Refine search Expand filter

Reports

Published

Actions for Health 2021

Health 2021

Health
Asset valuation
Compliance
Cyber security
Financial reporting
Infrastructure
Internal controls and governance
Procurement

This report analyses the results of our audits of the Health cluster agencies for the year ended 30 June 2021.

Our preferred approach is to table the ‘Report on State Finances’ in Parliament before any other cluster report. This is because the 'Report on State Finances' focuses on the audit results and observations relating to the Total State Sector Accounts, in effect a consolidation of all government agencies. This year the 'Report on State Finances' has been delayed due to significant accounting issues being considered in the Total State Sector Accounts and which may impact the Treasury and Transport clusters.

As there are no outstanding matters relating to audits in the Health cluster impacting the Total State Sector Accounts we have decided to break with normal practice and table this cluster report ahead of the ‘Report on State Finances’.

What the report is about

The results of Health cluster (the cluster) agencies' financial statements audits for the year ended 30 June 2021.

What we found

Unmodified audit opinions were issued for the financial statements of all Health cluster agencies.

The COVID-19 pandemic increased the complexity and number of accounting matters faced by the cluster. The total gross value of corrected misstatements in 2020–21 was $250.2 million, of which $226.0 million were pandemic related.

A qualified audit opinion was issued on the Annual Prudential Compliance Statement. The basis of the qualification related to 19 instances (18 in 2018–19) of non-compliance relating to three of the 20 prudential requirements across five aged care facilities.

What the key issues were

The total number of matters we reported to management across the cluster increased from 112 in 2019–20 to 116 in 2020–21. Of the 116 issues raised in 2020–21, three were high risk (one in 2019–20) and 57 were moderate risk (47 in 2019–20). Nearly one half of the issues were repeat issues.

The three new high-risk issues identified were:

Hotel Quarantine (HQ) fees

The absence of a tailored debt recovery strategy, data integrity issues and uncertainties around future HQ arrangements increased risks around the recoverability of HQ fees from travellers.

COVID-19 inventories

Data errors and anomalies in the impairment model and difficulties forecasting key factors impacting the management of Personal Protective Equipment (PPE) increased uncertainty associated with the valuation and impairment of COVID-19 inventories.

COVID-19 vaccines

The Commonwealth did not provide information about the cost of vaccines provided to NSW free of charge, which required the performance of internal valuations to reflect the consumption of vaccines in the financial statements.

What we recommended

Hotel Quarantine (HQ) fees

Develop a tailored assessment methodology to estimate recoverability of HQ fees and work with Revenue NSW to develop a tailored debt recovery strategy.

COVID-19 inventories

Review the current stocktaking and impairment methodology to incorporate validation of data key to the management of COVID-19 related PPE.

COVID-19 vaccines

Work with the Commonwealth to obtain primary price information on COVID-19 vaccines.

Fast facts

The Health cluster, comprising 15 local health districts, five pillars agencies, two specialty health networks and six shared state-wise services agencies, deliver health services to the people of New South Wales.

  • 100% unqualified audit opinions were issued on agencies' 30 June 2021 financial statements
  • 24 monetary misstatements were reported in 2020–21
  • high risk management letter findings were identified
  • 47.4% of reported issues were repeat issues
  • $23.5b property, plant and equipment as at 30 June 2021
  • $26.8b total expenditure incurred in 2020–21

This report provides Parliament and other users of the Health cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision-making are enhanced when financial reporting is accurate and timely. This chapter outlines our audit observations related to the financial reporting of agencies in the Health cluster (the cluster) for 2021.

Section highlights

  • Unqualified audit opinions were issued for all cluster agencies required to prepare general-purpose financial statements.

  • The total gross value of all corrected monetary misstatements for 2020–21 was $250.2 million, of which $226.0 million were related to complexities arising from the COVID-19 pandemic.

  • A qualified audit opinion was issued on the Ministry's Annual Prudential Compliance Statement.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision-making. This chapter outlines our observations and insights from our financial statement audits of agencies in the Health cluster.

Section highlights

  • The total number of internal control deficiencies has increased from 112 issues in 2019–20 to 116 in 2020–21. Of the 116 issues raised in 2020–21, three were high (one in 2019–20) and 57 were moderate (47 in 2019–20); with nearly one half of all control deficiencies reported in 2020–21 being repeat issues.
  • The complexities arising from accounting for agreements between governments to respond to the COVID-19 pandemic presented three new high risk audit findings with respect to the:
    • expected rate of recoverability of outstanding Hotel Quarantine fees
    • procurement, stocktaking and impairment of COVID-19 inventories
    • valuation and recognition of COVID-19 vaccines received from the Commonwealth Government.
  • Management of excessive leave balances and poor quality or lack of documentation supporting key agreements were amongst the repeat issues observed again in the 2020–21 financial reporting period.

Findings reported to management

The number of findings reported to management has increased, with 47.4 per cent of all issues being repeat issues

Breakdowns and weaknesses in internal controls increase the risk of fraud and error. Deficiencies in internal controls, matters of governance interest and unresolved issues were reported to management and those charged with governance of cluster agencies. The Audit Office does this through our management letters, which include observations, implications, recommendations and risk ratings.

In 2020–21, there were 116 findings raised across the cluster (112 in 2019–20). 47.4 per cent of all issues were repeat issues (38.4 per cent in 2019–20).

A delay in implementing audit recommendations increases the risk of intentional and accidental errors in processing information, producing management reports and generating financial statements. This can impair decision-making, affect service delivery and expose agencies to fraud, financial loss and reputational damage. Poor controls may also mean agency staff are less likely to follow internal policies, inadvertently causing the agency not to comply with legislation, regulation and central agency policies.

The table below describes the common issues identified across the cluster by category and risk rating.

Risk rating Issue
Information technology

Moderate2
7 new,
3 repeat

We identified the need for agencies to improve information technology processes and controls that support the integrity of financial data used to prepare agencies' financial statements. Of particular concern are issues associated with:

  • lack of reviews of user access and privileged user access for
  • HealthRoster
  • Assets and Facilities Management Online
  • vMoney Powerhouse
  • Patient Billing and Revenue Collection system.

Repeat issues included:

  • deficient password controls
  • no independent review for data integrity of any changes made to HealthRoster
  • incomplete reviews of StaffLink User Access.

Low1
4 new,
5 repeat

Internal control deficiencies or improvements

High3

1 new, 

0 repeat

We identified internal control weaknesses across key business processes, including new issues relating to:

  • procurement, stocktaking and impairment of COVID-19 inventories (personal protective equipment)
  • instances where employees' timesheets were approved in advance
  •  monthly reconciliations not reviewed in a timely manner
  • asset revaluation processes at Illawarra Shoalhaven Local Health District.
     

Repeat issues included:

  • forced finalisation of rosters in order to finalise processing of payroll
  • partial repeat issue relating to HealthShare NSW's stocktake process, refer to details in the following section of this report.

Moderate2
6 new,
12 repeat

 Low1
10 new,
4 repeat

Financial reporting

High3

2 new, 
0 repeat

We identified weaknesses with respect to financial reporting in relation to the:

  • expected rate of recoverability of outstanding Hotel Quarantine fees
  • valuation and recognition of COVID-19 vaccines received from the Commonwealth Government
  • application of AASB 16 'Leases'
  • improvement in health agencies' grant register to better support management's accounting treatment under the applicable revenue accounting standards.

Moderate2
6 new,
1 repeat

Low1
8 new,
3 repeat

Governance and oversight
Moderate2
9 new,
5 repeat

We identified opportunities for agencies to improve governance and oversight processes, including:

  • ensure better documentation around governance arrangements for major health capital works delivered by Health Infrastructure
  • absence of documented practices at health agencies level relating to Visiting Medical Officer claims.
     

Repeat issues include:

  • delegations manual for Health Infrastructure remains in draft and has done so since 2017.
Low1
2 new,
2 repeat
Non-compliance with key legislation and/or central agency policies
Moderate2
1 new,
7 repeat

We identified the need for agencies to improve compliance with key legislation and central agency policies, with new findings including:

  • bank signatories list not updated to remove terminated employees
  • subsequent changes made to Junior Medical Officers' approved rosters not approved by an authorised delegate.
     

Repeat issues include:

  • management of excessive annual leave
  • non-compliance with the Government Information (Public Access) Act 2009 (GIPA Act) by Ambulance NSW.
Low1
5 new,
13 repeat

4Extreme risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.
3 High risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.
2 Moderate risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.
1 Low risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.

Note: Management letter findings are based either on final management letters issued to agencies, or draft letters where findings have been agreed with management.

Complexities arising from the COVID-19 response

The 2020–21 audit identified three new high-risk findings

COVID-19 has presented the cluster with several new accounting challenges. New and evolving matters arose from changes to operating conditions, which characterised the 2020–21 financial reporting period. Issues with a high degree of estimation uncertainty will require ongoing attention as the strategies employed to deal with the COVID-19 pandemic evolve.

Expected rate of recovery of outstanding Hotel Quarantine invoices

The estimation of the amount likely to be recovered is complicated not only by the uncertainties that exist regarding the assumptions those estimations rely upon, but also the debt collection processes and strategies put into place to manage the accumulated debtors' balance. Debt collection is not administered by the cluster, but rather Revenue NSW. We observed an absence of a methodology to assess the likelihood of recovery. Instead, Sydney Local Health District was relying on Revenue NSW to develop and execute on a collection strategy. Sydney Local Health District was using the same approach to hotel quarantine debts as it did to other Health receivables. As the approach to managing international borders evolves over time, so too will the cluster's need to develop robust estimation models to assess the likely collectability of debtors. 

Procurement, management and impairment of COVID-19 inventories

$656.2 million of COVID-19 inventories were procured in 2020–21, with $220.2 million consumed; $558.7 million impaired and a further $217.1 million written off. Estimates of the degree to which inventories are expired, not fit for purpose or are faulty is often based on management judgement at all stages in the procurement cycle.

With respect to the stocktaking methodology applied, the following issues were identified:

  • discrepancies noted in the stock bin listing provided for audit
  • discrepancies in the recount sheet generated
  • inconsistent application of the stocktake methodology
  • inconsistent labelling of quarantined stock
  • a lack of an approach for validating stock expiry dates, which is a key input to the impairment calculations.

Although management had developed processes and a methodology to count as well as to assess the level of inventory that was not fit for purpose, ongoing attention to the operating environment that emerges post pandemic will be important in assessing the degree to which existing COVID-19 inventories can be integrated into a ‘business as usual’ model going forward. Further refinement of the key elements of the stocktaking methodology will also be required to ensure that key inputs upon which management relies to calculate the year-end inventory impairment provision can be appropriately validated.

Valuation and recognition of COVID-19 vaccines received from the Commonwealth Government

The 2020–21 financial reporting period saw the Commonwealth acquire COVID-19 vaccines and provide these to state jurisdictions to dispense to their communities. The vaccines, although provided free of charge require recognition. However, Health entities were not responsible for acquiring the vaccines and data on the vaccines' cost was not shared by the Commonwealth. Management undertook a valuation using publicly available data to estimate the value to attribute to the vaccine inventory; developed new systems and leveraged existing pharmacy systems to track physical quantities received from the Commonwealth and ultimately distributed to NSW citizens. As the response to the pandemic evolves, larger quantities, and new lines of vaccine stock will be dealt with, and policy settings will need to adapt when patterns of distribution of those vaccines (e.g., timing of third booster shots) emerge. The Ministry of Health will need to ensure that the valuations applied to the prices of inventory distributed and held in stock are as accurate as possible. This can be done through further refinement of the existing valuation methodology, obtaining price information from the Commonwealth and engaging specialist pharmaceutical valuers.

Emerging trends

Recognition of provisions without sufficient support

Several NSW Health entities raised accruals and provisions in 2020–21, which did not have an appropriate basis for recognition. Liabilities can only be recognised where there is a present obligation to make a payment arising from a past event. A number of these errors remain uncorrected in the financial statements of those entities as they are not material, individually or in aggregate to the financial statements as a whole. Increased training and guidance are required to ensure that treatment within the cluster is consistent and reflects events that have occurred and give rise to obligations.

Treatment of Commonwealth funding

In the 2020–21 and 2019–20 financial reporting periods, we observed prior period errors arising from the treatment of Commonwealth funding. These errors related to recognising revenue under funding agreements entered into with the Commonwealth in the incorrect period. The conditions of these funding arrangements, the transactional information requiring validation and the circumstances when revenue should be recognised are not always clear and can be complex. Early and continuous engagement with the Commonwealth is required to ensure that revenue recognition principles are consistently applied across the cluster.

Key repeat issues

Management of excessive annual leave

NSW Treasury guidelines stipulate annual leave balances exceeding 30 days are considered excess annual leave balances. Managing excess annual leave balances has been reported as an issue for the cluster for more than five years, with the average percentage of employees with excessive leave balances over the last five years being 36.1 per cent (35.5 per cent over five years covering 2015–16 to 2019–20).

The operational demands required to manage the COVID-19 pandemic have presented new challenges for the cluster in trying to manage its excessive leave balances. 39.2 per cent of employees now have excess leave balances at 30 June 2021 (35.4 per cent at 30 June 2020).

The state's leave policy C2020-12 Managing Accrued Recreation Leave Balances requires agencies to manage excessive leave balances to 30 days or less to maintain their workforces physical and mental health.

Accurate time recording

Forced-finalisation of time records by system administrators within HealthRoster remains an issue and we continue to observe time records forced-finalised by system administrators so pay runs can be finalised on a timely basis. During 2020–21, a total of two million (2.2 million in 2019–20) time records were force approved, which represents 5.7 per cent of total time records (6.9 per cent in 2019–20).

Existence, completeness and accuracy of key agreements

Delivery of major capital projects

Health Infrastructure (a division of the Health Administration Corporation) is responsible for the delivery of major capital projects with a budgeted spend of more than $10.0 million. Health Infrastructure oversee the planning, design, procurement, and construction phases. Capital works in progress are recognised in the financial statements of the health entity that intends to use those assets upon completion. The health entities recognise both the capital work in progress and the revenue associated with the capital funding from the Ministry for the construction of the assets. Capital funding is currently agreed with health entities as part of the annual Service Agreement. The assumption that the health entities control the assets during their construction is consistent with Health Infrastructure's role as an agent for the health entity and the Ministry's policy directive PD2020-033 'Management and control of Health Administration Corporation owned Real Property'.

We continued to observe a lack of clarity regarding agreements between Health Infrastructure, the Ministry and the cluster agency that will eventually receive the completed asset. This can lead to confusion and uncertainty around the rights and obligations of each party to the transaction.

Cross border patient funding arrangements

When patients require medical care in a jurisdiction where they are not generally domiciled, there are arrangements in place to provide funding to support cross border patient treatments. We have previously observed that agreements between NSW and other jurisdictions have not been finalised, and this continues to be the case. In the case of Victoria, no agreement has been finalised for the past seven years.

