asset Holding Entity of New South Wales' (TAHE) independent auditor's report, which draws attention to management's disclosure regarding proposed changes to TAHE's operating model.

Government's decision to convert TAHE into a non-commercial Public Non-Financial Corporation may impact the future valuation and the control of TAHE's assets.

Transport for NSW's valuation of roads and bridges resulted in a net increase to its asset value by $15.7 billion.

Transport for NSW and Sydney Metro have capitalised over $300 million of tender bid costs paid to unsuccessful tender bidders relating to significant infrastructure projects. Whilst NSW Treasury policy provides clarity on the reimbursement of unsuccessful bidders' costs, clearer guidance on how to account for these costs in agency's financial statements is required.

The key audit issues were

The number of issues reported to management decreased from 53 in 2021–22 to 49 in 2022–23.

High-risk findings include:

  • gaps in how Sydney Metro manages its contractors and how conflicts of interest are recorded and managed
  • future financial reporting implications to account for government's proposed changes to TAHE's future operating model, including asset valuations and control assessments of assets and operations
  • Parramatta Park Trust's tree assets' valuation methodology needs to be addressed.

Recommendations were made to address the identified deficiencies.

This report provides Parliament and other users of the Transport portfolio of agencies’ financial statements with the results of our audits, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Transport portfolio of agencies (the portfolio) for 2023.

Section highlights

  • Unqualified audit opinions were issued on all the portfolio agencies’ 30 June 2023 financial statements.
  • An 'Emphasis of Matter' paragraph was included in the Transport Asset Holding Entity of New South Wales’ (TAHE) Independent Auditor's Report to draw attention to management's disclosure regarding the proposed changes to TAHE's future operating model.
  • The total number of errors (including corrected and uncorrected) in the financial statements increased by 59% compared to the prior year.
  • The recent government's decision to convert TAHE into a non-commercial Public Non-Financial Corporation may impact the future valuation and the control of TAHE’s assets.
  • Transport for NSW needs to further improve its quality assurance processes over comprehensive valuations, in particular, ensuring key inputs used in the valuations are properly supported and verified.
  • Transport for NSW and Sydney Metro capitalised over $300 million of bid costs paid to unsuccessful bidders. NSW Treasury’s Bid Cost Contributions Policy does not contemplate how these costs should be recognised in agency’s financial statements. Transport agencies should work with NSW Treasury to develop an accounting policy for the bid cost contributions to ensure consistent application across the sector.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision-making.
This chapter outlines our observations and insights from our financial statement audits of agencies in the Transport portfolio.

Section highlights

  • The 2022–23 audits identified four high risks and 28 moderate risk issues across the portfolio. Thirty-nine per cent of issues were repeat findings.
  • Four high risk findings include:
    • TAHE’s asset valuations (new)
    • TAHE’s control of assets and operations (new)
    • Sydney Metro’s management of contractors and conflicts of interest (new)
    • Parramatta Park Trust’s valuation of trees (repeat).
  • The total number of findings decreased from 53 in 2021–22 to 49 in 2022–23. Many repeat findings related to control weaknesses over the asset valuation, payroll processes, conflicts of interest and information technology user access administration.


Appendix one – Misstatements in financial statements submitted for audit 

Appendix two – Early close procedures

Appendix three – Timeliness of financial reporting 

Appendix four – Financial data 

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Enterprise, Investment and Trade 2023

Enterprise, Investment and Trade 2023

Finance
Asset valuation
Compliance
Cyber security
Financial reporting
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Regulation
Risk

What this report is about

Results of the Enterprise, Investment and Trade portfolio of financial statement audits for the year ended 30 June 2023.

What we found

Unqualified audit opinions were issued for all completed Enterprise, Investment and Trade portfolio agencies.

An 'other matter' paragraph was included in the Jobs for NSW Fund's 30 June 2022 independent auditor's report to reflect the non-compliance with the Jobs for NSW Act 2015 (the Act). The Act requires the board to consist of seven members that include the Secretary of the Treasury, the Secretary of the Premier's Department, and five ministerial appointments. The board has consisted of two secretaries since 24 May 2019 when the independent members resigned. The remaining five members have not been appointed by the ministers as required by section 5(2) of the Act.

Financial statements were not prepared for the Responsible Gambling Fund, a special deposit account. Financial statements should be prepared unless NSW Treasury releases a Treasurer's Direction under section 7.8 of the GSF Act that will exempt the SDA from financial reporting requirements.

What the key issues were

The number of issues reported to management decreased from 65 in 2021–22 to 44 in 2022–23. Forty-six per cent of issues were repeated from the prior year.

Two high-risk issues were identified across the portfolio. One was a repeat issue where the Jobs for NSW Fund did not comply with legislation. The other high-risk issue was first identified in 2022–23 when the Department for Enterprise, Investment and Trade incorrectly recorded grants that did not meet the requirements of Australian Accounting Standards.

What we recommended

The Department should develop a robust model to ensure it only provides for grants that meet the eligibility criteria.

This report provides Parliament and other users of the Enterprise, Investment and Trade portfolio of agencies’ financial statements with the results of our audits, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision-making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Enterprise, Investment and Trade portfolio of agencies (the portfolio) for 2023.

Section highlights

  • Unqualified audit opinions were issued on all completed portfolio agencies’ 2022–23 financial statements.
  • An ‘other matter’ paragraph was included for the Jobs for NSW Fund’s 30 June 2022 financial report to reflect non-compliance with the Jobs for NSW Act 2015.
  • The Act requires the board to consist of seven members that include the Secretary of the Treasury, the Secretary of the Department of Premier and Cabinet (or their nominees) and five ministerial appointments, one of whom is to be appointed as Chair of the board. The board has consisted of the two secretaries since 24 May 2019 when the independent members resigned. The remaining five members have not been appointed by the ministers as required by section 5(2) of the Act.
  • An ‘emphasis of matter’ paragraph was included in the Jobs for NSW Fund’s 30 June 2022 financial report to draw attention to the financial report being prepared for the purpose of fulfilling the Jobs for NSW Fund’s financial reporting responsibilities as requested by the Treasurer’s delegate.
  • The total number of errors (including corrected and uncorrected) in the financial statements increased by 12% compared to the prior year.
  • The Responsible Gambling Fund (Special Deposit Account) did not prepare financial statements for the year ended 30 June 2023. Financial statements should be prepared unless NSW Treasury releases a Treasurer’s Direction under section 7.8 of the GSF Act that will exempt the Fund from financial reporting requirements. 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision-making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the Enterprise, Investment and Trade portfolio.

Section highlights

  • The audits identified two high-risk and 20 moderate risk issues across the portfolio. Of these, one was a high-risk repeat issue and ten were moderate-risk repeat issues.
  • One of the high-risk matters related to the Jobs for NSW Fund audit for the year ended 30 June 2022.
  • The other high-risk matter related to overstating grants relating to the Jobs Plus Program as the criteria to pay the grant was not met at 30 June 2023.
  • The total number of findings decreased from 65 to 44 with 2022–23 findings mainly related to deficiencies in accounting for property, plant and equipment and agencies having outdated policies. 

Appendix one – Misstatements in financial statements submitted for audit

Appendix two – Early close procedures

Appendix three – Timeliness of financial reporting

Appendix four – Financial data

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Management of the Critical Communications Enhancement Program

Management of the Critical Communications Enhancement Program

Finance
Health
Justice
Whole of Government
Cyber security
Information technology
Infrastructure
Internal controls and governance
Project management
Risk
Service delivery
Shared services and collaboration

What the report is about

Effective radio communications are crucial to NSW's emergency services organisations.

The Critical Communications Enhancement Program (CCEP) aims to deliver an enhanced public safety radio network to serve the five emergency services organisations (ESOs), as well as a range of other users.

This report assesses whether the NSW Telco Authority is effectively managing the CCEP.

What we found

Where it has already been delivered (about 50% of the state), the enhanced network meets most of the requirements of ESOs.

The CCEP will provide additional infrastructure for public safety radio coverage in existing buildings agreed to with ESOs. However, radio coverage inside buildings constructed after the CCEP concludes will be at risk because building and fire regulations do not address the need for in-building public safety radio coverage.

Around 98% of radios connected to the network can be authenticated to protect against cloning, though only 42% are.

The NSW Telco Authority has not settled with ESOs on how call encryption will be used across the network. This creates the risk that radio interoperability between ESOs will not be maximised.

When completed, the public safety radio network will be the only mission critical radio network for ESOs. It is unclear whether governance for the ongoing running of the network will allow ESOs to participate in future network operational decisions.

The current estimated capital cost for the NSW Telco Authority to complete the CCEP is $1.293 billion. This is up from an estimated cost of $400 million in 2016. The estimated capital cost was not publicly disclosed until $1.325 billion was shown in the 2021–22 NSW Budget Papers.

