Actions for Funding enhancements for police technology

Funding enhancements for police technology

Justice
Community Services
Information technology
Management and administration
Procurement
Project management

This report focuses on how the NSW Police Force managed a $100 million program to acquire new technology. The program invested in technologies intended to make police work safer and quicker. These included body-worn video (BWV) cameras, smart phone devices, mobile fingerprint scanners and hand-held drug testing devices.

The audit found that while the NSW Police Force mostly managed the ‘Policing for Tomorrow’ program effectively, investment decision making could be improved in the future. The NSW Police Force missed an opportunity to take a whole-of-organisation approach to identify capability gaps and target the acquired technologies to plug these.

The NSW Police Force has processes in place to monitor the benefits of some of the larger technology, but it does not do this consistently for all procured technology. It could not demonstrate that smaller projects are improving the efficiency or effectiveness of policing.

The audit also found that the NSW Police Force does not routinely engage with external stakeholders on the use or impacts of new technology that changes how officers interact with the public, noting that this will not always be possible for particularly sensitive procurements that involve covert technologies or methodologies.

The Auditor-General made three recommendations to guide improvement of NSW Police Force ICT procurement, benefits management and stakeholder engagement processes.

Read full report (PDF)

Ahead of the March 2015 election, the NSW Government announced a $100 million Policing for Tomorrow fund for the NSW Police Force to acquire technology intended to make police work safer and quicker. The announcement committed the NSW Police Force to several investment priorities, including body-worn video (BWV) cameras, smart phone devices (MobiPOL), mobile fingerprint scanners and hand-held drug testing devices. Otherwise, the NSW Police Force was allowed flexibility in identifying and resourcing suitable projects.

This audit assessed whether the Policing for Tomorrow fund was effectively managed to improve policing in New South Wales. We addressed the audit objective with the following audit questions:

  • Did the NSW Police Force efficiently and effectively identify, acquire, implement and maintain technology resourced by the fund?
  • Did the NSW Police Force establish effective governance arrangements for administering the fund, and for monitoring expected benefits and unintended consequences?
  • Did technology implemented under the fund improve the efficiency and effectiveness of policing in New South Wales?

Conclusion

The NSW Police Force's management of the Policing for Tomorrow fund was mostly effective. There are measures in place to assess the impact of the technologies on the efficiency and effectiveness of policing in NSW. However, these measures are not in place for all technologies funded by Policing for Tomorrow. A strategic whole-of-organisation approach to identifying and filling technology capability gaps may have assisted in better targeting funds and managing expected benefits.

The NSW Police Force identified, acquired, implemented and maintained a range of technologies resourced by the fund in an efficient and effective way. The election announcement committed the NSW Police Force to four specific projects which made up over three quarters of the fund value. Investment decisions for remaining funds were driven by the availability of funding and individual technology requirements rather than targeting improved policing outcomes and the capability necessary to achieve these.

The NSW Police Force missed an opportunity to take a whole-of-organisation approach to selecting technology projects for the remainder of the funds where it had discretion. This may have included considering less obvious back office technology or making different investment decisions driven by gaps in the agency's technology capabilities.

The NSW Police Force used effective governance arrangements for administering the Policing for Tomorrow fund, including using its existing ICT Executive Board. The NSW Police Force has adequate processes in place to drive benefits and monitor the impact of technology on the efficiency and effectiveness of policing for the larger projects funded by Policing for Tomorrow. Further work is required to ensure this for smaller projects.

The NSW Police Force tends to consider only impacts on the organisation in managing benefits and identifying unintended consequences. It does not routinely engage proactively with stakeholders, including partner criminal justice agencies and members of the community, on new technology that changes how police interact with the public.

We examined how effectively the NSW Police Force governed the Policing for Tomorrow fund, to ensure that key accountability and decision-making arrangements were in place to direct the $100 million spend to appropriate technologies. We also assessed how the NSW Police Force acquired, implemented and maintained technology funded by Policing for Tomorrow to determine the effectiveness of the relevant asset management.

The Policing for Tomorrow election commitment aimed to invest in technology to ‘make police work safer and quicker – meaning more time on the street combatting crime’. We assessed whether the NSW Police Force ensured that funded technologies have improved policing efficiency and effectiveness. We did not seek to independently assure the benefits or outcomes resulting from the technologies.

Appendix one – Response from agency

Appendix two – Policing for Tomorrow projects and expenditure

Appendix three – About the audit

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #334 - released 2 June 2020

Published

Actions for Train station crowding

Train station crowding

Transport
Management and administration
Risk
Service delivery
Workforce and capability

This report focuses on how Transport for NSW and Sydney Trains manage crowding at selected metropolitan train stations.

The audit found that while Sydney Trains has identified platform crowding as a key strategic risk, it does not have an overarching strategy to manage crowding in the short to medium term. Sydney Trains 'do not have sufficient oversight to know if crowding is being effectively managed’, the Auditor-General said.

Sydney Trains' operational response to crowding involves restricting customer access to platforms or station entries before crowding reaches unsafe levels or when it impacts on-time running. Assuming rail patronage increases, it is likely that Sydney Trains will restrict more customers from accessing platforms or station entries, causing customer delay. ‘Restricting customer access to platforms or station entries is not a sustainable approach to manage station crowding’, said the Auditor-General.

The Auditor-General made seven recommendations to improve Transport for NSW and Sydney Trains' management of station crowding. Transport for NSW have accepted these recommendations on behalf of the Transport cluster.

Public transport patronage has been impacted by COVID-19. This audit was conducted before these impacts occurred.

Read full report (PDF)

Sydney Trains patronage has increased by close to 34 per cent over the last five years, and Transport for NSW (TfNSW) expects the growth in patronage to continue over the next 30 years. As patronage increases there are more passengers entering and exiting stations, moving within stations to change services, and waiting on platforms. As a result, some Sydney metropolitan train stations are becoming increasingly crowded.

There are three main causes of station crowding:

  • patronage growth exceeding the current capacity limits of the rail network
  • service disruptions
  • special events.

Crowds can inhibit movement, cause discomfort and can lead to increased health and safety risks to customers. In the context of a train service, unmanaged crowds can affect service operation as trains spend longer at platforms waiting for customers to alight and board services which can cause service delays. Crowding can also prevent customers from accessing services.

Our 2017 performance audit, ‘Passenger Rail Punctuality’, found that rail agencies would find it hard to maintain train punctuality after 2019 unless they significantly increased the capacity of the network to carry trains and people. TfNSW and Sydney Trains have plans to improve the network to move more passengers. These plans are set out in strategies such as More Trains, More Services and in the continued implementation of new infrastructure such as the Sydney Metro. Since 2017, TfNSW and Sydney Trains have introduced 1,500 more weekly services to increase capacity. Additional network capacity improvements are in progress for delivery from 2022 onwards.

In the meantime, TfNSW and Sydney Trains need to use other ways of managing crowding at train stations until increased capacity comes on line.

This audit examined how effectively TfNSW and Sydney Trains are managing crowding at selected metropolitan train stations in the short and medium term. In doing so, the audit examined how TfNSW and Sydney Trains know whether there is a crowding problem at stations and how they manage that crowding.

TfNSW is the lead agency for transport in NSW. TfNSW is responsible for setting the standard working timetable that Sydney Trains must implement. Sydney Trains is responsible for operating and maintaining the Sydney metropolitan heavy rail passenger service. This includes operating, staffing and maintaining most metropolitan stations. Sydney Trains’ overall responsibility is to run a safe rail network to timetable.

Conclusion

Sydney Trains has identified platform crowding as a key strategic risk, but does not have an overarching strategy to manage crowding in the short to medium term. TfNSW and Sydney Trains devolve responsibility for managing crowding at stations to Customer Area Managers, but do not have sufficient oversight to know if crowding is being effectively managed. TfNSW is delivering a program to influence demand for transport in key precincts but the effectiveness of this program and its impact on station crowding is unclear as Transport for NSW has not evaluated the outcomes of the program.

TfNSW and Sydney Trains do not directly measure or collect data on station crowding. Data and observation on dwell time, which is the time a train waits at a platform for customers to get on and off trains, inform the development of operational approaches to manage crowding at stations. Sydney Trains has KPIs on reliability, punctuality and customer experience and use these to indirectly assess the impact of station crowding. TfNSW and Sydney Trains only formally assess station crowding as part of planning for major projects, developments or events.