We continue to note that the cluster has long outstanding receivables and payables with other states. The absence of formal agreements between the states hampers the settlement of the debts relating to the treatment of cross border patients. The following table shows the status of Cross Border Agreements between NSW and other jurisdictions:

States 2014–15 2015–16 2016–17 2017–18 2018–19 2019–20 2020–21
Queensland Signed Signed Signed Signed Signed Not finalised Not finalised
Victoria Not finalised Not finalised Not finalised Not finalised Not finalised Not finalised Not finalised
Australian Capital Territory Signed Signed Signed Signed Signed Signed Not finalised
South Australia Signed Signed Signed Signed Signed Signed Not finalised
Tasmania Signed Signed Signed Signed Signed Signed Not finalised
Northern Territory Signed Signed Signed Signed Signed Signed Not finalised
Western Australia Signed Signed Signed Signed Signed Signed Not finalised

Albury Base Hospital

Albury Base hospital is located on the border of NSW and Victoria and services residents of both states. Documentation supporting the extension of the expired Intergovernmental Agreement 2009–2017 between NSW and Victoria in relation to the integration of health services in Wodonga and Albury could not be located.

Appendix one – Misstatements in financial statements submitted for audit

Appendix two – Early close procedures

Appendix three – Timeliness of financial reporting

Appendix four – Financial data

 

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for COVID Intensive Learning Support Program

COVID Intensive Learning Support Program

Education
Management and administration
Project management
Service delivery
Workforce and capability

What the report is about

This audit examined a state-wide program to provide small-group tuition to students disadvantaged by the move to learning from home during 2020.

The audit assessed the design and implementation of the program.

What we found

The program design was based on research and data showing learning loss during 2020. 

The department rapidly planned and developed the policy design and guidelines for schools. 

Governance arrangements matured during program delivery.

The department changed the models for funding schools but did not clearly explain the reasons for doing so.

Government schools with over 900 students were disadvantaged by the funding model compared to smaller schools. 

Guidelines, resources and professional learning helped schools implement the program.

Staff eligibility for the program was expanded after reported difficulties in recruiting qualified teachers in some areas. 

Online tuition and third-party provider options were developed throughout the program.

There were issues with the quality and timeliness of data used to monitor school progress. 

Evaluation arrangements were developed early in the program.

Data limitations mean the evaluation will not be able to fully assess all program objectives.

What we recommended

  1. Distributing funds between schools more equitably and improving communication of the funding methods. 
  2. Clearer communication about the intended targeted group of students.
  3. Reviewing the time needed to administer the program.
  4. Improve support for educators other than qualified teachers.
  5. Offer the online tuition program to more schools.
  6. Analysis of the effects of learning from home during 2021 across equity groups and geographic areas.
  7. Working with universities to increase use of pre-service teachers in the program.

The report also identifies lessons learned for future programs.
 

Fast facts

  • $337m in total program funding. $289 million for government schools and $31 million for non government schools
  • 12 days to develop the policy and provide costings to Treasury 
  • 290,000 targeted students in government schools and 31,000 in non government schools
  • 80% of schools were providing small group tuition by the target start date of Week 6, Term 1
  • 2–4 months was the estimated student learning loss from the move to learning from home during 2020
  • 7,600 tutors engaged in the program as at September 2021.

The NSW Government announced the COVID Intensive Learning Support Program on 10 November 2020, as part of the 2020–21 NSW Budget. The primary goal of the $337 million program was to deliver intensive small group tuition for students who were disadvantaged by the move to remote and/or flexible learning, helping to close the equity gap. It included:

  • $306 million to provide small-group tuition for eligible students across every NSW Government primary, secondary and special purpose school
  • $31.0 million for around 400 non-government schools to provide small-group tuition to students with the greatest levels of need.

The objective of this audit was to assess the effectiveness of the design and implementation of the COVID Intensive Learning Support Program (the program). To address this objective, the audit assessed whether the Department of Education (the department):

  • effectively designed the program and supporting governance arrangements
  • is effectively implementing the program.

This audit focuses on activities between October 2020 and August 2021, which aimed to address the first session of learning from home in New South Wales. From August to October 2021, students in many areas of New South Wales were learning from home again, but this second period has not been a focus of this audit. On 18 October 2021, the NSW Government announced the program would be extended into 2022.

Conclusion

The COVID Intensive Learning Support Program was effectively designed to help students catch up on learning loss due to the interruptions to schooling caused by COVID-19. The department rapidly stood up a taskforce to implement the program and then developed supporting governance arrangements during implementation.

Most students in New South Wales were required to learn from home for at least seven weeks during 2020 due to the impact of the Novel-Coronavirus (COVID-19). The department researched, analysed and advised government on several options to address the learning loss that resulted. It recommended small group tuition as the preferred option as it was supported by available evidence and could be rolled out at scale with speed. It identified risks of ensuring an adequate supply of educators and options to address those risks. Consistent with its analysis of where the impact of the learning loss was most severe, the department proposed to direct funding to schools with higher concentrations of students from the most disadvantaged backgrounds.

The department established a cross-functional taskforce to conduct detailed planning and support program implementation. Short timeframes meant the taskforce initially sought approval for key decisions from the program sponsor and existing oversight bodies on an as-needed basis before dedicated program governance arrangements were formalised. Once established, the governance body met regularly to oversee program delivery.

The COVID Intensive Learning Support Program is being effectively implemented. The department has refined the program during rollout to respond to risks, issues and feedback from schools. Issues with how schools enter data into department systems have affected the timeliness and accuracy of program monitoring information.

The department provided schools with guidelines, example models of delivery, systems to record student progress and professional learning. Around 80 per cent of schools had begun delivering tuition under the program by the target date. Schools reported issues with sourcing qualified teachers as a key reason they were unable to start the program by the expected date. In response, the department expanded the type of staff schools could employ, developed an online tuition program, and allowed schools to engage third-party providers to help schools that had difficulty finding qualified teachers for the program.

The department used existing systems to monitor school progress in implementing the program. This reduced the administrative burden on schools, but there were several issues with data quality and timeliness. The program included a mid-year review point to check whether schools were on track to spend their funding. This helped focus schools on ensuring funding would be spent and allowed for redistribution between schools.

The department considered program evaluation early in policy design and planning. It embedded an evaluator on the taskforce and expanded a key assessment program to help provide evidence of impact. A process and outcome evaluation is underway which will help inform future delivery. The evaluation will examine educational impacts for students participating in the program but it has not established methods to reliably assess the extent to which the program has met a goal to help 'close the equity gap' for students.

This chapter considers how effectively the COVID Intensive Learning Support Program (the program) was designed and planned for implementation.

This chapter considers how effectively the COVID Intensive Learning Support Program was implemented over our period of review (Terms 1 and 2, 2021).

Appendix one – Response from agency

Appendix two – About the audit

Appendix three – Performance auditing

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #358 - released (15 December 2021).

Published

Actions for Education 2021

Education 2021

Education
Asset valuation
Compliance
Financial reporting
Information technology
Internal controls and governance
Procurement

This report analyses the results of our audits of the Education cluster agencies for the year ended 30 June 2021.

Our preferred approach is to table the ‘Report on State Finances’ in Parliament before any other cluster report. This is because the 'Report on State Finances' focuses on the audit results and observations relating to the Total State Sector Accounts, in effect a consolidation of all government agencies. This year the 'Report on State Finances' has been delayed due to significant accounting issues being considered in the Total State Sector Accounts and which may impact the Treasury and Transport clusters.

As there are no outstanding matters relating to audits in the Education cluster impacting the Total State Sector Accounts we have decided to break with normal practice and table this cluster report ahead of the ‘Report on State Finances’.

What the report is about

The results of the Education cluster (the cluster) agencies' financial statements audits for the year ended 30 June 2021.

What we found

Unmodified audit opinions were issued on the Department of Education (the department), the NSW Education Standards Authority and the NSW Skills Board's financial statements.

An 'other matter' paragraph was included in the Technical and Further Education Commission's (the TAFE Commission) audit opinion drawing attention to legislative non-compliance concerning financial delegations during the reporting year.

The number of misstatements identified in the financial statements of cluster agencies decreased from 14 in 2019–20 to seven.

What the key issues were

The department and the TAFE Commission revalued their land assets this year, recognising collective increases of $863.8 million.

The department and the TAFE Commission are not scheduled to perform comprehensive revaluations of their buildings until 2022–23. Construction costs, which are a key input in their current replacement cost valuation methodologies for buildings, may have increased by an estimated nine per cent since the last comprehensive revaluation in 2017–18 based on broad based indices used by the department and the TAFE Commission. While the estimated index increase indicates the fair value of buildings may exceed the carrying values, the use of such high-level indicators has a degree of estimation uncertainty due to the specialised nature of the assets. Therefore, both agencies did not adjust the values of their buildings.

The number of issues we reported to management decreased. Fifty per cent of issues were repeated from prior years.

Of the 11 newly identified moderate rated issues, seven related to internal control deficiencies, with six identified in procurement and payroll controls.

What we recommended

The department and the TAFE Commission reconsider policy settings governing the frequency of revaluations; and refine and consider the outcomes of interim fair value assessments to ensure asset carrying values reflect fair value at each balance date.

Cluster agencies should prioritise and action recommendations to address internal control deficiencies.

Fast facts

The Education cluster, comprising four agencies, administers and delivers education and training services for NSW students, workers and industry.

  • $38.6b property, plant and equipment as at 30 June 2021
  • $21.2b total expenditure incurred in 2020–21
  • 100% unqualified audit opinions were issued on agencies’ 30 June 2021 financial statements
  • 22 moderate risk management letter findings were identified and reported to management
  • monetary misstatements were reported in 2020–21
  • 50% of reported issues were repeat issues

This report provides Parliament and other users of the Education cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Education cluster (the cluster) for 2021.

Section highlights

  • Unqualified audit opinions were issued on the financial statements of cluster agencies.

  • Comprehensive revaluations of the Department of Education (the department) and the Technical and Further Education Commission's (the TAFE Commission) land assets resulted in collective net increases of $863.8 million to the carrying values of these entities' land assets.

  • Fair value assessments, based on broad indices, of the department and the TAFE Commission's buildings, indicated that replacement costs may have increased by an estimated nine per cent. Whilst the next comprehensive valuation is not scheduled until 2022–23, the department and the TAFE Commission will need to consider the outcomes of their annual assessments to ensure that the carrying amounts continue to reflect the fair value of these specialised assets in their financial statements.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the Education cluster.

Section highlights

  • The 2020–21 audits identified 22 moderate issues across the cluster. Eleven moderate risk issues were repeat issues and related to general and application information technology controls and deficiencies in procurement and payroll practices.
  • Of the 11 newly identified moderate rated issues, seven related to internal control deficiencies and improvements, with identified deficiencies in procurement and payroll accounting for six.
  • A high-risk issue identified in 2019–20 relating to the Department of Education's (the department) monitoring of privileged user activity has largely been addressed.

Findings reported to management

The number of findings reported to management has decreased. Fifty per cent of all issues were repeat issues

Breakdowns and weaknesses in internal controls increase the risk of fraud and error. Deficiencies in internal controls, matters of governance interest and unresolved issues were reported to management and those charged with governance of agencies. The Audit Office does this through management letters, which include observations, related implications, recommendations and risk ratings.

In 2020–21, there were 28 findings raised across the cluster (33 in 2019–20). Fifty per cent of all issues were repeat issues (45 per cent in 2019–20).

The most common repeat issues related to weaknesses in controls over information technology general controls, application controls, and identified deficiencies in procurement and payroll practices.

A delay in implementing audit recommendations increases the risk of intentional and accidental errors in processing information, producing management reports and generating financial statements. This can impair decision-making, affect service delivery and expose agencies to fraud, financial loss and reputational damage. Poor controls may also mean agency staff are less likely to follow internal policies, inadvertently causing the agency not to comply with legislation, regulation and central agency policies.

The table below describes the common issues identified across the cluster by category and risk rating.

Risk rating Issue
Information technology

Moderate2
2 new,
6 repeat

The financial audits identified areas for agencies to improve information technology processes and controls that support the integrity of financial data used to prepare agencies' financial statements. Of note were deficiencies identified in:
  • agencies' user access administration and change management procedures, notably in the timing and frequency of managerial reviews over the granting and revocation of access to key systems relevant to financial reporting
  • application controls and segregation of duties in payroll systems, allowing certain users to access or modify employee records as well as process payroll
  • system configurations whereby preparers of manual journals can also post without a secondary review
  • password reviews undertaken that align with approved password guidelines
  • the monitoring of privileged user activities.

Low1
2 new,
1 repeat

Internal control deficiencies or improvements

Moderate2
7 new,
4 repeat

The financial audits identified internal control weaknesses across key business processes relevant to financial reporting. Of note were deficiencies identified in:
  • the adequacy of monitoring and oversight activities over the use of multiple financial delegation configurations in finance systems for specific users
  • the timely recording and approval of overtime claims and higher duties allowances
  • the timely finalisation of policies and procedures
  • procurement practices including a high proportion of retrospective purchase orders and the timely receipting of goods and services
  • the timely notification of employee resignations or employees applying for leave without pay, leading to salary overpayments
  • the management of excessive annual leave balances
  • the extent of review or approval of changes to lease information.

 Low1
1 new,
2 repeat

Financial reporting

Moderate2
2 new,
1 repeat

The financial audits identified:
  • opportunities for agencies to strengthen their financial preparation processes to facilitate a timelier and more efficient year-end audit
  • the need for agencies with non-financial assets subject to fair value to reconsider policy settings governing the frequency of revaluations; and to refine and consider the outcomes of interim fair value assessments to ensure asset carrying values reflect fair value at each balance date.

Low1
0 new,
0 repeat


3 High risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.
2 Moderate risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.
1 Low risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.

 
Note: Management letter findings are based on final management letters issued to agencies.

The department continues to address recommendations to improve monitoring of privileged user access

Privileged users have higher levels of access to systems, and in some instances, may include access that can bypass segregation of duty controls. If reviews of access logs are not fully embedded in the control environment, the risk of unauthorised transactions occurring and not being detected in a timely manner is elevated.

In 2019–20 a high-risk issue was reported at the department relating to the inadequate monitoring and follow up of privileged user activity in its enterprise resource planning system – SAP. This year the department has largely addressed our findings by initiating a review of the identified instances of privileged user activity and establishing periodic oversight controls. There remains a need to improve the timeliness and completeness of these newly implemented controls.

Data analytics identified the root cause of internal control deficiencies in procurement and payroll

Our 2020–21 agency management letters identified seven new moderate risk internal control deficiency matters, of which six related to payroll and procurement.

To enhance our financial statement audit of the department we applied data analytics over elements of the department's procurement and payroll control processes. Our procedures, conducted over periods across the financial year, helped identify the following:

  • a low level of compliance with procurement practices requiring the creation of purchase orders before invoices are received. The root cause was a lack of understanding by agency staff of the procurement processes
  • transactions related to previous years being recorded in the current year. The root cause was a lack of understanding of the three-way matching process and the goods received/not invoiced facilities within SAP
  • negative payments in fortnightly pay runs, predominantly representing deductions to recover salary payments made in error. The root cause was the lack of timeliness in notifying payroll for cessation of employment, or for employees undertaking secondments who should have been classified as being on leave without pay.
 
 

Recommendation

We recommend cluster agencies prioritise and action recommendations to address the internal control deficiencies outlined above. 

