Refine search Expand filter

Reports

Published

Actions for Early childhood education

Early childhood education

Education
Compliance
Information technology
Management and administration
Project management
Regulation
Risk
Service delivery
Workforce and capability

Enrolments in quality early childhood education programs in New South Wales are increasing but are below the national benchmark, according to a report released today by the NSW Auditor-General, Margaret Crawford.

Ninety-five per cent of children should be enrolled in at least 600 hours in the year before school, but according to the latest NSW figures 77 per cent of children were enrolled in quality early childhood education programs. This 2015 figure is below the benchmark, but is a significant improvement on 2013 when 59 per cent were enrolled.

 

Parliamentary reference - Report number #271 - released 26 May 2016

Published

Actions for Supporting students with disability in NSW public schools

Supporting students with disability in NSW public schools

Education
Information technology
Management and administration
Service delivery
Workforce and capability

The Department of Education is doing a reasonable job in managing how well students with disability transition to a new school and supporting teachers to improve these students’ educational outcomes, according to a report released today by the NSW Auditor-General, Margaret Crawford.

The level of support provided to students with disability can vary between schools. This is partly due to cultural resistance in some schools and teachers not always having the necessary skills to support children with disability.

 

Parliamentary reference - Report number #270 - released 12 May 2016

Published

Actions for Reintegrating young offenders into the community after detention

Reintegrating young offenders into the community after detention

Justice
Management and administration
Shared services and collaboration
Workforce and capability

Juvenile Justice prepares and assists young people to reintegrate into the community reasonably well, given the complex needs of young people in detention, according to a report released today by the NSW Auditor-General, Margaret Crawford.

Juvenile Justice has many processes and programs to identify and address young people’s needs while in detention and links them to relevant support services in the community. It still faces some significant barriers which make reintegration difficult. Some are within its control to fix, such as improving training and recreational activities available to young people in detention. Others relate to external factors, such as the capacity of other organisations to address their reintegration needs like housing, education and employment, and a young person’s period of detention.

 

Parliamentary reference - Report number #269 - released 28 April 2016

Published

Actions for Performance frameworks in custodial centre operations

Performance frameworks in custodial centre operations

Justice
Management and administration
Risk
Service delivery

The effectiveness of Corrective Services NSW’s performance framework is limited because organisational key performance indicators (KPIs) do not cascade to public correctional centres, according to a report released today by the Acting New South Wales Auditor-General, Tony Whitfield.

'As a result, individual public correctional centres could not be assessed on how well they are contributing to overall Corrective Service objectives, and it is difficult to vary performance expectations in response to changing operating environments', said Mr Whitfield. 'Its commissioning and contestability project is designed to address these issues', he added.

 

Parliamentary reference - Report number #267 - released 3 March 2016

Published

Actions for Franchising of Sydney Ferries Network services

Franchising of Sydney Ferries Network services

Transport
Procurement
Service delivery

Franchising services on the Sydney Ferries Network was justified, and Transport for NSW’s management of the franchise has been largely effective according to a report released today by the NSW Acting Auditor-General, Tony Whitfield.

'Franchising has resulted in cost savings, good service performance, and effective risk transfer from government to the private sector operator', said Mr Whitfield.

 

Parliamentary reference - Report number #265 - released 4 February 2016

Published

Actions for Volume Twelve 2015 Part One Trade & Investment and TAFE

Volume Twelve 2015 Part One Trade & Investment and TAFE

Planning
Education
Asset valuation
Compliance
Financial reporting
Information technology
Internal controls and governance
Project management
Risk

Serious system limitations prevented TAFE NSW from providing sufficient and appropriate evidence to support recorded student revenue of $477 million, student receivables and accrued income of $47.6 million and unearned revenue of $398 million.
 