Sydney Trains devolve responsibility for crowd management to Customer Area Managers, who rely on frontline Sydney Trains staff to understand how crowding affects individual stations. Station staff at identified key metropolitan train stations have developed customer management plans (also known as crowd management plans). However, Sydney Trains does not have policies to support the creation, monitoring and evaluation of these plans and does not systematically collect data on when station staff activate crowding interventions under these plans.

Sydney Trains stated focus is on providing a safe and reliable rail service. As such, management of station crowding is a by-product of its strategies to manage customer safety and ensure on-time running of services. Sydney Trains' operational response to crowding involves restricting customer access to platforms or stations before crowding reaches unsafe levels, or when it impacts on-time running. As rail patronage increases, it is likely that Sydney Trains will need to increase its use of interventions to manage crowding. As Sydney Trains restrict more customers from accessing platforms or station entries, it is likely these customers will experience delays caused by these interventions.

Since 2015, TfNSW has been delivering the 'Travel Choices' program which aims to influence customer behaviour and to manage the demand for public transport services in key precincts. TfNSW is unable to provide data demonstrating the overall effectiveness of this program and the impact the program has on distributing public transport usage out of peak AM and PM times. TfNSW and Sydney Trains continue to explore initiatives to specifically address crowd management.

Conclusion

TfNSW and Sydney Trains do not directly measure or collect data on station crowding. There are no key performance indicators directly related to station crowding. Sydney Trains uses performance indicators on reliability, punctuality and customer experience to indirectly assess the impact of station crowding. Sydney Trains does not have a routine process for identifying whether crowding contributed to minor safety incidents. TfNSW and Sydney Trains formally assess station crowding as part of planning for major projects, developments or events.

 

Conclusion

Sydney Trains has identified platform crowding as a strategic risk but does not have an overarching strategy to manage station crowding. Sydney Trains' stated focus is on providing a safe and reliable rail service. As such, management of station crowding is a by-product of its strategies to manage customer safety and ensure on-time running of services.

Sydney Trains devolve responsibility for managing crowding at stations to Customer Area Managers but does not have sufficient oversight to know that station crowding is effectively managed. Sydney Trains does not have policies to support the creation, monitoring or evaluation of crowd management plans at key metropolitan train stations. The use of crowding interventions is likely to increase due to increasing patronage, causing more customers to experience delays directly caused by these activities.

TfNSW and Sydney Trains have developed interventions to influence customer behaviour and to manage the demand for public transport services but are yet to evaluate these interventions. As such, their impact on managing station crowding is unclear.

Appendix one – Response from agency

Appendix two – Sydney rail network

Appendix three – Rail services contract

Appendix four – Crowding pedestrian modelling

Appendix five – Airport Link stations case study

Appendix six – About the audit

Appendix seven – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #333 - released 30 April 2020

 

Published

Actions for Destination NSW's support for major events

Destination NSW's support for major events

Treasury
Financial reporting
Management and administration
Procurement
Project management
Service delivery

This report focuses on whether Destination NSW (DNSW) can demonstrate that its support for major events achieves value for money.

The audit found that DNSW’s processes for assessing and evaluating the major events it funds are mostly effective, but its public reporting does not provide enough transparency.

DNSW provides clear information to event organisers seeking funding and has a comprehensive methodology for conducting detailed event assessments. However, the reasons for decisions to progress events from the initial assessment to the detailed assessment stage are not documented in sufficient detail.

DNSW does not publish detailed information about the events it funds or the outcomes of these events. This means that members of the public are unable to see whether its activities achieve value for money. However, DNSW’s internal reporting to its key decision‑makers, including the CEO, the Board and the Minister is appropriate.

The Auditor-General made four recommendations to DNSW, aimed at improving the transparency of its activities, improving the documentation of decisions and certain compliance matters, and streamlining its approach to assessing and evaluating events that receive smaller amounts of funding.

Read full report (PDF)

Destination NSW (DNSW) provides funding to attract a range of major events to New South Wales, including high-profile professional sports matches and tournaments, musicals, art and museum exhibitions, and participation-focused events such as festivals and sports events that members of the public can enter. The NSW Government's rationale for providing funding is to encourage event organisers to hold events in New South Wales, and to ensure that events held in New South Wales maximise the potential for attracting overseas and interstate visitors.

This audit assessed whether DNSW can demonstrate that its support for major events achieves value for money. In making this assessment, the audit examined whether:

  • DNSW effectively assesses proposals to support major events
  • DNSW effectively evaluates the impact of its support for major events.

This audit focused on DNSW's work to attract major events to New South Wales. It did not assess DNSW's tourism promotion or development work, which includes developing tourism strategies, marketing and advertising campaigns, national and international partnerships, and regional programs.

Conclusion

Destination NSW's processes for assessing event applications and evaluating its support for major events are mostly effective. DNSW's internal systems allow it to know whether its decisions are achieving value for money. Its public reporting does not provide enough information about its activities and their outcomes, although it is consistent with that of equivalent organisations in other Australian jurisdictions.

DNSW's process for assessing applications for funding from organisers of major events is mostly effective. Clear information is provided to event organisers seeking funding, and DNSW has a comprehensive methodology for conducting detailed event assessments. However, the reasons for decisions to progress events from the initial assessment to the detailed assessment stage are not documented in sufficient detail.

DNSW has a framework for disclosure and monitoring staff conflicts of interest. However, its forms for staff to disclose conflicts of interest on specific events they are working on are ambiguous. DNSW's management of gifts and benefits broadly complies with the minimum standards set by the Public Service Commission, but there are some gaps in its implementation of these.

DNSW conducts an evaluation of each major event it supports. DNSW articulates expected outcomes in contracts with event organisers and uses a sound methodology to evaluate events. Internal reporting to its key decision-makers, including the CEO, the Board and the Minister is appropriate. However, DNSW does not publish detailed information about the events it funds or the outcomes of these events. This means that members of the public are unable to see whether its activities achieve value for money.

Appendix one – Response from Destination NSW

Appendix two – About the audit 

Appendix three – Performance auditing

 

Copyright Notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #332 - released 9 April 2020.

Published

Actions for Integrity of data in the Births, Deaths and Marriages Register

Integrity of data in the Births, Deaths and Marriages Register

Justice
Premier and Cabinet
Whole of Government
Cyber security
Fraud
Information technology
Internal controls and governance
Management and administration

This report outlines whether the Department of Customer Service (the department) has effective controls in place to ensure the integrity of data in the Births, Deaths and Marriages Register (the register), and to prevent unauthorised access and misuse.

The audit found that the department has processes in place to ensure that the information entered in the register is accurate and that any changes to it are validated. Although there are controls in place to prevent and detect unauthorised access to, and activity in the register, there were significant gaps in these controls. Addressing these gaps is necessary to ensure the integrity of information in the register.

The Auditor-General made nine recommendations to the department, aimed at strengthening controls to prevent and detect unauthorised access to, and activity in the register. These included increased monitoring of individuals who have access to the register and strengthening security controls around the databases that contain the information in the register.

The NSW Registry of Births Deaths and Marriages is responsible for maintaining registers of births, deaths and marriages in New South Wales as well as registering adoptions, changes of names, changes of sex and relationships. Maintaining the integrity of this information is important as it is used to confirm people’s identity and unauthorised access to it can lead to fraud or identity theft.

Read full report (PDF)

The NSW Registry of Births Deaths and Marriages (BD&M) is responsible for maintaining registers of births, deaths and marriages in New South Wales. BD&M is also responsible for registering adoptions, changes of name, changes of sex and relationships. These records are collectively referred to as 'the Register'. The Births, Deaths and Marriages Registration Act 1995 (the BD&M Act) makes the Registrar (the head of BD&M) responsible for maintaining the integrity of the Register and preventing fraud associated with the Register. Maintaining the integrity of the information held in the Register is important as it is used to confirm people's identity. Unauthorised access to, or misuse of the information in the Register can lead to fraud or identity theft. For these reasons it is important that there are sufficient controls in place to protect the information.

BD&M staff access, add to and amend the Register through the LifeLink application. While BD&M is part of the Department of Customer Service, the Department of Communities and Justice (DCJ) manages the databases that contain the Register and sit behind LifeLink and is responsible for the security of these databases.

This audit assessed whether BD&M has effective controls in place to ensure the integrity of data in the Births, Deaths and Marriages Register, and to prevent unauthorised access and misuse. It addressed the following:

  • Are relevant process and IT controls in place and effective to ensure the integrity of data in the Register and the authenticity of records and documents?
  • Are security controls in place and effective to prevent unauthorised access to, and modification of, data in the Register?

