The Auditor-General for New South Wales, Margaret Crawford, released a report today examining the management of the One TAFE NSW modernisation program.

In 2016, the Government released 'A Vision for TAFE NSW' which stated that TAFE NSW needed to become more flexible, efficient and competitive. It set out the need to progressively reduce significant cost inefficiencies, including by moving away from separate institutes to a single institute model. TAFE NSW established the One TAFE NSW modernisation program to deliver on that vision.

The Auditor General found that the One TAFE NSW modernisation program did not deliver against its key objectives within planned timeframes. The modernisation program originally aimed to realise $250 million in annual savings from 2018–19. Because of project delays and higher than expected transition costs, TAFE NSW did not meet the original savings target. TAFE NSW has made progress on key elements of the program and anticipates that savings will be realised in coming years.

The report makes two recommendations to improve governance arrangements for delivering on commercial objectives and increasing transparency of non commercial activities. 

The report also identifies a series of lessons for future government transformation programs.

TAFE NSW is the public provider of Vocational Education and Training (VET) in New South Wales. In 2018, TAFE NSW enrolled 436,000 students in more than 1,200 courses at around 130 locations across the State.

There have been major policy changes impacting TAFE NSW over the past decade. Under the Smart and Skilled reform, TAFE NSW started to compete with other Registered Training Organisations (RTOs) for a share of the student market.

In 2016, the NSW Government released 'A Vision for TAFE NSW'. The Vision stated that a failure to adapt to market circumstances had left TAFE NSW with unsustainable costs and inefficiencies. To address this, TAFE NSW needed to become more flexible, efficient and competitive. It set out that TAFE NSW must progressively reduce significant cost inefficiencies, including by moving away from a model of separate institutes to a One  TAFE NSW model. The NSW Government set TAFE NSW a target to achieve savings through implementing the Vision.

TAFE NSW established the One TAFE NSW modernisation program to deliver on that vision. The program initially aimed to deliver savings of $250 million per year from 2018–19, but this target was reviewed and updated as the program was being delivered.

This audit assessed whether TAFE NSW effectively managed the One TAFE NSW modernisation program to deliver on the NSW Government's vision for TAFE NSW. In making this assessment, the audit examined whether:

  • delivery of the program was well planned
  • the program was driven by sound governance arrangements
  • TAFE NSW is making progress against the intended outcomes of the program.

The audit focused on the effectiveness of planning, governance and reporting arrangements. It examined five projects within the overall modernisation program as case studies.

Conclusion

The One TAFE NSW modernisation program was an ambitious plan to deliver on the NSW Government’s vision for TAFE NSW, while achieving ongoing savings. Several factors contributed to TAFE NSW not effectively managing the program to deliver on planned timeframes and objectives. These factors include unclear expectations of the primary role of TAFE NSW, unrealistic timeframes, undertaking a large number of complex projects concurrently, governance arrangements that were not fit-for-purpose and poor-quality data.

Planning for the modernisation program and its projects was driven by top-down savings targets and pre-determined timeframes. This led to TAFE NSW attempting to deliver a large number of programs concurrently within tight timeframes. Program management capability was underdeveloped at the commencement of the program and this affected the quality of planning for delivery.

There was a lack of clarity around TAFE NSW's primary purpose. Part of the NSW Government's vision for TAFE NSW was for it to be more commercial, competitive and efficient. These objectives were not fully supported by existing legislation. The commercial objectives of the modernisation program conflicted with legislated social objectives for TAFE NSW. TAFE NSW did not have the autonomy to operate like a government-owned business in a market environment. And while TAFE NSW received separate funding to support students facing disadvantage this did not cover the costs of other non-commercial activities undertaken for social purposes, such as delivering uneconomic courses. The role of the TAFE Commission Board was ambiguous during the initial years of the program, which increased reporting requirements and blurred accountabilities for decision-making.