These limitations resulted in: 

  • a qualified audit opinion being issued for TAFE NSW;
  • delays in enrolling students;
  • inability to fully reconcile cash balances;
  • difficulties in reconciling student enrolments with revenues recorded in the financial statements;
  • large volumes of manual processing.

Published

Actions for Albert 'Tibby' Cotter Walkway

Albert 'Tibby' Cotter Walkway

Transport
Internal controls and governance
Procurement
Project management

On 17 September 2015, the Acting Auditor-General of New South Wales, Tony Whitfield, released a report on the Albert ‘Tibby’ Cotter Walkway which crosses over Anzac Parade in Moore Park. The Walkway’s primary function is to cater for event patrons in the precinct. Moore Park is listed on the State Heritage Register and is an open space specifically established to cater for public recreation.
 
Roads and Maritime Services (RMS) delivered the Walkway to an extremely tight timeframe. It was operational for the 2015 Cricket World Cup at the Sydney Cricket Ground as promised by the government. However, the World Cup deadline added substantially to the total cost of the Walkway, which is projected to be $38 million.
 
Transport for NSW and RMS could not provide evidence of a compelling economic or financial argument to support the construction of the Walkway or for the tight deadline. Also, the processes they adopted to provide assurance of the project’s value for money were not adequate.

 

Parliamentary reference - Report number #260 - released 17 September 2015

Published

Actions for Sydney metropolitan bus contracts

Sydney metropolitan bus contracts

Transport
Internal controls and governance
Management and administration
Procurement
Project management
Service delivery

On 9 September 2015, the Acting Auditor-General of New South Wales, Tony Whitfield, released a report on Sydney Metropolitan Bus Service Contracts.
 
All scheduled bus services in the Sydney metropolitan area are provided under contracts with the public and private operators. The contracts allow Transport for NSW (TfNSW) to determine what bus services are provided and to whom. This audit assessed the effectiveness of TfNSW’s design and management of these contracts.
 
Bus services provided under the Sydney Metropolitan Bus Service Contracts have largely been effective and efficient. Operators are mostly meeting their key performance indicators. Customer satisfaction is better than under the previous contracts and improving, patronage is increasing, and the unit costs of providing services are now lower than under the previous contracts. 
 
However, punctuality remains a problem. Private operators are mostly starting their trips on time, but rarely meeting their mid and end-of-trip targets. State Transit Authority’s (STA) punctuality is improving but is worse than private operators, and other areas of performance are generally below private operators.
 
The current situation is a substantial improvement over what we found in our 2010 audit on the previous contracts.

 

Parliamentary reference - Report number #258 - released 9 September 2015

Published

Actions for Identifying productivity in the public sector

Identifying productivity in the public sector

Health
Education
Community Services
Transport
Justice
Treasury
Whole of Government
Internal controls and governance
Management and administration

This report examines selected areas of government activity to see if sufficient information was available to identify and assess changes in productivity. The areas examined were primary and secondary school public education, acute inpatient care in NSW public hospitals, CityRail, the NSW Police Force, and the NSW Local Court.

Productivity is commonly defined as the amount of output per unit of input.

 

Parliamentary reference - Report number #256 - released 16 July 2015

Published

Actions for Implementing performance audit recommendations

Implementing performance audit recommendations

Premier and Cabinet
Treasury
Whole of Government
Health
Education
Community Services
Transport
Justice
Compliance
Internal controls and governance
Management and administration

NSW Government agencies have sound processes for implementing performance audit recommendations in Auditor-General’s Reports to Parliament. There are many cases of good practice. For example, some agencies formed a steering committee and developed a detailed plan to implement recommendations. Another incorporated the implementation of recommendations into both its business plan and the work plans of individual officers who were managing projects. Most agencies also used their Audit and Risk Committees to monitor recommendations.
 
We found some cases where agencies can improve how they coordinate actions to address recommendations. Most agencies were not revisiting these actions to determine whether they remain appropriate.

 

Parliamentary reference - Report number #254 - released 24 June 2015