Actions for CBD South East Sydney Light Rail: follow-up performance audit

CBD South East Sydney Light Rail: follow-up performance audit

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk
Service delivery

This is a follow-up to the Auditor-General's November 2016 report on the CBD South East Sydney Light Rail project. This follow-up report assessed whether Transport for NSW has updated and consolidated information about project costs and benefits. The audit found that Transport for NSW has not consistently and accurately updated project costs, limiting the transparency of reporting to the public. The Auditor-General reports that the total cost of the pr

Published

Actions for Train station crowding

Train station crowding

Transport
Management and administration
Risk
Service delivery
Workforce and capability

Sydney Trains patronage has increased by close to 34 per cent over the last five years, and Transport for NSW (TfNSW) expects the growth in patronage to continue over the next 30 years. As patronage increases there are more passengers entering and exiting stations, moving within stations to change services, and waiting on platforms. As a result, some Sydney metropolitan train stations are becoming increasingly crowded. There are three main causes of sta

Published

Actions for Solar Bonus Scheme

Solar Bonus Scheme

Premier and Cabinet
Compliance
Infrastructure
Management and administration
Project management
Regulation
Risk
Service delivery

A NSW Auditor General’s Report has found that the NSW Government and its agencies grossly underestimated the cost and number of people that would install systems under the Solar Bonus Scheme. By October 2010, the estimated cost of the Scheme, if it continued the way it was going, would have reached $3.988 billion. More than ten times the original estimate of $362 million. In response to the increased cost, the gross tariff for new applicants was reduced

Published

Actions for Prequalification Scheme: Performance and Management Services

Prequalification Scheme: Performance and Management Services

Premier and Cabinet
Finance
Compliance
Internal controls and governance
Management and administration
Regulation
Risk
Workforce and capability

There have been tangible improvements in the time it takes NSW Government agencies to engage consultants through the Government’s Prequalification Scheme. The Scheme was introduced in February 2008 to improve agencies’ procurement of consultants. More than 300 service providers have been prequalified and over $300 million worth of consultancy services have been provided. Ideally agencies should know what assignments each consultant has won, for what serv

Published

Actions for The Cross City Tunnel Project

The Cross City Tunnel Project

Transport
Treasury
Premier and Cabinet
Planning
Environment
Infrastructure
Management and administration
Procurement
Project management
Risk

In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs. Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate. In our opinion, however, the Government, Treasury an

In progress

Actions for Service NSW's handling of personal information

Service NSW's handling of personal information

Premier and Cabinet
Finance
Compliance
Cyber security
Fraud
Information technology
Internal controls and governance
Management and administration
Risk
Service delivery

This audit will assess how effectively Service NSW handles personal customer and business information to ensure its privacy. We will address the audit objective with the following audit criteria: Does Service NSW have processes and governance in place to identify and manage risks to the privacy of personal customer and business information? Does Service NSW have policies, processes and systems in place that support the effective handling of personal c

In progress

Actions for WestConnex: Changes since 2014

WestConnex: Changes since 2014

Transport
Compliance
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk
Service delivery

The WestConnex project is a motorway project that will link the M4 and M5 motorways with 33km of new motorway tunnels in Sydney. We conducted a performance audit of the WestConnex business case review process in 2014. Since then, the scope and projects included in WestConnex have changed. This audit will assess whether Transport for NSW and Infrastructure NSW effectively assessed and justified major scope changes to the WestConnex project since December