TAFE NSW's Strategic Plan 2016-22 nominated ten key milestones for delivery by January 2019. TAFE NSW has made progress against several important milestones, including that TAFE ‘is a single TAFE NSW brand’ and has 'industry specific TAFE NSW SkillsPoints'. Other key elements have yet to be delivered, including that TAFE NSW achieves 'integrated enterprise-wide business systems'. Because of delays to projects and higher than expected transition costs, TAFE NSW reported that it did not meet the originally targeted $250 million in annual savings for 2018–19 (which was reviewed and updated as the program was being delivered). 

Appendix one – Response from agency

Appendix two – About the audit

Appendix three – Performance auditing

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #346 - released 17 December 2020

Published

Actions for Managing the health, safety and wellbeing of nurses and junior doctors in high demand hospital environments

Managing the health, safety and wellbeing of nurses and junior doctors in high demand hospital environments

Health
Internal controls and governance
Management and administration
Workforce and capability

The Auditor-General for New South Wales, Margaret Crawford, released a report today examining NSW Health’s management of health and safety risks to nurses and junior doctors in high demand hospital wards over the past five years, including during the first six months of the 2020 COVID-19 health emergency.

The Auditor-General found that while NSW Health effectively managed most incidents and risks to the physical health and safety of hospital staff during ‘business as usual’ activities, systems and resources are not fully effective to manage staff psychological and wellbeing risks, particularly for nurses.

The Auditor-General found that NSW Health was effective in managing most COVID-19 health and safety risks to hospital staff. Overall effectiveness could have been improved had pandemic preparedness training been delivered across all Local Health Districts. Additionally, state-wide communication systems could have been improved to provide hospital clinicians with access to a ‘single source of truth’ with the latest advice from NSW Health authorities.

NSW Health’s planning and preparation for the supply of Personal Protective Equipment (PPE) was partially effective. At various times, some PPE items could not be sourced from established suppliers. Face masks, goggles and protective gowns were substituted with products that differed in shape, size and fitting from usual items, and in some hospitals, substituted masks were used without being locally fit tested by hospital staff.

The Auditor-General made seven recommendations aimed at enhancing hospital health and safety risk reporting practices, along with a recommendation that NSW Health conduct a post pandemic 'lessons learned' review and make policy and operational recommendations for future pandemic responses.

Over the past decade, there have been increases in the numbers of health and safety incidents affecting nurses and junior doctors in NSW hospitals. These increases have been associated with higher numbers of patients with acute mental health conditions, age-related cognitive impairments, and patients presenting in emergency departments under the influence of drugs and alcohol.  

This audit commenced in August 2019, with a focus on the health, safety and wellbeing of nurses and junior doctors in high demand hospital wards. Our audit focused on emergency departments, mental health wards and aged care wards during 'business as usual’ periods of hospital operations. 

In the early months of 2020, the novel coronavirus (COVID-19) brought new health and safety risks to hospital staff. These risks included the potential for infection amongst health workers, increased staff workloads, and impacts on staff wellbeing.  

In May 2020, we expanded the focus of the audit to assess the effectiveness of NSW Health’s management of the health and safety risks to staff during the COVID-19 health emergency. We assessed the impacts on emergency departments and intensive care units, as these were the wards where staff were most likely to come into contact with COVID-19.  

The Audit Office acknowledges the ongoing health and safety challenges that the pandemic has brought to NSW Health staff – in particular to hospital clinicians and the managers who support them.  

This audit assessed the effectiveness of NSW Health’s:

  • systems, forums and workplace cultures to support reporting and generate data about risk
  • initiatives to support safe workplaces and effectively respond to health and safety incidents
  • actions to continuously improve staff health, safety and wellbeing in hospital environments.

The first three chapters of this report describe the effectiveness of NSW Health’s ‘business as usual’ health and safety risk management. The fourth and fifth chapters describe the effectiveness of NSW Health’s health and safety risk management during the COVID-19 pandemic.  

Conclusion
NSW Health’s management of health and safety risks in NSW hospitals

NSW Health is effectively monitoring and managing most incidents and risks to the physical health and safety of nurses and junior doctors in NSW hospitals. However, systems and resources are not fully effective across all Local Health Districts for monitoring or managing psychological and wellbeing risks - particularly in relation to nurses.

