Actions for Health capital works

Health capital works

Health
Compliance
Infrastructure
Procurement
Project management

This report examines whether NSW Health effectively planned and delivered major capital works to meet the demand for health services in New South Wales.

The report found that NSW Health has substantially expanded health infrastructure across New South Wales since 2015. However, the program was driven by Local Health District priorities without assessment of the State’s broader and future‑focussed health requirements.

The report found that unclear decision making roles and responsibilities between Health Infrastructure and the Ministry of Health limited the ability of NSW Health to effectively test and analyse investment options.

Project delays and budget overruns on some major projects indicate that Health Infrastructure's project governance, risk assessment and management systems could be improved.

The Auditor‑General recommends that NSW Health ensure its capital projects offer the greatest value to New South Wales by establishing effective policy guidance and enhancing project governance and management systems.

Read full report (PDF)

Since 2011–12, NSW Health has aimed to improve its facilities and build 'future focused' infrastructure. The NSW Government’s 2015–16 election commitments established a four-year $5.0 billion capital program for NSW Health to build and upgrade more than 60 hospitals and health services. The 2019–20 State Budget committed a further $10.1 billion over four years for another 29 projects. This is the largest investment to date on health capital works in New South Wales.

Recent reviews of infrastructure have recognised that population and demographic growth will require a change in the delivery and composition of health infrastructure, including considering greater use of non-traditional, non-capital health service options and assets.

To ensure that expenditure on capital works represents the best value for money, NSW Health's business cases need to be robust and supported by evidence that demonstrates they are worthy investments. The NSW Process of Facility Planning has been the main framework guiding the detailed planning and development of NSW Health's capital works proposals. This framework was developed by the then NSW Department of Health in 2010. Its aim is to ensure investment proposals are supported by rigorous planning processes that address health service needs and provide value for money.

Infrastructure projects of the complexity and scale being delivered by NSW Health carry inherent risks. For example, unplanned cost escalations can potentially impact on the State’s finances. Unforeseen delays can also reduce the intended benefits. The growth in the State’s health capital spend and project profile, means its exposure to such risks has increased over time.

The objective of this audit was to assess the effectiveness of planning and delivery of major capital works to meet demand for health services in New South Wales. To address this objective, the audit examined whether:

  • the Ministry of Health has effective procedures for planning and prioritising investments in major health capital works
  • Health Infrastructure develops robust business cases for initiated major capital works that reliably inform government decision making
  • Health Infrastructure has effective project governance and management systems that support delivering projects on-time, within budget and achievement of intended benefits.

The audit focused on the Ministry of Health and Health Infrastructure – being the lead agencies within NSW Health responsible for prioritising, planning and delivering major health capital works across the State. The audit examined 13 business cases for eight discrete projects over a ten-year period.

Conclusion

NSW Health has substantially expanded health infrastructure across New South Wales since 2015. However, its planning and prioritisation processes were not assessed against a long-term statewide health infrastructure plan and lacked rigorous assessment against non-capital options creating a risk that they do not maximise value for New South Wales.

The scale of NSW Health's capital investment is significant and has grown substantially in recent years. The NSW Government’s election commitments in 2015–16 and 2019–20 collectively set out a $15.0 billion capital program to build and upgrade 89 hospitals and health services. NSW Health developed this infrastructure program in the absence of a statewide health infrastructure strategy and investment framework to focus its planning and decisions on the types of capital investments required to meet the long-term needs of the NSW health system.

Consequently, locally focused priorities of the State’s 17 Local Health Districts have been the primary drivers of NSW Health’s capital investments since 2015–16. Local Health District investment proposals for hospitals were developed without consideration of alternative health options such as community health service models, technology-driven eHealth care, or private sector options. Without rigorous assessment against a range of potential health service options, there is a risk that selected projects do not maximise value for New South Wales.

In recognition of the need for a statewide approach to infrastructure planning, the Ministry of Health recently developed a 20-year Health Infrastructure Strategy and prioritisation framework in 2019. The strategy was approved by the NSW Government in April 2020.

NSW Health's ability to effectively test and analyse its capital investment options has been compromised by unclear decision-making roles and responsibilities between its Health Infrastructure and the Ministry of Health agencies.

While both Health Infrastructure and the Ministry of Health have responsibilities for the assessment of business cases for proposed infrastructure projects, confusion about the roles of each agency at key steps compromised the efficacy of the process. Health Infrastructure and the Ministry of Health have differing views about which agency is responsible for testing business case inputs and conducting comprehensive options appraisals.

As a result of this confusion, Health Infrastructure and the Ministry of Health did not rigorously test Local Health District capital investment proposals against defined statewide health infrastructure investment priorities. The NSW Process of Facility Planning does not clarify the responsibilities of all parties in validating and prioritising Local Health District's Clinical Service Plans and progressing them to business cases.

NSW Health's infrastructure priorities are not sufficiently supported by transparent documentation of selection methodology and the rationale for decisions. Consequently, there is a risk that recommended options, whilst having some economic and health service merit, do not represent the greatest value.

Substantial delays and budget overruns on some major projects indicate that Health Infrastructure's project governance, risk assessment and management systems could be improved.

Health Infrastructure did not fully comply with NSW Government guidelines for developing business cases and making economic appraisals for proposed capital investments. These weaknesses, along with delays and budget overruns on some projects, demonstrate a need for Health Infrastructure to strengthen its project governance, management and quality control systems.

 

Over the period of review, NSW Government policies for business case development and submission have emphasised that effective governance arrangements are critical to a proposal's successful implementation.

NSW Health's Process of Facility Planning similarly highlights the importance of effective governance and project management for achieving good outcomes. It prescribes a general governance structure managed by Health Infrastructure that can be tailored to the planning and delivery of health infrastructure projects greater than $10.0 million.

Project challenges indicate opportunities for strengthening governance and project management

The three major hospital redevelopments examined in metropolitan, regional and rural areas had a combined Estimated Total Cost of more than $1.2 billion and comprised eight discrete projects and 13 separate business cases.

Almost all these projects experienced delivery challenges which impacted achievement of their original objectives and intended benefits. This is expected in complex and large-scale health infrastructure programs. However, in some projects the impacts were significant and resulted in substantial delays, unforeseen costs, and diversion of resources from other priority areas.

Our review of the selected case studies highlighted opportunities for enhancing governance and project management. Specifically, it indicates a need for improving transparency in the management of contingencies, risk management and assessments particularly relating to adverse site conditions and the selection of contractors. There is also a need to strengthen forward planning for options to address unfunded priorities within business cases that risk complicating the delivery of future project stages resulting in unforeseen costs and potentially avoidable budget overruns.

Need for increased transparency and accountability in the management of contingency funds

In February 2017, the Ministry's Capital Strategy Group approved the use of surplus funds of $13.76 million from Stage 1 of the Hornsby Ku-ring-gai Hospital Redevelopment for new works deemed needed to support Stage 2. Following this decision, Health Infrastructure finalised and submitted a business case addendum for Stage 1 to the Ministry in March 2017, addressing the new works comprising a two-storey building for medical imaging and paediatric floors. The business case addendum also addressed options to fit out and procure major medical imaging equipment. The Ministry approved the Stage 1 business case in July 2017, noting the Ministry's Capital Strategy Group had already approved the use of remaining Stage 1 funds to deliver the new works.

Stage 1 was completed in 2015, almost two years before the Stage 1 business case addendum was prepared in February 2017.

The Ministry's decision to approve the new works using $13.76 million of surplus Stage 1 funds did not comply with the NSW Treasury Circular TC 12/20. This policy establishes the Treasurer's approval must be sought and received before a new capital project with an Estimated Total Cost of $5.0 million or more can be approved by NSW Health. The Ministry therefore exceeded its delegated authority in making this decision, as it was not evident it had sought and received the Treasurer's approval prior to doing so.

Consequently, the surplus Stage 1 funds should not have been used by the Ministry to deliver new works in the circumstances. Instead, they should have been released from the Stage 1 project in accordance with established NSW Health procedures, and the Stage 1 Estimated Total Cost revised down accordingly. This did not occur, and NSW Health ultimately directed $11.0 million in surplus Stage 1 funds to the new works.

These circumstances indicate a need to strengthen transparency and accountability within NSW Health for the approval of new projects, and how contingency funds are used in the management of major health capital works. They also demonstrate the impact of weaknesses with options appraisal as the initial Stage 1 business case did not consider alternative options for addressing the initially unfunded works later covered by the Stage 1 business case addendum and ultimately funded from the Stage 1 contingency provision.

Weaknesses in service delivery planning resulted in unaccounted-for costs

In addition to proposing the above-noted new works, the 2017 Stage 1 Business Case Addendum for the Hornsby-Ku-ring-gai development sought to retrospectively address the estimated funding gap of around $14.0 million for the internal fit out, supply of major medical imaging equipment, and cost to operate the medical imaging service at Hornsby Ku-ring-gai Hospital also not addressed in the originally Stage 1 business case.

The Stage 1 business case addendum considered various procurement options to purchase and run the medical imaging services ranging from State operation purchase options to private operation purchase options.

It recommended outsourcing the operation and provision of equipment to the private sector based on estimated savings to the public sector initially of around $650,000 per annum reducing over time to $270,000. The Ministry endorsed this option in June 2017, but it did not ultimately proceed.

A July 2018 report to the Executive Steering Committee on the project shows NSW Health later decided to deliver operation of the medical imaging unit 'traditionally' with an updated estimate of the cost at approximately $16.4 million. The report also shows the Ministry supported the costs now being met by the Northern Sydney Local Health District.

This means the funding gap previously identified in the Stage 1 business case addendum for fitting out the medical imaging building and supply of major medical equipment would need to be met fully by the State, representing a $16.4 million cost overrun for the project.

Examined reports to the Executive Steering Committee show this was largely funded by the Northern Sydney Local Health District via the disposal of land realising approximately $15.0 million in proceeds.

This initially unforeseen cost, along with the additional $11.0 million for the new works approved under the Stage 1 business case addendum, were ultimately merged with the Stage 2 project initially approved in 2017–18 with an Estimated Total Cost of $200 million.