Conclusion

BD&M has processes and controls in place to ensure that the information entered in the Register is accurate and that amendments to the Register are validated. BD&M also has controls in place to prevent and detect unauthorised access to, and activity in the Register. However, there are significant gaps in these controls. Addressing these gaps is necessary to ensure the integrity of the information in the Register.

BD&M has detailed procedures for all registrations and amendments to the Register, which include processes for entering, assessing and checking the validity and adequacy of source documents. Where BD&M staff have directly input all the data and for amendments to the Register, a second person is required to check all information that has been input before an event can be registered or an amendment can be made. BD&M carries out regular internal audits of all registration processes to check whether procedures are being followed and to address non-compliance where required.

BD&M authorises access to the Register and carries out regular access reviews to ensure that users are current and have the appropriate level of access. There are audit trails of all user activity, but BD&M does not routinely monitor these. At the time of the audit, BD&M also did not monitor activity by privileged users who could make unauthorised changes to the Register. Not monitoring this activity created a risk that unauthorised activity in the Register would not be detected.

BD&M has no direct oversight of the database environment which houses the Register and relies on DCJ's management of a third-party vendor to provide the assurance it needs over database security. The vendor operates an Information Security Management System that complies with international standards, but neither BD&M nor DCJ has undertaken independent assurance of the effectiveness of the vendor's IT controls.

Appendix one – Response from agency

Appendix two – About the audit

Appendix three – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #330 - released 7 April 2020.

Published

Actions for Supporting the District Criminal Court

Supporting the District Criminal Court

Justice
Community Services
Information technology
Internal controls and governance
Project management

The Auditor-General for New South Wales, Margaret Crawford, released a report today on whether the Department of Communities and Justice (the department) effectively supports the efficient operation of the District Criminal Court system.

The audit found that in the provision of data and technology services, the department is not effectively supporting the efficient operation of the District Criminal Court system. The department has insufficient controls in place to ensure that data in the system is always accurate.

The department is also using outdated technology and could improve its delivery of technical support to courts.

The audit also assessed the implementation of the Early Appropriate Guilty Pleas reform. This reform aims to improve court efficiency by having more cases resolved earlier with a guilty plea in the Local Court. The audit found that the department effectively governed the implementation of the reform but is not measuring achievement of expected benefits, placing the objectives of the reform at risk.

The Auditor-General made seven recommendations to the department, aimed at improving the controls around courts data, reporting on key performance indicators, improving regional technical support and measuring the success of the Early Appropriate Guilty Pleas reform. 

The District Court is the intermediate court in the New South Wales court system. It hears most serious criminal matters, except murder, treason and piracy. The Department of Communities and Justice (the Department) provides support to the District Court in a variety of ways. For example, it provides security services, library services and front-desk services. This audit examined three forms of support that the Department provides to the District Court:

  • data collection, reporting and analysis - the Department collects data from cases in its case management system, JusticeLink, based on the orders Judges make in court and court papers
  • technology - the Department provides technology to courts across New South Wales, as well as technical support for this technology
  • policy - the Department is responsible for proposing and implementing policy reforms.

Recent years have seen a worsening of District Court efficiency, as measured in the Productivity Commission's Report on Government Services (RoGS). Efficiency in the court system is typically measured through timeliness of case completion. There is evidence that timeliness has worsened. For example, the median time from arrest to finalisation of a case in the District Court increased from 420 days in 2012–13 to 541 days in 2017–18.

As a result, the government has announced a range of measures to improve court performance, particularly in the District Court. These measures included the Early Appropriate Guilty Pleas (EAGP) reform. One of the objectives of EAGP is to improve court efficiency, which would be achieved by having more cases resolve with a guilty plea in the Local Court.

This audit assessed whether the Department of Communities and Justice effectively supports the efficient operation of the District Criminal Court system. We assessed this with the following lines of inquiry:

  • Does the Department effectively collect, analyse and report performance information relevant to court efficiency?
  • Does the Department effectively provide technology to support the efficient working of the courts?
  • Does the Department have effective plans, governance and monitoring for the Early Appropriate Guilty Pleas reform?

The audit did not consider other support functions provided by the Department. Further information on the audit, including detailed audit criteria, may be found in Appendix two.

Conclusion
In the provision of data and technology services, the Department is not effectively supporting the efficient operation of the District Criminal Court system. The Department has insufficient controls in place to ensure accurate data in the District Criminal Court system. The Department is also using outdated technology in significant numbers and could improve its delivery of technical support to meet agreed targets.
The Department effectively governed the implementation of the Early Appropriate Guilty Pleas reform. However, it is not ensuring that the benefits stated in the business case are being achieved, placing its objectives at risk.
The impact of inaccurate court data can be severe, and the Department does not have sufficient controls in place to ensure that its court data is accurate. Recent Bureau of Crime Statistics and Research reviews have identified data inaccuracies, and this demonstrates the Department needs strong controls in place to ensure that its court data is accurate.
The Department does not have a policy for data quality and has not formally assigned responsibility for data quality to any individual or branch. The Department also does not have a data dictionary outlining all the fields in its case management system. While the Department validates the highest risk items, such as warrants, to ensure that they are accurate, most data is not validated. The Department has recently commenced setting up a data unit for the Courts, Tribunals and Service Delivery branch. It is proposed that this unit will address most of the identified shortcomings.
The Department did not provide timely technical support to the court system in 2017 and is using outdated technology in significant numbers. The Digital and Technology Services branch of the Department had agreed a Service Level Agreement with the rest of the Department, outlining the expected speed of technical support responses. The branch did not meet response times in 2017. Performance improved in 2018, though DTS fell short of its targets for critical and moderate priority incidents. Critical incidents are particularly important to deal with in a timely manner as they include incidents which may delay a court sitting.
Requests for technical support rose significantly in 2018 compared to 2017, which may be related to the number of outdated pieces of technology. As at April 2019, the whole court system had 2,389 laptops or desktop computers outside their warranty period. The Department was also using other outdated technology. Outdated technology is more prone to failure and continuing to use it poses a risk of court delays.
The Department is not measuring all the expected benefits from the Early Appropriate Guilty Pleas reform, placing the objectives of the program at risk. The Early Appropriate Guilty Pleas business case outlined nine expected benefits from the reform. The Department is not measuring one of these benefits and is not measuring the economic benefits of a further five business case benefits. Not measuring the impact of the reform means that the Department does not know if it is achieving its objectives and if the reform had the desired impact.

The Department is responsible for providing technology to the courts, which can improve the efficiency of court operations by making them faster and cheaper. The Department is also responsible for providing technical support to courtrooms and registries. It is important that technical support is provided in a timely manner because some technical incidents can delay court sittings and thus impact on court efficiency. A 2013 Organisation for Economic Co‑operation and Development report emphasised the importance of technology and digitisation for reducing trial length.

While the Department may provide technology to the courts, they are not responsible for deciding when, how or if the technology is used in the courtroom.

The Department is using a significant amount of outdated technology, risking court delays

As of April 2019, the whole court system had 2,389 laptops or desktop computers out of warranty, 56.0 per cent of the court system's fleet. The court system also had 786 printing devices out of their normal warranty period, 75.1 per cent of all printers in use. The Department also advised that many of its court audio transcription machines are out of date. These machines must be running for the court to sit and thus it is critical that they are maintained to a high degree. The then Department of Justice estimated the cost of aligning its hardware across the whole Department with desired levels at $14.0 million per year for three years. Figures for the court system were not calculated but they are likely to be a significant portion of this figure.

Using outdated technology poses a risk to the court system as older equipment may be more likely to break down, potentially delaying courts or slowing down court services. In the court system throughout 2018, hardware made up 30.8 per cent of all critical incidents reported to technical support and 41.9 per cent of all high priority incidents. In addition, 16.2 per cent of all reported issues related to printing devices or printing.

From 2017 to 2018, technical support incidents from courts or court services increased. There were 4,379 technical support incidents in 2017, which increased significantly to 9,186 in 2018. The Department advised that some outside factors may have contributed to this increase. The Department was rolling out its new incident recording system throughout 2017, meaning that there would be an under‑reporting of incidents in that year. The Department also advised that throughout 2018 there was a greater focus on ensuring that every issue was logged, which had not previously been the case. Despite these factors, the use of outdated technology has likely increased the risk of technology breakages and may have contributed to the increase in requests for technical support.