We estimate that the full cost to government, including costs to the ESOs, of implementing the enhanced network is likely to exceed $2 billion.

We made recommendations about

  • The governance of the enhanced Public Safety Network (PSN) to support agency relationships.
  • The need to finalise a Traffic Mitigation Plan for when the network is congested.
  • The need to provide advice to the NSW Government about the regulatory gap for ensuring adequate network reach in future buildings.
  • The need to clarify how encryption and interoperability will work on the enhanced network.
  • The need for the NSW Telco Authority to comply with its policy on Infrastructure Capacity Reservation.
  • Expediting measures to protect against the risk of cloning by unauthenticated radios.

Public safety radio networks are critical for operational communications among Emergency Services Organisations (ESOs), which in New South Wales include:

  • NSW Ambulance
  • Fire and Rescue NSW
  • NSW Police Force
  • NSW Rural Fire Service
  • NSW State Emergency Service.1

Since 1993, these five ESOs have had access to a NSW Government owned and operated radio communications network, the Public Safety Network (PSN), to support their operational communications. Around 60 to 70 other entities also have access to this network, including other NSW government entities, Commonwealth government entities, local councils, community organisations, and utility companies.

Pursuant to the Government Telecommunications Act 2018 ('the Act'), the New South Wales Government Telecommunications Authority ('NSW Telco Authority') is responsible for the establishment, control, management, maintenance and operation of the PSN.2

Separate to the PSN, all ESOs and other government entities have historically maintained their own radio communication capabilities and networks. Accordingly, the PSN has been a supplementary source of operational radio communications for these entities.

These other radio networks maintained by ESOs and other entities are of varying size and capability, with many ageing and nearing their end-of-life. There was generally little or no interoperability between networks, infrastructure was often co-located and duplicative, and there were large gaps in geographic coverage.

In 2016, the NSW Telco Authority received dedicated NSW Government funding to commence the Critical Communications Enhancement Program (CCEP).

According to NSW Telco Authority's 2021–22 annual report, the CCEP is a transformation program for operational communications for NSW government agencies. The CCEP '…aims to deliver greater access to public safety standard radio communications for the State’s first responders and essential service agencies'. The objective of CCEP is to consolidate the large number of separate radio networks that are owned and operated by various NSW government entities and to enhance the state’s existing shared PSN. The program also aims to deliver increased PSN coverage throughout New South Wales.

The former NSW Government intended that as the enhanced PSN was progressively rolled-out across NSW, ESOs would migrate their radio communications to the enhanced network, before closing and decommissioning their own networks.

About this Audit

This audit assessed whether the CCEP is being effectively managed by the NSW Telco Authority to deliver an enhanced PSN that meets ESOs' requirements for operational communications.

We addressed the audit objective by answering the following two questions:

  1. Have agreed ESO user requirements for the enhanced PSN been met under day-to-day and emergency operational conditions?
  2. Has there been adequate transparency to the NSW Government and other stakeholders regarding whole-of-government costs related to the CCEP?

In answering the first question, we also considered how the agreed user requirements were determined. This included whether they were supported by evidence, whether they were sufficient to meet the intent of the CCEP (including in considering any role for new or alternative technologies), and whether they met any relevant technical standards and compliance obligations (including for cyber security resilience).

While other NSW government agencies and entities use the PSN, we focused on the experience of the five primary ESOs because these will be the largest users of the enhanced PSN.

Both the cost and time required to complete the CCEP roll-out have increased since 2016. While it was originally intended to be completed in 2020, this is now forecast to be 2027. Infrastructure NSW has previously assessed the reasons for the increases in time and cost. A summary of the findings made by Infrastructure NSW is presented in Chapter 1 of this report. Accordingly, as these matters had already been assessed, we did not re-examine them in this performance audit.

The auditee for this performance audit is the NSW Telco Authority, which is a statutory authority within the Department of Customer Service portfolio.

In addition to being responsible for the operation of the PSN, section 5 of the Act also prescribes that the NSW Telco Authority is:

  • to identify, develop and deliver upgrades and enhancements to the government telecommunications network to improve operational communications for government sector agencies
  • to develop policies, standards and guidelines for operational communications using telecommunications networks.

The NSW Telco Authority Advisory Board is established under section 10 of the Act. The role of the board is to advise the NSW Telco Authority and the minister on any matter relating to the telecommunications requirements of government sector agencies and on any other matter relating to the functions of the Authority. As of 2 June 2023, the responsible minister is the Minister for Customer Service and Digital Government.

The five identified ESOs are critical stakeholders of the CCEP and therefore they were consulted during this audit. However, the ESOs were not auditees for this performance audit.

Conclusion

In areas of New South Wales where the enhanced Public Safety Network has been implemented under the Critical Communications Enhancement Program, the NSW Telco Authority has delivered a radio network that meets most of the agreed requirements of Emergency Services Organisations for routine and emergency operations.
In April 2023, the enhanced Public Safety Network (PSN) was approximately 50% completed. In areas where it is used by Emergency Services Organisations (ESOs), the PSN generally meets agreed user requirements. This is demonstrated through extensive performance monitoring and reporting, which shows that agreed performance standards are generally achieved. Reviews by the NSW Government and the NSW Telco Authority found that the PSN performed effectively during major flood events in 2021 and 2022.

Where it is completed, PSN coverage is generally equal to or better than each ESO's individual pre-existing coverage. The NSW Telco Authority has a dedicated work program to address localised coverage gaps (or 'blackspots') in those areas where coverage has otherwise been substantively delivered. Available call capacity on the network far exceeds demand in everyday use. Any operational issues that may occur with the PSN are transparent to ESOs in real time.

The NSW Telco Authority consulted extensively with ESOs on requirements for the enhanced PSN, with relatively few ESO requirements not being included in the specifications for the enhanced PSN. Lessons from previous events, including the 2019–20 summer bushfires, have informed the design and implementation of the enhanced PSN (such as the need to ensure adequate backup power supply to inaccessible sites). The network is based on the Project 25 technical standards for mission-critical radio communications, which is widely-accepted in the public safety radio community throughout Australia and internationally.

There is no mechanism to ensure adequate radio coverage within new building infrastructure after the CCEP concludes, but the NSW Telco Authority and ESOs have agreed an approach to prioritise existing in-building sites for coverage for the duration of the CCEP.
The extent to which the PSN works within buildings and other built structures (such as railway tunnels) is of crucial importance to ESOs, especially the NSW Police Force, NSW Ambulance, and Fire and Rescue NSW. This is because a large proportion of their operational communications occurs within buildings.

There is no mechanism to ensure the adequacy of future in-building coverage for the PSN in new or refurbished buildings after the CCEP concludes. Planning, building, and fire regulations are silent on this issue. We note there are examples in the United States of how in-building coverage for public safety radio networks can be incorporated into building or fire safety codes.

In regard to existing buildings, it is not possible to know whether a building requires its own in-building PSN infrastructure until nearby outside radio sites, including towers and antennae, have been commissioned into the network. Only then can it be determined whether their radio transmissions are capable of penetrating inside nearby buildings. Accordingly, much of this work for in-building coverage cannot be done until outside radio sites are finished and operating.

In March 2023, the NSW Telco Authority and ESOs agreed on a list of 906 mandatory and 7,086

non-mandatory sites for in-building PSN coverage. Most of these sites will likely be able to receive radio coverage via external antennae and towers, however this cannot be confirmed until those nearby external PSN sites are completed. The parties also agreed on an approach to prioritising those sites where coverage is needed but not provided by antennae and towers. Available funding will likely only extend to ensuring coverage in sites deemed mandatory, which is nonetheless expected to meet the overall benchmark of achieving 'same or better' coverage than what ESOs had previously.

There is a risk that radio interoperability between ESOs will not be maximised because the NSW Telco Authority has not settled with ESOs how encryption will be used across the enhanced PSN.
End-to-end encryption of radio transmissions is a security feature that prevents radio transmissions being intercepted or listened to by people who are not meant to. The ability of the PSN to provide end-to-end encryption of operational communications is of critical importance to the two largest prospective users of the PSN: the NSW Police Force and NSW Ambulance. Given that encryption excludes other parties that do not have the requisite encryption keys, its use creates an obstacle to achieving a key intended benefit of the CCEP, that is a more interoperable PSN, where first responders are better able to communicate with other ESOs.

Further planning and collaboration between PSN participants are necessary to consider how these dual benefits can be achieved, including in what operational circumstances encrypted interoperability is necessary or appropriate.

The capital cost to the NSW Telco Authority of the CCEP, originally estimated at $400 million in 2016, was not made public until the 2021–22 NSW Budget disclosed an estimate of $1.325 billon.
The estimated capital cost to complete all stages of the CCEP increased over time. This increasing cost was progressively disclosed to the NSW Government through Cabinet processes between 2015–16 and 2021–22.