The extent of budget variation on the Hornsby Kur-ring-gai development has not been transparent

The 2019–20 State Budget provided an additional $65.0 million for a further Stage 2A to deliver additional built capacity to support outpatient services, enhanced allied health services, re-housed community health services and the delivery of prioritised clinical services unfunded as part of Stage 2. The funds were approved based on an Investment Decision Template (IDT) that examined two options in addition to the base case representing scoping alternatives to the preferred master planned capital solution.

However, we found the IDT showed around 23 per cent of the $65.0 million sought (i.e. $15.0 million) was to be allocated to fund the deficit in Stage 2, which had arisen as a result of project delays due to adverse site conditions. This was not discussed in the IDT.

The February 2020 report to the Executive Steering Committee shows a combined Stage 2 and 2A final forecast cost of $292.6 million against a potential budget of $290.7 million representing an overall deficit for the project of around 0.6 per cent.

However, this favourable final budget position does not transparently show the funding challenges experienced over the project's implementation to-date. The three major budget issues include:

  • inappropriate use of around $11.0 million in Stage 1 contingency for originally unfunded works contrary to Treasury policy
  • the additional $16.4 million cost unforeseen in the Stage 1 business case for delivering medical imaging services mostly funded through the sale of land
  • an additional $15.0 million from Stage 2A to cover the budget overrun in Stage 2 due to adverse site conditions.

The cumulative impact of these events is that Stages 1 and 2 of the Hornsby project cost approximately $42.4 million than it should have in the circumstances around 14 per cent more than what the revised combined Estimated Total Cost for both stages should have been after releasing the $11.0 million in surplus Stage 1 funds, with Stage 2 delayed by around 14 months.

Opportunity for strengthening risk management for adverse site conditions

Major construction projects often experience adverse site conditions which can be difficult to fully detect in advance. However, we found this was a common occurrence in the projects we examined sometimes with significant time and/or budget impacts indicating scope to enhance related risk and cost assessments. Specifically:

  • Hornsby Ku-ring-gai Hospital Redevelopment Stage 2: adverse site conditions during demolition works resulted in an 11-month delay for delivering the medical imaging unit and 14-month delay completing Stage 2 main works including need for additional $15.0 million in funds to cover the resultant budget deficit for the project.
  • Blacktown Mt Druitt Hospital Redevelopment Stage 2: adverse site conditions combined with project complexity delayed completion of the early works by approximately five months. This contributed to the delay in completing the main construction works which occurred around nine months later than planned in the business case.
  • Dubbo Health Service Redevelopment Stages 3 and 4: Health Infrastructure advised adverse site conditions including asbestos containing materials and ground conditions delayed works for the main building with completion forecast for March 2021, around 21 months later than planned in the final business case. This resulted in the need for additional $13.5 million to cover increased construction costs and risks, increasing the Stage 3 and 4 forecast final cost from $150 million to $163.5 million as at February 2020.

These examples indicate a risk the cumulative impact of adverse site conditions may be substantial when measured across both time and Health Infrastructure's full delivery program. They also point to potential for Health Infrastructure to achieve efficiencies and improved outcomes from strengthening its approach to assessing and mitigating the risks from adverse site conditions.

Limited due diligence with prospective contractors risks avoidable delays and costs

Main construction works on Stage 1 of the Dubbo Health Service Redevelopment were completed in October 2015, approximately 13 months later than planned in the final business case. Delays were mainly due to insolvency of the early works contractor resulting in their departure from the project. The ensuing 11-month delay in completing the early works significantly impacted the overall schedule and delivery of main construction works.

The insolvency event was significant as it affected nine separate Health Infrastructure projects – three of which had yet to reach practical completion. It also affected state-funded projects in other sectors. It resulted in the need for additional funding of $11.5 million that was provided in the 2014–15 State Budget increasing the total Stage 1 and 2 budget from $79.8 million to $91.3 million.

Health Infrastructure’s analysis of lessons learned shows it worked actively to mitigate the impacts of the insolvency event across all affected projects. However, it also indicates a risk the lessons were mainly focused on mitigating the impacts after an insolvency event occurred rather than on prevention.

Although Health Infrastructure initially commissioned a financial assessment of the now insolvent early works contractor before engagement, it did not detect any risks of the impending insolvency and instead concluded the contractor was in a strong financial position. However, the contractor became insolvent shortly after commencement approximately seven months later. This indicates a risk of weaknesses in the assessment performed that was not explicitly addressed by the lessons learned.

Delivery of the main construction works were further impacted by disputes with the main works contractor over the scope of works for the renal unit resulting in Health Infrastructure terminating the contract in November 2016 following lengthy negotiations over several months.

The scope of works relating to the renal unit were ultimately transferred to Stages 3 and 4 and were delivered in December 2019, around five years later than originally planned in the business case.

Health Infrastructure advised the delay was ultimately beneficial to the project because the refurbishment works for the renal unit, initially scheduled for Stages 1 and 2, would have been demolished to accommodate the new Western Cancer Centre proposed after Stages 1 and 2 and currently being delivered in parallel with Stages 3 and 4.

Health Infrastructure advised the actual cost of Stages 1 and 2 was $84.7 million against the budget of $91.3 million. The residual $6.6 million relates to the renal works not delivered during Stage 1 and 2 and transferred to Stage 3 and 4.

Health Infrastructure advised the contractual provisions for mitigating insolvency events 'in-flight' are limited highlighting the importance of proactive and effective due diligence prior to engaging contractors for significant construction projects.

Need for a quality framework linked to staff training and capability development

Health Infrastructure's 2017-20 Corporate Plan identifies the development of a quality framework to support delivery of future-focused outcomes as a key organisational priority. Related initiatives within the Corporate Plan describe a framework underpinned by a Quality Committee providing advice on:

  • records management, to meet the requirements of the State Records Act 1998
  • project assurance, to ensure future focused outcomes and enhance Health Infrastructure's Standards, Policies, Procedures and Guidelines, Templates and Design Guidance Notes
  • knowledge management and library services, to promote and leverage from project learnings.

Although Health Infrastructure has some elements of a quality framework it is not yet fully in place. Health Infrastructure advised it had yet to establish the quality framework and related committee described in its Corporate Plan due in part to its focus on responding to the growth of its capital program.

Health Infrastructure's Development and Innovation team has been active in supporting continuous improvement in knowledge and project management including development of business cases. Although useful, these initiatives have relied heavily on leveraging and disseminating insights from Gateway reviews and have not formed part of a systematic quality and continuous improvement framework.

The limited focus on the quality of business cases is reflected in internal performance monitoring and reporting which focuses mainly on tracking the delivery of projects against internal benchmarks, often revised from the baselines in the business case, and expenditure against cashflow targets. There is no evident internal monitoring and/or reporting to the Chief Executive and Board on defined quality metrics linked to business case development and staff capability.

Performance reporting on balanced scorecard metrics has similarly focused mainly on process rather than quality and has been inconsistent in recent years.

Appendix one – Response from agency

Appendix two – About the audit

Appendix three – Performance auditing

Appendix four – Ministry of Health planning tools and guidelines

Appendix five – Streamlined investment decision process for Health Capital Projects

Appendix six – Timeline of business cases and relevant policy guidelines

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #338 - released 12 August 2020

Published

Actions for Their Futures Matter

Their Futures Matter

Justice
Community Services
Education
Health
Whole of Government
Cross-agency collaboration
Internal controls and governance
Management and administration
Project management

The Auditor-General for New South Wales, Margaret Crawford, released a report today examining whether the Department of Communities and Justice had effective governance and partnership arrangements in place to deliver ‘Their Futures Matter’.

Their Futures Matter was intended to place vulnerable children and families at the heart of services, and direct investment to where funding and programs deliver the greatest social and economic benefits. It was a four-year whole-of-government reform in response to the 2015 Tune Review of out-of-home care.

The Auditor-General found that while important foundations were put in place, and new programs trialled, the key objective to establish an evidence-based whole-of-government early intervention approach for vulnerable children and families in NSW was not achieved.

Governance and cross-agency partnership arrangements to deliver Their Futures Matter were found to be ineffective. 'Their Futures Matter lacked mechanisms to secure cross portfolio buy‑in and did not have authority to drive reprioritisation of government investment', the Auditor-General said.

At the reform’s close, the majority of around $380 million in investment funding remains tied to existing agency programs, with limited evidence of their comparative effectiveness or alignment with Their Futures Matter policy objectives. The reform concluded on 30 June 2020 without a strategy or plan in place to achieve its intent.

The Auditor-General made four recommendations to the Department of Communities and Justice, aimed at improving implementation of outstanding objectives, revising governance arrangements, and utilising the new human services data set to address the intent of the reform. However, these recommendations respond only in part to the findings of the audit.

According to the Auditor-General, ‘Cross-portfolio leadership and action is required to ensure a whole-of-government response to delivering the objectives of Their Futures Matter to improve outcomes for vulnerable children, young people and their families in New South Wales.’

Read full report (PDF)

In 2016, the NSW Government launched 'Their Futures Matter' (TFM) - a whole-of-government reform aimed at delivering improved outcomes for vulnerable children, young people and their families. TFM was the government's key response to the 2015 Independent Review of Out of Home Care in New South Wales (known as 'the Tune Review').

The Tune Review found that, despite previous child protection reforms, the out of home care system was ineffective and unsustainable. It highlighted that the system was not client-centred and was failing to improve the long-term outcomes for vulnerable children and families. The review found that the greatest proportion of relevant expenditure was made in out of home care service delivery rather than in evidence-based early intervention strategies to support children and families when vulnerabilities first become evident to government services (such as missed school days or presentations to health services).

The then Department of Family and Community Services (FACS) designed the TFM reform initiatives, in consultation with central and human services agencies. A cross-agency board, senior officers group, and a new unit in the FACS cluster were established to drive the implementation of TFM. In the 2016–17 Budget, the government allocated $190 million over four years (2016–17 to 2019–20) to the reform. This resourced the design and commissioning of evidence-based pilots, data analytics work, staffing for the implementation unit and secretariat support for the board and cross-agency collaboration.