Refreshing technology on a regular basis would reduce the risk of hardware failures and ensure that equipment is covered by warranty.

The Department did not meet all court technical support targets in 2017 and 2018

The Digital and Technology Services branch (DTS) was responsible for providing technical support to the courts and the Courts and Tribunal Services branch prior to July 2019. DTS provided technical support in line with a Service Level Agreement (SLA) with the Department. In 2017, DTS did not provide this support in a timely manner. Performance improved in 2018, though DTS fell short of its targets for critical and moderate priority incidents. Exhibit 7 outlines DTS' targets under the SLA.

Exhibit 7: Digital and Technology Services' Service Level Agreement
Priority Target resolution time Target percentage in time (%)
1. Critical 4 hours 80
2. High 1 day 80
3. Moderate 3 days 85
4. Low 5 days 85
Source: Department of Communities and Justice, 2019.

Critical incidents are particularly important for the Department to deal with in a timely manner because these include incidents which may delay a court sitting until resolved or incidents which impact on large numbers of staff. Some of the critical incidents raised with DTS specifically stated that they were delaying a court sitting, often due to transcription machines not working. High priority incidents include those where there is some impact on the functions of the business, which may in turn affect the efficiency of the court system. High priority incidents also include those directly impacting on members of the Judiciary. 

This audit examined DTS' performance against its SLA in the 2017 and 2018 calendar years across the whole court system, not just the District Court. The total number of incidents, as well as critical and high priority incidents, can be seen in Exhibit 8.

Exhibit 8: Number of incidents in 2017 and 2018
Priority 2017 2018
All 4,379 9,186
1. Critical 48 91
2. High 128 315
Source: Audit Office of NSW analysis of Department of Communities and Justice data, 2019.

The Department's results against its SLA in 2017 and 2018 are shown in Exhibit 9.

The Early Appropriate Guilty Pleas (EAGP) reform consists of five main elements:

  • early disclosure of evidence from NSW Police Force to the prosecution and defence
  • early certification of what the accused is going to be charged with to minimise changes
  • mandatory criminal case conferencing between the prosecutor and accused's representation
  • changes to Local Court case management
  • more structured sentence discounts.

More detailed descriptions of each of these changes can be found in the Introduction. These reform elements are anticipated to have three key effects:

  • accelerate the timing of guilty pleas
  • increase the overall proportion of guilty pleas
  • decrease the average length of contested trials.

Improving District Court efficiency is one of the stated aims of EAGP, which would be achieved by having more cases resolve in the Local Court and having fewer defendants plead guilty on the day of their trial in the District Court. The reform commenced in April 2018 and it is too early to state the impact of this reform on District Court efficiency.

The Department is responsible for delivering EAGP in conjunction with other justice sector agencies. They participated in the Steering Committee and the Working Groups, as well as providing the Project Management Office (PMO).

The Department is not measuring the economic benefits stated in the EAGP business case

The business case for EAGP listed nine quantifiable benefits which were expected to be derived from the achievement of the three key effects listed above. The Department is not measuring one of these benefits and is not measuring the economic benefits for five more, as shown in Exhibit 12.

Benefit Economic benefit (over ten years) Being measured?
Accelerated timing of guilty pleas $54.6m yellow circle with minus in the center
Increased guilty plea rate $90.7m yellow circle with minus in the center
Decreased average trial length $27.5m yellow circle with minus in the center
A reduction in the delay of indictable matters proceeding to trial N/A check circle mauve
Increase the number of finalised matters per annum N/A check circle mauve
Reduction of the current backlog of criminal trials in the District Court N/A check circle mauve
Reduction in bed pressure on the correction system due to reduced
average time in custody
$13.7m Exclamation circle red
Productivity improvements due to reduction in wasted effort $53.3m yellow circle with minus in the center
Bankable cost savings due to jury empanelment avoided $2.5m yellow circle with minus in the center

 

Exhibit 12: The Department's measurement of quantifiable benefits
Key check circle mauve Measuring yellow circle with minus in the center Not measuring economic benefit Exclamation circle red Not measuring
Source: Audit Office of NSW analysis.

While it is too early to comment on the overall impact of EAGP, better practice in benefits realisation involves an ongoing effort to monitor benefits to ensure that the reform is on target and determine whether any corrective action is needed.

The Department is measuring the number of finalised matters per annum and while the Department is not measuring the reduction in the backlog as part of this program, this measure is reported as part of the Department's internal reporting framework. The Department is not monitoring the reduction in delay of indictable matters proceeding to trial directly as part of this reform, but this does form part of the monthly Operational Performance Report which the Department sends to the EAGP Steering Committee.

The Department is not monitoring any of the economic benefits stated in the business case. These economic benefits are a mixture of bankable savings and productivity improvements. This amounts to a total of $242.3 million over ten years which was listed in the business case as potential economic benefits from the implementation of this reform against the total cost of $206.9 million over ten years. The Department is collecting proxy indicators which would assist in these calculations for several indicators, but it is not actively monitoring these savings. For example, the Department is monitoring average trial length, but is not using this information to calculate economic benefits derived from changes in trial length.

The Department is also not collecting information related to the average length of custody as part of this program. This means that it is unable to determine if EAGP is putting less pressure on the correctives system and it is not possible for the Department to calculate the savings from this particular benefit.

While stakeholders are optimistic about the impact of EAGP, not measuring the expected benefits stated in the business case means that the Department does not know if the reform is achieving what it was designed to achieve. Further, the Department does not know if it must take corrective action to ensure that the program achieves the stated benefits. These two things put the overall program benefits at risk.

The Department has not assigned responsibility for the realisation of each benefit, potentially risking the success of the program

The Department has not assigned responsibility for the realisation of each benefit stated in the business case. The Department holds the Steering Committee responsible for the realisation of all benefits. Benefits realisation is the process which ensures that the agency reaches benefits as stated in the business case. Assigning responsibility for benefits realisation to the Steering Committee rather than individuals is not in line with good practice.

Good practice benefits realisation involves assigning responsibility for the realisation of each benefit to an individual at the business unit level. This ensures there is a single point of accountability for each part of the program with knowledge of the benefit and the ability to take corrective action if it looks like that benefit will not be realised. This responsibility should sit at the operational level where detailed action can most easily be undertaken. The role of a Steering Committee in benefits realisation is to ensure that responsible parties are monitoring their benefits and taking appropriate corrective action.

The Department advised that it believes the Steering Committee should have responsibility for the realisation of benefits due to the difficulty of attributing the achievement of each benefit to one part of the reform alone. Given the Steering Committee meets only quarterly, it is not well placed to take action in response to variances in performance.

A BOCSAR evaluation is planned, however data errors make some of the information unreliable

BOCSAR are planning to undertake an overall evaluation of EAGP which is planned for release in 2021. Undertaking this evaluation will require high quality data to gain an understanding of the drivers of the reform. However, data captured throughout the first year of EAGP has proven unreliable, which may reduce the usefulness of BOCSAR's evaluation. These data issues were discussed in Exhibit 5 in Chapter 2, above. Access to accurate data is vital for conducting any program evaluation and inaccurate data raises the risk that the BOCSAR evaluation will not be able to provide an accurate evaluation of the impact of EAGP.

In addition to the BOCSAR evaluation, the Department had plans for a series of 'snapshot' evaluations for some of the key elements of the reform to ensure that they were operating effectively. These were initially delayed due to an efficiency dividend which affected EAGP. In August 2019, the Department commissioned a review of the implementation of several key success factors for EAGP.

There was clear governance throughout the implementation of EAGP

The implementation stage of EAGP had clear governance, lines of authority and communication. The Steering Committee, each Working Group and each agency had clear roles and responsibilities, and these were organised through a Project Management Office (PMO) provided by the former Department of Justice. The governance structure throughout the implementation phase can be seen at Exhibit 13.

The Steering Committee was established in December 2016 and met regularly from March 2017. It comprised senior members of key government agencies, as well as the Chief Judge and the Chief Magistrate for most of the duration of the implementation period. The Steering Committee met at least monthly throughout the life of the program. The Steering Committee was responsible for overseeing the delivery of EAGP and making key decisions relating to implementation, including spending decisions. The Chief Judge and the Chief Magistrate abstained from financial decisions. The Steering Committee updated the governance and membership of the Steering Committee as appropriate throughout the life of the reform.