Appendix one – Early close procedures

 

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Published

Actions for Access to health services in custody

Access to health services in custody

Health
Justice
Management and administration
Service delivery

What the report is about

This audit assessed whether adults in custody have effective access to health services. The audit examined the activities of Justice Health and Corrective Services NSW.

What we found

The majority of custodial patients receive timely health care, but a small proportion of patients are not receiving care within target timeframes.

Eleven per cent of scheduled health appointments are not attended, and agencies can do more to understand the reasons for non-attendance.

Demand for mental health care exceeds service capacity and some patients are held in environments not appropriate for their needs.

Justice Health's information systems do not support the effective transfer of medical records as patients move around the prison network.

Not all patients are released from custody with a discharge plan.

Justice Health's system managers do not receive sufficiently detailed reports to understand strategic risks or opportunities to improve access to health services.

Public and private prison health operators do not report against consistent performance measures.

Justice Health is mandated to assess health services in private prisons. This conflicts with its role as a contracted provider of health services in the private prison system.

What we recommended

Enhanced reporting on patient access to health services, to identify risks and challenges across key service areas.

Identification and implementation of the improvements required for information to be shared across the custodial network and with external health providers.

Development of a framework to govern and monitor costs for patient health escorts and movements.

Development of a framework to govern responsibilities for mental health services.

Progression of infrastructure plans that address the lack of specialist accommodation for mental health patients and aged and frail patients.

Collaboration to align the performance measures to enable benchmarking between public and private prison health services.

Action to remediate the conflicting monitoring arrangements of public and private prison health operators.

Fast facts

  • 13,063 adults in the NSW prison population at 31 March 2021
  • 31,750 unique adult patients provided with medical care in 2020
  • 770,000 occasions of medical care provided by Justice Health in 2020
  • 50% of all health treatment in prisons is provided to patients who receive immediate medical attention
  • 60,000 appointments for health care in prisons were not attended in 2020
  • 94,810 occasions of psychology service provided by Corrective Services in 2020

Access to health services in custody

This audit examined whether adults in the New South Wales public prison system have effective access to health services. In making this assessment, we considered whether Justice Health and Corrective Services NSW effectively cooperate and coordinate so that patients have timely access to health services, systems and practices support continuity of care, and access to health services is monitored and reviewed.

As part of this audit, we assessed actions undertaken by Justice Health and Corrective Services NSW in managing the first COVID-19 outbreak in 2020. However, due to the timing of this audit report, this audit does not report on the agencies’ response to managing the current outbreak of COVID-19 in September 2021.

Health services in New South Wales prisons are delivered by both public and private operators. The public prison system is made up of 33 correctional centres and the Long Bay Hospital. All health services in the public prison system are delivered by the Justice Health and Forensic Mental Health Network (Justice Health).

In the public prison system, Justice Health is responsible for the clinical care of patients with physical and mental illnesses. Clinicians provide health assessments, treatments, medication management, and some counselling services in prison health clinics. Patients are triaged by primary health nurses and if they require treatments or medication, they are referred to prison‑based doctors including specialists or other clinicians. Patients requiring complex or emergency care are transferred to hospitals or other specialty services outside the prison complex.

Private operators deliver health services in three private prisons through contract arrangements with Corrective Services NSW. Justice Health delivers health care at one correctional centre via a contract arrangement with Corrective Services NSW. In total, contracted health service operators deliver health care to approximately 25 per cent of the New South Wales prison population.

Justice Health is required by law to monitor the performance of contracted health service providers in New South Wales prisons, including services provided at the John Morony Correctional Centre. The Auditor‑General’s mandate does not permit a direct examination of information held by private sector entities, however this audit does assess the effectiveness of Justice Health's role in monitoring health services in private prisons.

Corrective Services NSW is responsible for security in public prisons, including the facilitation of patient access to health care at prison health clinics and the transfer of patients to hospitals and other health services outside of the prison environment. Corrective Services NSW also delivers behaviour‑based psychology services. Some are delivered as behaviour modification courses that aim to reduce criminal and offending activity amongst the prison population. These programs may be linked to parole or other custodial conditions. Other psychology services include counselling for people with self‑harming or suicidal behaviours.

Research from the Australian Institute of Health and Welfare indicates that people in custody are more likely than the general population to be affected by chronic and acute illnesses, including higher rates of mental illness and communicable diseases1. In March 2021, there were 13,063 adults in custody in New South Wales.

The objective of this performance audit was to assess whether adults in the public prison system have effective access to health services. In making this assessment, we considered whether Justice Health and Corrective Services NSW effectively cooperate and coordinate so that:

  • patients have timely access to health services
  • systems and practices support the continuity of health care
  • access to health services is monitored, reviewed, and reported across the network. 

1The Australian Institute of Health and Welfare, Adult Prisoners Snapshot, 11 September 2019. At: https://www.aihw.gov.au/reports/australias-welfare/adult-prisoners.
 

Conclusion

Justice Health delivers timely health care to adult custodial patients who need routine medications and treatment for minor medical conditions. Justice Health also delivers timely care to patients requiring urgent medical attention, including emergency transfers to hospitals. However, Justice Health does not always meet recommended timeframes to deliver health care to patients who are waitlisted for treatment from doctors and other medical specialists, or for those waiting for assessments and prescriptions.

In 2020, Justice Health provided over 770,000 instances of medical care to adults in the New South Wales prison network. Approximately half of this health care was delivered on the spot, by nurses who dispensed routine medications or treated the minor medical ailments of 'walk‑in' patients.

Doctors, specialists, and nurse clinicians delivered the other half of prison health care via scheduled health appointments. In most cases, this health care was timely, except for a proportion of patients who were waiting for time‑critical treatments, prescriptions, or assessments. In 2020, 40 per cent of patients identified as 'Priority 1' did not receive care within the recommended three‑day timeframe. Patients waiting for these appointments constitute a small proportion of all health care delivered in 2020, at about one per cent of all health care. Nevertheless, the needs of Priority 1 patients are significant, and Justice Health does not know whether the prolonged wait times led to deteriorations in health outcomes, or other adverse outcomes.

Close to 1,000 patients required emergency treatment in 2020, and were transferred to hospitals as soon as their medical condition was identified by prison health staff.

Justice Health uses multiple information management systems that are not sufficiently linked to transfer all patient medical records and appointment information when patients are moved across the prison system. Appointment schedules and patient medications are transferred through manual processes. There is also limited information sharing with community health providers when custodial patients enter or leave custody.

Justice Health has multiple and parallel information systems, including paper‑based medical records. These systems are not effective for information sharing across the prison system as patients are moved between prisons and facilities at frequent intervals. Clinical staff are not always alerted when a patient is moved from one prison to another, or released from custody after a court appearance. This impacts on the effective scheduling and management of prison health appointments, and the exchange of patient health records across the prison network.

Justice Health's information systems and protocols also do not support the effective exchange of information with external health providers. The transfer of health information is a manual process and there can be significant delays in providing or receiving information from community health providers when custodial patients enter prisons or are released.

Corrective Services NSW and Justice Health executives do not receive sufficiently detailed information or reports to understand the impediments to health service accessibility and to enable system improvements. There is also limited joint planning between the two agencies to improve patient access to health care. The governance and monitoring arrangements for public and private prison health services are flawed and create a conflict of interest for Justice Health as both a service provider and a system monitor.

Justice Health's data dashboard assists managers and clinicians to understand and manage the wait times for health appointments at the prison service level. However, reporting to senior executives on wait times for health services is insufficiently detailed to indicate risks or opportunities for strategic improvement. Corrective Services NSW does not produce sufficiently detailed reports on the costs of transferring custodial patients to health appointments outside the prison network to improve efficiencies or understand trends over time.

There is not enough system‑level planning between Corrective Services NSW and Justice Health to optimise patient attendance at health appointments. Greater collaboration is needed to improve appointment scheduling through notifications about patient movements across the prison network.

There are limitations in the performance monitoring of public and private prison health services. It is not possible to benchmark or compare public and private prison health services and outcomes because the two systems do not report against common Key Performance Indicators.

While Justice Health has taken steps to maintain independence and transparency in its legislated role as assessor of health services in private prisons, there is an inherent conflict of interest in this monitoring role, as Justice Health is also a contracted provider of health services in the private prison system.

1. Key findings

The majority of custodial patients receive timely health care, but a small proportion of patients with priority appointments are not receiving care within target timeframes

Approximately half of all health care provided by Justice Health is immediate. It is delivered to 'walk‑in' patients as soon as they present at prison health clinics. Most of these patients are receiving daily medications, while a small proportion require urgent or immediate care for injuries or illnesses. The other half of prison health care is delivered via scheduled appointments. Patients waiting for health appointments are given a priority rating according to the time within which they should be seen by a clinician.

Patients requiring the most time‑critical care are given a Priority 1 rating. These patients should receive treatment within one to three days. In December 2020, the average wait time for Priority 1 treatment was five and a half days, almost double the target. This is an improvement on wait times in June 2019, when the average wait time was just over 13 days. Justice Health does not assess or measure the impacts of delayed care on these patients.

According to Justice Health, the high numbers of ‘walk‑ins’ contribute to increased wait times for medical appointments. In addition, some specialty health clinics operate weekly, which means that patients cannot be seen by specialists within a one to three‑day timeline. Security events such as prison lockdowns can also contribute to increased wait times, as they limit the access that patients have to prison health clinics during out‑of‑cell hours.

If patients need emergency medical treatment, they are transferred to hospitals in line with Justice Health's policy. In 2020, just over 1,000 patients were transferred to hospital for emergency medical care.

A significant proportion of prison health appointments are not attended, and not enough is being done to understand the reasons, or to improve attendance rates

In 2020, 11 per cent of all scheduled health appointments in prison clinics were not attended. This amounts to approximately 60,000 appointments over the year. Non‑attended appointments have flow‑on impacts on wait times and backlogs for scheduled health appointments. Understanding why they occur is necessary to improve efficiencies in scheduling and patient access to health services.

In 2020, the most common reason for non‑attended health appointments was: 'patient unable to attend'. Justice Health clinicians use this when patients do not arrive at the prison health clinic at the scheduled time, and clinicians lack any other information to explain the non‑attendance.

The second most common recorded reason for non‑attended appointments was: 'cancelled by Corrective Services NSW'. These cancellations are due to operational or security reasons, including prison lockdowns. Data from Justice Health indicates that in 2020, there were an average of 12 lockdowns per week across New South Wales prisons.

A range of factors can impact on patient attendance at appointments, some of which are unavoidable. That said, more can be done to understand and reduce non‑attendance. For example, there is potential for Corrective Services NSW to implement tighter protocols to update information about patient availability on the daily movement lists. This might include checking whether patients are willing to attend appointments. Similarly, there is potential for Justice Health clinicians to implement tighter protocols to check patient lists ahead of scheduled appointments, and to re‑schedule appointments where patients are unavailable.

Demand for mental health care exceeds service capacity and some patients are held in environments that are not appropriate for their needs

There is a high demand for mental health services in New South Wales prisons. In March 2021, at least 143 mental health patients were waiting for access to an acute or sub‑acute mental health unit across the New South Wales prison system. The average wait time for a mental health facility was 43 days. Seventeen patients had wait times of over 100 days. Patients waiting for sub‑acute mental health services had longer wait times than those waiting for acute mental health services.

There are limited mental health beds for women across the New South Wales prison network. There are ten allocated beds for women at the Mental Health Screening Unit at Silverwater Correctional Complex, and no allocated beds for women at Long Bay Hospital.

A lack of bed availability in the Forensic Hospital means that, as of February 2021, 63 forensic patients were being held in mental health facilities in mainstream prisons, when they should have been accommodated in the Forensic Hospital. Some of these forensic patients have been held in mainstream prison facilities for decades.

Cross‑agency co‑operation and planning is required to identify and build infrastructure that will reduce wait times for mental health beds. Over several years, Justice Health has developed, reviewed, and worked to progress a strategic plan for NSW Forensic Mental Health that includes enhanced mental health bed capacity across the NSW system. The latest version of this strategic plan remains in draft and has yet to be approved by the NSW Ministry of Health.

In 2016, Corrective Services NSW commenced a Prison Bed Capacity Program. It was focussed on enhancing capacity across the prison system and did not include specialist health beds. More recently, Corrective Services NSW has been developing a business case to improve the provision of specialist health care facilities across the network, including mental health facilities.

Justice Health's clinical information systems do not support the effective transfer of health appointments or medication records as patients are moved to new prison locations

Justice Health's clinical information systems are multiple and complex. There are five health information systems that include a mix of electronic and paper‑based records. Information management systems contain clinical records, appointment information, medication records, dental records, and specialist health information. Corrective Services NSW maintain separate information systems relating to prison records and psychology treatment information.

The transfer of people across different correctional centres is a frequent occurrence. In 2020, there were over 41,000 movements between correctional centres. People are transferred for a range of reasons including for security purposes, or to be located closer to hospitals or specialist health services.

Justice Health receives a list of patient transfers one day prior to transfer. Nurses are required to prepare medications and clinical handovers for patients with complex health conditions. These handovers are verbal, however short timeframes mean that handover is not always possible.

While each patient's electronic health records are available across the network, transfer of appointment waitlists must be done manually. There is no automatic alert within the information systems to tell staff that a patient has been moved to another prison. There is a risk that if appointment records are not manually updated, or if staff at destination clinics are not contacted, then appointments will be overlooked.

Justice Health is working with eHealth NSW to develop an improved Electronic Medication Management (EMM) program with expected delivery in late 2021. The EMM has potential to improve the transfer of patient medication records, but it will not fully remediate all inefficiencies of the current systems.

Corrective Services NSW and Justice Health do not engage in sufficient joint planning to improve efficiencies in transports or escorts to health services

Corrective Services NSW and Justice Health do not engage in joint system‑level planning to mitigate the risks and the costs associated with transferring patients to health clinics in prisons, or non‑prison‑based health care. There are no protocols, and limited sharing of information to improve efficiencies in planning and coordinating patient transfers.

Corrective Services NSW does not collate or report on the costs of transporting patients to hospitals and specialist care. While there is data on the overall cost of medical escorts, estimated to be $19.9 million in 2020, Corrective Services NSW is not able to disaggregate this data to determine the reasons for transfers or the system‑level costs. For example, Corrective Services NSW does not know how many prison lockdowns occur when hospital transfers are required.

Medical escorts to specialist health services and hospitals increase the costs to the prison system and contribute to risks in prison management. Medical escorts contributed to 16 per cent of metropolitan prison lockdowns at the peak in 2018, though escort numbers have since been declining. Some Local Health Districts report significant concerns around safety incidents and assaults on staff during medical escorts to hospital.

Corrective Services NSW does not know if transport costs have increased since the 2016 Prison Bed Capacity Program which expanded prison beds in regional New South Wales. To date, there has been no assessment of the cost of taking patients to tertiary hospitals or specialist services. Corrective Services NSW has identified this as an area for improvement.

Justice Health's system managers do not receive sufficiently detailed reports on wait times for health care, to understand strategic risks or opportunities for system improvement

Justice Health's senior executives receive monthly reports on patient wait times for services in prison health clinics. These reports contain headline data about the numbers of days that patients wait for scheduled health appointments by their allocated priority level. Wait time data are averaged across all New South Wales prison health clinics. With some exceptions, almost all executive level reports describe system‑wide appointment wait times without offering further specific detail. For example, there is limited information which would allow managers to understand the performance of specialty health groups, or to make any comparative analysis of the performance of different prison facilities.