As part of the TFM reform, the Department of Premier and Cabinet, NSW Treasury and partnering agencies (NSW Health, Department of Education and Department of Justice) identified various existing programs that targeted vulnerable children and families (such as the preceding whole-of-government ‘Keep Them Safe’ reform coming to an end in June 2020). Funding for these programs, totalling $381 million in 2019–20, was combined to form a nominal ‘investment pool’. The government intended that the TFM Implementation Board would use this pool to direct and prioritise resource allocation to evidence-based interventions for vulnerable children and families in NSW.

This audit assessed whether TFM had effective governance and partnership arrangements in place to enable an evidence-based early intervention investment approach for vulnerable children and families in NSW. We addressed the audit objective with the following audit questions:

  • Was the TFM reform driven by effective governance arrangements?
  • Was the TFM reform supported by effective cross-agency collaboration?
  • Has the TFM reform generated an evidence base to inform a cross-agency investment approach in the future?

The audit did not seek to assess the outcomes for children, young people and families achieved by TFM programs and projects.

Conclusion

The governance and cross-agency partnership arrangements used to deliver the Their Futures Matter reform were ineffective. Important foundations were put in place, and new programs trialled over the reform's four years. However, an evidence-based whole-of-government early intervention approach for vulnerable children and families in NSW − the key objective of the reform − was not established. The reform concluded in June 2020 without a strategy or plan in place to achieve its intent.

The governance arrangements established for the Their Futures Matter (TFM) reform did not provide sufficient independence, authority and cross-agency clout to deliver on the reform’s intent. This hindered delivery of the reform's key elements, particularly the redirection of funding to evidence-based earlier intervention supports, and limited the impact that TFM could have on driving system change.

TFM increased focus on the contribution that other agencies outside of the former Family and Community Services portfolio could make in responding to the needs of vulnerable children and families, and in reducing the demand costs of related government service delivery. Despite being a whole-of-government reform, TFM lacked mechanisms to secure cross-portfolio buy-in and lacked the powers to drive reprioritisation of government investment in evidence-based and earlier intervention supports across agencies. At the reform’s close, the majority of the reform's investment pool funding remained tied to existing agency programs, with limited evidence of their comparative effectiveness or alignment with Their Futures Matter policy objectives.

TFM began building an evidence base about ‘what works’, including piloting programs and creating a new dataset to identify risk factors for vulnerability and future costs to government. However, this evidence base does not yet comprehensively map how existing services meet needs, identify system duplications or gaps, nor demonstrate which government funded supports and interventions are most effective to make a difference to life outcomes for vulnerable children and families in NSW.
Despite these issues, the need, intent and vision for Their Futures Matter remains relevant and urgent, as issues identified in the Tune Review remain pertinent.

Their Futures Matter (TFM) is a whole-of-government reform to deliver improved outcomes for vulnerable children, young people and their families.

Supported by a cross-agency TFM Board, and the TFM Unit in the then Department of Family and Community Services (FACS), the reform aimed to develop whole-of-government evidence-based early intervention investment approaches for vulnerable children and families in NSW.

Governance refers to the structures, systems and practices that an organisation has in place to:

  • assign decision-making authorities and establish the organisation's strategic direction
  • oversee the delivery of its services, the implementation of its policies, and the monitoring and mitigation of its key risks
  • report on its performance in achieving intended results, and drive ongoing improvements.

We examined whether the TFM reform was driven by effective governance arrangements and cross-agency collaboration.

The reform agenda and timeframe set down for Their Futures Matter (TFM) were ambitious. This chapter assesses whether the TFM Board and TFM Unit had the capability, capacity and clout within government to deliver the reform agenda.

Creating a robust evidence base was important for Their Futures Matter, in order to:

  • identify effective intervention strategies to improve supports and outcomes for vulnerable children and families
  • make efficient use of taxpayer money to assist the maximum number of vulnerable children and families
  • inform the investment-based approach for future funding allocation.

This chapter assesses whether the TFM reform has developed an evidence base to inform cross-agency investment decisions.

Appendix one – Response from agency

Appendix two – TFM governance entities

Appendix three – TFM Human Services Data Set

Appendix four – TFM pilot programs

Appendix five – About the audit

Appendix six – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #337 - released 24 July 2020

Published

Actions for CBD South East Sydney Light Rail: follow-up performance audit

CBD South East Sydney Light Rail: follow-up performance audit

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk
Service delivery

This is a follow-up to the Auditor-General's November 2016 report on the CBD South East Sydney Light Rail project. This follow-up report assessed whether Transport for NSW has updated and consolidated information about project costs and benefits.

The audit found that Transport for NSW has not consistently and accurately updated project costs, limiting the transparency of reporting to the public.

The Auditor-General reports that the total cost of the project will exceed $3.1 billion, which is above the revised cost of $2.9 billion published in November 2019. $153.84 million of additional costs are due to omitted costs for early enabling works, the small business assistance package and financing costs attributable to project delays.

The report makes four recommendations to Transport for NSW to publicly report on the final project cost, the updated expected project benefits, the benefits achieved in the first year of operations and the average weekly journey times.

Read full report (PDF)

The CBD and South East Light Rail is a 12 km light rail network for Sydney. It extends from Circular Quay along George Street to Central Station, through Surry Hills to Moore Park, then to Kensington and Kingsford via Anzac Parade and Randwick via Alison Road and High Street.

Transport for NSW (TfNSW) is responsible for planning, procuring and delivering the Central Business District and South East Light Rail (CSELR) project. In December 2014, TfNSW entered into a public private partnership with ALTRAC Light Rail as the operating company (OpCo) responsible for delivering, operating and maintaining the CSELR. OpCo engaged Alstom and Acciona, who together form its Design and Construct Contractor (D&C).

On 14 December 2019, passenger services started on the line between Circular Quay and Randwick. Passenger services on the line between Circular Quay and Kingsford commenced on 3 April 2020.

In November 2016, the Auditor-General published a performance audit report on the CSELR project. The audit found that TfNSW would deliver the CSELR at a higher cost with lower benefits than in the approved business case, and recommended that TfNSW update and consolidate information about project costs and benefits and ensure the information is readily accessible to the public.

In November 2018, the Public Accounts Committee (PAC) examined TfNSW's actions taken in response to our 2016 performance audit report on the CSELR project. The PAC recommended that the Auditor-General consider undertaking a follow-up audit on the CSELR project. The purpose of this follow-up performance audit is to assess whether TfNSW has effectively updated and consolidated information about project costs and benefits for the CSELR project.

Conclusion

Transport for NSW has not consistently and accurately updated CSLER project costs, limiting the transparency of reporting to the public. In line with the NSW Government Benefits Realisation Management Framework, TfNSW intends to measure benefits after the project is completed and has not updated the expected project benefits since April 2015.

Between February 2015 and December 2019, Transport for NSW (TfNSW) regularly updated capital expenditure costs for the CSELR in internal monthly financial performance and risk reports. These reports did not include all the costs incurred by TfNSW to manage and commission the CSELR project.

Omitted costs of $153.84 million for early enabling works, the small business assistance package and financing costs attributable to project delays will bring the current estimated total cost of the CSELR project to $3.147 billion.

From February 2015, TfNSW did not regularly provide the financial performance and risk reports to key CSELR project governance bodies. TfNSW publishes information on project costs and benefits on the Sydney Light Rail website. However, the information on project costs has not always been accurate or current.

TfNSW is working with OpCo partners to deliver the expected journey time benefits. A key benefit defined in the business plan was that bus services would be reduced owing to transfer of demand to the light rail - entailing a saving. However, TfNSW reports that the full expected benefit of changes to bus services will not be realised due to bus patronage increasing above forecasted levels.

Appendix one – Response from agency

Appendix two – Governance and reporting arrangements for the CSELR

Appendix three – 2018 CSELR governance changes

Appendix four – About the audit

Appendix five – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #335 - released 11 June 2020

Published

Actions for Funding enhancements for police technology

Funding enhancements for police technology

Justice
Community Services
Information technology
Management and administration
Procurement
Project management

This report focuses on how the NSW Police Force managed a $100 million program to acquire new technology. The program invested in technologies intended to make police work safer and quicker. These included body-worn video (BWV) cameras, smart phone devices, mobile fingerprint scanners and hand-held drug testing devices.

The audit found that while the NSW Police Force mostly managed the ‘Policing for Tomorrow’ program effectively, investment decision making could be improved in the future. The NSW Police Force missed an opportunity to take a whole-of-organisation approach to identify capability gaps and target the acquired technologies to plug these.

The NSW Police Force has processes in place to monitor the benefits of some of the larger technology, but it does not do this consistently for all procured technology. It could not demonstrate that smaller projects are improving the efficiency or effectiveness of policing.

The audit also found that the NSW Police Force does not routinely engage with external stakeholders on the use or impacts of new technology that changes how officers interact with the public, noting that this will not always be possible for particularly sensitive procurements that involve covert technologies or methodologies.

The Auditor-General made three recommendations to guide improvement of NSW Police Force ICT procurement, benefits management and stakeholder engagement processes.

Read full report (PDF)

Ahead of the March 2015 election, the NSW Government announced a $100 million Policing for Tomorrow fund for the NSW Police Force to acquire technology intended to make police work safer and quicker. The announcement committed the NSW Police Force to several investment priorities, including body-worn video (BWV) cameras, smart phone devices (MobiPOL), mobile fingerprint scanners and hand-held drug testing devices. Otherwise, the NSW Police Force was allowed flexibility in identifying and resourcing suitable projects.

This audit assessed whether the Policing for Tomorrow fund was effectively managed to improve policing in New South Wales. We addressed the audit objective with the following audit questions:

  • Did the NSW Police Force efficiently and effectively identify, acquire, implement and maintain technology resourced by the fund?
  • Did the NSW Police Force establish effective governance arrangements for administering the fund, and for monitoring expected benefits and unintended consequences?
  • Did technology implemented under the fund improve the efficiency and effectiveness of policing in New South Wales?

