The Auditor-General for New South Wales, Margaret Crawford, released a report today examining the planning and delivery of new, redeveloped and upgraded public schools.

School Infrastructure NSW has identified the need to accommodate an additional 180,000 enrolments in public schools by 2039 with a large portion of this growth expected in metropolitan Sydney. It has also identified that around 34,000 teaching spaces will require upgrading to be fit-for-purpose.

Although School Infrastructure NSW has developed a long-term strategic plan that advises government of ongoing funding requirements, it has not presented a list of priorities to meet those needs. Developing a longer-term list of priorities would help signal the areas of greatest need and allow more time to develop the best options to meet those needs.

The audit found that School Infrastructure NSW has focused on delivering existing projects, election commitments and other government announcements. This has diverted attention from identifying and delivering projects that would have better met present and future needs. 

The report makes eight recommendations to improve long-term planning for future needs, strengthen the quality of estimated project costs and benefits, and embed a continuous improvement program. 

In 2016, the Department of Education prepared a School Assets Strategic Plan (2016 SASP) which outlined long-term funding needs to support the expected growth in enrolments to 2031. Following the release of the 2016 SASP, the NSW Government substantially increased funding for new and upgraded schools from $2.4 billion in the 2016–17 State Budget to $4.2 billion in 2017–18.

In 2017, the Department of Education established School Infrastructure NSW (SINSW) to lead the delivery of the 2016 SASP and the 123 new projects announced in the 2017–18 Budget. This significantly larger program of work required rapid development of internal capacity, governance arrangements, and project management systems. This needed to be done at the same time as scoping and planning for the list of announced projects.

As there are limited funds available to meet growing needs across the State, it is important that SINSW has effective methods to prioritise projects to communities with the greatest need. To ensure that projects deliver value for money, business cases need to have robust estimates of project costs and benefits. Business cases also need to account for the inherent risks in delivering infrastructure projects. Unplanned cost escalations can reduce the number of new or modernised classrooms SINSW can deliver. Unforeseen delays may also impact families who make significant life choices based on their expectations that a school will open at the beginning of the school year.

The objective of this audit was to assess the effectiveness of planning and delivery of new, upgraded and redeveloped schools to meet demand for public school education in New South Wales. To address this objective, the audit examined whether the Department:

  • has effective procedures for planning and prioritising school capital works to meet present and future demands
  • develops robust business cases for school capital works that reliably inform decision-making
  • has effective program/project governance and management systems that support delivering projects on-time, within budget and achievement of intended benefits.

The audit examined business cases for 12 projects as case studies. These include a mix of projects initiated before and after the establishment of SINSW.

This audit commenced in June 2020 and examined strategies and demographic projections developed prior to the emergence of COVID-19. This audit did not examine potential longer-term impacts of COVID-19 on future demands for public school education.

Conclusion

School Infrastructure NSW has been focused on delivering existing projects, election commitments and other government announcements. This has diverted attention from identifying and delivering projects that would have better met present and future student and classroom needs. While it has developed a long-term strategic plan that advises government of ongoing funding requirements, it has not presented a list of priorities to meet these needs.

In its first years of operation, SINSW has focused on delivering existing projects and the 123 new projects announced in the 2017–18 Budget. Further NSW Government announcements in the 2018–19 Budget, election commitments in the 2019–20 Budget, and announcements in the 2020–21 Budget, made up the majority of new projects, rather than projects prioritised by SINSW. 

In early 2020, SINSW advised the NSW Government that the currently funded infrastructure program would not meet forecast classroom requirements for 2023 and beyond. The School Asset Strategic Plan 2020 estimates the annual level of investment needed over the next 20 years to meet growth, update and upgrade facilities to meet compliance obligations. However, SINSW’s ten-year Capital Investment Plans for 2018–19, 2019–20 and 2020–21 only identified priorities over a two-year horizon.

Developing a longer-term pipeline of priorities would signal the areas of greatest need and allow greater scope to consider a range of options to best meet those needs.

SINSW has made progress in planning across geographic areas but needs to better prioritise which projects move forward.

Given the current and projected needs for new classrooms, it is vital that SINSW provides long-term advice based on thorough state-wide analysis to help prioritise projects that best meet this demand.