Executive reports are also not detailed enough to indicate whether prisons with particular security classifications offer greater or lesser access to health services. It is not possible to assess whether patients in metropolitan or regional prisons have different levels of health service access. This prevents managers from identifying strategic risks across the prison network, targeting resources to the areas of greatest risk, and making strategic improvements in system performance.

Trend data on wait times for the different health specialty areas is also required to enable senior managers to compare wait times across prison facilities, security classifications, and localities.

In response to the preliminary findings of this audit, Justice Health has made some improvements to its executive‑level wait time reports. This includes additional detail on health appointment wait times by prison facilities and wait times by health specialty areas.

It is not possible to compare or benchmark the performance of public and private prison health operators or to compare prison health against community health standards

It is not possible to compare or benchmark the performance of the public and private prison health operators in New South Wales using the current Key Performance Indicator (KPI) data. KPI data do not correlate across the public and private systems.

Justice Health reports to the Ministry of Health on 44 prison health KPIs. The 44 KPIs for the public prison system do not align with the seven KPIs the private health operators report against in their contracts with Corrective Services NSW. This means that public and private operators focus on different service areas. For example, private operators have a performance measure for ensuring that custodial patients are provided with release plans. Justice Health does not have a similar measure.

The KPI specifications for the private prison health system were developed by Corrective Services NSW with input from the Ministry of Health. The KPI specifications for the public prison health system were developed by the Ministry of Health in collaboration with Justice Health. There is no rationale for the difference in performance indicators across the public and private systems.

Private providers currently deliver prison services to 25 per cent of the prison population of New South Wales. This proportion has been increasing since 2016. Public and private health operators deliver comparable health services so there is scope to compare performance across the systems.

Justice Health aligns its standard for prison health services with a 'community’ standard of health care access. However, with existing health monitoring measures, it is not possible to assess how well Justice Health is tracking against community health standards with available data from most health specialties.

There is an inherent conflict of interest in Justice Health's monitoring role of health services in private prisons, as Justice Health is also a provider of health services in a private prison

There is a legislated requirement for Justice Health to monitor the performance of private health operators in New South Wales prisons. This monitoring role is described in the Crimes (Administration of Sentences) Act 1999.

Justice Health's monitoring role includes the collection and analysis of health performance data from private health operators, and periodic site visits to assess health service performance. Justice Health reports the findings of monitoring activities to Corrective Services NSW, the contract manager for private prisons.

Justice Health's monitoring role commenced in the late 1990s. In recent years, this role has expanded as the NSW Government has increased the number of privately managed prisons across the state. Justice Health now monitors health services in four private prisons, accounting for approximately one quarter of all custodial patients in the New South Wales prison system.

In 2018, Justice Health was awarded a contract to provide health services at the John Morony Correctional Centre. Justice Health also monitors the health services this Correctional Centre. The timing of the 1999 legislation did not anticipate that Justice Health would be a provider of the services it is required to monitor.

Justice Health has taken steps to maintain independence and transparency in its monitoring role by establishing a number of arms‑length governance arrangements. Justice Health set up a Commissioning Unit that operates independently from its service delivery operations. Justice Health also established an alternative reporting chain via a Board subcommittee to oversee the performance of health providers in private prisons.

Despite all actions to establish independence, the monitoring role confers dual responsibilities on the Chief Executive of Justice Health as both an operational manager of health services in a private prison and as a manager responsible for monitoring these same services. As a result, the Chief Executive of Justice Health has access to information about the overall performance of the private prison health system in New South Wales.

As a competitor for the provision of health services in privately operated prisons, Justice Health has access to information to which other private health providers do not. This potentially gives Justice Health a competitive advantage over other private health operators.

2. Recommendations

By December 2022, Justice Health should:

1. enhance reporting on patient access to health services to ensure that system managers can identify risks, challenges, and system improvements across key areas of its service profile

2. in collaboration with the NSW Ministry of Health, identify and implement the required improvements to its health information management systems that will enable effective transfers of patient clinical records and appointment information across the custodial network and with external health providers.

By December 2022, Justice Health and Corrective Services NSW should:

3. develop a joint framework to govern and monitor the costs of their common and connected responsibilities for patient health movements across the prison network and to external health services

4. develop a joint framework to govern their common and connected responsibilities for mental health services.

By December 2022, Justice Health and Corrective Services NSW, in collaboration with the NSW Ministry of Health, should:

5. progress infrastructure plans and projects that address the lack of specialist accommodation for mental health patients and aged and frail patients

6. standardise and align the key performance indicators that monitor the performance of health operators in public and private prisons so that system‑wide benchmarking is possible.

By December 2022, the NSW Ministry of Health should:

7. take action to remediate the conflicting monitoring arrangements of public and private prison health operators.

Appendix one – Response from agencies

Appendix two – About the audit

Appendix three – Performance auditing

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #356 - released (23 September 2021).

Published

Actions for Delivering school infrastructure

Delivering school infrastructure

Education
Infrastructure
Management and administration
Project management

The Auditor-General for New South Wales, Margaret Crawford, released a report today examining the planning and delivery of new, redeveloped and upgraded public schools.

School Infrastructure NSW has identified the need to accommodate an additional 180,000 enrolments in public schools by 2039 with a large portion of this growth expected in metropolitan Sydney. It has also identified that around 34,000 teaching spaces will require upgrading to be fit-for-purpose.

Although School Infrastructure NSW has developed a long-term strategic plan that advises government of ongoing funding requirements, it has not presented a list of priorities to meet those needs. Developing a longer-term list of priorities would help signal the areas of greatest need and allow more time to develop the best options to meet those needs.

The audit found that School Infrastructure NSW has focused on delivering existing projects, election commitments and other government announcements. This has diverted attention from identifying and delivering projects that would have better met present and future needs. 

The report makes eight recommendations to improve long-term planning for future needs, strengthen the quality of estimated project costs and benefits, and embed a continuous improvement program. 

In 2016, the Department of Education prepared a School Assets Strategic Plan (2016 SASP) which outlined long-term funding needs to support the expected growth in enrolments to 2031. Following the release of the 2016 SASP, the NSW Government substantially increased funding for new and upgraded schools from $2.4 billion in the 2016–17 State Budget to $4.2 billion in 2017–18.

In 2017, the Department of Education established School Infrastructure NSW (SINSW) to lead the delivery of the 2016 SASP and the 123 new projects announced in the 2017–18 Budget. This significantly larger program of work required rapid development of internal capacity, governance arrangements, and project management systems. This needed to be done at the same time as scoping and planning for the list of announced projects.

As there are limited funds available to meet growing needs across the State, it is important that SINSW has effective methods to prioritise projects to communities with the greatest need. To ensure that projects deliver value for money, business cases need to have robust estimates of project costs and benefits. Business cases also need to account for the inherent risks in delivering infrastructure projects. Unplanned cost escalations can reduce the number of new or modernised classrooms SINSW can deliver. Unforeseen delays may also impact families who make significant life choices based on their expectations that a school will open at the beginning of the school year.

The objective of this audit was to assess the effectiveness of planning and delivery of new, upgraded and redeveloped schools to meet demand for public school education in New South Wales. To address this objective, the audit examined whether the Department:

  • has effective procedures for planning and prioritising school capital works to meet present and future demands
  • develops robust business cases for school capital works that reliably inform decision-making
  • has effective program/project governance and management systems that support delivering projects on-time, within budget and achievement of intended benefits.

The audit examined business cases for 12 projects as case studies. These include a mix of projects initiated before and after the establishment of SINSW.

This audit commenced in June 2020 and examined strategies and demographic projections developed prior to the emergence of COVID-19. This audit did not examine potential longer-term impacts of COVID-19 on future demands for public school education.

Conclusion

School Infrastructure NSW has been focused on delivering existing projects, election commitments and other government announcements. This has diverted attention from identifying and delivering projects that would have better met present and future student and classroom needs. While it has developed a long-term strategic plan that advises government of ongoing funding requirements, it has not presented a list of priorities to meet these needs.

In its first years of operation, SINSW has focused on delivering existing projects and the 123 new projects announced in the 2017–18 Budget. Further NSW Government announcements in the 2018–19 Budget, election commitments in the 2019–20 Budget, and announcements in the 2020–21 Budget, made up the majority of new projects, rather than projects prioritised by SINSW. 

In early 2020, SINSW advised the NSW Government that the currently funded infrastructure program would not meet forecast classroom requirements for 2023 and beyond. The School Asset Strategic Plan 2020 estimates the annual level of investment needed over the next 20 years to meet growth, update and upgrade facilities to meet compliance obligations. However, SINSW’s ten-year Capital Investment Plans for 2018–19, 2019–20 and 2020–21 only identified priorities over a two-year horizon.

Developing a longer-term pipeline of priorities would signal the areas of greatest need and allow greater scope to consider a range of options to best meet those needs.

SINSW has made progress in planning across geographic areas but needs to better prioritise which projects move forward.

Given the current and projected needs for new classrooms, it is vital that SINSW provides long-term advice based on thorough state-wide analysis to help prioritise projects that best meet this demand.

SINSW has improved its capabilities, processes, and systems to support planning in ‘School Community Groups’, which are clusters of between 5 to 15 schools in a geographic area. This addresses a key direction identified in the School Assets Strategic Plan 2016. It has developed a planning tool which allows it to prioritise School Community Groups based on weighted criteria. It has also developed an approach to identify potential projects within School Community Groups but has not yet put in place a structured process to prioritise which projects move to the business case stage to seek funding for delivery.

Business cases we examined established service needs, but several had shortcomings in scope definition, cost estimation and risk identification.

Most business cases we examined demonstrated the service need and consultation with stakeholders helped to incorporate educational requirements. Common templates and specific cost-benefit guidance developed in partnership with NSW Treasury has helped to promote consistency across business cases.

However, there were shortcomings in several business cases we reviewed. Business cases for projects already announced by government presented a limited number of options, and the process for eliminating other options was not transparent. Cost increases and contingency drawdowns for several projects indicate that scoping, costing and risk assessments could be improved, especially for complex projects.

Standard program management systems and governance arrangements support project delivery, however, there is scope for better ongoing oversight of benefits.

SINSW applies standard governance arrangements to projects based on their size. Higher value projects have executive oversight while lower value projects are overseen on a regional basis. SINSW has improved its project management systems to provide more consistent data and greater transparency to senior management over project status, cost and use of contingencies.

SINSW has worked with NSW Treasury to define a consistent set of benefits for new and redeveloped schools. Estimated benefits are currently based on international contexts but SINSW advises it is undertaking further research to improve the evidence base in this area. The current approach to ongoing monitoring, reporting and evaluation of project benefits places responsibility on the infrastructure delivery team. This team is not the most appropriate area to monitor ongoing benefits, which are expected to accrue many years after delivery and depend on actions in other areas of the Department.

1. Key findings

SINSW delivered projects against an established program of works in its first years of operation

At establishment, SINSW inherited a portfolio of existing projects and 123 new projects announced as part of the 2017–18 Budget (to commence over 2017–18 and 2018–19). It has progressively worked through individual project planning to deliver against these projects.

The 2018–19 Budget funded two new projects that had not already been announced. Both projects were identified by SINSW as a priority. The 2018–19 Budget also allocated funding for 'planning' 22 new projects. Seventeen of the 22 projects had been identified by SINSW as a priority.

SINSW identified 31 new priority projects in its Capital Investment Plan for 2019–20. Thirteen of these projects were funded in that year with a further 27 projects included as election commitments. SINSW identified 20 new projects in its Capital Investment Plan for 2020–21 but only two of these were funded. SINSW advised this was due to a constrained budget environment.

There is an anticipated shortfall of classrooms based on the current funded program

Despite increased funding since 2017–18, SINSW advised the NSW Government in early 2020 that the currently funded infrastructure program would not meet forecast classroom requirements for 2023 and beyond. Accordingly, it is vital that new funding is prioritised to projects which best meet demand.

SINSW only identified specific priorities over a two-year horizon in its Capital Investment Plans for 2018–19, 2019–20 and 2020–21. The School Assets Strategic Plan 2016 and the 2020 update make the case for sustained funding for school building and redevelopment. These plans estimate annual funding requirements and show geographic areas with increasing forecast enrolments. Detailing how priorities over a ten-year timeframe fit within a ten-year capital planning limit would create more certainty about meeting growth demands.

There has been progress in formalising prioritisation frameworks, data tools and supporting governance arrangements

SINSW committed to planning for new and redeveloped schools in 'School Community Groups' in the School Assets Strategic Plan 2016. This is a new way of planning which considers the educational needs over a defined geographical area. It has developed a planning tool to prioritise School Community Groups based on weighted criteria. It has also established governance frameworks to improve transparency over decisions to reprioritise this list.

SINSW has refined its approach to planning in School Community Groups over the past four years. It now prepares Service Needs Reports to investigate needs, identify projects, prioritise, determine scope and timing, and assess non-capital options. SINSW has yet to finalise arrangements for how needs identified in Service Needs Reports progress to the strategic business case stage.

Projects announced prior to developing a business case have less opportunity to consider a range of options to meet the service needs

Business cases for projects already announced by government (or announced for planning) go through the same process of determining the service need and impacts on surrounding schools. However, for some announced projects, the range of options considered in the business case is influenced by the parameters of the announcement. This makes it more difficult to genuinely pursue alternate options that could better meet the identified service need.

Projects identified by SINSW have a more rigorous process of considering options. Service Needs Reports explore a wide range of asset and non-asset interventions across the School Community Group. Options are narrowed as the projects move through the strategic and final business case stages. SINSW uses its Investment Review Committee to engage key stakeholders early in the process so that they are informed about how non-asset solutions have been considered and why SINSW is progressing the business case for a capital solution for particular projects.

Several business cases underestimated project costs and risks, leading to scope and budget increases

Several business cases we reviewed did not adequately identify the initial scope requirements, project-specific risks or the likely project cost. For two business cases, this appeared to be due to an attempt to fit the project within a predetermined amount. Announcing a project’s scope, budget and timeframe before proper planning increases risks to successful delivery against expectations.

Several of the projects we examined required drawdowns on contingency funds due to inadequate consideration of scope, costs and project risks at the planning stage. Contingency funds are intended for unanticipated extra costs rather than those that could have or should have been identified at the planning stage.

Guidance on benefit calculations has provided a consistent framework for business cases

Business cases we examined presented a consistent set of benefits based on guidance developed in partnership with NSW Treasury. Following this guidance helps to compare cost-benefit analyses across business cases. However, the evidence for the estimated benefits is based on contexts outside of NSW. SINSW has the tools and data sources to calculate benefits more suited to the context of particular schools. Doing so would improve the accuracy of cost-benefit analyses. SINSW advised that it is currently updating the guidance in partnership with NSW Treasury.

SINSW involves school principals, executives and teaching staff in developing education rationales when commencing projects. These documents help align projects with education outcomes. They also provide a baseline for post-occupancy evaluation, which is important to determine whether the new school infrastructure is being used in the ways that were anticipated in the business case.