Conclusion

The NSW Police Force's management of the Policing for Tomorrow fund was mostly effective. There are measures in place to assess the impact of the technologies on the efficiency and effectiveness of policing in NSW. However, these measures are not in place for all technologies funded by Policing for Tomorrow. A strategic whole-of-organisation approach to identifying and filling technology capability gaps may have assisted in better targeting funds and managing expected benefits.

The NSW Police Force identified, acquired, implemented and maintained a range of technologies resourced by the fund in an efficient and effective way. The election announcement committed the NSW Police Force to four specific projects which made up over three quarters of the fund value. Investment decisions for remaining funds were driven by the availability of funding and individual technology requirements rather than targeting improved policing outcomes and the capability necessary to achieve these.

The NSW Police Force missed an opportunity to take a whole-of-organisation approach to selecting technology projects for the remainder of the funds where it had discretion. This may have included considering less obvious back office technology or making different investment decisions driven by gaps in the agency's technology capabilities.

The NSW Police Force used effective governance arrangements for administering the Policing for Tomorrow fund, including using its existing ICT Executive Board. The NSW Police Force has adequate processes in place to drive benefits and monitor the impact of technology on the efficiency and effectiveness of policing for the larger projects funded by Policing for Tomorrow. Further work is required to ensure this for smaller projects.

The NSW Police Force tends to consider only impacts on the organisation in managing benefits and identifying unintended consequences. It does not routinely engage proactively with stakeholders, including partner criminal justice agencies and members of the community, on new technology that changes how police interact with the public.

We examined how effectively the NSW Police Force governed the Policing for Tomorrow fund, to ensure that key accountability and decision-making arrangements were in place to direct the $100 million spend to appropriate technologies. We also assessed how the NSW Police Force acquired, implemented and maintained technology funded by Policing for Tomorrow to determine the effectiveness of the relevant asset management.

The Policing for Tomorrow election commitment aimed to invest in technology to ‘make police work safer and quicker – meaning more time on the street combatting crime’. We assessed whether the NSW Police Force ensured that funded technologies have improved policing efficiency and effectiveness. We did not seek to independently assure the benefits or outcomes resulting from the technologies.

Appendix one – Response from agency

Appendix two – Policing for Tomorrow projects and expenditure

Appendix three – About the audit

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #334 - released 2 June 2020

Published

Actions for Train station crowding

Train station crowding

Transport
Management and administration
Risk
Service delivery
Workforce and capability

This report focuses on how Transport for NSW and Sydney Trains manage crowding at selected metropolitan train stations.

The audit found that while Sydney Trains has identified platform crowding as a key strategic risk, it does not have an overarching strategy to manage crowding in the short to medium term. Sydney Trains 'do not have sufficient oversight to know if crowding is being effectively managed’, the Auditor-General said.

Sydney Trains' operational response to crowding involves restricting customer access to platforms or station entries before crowding reaches unsafe levels or when it impacts on-time running. Assuming rail patronage increases, it is likely that Sydney Trains will restrict more customers from accessing platforms or station entries, causing customer delay. ‘Restricting customer access to platforms or station entries is not a sustainable approach to manage station crowding’, said the Auditor-General.

The Auditor-General made seven recommendations to improve Transport for NSW and Sydney Trains' management of station crowding. Transport for NSW have accepted these recommendations on behalf of the Transport cluster.

Public transport patronage has been impacted by COVID-19. This audit was conducted before these impacts occurred.

Read full report (PDF)

Sydney Trains patronage has increased by close to 34 per cent over the last five years, and Transport for NSW (TfNSW) expects the growth in patronage to continue over the next 30 years. As patronage increases there are more passengers entering and exiting stations, moving within stations to change services, and waiting on platforms. As a result, some Sydney metropolitan train stations are becoming increasingly crowded.

There are three main causes of station crowding:

  • patronage growth exceeding the current capacity limits of the rail network
  • service disruptions
  • special events.

Crowds can inhibit movement, cause discomfort and can lead to increased health and safety risks to customers. In the context of a train service, unmanaged crowds can affect service operation as trains spend longer at platforms waiting for customers to alight and board services which can cause service delays. Crowding can also prevent customers from accessing services.

Our 2017 performance audit, ‘Passenger Rail Punctuality’, found that rail agencies would find it hard to maintain train punctuality after 2019 unless they significantly increased the capacity of the network to carry trains and people. TfNSW and Sydney Trains have plans to improve the network to move more passengers. These plans are set out in strategies such as More Trains, More Services and in the continued implementation of new infrastructure such as the Sydney Metro. Since 2017, TfNSW and Sydney Trains have introduced 1,500 more weekly services to increase capacity. Additional network capacity improvements are in progress for delivery from 2022 onwards.

In the meantime, TfNSW and Sydney Trains need to use other ways of managing crowding at train stations until increased capacity comes on line.

This audit examined how effectively TfNSW and Sydney Trains are managing crowding at selected metropolitan train stations in the short and medium term. In doing so, the audit examined how TfNSW and Sydney Trains know whether there is a crowding problem at stations and how they manage that crowding.

TfNSW is the lead agency for transport in NSW. TfNSW is responsible for setting the standard working timetable that Sydney Trains must implement. Sydney Trains is responsible for operating and maintaining the Sydney metropolitan heavy rail passenger service. This includes operating, staffing and maintaining most metropolitan stations. Sydney Trains’ overall responsibility is to run a safe rail network to timetable.

Conclusion

Sydney Trains has identified platform crowding as a key strategic risk, but does not have an overarching strategy to manage crowding in the short to medium term. TfNSW and Sydney Trains devolve responsibility for managing crowding at stations to Customer Area Managers, but do not have sufficient oversight to know if crowding is being effectively managed. TfNSW is delivering a program to influence demand for transport in key precincts but the effectiveness of this program and its impact on station crowding is unclear as Transport for NSW has not evaluated the outcomes of the program.

TfNSW and Sydney Trains do not directly measure or collect data on station crowding. Data and observation on dwell time, which is the time a train waits at a platform for customers to get on and off trains, inform the development of operational approaches to manage crowding at stations. Sydney Trains has KPIs on reliability, punctuality and customer experience and use these to indirectly assess the impact of station crowding. TfNSW and Sydney Trains only formally assess station crowding as part of planning for major projects, developments or events.

Sydney Trains devolve responsibility for crowd management to Customer Area Managers, who rely on frontline Sydney Trains staff to understand how crowding affects individual stations. Station staff at identified key metropolitan train stations have developed customer management plans (also known as crowd management plans). However, Sydney Trains does not have policies to support the creation, monitoring and evaluation of these plans and does not systematically collect data on when station staff activate crowding interventions under these plans.

Sydney Trains stated focus is on providing a safe and reliable rail service. As such, management of station crowding is a by-product of its strategies to manage customer safety and ensure on-time running of services. Sydney Trains' operational response to crowding involves restricting customer access to platforms or stations before crowding reaches unsafe levels, or when it impacts on-time running. As rail patronage increases, it is likely that Sydney Trains will need to increase its use of interventions to manage crowding. As Sydney Trains restrict more customers from accessing platforms or station entries, it is likely these customers will experience delays caused by these interventions.

Since 2015, TfNSW has been delivering the 'Travel Choices' program which aims to influence customer behaviour and to manage the demand for public transport services in key precincts. TfNSW is unable to provide data demonstrating the overall effectiveness of this program and the impact the program has on distributing public transport usage out of peak AM and PM times. TfNSW and Sydney Trains continue to explore initiatives to specifically address crowd management.

Conclusion

TfNSW and Sydney Trains do not directly measure or collect data on station crowding. There are no key performance indicators directly related to station crowding. Sydney Trains uses performance indicators on reliability, punctuality and customer experience to indirectly assess the impact of station crowding. Sydney Trains does not have a routine process for identifying whether crowding contributed to minor safety incidents. TfNSW and Sydney Trains formally assess station crowding as part of planning for major projects, developments or events.

 

Conclusion

Sydney Trains has identified platform crowding as a strategic risk but does not have an overarching strategy to manage station crowding. Sydney Trains' stated focus is on providing a safe and reliable rail service. As such, management of station crowding is a by-product of its strategies to manage customer safety and ensure on-time running of services.

Sydney Trains devolve responsibility for managing crowding at stations to Customer Area Managers but does not have sufficient oversight to know that station crowding is effectively managed. Sydney Trains does not have policies to support the creation, monitoring or evaluation of crowd management plans at key metropolitan train stations. The use of crowding interventions is likely to increase due to increasing patronage, causing more customers to experience delays directly caused by these activities.

TfNSW and Sydney Trains have developed interventions to influence customer behaviour and to manage the demand for public transport services but are yet to evaluate these interventions. As such, their impact on managing station crowding is unclear.

Appendix one – Response from agency

Appendix two – Sydney rail network

Appendix three – Rail services contract

Appendix four – Crowding pedestrian modelling

Appendix five – Airport Link stations case study

Appendix six – About the audit

Appendix seven – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #333 - released 30 April 2020

 

Published

Actions for Integrity of data in the Births, Deaths and Marriages Register

Integrity of data in the Births, Deaths and Marriages Register

Justice
Premier and Cabinet
Whole of Government
Cyber security
Fraud
Information technology
Internal controls and governance
Management and administration

This report outlines whether the Department of Customer Service (the department) has effective controls in place to ensure the integrity of data in the Births, Deaths and Marriages Register (the register), and to prevent unauthorised access and misuse.

The audit found that the department has processes in place to ensure that the information entered in the register is accurate and that any changes to it are validated. Although there are controls in place to prevent and detect unauthorised access to, and activity in the register, there were significant gaps in these controls. Addressing these gaps is necessary to ensure the integrity of information in the register.

The Auditor-General made nine recommendations to the department, aimed at strengthening controls to prevent and detect unauthorised access to, and activity in the register. These included increased monitoring of individuals who have access to the register and strengthening security controls around the databases that contain the information in the register.

The NSW Registry of Births Deaths and Marriages is responsible for maintaining registers of births, deaths and marriages in New South Wales as well as registering adoptions, changes of names, changes of sex and relationships. Maintaining the integrity of this information is important as it is used to confirm people’s identity and unauthorised access to it can lead to fraud or identity theft.