In 2016, the full capital cost to the NSW Telco Authority of completing the CCEP was estimated to be $400 million. This estimated cost was not publicly disclosed, nor were subsequent increases, until the cost of $1.325 billion was publicly disclosed in the 2021–22 NSW Budget (revised down in the 2022–23 NSW Budget to $1.293 billion).

There has been no transparency about the whole-of-government cost of implementing the enhanced PSN through the CCEP.
In addition to the capital costs incurred directly by the NSW Telco Authority for the CCEP, ESOs have incurred costs to maintain their own networks due to the delay in implementing the CCEP. The ESOs will continue to incur these costs until they are able to fully migrate to the enhanced PSN, which is expected to be in 2027. These costs have not been tracked or reported as part of transparently accounting for the whole-of-government cost of the enhanced PSN. This is despite Infrastructure NSW in 2019 recommending to the NSW Telco Authority that it conduct a stocktake of such costs so that a whole-of-government cost impact is available to the NSW Government.

1 The definition of 'emergency services organisation' is set out in the State Emergency and Rescue Management Act 1989 (NSW). In addition to the five ESOs discussed in this report, the definition also includes: Surf Life Saving New South Wales; New South Wales Volunteer Rescue Association Inc; Volunteer Marine Rescue NSW; an agency that manages or controls an accredited rescue unit; and a non-government agency that is prescribed by the regulations for the purposes of this definition.
2 Section 15(1) of the Government Telecommunications Act 2018 (NSW).

The NSW Telco Authority established and tracked its own costs for the CCEP

Over the course of the program from 2016, the NSW Telco Authority prepared a series of business cases and program reviews that estimated its cost of implementing the program in full, including those shown in Exhibit 6 below.

Exhibit 6: Estimated costs to fully implement the CCEP
Source Capital cost ($ million) Operating cost
($ million)
Completion date
March 2016 business case 400 37.3 2020
November 2017 internal review 476.7 41.7 2022
March 2020 business case 950–1,050 -- 2025
October 2020 business case 1,263.1 56.1 2026

Source: CCEP business cases as identified.

In response to the 2016 CCEP business case, the then NSW Government approved the NSW Telco Authority implementing the CCEP in full, with funding provided in stages. The NSW Telco Authority tracked its costs against approved funding, with monthly reports provided to the multi-agency Program Steering Committee

Throughout the program, the NSW Government was informed of increasing costs being incurred by the NSW Telco Authority for the CCEP

The various business cases, program updates, and program reviews prepared by the NSW Telco Authority were provided to the NSW Government through the required Cabinet process when seeking approval for the program proceeding and requests for both capital and operational funding. These provided clear indication of the changing overall cost of the CCEP to the NSW Telco Authority, as well as the delays that were being experienced.

There was no transparency to the Parliament and community about changes in the capital cost of the CCEP until the 2021–22 NSW Budget

As the business cases for the CCEP were not publicly available, the only sources of information about capital cost were NSW Budget papers and media releases. The information provided in the annual Budget papers prior to the 2021–22 NSW Budget provided no visibility of the estimated full capital cost to complete all stages of the CCEP. As shown in Exhibit 7 below, this information was fragmented and complex.

Media releases about the progress of the CCEP did not provide the estimated total cost to the NSW Telco Authority of $1.325 billion to complete all stages of the CCEP until June 2021. Prior to this date, media releases only provided funding for the initial stages of the program or for the stages subject to a funding announcement.

Even during the September 2019 and March 2020 Parliamentary Estimate Committee hearings where the costings and delays to the CCEP were raised, the estimated full cost of the CCEP was not revealed.

Exhibit 7: CCEP funding in NSW Budget papers from 2015–16 to 2022–23
Financial year Type of major work Description of expenditure Forecast estimate to complete ($ million) Estimated duration
2015–16 New work Infrastructure Rationalisation Program: Planning and Pilot 18.3 2015–16
2016–17 Work in progress CCEP Planning and Pilot 18.3 2015–17
New work CCEP 45 2016–17
2017–18 New work CCEP 190.75 2017–21
2018–19 Work in progress CCEP North Coast and State-wide Detailed Design 190.75 2017–21
New work CCEP Greater Metropolitan Area 236 2018–22
2019–20 Work in progress CCEP 426.9 2018–22
2020–21 Work in progress CCEP 664.8 2018–22
2021–22 Work in progress CCEP 1,325 2018–26
2022–23 Work in progress CCEP 1,292.8 2018–26

Source: NSW Treasury, Annual State Budget Papers.

The original business case for the CCEP included estimated ESO costs, though these costs were not tracked throughout the program

Estimates for ESO costs for operating and maintaining their own radio networks over the four years from 2016–17 were included in the original March 2016 business case. They included $75.2 million for capital expenditure and $95 million for one-off operating costs. These costs, as well as costs incurred by ESOs due to the delay in the program, were not subsequently tracked by the NSW Telco Authority.

In January 2017, Infrastructure NSW reviewed the CCEP business case of March 2016. In this review, Infrastructure NSW recommended that the NSW Telco Authority identify combined and apportioned costs and cashflow for all ESOs over the CCEP funding period reflecting all associated costs to deliver the CCEP. These to include additional incidental capital costs accruing to ESOs, transition and migration to the new network and the cost (capital and operational) of maintaining existing networks. This recommendation was implemented in the November 2017 program review, with ESO capital costs estimated as $183 million.

In 2019, Infrastructure NSW conducted a Deep Dive Review on the progress of the CCEP. In this review, Infrastructure NSW made what it described as a 'critical recommendation' that the NSW Telco Authority:

…coordinate a stocktake of the costs of operational bridging solutions implemented by PSAs [ESOs] as a result of the 18-month delay, so that a whole-of-government cost impact is available to the NSW Government.  

It should be noted that the delay to CCEP completion now is seven years and that further ‘operational bridging solutions’ have been needed by the ESOs.

'Stay Safe and Keep Operational' costs incurred by ESOs will be significantly higher than originally estimated

Stay Safe and Keep Operational (SSKO) funding was established to provide funding to ESOs to maintain their legacy networks while the CCEP was refreshing and enhancing the PSN. This recognised that much of the network infrastructure relied on by ESOs had reached – or was reaching – obsolescence and would either require extensive maintenance or replacement before the PSN was available for ESOs to migrate to it. ESOs may apply to NSW Treasury for SSKO funding, with their specific proposals being reviewed (and endorsed, where appropriate) by the NSW Telco Authority. Accordingly, SSKO expenditure does not fall within the CCEP budget allocation.

As shown in the table below, extracted from the March 2016 CCEP business case, the total expected cost for SSKO purposes over the course of the CCEP was originally $40 million, assuming the enhanced PSN would be fully available by 2020.

Exhibit 8: Stay Safe and Keep Operational forecast costs, 2017 to 2020
Year 2017 2018 2019 2020 Total
SSKO forecast ($ million) 12.5 15 10 2.5 40

Source: March 2016 CCEP business case.

In October 2022, the expected completion date for the CCEP was re-baselined to August 2027. Accordingly, ESOs will be required to continue to maintain their radio networks using legacy equipment for seven years longer than the original 2020 forecast. This will likely become progressively more expensive and require additional SSKO funding. For example, NSW Telco Authority endorsed SSKO bids for 2022–23 exceeded $35 million for that year alone.

Compared to the original forecast made in the March 2016 CCEP business case of $40 million, we found ESOs had estimated SSKO spending to 2027 will be $292.5 million.

A refresh of paging network used by ESOs and the decommissioning of redundant sites were both removed from the original 2016 scope of the CCEP

Paging

A paging network is considered an important user requirement by the Fire and Rescue NSW, NSW Rural Fire Service, and NSW State Emergency Service. The 2016 CCEP business case included a paging network refresh within the program scope of works. This was reiterated in the November 2017 internal review of the program. These documents did not estimate a cost for this refresh. The March 2020 and October 2020 business cases excluded paging from the program scope. The audit is unable to identify when, why or by whom the decision was made to remove paging from the program scope, something that was also not well communicated to the affected ESOs.

In 2021, after representations from the affected ESOs, the NSW Telco Authority prepared a separate business case for a refresh of the paging network at an estimated capital cost of $60.31 million. This program was subsequently approved by the NSW Government and included in the 2022–23 NSW Budget.

In determining an estimated full whole-of-government cost of delivering the enhanced PSN, we have included the budgeted cost of the paging network refresh on the basis that:

  • it was expressly included in the original approved March 2016 business case
  • the capability is deemed essential to the needs of three ESOs.