Appendix one – Response from agency
 
Appendix two – About the audit 

Appendix three – Performance auditing 

 

Copyright Notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary Reference: Report number #329 - released 18 December 2019

Published

Actions for Ensuring contract management capability in government - HealthShare NSW

Ensuring contract management capability in government - HealthShare NSW

Health
Management and administration
Procurement
Project management

This report examined whether HealthShare NSW, a part of NSW Health, has the required contract management capability to effectively manage goods and services contracts valued over $250,000. 

The report found that HealthShare has a procurement framework that should support effective contract management, but it is not applying it consistently. In particular, the audit found that HealthShare was not applying key contract management elements to over 80 per cent of the high-value contracts it manages. The audit also found that HealthShare’s contract management practices were limited by inadequate performance monitoring.

'Effective contract management is essential to ensure the contracts HealthShare enters into are delivering as expected and ensuring value for money,' said the Auditor-General. 'Without this, the value for money or savings HealthShare achieves when it negotiates these contracts is at risk of being eroded over the life of the contract.'

The report recommends that NSW Health develop a performance improvement plan to ensure HealthShare is fully compliant with procurement policies and that NSW Health meets its obligations under the Government's Accreditation Program for Goods and Services Procurement.

HealthShare is a NSW Health entity responsible for providing shared services, including procurement, to support the delivery of patient care within the NSW health system. In 2018, HealthShare procured high value goods and services contracts with an annual estimated total spend of around $1.8 billion, with most of the contracts of long duration.

NSW Government agencies are increasingly delivering services and projects through contracts with third parties. These contracts can be complex and governments face challenges in negotiating and implementing them effectively. A robust contract management framework helps ensure all parties meet their obligations, contractual relationships are well managed, agencies achieve value for money, and deliverables meet the required standards and agreed timeframes.

Contract management capability is a broad term, which can include aspects of individual staff capability (such as staff knowledge, skills and experience) as well as organisational capability (such as policies, frameworks and processes).

The NSW Procurement Board is responsible for overseeing the Government's procurement system, setting policy and ensuring compliance. It has accredited the Health Administration Corporation (HAC) to procure goods and services with no upper financial limit. Under the terms of this accreditation, the Secretary, NSW Health (as head of HAC) has delegated the procurement of high-value (over $250,000) goods and services contracts within NSW Health to only the Ministry of Health and HealthShare NSW (HealthShare).

HealthShare NSW (HealthShare) is a NSW Health entity responsible for providing shared services, including procurement, to support the delivery of patient care within the NSW health system. In 2018, HealthShare procured high-value goods and services contracts with an annual estimated total spend of around $1.8 billion, with most of the contracts of long duration.

HealthShare’s Contract Management Guide states that, without rigorous contract management, 75 per cent of projected sourcing savings can disappear within 18 months of the contract starting.

This audit examined whether HealthShare has the required capability to effectively manage high-value goods and services contracts. Contracts we examined included critical items such as food services in hospitals, patient transport services, intravenous equipment and kidney dialysis services, where risks include patient safety as well as value for money. We did not examine infrastructure, construction or information communication and technology contracts. We also did not examine HealthShare’s sourcing processes, including identifying business needs, tendering and contract award.

We assessed HealthShare against the following criteria:

  1. HealthShare's systems, policies and procedures support effective contract management and are consistent with relevant frameworks, policies and guidelines.
  2. HealthShare has capable personnel to effectively conduct the monitoring activities throughout the life of the contract.

We included the NSW Public Service Commission and NSW Treasury, through NSW Procurement, as auditees because they administer policies which directly affect contract management capability. These include:

  • NSW Procurement Board Directions and policies
  • NSW Government Procurement Policy Framework
  • Accreditation Program for Goods and Services Procurement
  • the NSW Public Sector Capability Framework.

NSW Procurement was transferred to NSW Treasury from the former Department of Finance, Services and Innovation on 1 July 2019 as part of changes to government administrative arrangements.

Conclusion
HealthShare is not applying the capability needed to effectively manage high-value (over $250,000) goods and services contracts. HealthShare's procurement framework includes elements that should support effective contract management, and it has a systematic approach to managing staff contract management capability. That said, HealthShare is not implementing key contract management elements of its own framework. As such, the value for money or savings it achieves when it negotiates contracts is at risk of being eroded over the life of these contracts.
Effective contract management is essential for HealthShare to ensure contracts it enters into are delivering the goods and services expected and achieving value for money, safety and quality. The Ministry of Health and HealthShare have invested in developing and implementing systems and tools to support effective contract management. In line with its obligations under the Agency Accreditation Program for Goods and Services Procurement (accreditation program), the Ministry of Health mandates the use of contract management plans for high-value contracts. The Ministry of Health also requires that all health entities use the PROcure contract management system for ongoing management of contracts with a value over $150,000. HealthShare is not complying with these directions for over 80 per cent of the contracts it manages.
In the absence of HealthShare following its framework, and the Ministry of Health’s directions, we looked for other evidence that HealthShare was effectively managing high-value contracts. We found that HealthShare’s contract management practices were limited by inadequate performance monitoring.
When Local Health Districts (LHDs) need to procure high-value goods and services, the Ministry of Health’s procurement policy requires that they use HealthShare to source and manage the procurement. This is to manage risk and provide oversight of procurement and contracts across the NSW health system. Despite this policy, HealthShare was only managing the sourcing stage of the procurement and transferring responsibility for contract management to the relevant LHD.

Appendix one – Response from agencies

Appendix two – Contract performance management summary

Appendix three – About the audit

Appendix four – Performance auditing

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary Reference: Report number #328 - released 31 October 2019

Published

Actions for Mental health service planning for Aboriginal people in New South Wales

Mental health service planning for Aboriginal people in New South Wales

Health
Management and administration
Project management
Service delivery
Workforce and capability

A report released by the Auditor-General for New South Wales, Margaret Crawford, has found that NSW Health is not forming effective partnerships with Aboriginal communities to plan, design and deliver appropriate mental health services. There is limited evidence that NSW Health is using the knowledge and expertise of Aboriginal communities to guide how mental health care is structured and delivered.

Mental illness (including substance use disorders) is the main contributor to lower life expectancy and increased mortality in the Aboriginal population of New South Wales. It contributes to a higher burden of disease and premature death at rates that are 40 per cent higher than the next highest chronic disease group, cardiovascular disease.1 

Aboriginal people have significantly higher rates of mental illness than non Aboriginal people in New South Wales. They are more likely to present at emergency departments in crisis or acute phases of mental illness than the rest of the population and are more likely to be admitted to hospital for mental health treatments.2 

In acknowledgement of the significant health disparities between Aboriginal and non Aboriginal people, NSW Health implemented the NSW Aboriginal Health Plan 2013 2023 (the Aboriginal Health Plan). The overarching message of the Aboriginal Health Plan is ‘to build respectful, trusting and effective partnerships with Aboriginal communities’ and to implement ‘integrated planning and service delivery’ with sector partners. Through the Plan, NSW Health commits to providing culturally appropriate and ‘holistic approaches to the health of Aboriginal people'.

The mental health sector is complex, involving Commonwealth, state and non government service providers. In broad terms, NSW Health has responsibility to support patients requiring higher levels of clinical support for mental illnesses, while the Commonwealth and non government organisations offer non acute care such as assessments, referrals and early intervention treatments.

The NSW Health network includes 15 Local Health Districts and the Justice Health and Forensic Mental Health Network that provide care to patients during acute and severe phases of mental illness in hospitals, prisons and community service environments. This includes care to Aboriginal patients in the community at rates that are more than four times higher than the non Aboriginal population. Community services are usually provided as follow up after acute admissions or interactions with hospital services. The environments where NSW Health delivers mental health care include:

  • hospital emergency departments, for short term assessment and referral
  • inpatient hospital care for patients in acute and sub acute phases of mental illness
  • mental health outpatient services in the community, such as support with medications
  • custodial mental health services in adult prisons and juvenile justice centres.

The NSW Government is reforming its mental health funding model to incrementally shift the balance from hospital care to enhanced community care. In 2018–19, the NSW Government committed $400 million over four years into early intervention and specialist community mental health teams.