NSW Health’s incident management system is effective for recording health and safety incidents in hospital wards where incidents occur infrequently, and staff have time to log incident details during shift hours. However, in high demand wards where incidents and risks are common, staff report that they are unable to log all incidents due to the frequency of events, and the time it takes to record incidents in the system.

NSW Health is taking reasonable steps to manage and respond to physical health and safety incidents in NSW hospitals, but psychological and wellbeing risks and incidents are not routinely recorded or escalated to managers. Stress debriefing is not consistently available to staff after difficult or traumatic workplace incidents.

The Ministry of Health could improve its information sharing and data reporting on state-wide health and safety risks in NSW hospitals, and communicate risk trends to the wider NSW health system. This would assist managers to identify common health and safety issues, and target their responses. The Ministry has not set up systems or strategies to identify or support the expansion of successful health and safety initiatives across the NSW health system.

NSW Health’s management of health and safety risks associated with COVID-19

To date, NSW Health has effectively managed most COVID-19 related health and safety risks to hospital staff. The overall effectiveness of NSW Health's preparations and responses to COVID-19 could have been improved in the early phases of the health emergency - from January to early April 2020 - by ensuring that hospital staff in all Local Health Districts had access to pandemic training, that all emergency response policies had been updated and circulated, that state-wide communication systems were able to be rapidly upscaled to deliver consistent messages to hospital staff across the health system, and that PPE supply lines could provide sufficient stock to meet requirements during all pandemic response phases.

Local Health District executives and hospital managers effectively guided and supported nurses and junior doctors to manage and minimise most COVID-19 health and safety risks in hospital environments. However, communication with frontline staff could have been improved in the early stages of the pandemic. The Ministry did not set up a centralised communication channel to communicate consistent messages and advice to hospital clinicians until April 2020. This finding is consistent with a finding from the 2009 review into NSW Health’s response to the H1N1 influenza outbreak. Clinical staff advised that the lack of a centralised communication channel, substantially increased their workloads as they checked numerous sources for the latest and most authoritative advice.

Prior to COVID-19, pandemic response training was limited across the NSW Health system. Nurse managers of emergency departments and intensive care units reported that there was limited training or familiarisation with the NSW Pandemic Plan. Key policies describing infection control principles for emergency departments and intensive care units were outdated and had not been revised within required timelines.

NSW Health's planning and preparation for the supply and management of personal protective equipment (PPE) has been partially effective, with PPE available to hospital staff at all times. However, at various intervals, some PPE could not be sourced from established suppliers. Face masks, goggles and protective gowns were substituted with products that differed in shape, size and fitting, from the usual PPE stock. Staff reported that in the early stages of the pandemic, substituted masks were not locally fit tested by hospital staff in some emergency departments.

1. Audit recommendations

By December 2021, NSW Health should:

  1. Evaluate the effectiveness of the new incident management system to enable full reporting of health and safety incidents and risks in all hospital wards, including those where incidents and risks are common, and monitor for consistency of reporting over time
  2. Expand the categories of hospital incident data reported to Ministry executives in the Work Health and Safety Dashboard reports, including by linking injury data to incident types by hospital ward category, and monitor in conjunction with Local Health Districts for emerging trends and improvement over time
  3. Ensure that nurses and junior doctors have regular opportunities to report on risks to their psychological health and wellbeing, and that system managers have access to aggregate data to guide responses to mitigate these risks
  4. Develop and implement an evidence-based guiding framework and strategy to support hospital staff in the aftermath of traumatic or unexpected workplace incidents, and monitor implementation
  5. At regular intervals, publicly report aggregate Root Cause Analysis data detailing the hospital system factors that contribute to clinical incidents
  6. Develop and implement a systemwide platform for sharing research and information about hospital health and safety initiatives across the health system
  7. Conduct a post-pandemic 'lessons learned' review focusing on the effectiveness of key strategies deployed in the management of the COVID-19 pandemic and make policy and operational recommendations for future pandemic responses. In particular, ensure:
    • regular scenario-based pandemic training for hospital staff
    • updated policies and protocols for hospital infection controls
    • capability to upscale authoritative communication with frontline health workers at the earliest notification of a health emergency and for the duration of the emergency
    • systems and safeguards to ensure the supply and availability of clinically appropriate personal protective equipment (PPE) during all phases of a pandemic.