Decommissioning costs

The 2016 CCEP business case included cost estimates for decommissioning surplus sites (whether ‘old’ GRN sites or sites belonging to ESOs’ own networks). These estimates were provided for both the NSW Telco Authority ($38 million) and for the ESOs ($55 million). However, while these estimates were described, they were not included as part of the NSW Telco Authority's estimated capital cost ($400 million) or (more relevantly) operating cost ($37.3 million) for the CCEP. This is despite decommissioning being included as one of eight planned activities for the rollout of the program.

In the October 2020 business case, an estimate of $201 million was included for decommissioning agency networks based on a model whereby:

  • funding would be coordinated by the NSW Telco Authority
  • scheduling and reporting through an inter-agency working group and
  • where appropriate, agencies would be appointed as the most appropriate decommissioning party.

This estimated cost is not included in the CCEP budget.

In determining an estimated full whole-of-government cost of the enhanced PSN, we have included the estimated cost of decommissioning on the basis that:

  • decommissioning was included in the 2016 CCEP business case as one of eight 'planned activities for the rollout of the program'
  • effective decommissioning of surplus sites and equipment (including as described in the business case as incorporating asset decommissioning, asset re-use, and site make-good) is an inherent part of the program management for an enhanced PSN
  • costs incurred in decommissioning are entirely a consequence of the CCEP program.

The estimated minimum cost of building an enhanced PSN consistent with the original proposal is over $2 billion

We have derived two estimated minimum whole-of-government costs for delivering an enhanced PSN. These are:

  • $2.04 billion when calculated from NSW Telco Authority data – shown as estimate A in Exhibit 9 below.
  • $2.26 billion when calculated from ESO supplied data – shown as estimate B in Exhibit 9.

Both totals include:

  • budgeted amounts for both CCEP capital expenditure ($1,292.8 million) and operating expenditure ($139 million)
  • the NSW Telco Authority's 2020 estimated cost for decommissioning ($201 million)
  • the NSW Telco Authority's approved funding for paging refresh ($60.3 million).

The two estimated totals primarily vary around the capital expenditure of ESOs (particularly SSKO funding). To determine these costs, we used ESO provided actual SSKO costs to date, as well as their estimates for maintaining their legacy radio networks through to 2027.

The equivalent cost estimates from the NSW Telco Authority were sourced from the November 2017 internal review and the October 2020 business case for CCEP. It should be noted that the amounts for both estimates are not audited, or verified, but do provide an indication of how whole-of-government costs have grown over the course of the program.

The increase in and reasons for the increase in total CCEP costs (capital and one-off operating) incurred or forecast by the NSW Telco Authority (from $437.3 million in 2016 to $1,431.8 million in 2022) have been provided to the NSW Government through various business cases and reviews prepared by the NSW Telco Authority, as well as by reviews conducted by Infrastructure NSW as part of its project assurance responsibilities.

However, the growth in ESO costs and other consequential costs, such as paging and decommissioning, from around $263 million in the 2016 CCEP business case to between $600 million and $800 million, has to a large degree remained invisible and unexplained to the NSW Government and other stakeholders

Exhibit 9: Estimated whole-of-government costs of the enhanced PSN
  Estimated whole-of-government cost, over time
Cost type 20161 20172 20203 2023–Estimate A4 2023–Estimate B5
$ million $ million $ million $ million $ million
CCEP capital expenditure 400a 476.7b 1,263.1c 1,292.8d 1,292.8d
CCEP operating expenditure 37.3a 41.7b 41.5e 139d 139d
CCEP total 437.3 518.4 1,304.6 1,431.8 1,431.8
ESO capital expenditure 75.2a,f 183b,e 75.4e 258.4g 292.5
ESO one-off operating expenditure 93a n.a.l 86.5e 86.5h 273
ESO total 168.2 183 161.9 344.9 565.5
Paging n.a.i n.a.i n.a.j 60.3k 60.3k
Decommissioning 93 n.a.l 201.0 201h 201
Paging and decommissioning total 93 n.a. 201 261.3 261.3
Whole-of-government total 698.5 701.4 1,667.5 2,038 2,258.6

Notes:
  1. Financial year 2016 to Financial year 2020.
  2. Financial year 2016 to Financial year 2021.
  3. Financial year 2016 to Financial year 2025.
  4. Financial year 2016 to Financial year 2026.
  5. Financial year 2022 to Financial year 2025.
  6. Stay Safe and Keep Operational (SSKO) costs plus terminals costs.
  7. November 2017 internal review and October 2020 Business case.
  8. October 2020 Business case.
  9. Included in CCEP capital expenditure at that time.
  10. By 2020, a refresh of the paging network had been removed from the CCEP scope.
  11. A separate business case for a refresh of the paging network was approved by government in 2022.
  12. Figure not included in the source document.
Sources:
  1. March 2016 CCEP business case.
  2. November 2017 Internal Review conducted by the NSW Telco Authority.
  3. October 2020 CCEP business case.
  4. Derived from business cases, with ESO costs drawn from NSW Telco Authority data.
  5. Derived from business cases, with ESO costs based on data provided to the Audit Office of New South Wales by each of the five ESOs.

Appendix one – Response from agency

Appendix two – Trunked public safety radio networks

Appendix three – About the audit

Appendix four – Performance auditing

 

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #383 - released 23 June 2023

 

Published

Actions for Natural disasters

Natural disasters

Community Services
Environment
Finance
Local Government
Planning
Transport
Treasury
Whole of Government
Asset valuation
Compliance
Financial reporting
Infrastructure
Regulation
Risk
Service delivery

What this report is about

This report draws together the financial impact of natural disasters on agencies integral to the response and impact of natural disasters during 2021–22.

What we found

Over the 2021–22 financial year $1.4 billion from a budget of $1.9 billion was spent by the NSW Government in response to natural disasters.

Total expenses were less than the budget due to underspend in the following areas:

  • clean-up assistance, including council grants
  • anticipated temporary accommodation support
  • payments relating to the Northern Rivers Business Support scheme for small businesses.

Natural disaster events damaged council assets such as roads, bridges, waste collection centres and other facilities used to provide essential services. Additional staff, contractors and experts were engaged to restore and repair damaged assets and minimise disruption to service delivery.

At 30 June 2022, the estimated damage to council infrastructure assets totalled $349 million.

Over the first half of the 2022–23 financial year, councils experienced further damage to infrastructure assets due to natural disasters. NSW Government spending on natural disasters continued with a further $1.1 billion spent over this period.

Thirty-six councils did not identify climate change or natural disaster as a strategic risk despite 22 of these having at least one natural disaster during 2021–22.

Section highlights

  • $1.4 billion from a budget of $1.9 billion was spent by the NSW Government in response to natural disasters during 2021–22.
  • Budget underspent for temporary housing and small business support as lower than expected need.

Section highlights

  • 83 local council areas were impacted by natural disasters during 2021–22, with 58 being impacted by more than one type of natural disaster.
  • $349 million damage to council infrastructure assets at 30 June 2022.

 

Published

Actions for Government's acquisition of private property: Sydney Metro project

Government's acquisition of private property: Sydney Metro project

Transport
Planning
Whole of Government
Compliance
Infrastructure
Internal controls and governance
Project management
Risk

What the report is about

Sydney Metro is Australia’s largest public transport project. It requires the acquisition of many private properties, including residential and business properties.

This audit assessed the effectiveness of the acquisition of private properties for the Sydney Metro project. The audited agencies were Sydney Metro, the Department of Planning and Environment (Valuer General NSW) and Transport for NSW (the Centre for Property Acquisition).

The audit assessed agencies against the framework for property acquisitions in New South Wales. It did not re-perform the valuations done for individual properties that were acquired by Sydney Metro.

What we found

Acquisitions of private property for the Sydney Metro project were mostly effective in the sample of acquisitions we assessed. We found Sydney Metro:

  • complied with legislative and policy requirements for compensation and communication with people subject to property acquisitions
  • kept accurate records of its acquisitions and applied probity controls consistently
  • did not complete detailed plans or negotiation strategies for the high-risk and high-value acquisitions we reviewed
  • did not comply with legislative timelines for most compulsory acquisitions because of delays in receiving the required information from the Valuer General in these cases.

The Centre for Property Acquisition has overseen the implementation of reforms to residential acquisition processes, but its assessment of the effectiveness of these reforms has not been comprehensive.

What we recommended

The audit made four recommendations to the audited agencies to improve:

  • plans and strategies for the acquisition of high-risk and high-value properties
  • timeliness of issuing compensation determinations for compulsory acquisitions
  • data quality on the experience of people subject to property acquisitions.