SINSW could elevate its existing assurance review process to consolidate lessons learned

SINSW engages external peer reviewers to conduct assurance reviews on its projects at multiple stages of planning and delivery. It has established a Community of Practice for external reviewers to keep them up to date on new developments and requirements. Higher value projects are also subject to review by Infrastructure NSW under the Investor Assurance Framework.

By looking at all projects at all stages, assurance reviews can identify systematic issues across the full portfolio of projects. A recent assurance review analysed common findings from reviews of strategic and final business cases. This provides a helpful way to improve internal processes. SINSW advised that it is implementing a continuous improvement program, which will be able to take findings from assurance reviews to build organisational capabilities.

2. Recommendations

By September 2021, the Department of Education should:

  1. finalise the investment prioritisation approach with agreement from key stakeholders
  2. finalise and update on an ongoing basis a ten-year list of priorities to meet the forecast demand for new classrooms and contemporary fit for purpose learning environments, which identifies individual projects and programs in the short-term and priority geographic areas and programs in the medium-term
  3. seek a ten-year Capital Planning Limit from NSW Treasury to ensure the needs identified in the ten-year list of priorities are met and are coordinated with the forward capital programs of other agencies
  4. improve the quality of data on cost benchmarks that underpin the annual ten-year Capital Investment Plan and updates to the School Assets Strategic Plan
  5. embed an evidence-based cost benefit analysis framework for school investment, in consultation with NSW Treasury, by:
    • validating benefits estimated in previous business cases with actual results
    • building the evidence base in relation to contemporary learning environments
  6. regularly share data on forecast needs with relevant planning agencies to promote strategic opportunities for servicing education needs
  7. implement the continuous improvement program for service planning, options assessment, business case development, project delivery and handover. The program should be informed by findings from assurance reviews, post-occupancy evaluations and project lessons learned
  8. establish benefits realisation processes and practices that:
    • ensure business cases set baselines and targets for benefits
    • review benefits during delivery, prior to handover and as part of Post Occupancy Evaluations
    • identify which part(s) of the Department are best placed to develop, manage and evaluate benefits on an ongoing basis.

Note:

The Department's formal response to this report at Appendix one states that while it 'supports the recommendations, it considers the proposed six-month timeframe to be an unreasonably short period for a large and complex organisation to effectively implement many of these recommendations'. It suggests 12 months would be needed to implement the recommendations.

The recommendations stemming from this audit are core business for SINSW. The Audit Office considers it important for SINSW to place priority on implementing the recommendations in time to inform the 2022–23 budget cycle. Extending the deadline to April 2022 would place action outside of that budget cycle.

There have been significant increases in funding for education infrastructure since the 2017–18 Budget and further growth in demand for places in schools is forecast. SINSW has the challenge, not only of meeting the need for new classrooms due to population growth, but also upgrading facilities to enable modern teaching techniques. In addition, community expectations of what constitutes a vibrant and successful school community continues to increase.

Given growing demand and budget constraints, projects must be selected to best meet the needs of the community and planning and prioritisation are vital. SINSW has been progressing planning for announced projects as well as implementing a new type of strategic state-wide planning and prioritisation, cluster planning, where options are developed for School Community Groups.

The primary role of a business case is to reliably inform an investment and/or policy decision. Over the period of review, the NSW Government's guidelines for business cases have established this requires recommendations based on convincing arguments, sufficient evidence, and accurate costing of alternatives and expected benefits. Business case guidelines are underpinned by guides for economic appraisal and cost-benefit analysis.

As SINSW moves to prioritise business cases for interventions in School Community Groups, it will increasingly need to demonstrate rigour in its assessment of all options. It will also need to ensure that scope identification, cost and risk planning and the setting of contingencies are accurate. This will help decision-makers better understand, plan for and manage the investment required to meet the demand for school infrastructure.

For this audit, we examined business cases and related documentation for 12 projects. Several of these projects were developed before School Infrastructure NSW was established in mid-2017.

Over the period of review, NSW Government policies for business case development and submission have emphasised that effective governance arrangements are critical to a proposal's successful implementation.

SINSW's guidance similarly highlight the importance of effective governance and project management for achieving good outcomes. It prescribes a general governance structure managed by SINSW that can be tailored to the planning and delivery of school infrastructure projects.

Appendix one – Response from agency
 
Appendix two – About the audit 

Appendix three – Performance auditing 


Copyright Notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #347 - released (8 April 2021).

Auditor-General’s Report to Parliament on Delivering School Infrastructure 

This corrigendum has been prepared to amend the following text within my Auditor-General’s Report to Parliament on Delivering School Infrastructure, dated 8 April 2021. 

On page two, the original text was as follows: 

Further NSW Government announcements in the 2018–19 Budget and election commitments in the 2019–20 Budget made up the majority of new projects, rather than projects prioritised by SINSW. 

The original text has now been changed to 

Further NSW Government announcements in the 2018–19 Budget, election commitments in the 2019–20 Budget, and announcements in the 2020–21 Budget, made up the majority of new projects, rather than projects prioritised by SINSW. 

On page three, the original text was as follows: 

The 2018–19 Budget funded three new projects that had not already been announced. One of the three projects was identified by SINSW as a priority. 

The original text has now been changed to: 

The 2018–19 Budget funded two new projects that had not already been announced. Both projects were identified by SINSW as a priority. 

On page three the original text was as follows: 

SINSW identified 33 priority projects in its Capital Investment Plan for 2019–20.

The original text has now been changed to  

SINSW identified 31 new priority projects in its Capital Investment Plan for 2019–20. 

On page eleven, in Exhibit 4, the original text was as follows: 

The 2018–19 NSW Budget announced funding for an additional 43 new and upgraded schools to commence works in 2018–19. Of the 43 projects: 

•    1 was identified by SINSW as a priority in its Capital Investment Plan (SINSW requested funding for one new project)
•    40 had already been announced
•    2 were new announcements (not identified as a priority by SINSW in its Capital Investment Plan).

The original text has now been changed to: 

The 2018–19 NSW Budget announced funding for an additional 42 new and upgraded schools to commence works in 2018–19. Of the 42 projects: 

•    2 were identified by SINSW as a priority in its Capital Investment Plan (SINSW requested funding for two new projects)
•    40 had already been announced.

On page eleven, the original text was as follows: 

The 2019–20 NSW Budget announced funding for an additional 40 new and upgraded schools as election commitments. Of the 40 election commitment projects: 

•    13 were identified by SINSW as priorities in its Capital Investment Plan (SINSW requested funding for a total of 33 new projects)
•    27 were new announcements (not identified as a priority by SINSW in its Capital Investment Plan).

The original text has now been changed to: 

The 2019–20 NSW Budget announced funding for an additional 40 new and upgraded schools as election commitments. Of the 40 election commitment projects: 

•    13 were identified by SINSW as priorities in its Capital Investment Plan (SINSW requested funding for a total of 31 new projects)
•    27 were new announcements (not identified as a priority by SINSW in its Capital Investment Plan).

The above changes will be reflected in the version of the report published on the Audit Office website and should be considered the true and accurate version.  

 

Published

Actions for One TAFE NSW modernisation program

One TAFE NSW modernisation program

Education
Finance
Management and administration
Project management
Shared services and collaboration

The Auditor-General for New South Wales, Margaret Crawford, released a report today examining the management of the One TAFE NSW modernisation program.

In 2016, the Government released 'A Vision for TAFE NSW' which stated that TAFE NSW needed to become more flexible, efficient and competitive. It set out the need to progressively reduce significant cost inefficiencies, including by moving away from separate institutes to a single institute model. TAFE NSW established the One TAFE NSW modernisation program to deliver on that vision.

The Auditor General found that the One TAFE NSW modernisation program did not deliver against its key objectives within planned timeframes. The modernisation program originally aimed to realise $250 million in annual savings from 2018–19. Because of project delays and higher than expected transition costs, TAFE NSW did not meet the original savings target. TAFE NSW has made progress on key elements of the program and anticipates that savings will be realised in coming years.

The report makes two recommendations to improve governance arrangements for delivering on commercial objectives and increasing transparency of non commercial activities. 

The report also identifies a series of lessons for future government transformation programs.

TAFE NSW is the public provider of Vocational Education and Training (VET) in New South Wales. In 2018, TAFE NSW enrolled 436,000 students in more than 1,200 courses at around 130 locations across the State.

There have been major policy changes impacting TAFE NSW over the past decade. Under the Smart and Skilled reform, TAFE NSW started to compete with other Registered Training Organisations (RTOs) for a share of the student market.

In 2016, the NSW Government released 'A Vision for TAFE NSW'. The Vision stated that a failure to adapt to market circumstances had left TAFE NSW with unsustainable costs and inefficiencies. To address this, TAFE NSW needed to become more flexible, efficient and competitive. It set out that TAFE NSW must progressively reduce significant cost inefficiencies, including by moving away from a model of separate institutes to a One  TAFE NSW model. The NSW Government set TAFE NSW a target to achieve savings through implementing the Vision.

TAFE NSW established the One TAFE NSW modernisation program to deliver on that vision. The program initially aimed to deliver savings of $250 million per year from 2018–19, but this target was reviewed and updated as the program was being delivered.

This audit assessed whether TAFE NSW effectively managed the One TAFE NSW modernisation program to deliver on the NSW Government's vision for TAFE NSW. In making this assessment, the audit examined whether:

  • delivery of the program was well planned
  • the program was driven by sound governance arrangements
  • TAFE NSW is making progress against the intended outcomes of the program.

The audit focused on the effectiveness of planning, governance and reporting arrangements. It examined five projects within the overall modernisation program as case studies.

Conclusion

The One TAFE NSW modernisation program was an ambitious plan to deliver on the NSW Government’s vision for TAFE NSW, while achieving ongoing savings. Several factors contributed to TAFE NSW not effectively managing the program to deliver on planned timeframes and objectives. These factors include unclear expectations of the primary role of TAFE NSW, unrealistic timeframes, undertaking a large number of complex projects concurrently, governance arrangements that were not fit-for-purpose and poor-quality data.

Planning for the modernisation program and its projects was driven by top-down savings targets and pre-determined timeframes. This led to TAFE NSW attempting to deliver a large number of programs concurrently within tight timeframes. Program management capability was underdeveloped at the commencement of the program and this affected the quality of planning for delivery.

There was a lack of clarity around TAFE NSW's primary purpose. Part of the NSW Government's vision for TAFE NSW was for it to be more commercial, competitive and efficient. These objectives were not fully supported by existing legislation. The commercial objectives of the modernisation program conflicted with legislated social objectives for TAFE NSW. TAFE NSW did not have the autonomy to operate like a government-owned business in a market environment. And while TAFE NSW received separate funding to support students facing disadvantage this did not cover the costs of other non-commercial activities undertaken for social purposes, such as delivering uneconomic courses. The role of the TAFE Commission Board was ambiguous during the initial years of the program, which increased reporting requirements and blurred accountabilities for decision-making.

TAFE NSW's Strategic Plan 2016-22 nominated ten key milestones for delivery by January 2019. TAFE NSW has made progress against several important milestones, including that TAFE ‘is a single TAFE NSW brand’ and has 'industry specific TAFE NSW SkillsPoints'. Other key elements have yet to be delivered, including that TAFE NSW achieves 'integrated enterprise-wide business systems'. Because of delays to projects and higher than expected transition costs, TAFE NSW reported that it did not meet the originally targeted $250 million in annual savings for 2018–19 (which was reviewed and updated as the program was being delivered). 

Appendix one – Response from agency

Appendix two – About the audit

Appendix three – Performance auditing

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #346 - released 17 December 2020

Published

Actions for Health 2020

Health 2020

Health
Compliance
Financial reporting
Infrastructure
Internal controls and governance
Service delivery

This report analyses the results of our audits of financial statements of the Health cluster for the year ended 30 June 2020. The table below summarises our key observations.

1. Financial reporting

Financial reporting

Unqualified financial audit opinions

The financial statements of NSW Health and its 25 controlled entities received unqualified opinions.

The number of corrected and uncorrected misstatements increased from the prior year. Misstatements related predominantly to the implementation of new accounting standards, asset revaluations and accounting for new revenue streams to cover the cost of HSW Health’s response to the COVID-19 pandemic.

Qualified compliance audit opinion

We issued a qualified audit opinion for the Ministry of Health’s Annual Prudential Compliance Statement for aged care facilities operated by NSW Health. We identified 18 instances of material non-compliance with the Fees and Payments Principles 2014 (No. 2) (the Principles) in 2019–20 (30 in 2018–19).

Financial performance

NSW Health received an additional $3.3 billion in funding to cover costs associated with its response to the COVID-19 pandemic.

The impacts of the COVID-19 pandemic on the cluster were significant for health entities and included changes to operations, increased revenues, expenditure, assets and liabilities. Cancellation of elective surgery and decreased emergency department presentations meant that despite the pandemic, activity levels at many health entities decreased. Health Pathology and HealthShare were notable exceptions.

In the period to the 30 June 2020, NSW Health reported that over 900,000 COVID-19 tests were conducted. Health Pathology conducted over 500,000 of these tests. Health Pathology's surge requirements were enhanced through arrangements with 13 private sector providers. HealthShare purchased $864.2 million of personal protective equipment.

Overall, NSW Health recorded an operating surplus of $3.1 billion in 2019–20, an increase of $2.0 billion from 2018–19. As in previous years, the surplus largely resulted from additional revenue received to fund capital projects including the construction of new facilities, upgrades and redevelopments. In 2019–20 additional Commonwealth and State funding for the purchase and stockpiling of personal protective equipment also contributed to the operating surplus.

Overtime payments The Ambulance Service of NSW’s (NSW Ambulance) reduced their overtime payments to $79.7 million in 2019–20 ($83.1 million in 2018–19). Overtime payments in 2019–20 included $6.8 million related to the response to the 2019–20 bushfire season. NSW Ambulance overtime payments represent 16.8 per cent of total overtime payments in the cluster.

2. Audit observations

Internal control deficiencies

We identified more internal control deficiencies in 2019–20. The number of repeat issues from prior years also remains high.

NSW Health addressed 18 out of the 25 information system control deficiencies during the year.

Several key agreements lacked formal documentation. This included agreements between the Ministry and health entities, between health entities and agencies in other clusters and between the Ministry and health departments in other jurisdictions.

Infrastructure delivery NSW Health had 44 ongoing major capital projects at 30 June 2020 with a total revised budget of $12.3 billion. The revised total budget of $12.3 billion is $2.0 billion more than the original budget. NSW Health revises budgets when it combines project stages.

This report provides parliament and other users of the Health cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

The impacts of the COVID-19 pandemic on the cluster were significant and included changes to the operations of the health entities and increased revenue, expenditure, assets and liabilities.

As a part of this year's audits of health entities, we have considered:

  • financial implications of the COVID-19 emergency at both health entity and cluster levels
  • changes to agencies' operating models
  • agencies' access to technology and the maturity of systems and controls to prevent unauthorised and fraudulent access to data.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

The response to the COVID-19 pandemic primarily impacted the financial reporting of NSW Health through:

  • additional revenue from the State government in the form of grants and stimulus payments
  • additional revenue from the Commonwealth government under the National Partnership Agreement for COVID-19 to cover part of the cost of responding to the COVID-19 pandemic
  • increased expenses, largely due to increased payments to private health operators to maintain their viability during the COVID-19 pandemic and later to assist with public patient elective surgery waitlists and increased cleaning costs
  • increased purchases of personal protective equipment.