Local Health Districts were effective in leading health and safety infection control activity

According the NSW Health Influenza Pandemic Plan (Pandemic Plan), the Chief Executives of Local Health Districts have ultimate responsibility for public health unit preparations during health emergencies. If necessary, they can ‘draw on the support of the State Pandemic Management Team and local emergency management resources’.

During the preparations and early response phases to the COVID-19 pandemic, Local Health Districts were at the forefront of most NSW hospital activity. They took the lead role in developing hospital infection control protocols and guidance about the appropriate uses of Personal Protective Equipment (PPE). Each Local Health District established its own responses to the health emergency, based on the best clinical advice available to them. The localised approach meant that there were some minor differences in infection control practices across the NSW health system.

Throughout February and March 2020, there was limited centralised policy or guidance from the Ministry and its Pillar Health agencies about COVID-19 infection control practices. It was not possible to mandate practices at a time when information about the virus was evolving. Clinical responses were changing as more became known about COVID-19, especially about its patterns of transmission and its impacts on people with the disease.

During February and March 2020, Local Health District executives communicated with hospital staff via a range of methods. Some sent daily e-memos with the latest updates. Some scheduled more regular meetings with hospital clinicians. Some Districts set up extensive staff training sessions and information briefings to keep all personnel updated with the latest advice. Physical distancing made it difficult to bring staff together in large groups, so a range of communications measures were implemented.

Clinical staff also utilised their clinical training and expertise to prepare their wards and train frontline staff in infection control procedures. Some sourced information from national and international colleagues to add to localised knowledge of the virus.

When the first evidence of COVID-19 community transmission was identified in the Northern Sydney Local Health District, hospital staff followed infection control protocols that were based on local guidance and information. With the support from the District executive team and infectious diseases experts, hospital clinicians set up their own infection control protocols and PPE protections. Within a week the District had produced a matrix to guide staff in the uses of PPE during COVID-19 procedures, and had circulated the guidance to all hospital clinicians.

At the end of March 2020, a version of the Northern Sydney PPE matrix was published on the Clinical Excellence Commission’s website and it has now become NSW Health’s standard guideline for PPE during COVID-19 procedures. Once this guideline was published centrally, infection control practices were standardised across NSW hospitals.

This form of District-led policy making is not ‘business as usual’ practice for NSW Health. Policy making processes were somewhat reversed during the early response phases to COVID-19. This flexible policy approach supports the governance arrangements described in the Pandemic Plan, which assigns responsibility for ‘supporting and maintaining quality care across health services and implementing infection control measures as appropriate’ to Local Health Districts.

In non-health emergency situations, clinical policy and protocols are usually initiated and developed by the Ministry and the Clinical Excellence Commission and are subsequently shared across the health system after a quality control process. The localised approach adopted in the months from February to March 2020, allowed for rapid and flexible responses to changing information – to protect the health and safety of the hospital workforce and the wider community.

Hospital staff across NSW would have been better prepared for COVID-19 if pandemic training had been delivered across all Local Health Districts in the past decade

Local Health Districts are responsible for training hospital staff in preparation for public health emergencies. NSW’s policy describing Public Health Emergency Response Preparedness Minimum Standards requires that clinical staff participate in at least one annual emergency training exercise if they hold a position where they are likely to be called upon in an emergency. Staff must participate in an actual response exercise or a relevant training session. The training must also include re-familiarisation with PPE.

Available evidence about emergency response training in NSW indicates that at least two Local Health Districts have delivered pandemic focussed training in the past decade. Our interviews with managers of emergency departments and intensive care units indicates that most other Districts have focused their emergency training on mass patient trauma incidents such as plane crashes, train crashes and terrorist attacks. While the potential for these types of mass trauma events is real, and warrants training and preparation, significant global outbreaks of diseases have also had potential to threaten NSW communities. In previous decades, global health communities have been at risk of diseases such as the Severe Acute Respiratory Syndrome (SARS) and Middle East Respiratory Syndrome (MERS).