Read full report (PDF)

The NSW Registry of Births Deaths and Marriages (BD&M) is responsible for maintaining registers of births, deaths and marriages in New South Wales. BD&M is also responsible for registering adoptions, changes of name, changes of sex and relationships. These records are collectively referred to as 'the Register'. The Births, Deaths and Marriages Registration Act 1995 (the BD&M Act) makes the Registrar (the head of BD&M) responsible for maintaining the integrity of the Register and preventing fraud associated with the Register. Maintaining the integrity of the information held in the Register is important as it is used to confirm people's identity. Unauthorised access to, or misuse of the information in the Register can lead to fraud or identity theft. For these reasons it is important that there are sufficient controls in place to protect the information.

BD&M staff access, add to and amend the Register through the LifeLink application. While BD&M is part of the Department of Customer Service, the Department of Communities and Justice (DCJ) manages the databases that contain the Register and sit behind LifeLink and is responsible for the security of these databases.

This audit assessed whether BD&M has effective controls in place to ensure the integrity of data in the Births, Deaths and Marriages Register, and to prevent unauthorised access and misuse. It addressed the following:

  • Are relevant process and IT controls in place and effective to ensure the integrity of data in the Register and the authenticity of records and documents?
  • Are security controls in place and effective to prevent unauthorised access to, and modification of, data in the Register?

Conclusion

BD&M has processes and controls in place to ensure that the information entered in the Register is accurate and that amendments to the Register are validated. BD&M also has controls in place to prevent and detect unauthorised access to, and activity in the Register. However, there are significant gaps in these controls. Addressing these gaps is necessary to ensure the integrity of the information in the Register.

BD&M has detailed procedures for all registrations and amendments to the Register, which include processes for entering, assessing and checking the validity and adequacy of source documents. Where BD&M staff have directly input all the data and for amendments to the Register, a second person is required to check all information that has been input before an event can be registered or an amendment can be made. BD&M carries out regular internal audits of all registration processes to check whether procedures are being followed and to address non-compliance where required.

BD&M authorises access to the Register and carries out regular access reviews to ensure that users are current and have the appropriate level of access. There are audit trails of all user activity, but BD&M does not routinely monitor these. At the time of the audit, BD&M also did not monitor activity by privileged users who could make unauthorised changes to the Register. Not monitoring this activity created a risk that unauthorised activity in the Register would not be detected.

BD&M has no direct oversight of the database environment which houses the Register and relies on DCJ's management of a third-party vendor to provide the assurance it needs over database security. The vendor operates an Information Security Management System that complies with international standards, but neither BD&M nor DCJ has undertaken independent assurance of the effectiveness of the vendor's IT controls.

Appendix one – Response from agency

Appendix two – About the audit

Appendix three – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #330 - released 7 April 2020.

Published

Actions for Supporting the District Criminal Court

Supporting the District Criminal Court

Justice
Community Services
Information technology
Internal controls and governance
Project management

The Auditor-General for New South Wales, Margaret Crawford, released a report today on whether the Department of Communities and Justice (the department) effectively supports the efficient operation of the District Criminal Court system.

The audit found that in the provision of data and technology services, the department is not effectively supporting the efficient operation of the District Criminal Court system. The department has insufficient controls in place to ensure that data in the system is always accurate.

The department is also using outdated technology and could improve its delivery of technical support to courts.

The audit also assessed the implementation of the Early Appropriate Guilty Pleas reform. This reform aims to improve court efficiency by having more cases resolved earlier with a guilty plea in the Local Court. The audit found that the department effectively governed the implementation of the reform but is not measuring achievement of expected benefits, placing the objectives of the reform at risk.

The Auditor-General made seven recommendations to the department, aimed at improving the controls around courts data, reporting on key performance indicators, improving regional technical support and measuring the success of the Early Appropriate Guilty Pleas reform. 

The District Court is the intermediate court in the New South Wales court system. It hears most serious criminal matters, except murder, treason and piracy. The Department of Communities and Justice (the Department) provides support to the District Court in a variety of ways. For example, it provides security services, library services and front-desk services. This audit examined three forms of support that the Department provides to the District Court:

  • data collection, reporting and analysis - the Department collects data from cases in its case management system, JusticeLink, based on the orders Judges make in court and court papers
  • technology - the Department provides technology to courts across New South Wales, as well as technical support for this technology
  • policy - the Department is responsible for proposing and implementing policy reforms.

Recent years have seen a worsening of District Court efficiency, as measured in the Productivity Commission's Report on Government Services (RoGS). Efficiency in the court system is typically measured through timeliness of case completion. There is evidence that timeliness has worsened. For example, the median time from arrest to finalisation of a case in the District Court increased from 420 days in 2012–13 to 541 days in 2017–18.

As a result, the government has announced a range of measures to improve court performance, particularly in the District Court. These measures included the Early Appropriate Guilty Pleas (EAGP) reform. One of the objectives of EAGP is to improve court efficiency, which would be achieved by having more cases resolve with a guilty plea in the Local Court.

This audit assessed whether the Department of Communities and Justice effectively supports the efficient operation of the District Criminal Court system. We assessed this with the following lines of inquiry:

  • Does the Department effectively collect, analyse and report performance information relevant to court efficiency?
  • Does the Department effectively provide technology to support the efficient working of the courts?
  • Does the Department have effective plans, governance and monitoring for the Early Appropriate Guilty Pleas reform?

The audit did not consider other support functions provided by the Department. Further information on the audit, including detailed audit criteria, may be found in Appendix two.

Conclusion
In the provision of data and technology services, the Department is not effectively supporting the efficient operation of the District Criminal Court system. The Department has insufficient controls in place to ensure accurate data in the District Criminal Court system. The Department is also using outdated technology in significant numbers and could improve its delivery of technical support to meet agreed targets.
The Department effectively governed the implementation of the Early Appropriate Guilty Pleas reform. However, it is not ensuring that the benefits stated in the business case are being achieved, placing its objectives at risk.
The impact of inaccurate court data can be severe, and the Department does not have sufficient controls in place to ensure that its court data is accurate. Recent Bureau of Crime Statistics and Research reviews have identified data inaccuracies, and this demonstrates the Department needs strong controls in place to ensure that its court data is accurate.
The Department does not have a policy for data quality and has not formally assigned responsibility for data quality to any individual or branch. The Department also does not have a data dictionary outlining all the fields in its case management system. While the Department validates the highest risk items, such as warrants, to ensure that they are accurate, most data is not validated. The Department has recently commenced setting up a data unit for the Courts, Tribunals and Service Delivery branch. It is proposed that this unit will address most of the identified shortcomings.
The Department did not provide timely technical support to the court system in 2017 and is using outdated technology in significant numbers. The Digital and Technology Services branch of the Department had agreed a Service Level Agreement with the rest of the Department, outlining the expected speed of technical support responses. The branch did not meet response times in 2017. Performance improved in 2018, though DTS fell short of its targets for critical and moderate priority incidents. Critical incidents are particularly important to deal with in a timely manner as they include incidents which may delay a court sitting.
Requests for technical support rose significantly in 2018 compared to 2017, which may be related to the number of outdated pieces of technology. As at April 2019, the whole court system had 2,389 laptops or desktop computers outside their warranty period. The Department was also using other outdated technology. Outdated technology is more prone to failure and continuing to use it poses a risk of court delays.
The Department is not measuring all the expected benefits from the Early Appropriate Guilty Pleas reform, placing the objectives of the program at risk. The Early Appropriate Guilty Pleas business case outlined nine expected benefits from the reform. The Department is not measuring one of these benefits and is not measuring the economic benefits of a further five business case benefits. Not measuring the impact of the reform means that the Department does not know if it is achieving its objectives and if the reform had the desired impact.

The Department is responsible for providing technology to the courts, which can improve the efficiency of court operations by making them faster and cheaper. The Department is also responsible for providing technical support to courtrooms and registries. It is important that technical support is provided in a timely manner because some technical incidents can delay court sittings and thus impact on court efficiency. A 2013 Organisation for Economic Co‑operation and Development report emphasised the importance of technology and digitisation for reducing trial length.

While the Department may provide technology to the courts, they are not responsible for deciding when, how or if the technology is used in the courtroom.

The Department is using a significant amount of outdated technology, risking court delays

As of April 2019, the whole court system had 2,389 laptops or desktop computers out of warranty, 56.0 per cent of the court system's fleet. The court system also had 786 printing devices out of their normal warranty period, 75.1 per cent of all printers in use. The Department also advised that many of its court audio transcription machines are out of date. These machines must be running for the court to sit and thus it is critical that they are maintained to a high degree. The then Department of Justice estimated the cost of aligning its hardware across the whole Department with desired levels at $14.0 million per year for three years. Figures for the court system were not calculated but they are likely to be a significant portion of this figure.

Using outdated technology poses a risk to the court system as older equipment may be more likely to break down, potentially delaying courts or slowing down court services. In the court system throughout 2018, hardware made up 30.8 per cent of all critical incidents reported to technical support and 41.9 per cent of all high priority incidents. In addition, 16.2 per cent of all reported issues related to printing devices or printing.

From 2017 to 2018, technical support incidents from courts or court services increased. There were 4,379 technical support incidents in 2017, which increased significantly to 9,186 in 2018. The Department advised that some outside factors may have contributed to this increase. The Department was rolling out its new incident recording system throughout 2017, meaning that there would be an under‑reporting of incidents in that year. The Department also advised that throughout 2018 there was a greater focus on ensuring that every issue was logged, which had not previously been the case. Despite these factors, the use of outdated technology has likely increased the risk of technology breakages and may have contributed to the increase in requests for technical support.

Refreshing technology on a regular basis would reduce the risk of hardware failures and ensure that equipment is covered by warranty.

The Department did not meet all court technical support targets in 2017 and 2018

The Digital and Technology Services branch (DTS) was responsible for providing technical support to the courts and the Courts and Tribunal Services branch prior to July 2019. DTS provided technical support in line with a Service Level Agreement (SLA) with the Department. In 2017, DTS did not provide this support in a timely manner. Performance improved in 2018, though DTS fell short of its targets for critical and moderate priority incidents. Exhibit 7 outlines DTS' targets under the SLA.