The NSW Government has the power to acquire land that is owned or leased by individuals or businesses, if it is needed for a public purpose. The power arises from the Land Acquisition (Just Terms Compensation) Act 1991 (the Just Terms Act). Government agencies that have the power to compulsorily acquire private property are referred to as ‘acquiring authorities’. People who are subject to acquisitions are referred to as ‘affected parties’ and include property owners (business or residential), businesses with a commercial lease on a property, or individuals with residential tenancy leases. In recent years, the vast majority of acquisitions by the NSW Government have been for public transport or road projects.

Sydney Metro is a NSW Government agency with responsibility for building the Sydney Metro railway project. Sydney Metro is Australia’s largest public transport project. The project requires the acquisition of a large number of private properties. Sydney Metro has been one of the largest acquirers of private property in recent years, completing over 500 acquisitions between 2020 and mid-2022, with a total acquisition value of over $2 billion. Other agencies and statutory officers involved in the acquisition of property for the Sydney Metro project include:

  • the Department of Planning and Environment (DPE), which supports the minister responsible for the Just Terms Act. DPE also provides staff to the Valuer General of NSW
  • the Valuer General of NSW, an independent statutory officer that determines compensation in cases where the acquiring authority and the affected party cannot agree on compensation for property that has been acquired
  • Transport for NSW, which includes the Centre for Property Acquisition (CPA). The CPA does not have a direct role in acquiring properties, but its responsibilities include developing guidance for acquiring agencies and monitoring and reporting on their activities.

About this audit

The objective of this audit was to assess the effectiveness of acquisitions of private properties for Sydney Metro projects. The audit assessed agencies against the legislative and policy requirements in place for government acquisitions of private property in New South Wales. In line with the Audit Office's legislative mandate, the audit does not comment on the merits of the policy objectives reflected in the Just Terms Act.

The audit examined a sample of 20 property acquisitions. This was not a statistically representative sample. While our report provides comments on Sydney Metro’s overall acquisition processes, it does not provide assurance regarding the acquisitions that were not examined for this audit.

The audit did not re-perform the valuations done for individual properties that were acquired by Sydney Metro. Affected parties who disagree with the valuation of their property have the right to seek independent assessment of this via the Valuer General and the Land and Environment Court.

Conclusion

Acquisitions of property for the Sydney Metro project were mostly effective in the sample of acquisitions we assessed. Sydney Metro followed requirements for communication with affected parties. Compensation processes were conducted in compliance with legislative requirements, but compensation determinations for compulsory acquisitions were not completed within legislated time frames due to delays in receiving these from the Valuer General. Governance and probity processes were followed consistently, with some relatively minor exceptions. 

Sydney Metro has detailed guidelines for acquisitions that are based on relevant legislation and government policy. In the 20 acquisitions we assessed for this audit, these procedures were followed consistently. This included adhering to minimum timelines for negotiation periods, engaging independent valuers and other experts when needed, and complying with governance and probity processes.

Sydney Metro staff followed requirements for communication and support for residential acquisitions by assigning ‘personal managers’ and providing additional support to affected parties when needed. The Centre for Property Acquisition (CPA) has overseen reforms to the residential property acquisition process in recent years. These reforms include the introduction of the NSW Property Acquisition Standards and the use of personal managers, in addition to the existing acquisition managers, for residential acquisitions. However, the CPA has not assessed the impact of these changes on the experiences on people affected by property acquisitions.

Sydney Metro did not comply with the legislative requirement to provide a formal compensation notice to the affected party within 45 days of a compulsory acquisition starting in any of the eight relevant acquisitions in our sample. This was because Sydney Metro must wait for the Valuer General to complete a compensation determination before Sydney Metro can send the compensation notice, and the Valuer General did not do this within 45 days. We acknowledge that Sydney Metro does not have full control over this process, and that it has taken steps to mitigate the impact of delays on affected parties. 

This chapter presents our findings on Sydney Metro's acquisition of industrial and commercial properties. Industrial properties include construction businesses and manufacturing facilities. Commercial properties were mostly properties such as shopping centres and office towers. Many of these acquisitions involve businesses and properties that are relatively complex and have high values. This means the valuation process can require multiple experts and can be lengthy and contested. Adherence to governance and probity requirements is important for these acquisitions in order to demonstrate that the acquiring authority has achieved value for money.

This chapter presents our findings on Sydney Metro's acquisition of residential properties, which include apartments and houses, and small business leases, which mostly affected businesses in small shopping centres or arcades. Most of these acquisitions were lower value compared to industrial and commercial property acquisitions and did not require as much expert advice on complex technical issues. However, residential property acquisitions can be personally distressing for the affected parties and require staff from the acquiring authority to provide support and show empathy while ensuring legislative compliance and value for money.

Appendix one – Responses from agencies

Appendix two – About the audit 

Appendix three – Performance auditing 

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #375 - released 9 February 2023

Published

Actions for Design and implementation of the Transport Asset Holding Entity

Design and implementation of the Transport Asset Holding Entity

Transport
Treasury
Asset valuation
Financial reporting
Infrastructure
Procurement
Risk
Service delivery

What the report is about

The Transport Asset Holding Entity (TAHE) is the State's custodian of rail assets. It is a state owned corporation and commenced operating on 1 July 2020.

This audit assessed the effectiveness of NSW Government agencies' design and implementation of TAHE. We audited TAHE, Transport for NSW (TfNSW) and NSW Treasury.

Separate and related audits on TAHE are reported in 'State Finances 2022', 'State Finances 2021' and 'Transport and Infrastructure 2022' reports.

What we found

The design and implementation of TAHE, which spanned seven years, was not effective.

The process was not cohesive or transparent. It delivered an outcome that is unnecessarily complex in order to support an accounting treatment to meet the NSW Government's short-term Budget objectives, while creating an obligation for future governments.

The benefits of TAHE were claimed in the 2015–16 NSW Budget before the enabling legislation was passed by Parliament in 2017. This committed the agencies to implement a solution that justified the 2015–16 Budget impacts, regardless of any challenges that arose.

Rail safety arrangements were a priority throughout TAHE's design and implementation, and risks were raised and addressed.

Agencies relied heavily on consultants on matters related to the creation of TAHE, but failed to effectively manage these engagements. Agencies failed to ensure that consultancies delivered independent advice as an input to decision-making. A small number of firms were used repeatedly to provide advice on the same topic. The final cost of TAHE-related consultancies was $22.6 million compared to the initial estimated cost of $12.9 million.

What we recommended

We recommended that the audited agencies should:

  • improve accountability and transparency for major new fiscal transformation initiatives
  • ensure entities do not reflect the financial impact of significant initiatives in the Budget when there is uncertainty, or it creates perverse incentives
  • review record keeping practices, systems and policies to ensure compliance with the State Records Act 1998, and the NSW Government Information Classification, Labelling and Handling Guidelines
  • review procurement policies to ensure that consultant use complies with all NSW Government policy requirements.

The NSW Government established the Transport Asset Holding Entity (TAHE), a statutory State Owned Corporation (SOC), on 1 July 2020 to replace the former rail infrastructure owner – RailCorp. It is the State's custodian of rail network assets, including rail tracks and other infrastructure, rolling stock, land, train stations and facilities, retail space, and signal and power systems, within metropolitan and regional New South Wales. It is responsible for $2.8 billion of major capital projects in 2022–23.

TAHE was established under Part 2 of the Transport Administration Act 1988 and is governed by a decision-making board. The Treasurer and the Minister for Finance and Employee Relations are the Shareholding Ministers of TAHE, and they annually agree performance expectations articulated in a Statement of Corporate Intent.

Whereas TAHE is the custodian of rail assets, Sydney Trains and NSW Trains operate public rail services. TAHE does not have responsibility for the operation of the heavy rail network or train services, nor does it have network control functions. TAHE, Sydney Trains and NSW Trains are in the Transport and Infrastructure cluster in the public sector (formerly the Transport cluster and renamed in April 2022), which also includes Sydney Metro and Transport for NSW (TfNSW).

TfNSW leads the Transport and Infrastructure cluster. Its role is to set the strategic direction for transport across the State. This involves the shaping of planning, policy, strategy, regulation, resource allocation and other service and non-service delivery functions for all modes of transport.

TAHE's Operating Licence is granted by the Portfolio Minister and authorises the entity to perform the functions required to acquire, develop, finance, divest and hold assets, pursuant to the Transport Administration Act 1988. The Portfolio Minister also issues a Statement of Expectations which outlines the government’s expectation for the business for the next three to five years.

TAHE's original Portfolio Minister was the Minister for Transport who approved, on 30 June 2020, the issuing of an interim 12-month Operating Licence to enable TAHE to commence operating on 1 July 2020. The Portfolio Minister then granted TAHE's current Operating Licence in 2021. After TAHE requested a 12-month extension to its current Operating Licence, its next Operating Licence is due on 1 July 2024. The current Portfolio Minister is the Minister for Infrastructure, Cities and Active Transport.