This audit assessed the effectiveness of NSW Health’s planning and coordination of mental health services and service pathways for Aboriginal people in New South Wales. We addressed the audit objective by answering three questions: 

  1. Is NSW Health using evidence to plan and inform the availability of mental health services for Aboriginal people in New South Wales?
  2. Is NSW Health collaborating with partners to create accessible mental health service pathways for Aboriginal people?
  3. Is NSW Health collaborating with partners to ensure the appropriateness and quality of mental health services for Aboriginal people?
Conclusion

NSW Health is not meeting the objectives of the NSW Aboriginal Health Plan, to form effective partnerships with Aboriginal Community Controlled Health Services and Aboriginal communities to plan, design and deliver mental health services.

There is limited evidence that existing partnerships between NSW Health and Aboriginal communities meet its own commitment to use the ‘knowledge and expertise of the Aboriginal community (to) guide the health system at every level, including (for) the identification of key issues, the development of policy solutions, the structuring and delivery of services' 3 and the development of culturally appropriate models of mental health care.

NSW Health is planning and coordinating its resources to support Aboriginal people in acute phases of mental illness in hospital environments. However, it is not effectively planning for the supply and delivery of sufficient mental health services to assist Aboriginal patients to manage mental illness in community environments. Existing planning approaches, data and systems are insufficient to guide the $400 million investment into community mental health services announced in the 2018–19 Budget.

NSW Health is not consistently forming partnerships to ensure coordinated care for patients as they move between mental health services. There is no policy to guide this process and practices are not systematised or widespread.

In this report, the term ‘Aboriginal people’ is used to describe both Aboriginal and Torres Strait Islander peoples. The Audit Office of NSW acknowledges the diversity of traditional countries and Aboriginal language groups across the state of New South Wales.


1 Australian Burden of Disease Study: Impact and causes of illness and death in Aboriginal and Torres Strait Islander people 2011 (unaudited).
2 Australian Institute of Health and Welfare data 2016–17 (unaudited).
3 NSW Health, The Aboriginal Health Plan 2013-2023.

In May 2019, the Audit Office of New South Wales invited Aboriginal mental health clinicians and policy experts from government and non-government organisations to attend a one-day workshop. Workshop attendees advised on factors that improve the quality and appropriateness of mental health care for Aboriginal people in New South Wales. They described appropriate mental health care as:

  • culturally safe, allowing Aboriginal people to draw strength in their identity, culture and community
  • person centred and focussed on individual needs
  • delivered by culturally competent staff with no bias
  • holistic, trauma-informed and focussed on early intervention where possible
  • delivered in places that are appropriate including outreach to homes and communities
  • welcoming of the involvement of local Aboriginal community and connected to local knowledge and expertise including totems and kinship structures. 

The definition of 'appropriate' mental health care for Aboriginal people throughout this report is based on this advice.

Aboriginal people access emergency services at much higher rates than non-Aboriginal people

The choices that people make in relation to health service options provide some insight into the suitability and appropriateness of the service to their needs.

Aboriginal people have different mental health service use patterns than non-Aboriginal people. Aboriginal people are much more likely to be in a crisis situation before receiving mental health services, usually in an emergency department of a hospital.

Aboriginal people make up three per cent of the total New South Wales population, but they constitute 11 per cent of emergency department presentations for mental health treatments. In regional areas, Aboriginal people make up 20.5 per cent of presentations at emergency departments for mental health reasons. 

A number of factors help to explain Aboriginal mental health service usage patterns. According to government and non-government mental health organisations:

  • emergency department services are better known to Aboriginal people than other mental health services
  • community-based models of care are not appropriate for Aboriginal people
  • Aboriginal people are reluctant to access community-based mental health services to prevent crisis situations
  • community mental health services are not available for Aboriginal people after hours and during the weekend, so emergency services are the only option.

The statewide proportions of Aboriginal people presenting at emergency departments for mental health treatments has been increasing over time (Exhibit 6).

Appendix one – Response from agency

Appendix two – The NSW Aboriginal Health Plan

Appendix three – About the audit

Appendix four – Performance auditing

 

Parliamentary Reference: Report number #326 - released 29 August 2019

Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Transport Access Program

Transport Access Program

Transport
Infrastructure
Project management
Service delivery

The following report is available in an Easy English version that is intended to meet the needs of some people with lower literacy skills, some people with an intellectual disability and some people from different cultural backgrounds.

View the Easy English version of the Transport Access Program report

Transport for NSW’s process for selecting and prioritising projects for the third stage of its Transport Access Program balanced compliance with national disability standards with broader customer outcomes. Demographics, deliverability and value for money were also considered. However, Transport for NSW does not know the complete scope of work required for full compliance, limiting its ability to demonstrate that its approach is effective, according to a report released today by the Auditor-General for New South Wales, Margaret Crawford.

Access to transport is critical to ensuring that people can engage in all aspects of community life, including education, employment and recreation. People with disability can encounter barriers when accessing public transport services. In 2015, there were 1.37 million people living with disability in New South Wales.

Accessible public transport is about more than physical accessibility. It also means barrier-free access for people who have vision, hearing or cognitive impairments. All users, not just people with disability, benefit from improvements to the accessibility and inclusiveness of transport services. 

Transport for NSW has an obligation under Australian Government legislation to provide accessible services to people with disabilities in a manner which is not discriminatory. Under the Disability Standards for Accessible Public Transport 2002 (the DSAPT - an instrument of the Disability Discrimination Act 1992 (the Act) (Commonwealth)), there is a requirement to modify and develop new infrastructure, means of transport and services to provide access for people with disabilities. All public transport operators are required to ensure that at least 90 per cent of their networks met DSAPT by December 2017 and the networks will need to be 100 per cent compliant with all parts of the standards by 31 December 2022. Trains are not required to be fully compliant with DSAPT until December 2032. 

The Transport Access Program (TAP) is Transport for NSW's largest program with a specific focus on improving access to public transport for people with disability. The TAP is a series of projects to upgrade existing public transport infrastructure across four networks: Sydney Trains, Intercity Trains, Regional Trains and Sydney Ferries. Transport for NSW established the TAP as a rolling program and, to date, it has delivered the first tranche of TAP (TAP 1) and is completing the final projects for the second tranche (TAP 2). NSW budget papers estimate that by 30 June 2018, Transport for NSW had spent $1.2 billion in the TAP since its commencement in 2011-12.

After the completion of TAP 1 and TAP 2 (as well as through other transport infrastructure programs), Transport for NSW estimates that 58.5 per cent of the Sydney Trains, Regional Trains and Intercity Trains networks, and 66 per cent of the Sydney Ferries network, will be accessible. To close the significant gap in compliance with the DSAPT target, the objective for TAP 3 is ‘to contribute to Disability Discrimination Act 1992 related targets through DSAPT compliance upgrades’. 

The audit assessed whether Transport for NSW has an effective process to select and prioritise projects as part of the TAP, with a specific focus on the third tranche of TAP funding.

In August 2018, at the commencement of this audit, Transport for NSW intended to complete the selection of projects for the TAP 3 final business case in December 2018. Transport for NSW advise that it now intends to complete the development stage and final business case in the first quarter of 2019, prior to the final investment decision of the TAP program. This report is based on the TAP 3 strategic business case and information provided by Transport for NSW up to December 2018.

Conclusion
Transport for NSW’s process for selecting and prioritising projects for TAP 3 balanced DSAPT compliance goals with broader customer outcomes. It also considered demographics, deliverability and value for money. However, Transport for NSW does not know the complete scope of work required for full DSAPT compliance, and this limits its ability to demonstrate that its approach is effective. 
Transport for NSW has applied most of the external review recommendations from previous funding rounds to the implementation of the third round of TAP funding (TAP3), with positive results. Changes made include a clear objective for TAP 3 to focus on improving compliance, improved governance arrangements, and better consideration of deliverability and design during project planning. 
Through TAP 3, Transport for NSW is also trying to better address disability access in a way that balances DSAPT compliance with other considerations - such as population demographics, access to services and value for money. Transport for NSW developed an objective prioritisation and selection methodology to assess projects for TAP 3 funding. 
Transport for NSW cannot quantify the work needed to meet DSAPT compliance targets across the rail and ferry networks as it has not completed a comprehensive audit of compliance. This information is needed to ensure the effective targeting of funding, and to measure the contribution of TAP 3 work to meeting the DSAPT compliance targets. Instead, Transport for NSW has undertaken a phased approach to completing a comprehensive audit of compliance across the networks, with a focus on first assessing compliance at locations that are not wheelchair accessible. This creates two problems. First, Transport for NSW does not know the complete scope of work required to achieve DSAPT compliance. Second, not all wheelchair accessible locations fully meet DSAPT standards.
Transport for NSW's proposed communication plan for the schedule of TAP 3 funded works does not align with its Disability Inclusion Action Plan 2018-2022. The Disability Inclusion Action Plan commits Transport for NSW to providing a full list of stations and wharves to be upgraded with their estimated time of construction when the next round of funding, TAP 3, is announced. Given the long timeframes associated with improving transport infrastructure, this information is important as it allows people to make informed decisions about where they live, work or study. Instead, Transport for NSW plans to communicate information to customers on a project by project basis.