In the two Districts where pandemic training was provided in NSW, staff participated in community influenza vaccination exercises. These were focused on upskilling staff to follow emergency command structures, manage high volume patient flows, and organise sanitisation logistics during a hospital-based training exercise.

Our interviews with nurse managers in emergency departments and intensive care units indicate that in the majority of other Local Health Districts, key personnel were unaware of the NSW Pandemic Plan. Interviewed staff also reported insufficient scenario-based training in pandemic responses over the last ten years.

The Ministry, the Clinical Excellence Commission and the Health Education and Training Institute (HETI) are responsible for online training and 'state-wide strategies and resources to maintain high levels of compliance with infection control and patient safety recommendations'. The HETI website contains online training modules in infection control and PPE donning and doffing procedures. Other infection control information and research is available on the websites of the Clinical Excellence Commission and the Agency for Clinical Innovation.

Online training modules are effective for upskilling staff in a range of skills, but are not a substitute for real-time, rapid incident response training. Face-to-face training provides opportunities for first responders to test procedures in hospital environments. Incident response training provides opportunities for staff to assess their levels of compliance with protocols and their competence with equipment in scenario situations. It is the responsibility of Local Health Districts to provide this form of training to the health staff in their District.

Two NSW Health policies that govern clinical arrangements during pandemics are outdated

The Ministry had not updated two policies that had the potential to assist emergency departments and intensive care units in aspects of their ward preparation for the COVID-19 pandemic. Both policies were on the NSW Health website, but neither were shared with hospital staff in the planning phases for the pandemic. Both policies are out of date and have not been revised within required timeframes.

The 2010 Influenza Pandemic - Providing Critical Care policy was due for review in May 2015 and was not updated at the time of the COVID-19 health emergency. Similarly, the 2007 policy Hospital Response to Pandemic Influenza Part 1: Emergency Department Response was due for review in June 2012 and has not been updated.

These policies were designed to assist clinical staff to make necessary ward arrangements for infection control. They set out the steps for rapid identification of contingent workforces, isolation procedures, and management of patient flows to separate those with suspected infection from other patient cohorts. They were a potential addendum to the NSW Pandemic Plan which describes the command and control responsibilities of health agencies in health emergencies.

Our interviews with nurse managers from emergency departments and intensive care units indicate that in the absence of pandemic policy, they sought clinical guidance from external sources and Local Health District experts. Interviewees told us that a lack of policy guidance about ward arrangements and infection control practices in a pandemic increased their workloads and hours of overtime in the early response phases to COVID-19. With the support of Local Health Districts, clinical staff made rapid adjustments in order to respond to changing testing requirements and ward arrangements.

The Ministry was slow to establish a centralised communication channel to communicate with frontline staff

NSW Health’s governance and communication arrangements during a pandemic are set out in the Pandemic Plan. The Plan requires that government agencies ‘commence enhanced arrangements, establish communications measures’ and confirm ‘governance arrangements’ when there is evidence of person to person transmission during an influenza outbreak. NSW Health received the first notifications of the novel coronavirus risks in January 2020.

During the preparation and early response phases to COVID-19, the Ministry and its central agencies were slow in establishing a single, authoritative channel through which to communicate consistent messages to frontline staff. Clinical staff required up-to-date information about COVID-19 testing criteria as requirements were changing rapidly, sometimes daily. While there was no expectation for fixed policy at this time, hospital staff required the latest instructions about treatment requirements, and updates on the numbers of COVID-19 infections in their region.

As information about COVID-19 was evolving, information was communicated across the health system via ‘multiple channels and sources’. While the Ministry and its central agencies communicated extensively with Local Health Districts during March 2020, hospital staff reported to us that they weren’t always sure where they could find the latest advice about testing protocols or infection controls.