About this audit

This audit assessed the effectiveness of NSW Government agencies' design and implementation of TAHE. In making this assessment, we considered whether: 

  • the process of designing and implementing TAHE was cohesive and transparent, and delivered an effective outcome
  • agencies' roles and responsibilities were clear in the planning of TAHE
  • agencies effectively identified and managed certain risks.

Conclusion

The design and implementation of TAHE was not effective. The process was not cohesive or transparent. It delivered an outcome that is unnecessarily complex in order to meet the NSW Government's short-term Budget objectives, while creating an obligation for future governments to sustain TAHE through continuing investment, and funding of the state owned rail operators. The ineffective process to design TAHE delivered a model that entails significant uncertainty as to whether the anticipated longer-term financial improvements to the Budget position can be achieved or sustained.

NSW Treasury and TfNSW had different objectives for TAHE

Up to June 2013, RailCorp had been the owner and operator of rail services and maintainer of the metropolitan rail network for almost a decade. It had been operating as a not-for-profit Public Non-Financial Corporation (PNFC).

In 2012, NSW Treasury (hereafter Treasury) decided there was a risk that the Australian Bureau of Statistics (ABS) would reclassify RailCorp to the General Government Sector (GGS), meaning depreciation expenses of approximately $870 million would be reflected in the GGS Budget. Treasury wanted to avoid this impact on the GGS Budget, and considered the establishment of a transport asset holding entity as a means to do so. Capital grants to RailCorp were being treated as an expense to the GGS Budget.

TfNSW also wanted an asset holding entity – but one that would be a non-trading ‘shell’ company with no staff that would hold and manage all public transport assets. TfNSW's concept envisaged the entity would have a structure that would enable future public transport reforms and strategic directions while ensuring vertical integration of operations between asset owners and the rail operators to maintain rail safety.

However, Treasury pursued its objective to improve the GGS Budget result, and sought to expand on TfNSW's 'shell' asset holding entity concept. Treasury wanted an entity that could generate a return on investment, as this meant that government investment in transport assets could be treated as equity investments, rather than a Budget expense, and in turn improve the GGS Budget position. As an example of the potential impact of creating this new entity, capital grants of $2.3 billion were paid to RailCorp in 2013–14. If Treasury's objective was met, grants of this significance would then be treated as an equity investment, rather than an expense in the GGS Budget.

In 2017, Treasury's preferred option was progressed through legislation, but both agencies' central objectives for the proposed asset holding entity would continue to prove difficult to reconcile. To achieve Treasury's objective to improve the Budget result, the entity would need to generate a return on investment (this is further discussed below). However, TfNSW expressed concerns that the prioritisation of rail safety, and the effective management of governance, regulation and operations would be more complex in an entity with commercial imperatives.

Asset holding entities are a common approach to the management of transport assets in Australia and internationally, and there are a range of approaches to how they are structured and used. Such structures should be driven by the goal of improved asset management. Ultimately, TfNSW's objectives could have been delivered through a simpler entity structure. However, reconciling TfNSW's objectives with Treasury's imperative to deliver and justify a Budget improvement in the short-term resulted in an overly lengthy process and an unnecessarily complex outcome that places an obligation on future governments to sustain. There is still significant uncertainty as to whether the short-term improvements to the Budget can continue to be realised in the longer-term.

The Budget benefits of TAHE were claimed before the entity was legislated, committing the agencies to deliver, regardless of the complexities that subsequently arose

The 2015–16 GGS Budget treated the government's investment in TAHE (still known at this time as RailCorp) as an equity contribution. This had the immediate impact of improving the Budget result by $1.8 billion per annum. However, the legislation to enable the establishment of TAHE had not yet been passed by Parliament, key elements of the operating model were still under development, and imminent changes in accounting standards had the potential to impact TAHE's financial model. The decision to book the benefits in the Budget early committed the involved agencies to implement a solution that justified the 2015–16 Budget impacts, irrespective of the challenges that arose. 

TAHE's financial structure requires circular government investment to work

For the NSW Government to continue to treat its investment in TAHE as an equity contribution, rather than an expense to the Budget, there must be a reasonable expectation that TAHE will generate a sufficient rate of return as required by the Government Finance Statistics (GFS) framework. In doing so, it needs to recover a revaluation loss created by a $20.3 billion reduction in the value of its assets which was incurred in its first full year of operation. This loss occurred as a result of a revaluation of TAHE's assets when RailCorp (a not-for profit entity) became TAHE (a for-profit commercial entity) – and is discussed further in the 'Key findings' below.

TAHE generates a small portion of its income from transactions with the private sector but, as noted in our report 'State Finances 2021', TAHE receives the majority of its revenue (more than 80%) from access and licence fee agreements with Sydney Trains and NSW Trains. Both of these entities are funded by grants (a Budget expense) to TfNSW from the GGS Budget.

Based on Treasury’s correspondence with the ABS in 2015, TAHE was initially expected to pay a return on equity of 7% in 2016–17. The assumption of a 7% return persisted through to 2018, after the legislation enabling the establishment of TAHE was passed by Parliament. However, when the initial access and licence fees were agreed on 1 July 2020, this figure had been revised to an expected rate of return of 1.5% excluding the revaluation loss. This was below the long-term inflation target and did not include the recovery of the revaluation loss – risking the government's ability to treat its investment in TAHE as an equity contribution. Importantly, as TAHE is primarily reliant on fees paid by the state owned rail operators that, in turn, are funded by the GGS Budget (as an expense), the decision to change the returns model from 7% to 1.5% would in its own right have had a positive impact on the GGS Budget. However, the decision to use a 1.5% return would ultimately be problematic as it made it difficult to treat the government's contributions to TAHE as an equity investment, as discussed below.

On 14 December 2021, to avoid a qualified audit opinion, the NSW Government made the decision to increase TAHE's expected rate of return to 2.5%, equal to the Reserve Bank’s long-term inflation target.

In 2021-22, TAHE needed to start charging rail operators higher access and licence fees in order to generate a return of 2.5%, so as to support the government's treatment of its investment in TAHE as an equity contribution in the GGS Budget. This meant the government needed to provide additional grant (expense) funding to the state owned rail operators so they could pay the increased access and licence fees to TAHE. Based on current projections, TAHE is not expected to recover the revaluation loss until 2046.

There remains a risk that TAHE will not be able to generate a sufficient return on the NSW Government's investment without relying on increased funding to state owned rail operators so that they can in turn pay the higher access and licence fees. TAHE's ability to generate returns on government investment from other sources are uncertain and may not be achievable or sustainable. Current modelling highlights that TAHE remains largely reliant, through to 2046, on increasing fees (which are assumed to increase at 2.5% per annum from 2031 onwards when the current 10 year contracts with rail operators expire) paid by the state owned rail operators that remain principally reliant on GGS Budget grants.

The process of designing and implementing TAHE was not transparent to independent scrutiny

Our report 'State Finances 2021' commented that Treasury did not always provide this Office with information relating to TAHE on a timely basis. Similarly, during this performance audit, there were also multiple instances where auditees were unable to provide documentation regarding key activities in the process to deliver TAHE. Agencies also applied higher sensitivity classifications to large tranches of documents than was justified or required by policy. Of particular concern is the incorrect classification of documents as Cabinet sensitive information. The incorrect or over-classification of documentation as Cabinet sensitive delayed this Office's ability to provide scrutiny or independent assurance.

There was a lack of clarity around the roles and responsibilities of governance structures set up to oversee the design and implementation of TAHE

From 2014, multiple workstreams and advisory committees were established to progress the design and implementation of TAHE. For some of these committees and workstreams, there is limited information on what they were tasked to do and what they achieved. Most had ceased meeting by 2018, before significant work needed to deliver TAHE was completed.

The lack of clarity around the roles and responsibilities of these governance structures reduced opportunities for TfNSW and Treasury to reconcile their differing objectives for TAHE, and resolve key questions earlier in the process.

There was a heavy reliance on consulting firms throughout the process to establish TAHE, and the management of consultant engagements failed to ensure that agencies received independent advice to support objective decision-making

In 2020, Treasury and TfNSW failed to prevent, identify, or adequately manage a conflict of interest when they engaged the same 'Big 4' consulting firm to work on separate TAHE-related projects. Both agencies used the firm's work to further their respective views with regard to the financial implications of TAHE's operating model. At this time those views were still unreconciled.

Treasury engaged the firm to provide a fiscal risk management strategy and advice on the impact of changes to accounting standards. TfNSW engaged the same firm to develop operating and financial models for TAHE, which raised concerns regarding the viability of TAHE. Disputes arose around the findings of these reports. Treasury disagreed with some of the outcomes of the work commissioned by TfNSW, relating to accounting treatment and fiscal advice.