SINSW has improved its capabilities, processes, and systems to support planning in ‘School Community Groups’, which are clusters of between 5 to 15 schools in a geographic area. This addresses a key direction identified in the School Assets Strategic Plan 2016. It has developed a planning tool which allows it to prioritise School Community Groups based on weighted criteria. It has also developed an approach to identify potential projects within School Community Groups but has not yet put in place a structured process to prioritise which projects move to the business case stage to seek funding for delivery.

Business cases we examined established service needs, but several had shortcomings in scope definition, cost estimation and risk identification.

Most business cases we examined demonstrated the service need and consultation with stakeholders helped to incorporate educational requirements. Common templates and specific cost-benefit guidance developed in partnership with NSW Treasury has helped to promote consistency across business cases.

However, there were shortcomings in several business cases we reviewed. Business cases for projects already announced by government presented a limited number of options, and the process for eliminating other options was not transparent. Cost increases and contingency drawdowns for several projects indicate that scoping, costing and risk assessments could be improved, especially for complex projects.

Standard program management systems and governance arrangements support project delivery, however, there is scope for better ongoing oversight of benefits.

SINSW applies standard governance arrangements to projects based on their size. Higher value projects have executive oversight while lower value projects are overseen on a regional basis. SINSW has improved its project management systems to provide more consistent data and greater transparency to senior management over project status, cost and use of contingencies.

SINSW has worked with NSW Treasury to define a consistent set of benefits for new and redeveloped schools. Estimated benefits are currently based on international contexts but SINSW advises it is undertaking further research to improve the evidence base in this area. The current approach to ongoing monitoring, reporting and evaluation of project benefits places responsibility on the infrastructure delivery team. This team is not the most appropriate area to monitor ongoing benefits, which are expected to accrue many years after delivery and depend on actions in other areas of the Department.

1. Key findings

SINSW delivered projects against an established program of works in its first years of operation

At establishment, SINSW inherited a portfolio of existing projects and 123 new projects announced as part of the 2017–18 Budget (to commence over 2017–18 and 2018–19). It has progressively worked through individual project planning to deliver against these projects.

The 2018–19 Budget funded two new projects that had not already been announced. Both projects were identified by SINSW as a priority. The 2018–19 Budget also allocated funding for 'planning' 22 new projects. Seventeen of the 22 projects had been identified by SINSW as a priority.

SINSW identified 31 new priority projects in its Capital Investment Plan for 2019–20. Thirteen of these projects were funded in that year with a further 27 projects included as election commitments. SINSW identified 20 new projects in its Capital Investment Plan for 2020–21 but only two of these were funded. SINSW advised this was due to a constrained budget environment.

There is an anticipated shortfall of classrooms based on the current funded program

Despite increased funding since 2017–18, SINSW advised the NSW Government in early 2020 that the currently funded infrastructure program would not meet forecast classroom requirements for 2023 and beyond. Accordingly, it is vital that new funding is prioritised to projects which best meet demand.

SINSW only identified specific priorities over a two-year horizon in its Capital Investment Plans for 2018–19, 2019–20 and 2020–21. The School Assets Strategic Plan 2016 and the 2020 update make the case for sustained funding for school building and redevelopment. These plans estimate annual funding requirements and show geographic areas with increasing forecast enrolments. Detailing how priorities over a ten-year timeframe fit within a ten-year capital planning limit would create more certainty about meeting growth demands.

There has been progress in formalising prioritisation frameworks, data tools and supporting governance arrangements

SINSW committed to planning for new and redeveloped schools in 'School Community Groups' in the School Assets Strategic Plan 2016. This is a new way of planning which considers the educational needs over a defined geographical area. It has developed a planning tool to prioritise School Community Groups based on weighted criteria. It has also established governance frameworks to improve transparency over decisions to reprioritise this list.

SINSW has refined its approach to planning in School Community Groups over the past four years. It now prepares Service Needs Reports to investigate needs, identify projects, prioritise, determine scope and timing, and assess non-capital options. SINSW has yet to finalise arrangements for how needs identified in Service Needs Reports progress to the strategic business case stage.

Projects announced prior to developing a business case have less opportunity to consider a range of options to meet the service needs

Business cases for projects already announced by government (or announced for planning) go through the same process of determining the service need and impacts on surrounding schools. However, for some announced projects, the range of options considered in the business case is influenced by the parameters of the announcement. This makes it more difficult to genuinely pursue alternate options that could better meet the identified service need.