Frontline staff told audit office staff that they were checking multiple sources and time-stamping advice to ensure they had the most up to date information on a daily basis. While some Local Health Districts managed clear communication links with frontline staff, nurse managers told us that communication was ‘chaotic’ during the early phases of pandemic preparation. Key personnel were not always available outside business hours and nurse managers advise that they spent hours at the end of shifts, seeking and printing the latest advice for weekend and night shift personnel. By the end of March 2020, the Ministry and the Clinical Excellence Commission websites became better organised to communicate with frontline clinicians.

A recommendation to the Ministry of Health after H1N1 swine flu could be equally applied in the COVID-19 context. The NSW Government’s report: Key Recommendations on Pandemic (H1N1) 2009 Influenza recommended the establishment of ‘clear pathways of communication … so that all employees have confidence in where their information will come from and who they should approach if they need additional information.’

NSW Health acknowledges the challenges and the lessons from the early phases of the COVID-19 pandemic. For example, a strategy released in August 2020, sets out NSW Health’s own recommendation for the future management of PPE including: ‘Aligning a single source of truth for PPE education and evidence-based guidance to ensure clarity of information on appropriate use, supported by an influential network of Infection Prevention and Control (IPC) practitioners at the forefront.

Ministry executives advise that communication with health staff has improved since the early phases of the pandemic. The Ministry now sends weekly COVID-19 updates to over 130,000 health staff via email. In addition, NSW Health now has two COVID-19 tabs on its website with current information, including COVID-19 testing advice. According to Ministry executives, these communication channels could be used or replicated if needed for future health emergencies. The Ministry also provides health information and updates via a phone application called Med App. This App is preferred by doctors and is less likely to be used by nurses. As at October 2020, there are 13,000 users of Med App. Push notifications can be made on Med App through SMS alerts.

Personal protective equipment (PPE) was not always available in required sizes and some hospital masks and gowns were substituted with products that differed from the usual items

Since the emergence of COVID-19 in Australia, all clinicians in NSW hospitals have had access to some form of PPE for their clinical requirements. If staff did not have appropriate equipment for each COVID-19 related procedure, they were guided by the formal advice issued to the NSW Health workforce on 11 March 2020 stating that: ‘The safety of NSW Health staff is a priority at all times, especially during COVID-19. Where safe working practices confirm specific PPE (e.g. face shields/masks or other equipment) are required for the protection of staff due to COVID-19, in all circumstances:

  • staff are to wear prescribed PPE as instructed
  • staff are not to undertake or be required to undertake tasks requiring PPE if the PPE is not available for use. Any such tasks are not to proceed until required PPE is available
  • any staff member who is concerned about their safety must raise their concerns immediately to their manager.’

At periods during March and April 2020, some PPE items were not available in the required sizes or the regular brands to which staff were accustomed. HealthShare NSW was not able to source PPE from usual suppliers. HealthShare NSW sourced PPE including N95 masks from non-traditional suppliers. Some PPE items differed in shape and size from the usual hospital equipment. While senior executives from HealthShare NSW advise that all products were approved by the Therapeutic Goods Administration (TGA), in some hospitals, nurse managers advise that staff were not able to ‘fit test’ substituted masks. Fit testing determines the type and the size of the respirator mask that achieves an adequate seal on an individual’s face.

In March and April 2020, ‘duck bill’ (N95) masks were not available in some hospitals. According to stock managers and clinical managers in Local Health Districts, duck bills are the preferred mask for staff with smaller faces, particularly female staff members. The duck bill mask is a standard PPE product, and as such, is fit tested during mandatory PPE training. During the early response phases to COVID-19, most Local Health Districts were provided with substitute N95 masks. Fit testing of the substituted N95 masks was not able to be conducted in all NSW hospitals during the early phases of COVID-19. During the first wave of COVID-19 in March and April 2020, hospital staff told audit staff that there was no time and a lack of equipment to appropriately fit test substituted N95 masks.

Nurse managers in emergency departments advise that in some instances, staff made adaptations to PPE to improve protections, such as doubling masks, adding elastics or bringing their own equipment. These adaptations were not consistent with guidelines. Nurse managers advise that in some cases, adaptations to PPE or ill-fitting masks created pressure sores and contact dermatitis. Just over half of the stock managers of Local Health Districts advised that PPE stock was procured from outside the HealthShare NSW system. Stock managers in some Districts advise that facial shields and goggles sourced from non-traditional suppliers by HealthShare NSW were of a lesser quality than standard equipment. Stock managers and nurse managers reported that the changes in PPE products caused confusion and stress amongst staff.