The management of this conflict (real or perceived) was left to the 'Big 4' consulting firm when it was more appropriate for it to be managed by Treasury and TfNSW. If these agencies had communicated more effectively, used available governance structures consistently, and shared information openly about their use of the firm and the nature of their respective engagements, these disputes might have been avoided. This issue, coupled with deficiencies in procurement by both agencies, reflected and further perpetuated the lack of cohesion in the design and implementation of TAHE.

More broadly, over the period 2014 – 2021, 16 separate consulting firms were employed to work on 36 contracts, valued at over $22.56 million, relating to TAHE ranging from accounting and legal advice, project management, and the provision of administrative support and secretariat services.

Consultants are legitimately used by agencies to provide advice on how to achieve the outcomes determined by government, including advising agencies on the risks and challenges in achieving those outcomes. Similarly, consultants can provide expert knowledge in the service of achieving those outcomes and managing the risks. However, the heavy reliance on consulting firms during the design and implementation of TAHE heightened the risk that agencies were not receiving value for money, were outsourcing tasks that should be performed by the public service, and did not mitigate the risk that the advice received was not objective and impartial. The risk that the role of consultants could have been blurred between providing independent advice to government on options and facilitating a pre-determined outcome was not effectively treated or mitigated. This risk was amplified because a small number of firms were used repeatedly to provide advice on one topic. The effective procurement and management of consultants is an obligation of government agencies.

Appendix one – Responses from audited agencies, and Audit Office clarification of matters raised in the TAHE formal response 

Appendix two – Classification of government entities 

Appendix three – About the audit 

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #372 - released 24 January 2023

 

Published

Actions for Transport and Infrastructure 2022

Transport and Infrastructure 2022

Transport
Asset valuation
Financial reporting
Information technology
Infrastructure
Management and administration
Procurement

What the report is about

Result of the Transport and Infrastructure cluster agencies' financial statement audits for the year ended 30 June 2022.

What we found

Unmodified audit opinions were issued for all Transport and Infrastructure cluster agencies' financial statements.

An 'other matter' paragraph was included in TAHE's Independent Auditor's Report for its 30 June 2022 financial statements which draws attention to Transport and Asset Holding Entity's (TAHE) reliance on government-funded customers.

We included an ‘emphasis of matter’ paragraph in the Independent Auditor’s Report for State Transit Authority of New South Wales’ (the authority) 30 June 2022 financial statements, which draws attention to the financial statements being prepared on a liquidation basis as the authority’s principal activities ceased operations on 3 April 2022.

What the key issues were

The 2021–22 audits identified five high-risk findings:

  • detailed business modelling to support returns from TAHE
  • valuation of assets at TAHE
  • control of assets at TAHE
  • accounting and valuation of tree assets at Centennial Park and Moore Park Trust and Parramatta Park Trust.

Access and licence fees - TAHE

Revised commercial agreements were signed between TAHE, the operators and Transport for NSW on 23 June 2022 to reflect increased access and licence fees detailed in the 18 December 2021 Heads of Agreement.

TAHE’s ability to generate the expected return of 2.5% based on the current modelling is heavily reliant on the government funding the public rail operators (TAHE's customers).

There are risks that:

  • TAHE will not be able to recontract for access and licence fees at a level that is consistent with current projections
  • future governments' funding to TAHE's key customers will not be sufficient to fund payment of access and licence fees at a level that is consistent with current projections
  • TAHE will be unable to grow its non-government revenues.

Valuation of assets - TAHE

Although TAHE's selected valuation of assets falls within an acceptable range, there remains a significant gap between what has been assessed as an acceptable range and TAHE's range.

What we recommended

Control of assets - TAHE

While we accepted TAHE’s position on control for the current year, NSW Treasury and TAHE should continue to monitor the risk that control of TAHE assets could change in future reporting periods. TAHE must continue to demonstrate control of its assets or the current accounting presentation would need to be reconsidered.

This report provides Parliament and other users of the Transport and Infrastructure cluster’s financial statements with the results of our audits, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision-making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Transport and Infrastructure cluster (the cluster) for 2022.

Section highlights

  • Unqualified audit opinions were issued on all Transport and Infrastructure cluster agencies' financial statements.
  • An 'Other Matter' paragraph was included in the Transport Asset Holding Entity of New South Wales' (TAHE) Independent Auditor's Report to draw attention to TAHE's reliance on government-funded customers.
  •  An 'Emphasis of Matter' paragraph was included in the State Transit Authority of New South Wales' (the authority) Independent Auditor's Report to draw attention to management’s disclosures that State Transit Authority of New South Wales' financial statements for the year ended 30 June 2022 were prepared on a liquidation basis as the authority’s principal activities ceased operations on 3 April 2022.
  • While TAHE's valuation of assets at 30 June 2022 was within an acceptable range of valuation outcomes, there remained significant differences in assumptions used when compared with relevant market benchmarks.
  • Sydney Metro corrected two prior period errors of $1.5 billion and $51 million in accounting and valuation of assets, and double counting of assets capitalised in infrastructure as well as assets under construction respectively.

 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision-making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the cluster.

Section highlights

  • The number of findings reported to management decreased from 87 in 2020–21 to 59 in 2021–22.
  • Repeat findings accounted for 54.2% of management letter points. Many repeat findings related to controls over payroll, including management of annual leave and processing of timesheets, management of conflicts of interests, weaknesses in controls over information technology user access administration and password management.
  • One new high-risk issue was identified in 2020–21, and four high-risk repeat issues remained.
  • The five high-risk issues arose from the audit in the cluster, with respect to:
    • control over TAHE assets and operations (repeat)
    • TAHE detailed business modelling to support returns (repeat)
    • valuation of trees (repeat for Parramatta Park Trust and Centennial Park and Moore Park Trust)
    • TAHE asset valuations.

 

Appendix one – Misstatements in financial statements submitted for audit

Appendix two – Early close procedures

Appendix three – Timeliness of financial reporting

Appendix four – Financial data

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Health 2022

Health 2022

Health
Whole of Government
Asset valuation
Compliance
Cyber security
Financial reporting
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Risk
Service delivery
Shared services and collaboration
Workforce and capability

What the report is about

Result of Health cluster (the cluster) agencies' financial statement audits for the year ended 30 June 2022.

What we found

Unmodified audit opinions were issued for the financial statements for all Health cluster agencies.

The COVID-19 pandemic continued to increase the complexity and number of accounting matters faced by the cluster. The total gross value of corrected misstatements in 2021–22 was $353.3 million, of which $186.7 million related to an increase in the impairment provision for Rapid Antigen Tests (RATs).

A qualified audit opinion was issued on the Annual Prudential Compliance Statement related to five residential aged care facilities. There were 20 instances (19 in 2020–21) of non-compliance with the prudential responsibilities within the Aged Care Act 1997.

What the key issues were

The total number of matters we reported to management across the cluster decreased from 116 in 2020–21 to 67 in 2021–22. Of the 67 issues raised, four were high risk (three in 2020-21) and 37 were moderate risk (57 in 2020–21). Nearly half of all control deficiencies reported in 2021–22 were repeat issues.

Three unresolved high-risk issues were:

  • COVID-19 inventories impairment – we continued to identify issues relating to management’s impairment model which relies on anticipated future consumption patterns. RATs had not been assessed for impairment.

  • Asset capitalisation threshold – management has not reviewed the appropriateness of the asset capitalisation threshold since 2006.

  • Forced-finalisation of HealthRoster time records – we continued to observe unapproved rosters being finalised by system administrators so payroll can be processed on time. 2.6 million time records were processed in this way in 2021–22.

What we recommended

  • COVID-19 inventories impairment – ensure consumption patterns are supported by relevant data and plans.

  • Assets capitalisation threshold – undertake further review of the appropriateness of applying a $10,000 threshold before capitalising expenditure on property, plant and equipment.

  • Forced-finalisation of HealthRoster time records – develop a methodology to quantify the potential monetary value of unapproved rosters being finalised.

This report provides Parliament and other users of Health cluster (the cluster) agencies' financial statements with the results of our audits, analysis, conclusions and recommendations in the following areas:

  • financial reporting

  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision-making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Health cluster (the cluster) for 2022.

Section highlights

  • Unqualified audit opinions were issued for all cluster agencies required to prepare general purpose financial statements.

  • The total gross value of corrected monetary misstatements for 2021–22 was $353.3 million, of which, $186.7 million related to an increase in the impairment provision for Rapid Antigen Tests.

  • A qualified audit opinion was issued on the ministry's Annual Prudential Compliance Statements.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision-making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the cluster.

Section highlights

  • The total number of internal control deficiencies has decreased from 116 in 2020–21 to 67 in 2021–22. Of the 67 issues raised in 2021–22, four were high (2020–21: 3) and 37 were moderate (2020–21: 57); with nearly half of all control deficiencies reported in 2021–22 being repeat issues.