Projects identified by SINSW have a more rigorous process of considering options. Service Needs Reports explore a wide range of asset and non-asset interventions across the School Community Group. Options are narrowed as the projects move through the strategic and final business case stages. SINSW uses its Investment Review Committee to engage key stakeholders early in the process so that they are informed about how non-asset solutions have been considered and why SINSW is progressing the business case for a capital solution for particular projects.

Several business cases underestimated project costs and risks, leading to scope and budget increases

Several business cases we reviewed did not adequately identify the initial scope requirements, project-specific risks or the likely project cost. For two business cases, this appeared to be due to an attempt to fit the project within a predetermined amount. Announcing a project’s scope, budget and timeframe before proper planning increases risks to successful delivery against expectations.

Several of the projects we examined required drawdowns on contingency funds due to inadequate consideration of scope, costs and project risks at the planning stage. Contingency funds are intended for unanticipated extra costs rather than those that could have or should have been identified at the planning stage.

Guidance on benefit calculations has provided a consistent framework for business cases

Business cases we examined presented a consistent set of benefits based on guidance developed in partnership with NSW Treasury. Following this guidance helps to compare cost-benefit analyses across business cases. However, the evidence for the estimated benefits is based on contexts outside of NSW. SINSW has the tools and data sources to calculate benefits more suited to the context of particular schools. Doing so would improve the accuracy of cost-benefit analyses. SINSW advised that it is currently updating the guidance in partnership with NSW Treasury.

SINSW involves school principals, executives and teaching staff in developing education rationales when commencing projects. These documents help align projects with education outcomes. They also provide a baseline for post-occupancy evaluation, which is important to determine whether the new school infrastructure is being used in the ways that were anticipated in the business case.

SINSW could elevate its existing assurance review process to consolidate lessons learned

SINSW engages external peer reviewers to conduct assurance reviews on its projects at multiple stages of planning and delivery. It has established a Community of Practice for external reviewers to keep them up to date on new developments and requirements. Higher value projects are also subject to review by Infrastructure NSW under the Investor Assurance Framework.

By looking at all projects at all stages, assurance reviews can identify systematic issues across the full portfolio of projects. A recent assurance review analysed common findings from reviews of strategic and final business cases. This provides a helpful way to improve internal processes. SINSW advised that it is implementing a continuous improvement program, which will be able to take findings from assurance reviews to build organisational capabilities.

2. Recommendations

By September 2021, the Department of Education should:

  1. finalise the investment prioritisation approach with agreement from key stakeholders
  2. finalise and update on an ongoing basis a ten-year list of priorities to meet the forecast demand for new classrooms and contemporary fit for purpose learning environments, which identifies individual projects and programs in the short-term and priority geographic areas and programs in the medium-term
  3. seek a ten-year Capital Planning Limit from NSW Treasury to ensure the needs identified in the ten-year list of priorities are met and are coordinated with the forward capital programs of other agencies
  4. improve the quality of data on cost benchmarks that underpin the annual ten-year Capital Investment Plan and updates to the School Assets Strategic Plan
  5. embed an evidence-based cost benefit analysis framework for school investment, in consultation with NSW Treasury, by:
    • validating benefits estimated in previous business cases with actual results
    • building the evidence base in relation to contemporary learning environments
  6. regularly share data on forecast needs with relevant planning agencies to promote strategic opportunities for servicing education needs
  7. implement the continuous improvement program for service planning, options assessment, business case development, project delivery and handover. The program should be informed by findings from assurance reviews, post-occupancy evaluations and project lessons learned
  8. establish benefits realisation processes and practices that:
    • ensure business cases set baselines and targets for benefits
    • review benefits during delivery, prior to handover and as part of Post Occupancy Evaluations
    • identify which part(s) of the Department are best placed to develop, manage and evaluate benefits on an ongoing basis.

Note:

The Department's formal response to this report at Appendix one states that while it 'supports the recommendations, it considers the proposed six-month timeframe to be an unreasonably short period for a large and complex organisation to effectively implement many of these recommendations'. It suggests 12 months would be needed to implement the recommendations.

The recommendations stemming from this audit are core business for SINSW. The Audit Office considers it important for SINSW to place priority on implementing the recommendations in time to inform the 2022–23 budget cycle. Extending the deadline to April 2022 would place action outside of that budget cycle.

There have been significant increases in funding for education infrastructure since the 2017–18 Budget and further growth in demand for places in schools is forecast. SINSW has the challenge, not only of meeting the need for new classrooms due to population growth, but also upgrading facilities to enable modern teaching techniques. In addition, community expectations of what constitutes a vibrant and successful school community continues to increase.