Chapter one outlines the impacts of NSW Health’s response to the COVID-19 pandemic. This chapter outlines our other audit observations related to the financial reporting of agencies in the Health cluster for 2020.

Section highlights

  • Unqualified audit opinions were issued for all health entities’ financial statements, although more misstatements were identified than last year.
  • NSW Health recorded an operating surplus of $3.1 billion, an increase of $2.0 billion from 2018–19. This is largely due to additional capital grants for new facilities, upgrades and redevelopments and additional Commonwealth and State funding for the purchase of personal protective equipment.
  • NSW Health’s expenses increased by 5.5 per cent in 2019–20 (7.0 per cent in 2018–19) despite the impact of the COVID-19 pandemic. The primary causes for the growth in expenses are increases in:
    • employee related expenses due to higher employee numbers, increased overtime and a 2.5 per cent award increase
    • payments to private health operators to maintain their viability during the COVID-19 pandemic and later to assist with public patient elective surgery waitlists
    • payments to private health operators due to the first full year of operation of the Northern Beaches hospital.
  • The Ambulance Service of NSW (NSW Ambulance) continued to report higher overtime payments than other health entities. However, despite the response to the 2019–20 bushfire season, their overtime payments were lower than last year. NSW Ambulance paid $79.7 million in overtime payments in 2019–20 ($83.1 million in 2018–19).
  • A qualified audit opinion was issued for the Ministry of Health’s Annual Prudential Compliance Statement for aged care facilities operated by NSW Health. There were 18 instances of material non-compliance with the Fees and Payments Principles 2014 (No. 2) (the Principles) in 2019–20 (30 in 2018–19)

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

The primary impact of the COVID-19 pandemic on the effectiveness of the internal controls of NSW Health and health entities relates to the effectiveness of controls implemented by HealthShare relating to the stocktake of personal protective equipment inventories. Inventory managed by HealthShare increased by 2,746 per cent during 2019–20. HealthShare’s inventory controls did not maintain pace with the sudden, significant increase.

The impacts of NSW Health’s response to the COVID-19 pandemic are outlined in chapter one. This chapter outlines other observations and insights from our financial statement audits of agencies in the Health cluster.

Section highlights

  • The number of internal control deficiencies has increased since 2018–19. More than a third of control deficiencies are repeat issues.
  • Control deficiencies that relate to managing employees’ leave and employee’s time recording continue to be difficult for entities to resolve, particularly during the ongoing response to the COVID-19 pandemic.
  • Several key agreements were undocumented. These included agreements between the Ministry and the health entities, between health entities, and between the Ministry and entities in other clusters and jurisdictions. These related to:
    • a loan arrangement between the Ministry and HealthShare for $319 million.
    • Northern Sydney Local Health District's use of land and buildings owned by the Graythwaite Charitable Trust
    • agreements for the treatment of New South Wales residents while they are interstate, and interstate residents receiving treatment while they are in New South Wales from Queensland, Victoria, South Australia and the ACT for both 2019–20 and 2018–19.
  • NSW Health reported that they completed nine major capital projects during 2019–20. As at 30 June 2020 there were 44 ongoing major capital health projects in NSW. The revised capital budget for these projects in total was $2.0 billion more than the original budget of $10.3 billion. NSW Health reported the budget revisions are largely the result of combining project stages.

Appendix one – List of 2020 recommendations 

Appendix two – Status of 2019 recommendations 

Appendix three – Financial data

Appendix four – Analysis of financial indicators 

Appendix five – Analysis of performance against budget

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Auditor-General’s Report to Parliament

Health 2020

11 December 2020

This corrigendum has been prepared to amend the following text within the Auditor-General’s Report to Parliament on Health 2020, dated 10 December 2020.

NSW Health emergency department treatment times

On page five the original text was as follows:

NSW Health also measures the percentage of patients whose clinical care in emergency departments is completed within four hours. The measure is used as an indicator of accessibility to public hospital services.

NSW Health aims to complete clinical care in the emergency department for 81 per cent of patients within four hours. In 2019–20 NSW Health reports it completed clinical care within four hours for 72.1 per cent of patients (a 7.3 per cent decrease from 2018–19).

At Western Sydney Local Health District, 59 per cent of patients were treated within the targeted timeframe. NSW Health attribute this to the profile of patients presenting in emergency departments and additional time taken processing COVID-19 patients to ensure staff safety.

The original text has now been changed to:

NSW Health also measures the percentage of patients with total time in the emergency department of four hours or less for each local health district. The measure is used as an indicator of accessibility to public hospital services.

Local Health Districts Target % (2019–20) Actual % (2019–20)
Central Coast 77.0 59.9
Far West 90.2 86.6
Hunter New England 81.0 72.5
Illawarra Shoalhaven 79.0 60.2
Mid North Coast 82.0 76.7
Murrumbidgee 85.3 81.9
Nepean Blue Mountains 79.0 65.5
Northern NSW 81.0 78.2
Northern Sydney 79.0 73.9
South Eastern Sydney 78.0 70.3
South Western Sydney 78.0 61.2
Southern NSW 85.0 83.0
Sydney 76.0 70.9
Sydney Children’s Hospitals Network 80.0 72.1
Western NSW 85.9 81.0
Western Sydney 78.0 59.0
St Vincent's Health Network* 75.0 65.4
* St Vincent’s Health Network Sydney (SVHNS) comprises of St Vincent’s Hospital Sydney Limited as the affiliated health organisation in respect of four recognised establishments under the Health Services Act 1997 (NSW) (Health Services Act). Under the Health Services Act, St Vincent’s Hospital Sydney Limited, is treated as a Network for the purposes of the National Health Reform Agreement in respect of the three recognised establishments: St Vincent’s Hospital, Darlinghurst; Sacred Heart Health Service, Darlinghurst; St Joseph’s Hospital, Auburn; and St Vincent's Correctional Health, Parklea.
Source: NSW Health (unaudited)

The above changes will be reflected in the version of the report published on the Audit Office website and should be considered the true and accurate version.

Published

Actions for Education 2020

Education 2020

Education
Asset valuation
Compliance
Financial reporting
Fraud
Information technology
Internal controls and governance
Management and administration
Procurement

The Auditor-General for New South Wales, Margaret Crawford, released a report today titled Education 2020. This report focuses on key observations and findings from the most recent audits of agencies in the Education cluster.

Unqualified audit opinions were issued for all cluster agencies’ financial statements. However, internal control deficiencies were identified across the cluster agencies, including deficiencies in the management of purchasing cards and 15 internal control issues that were repeated from the previous year.

The 2019–20 natural disasters caused widespread damage in both Northern and Southern NSW. The COVID‑19 pandemic further challenged agencies, requiring social distancing and other infection control measures which disrupted the traditional means of teaching students. Agencies have adjusted their operations to respond to these emergency events.

The TAFE Commission’s revenues 2019–20 were impacted by the pandemic. Lower enrolments and an increase in fee-free short courses offered during the year contributed to the result.

Read the PDF report

This report analyses the results of our audits of financial statements of entities within the Education cluster for the year ended 30 June 2020. The table below summarises our key observations and recommendations.

1. Financial reporting 

Audit opinions Unqualified audit opinions were issued for all cluster agencies' 30 June 2020 financial statements audits.
New accounting standards

Agencies implemented three new accounting standards during the year.

Our financial statement audits of the Department of Education (the Department) and NSW Education Standards Authority (NESA) identified issues with the leasing information provided by Property NSW (PNSW). Despite the outsourcing arrangement, both the Department and NESA remain ultimately responsible for the completeness and accuracy of this information, which would have benefited from a more thorough quality assurance, validation and review process before they placed reliance upon it.

Recommendation:

We recommend the Department and NESA:

  • quality assure and validate the information provided by PNSW
  • ensure changes made by PNSW to lease data are supported and that assumptions and judgements applied are appropriate
  • document their review of the data supplied.
Changes were made to the financial reporting requirements this year to account for the impact of the pandemic

Emergency legislation was enacted during the year in response to the COVID-19 pandemic. The legislation revised the statutory reporting deadlines for agencies to submit their financial statements and allowed the Treasurer to continue authorising payments from the consolidated fund until the enactment of the 2020–21 budget.

All cluster agencies prepared their financial statements on a going concern basis and submitted their financial statements within the revised statutory deadlines.

The State provided $159.0 million in stimulus funding to support the operations of cluster agencies during emergency events. Nearly half of this funding was to support cleaning activities by the Department and the Technical and Further Education Commission (the TAFE Commission) during the COVID-19 pandemic.

Quality and timeliness of financial reporting

The number of monetary misstatements identified in agencies' financial statements decreased to 14 (23 in 2018–19).

While the number of corrections made to the financial statements after the submission date increased to eight (two in 2018–19), it is important to note these corrections provide parliament and other users of the financial statements increased confidence in the accuracy and presentation of agencies' performance and financial position.

Sustainability of cluster agencies The TAFE Commission's enrolments declined, and operating margins reduced, both being impacted by the COVID-19 pandemic.

2. Audit observations

Internal control deficiencies

We identified 33 internal control issues, including 15 findings that were repeated from previous years.

A high-risk issue was reported at the Department relating to the inadequate monitoring and follow up of privileged user activity in its enterprise resource planning system – SAP.

Repeat findings relate to ongoing deficiencies in information technology controls and management policies, practices and procedures.

Recommendation:

Cluster agencies should:

  • prioritise and action recommendations to address internal control deficiencies
  • review and confirm the appropriateness of existing privileged user access accounts
  • implement a rigorous monitoring regime to ensure that any improper use of privileged user accounts can be detected in a timely manner.
Agency responses to emergency events

The Department established a separate bushfire relief directorate and COVID-19 Taskforce to assist and support school communities in response to recent emergencies.

Other cluster agencies have established committees or response teams to oversee and address all aspects of the impact of COVID-19.

Schools review 2019 We continue to identify instances of non-compliance in relation to cash management and procurement at schools.
Use of purchasing cards at the Department of Education

Since 2015, the NSW Government has encouraged the use of purchasing cards by public sector agencies. Purchasing cards are efficient to transact low value, high volume procurement of goods and services, but the use must be effectively monitored.

Our review of the Department's purchasing cards identified weaknesses in its oversight and monitoring controls, including the issue and cancellation of purchasing cards

Opportunities exist for the Department to better monitor card use. Tools such as data analytics are an efficient and effective detective control to identify irregular activity or misuse by cardholders.

Recommendation:

The Department should:

  • improve the accuracy and completeness of exit procedures for terminated employees to ensure cards are returned and cancelled
  • perform periodic reviews to ensure active cards are held only by current employees
  • set transaction limits that do not exceed the limits of the user’s financial delegation
  • establish a data analytics regime to help analyse and identify high risk patterns and anomalies in their purchasing card usage, augmenting their existing monitoring and detective controls.

 

This report provides parliament and other users of the Education cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations
  • the impact of emergencies and the COVID-19 pandemic.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

The COVID-19 Legislation Amendment (Emergency Measures–Treasurer) Act 2020 amended legislation administered by the Treasurer to implement further emergency measures as a result of the COVID-19 pandemic. These amendments:

  • allowed the Treasurer to authorise payments from the consolidated fund until the enactment of the 2020–21 budget – supporting the going concern assessments of cluster agencies
  • revised budgetary, financial and annual reporting time frames – impacting the timeliness of financial reporting
  • exempted certain statutory bodies and departments from preparing financial statements.

This chapter outlines our audit observations related to the financial reporting of agencies in the Education cluster for 2020, including any financial implications from the recent emergency events.

Section highlights 

Unqualified audit opinions were issued on the financial statements of cluster agencies.

All cluster agencies met the revised statutory deadlines for completing early close procedures and submitting their financial statements.
 
Emergency legislation allowing the Treasurer to continue authorising payments from the consolidated fund under the existing Appropriations Act enabled cluster agencies to prepare financial statements on a going concern basis.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our:

  • observations and insights from our financial statement audits of agencies in the Education cluster. It also comments on our review of elements of the financial control framework applied by schools in NSW whose financial results form part of the Department of Education's (the Department) financial statements.
  • assessment of how well cluster agencies adapted their systems, policies and procedures, and governance arrangements in response to recent emergencies.

Section highlights

  • A high-risk issue regarding inadequate monitoring of privileged user access was identified at the Department.
  • We continue to observe issues by schools in relation to cash management and non-compliance with procurement guidelines and purchasing card use.
  • Opportunities exist for the Department and cluster agencies to enhance their monitoring and review of purchasing card activities. Tools such as data analytics procedures provide an efficient and effective detective control, particularly when used in conjunction with independent spot-checks.

Appendix one – List of 2020 recommendations

Appendix two – Status of 2019 and 2018 recommendations

Appendix three – Financial data

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Internal controls and governance 2020

Internal controls and governance 2020

Education
Environment
Community Services
Finance
Health
Industry
Justice
Premier and Cabinet
Transport
Treasury
Compliance
Cyber security
Information technology
Internal controls and governance
Management and administration
Procurement

The Auditor-General for New South Wales, Margaret Crawford today released her report on the findings and recommendations from the 2019–20 financial audits that relate to internal controls and governance at 40 of the largest agencies in the NSW public sector.

The bushfire and flood emergencies and the COVID‑19 pandemic continue to have a significant impact on the people and public sector of New South Wales. The scale of the government response to these events has been significant. The report focuses on the effectiveness of internal controls and governance processes, including relevant agencies’ response to the emergencies. In particular, the report focuses on:

  • financial and information technology controls
  • business continuity and disaster recovery planning arrangements
  • procurement, including emergency procurement
  • delegations that support timely and effective decision-making.

Due to the ongoing impact of COVID‑19 agencies have not yet returned to a business‑as‑usual environment. ‘Agencies will need to assess their response to the recent emergencies and update their business continuity, disaster recovery and other business resilience frameworks to reflect the lessons learnt from these events’ the Auditor-General said.

The report noted that special procurement provisions were put in place to allow agencies to better respond to the COVID-19 pandemic. The Auditor-General recommended agencies update their procurement policies to reflect the current requirements of the NSW Procurement Framework and the emergency procurement requirements.

Read the PDF report

This report analyses the internal controls and governance of 40 of the largest agencies in the NSW public sector for the year ended 30 June 2020. These 40 agencies constitute an estimated 85 per cent of total expenditure for all NSW public sector agencies.

1. Internal control trends
New, repeat and high risk findings

Internal control deficiencies increased by 13 per cent compared to last year. This is predominately due to a seven per cent increase in new internal control deficiencies and 24 per cent increase in repeat internal control deficiencies. There were ten high risk findings compared to four last year.

The recent emergencies have consumed agency time and resources and may have contributed to the increase in internal control deficiencies, particularly repeat deficiencies.