  • The following four issues were reported in 2021–22 as high risk:

    • impairment of COVID-19 inventories

    • inadequate review over the appropriateness of asset capitalisation threshold

    • forced-finalisation of HealthRoster time records

    • COVID-19 vaccination inventories – data quality issue at 31 March 2022.

  • Management of excessive leave balances and poor quality or lack of documentation supporting key agreements continued to be the key repeat issues observed in the 2021–22 financial reporting period.

Appendix one – Misstatements in financial statements submitted for audit

Appendix two – Early close procedures

Appendix three – Timeliness of financial reporting

Appendix four – Financial data

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Audit Insights 2018-2022

Audit Insights 2018-2022

Community Services
Education
Environment
Finance
Health
Industry
Justice
Local Government
Premier and Cabinet
Planning
Transport
Treasury
Universities
Whole of Government
Asset valuation
Cross-agency collaboration
Compliance
Cyber security
Financial reporting
Fraud
Information technology
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Regulation
Risk
Service delivery
Shared services and collaboration
Workforce and capability

What the report is about

In this report, we have analysed the key findings and recommendations from our audit reports over the past four years.

This analysis includes financial audits, performance audits, and compliance audits of state and local government entities that were tabled in NSW Parliament between July 2018 and February 2022.

The report is framed by recognition that the past four years have seen significant challenges and emergency events.

The scale of government responses to these events has been wide-ranging, involving emergency response coordination, service delivery, governance and policy.

The report is a resource to support public sector agencies and local government to improve future programs and activities.

What we found

Our analysis of findings and recommendations is structured around six key themes:

  • Integrity and transparency
  • Performance and monitoring
  • Governance and oversight
  • Cyber security and data
  • System planning for disruption
  • Resource management.

The report draws from this analysis to present recommendations for elements of good practice that government agencies should consider in relation to these themes. It also includes relevant examples from recent audit reports.

In this report we particularly call out threats to the integrity of government systems, processes and governance arrangements.

The report highlights the need for balanced advice to government on options and risks, for transparent documentation and reporting of directions and decisions, and for early and open sharing of information with integrity bodies and audit.

A number of the matters highlighted in this report are similar to those described in our previous Insights Report, (Performance Audit Insights: key findings from 2014–2018) specifically in relation to cyber and information security, to performance measurement, reporting and evaluation, and system and workforce planning and capability.

Fast facts

  • 72 audits included in the Audit Insights 2018–2022 analysis
  • 4 years of audits tabled by the Auditor-General for New South Wales
  • 6 key themes for Audit Insights 2018–2022.

picture of Margaret Crawford Auditor-General for New South Wales in black dress with city skyline as backgroundI am pleased to present the Audit Insights 2018–2022 report. This report describes key findings, trends and lessons learned from the last four years of audit. It seeks to inform the New South Wales Parliament of key risks identified and to provide insights and suggestions to the agencies we audit to improve performance across the public sector.

The report is framed by a very clear recognition that governments have been responding to significant events, in number, character and scale, over recent years. Further, it acknowledges that public servants at both state and council levels generally bring their best selves to work and diligently strive to deliver great outcomes for citizens and communities. The role of audit in this context is to provide necessary assurance over government spending, programs and services, and make suggestions for continuous improvement.

A number of the matters highlighted in this report are similar to those described in our previous Insights Report, (Performance Audit Insights: key findings from 2014–2018) specifically in relation to cyber and information security, to performance measurement, reporting and evaluation, and system and workforce planning and capability.

However, in this report we particularly call out threats to the integrity of government systems, processes and governance arrangements. We highlight the need for balanced advice to government on options and risks, for transparent documentation and reporting of directions and decisions, and for early and open sharing of information with integrity bodies and audit. Arguably, these considerations are never more important than in an increasingly complex environment and in the face of significant emergency events and they will be key areas of focus in our future audit program.

While we have acknowledged the challenges of the last few years have required rapid responses to address the short-term impacts of emergency events, there is much to be learned to improve future programs. I trust that the insights developed in this report provide a helpful resource to public sector agencies and local government across New South Wales. I would be pleased to receive any feedback you may wish to offer.

Margaret Crawford
Auditor-General for New South Wales

Integrity and transparency Performance and monitoring Governance and oversight Cyber security and data System planning Resource management
Insufficient documentation of decisions reduces the ability to identify, or rule out, misconduct or corruption. Failure to apply lessons learned risks mistakes being repeated and undermines future decisions on the use of public funds. The control environment should be risk-based and keep pace with changes in the quantum and diversity of agency work. Building effective cyber resilience requires leadership and committed executive management, along with dedicated resourcing to build improvements in cyber security and culture. Priorities to meet forecast demand should incorporate regular assessment of need and any emerging risks or trends. Absence of an overarching strategy to guide decision-making results in project-by-project decisions lacking coordination. Governments must weigh up the cost of reliance on consultants at the expense of internal capability, and actively manage contracts and conflicts of interest.
Government entities should report to the public at both system and project level for transparency and accountability. Government activities benefit from a clear statement of objectives and associated performance measures to support systematic monitoring and reporting on outcomes and impact. Management of risk should include mechanisms to escalate risks, and action plans to mitigate risks with effective controls. In implementing strategies to mitigate cyber risk, agencies must set target cyber maturity levels, and document their acceptance of cyber risks consistent with their risk appetite. Service planning should establish future service offerings and service levels relative to current capacity, address risks to avoid or mitigate disruption of business and service delivery, and coordinate across other relevant plans and stakeholders. Negotiations on outsourced services and major transactions must maintain focus on integrity and seeking value for public funds.
Entities must provide balanced advice to decision-makers on the benefits and risks of investments. Benefits realisation should identify responsibility for benefits management, set baselines and targets for benefits, review during delivery, and evaluate costs and benefits post-delivery. Active review of policies and procedures in line with current business activities supports more effective risk management. Governments hold repositories of valuable data and data capabilities that should be leveraged and shared across government and non-government entities to improve strategic planning and forecasting. Formal structures and systems to facilitate coordination between agencies is critical to more efficient allocation of resources and to facilitate a timely response to unexpected events. Transformation programs can be improved by resourcing a program management office.
Clear guidelines and transparency of decisions are critical in distributing grant funding. Quality assurance should underpin key inputs that support performance monitoring and accounting judgements. Governance arrangements can enable input into key decisions from both government and non-government partners, and those with direct experience of complex issues.     Workforce planning should consider service continuity and ensure that specialist and targeted roles can be resourced and allocated to meet community need.
Governments must ensure timely and complete provision of information to support governance, integrity and audit processes.          
Read more Read more Read more Read more Read more Read more

 

This report brings together a summary of key findings arising from NSW Audit Office reports tabled in the New South Wales Parliament between July 2018 and February 2022. This includes analysis of financial audits, performance audits, and compliance audits tabled over this period.

  • Financial audits provide an independent opinion on the financial statements of NSW Government entities, universities and councils and identify whether they comply with accounting standards, relevant laws, regulations, and government directions.
  • Performance audits determine whether government entities carry out their activities effectively, are doing so economically and efficiently, and in accordance with relevant laws. The activities examined by a performance audit may include a selected program or service, all or part of an entity, or more than one government entity. Performance audits can consider issues which affect the whole state and/or the local government sectors.
  • Compliance audits and other assurance reviews are audits that assess whether specific legislation, directions, and regulations have been adhered to.

This report follows our earlier edition titled 'Performance Audit Insights: key findings from 2014–2018'. That report sought to highlight issues and themes emerging from performance audit findings, and to share lessons common across government. In this report, we have analysed the key findings and recommendations from our reports over the past four years. The full list of reports is included in Appendix 1. The analysis included findings and recommendations from 58 performance audits, as well as selected financial and compliance reports tabled between July 2018 and February 2022. The number of recommendations and key findings made across different areas of activity and the top issues are summarised at Exhibit 1.

The past four years have seen unprecedented challenges and several emergency events, and the scale of government responses to these events has been wide-ranging involving emergency response coordination, service delivery, governance and policy. While these emergencies are having a significant impact today, they are also likely to continue to have an impact into the future. There is much to learn from the response to those events that will help the government sector to prepare for and respond to future disruption. The following chapters bring together our recommendations for core elements of good practice across a number of areas of government activity, along with relevant examples from recent audit reports.

This 'Audit Insights 2018–2022' report does not make comparative analysis of trends in public sector performance since our 2018 Insights report, but instead highlights areas where government continues to face challenges, as well as new issues that our audits have identified since our 2018 report. We will continue to use the findings of our Insights analysis to shape our future audit priorities, in line with our purpose to help Parliament hold government accountable for its use of public resources in New South Wales.

Appendix one – Included reports, 2018–2022

Appendix two – About this report

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.