In 2015, there were 1.37 million people living with disability in New South Wales. Access to transport is critical to ensuring that people can engage in all aspects of community life, including education, employment and recreation. People with disability can encounter barriers when accessing public transport services. 

The social model of disability, outlined in the United Nations Convention on the Rights of Persons with Disabilities, views people with disability as not disabled by their impairment but by the barriers in the community and environment that restrict their full and effective participation in society on an equal basis with others. 

Accessible public transport is more than the provision of physical access to premises and conveyances, it provides barrier-free access for people who have vision, hearing or cognitive impairments. All users, not just people with disability, benefit from improvements to the accessibility and inclusiveness of transport services.

According to the Australian Bureau of Statistics, the main types of difficulties experienced by people with disability when using public transport relate to steps (39.9 per cent), difficulty getting to stops and stations (25 per cent), fear and anxiety (23.3 per cent) and lack of seating or difficulty standing (20.7 per cent).

Transport for NSW has a Disability Inclusion Action Plan (the Action Plan) 2018-2022 that sets an overall framework for planning, delivering and reporting on initiatives to increase accessibility of the transport network. It covers all elements of the journey experienced when using public transport, including journey planning, staff training, customer services and interaction between the physical environment and modes of transport. Appendix five outlines the guiding principles of the Action Plan.

Transport for NSW's Transport Social Policy branch developed the Action Plan in consultation with internal and external stakeholders. The director of the Transport Social Policy branch is a member of the TAP executive steering committee, which supports alignment between the Action Plan and TAP.

Transport for NSW's Disability Inclusion Action Plan describes a customer focussed approach to accessibility

One of the guiding principles of the Action Plan is ‘intelligent compliance’. Transport for NSW describes this as compliance that prioritises customer-focused outcomes over a narrow focus on legal compliance with accessibility standards. As well as being compliant, infrastructure should be practical, usable, fit for purpose and convenient. 

The TAP prioritisation and selection methodology reflects Transport for NSW’s focus on intelligent compliance. We consider this a reasonable approach as had Transport for NSW focussed exclusively on achieving compliance with the DSAPT targets by upgrading the most affordable infrastructure, some locations, that are used by more customers, would remain inaccessible to people with disability. However, this approach should not be seen as an alternative to Transport for NSW meeting its DSAPT compliance obligations.

TAP program staff consult with the Accessible Transport Advisory Committee

The Accessible Transport Advisory Committee (ATAC) has representatives from disability and ageing organisations, who provide expert guidance to Transport for NSW on access and inclusion. The ATAC provide guidance and feedback on projects and project solutions, including user testing where appropriate. TAP program staff provide regular updates at ATAC meetings, which include briefings on progress. The ATAC also provides feedback and suggestions to TAP program staff, which is considered and sometimes included in current and future projects.For example, in March 2017 the TAP program team briefed the ATAC on the challenges with respect to a number of ferry wharves and sought support for DSAPT exemptions proposed in the TAP 3 strategic business case.

Case study: Feedback on Braille lettering for lift buttons
In June 2018, the Program team sought feedback on a variety of lift button options to improve accessibility on future TAP projects. In September 2018, during the ATAC meeting attended by the Audit Office, the program team sought feedback on the standard designs for TAP 3. Some ATAC members noted that the standard design included Braille lettering on the lift buttons, and that this was not good practice because people can accidently press the button while reading it. As a result, Transport for NSW are incorporating this feedback into design requirements for the lifts for TAP 3, which will consider larger buttons, clearer Braille and Braille signage adjacent to the button.

Transport for NSW has not briefed the Advisory Committee on the outcome of the prioritisation and selection process

TAP program staff briefed the Advisory Committee about the prioritisation and selection methodology, after the Minister approved it in 2016. However, Transport for NSW have not briefed or consulted the Advisory Committee on the outcome of the prioritisation process. Infrastructure NSW noted this issue during its review of the strategic business case. 

Transport for NSW advised us that it established the ATAC as an advisory group, and that Transport for NSW does not disclose sensitive information to it. Transport for NSW intends to share the outcome of the prioritisation process following the completion of the TAP 3 development stage and final investment decision.

The TAP communication plan does not fully meet the requirements of the Disability Inclusion Action Plan

The Disability Inclusion Action Plan includes an action item to ‘provide a listing of stations and wharves to be upgraded with estimated time of construction as each new tranche of the Transport Access Program is announced’ The TAP Communication Plan that we reviewed does not include this provision instead focussing on communication on a per project basis. Given the long timeframes associated with improving transport infrastructure, this information is important as it allows people to make informed decisions about where they live, work or study.

Published

Actions for Newcastle Urban Transformation and Transport Program

Newcastle Urban Transformation and Transport Program

Transport
Planning
Compliance
Infrastructure
Management and administration
Procurement
Project management

The urban renewal projects on former railway land in the Newcastle city centre are well targeted to support the objectives of the Newcastle Urban Transformation and Transport Program (the Program), according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the government. However, the evidence that the cost of the light rail will be justified by its contribution to the Program is not convincing.

The Newcastle Urban Transformation and Transport Program (the Program) is an urban renewal and transport program in the Newcastle city centre. The Hunter and Central Coast Development Corporation (HCCDC) has led the Program since 2017. UrbanGrowth NSW led the Program from 2014 until 2017. Transport for NSW has been responsible for delivering the transport parts of the Program since the Program commenced. All references to HCCDC in this report relate to both HCCDC and its predecessor, the Hunter Development Corporation. All references to UrbanGrowth NSW in this report relate only to its Newcastle office from 2014 to 2017.

This audit had two objectives:

  1. To assess the economy of the approach chosen to achieve the objectives of the Program.
  2. To assess the effectiveness of the consultation and oversight of the Program.

We addressed the audit objectives by answering the following questions:

a) Was the decision to build light rail an economical option for achieving Program objectives?
b) Has the best value been obtained for the use of the former railway land?
c) Was good practice used in consultation on key Program decisions?
d) Did governance arrangements support delivery of the program?

Conclusion
1. The urban renewal projects on the former railway land are well targeted to support the objectives of the Program. However, there is insufficient evidence that the cost of the light rail will be justified by its contribution to Program objectives.

The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the Government. HCCDC, and previously UrbanGrowth NSW, identified and considered options for land use that would best meet Program objectives. Required probity processes were followed for developments that involved financial transactions. Our audit did not assess the achievement of these objectives because none of the projects have been completed yet.

Analysis presented in the Program business case and other planning documents showed that the light rail would have small transport benefits and was expected to make a modest contribution to broader Program objectives. Analysis in the Program business case argued that despite this, the light rail was justified because it would attract investment and promote economic development around the route. The Program business case referred to several international examples to support this argument, but did not make a convincing case that these examples were comparable to the proposed light rail in Newcastle.

The audited agencies argue that the contribution of light rail cannot be assessed separately because it is a part of a broader Program. The cost of the light rail makes up around 53 per cent of the total Program funding. Given the cost of the light rail, agencies need to be able to demonstrate that this investment provides value for money by making a measurable contribution to the Program objectives.

2. Consultation and oversight were mostly effective during the implementation stages of the Program. There were weaknesses in both areas in the planning stages.

Consultations about the urban renewal activities from around 2015 onward followed good practice standards. These consultations were based on an internationally accepted framework and met their stated objectives. Community consultations on the decision to close the train line were held in 2006 and 2009. However, the final decision in 2012 was made without a specific community consultation. There was no community consultation on the decision to build a light rail.