Given growing demand and budget constraints, projects must be selected to best meet the needs of the community and planning and prioritisation are vital. SINSW has been progressing planning for announced projects as well as implementing a new type of strategic state-wide planning and prioritisation, cluster planning, where options are developed for School Community Groups.

The primary role of a business case is to reliably inform an investment and/or policy decision. Over the period of review, the NSW Government's guidelines for business cases have established this requires recommendations based on convincing arguments, sufficient evidence, and accurate costing of alternatives and expected benefits. Business case guidelines are underpinned by guides for economic appraisal and cost-benefit analysis.

As SINSW moves to prioritise business cases for interventions in School Community Groups, it will increasingly need to demonstrate rigour in its assessment of all options. It will also need to ensure that scope identification, cost and risk planning and the setting of contingencies are accurate. This will help decision-makers better understand, plan for and manage the investment required to meet the demand for school infrastructure.

For this audit, we examined business cases and related documentation for 12 projects. Several of these projects were developed before School Infrastructure NSW was established in mid-2017.

Over the period of review, NSW Government policies for business case development and submission have emphasised that effective governance arrangements are critical to a proposal's successful implementation.

SINSW's guidance similarly highlight the importance of effective governance and project management for achieving good outcomes. It prescribes a general governance structure managed by SINSW that can be tailored to the planning and delivery of school infrastructure projects.

Appendix one – Response from agency
 
Appendix two – About the audit 

Appendix three – Performance auditing 


Copyright Notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #347 - released (8 April 2021).

Auditor-General’s Report to Parliament on Delivering School Infrastructure 

This corrigendum has been prepared to amend the following text within my Auditor-General’s Report to Parliament on Delivering School Infrastructure, dated 8 April 2021. 

On page two, the original text was as follows: 

Further NSW Government announcements in the 2018–19 Budget and election commitments in the 2019–20 Budget made up the majority of new projects, rather than projects prioritised by SINSW. 

The original text has now been changed to 

Further NSW Government announcements in the 2018–19 Budget, election commitments in the 2019–20 Budget, and announcements in the 2020–21 Budget, made up the majority of new projects, rather than projects prioritised by SINSW. 

On page three, the original text was as follows: 

The 2018–19 Budget funded three new projects that had not already been announced. One of the three projects was identified by SINSW as a priority. 

The original text has now been changed to: 

The 2018–19 Budget funded two new projects that had not already been announced. Both projects were identified by SINSW as a priority. 

On page three the original text was as follows: 

SINSW identified 33 priority projects in its Capital Investment Plan for 2019–20.

The original text has now been changed to  

SINSW identified 31 new priority projects in its Capital Investment Plan for 2019–20. 

On page eleven, in Exhibit 4, the original text was as follows: 

The 2018–19 NSW Budget announced funding for an additional 43 new and upgraded schools to commence works in 2018–19. Of the 43 projects: 

•    1 was identified by SINSW as a priority in its Capital Investment Plan (SINSW requested funding for one new project)
•    40 had already been announced
•    2 were new announcements (not identified as a priority by SINSW in its Capital Investment Plan).

The original text has now been changed to: 

The 2018–19 NSW Budget announced funding for an additional 42 new and upgraded schools to commence works in 2018–19. Of the 42 projects: 

•    2 were identified by SINSW as a priority in its Capital Investment Plan (SINSW requested funding for two new projects)
•    40 had already been announced.

On page eleven, the original text was as follows: 

The 2019–20 NSW Budget announced funding for an additional 40 new and upgraded schools as election commitments. Of the 40 election commitment projects: 

•    13 were identified by SINSW as priorities in its Capital Investment Plan (SINSW requested funding for a total of 33 new projects)
•    27 were new announcements (not identified as a priority by SINSW in its Capital Investment Plan).

The original text has now been changed to: 

The 2019–20 NSW Budget announced funding for an additional 40 new and upgraded schools as election commitments. Of the 40 election commitment projects: 

•    13 were identified by SINSW as priorities in its Capital Investment Plan (SINSW requested funding for a total of 31 new projects)
•    27 were new announcements (not identified as a priority by SINSW in its Capital Investment Plan).

The above changes will be reflected in the version of the report published on the Audit Office website and should be considered the true and accurate version.