Actions for Managing Departmental Amalgamations

Managing Departmental Amalgamations

Industry
Finance
Internal controls and governance
Management and administration
Project management
Service delivery
Shared services and collaboration

Both Commerce and DPI substantially achieved their stated amalgamation savings objectives as set by government. The departments are expected to achieve savings targets of about $150 million and $190 million respectively over their first four years. Our analysis indicates that there are two key factors in successful amalgamations. The first is effective early planning by departments based on clear objectives, supported by quick action. Second, significant synergies in service delivery can be achieved when departments with similar services and customers are amalgamated. The Department of Primary Industries is an example.

 

Parliamentary reference - Report number #175 - released 5 March 2008

Published

Actions for Improving efficiency of irrigation water use on farms

Improving efficiency of irrigation water use on farms

Industry
Management and administration
Procurement
Service delivery
Shared services and collaboration

The Department of Primary Industries (DPI) has a crucial role in assisting the irrigation industry to respond to the conflicting demands placed upon the state’s water resources. The State Plan emphasises the importance of water to agriculture, and gives DPI responsibility to use its training programs to help farmers continue to increase water use efficiency. DPI needs to work closely with agencies with which it shares responsibilities in the State Plan to ensure that its water use efficiency activities contribute to the State Plan goals. It needs to work closely with Treasury to document the services it will require to do this, the resources which will be needed, and how its success will be measured. This will ensure that DPI is well placed to continue to assist the NSW farming industry to adapt and survive periods of reduced water availability. 

 

Parliamentary reference - Report number #172 - released 21 November 2007

Published

Actions for Responding to homelessness

Responding to homelessness

Health
Community Services
Internal controls and governance
Management and administration
Project management
Service delivery
Shared services and collaboration

Many projects, both Partnership Against Homelessness and by individual agencies, have shown good results or led to improvements. One example is helping mental health patients maintain stable housing. Another is providing street outreach services to homeless people in inner Sydney. Despite these efforts, we were unable to determine how well the government is responding to homelessness statewide. This is because there are no statewide performance measures or targets on homelessness. Also there is limited benchmarking, and no formal means of spreading information on homelessness initiatives and projects.

 

Parliamentary reference - Report number #165 - released 2 May 2007

Published

Actions for Helping older people access a residential aged care facility

Helping older people access a residential aged care facility

Health
Community Services
Compliance
Internal controls and governance
Management and administration
Risk
Service delivery
Shared services and collaboration
Workforce and capability

Assessment processes for older people needing to go to an Residential Aged Care Facility (RACF) vary depending on the processes of the Aged Care Assessement Teams (ACAT) they see and whether or not they are in hospital. The data collected on ACAT performance was significantly revised during 2004 making comparisons with subsequent years problematic. ACATs have more responsibilities than assessing older people for residential care. It is not clear whether they have sufficient resources for this additional workload.

 

Parliamentary reference - Report number #160 - released 5 December 2006

Published

Actions for Fraud control improvement kit: Meeting your fraud control obligations

Fraud control improvement kit: Meeting your fraud control obligations

Whole of Government
Fraud
Internal controls and governance
Management and administration

Fraud risks, and fraud control obligations, are growing at a rate which demands that more be done.  Our 2005 report showed that still only 50 per cent of NSW public sector organisations had achieved an adequate level of performance in developing and implementing a fraud control strategy.  In response to this, our 2005 report provided a range of recommendations for improving fraud control and urged that fraud control become a key item for attention by audit committees.

We recognise that organisations need a simple and effective way to review and monitor how effectively they are implementing fraud control strategies.  This kit has been developed for precisely that purpose.  Its development reflects an extended period of consultation, focus-group review and pilot-testing to ensure that that the kit is simple to use, practical and flexible.  The kit assists organisations to meet their fraud control obligations in a cost-effective manner, tailored to their situation and based on risk.

 

Parliamentary reference - Report number #156 - released 20 July 2006

Published

Actions for Agency use of performance information to manage services

Agency use of performance information to manage services

Treasury
Whole of Government
Management and administration

Overall the results were mixed. There is some good news but this is such a basic and vital issue that we must conclude that a good deal more needs to be done. Three agencies did not have sufficient information to provide a balanced view of services. And two of these agencies could not tell us whether their services actually made a difference to customers. Across the ten programs we found many examples of good practice, but some variation in the quality and coverage of performance measures. Agencies that we identified as not having sufficient information to judge services were either unaware of its importance, collected data on activities but not results or reported system limitations.

 

Parliamentary reference - Report number #153 - released 21 June 2006

Published

Actions for The Cross City Tunnel Project

The Cross City Tunnel Project

Transport
Treasury
Premier and Cabinet
Planning
Environment
Infrastructure
Management and administration
Procurement
Project management
Risk

In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs. Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate.

In our opinion, however, the Government, Treasury and the RTA did not sufficiently consider the implications of an upfront payment involving more than simple project cost reimbursement (i.e. the ‘Business Consideration Fee’ component). In addition, the RTA was wrong to change the toll escalation factor late in 2002 to compensate the tunnel operator, Cross City Motorway Pty Ltd, for additional costs.

 

Parliamentary reference - Report number #152 - released 31 May 2006

Published

Actions for Agencies working together to improve services

Agencies working together to improve services

Premier and Cabinet
Treasury
Justice
Transport
Education
Internal controls and governance
Service delivery
Shared services and collaboration

In the cases we examined, we found that agencies working together can improve services or results. However, the changes were not always as great as anticipated or had not reached maximum potential. Establishing the right governance framework and accountability requirements between partners at the start of the project is critical to success. And joint responsibility requires new funding and reporting arrangements to be developed.

 

Parliamentary reference - Report number #149 - released 22 March 2006

Published

Actions for The New Schools Privately Financed Project

The New Schools Privately Financed Project

Education
Treasury
Infrastructure
Management and administration
Procurement
Project management

In our view the contracts in the New Schools Privately Financed Project were established and let in a way that greatly assists their potential for delivering value for money. The contracts in the New Schools Privately Financed Project are at an early stage of their 30 year lives and the savings and other benefits are not guaranteed. The contracts will need to be carefully managed over the 30 year period to ensure that benefits are realised and that costs do not escalate beyond expectations.

 

Parliamentary reference - Report number #148 - released 8 March 2006

Published

Actions for Liverpool to Parramatta Bus Transitway

Liverpool to Parramatta Bus Transitway

Transport
Treasury
Infrastructure
Management and administration
Project management
Service delivery

Several of my recent audits have identified a need to improve our public transport system – both for the benefit of travellers and to assist in achieving better air quality.

Bus Transitways can provide a good public transport solution for lower density population areas, potentially at a relatively low capital cost. This audit examines the transitway running between Liverpool and Parramatta, the first of several planned for Sydney. This audit should contribute to a better understanding of the lessons learnt from this first project, and so to future transitways providing better value for money.

But this audit also raises broader issues.

It highlights the importance of accurately projecting the total cost of major infrastructure projects before governments lock in their decisions. It also highlights the need for sound decision-making processes when government agencies compete with the private sector. The principles and recommendations flowing from these issues are ones I would draw to the attention of all agencies, and to the Government.

 