Exhibit 7: Digital and Technology Services' Service Level Agreement
Priority Target resolution time Target percentage in time (%)
1. Critical 4 hours 80
2. High 1 day 80
3. Moderate 3 days 85
4. Low 5 days 85
Source: Department of Communities and Justice, 2019.

Critical incidents are particularly important for the Department to deal with in a timely manner because these include incidents which may delay a court sitting until resolved or incidents which impact on large numbers of staff. Some of the critical incidents raised with DTS specifically stated that they were delaying a court sitting, often due to transcription machines not working. High priority incidents include those where there is some impact on the functions of the business, which may in turn affect the efficiency of the court system. High priority incidents also include those directly impacting on members of the Judiciary. 

This audit examined DTS' performance against its SLA in the 2017 and 2018 calendar years across the whole court system, not just the District Court. The total number of incidents, as well as critical and high priority incidents, can be seen in Exhibit 8.

Exhibit 8: Number of incidents in 2017 and 2018
Priority 2017 2018
All 4,379 9,186
1. Critical 48 91
2. High 128 315
Source: Audit Office of NSW analysis of Department of Communities and Justice data, 2019.

The Department's results against its SLA in 2017 and 2018 are shown in Exhibit 9.

The Early Appropriate Guilty Pleas (EAGP) reform consists of five main elements:

  • early disclosure of evidence from NSW Police Force to the prosecution and defence
  • early certification of what the accused is going to be charged with to minimise changes
  • mandatory criminal case conferencing between the prosecutor and accused's representation
  • changes to Local Court case management
  • more structured sentence discounts.

More detailed descriptions of each of these changes can be found in the Introduction. These reform elements are anticipated to have three key effects:

  • accelerate the timing of guilty pleas
  • increase the overall proportion of guilty pleas
  • decrease the average length of contested trials.

Improving District Court efficiency is one of the stated aims of EAGP, which would be achieved by having more cases resolve in the Local Court and having fewer defendants plead guilty on the day of their trial in the District Court. The reform commenced in April 2018 and it is too early to state the impact of this reform on District Court efficiency.

The Department is responsible for delivering EAGP in conjunction with other justice sector agencies. They participated in the Steering Committee and the Working Groups, as well as providing the Project Management Office (PMO).

The Department is not measuring the economic benefits stated in the EAGP business case

The business case for EAGP listed nine quantifiable benefits which were expected to be derived from the achievement of the three key effects listed above. The Department is not measuring one of these benefits and is not measuring the economic benefits for five more, as shown in Exhibit 12.

Benefit Economic benefit (over ten years) Being measured?
Accelerated timing of guilty pleas $54.6m yellow circle with minus in the center
Increased guilty plea rate $90.7m yellow circle with minus in the center
Decreased average trial length $27.5m yellow circle with minus in the center
A reduction in the delay of indictable matters proceeding to trial N/A check circle mauve
Increase the number of finalised matters per annum N/A check circle mauve
Reduction of the current backlog of criminal trials in the District Court N/A check circle mauve
Reduction in bed pressure on the correction system due to reduced
average time in custody
$13.7m Exclamation circle red
Productivity improvements due to reduction in wasted effort $53.3m yellow circle with minus in the center
Bankable cost savings due to jury empanelment avoided $2.5m yellow circle with minus in the center

 

Exhibit 12: The Department's measurement of quantifiable benefits
Key check circle mauve Measuring yellow circle with minus in the center Not measuring economic benefit Exclamation circle red Not measuring
Source: Audit Office of NSW analysis.

While it is too early to comment on the overall impact of EAGP, better practice in benefits realisation involves an ongoing effort to monitor benefits to ensure that the reform is on target and determine whether any corrective action is needed.

The Department is measuring the number of finalised matters per annum and while the Department is not measuring the reduction in the backlog as part of this program, this measure is reported as part of the Department's internal reporting framework. The Department is not monitoring the reduction in delay of indictable matters proceeding to trial directly as part of this reform, but this does form part of the monthly Operational Performance Report which the Department sends to the EAGP Steering Committee.

The Department is not monitoring any of the economic benefits stated in the business case. These economic benefits are a mixture of bankable savings and productivity improvements. This amounts to a total of $242.3 million over ten years which was listed in the business case as potential economic benefits from the implementation of this reform against the total cost of $206.9 million over ten years. The Department is collecting proxy indicators which would assist in these calculations for several indicators, but it is not actively monitoring these savings. For example, the Department is monitoring average trial length, but is not using this information to calculate economic benefits derived from changes in trial length.

The Department is also not collecting information related to the average length of custody as part of this program. This means that it is unable to determine if EAGP is putting less pressure on the correctives system and it is not possible for the Department to calculate the savings from this particular benefit.

While stakeholders are optimistic about the impact of EAGP, not measuring the expected benefits stated in the business case means that the Department does not know if the reform is achieving what it was designed to achieve. Further, the Department does not know if it must take corrective action to ensure that the program achieves the stated benefits. These two things put the overall program benefits at risk.

The Department has not assigned responsibility for the realisation of each benefit, potentially risking the success of the program

The Department has not assigned responsibility for the realisation of each benefit stated in the business case. The Department holds the Steering Committee responsible for the realisation of all benefits. Benefits realisation is the process which ensures that the agency reaches benefits as stated in the business case. Assigning responsibility for benefits realisation to the Steering Committee rather than individuals is not in line with good practice.

Good practice benefits realisation involves assigning responsibility for the realisation of each benefit to an individual at the business unit level. This ensures there is a single point of accountability for each part of the program with knowledge of the benefit and the ability to take corrective action if it looks like that benefit will not be realised. This responsibility should sit at the operational level where detailed action can most easily be undertaken. The role of a Steering Committee in benefits realisation is to ensure that responsible parties are monitoring their benefits and taking appropriate corrective action.

The Department advised that it believes the Steering Committee should have responsibility for the realisation of benefits due to the difficulty of attributing the achievement of each benefit to one part of the reform alone. Given the Steering Committee meets only quarterly, it is not well placed to take action in response to variances in performance.

A BOCSAR evaluation is planned, however data errors make some of the information unreliable

BOCSAR are planning to undertake an overall evaluation of EAGP which is planned for release in 2021. Undertaking this evaluation will require high quality data to gain an understanding of the drivers of the reform. However, data captured throughout the first year of EAGP has proven unreliable, which may reduce the usefulness of BOCSAR's evaluation. These data issues were discussed in Exhibit 5 in Chapter 2, above. Access to accurate data is vital for conducting any program evaluation and inaccurate data raises the risk that the BOCSAR evaluation will not be able to provide an accurate evaluation of the impact of EAGP.

In addition to the BOCSAR evaluation, the Department had plans for a series of 'snapshot' evaluations for some of the key elements of the reform to ensure that they were operating effectively. These were initially delayed due to an efficiency dividend which affected EAGP. In August 2019, the Department commissioned a review of the implementation of several key success factors for EAGP.

There was clear governance throughout the implementation of EAGP

The implementation stage of EAGP had clear governance, lines of authority and communication. The Steering Committee, each Working Group and each agency had clear roles and responsibilities, and these were organised through a Project Management Office (PMO) provided by the former Department of Justice. The governance structure throughout the implementation phase can be seen at Exhibit 13.

The Steering Committee was established in December 2016 and met regularly from March 2017. It comprised senior members of key government agencies, as well as the Chief Judge and the Chief Magistrate for most of the duration of the implementation period. The Steering Committee met at least monthly throughout the life of the program. The Steering Committee was responsible for overseeing the delivery of EAGP and making key decisions relating to implementation, including spending decisions. The Chief Judge and the Chief Magistrate abstained from financial decisions. The Steering Committee updated the governance and membership of the Steering Committee as appropriate throughout the life of the reform.

Appendix one – Response from agency
 
Appendix two – About the audit 

Appendix three – Performance auditing 

 

Copyright Notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary Reference: Report number #329 - released 18 December 2019

Published

Actions for Education 2019

Education 2019

Education
Financial reporting
Information technology
Internal controls and governance
Management and administration
Shared services and collaboration
Workforce and capability

This report focuses on key observations and findings from the most recent financial audits of agencies in the Education cluster. From 1 July 2019, the Technical and Further Education Commission, the NSW Skills Board and the functions and activities associated with vocational training and skills form part of the Education cluster.

Unqualified audit opinions were issued for all cluster agencies’ financial statements. However, internal control deficiencies were identified across the cluster agencies, including 14 findings that were repeated from the previous year. Control deficiencies were also identified in a sample of the state’s 2,200 schools. Schools did not always apply the guidance in the Department of Education's ‘Finance in Schools Handbook’, resulting in control weaknesses in key areas such as governance, cash management and procurement.

'In addition, we continue to observe inconsistencies in the employee leave data reported from the Department of Education’s payroll system, which impact the reliability of estimates of the Department’s liability for employee benefits. The robustness of the Department's quality assurance over leave liability data should be improved', the Auditor-General said.

Download the Education 2019 report (PDF)

This report analyses the results of our audits of financial statements of entities within the Education cluster for the year ended 30 June 2019. The table below summarises our key observations.

1. Machinery of Government changes

The Education cluster has expanded From 1 July 2019, the Technical and Further Education Commission, the NSW Skills Board and the functions and activities associated with vocational training and skills now form part of the Education cluster.

2. Financial reporting

Audit opinions

Unqualified audit opinions were issued for all cluster agencies' 30 June 2019 financial statements audits.

The number of corrections to disclosures in the financial statements, which increased this year, could have been reduced by a more thorough quality assurance over the information underpinning the financial statements.

Recommendation: Cluster agencies should improve their quality assurance processes for financial reporting to improve the accuracy of financial statements presented for audit.

Preparedness for new accounting standards

Agencies will implement four new accounting standards shortly. Three are effective from 1 July 2019 and the fourth is effective from 1 July 2020. Cluster agencies needed to do more work on their impact assessments to better prepare for their implementation from 1 July 2019.

Recommendation: Cluster agencies should finalise their plans to implement the new accounting standards as soon as possible.

Timeliness of financial reporting

All cluster agencies met the statutory deadline for completing early close procedures and submitting their financial statements for audit.