Agencies should:

  • prioritise addressing high-risk findings
  • address repeat internal control deficiencies by re-setting action plans and timeframes and monitoring the implementation status of recommendations.
Common findings

A number of findings remain common across multiple agencies over the last four years, including:

  • out of date or missing policies to guide appropriate decisions
  • poor record keeping and document retention
  • incomplete or inaccurate centralised registers or gaps in these registers.
2. Information technology controls
IT general controls

We found deficiencies in information security controls over key financial systems including:

  • user access administration deficiencies relating to inadequate oversight of the granting, review and removal of user access at 53 per cent of agencies
  • privileged users were not appropriately monitored at 43 per cent of agencies
  • deficient password controls that did not align to the agency's own password policies at 25 per cent of agencies.

The deficiencies above increase the risk of non-compliance with the NSW Cyber Security Policy, which requires agencies to have processes in place to manage user access, including privileged user access to sensitive information or systems and remove that access once it is not required or employment is terminated.

3. Business continuity and disaster recovery planning
Assessing risks to business continuity and Scenario testing

The response to the recent emergencies and the COVID-19 pandemic has encompassed a wide range of activities, including policy setting, on-going service delivery, safety and availability of staff, availability of IT and other systems and financial management. Agencies were required to activate their business continuity plans in response, and with the continued impact of COVID-19 have not yet returned to a business-as-usual environment.

Our audits focused on the preparedness of agency business continuity and disaster recovery planning arrangements prior to the onset of the COVID-19 pandemic.

We identified deficiencies in agency business continuity and disaster recovery planning arrangements. Twenty-three per cent of agencies had not conducted a business impact analysis (BIA) to identify critical business functions and determine business continuity priorities. Agencies can also improve the content of their BIA. For example, ten per cent of agencies' BIAs did not include recovery time objectives and six per cent of agencies did not identify key IT systems that support critical business functions. Scenario testing improves the effectiveness with which a live crisis is handled, but 40 per cent of agencies had not conducted a business continuity scenario testing exercise in the period from 1 January 2019 to 31 December 2019. There were also opportunities to improve the effectiveness of scenario testing exercises by:

  • involving key dependent or inter-dependent third parties who support or deliver critical business functions
  • testing one or more high impact scenarios identified in their business continuity plan
  • preparing a formalpost-exercise report documenting the outcome of their scenario testing.

Agencies have responded to the recent emergencies but addressing deficiencies will ensure agencies have adequate safeguards in their processes to again respond in the future, if required.

During 2020–21 we plan to conduct a performance audit on 'Business continuity and disaster recovery planning'. This audit will consider the effectiveness of agency business continuity planning arrangements to maintain business continuity through the recent emergencies and/or COVID-19 pandemic and return to a business-as-usual environment. We also plan to conduct a performance audit on whole-of-government 'Coordination of emergency responses'.

Responding to disruptions

We found agencies' governance functions could have been better informed about responses to disruptive incidents that had activated a business continuity or disaster recovery response between 1 January 2019 to 31 December 2019. For instance:

in 89 per cent of instances where a business continuity response was activated, a post-incident review had been performed. In 82 per cent of these instances, the outcomes were reported to a relevant governance or executive management committee

in 95 per cent of instances where a disaster recovery response was activated, a post incident review had been performed. In 86 per cent of these instances, the outcomes were reported to a relevant governance committee or executive management committee.

Examples of recorded incidents included extensive air quality issues and power outages due to bushfires, system and network outages, and infected and hijacked servers.

Agencies should assess their response to the recent emergencies and the COVID-19 pandemic and update business continuity, disaster recovery and other business resilience frameworks to incorporate lessons learned. Agencies should report to those charged with governance on the results and planned actions.

Management review and oversight Eighty-two per cent and 86 per cent of agencies report to their audit and risk committees (ARC) on their business continuity and disaster recovery planning arrangements, respectively. Only 18 per cent and five per cent of ARCs are briefed on the results of respective scenario testing. Briefing ARCs on the results of scenario testing exercises helps inform their decisions about whether sound and effective business continuity and disaster recovery arrangements have been established.
4. Procurement, including emergency procurement
Policy framework

Agency procurement policies did not capture the requirements of several key NSW Procurement Board Directions (the Directions), increasing the risk of non-compliance with the Directions. We noted: 

  • 67 per cent of agencies did specify that procurement above $650,000 must be open to market unless exempt or procured through an existing Whole of Government Scheme or contract
  • 36 per cent of agencies did specify that procurements above $500,000 payable in foreign currencies must be hedged
  • 69 per cent of agencies' policies did specify that the agency head or cluster CFO must authorise the engagement of consultants where the engagement of the supplier does not comply with the standard commercial framework.

Recommendation: Agencies should review their procurement policies and guidelines to ensure they capture the key requirements of the NSW Government Procurement Policy Framework, including NSW Procurement Board Directions.

Managing contracts

Eighty-eight per cent of agencies maintain a central contract register to record all details of contracts above $150,000, which is a requirement of GIPA legislation. Of the agencies that maintained registers, 13 per cent did not capture all contracts and eight per cent did not include all relevant contract details.

Sixteen per cent of agencies did not periodically review their contract register. Timely review increases compliance with GIPA legislation, and enhances the effectiveness with which procurement business units monitor contract end dates, contract extensions and commence new procurement.

Training and support

Ninety-three per cent of agencies provide training to staff involved in procurement processes, and a further 77 per cent of agencies provide this training on an on-going basis. Of the seven per cent of agencies that had not provided training to staff, we noted gaps in aspects of their procurement activity, including:

  • not conducting value for money assessments prior to renewing or extending the contract with their existing supplier
  • not obtaining approval from a delegated authority to commence the procurement process
  • procurement documentation not specifying certain key details such as the conditions for participation including any financial guarantees and dates for the delivery of goods or supply of services.

Training on procurement activities ensures there is effective management of procurement processes to support operational requirements, and compliance with procurement directions.

Procurement activities While agencies had implemented controls for tender activities above $650,000, 43 per cent of unaccredited agencies did not comply with the NSW Procurement Policy Framework because they had not had their procurement endorsed by an accredited agency within the cluster or by NSW Procurement. This endorsement aims to ensure the procurement is properly planned to deliver a value for money outcome before it commences.
Emergency procurement

As at 30 June 2020, agencies within the scope of this report reported conducting 32,239 emergency procurements with a total contract value of $316,908,485. Emergency procurement activities included the purchase of COVID-19 cleaning and hygiene supplies.

The government, through NSW Procurement released the 'COVID-19 Emergency procurement procedure', which relaxed procurement requirements to allow agencies to make COVID-19 emergency procurements. Our review against the emergency procurement measures found most agencies complied with requirements. For example:

  • 95 per cent of agencies documented an assessment of the need for the emergency procurement for the good and/or service
  • 86 per cent of agencies obtained authorisation of the emergency procurement by the agency head or the nominated employee under Public Works and Procurement Regulation 2019
  • 76 per cent of agencies reported the emergency procurement to the NSW Procurement Board.

Complying with the procedure helps to ensure government resources are being efficiently, effectively, economically and in accordance with the law.

Recommendation: Agency procurement frameworks should be reviewed and updated so they can respond effectively to emergency situations that may arise in the future. This includes:

  • updating procurement policies and guidelines to define an emergency situation, specify who can approve emergency procurement and capture other key requirements
  • using standard templates and documentation to prompt users to capture key requirements, such as needs analysis, supplier selection criteria, price assessment criteria, licence and insurance checks
  • having processes for reporting on emergency procurements to those charged with governance and NSW Procurement.
5. Delegations
Instruments of delegation

We found that agencies have established financial and human resources delegations, but some had not revisited their delegation manuals following the legislative and machinery of government changes. For those agencies impacted by machinery of government changes we noted:

  • 16 per cent of agencies had not updated their financial delegations to reflect the changes
  • 16 per cent of agencies did not update their human resources delegations to reflect the changes.

Delegations manuals are not always complete; 16 per cent of agencies had no delegation for writing off bad debts and 26 per cent of agencies had no delegation for writing off capital assets.

Recommendation: Agencies should ensure their financial and human resources delegation manuals contain regular set review dates and are updated to reflect the Government Sector Finance Act 2018, machinery of government changes and their current organisational structure and roles and responsibilities.

Compliance with delegations

Agencies did not understand or correctly apply the requirements of the Government Sector Finance Act 2018 (GSF Act), resulting in non-compliance with the Act. We found that 18 per cent of agencies spent deemed appropriations without obtaining an authorised delegation from the relevant Minister(s), as required by sections 4.6(1) and 5.5(3) of the GSF Act.

Further detail on this issue will be included in our Auditor-General's Reports to Parliament on Central Agencies, Education, Health and Stronger Communities, which will be tabled throughout December 2020.

Recommendation: Agencies should review financial and human resources delegations to ensure they capture all key functions of laws and regulations, and clearly specify the relevant power or function being conferred on the officer.

6. Status of 2019 recommendations
Progress implementing last year's recommendations

Recommendations were made last year to improve transparency over reporting on gifts and benefits and improve the visibility management and those charged with governance had over actions taken to address conflicts of interest that may arise. This year, we continue to note:

  • 38 per cent of agencies have not updated their gifts and benefits register to include all the key fields required under the minimum standards set by the Public Service Commission
  • 56 per cent of agencies have not provided training to staff and 63 per cent of agencies have not implemented an annual attestation process for senior management
  • 97 per cent of agencies have not published their gifts and benefits register on their website and 41 per cent of agencies are not reporting on trends in the gifts and benefits register to those charged with governance.

While we acknowledge the significance of the recent emergencies, which have consumed agency time and resources, we note limited progress has been made implementing these recommendations. Further detail on the status of implementing all recommendations is in Appendix 2.

Recommendation: Agencies should re-visit the recommendations made in last year's report on internal controls and governance and action these recommendations.

Internal controls are processes, policies and procedures that help agencies to:

  • operate effectively and efficiently
  • produce reliable financial reports
  • comply with laws and regulations
  • support ethical government.

This chapter outlines the overall trends for agency controls and governance issues, including the number of audit findings, the degree of risk those deficiencies pose to the agency, and a summary of the most common deficiencies we found across agencies. The rest of this report presents this year’s controls and governance findings in more detail.

Section highlights

We identified ten high risk findings, compared to four last year with two findings repeated from the previous year. There was an overall increase of 13 per cent in the number of internal control deficiencies compared to last year due to a seven per cent increase in new internal control deficiencies, and a 24 per cent increase in repeat internal control deficiencies. The recent emergencies have consumed agency time and resources and may have contributed to the increase in internal control deficiencies, particularly repeat deficiencies.

We identified a number of findings that remain common across multiple agencies over the last four years. Some of these findings related to areas that are fundamental to good internal control environments and effective organisational governance. Examples include:

  • out of date or missing policies to guide appropriate decisions
  • poor record keeping and document retention
  • incomplete or inaccurate centralised registers, or gaps in these registers.

Policies, procedures and internal controls should be properly designed, be appropriate for the current organisational structure and its business activities, and work effectively.

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency controls to manage key financial systems.

Section highlights

Government agencies’ financial reporting is heavily reliant on information technology (IT). We continue to see a high number of deficiencies related to IT general controls, particularly those related to user access administration. These controls are key in adequately protecting IT systems from inappropriate access and misuse.

IT is also important to the delivery of agency services. These systems often provide the data to help monitor the efficiency and effectiveness of agency processes and services they deliver. Our financial audits do not review all agency IT systems. For example, IT systems used to support agency service delivery are generally outside the scope of our financial audit. However, agencies should also consider the relevance of our findings to these systems.

Agencies need to continue to focus on assessing the risks of inappropriate access and misuse and the implementation of controls to adequately protect their systems, focussing on the processes in place to grant, remove and monitor user access, particularly privileged user access.

 

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency business continuity and disaster recovery planning arrangements.

Section highlights

We identified deficiencies in agency business continuity and disaster recovery planning arrangements and opportunities for agencies to enhance their business continuity management and disaster recovery planning arrangements. This will better prepare them to respond to a disruption to their critical functions, resulting from an emergency or other serious event. Twenty-three per cent of agencies had not conducted a business impact analysis (BIA) to identify critical business functions and determine business continuity priorities and 40 per cent of agencies had not conducted a business continuity scenario testing exercise in the period from 1 January 2019 to 31 December 2019. Scenario testing improves the effectiveness with which a live crisis is handled.

This section focusses on the preparedness of agency business continuity and disaster recovery planning arrangements prior to the onset of the COVID-19 pandemic. While agencies have responded to the recent emergencies, proactively addressing deficiencies will ensure agencies have adequate safeguards in their processes to again respond in the future, if required.

During 2020–21 we plan to conduct a performance audit on 'Business continuity and disaster recovery planning'. This audit will consider the effectiveness of agency business continuity planning arrangements to maintain business continuity through the recent emergencies and/or COVID-19 pandemic and return to a business-as-usual environment. We also plan to conduct a performance audit on whole-of-government 'Coordination of emergency responses'.

 

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of procurement agency procurement policies and procurement activity.

Section highlights

We found agencies have procurement policies in place to manage procurement activity, but the content of these policies was not sufficiently detailed to ensure compliance with NSW Procurement Board Directions (the Directions). The Directions aim to ensure procurement activity achieves value for money and meets the principles of probity and fairness.

Agencies have generally implemented controls over their procurement process. In relation to emergency procurement activity, agencies reported conducting 32,239 emergency procurements with a total contract value of $316,908,485 up to 30 June 2020. Our review of emergency procurement activity conducted during 2019–20 identified areas where some agencies did not fully comply with the 'COVID-19 Emergency procurement procedure'.

We also found not all agencies are maintaining complete and accurate contract registers. This not only increases the risk of non-compliance with GIPA legislation, but also limits the effectiveness of procurement business units to monitor contract end dates, contract extensions and commence new procurement in a timely manner. We noted instances where agencies renewed or extended contracts without going through a competitive tender process during the year.

 

This chapter outlines our audit observations, conclusions and recommendations, arising from our review of agency compliance with financial and human resources delegations.

Section highlights
We found that agencies are not always regularly reviewing and updating their financial and human resources delegations when there are changes to legislation or other organisational changes within the agency or from machinery of government changes. For example, agencies did not understand or correctly apply the requirements of the GSF Act, resulting in non-compliance with the Act. We found that 18 per cent of agencies spent deemed appropriations without obtaining an authorised delegation from the relevant Minister(s), as required by sections 4.6(1) and 5.5(3) of the GSF Act.
In order for agencies to operate efficiently, make necessary expenditure and human resource decisions quickly and lawfully, particularly in emergency situations, it is important that delegations are kept up to date, provide clear authority to decision makers and are widely communicated.

Appendix one – List of 2020 recommendations 

Appendix two – Status of 2019 recommendations

Appendix three – Cluster agencies

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for State Finances 2020

State Finances 2020

Education
Finance
Community Services
Health
Justice
Industry
Planning
Environment
Premier and Cabinet
Transport
Treasury
Whole of Government
Financial reporting

The Auditor-General for New South Wales, Margaret Crawford, released her report today on State Finances for the year ended 30 June 2020.

‘I am pleased to once again report that I issued an unmodified audit opinion on the State’s consolidated financial statements,’ the Auditor-General said.

The report acknowledges this has been a challenging year, with New South Wales impacted by natural disasters and the COVID-19 pandemic.

The State’s Budget Result, reported in the financial statements, was a deficit of $6.9 billion. This is different to the 2019-20 budget forecast surplus of $1.0 billion and is an outcome of the government’s significant response to bushfires and COVID-19.