The governance arrangements that were in place during the planning stages of the Program did not provide effective oversight. This meant there was not a single agreed set of Program objectives until 2016 and roles and responsibilities for the Program were not clear. Leadership and oversight improved during the implementation phase of the Program. Roles and responsibilities were clarified and a multi-agency steering committee was established to resolve issues that needed multi-agency coordination.
The light rail is not justified by conventional cost-benefit analysis and there is insufficient evidence that the indirect contribution of light rail to achieving the economic development objectives of the Program will justify the cost.
Analysis presented in Program business cases and other planning documents showed that the light rail would have small transport benefits and was expected to make a modest contribution to broader Program objectives. Analysis in the Program business case argued that despite this, the light rail was justified because it would attract investment and promote economic development around the route. The Program business case referred to several international examples to support this argument, but did not make a convincing case that these examples were comparable to the proposed light rail in Newcastle.
The business case analysis of the benefits and costs of light rail was prepared after the decision to build light rail had been made and announced. Our previous reports, and recent reports by others, have emphasised the importance of completing thorough analysis before announcing infrastructure projects. Some advice provided after the initial light rail decision was announced was overly optimistic. It included benefits that cannot reasonably be attributed to light rail and underestimated the scope and cost of the project.
The audited agencies argue that the contribution of light rail cannot be assessed separately because it is part of a broader Program. The cost of the light rail makes up around 53 per cent of the total Program funding. Given the high cost of the light rail, we believe agencies need to be able to demonstrate that this investment provides value for money by making a measurable contribution to the Program objectives.

Recommendations
For future infrastructure programs, NSW Government agencies should support economical decision-making on infrastructure projects by:
  • providing balanced advice to decision makers on the benefits and risks of large infrastructure investments at all stages of the decision-making process
  • providing scope and cost estimates that are as accurate and complete as possible when initial funding decisions are being made
  • making business cases available to the public.​​​​​​
The planned uses of the former railway land achieve a balance between the economic and social objectives of the Program at a reasonable cost to the government.

The planned uses of the former railway land align with the objectives of encouraging people to visit and live in the city centre, creating attractive public spaces, and supporting growth in employment in the city. The transport benefits of the activities are less clear, because the light rail is the major transport project and this will not make significant improvements to transport in Newcastle.

The processes used for selling and leasing parts of the former railway land followed industry standards. Options for the former railway land were identified and assessed systematically. Competitive processes were used for most transactions and the required assessment and approval processes were followed. The sale of land to the University of Newcastle did not use a competitive process, but required processes for direct negotiations were followed.

Recommendation
By March 2019, the Hunter and Central Coast Development Corporation should:
  • work with relevant stakeholders to explore options for increasing the focus on the heritage objective of the Program in projects on the former railway land. This could include projects that recognise the cultural and industrial heritage of Newcastle.
Consultations about the urban renewal activities followed good practice standards, but consultation on transport decisions for the Program did not.

Consultations focusing on urban renewal options for the Program included a range of stakeholders and provided opportunities for input into decisions about the use of the former railway land. These consultations received mostly positive feedback from participants. Changes and additions were made to the objectives of the Program and specific projects in response to feedback received. 

There had been several decades of debate about the potential closure of the train line, including community consultations in 2006 and 2009. However, the final decision to close the train line was made and announced in 2012 without a specific community consultation. HCCDC states that consultation with industry and business representatives constitutes community consultation because industry representatives are also members of the community. This does not meet good practice standards because it is not a representative sample of the community.

There was no community consultation on the decision to build a light rail. There were subsequent opportunities for members of the community to comment on the implementation options, but the decision to build it had already been made. A community and industry consultation was held on which route the light rail should use, but the results of this were not made public. 

Recommendation
For future infrastructure programs, NSW Government agencies should consult with a wide range of stakeholders before major decisions are made and announced, and report publicly on the results and outcomes of consultations. 

The governance arrangements that were in place during the planning stages of the Program did not provide effective oversight. Project leadership and oversight improved during the implementation phase of the Program.

Multi-agency coordination and oversight were ineffective during the planning stages of the Program. Examples include: multiple versions of Program objectives being in circulation; unclear reporting lines for project management groups; and poor role definition for the initial advisory board. Program ownership was clarified in mid-2016 with the appointment of a new Program Director with clear accountability for the delivery of the Program. This was supported by the creation of a multi-agency steering committee that was more effective than previous oversight bodies.

The limitations that existed in multi-agency coordination and oversight had some negative consequences in important aspects of project management for the Program. This included whole-of-government benefits management and the coordination of work to mitigate impacts of the Program on small businesses.

Recommendations
For future infrastructure programs, NSW Government agencies should: 

  • develop and implement a benefits management approach from the beginning of a program to ensure responsibility for defining benefits and measuring their achievement is clear
  • establish whole-of-government oversight early in the program to guide major decisions. This should include:
    • agreeing on objectives and ensuring all agencies understand these
    • clearly defining roles and responsibilities for all agencies
    • establishing whole-of-government coordination for the assessment and mitigation of the impact of major construction projects on businesses and the community.

By March 2019, the Hunter and Central Coast Development Corporation should update and implement the Program Benefits Realisation Plan. This should include:

  • setting measurable targets for the desired benefits
  • clearly allocating ownership for achieving the desired benefits
  • monitoring progress toward achieving the desired benefits and reporting publicly on the results.

Appendix one - Response from agencies    

Appendix two - About the audit

Appendix three - Performance auditing

 

Parliamentary reference - Report number #310 - released 12 December 2018

Published

Actions for Mobile speed cameras

Mobile speed cameras

Transport
Compliance
Financial reporting
Information technology
Internal controls and governance
Management and administration
Regulation
Service delivery

Key aspects of the state’s mobile speed camera program need to be improved to maximise road safety benefits, according to a report released today by the Auditor-General for New South Wales, Margaret Crawford. Mobile speed cameras are deployed in a limited number of locations with a small number of these being used frequently. This, along with decisions to limit the hours that mobile speed cameras operate, and to use multiple warning signs, have reduced the broad deterrence of speeding across the general network - the main policy objective of the mobile speed camera program.

The primary goal of speed cameras is to reduce speeding and make the roads safer. Our 2011 performance audit on speed cameras found that, in general, speed cameras change driver behaviour and have a positive impact on road safety.

Transport for NSW published the NSW Speed Camera Strategy in June 2012 in response to our audit. According to the Strategy, the main purpose of mobile speed cameras is to reduce speeding across the road network by providing a general deterrence through anywhere, anytime enforcement and by creating a perceived risk of detection across the road network. Fixed and red-light speed cameras aim to reduce speeding at specific locations.

Roads and Maritime Services and Transport for NSW deploy mobile speed cameras (MSCs) in consultation with NSW Police. The cameras are operated by contractors authorised by Roads and Maritime Services. MSC locations are stretches of road that can be more than 20 kilometres long. MSC sites are specific places within these locations that meet the requirements for a MSC vehicle to be able to operate there.

This audit assessed whether the mobile speed camera program is effectively managed to maximise road safety benefits across the NSW road network.

Conclusion

The mobile speed camera program requires improvements to key aspects of its management to maximise road safety benefits. While camera locations have been selected based on crash history, the limited number of locations restricts network coverage. It also makes enforcement more predictable, reducing the ability to provide a general deterrence. Implementation of the program has been consistent with government decisions to limit its hours of operation and use multiple warning signs. These factors limit the ability of the mobile speed camera program to effectively deliver a broad general network deterrence from speeding.

Many locations are needed to enable network-wide coverage and ensure MSC sessions are randomised and not predictable. However, there are insufficient locations available to operate MSCs that meet strict criteria for crash history, operator safety, signage and technical requirements. MSC performance would be improved if there were more locations.

A scheduling system is meant to randomise MSC location visits to ensure they are not predictable. However, a relatively small number of locations have been visited many times making their deployment more predictable in these places. The allocation of MSCs across the time of day, day of week and across regions is prioritised based on crash history but the frequency of location visits does not correspond with the crash risk for each location.

There is evidence of a reduction in fatal and serious crashes at the 30 best-performing MSC locations. However, there is limited evidence that the current MSC program in NSW has led to a behavioural change in drivers by creating a general network deterrence. While the overall reduction in serious injuries on roads has continued, fatalities have started to climb again. Compliance with speed limits has improved at the sites and locations that MSCs operate, but the results of overall network speed surveys vary, with recent improvements in some speed zones but not others.
There is no supporting justification for the number of hours of operation for the program. The rate of MSC enforcement (hours per capita) in NSW is less than Queensland and Victoria. The government decision to use multiple warning signs has made it harder to identify and maintain suitable MSC locations, and impeded their use for enforcement in both traffic directions and in school zones. 

Appendix one - Response from agency

Appendix two - About the audit

Appendix three - Performance auditing

 

Parliamentary reference - Report number #308 - released 18 October 2018