The Department of Education (the Department) delays tabling its financial statements in parliament so it can report its operational outcomes, which are aligned to the calendar year, in a single report. This reduces transparency over the Department's financial statements as they are tabled more than ten months after the end of the financial year.

Recommendation: The Department should table its financial statements in parliament earlier, in line with other NSW Government agencies.

Inconsistencies in the employee leave data We continue to observe inconsistencies in the employee leave data reported from the Department’s payroll system, which impacts the reliability of estimates of the Department's liability for employee benefits. The robustness of the Department's quality assurance over leave liability data should be improved.

3. Audit observations

Internal control deficiencies

We identified 55 internal control issues, including 14 findings that were repeated from the previous year.

Issues were identified with user access administration, segregation of duties in the Department's key application system and timely preparation and review of key reconciliations.

Recommendation: Cluster agencies should prioritise and action recommendations to address internal control weaknesses.

Schools review 2018

Our review of a selection of NSW schools identified deficiencies in how they applied the Department of Education's ‘Finance in Schools Handbook’, resulting in control weaknesses in key areas such as governance, cash management and procurement.

Recommendation: The Department should ensure all schools apply the Department’s ‘Finance in Schools Handbook’ as it is a key internal control.

 

This report provides parliament and other users of the Education cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

This cluster was significantly impacted by the Machinery of Government changes. The Technical and Further Education Commission and the NSW Skills Board, part of the former Industry cluster, were transferred on 1 July 2019. This report focuses on agencies in the Education cluster from 1 July 2019. Please refer to the section on Machinery of Government changes for more details.

Machinery of Government refers to how the government organises the structures and functions of the public service. Machinery of Government changes are where the government reorganises these structures and functions, and the changes are given effect by Administrative Arrangements Orders.

Section highlights

The 2019 Machinery of Government changes significantly impacted the Education cluster. From 1 July 2019, the functions and activities associated with the administration of legislation allocated to the Minister for Skills and Tertiary Education were transferred from the former Industry cluster to the Education cluster. Aboriginal Affairs NSW was transferred from the Department of Education (the Department) to the Department of Premier and Cabinet.

The Department is the principal agency in the cluster. The Machinery of Government changes bring new responsibilities, risks and challenges to the cluster.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Education cluster for 2019.

Section highlights

Unqualified audit opinions were issued on the financial statements of cluster agencies. However, a more thorough quality review process of the financial statements submitted for audit would help reduce the number of corrections to those statements.

All cluster agencies met the statutory deadlines for completing the early close procedures and submitting the financial statements.

We continue to observe inconsistencies in the employee leave data reported from the Department of Education’s (the Department) payroll system. The robustness of the Department's quality assurance over leave liability data should be improved.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the Education cluster. It also comments on our review of the financial control framework applied by 70 schools in NSW whose financial results form part of the Department of Education's (the Department) financial statements.

Section highlights

  • Audit Office management letter recommendations to address internal control weaknesses should be actioned promptly, with a focus on addressing repeat issues. The 2018–19 financial audits of cluster agencies identified 55 internal control issues, including 14 that were carried forward from the previous year.
  • Application controls are procedures that operate at a business process level designed to ensure the integrity of accounting records. The Department can mitigate the risk of fraud or error in preparing its financial statements if segregation of duties are appropriately configured in their key application system.
  • Our review of a selection of schools across NSW identified deficiencies in how schools apply the Department’s financial management practices and governance arrangements.

Appendix one – List of 2019 recommendations

Appendix two – Status of 2018 recommendations

Appendix three – Cluster agencies

Appendix four – Financial data

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Stronger Communities 2019

Stronger Communities 2019

Justice
Community Services
Compliance
Financial reporting
Internal controls and governance
Management and administration
Project management
Service delivery
Shared services and collaboration
Workforce and capability

A report has been released on the NSW Stronger Communities cluster.

From 1 July 2019, the functions of the former Department of Justice, the former Department of Family and Community Services and many of the cluster agencies moved to the new Stronger Communities cluster. The Department of Communities and Justice is the principal agency in the new Stronger Communities cluster.

The report focuses on key observations and findings from the most recent financial audits of agencies in the Stronger Communities cluster.

Unqualified audit opinions were issued on the financial statements for all agencies in the cluster.  

There were 157 audit findings on internal controls. Two of these were high risk and 59 were repeat findings from previous financial audits. ‘Cluster agencies should prioritise actions to address internal control weaknesses promptly with particular focus given to issues that are assessed as high risk’, the Auditor-General said.

The report notes that the NSW Government’s new workers' compensation legislation, which gave eligible firefighters presumptive rights to workers' compensation, cost emergency services agencies $180 million in 2018–19, mostly in increased premiums.

Download the PDF version of report

This report analyses the results of our audits of financial statements of the agencies comprising the Stronger Communities cluster for the year ended 30 June 2019. The table below summarises our key observations.

This report provides parliament and other users of the financial statements of agencies in the Stronger Communities cluster with the results of our audits, our observations, analyses, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

This cluster was significantly impacted by the Machinery of Government (MoG) changes on 1 July 2019. This report focuses on the agencies that from 1 July 2019, comprised the Stronger Communities cluster. The MoG changes moved some agencies from the clusters to which they belonged in 2018–19 to the Stronger Communities cluster. Conversely, the MoG also moved some agencies formerly in the Family and Community Services cluster and Justice cluster elsewhere. Please refer to the section on Machinery of Government changes for more details.

The Department of Communities and Justice is the principal agency of the cluster. The newly created department combines functions of the former Department of Justice and the Department of Family and Community Services.

Machinery of Government (MoG) refers to how the government organises the structures and functions of the public service. MoG changes occur when the government reorganises these structures and functions and those changes are given effect by Administrative Orders.

The MoG changes announced following the NSW State election on 23 March 2019 significantly impacted the Stronger Communities cluster through Administrative Changes Orders issued on 2 April 2019 and 1 May 2019. These orders took effect on 1 July 2019.

Section highlights

The 2019 MoG changes significantly impacted the former Justice and Family and Community Services (FACS) departments and clusters.

  • The Stronger Communities cluster combines most of the functions and agencies of the former Justice and FACS clusters from 1 July 2019.
  • The Department of Communities and Justice is now the principal agency in the new cluster.
  • The MoG changes bring new responsibilities, risks and challenges to the cluster.
  • A temporary office has been established by the Department of Communities and Justice to support the cluster in the planning, delivery and reporting associated with implementing the changes.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations relating to the financial reporting of agencies in the Stronger Communities cluster for 2019.

Section highlights
  • Unqualified audit opinions were issued for all agencies' 30 June 2019 financial statements. However, further actions can be taken by some cluster agencies to enhance the quality of their financial reporting.
  • In November 2018, the Department of Justice implemented a new Victims Support Services system called VS Connect. Significant data quality issues arising from the VS Connect system implementation impacted the Department's ability to reliably estimate its Victims Support Scheme claims liabilities at 30 June 2019.
    We recommend the Department of Communities and Justice resolves the data quality issues in the new VS Connect System before 30 June 2020 and capture and apply lessons learned from recent project implementations, including LifeLink, Justice SAP and VS Connect, in any relevant future implementations.
  • Our audits found some cluster agencies needed to do more work on their impact assessments and preparedness to implement the new accounting standards, to minimise the risk of errors in their 2019–20 financial statements.
  • Cluster agencies with annual leave balances exceeding the State's target should further review their approach to managing leave balances.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the Stronger Communities cluster.

Section highlights

  • Cluster agencies should action recommendations to address internal control weaknesses promptly. Particular focus should be given to prioritising high risk issues. The 2018–19 financial audits of cluster agencies identified 157 internal control issues. Of these, two were high risk and 37.6 per cent were repeat findings from previous audits.
  • Data from the Department of Justice shows the inmate population reached a maximum of 13,798, compared to an operational capacity of 14,626 beds on 31 August 2019. This equates to an operational vacancy rate of 5.7 per cent, which is more than the recommended 5.0 per cent buffer. This is the first time the vacancy rate has exceeded the target over the last five years. Growth in the NSW prison population is being managed through the NSW Government's $3.8 billion Prison Bed Capacity Program.
  • In September 2018, the NSW Government introduced new workers' compensation legislation, which gives eligible firefighters presumptive rights to workers' compensation when diagnosed with one of 12 prescribed cancers. The new legislation cost emergency services agencies $180 million in 2018–19, mainly through additional workers' compensation premiums.

Appendix one – Timeliness of financial reporting by agency

Appendix two – Management letter findings by agency

Appendix three – List of 2019 recommendations 

Appendix four – Status of 2018 recommendations 

Appendix five – Cluster agencies 

Appendix six – Financial data 

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Transport 2019

Transport 2019

Transport
Asset valuation
Financial reporting
Infrastructure
Internal controls and governance
Management and administration
Service delivery
Workforce and capability

This report details the results of the financial audits of NSW Government's Transport cluster for the financial year ended 30 June 2019. The report focuses on key observations and findings from the most recent financial statement audits of agencies in the Transport cluster.

Unqualified audit opinions were issued for all agencies' financial statements. However, valuations of assets continue to create challenges across the cluster. The Audit Office identified some deficiencies in relation to asset valuations at Transport for NSW, Roads and Maritime Services, Rail Corporation New South Wales and Sydney Metro.

The Audit Office noted an increase in findings on internal controls across the Transport cluster. Key themes related to information technology, asset management and employee leave entitlements. The report also highlights the status of significant infrastructure projects across the Transport cluster.

The report makes several recommendations including:

  • agency finance teams need to be consulted on major business decisions and commercial transactions at the time of their execution to assess the financial reporting impacts
  • the Department of Transport should ensure consistent accounting policies are applied across its controlled entities.

Download the Transport 2019 report (PDF)

This report analyses the results of our audits of financial statements of the Transport cluster for the year ended 30 June 2019. The table below summarises our key observations.

1. Machinery of Government changes
Transport for NSW, as the
lead agency, will absorb the
functions of Roads and
Maritime Services

The NSW Government announced its intention to integrate Roads and Maritime Services (RMS) into Transport for NSW (TfNSW) as part of the Machinery of Government changes.