The report summarises a number of audit and accounting matters arising from the audit of the Total State Sector Accounts, a sector that comprises 291 entities controlled by the NSW Government with total assets of $495 billion and total liabilities of $256 billion.

Read full report (PDF)

Our audit opinion on the State’s 2019–20 financial statements was unmodified

An unmodified audit opinion was issued on the State’s 2019–20 consolidated financial statements.

The State extended signing its financial statements by six weeks.

Natural disasters, the COVID-19 pandemic and other factors impacted the State’s 2019–20 reporting timetable. The State extended signing its financial statements by six weeks, compared with 2018–19.

All agencies were also given a two-week extension to prepare their financial statements compared with 2018–19. Further extensions beyond two weeks were subsequently approved for the following 11 agencies (7 in 2018–19) to submit completed financial statements for audit:

  • Department of Communities and Justice
  • Department of Customer Service
  • Department of Planning, Industry and Environment
  • Department of Regional NSW
  • Department of Transport
  • Environment Protection Authority
  • Infrastructure NSW
  • Lord Howe Island Board
  • NSW Crown Holiday Parks Land Manager
  • Service NSW
  • Water Administration Ministerial Corporation.

The extensions reflected that the COVID-19 pandemic impacted agencies’ work environments during the first six months of 2020. This was at a time when many were still implementing machinery of government changes and preparing to implement three significant new accounting standards:

  • AASB 15 Revenue from Contracts with Customers (issued December 2014, effective 1 July 2019)
  • AASB 16 Leases (issued February 2016, effective 1 July 2019)
  • AASB 1058 Income of Not-for-profit entities (issued December 2016, effective 1 July 2019).

These new accounting standards were issued some years before they became effective, to allow reporting entities sufficient time to prepare for implementation. Notwithstanding this, some agencies had not fully implemented the new accounting standards in time for early close procedures, and the unforeseen impact of COVID-19 further complicated the year-end financial reporting processes for the State and its agencies.

The graph below shows the number of reported errors exceeding $20 million over the past five years in agencies’ financial statements presented for audit.

In 2019–20, agency financial statements presented for audit contained 19 errors exceeding $20 million (six in 2018–19). The total value of these errors increased to $1.4 billion ($927 million in 2018–19).

The errors resulted from:

  • incorrectly applying Australian Accounting Standards and Treasury Policies
  • incorrect judgements and assumptions when valuing noncurrent physical assets and liabilities
  • incorrectly interpreting the accounting treatment for unspent stimulus funding.

Errors in agency financial statements exceeding $20m (2016–2020)

$4.1 billion in stimulus funding was allocated in 2019–20

The government implemented an economic stimulus package primarily to mitigate the impacts of the COVID-19 pandemic on New South Wales.

The COVID-19 pandemic and bushfires had a significant impact on the State’s finances, reducing its revenue and increasing its expenses especially in sectors directly responsible for responding to the COVID-19 pandemic, such as Health.

The government announced a $4.1 billion health and economic stimulus package in 2019–20. This primarily included:

  • $2.2 billion in health measures including purchases of essential medical equipment and increasing clinical health capacity (like intensive care spaces)
  • $1.0 billion in small business and land tax relief
  • $355 million in extra cleaning services and quarantine costs.

Cluster agencies had spent $3.0 billion (just under 75 per cent) of the COVID-19 stimulus package by 30 June 2020.

The Health cluster incurred most of this expenditure.

Total spend relating to bushfires was $1.3 billion in 2019–20.

The graph below shows the total allocation and spend by cluster to 30 June 2020.

Economic stimulus allocation and spend by cluster to 30 June 2020

Deficit of $6.9 billion compared with a budgeted surplus of $1.0 billion

An outcome of the government’s overall activity and policies is its net operating balance (Budget Result). This is the difference between the cost of general government service delivery and the revenue earned to fund these sectors.

The General Government Sector, which comprises 199 entities, generally provides goods and services funded centrally by the State.

The Non-General Government Sector, which comprises 92 government businesses, generally provides goods and services, such as water, electricity and financial services that consumers pay for directly.

The Budget Result for the 2019–20 financial year was a deficit of $6.9 billion. The original budget forecast, set before the COVID-19 pandemic and bushfires, was a $1.0 billion surplus. The main driver of the change in result was:

  • $1.3 billion of higher employee costs, mainly due to:
    • increased workers compensation claims
    • additional personnel required (mainly in the Health sector) to respond to the COVID-19 pandemic
  • $2.3 billion of higher operating expenses, mainly due to:
    • $828 million from first time recognition of a child abuse claim liability
    • $507 million from additional insurance claims from the NSW bushfires
    • $343 million from COVID-19 claims by agencies for loss of revenue.
  • $1.8 billion in higher grants and subsidy expenses, mainly due to:
    • small business grants
    • COVID-19 quarantine compliance measures
    • costs incurred in response to the 2019–20 bushfires, drought and disaster relief payments
    • third party-controlled assets that were subsequently transferred to councils and utility providers, mainly arising from construction of the CBD and South East Light Rail.

The deficit was further driven by:

  • $1.9 billion less taxation revenue, mainly resulting from:
    • $1.3 billion less in payroll tax due to relief measures introduced by the government as part of its COVID-19 economic stimulus
    • $424 million less in gambling and betting taxes, due to venue closures required by COVID-19 public health orders
  • $523 million less in dividends and income tax revenue from the Non-General Government Sector, due to lower dividends received from NSW Treasury Corporation and from the State’s other commercial government businesses
  • lower fines, regulatory fees and other revenue, due to a $305 million decrease in mining royalties, largely driven by lower coal prices.

Main drivers of the 2019–20 actual vs. budget variance

Revenues increased $209 million to $86.3 billion

In 2019–20, the State’s total revenues increased by $209 million to $86.3 billion, 0.2 per cent higher than in 2018–19. COVID-19 impacted taxation revenue, which fell by $1.1 billion and revenue from the sale of goods and services, which fell by $1.1 billion. These falls were offset by a $2.5 billion (7.7 per cent) increase in grants and subsidies from the Australian Government, mainly in the form of additional stimulus funding.

Taxation revenue fell 3.5 per cent

Taxation revenue fell by $1.1 billion, mainly due to a:

  • $861 million fall in payroll tax as a result of COVID-19 relief (reduced payroll tax payments for eligible small businesses)
  • $430 million fall in stamp duty collections, driven by lower than expected growth in the property market
  • $427 million decline in gambling and betting taxes, mainly due to venue closures driven by COVID-19 public health orders.

Stamp duties of $8.8 billion were the largest source of taxation revenue, $473 million higher than payroll tax, the second-largest source of taxation revenue.

Australian Government grants and subsidies

The State received $34.2 billion in grants and subsides which are mainly from the Australian Government, $2.4 billion more than in 2018–19.

The increase was driven by a $1.1 billion increase in Commonwealth Specific Purpose Payments to support the Health cluster respond to the COVID-19 pandemic. Commonwealth National Partnership Payments increased by a similar amount to provide the State with Natural Disaster relief.

Sales of goods and services

In 2019–20, sales of goods and services fell $1.1 billion. This was due to the COVID-19 pandemic reducing:

  • patronage and related transport passenger revenue
  • health billing activities with elective surgery being put on hold
Fines, regulatory fees and other revenues

Fines, regulatory fees and other revenues fell $505 million. This was mainly due to a $409 million decrease in mining royalties attributed to a drop in thermal coal prices during 2019–20.

Other dividends and distributions

Other dividends and distributions rose by $616 million due to higher distributions received from the State’s investments. This was due to an additional $1.3 billion held in the State’s investment portfolio compared with last year.

Expenses increased $8.2 billion to $96.0 billion

The State’s expenses increased 9.3 per cent compared with 2018–19. Most of the increase was due to higher employee expenses, other operating costs and grants and subsidies.

Employee expenses, including superannuation, increased 5.7 per cent to $42.6 billion.

Salaries and wages increased to $42.6 billion from $40.3 billion in 2018–19. This was mainly due to increases in staff numbers and a 2.5 per cent increase in pay rates across the sector. Salaries and wages for the Education and Health sectors increased by $659 million and $732 million in each sector respectively.

The Health sector employed an additional 2,763 full time staff in 2019–20. It also incurred more overtime in response to COVID-19. Education increased staff numbers by 4,866 full time equivalents and paid a one off 11 per cent pay rise to school administration staff in 2019–20. Historically, the government wages policy aims to limit growth in employee remuneration and other employee related costs to no more than 2.5 per cent per annum.

Operating expenses increased 8.7 per cent to $27.0 billion.

Operating expenses increased to $27.0 billion in 2019–20 ($24.8 billion in 2018–19) due to higher operating activities in Health. The higher level of activities and related costs is attributed to a full year of operations at the Northern Beaches Hospital (opened November 2018), and responding to COVID-19. The response to COVID-19 involved the State providing viability payments to private hospitals, higher visiting medical officer costs due to additional overtime hours and spending more on equipment to set up COVID-19 testing clinics.

Insurance claims increased by $2.0 billion. This was mainly due to NSW Self Insurance Corporation (SiCorp) recognising a liability for child abuse claims incurred but not reported for the first time, and claims for the 2019–20 bushfires, floods and COVID-19.

Health costs remain the State’s highest expense.

Total expenses of the State were $96 billion ($87.8 billion in 2018–19). Traditionally, the following clusters have the highest expenses as a percentage of total government expenses:

  • Health – 24.3 per cent (25.8 per cent in 2018–19)
  • Education – 17.6 per cent (19.3 per cent in 2018–19)
  • Transport - 12.8 per cent (12.6 per cent in 2018–19).

General public service expenses as a percentage of total State expenses is higher due to a $2.0 billion increase in SiCorp’s accrued claim expenses.

Other expenses increased due to additional grant funding by the State for drought relief and COVID-19 stimulus spend.

Health expenses increased by $632 million compared with 2018–19 but fell as a proportion of total State expenses.

Education expenses remained stable compared with last year due to savings in student transportation costs primarily driven by COVID-19. This led to a decrease in the proportion of the State’s costs relating to education activities.

Grants and subsidies increased $2.5 billion to $14.1 billion.

The increase in grants and subsidies was due to payments the State made to support businesses and local communities in the face of COVID-19 and bushfires. In addition, the State transferred CBD and South East Light Rail assets to councils and utility providers during 2019–20 as it no longer controlled these.

Depreciation expense increased $1.0 billion to $9.2 billion.

Depreciation increased to $9.2 billion from $8.0 billion in 2018–19. At 1 July 2019, the State implemented the new leases standard recognising a right of use (ROU) asset and related lease liability in its financial statements. The value of ROU assets are amortised over the term of the lease. This contributed to $980 million of the increase in 2019–20 depreciation expense. Last year, these costs were previously reported within other operating expenses.

Assets grew by $28.0 billion to $495 billion

The State’s assets primarily include physical assets such as land, buildings and infrastructure, and financial assets such as cash, and other financial instruments and equity investments. The value of total assets increased by $28.0 billion to $495 billion. This was a six per cent increase compared with 2018–19, mostly due to changes in asset carrying values.

Of the State’s $28.0 billion increase in asset values, $9.3 billion was due to a new accounting standard requirement for operating leases to be valued and recorded on balance sheet for the first time.

AASB 16 Leases requires entities recognise values for right-ofuse assets (ROU) for the first time. An ROU asset is a lessee’s right to use an asset, the value of which is amortised over the term of the lease. This standard came into effect from 1 July 2019.

Valuing the State’s physical assets

State’s physical assets valued at $365 billion.

The value of the State’s physical assets increased by $14.1 billion to $365 billion in 2019–20. The assets include land and buildings ($168 billion), infrastructure ($180 billion) and plant and equipment ($16.7 billion). A prior period error relating to the valuation of RMS infrastructure assets reduced the reported values by $1.0 billion from $352 billion to $351 billion at 30 June 2019.

The movement in physical asset values between years includes additions, disposals, depreciation and valuation adjustments. Other movements include reclassification of physical assets leased under finance leases to right of use assets upon adoption of AASB 16 Leases on 1 July 2019.

Movements in physical asset values

Liabilities increased $38.4 billion to $256 billion

The State borrowed additional funds in response to natural disasters and COVID-19.

The State’s borrowings rose by $33.9 billion to $113.8 billion at 30 June 2020. This accounted for most of the increase in the State’s total liabilities.

The value of TCorp bonds on issue increased by $25.2 billion to $97.0 billion to largely fund capital expenditure and costs associated with the bushfires, drought and COVID-19.

TCorp bonds are actively traded in financial markets and are guaranteed by the NSW Government.

Over 2019–20, TCorp continued to take advantage of lower interest rates, buying back short-term bonds and replacing them with longer dated debt. This lengthens the portfolio matching liabilities with the funding requirements for infrastructure assets.

With effect from 1 July 2019, AASB 16 Leases required the State to recognise liabilities for operating leases for the first time. This increased total lease liabilities from $5.3 billion at 30 June 2019 to $11.8 billion at 30 June 2020.

More than a third of the State’s liabilities relate to its employees. They include unfunded superannuation and employee benefits, such as long service and recreation leave.

Valuing these obligations involves complex estimation techniques and significant judgements. Small changes in assumptions and other variables, such as a lower discount rate, can materially impact the valuation of liability balances in the financial statements.

The State’s unfunded superannuation liability rose $300 million from $70.7 billion to $71.0 billion at 30 June 2020. This was mainly due to a lower discount rate of 0.87 per cent (1.32 per cent in 2018–19). The State’s unfunded superannuation liability represents the value of its obligations to past and present employees less the value of assets set aside to fund those obligations.

 

The State maintained its AAA credit rating

The object of the Fiscal Responsibility Act 2012 is to maintain the State’s AAA credit rating.

The government manages New South Wales’ finances in accordance with the Fiscal Responsibility Act 2012 (the Act).

The Act establishes the framework for fiscal responsibility and the strategy to maintain the State’s AAA credit rating and service delivery to the people of New South Wales.

The legislation sets out targets and principles for financial management to achieve this.

This year, the State’s credit rating from Standard & Poor’s changed from AAA/Stable to AAA/Negative. Moody’s Investors Service credit rating of Aaa/Stable did not change from the previous year.

The fiscal target for achieving this objective is that General Government annual expenditure growth should be lower than long term average revenue growth.

The State did not achieve its fiscal target of maintaining annual expenditure growth below the long-term revenue growth rate target of 5.6 per cent.

In 2019–20, General Government expenditure grew by 9.7 per cent (5.5 per cent in 2018–19).

Expenditure items that contributed most to the growth rate include:

  • recurrent grants and subsidies (20.4 per cent)
  • other operating expenses (9.5 per cent)
  • employee costs (including superannuation) (5.6 per cent)

Recurrent grant and subsidy expenses increased by $2.8 billion in 2019–20 mainly due to the COVID-19 and natural disaster payments. Other operating expenses increased mainly due to a $2.0 billion increase in SiCorp insurance claims. This included the $828 million provision for child abuse claims incurred but not reported. The bushfires and COVID-19 pandemic also increased the number and cost of claims in 2019–20.

Superannuation funding position since inception of the Act - AASB 1056 Valuation