This change was not included in the Administrative Orders as the Transport Administration Act 1988 No. 109 governs the composition of the Transport cluster. The Transport Administration Amendment (RMS Dissolution) Act 2019 (the Act) received assent on 22 November 2019. The Act dissolves RMS and transfers the assets, rights and liabilities of RMS to TfNSW. As at the date of this Report, the Act is not yet in force.

Transport is considering the impact of the changes on its operating model and financial reporting.

2. Financial reporting
Audit opinions

Unqualified audit opinions were issued on the 2018–19 financial statements of all agencies in the Transport cluster.

TfNSW and Sydney Metro obtained a three-week extension from NSW Treasury to submit their financial statements for audit to resolve accounting issues surrounding the valuation of property, plant and equipment.

The Department of Transport reported total consolidated property, plant and equipment of $158 billion at 30 June 2019. In 2018–19, there were issues with asset valuations at TfNSW, RMS, Sydney Metro and Rail Corporation New South Wales (RailCorp), resulting in adjustments after the submission of financial statements for audit and the correction of a prior period error.

There was also a prior period error resulting from an agreement between TfNSW and the former UrbanGrowth Development Corporation due to a lack of assessment of the financial reporting implications at the time of signing the agreement.

Recommendation: Agency finance teams need to be consulted on major business decisions and commercial transactions to assess their accounting impacts at the time of their execution, rather than at the end of a financial year. Agencies also need to resolve all key accounting issues such as valuations as part of the early close procedures.

This would improve the quality of financial reporting and avoid the need for extensions for agencies to submit their financial statements for audit.

Preparedness for new
accounting standards
Agencies across the cluster are progressing in their implementation of the new accounting standards.

Transport cluster agencies need to improve their contracts registers to ensure they have a complete list of contracts and agreements to assess the impact of the new accounting standards.
Valuation of assets remains
a challenge in the
Transport cluster

Whilst agencies complied with the requirements of the accounting standards and NSW Treasury policies on valuations, the Audit Office identified some deficiencies in relation to asset valuations across the cluster.

TfNSW reported a retrospective correction of a prior period error at 1 July 2017 which resulted in a reduction in the valuation of its Country Rail Network earthworks by $2.1 billion. This was due to survey results which identified the earthworks were flatter and lower than estimated in the valuation at 30 June 2017.

RMS made several adjustments during the year to correct asset values due to changes to valuation assumptions or data improvements. This included:

  • reduction of $318 million in the value of land under roads
  • decrease of $84.9 million to the value of land and buildings
  • changes to the value of traffic control and traffic signal network assets, due to data improvements.

Sydney Metro North West officially opened in May 2019 and reported total assets of $9.1 billion. Sydney Metro derecognised $322 million in assets constructed to facilitate its operation but transferred to councils and utilities.

Inconsistent accounting
policies across the
Transport cluster

There was an inconsistency identified in the cluster relating to the valuation of substratum land. In 2018–19, RailCorp derecognised $109 million of substratum land to ensure consistency in its approach with other Transport agencies.

As the parent entity, the Department of Transport needs to ensure accounting policies are consistently applied across all controlled entities for consolidation purposes. Inconsistencies in the application of accounting standards across agencies will impact comparability of financial reporting and decision making across the Transport cluster.

Recommendation: The Department of Transport should ensure consistent accounting policies are applied across its controlled entities.

Revenue growth

Public transport passenger revenue increased by $89.0 million (5.9 per cent) in 2018–19, and patronage increased by 37.8 million (4.9 per cent) across all modes of transport based on data provided by TfNSW.

The increase in revenue is mainly due to an increase in patronage as well as the annual increase in fares.

Negative Opal cards

Negative balance Opal cards resulted in $2.9 million in revenue not collected in 2018–19 ($10.4 million since the introduction of Opal).

In January 2019, Transport made a change to the Sydney Airport stations to prevent customers with high negative balances exiting the station. In addition, in late 2018, Transport increased the minimum top up values for new cards at the airport stations.

Recommendation (repeat): TfNSW should implement further measures to prevent the loss of revenue from passengers tapping off with negative balance Opal cards.

3. Audit observations
Internal controls There was an increase in findings on internal controls across the Transport cluster. Key themes relate to information technology, employee leave entitlements and asset management.

Twenty-nine per cent of all issues were repeat issues. The majority of the repeat issues related to information technology controls.
Write-off of assets In addition to a $322 million derecognition of assets transferred to councils and utilities by Sydney Metro and a $109 million derecognition of substratum land at RailCorp, the Transport cluster wrote-off $278 million of assets related to roads, bridges, maritime assets, traffic signals and controls network.

These mainly related to roads, bridges, maritime assets, traffic signals and the control network where new infrastructure assets substantially replaced an existing asset as part of construction activities.
Transport Asset Holding
Entity (TAHE)
TAHE was established to be a dedicated asset manager for the delivery of public transport asset management. The Transport Administration Amendment (Transport Entities) Act 2017 will transition RailCorp into TAHE. RailCorp is now expected to transition to TAHE from 1 July 2020 (previously 1 July 2019). Several working groups have been considering various aspects of the TAHE transition including its status as a for profit Public Trading Enterprise, the operating model and the impact of the new accounting standards AASB 16 'Leases' and AASB 1059 'Service Concession Arrangements: Grantors'. The considerations of these aspects identified several challenges in the implementation of TAHE which has led to the revised transition date. Given the delays in implementation, it is important to clarify the intent of the TAHE model.
Excess annual leave

Twenty-six per cent of Transport employees have annual leave balances exceeding 30 days. Of the employees with excess leave balances, 732 (10.3 per cent) did not take any annual leave in 2018–19.

Recommendation (repeat): Transport entities should further review the approach to managing excess annual leave in 2019–20. They should:

  • monitor current and projected leave balances to the end of the financial year each month
  • agree formal leave plans with employees to reduce leave balances over an acceptable timeframe
  • ensure leave plans are actioned appropriately
  • encourage all staff with excess leave balances take a minimum two-week period of leave per year.
Completeness and
accuracy of contracts
registers

There are no centralised processes to record all significant contracts and agreements in a register across the Transport cluster.

Across the Transport cluster, contracts and agreements are maintained by the individual agencies using disparate registers. Agencies must perform detailed assessments of their existing contracts and agreements to quantify the impact of the new accounting standards (AASB 16 ‘Leases’, AASB 15 ‘Revenue from Contracts with Customers’, AASB 1058 ‘Income of Not-for-Profit Entities’ and AASB 1059 'Service Concession Arrangements: Grantors').

In 2018–19, there was also a prior period error resulting from an agreement between TfNSW and another government agency due to a lack of assessment of the financial reporting implications at the time of signing the agreement.

A lack of a complete register of all contracts and agreements increases the risk that agencies may not be able to assess the full impact of the new accounting standards, as well as perform a complete assessment of the financial reporting implications of contracts and agreements.

Recommendation: Transport agencies should implement a process to centrally capture all significant contracts and agreements entered. This will ensure:

  • agencies are fully aware of contractual and other obligations
  • appropriate assessment of financial reporting implications
  • assessment of new accounting standards, in particular AASB 16 ‘Leases’, AASB 15 'Revenue from Contract with Customers', AASB 1058 'Income of Not-for-Profit Entities ' and AASB 1059 'Service Concession Arrangements: Grantors' are accurate and complete.

 

This report provides parliament and other users of the Transport cluster’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

This cluster was impacted by the Machinery of Government changes on 1 July 2019. The NSW Government announced its intention to integrate Roads and Maritime Services (RMS) into Transport for NSW (TfNSW). This report is focused on the Transport cluster prior to these changes. Please refer to the section on Machinery of Government changes for more details.

Machinery of Government refers to how the government organises the structures and functions of the public service. Machinery of Government changes are where the government reorganises these structures and functions, and are given effect by Administrative orders.

The Transport cluster was impacted by recent Machinery of Government changes. These changes were announced by the Department of Premier and Cabinet but were not included in the Administrative Orders as the Transport Administration Act 1988 No. 109 governs the composition of the Transport cluster. It was the intention of government to transfer the functions of the RMS into TfNSW. This requires legislative changes to the Transport Administration Act 1988 No. 109.

Section highlights

Under the Machinery of Government changes, the NSW Government will transfer the functions of RMS into TfNSW.

  • The Transport Administration Amendment (RMS Dissolution) Act 2019 (the Act) received assent on 22 November 2019.
  • The Act will dissolve RMS and transfer its functions, assets, rights and liabilities to TfNSW.
  • As at the date of this report, the Act is not yet in force.
  • There are risks and challenges for asset and liability transfers, governance and retention of knowledge.
  • As of 1 July 2019, administrative arrangements (delegations and reporting line changes) were put in place to enable TfNSW and RMS to operate within a single management structure, while still remaining as separate legal entities.
  • Transport is working on a number of options as to how to implement the changes. 

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Transport cluster for 2019.

Section highlights

  • Unqualified audit opinions were issued on all agencies' financial statements.
  • RMS required an extension from NSW Treasury for their early close procedures.
  • TfNSW and Sydney Metro required extensions to submit their year-end financial statements.
  • Valuation of assets remains a challenge across the cluster.
  • There remains Opal cards with negative balances.
  • Sydney Metro derecognised assets of $322 million in relation to assets constructed for third parties.
  • Inconsistencies in the application of accounting policies across cluster agencies impact comparability of financial reporting across the Transport cluster.

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the Transport cluster.

Section highlights

  • There was an increase in findings on internal controls across the Transport cluster. Twenty-nine per cent of all issues were repeat issues.
  • Transport entities wrote-off over $278 million of assets which were replaced by new assets or technology.
  • Twenty-six per cent of Transport employees have excess annual leave.
  • There are no processes to ensure all significant contracts and agreements are captured by agencies in a centralised register.

Appendix one – Timeliness of financial reporting by agency 

Appendix two – Management letter findings by agency 

Appendix three – List of 2019 recommendations 

Appendix four – Status of 2017 and 2018 recommendations 

Appendix five – Cluster agencies 

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.