Local Health Districts were proactive in assisting hospital staff to mitigate risks of COVID-19 infections. Some Local Health Districts assigned ‘tiger teams’ to assist staff with their PPE practices. Tiger teams provide clinical expertise and advice to staff, answer questions about infection control and provide training on PPE practice in hospital ward environments. They assist and support PPE donning and doffing practices to ensure the appropriate sequencing of applying and removing PPE for effective infection control. They provide mask fit checking guidance to assist staff in correct PPE practices.

Districts ran extensive refresher PPE training sessions for clinical staff. Some hospitals ran regular PPE demonstrations so that staff could observe correct PPE procedures at set times during the day. These activities assisted staff to implement appropriate infection control in the period before the Clinical Excellence Commission’s web-based materials and videos became available in late March and early April 2020. These online resources now provide comprehensive guidance to hospital staff in PPE practices.

HealthShare NSW placed limits or caps on some high-demand PPE items that were too low to meet requirements in some Local Health Districts and had to be adjusted to meet actual demand

The NSW Pandemic Plan describes the responsibilities of the Ministry and its central agencies to manage and maintain the State Medical Stockpile of essential PPE supplies and antiviral medications. During a pandemic, HealthShare NSW has responsibility for warehousing, monitoring and distributing health supplies to the health workforce.

Due to a reported global shortage of PPE and limits to the NSW stockpile, HealthShare NSW placed limits on the provision of approximately 100 high-demand items to NSW hospitals. HealthShare NSW advise that the PPE order capping ceilings were implemented ‘to ensure local stockpiling does not occur’. A centralised ordering process was established with Local Health Districts so that PPE product ordering occurred through single hospital locations (214 across the State), rather than at the ward level. Escalation processes were established to allow Districts to request one-off increases to supply, and a process was set up to permanently increase the order cap limit for any PPE item by facility.

According to HealthShare NSW, ‘as incoming central supply has improved, order caps have subsequently increased in line with strong engagement and governance with the Local Health Districts to ensure the appropriate levels of supply are provided’. The original capped levels were determined by assessing PPE usage in wards during the flu season of 2019. As the flu season case numbers of 2019 were relatively low, some Local Health District managers advised that the levels of PPE during 2019 were not comparable to the level of PPE required for the COVID-19 pandemic.

After advocacy from hospital stock managers and clinicians, HealthShare NSW increased capped PPE levels in many Local Health Districts.

Executive members of the State Health Emergency Operations Centre (SHEOC) advise that its PPE supply strategy needs to be carefully developed as there are vast differences in PPE usage rates during 'business as usual' periods and pandemic periods. If NSW Health kept the level of PPE required in planning for a worst-case scenario, this would equate to an extensive surplus of PPE that could not be utilised during business as usual periods. The SHEOC Executive advise that it is not feasible or economical to store this level of PPE. They advise that given the costs of PPE, and the fact that the products have a shelf life, a diversified supply line is a more reliable method for ensuring PPE during surge and non-surge periods.

Early data modelling showed ICU patient numbers at levels not manageable with levels of ventilators and equipment

Early projections of patient numbers requiring acute care for COVID-19, were at levels that would not have been manageable with the equipment and resources of NSW hospitals. Throughout March through to May 2020, government data modelling indicated significant surges of community infections and surges in intensive care patients.

Early estimates were based on overseas trends, and if actual cases had matched projections, NSW hospitals would not have had sufficient ventilators to meet demand. The knowledge of this shortfall caused high levels of anxiety among nursing and medical staff.

While the data was based on the best available information, it had negative implications for the health and safety of the nurse and junior doctor workforce. Managers of intensive care wards and emergency departments reported stress amongst the workforce. Staff concerns were primarily about being faced with ‘the unmanageable’, along with heightened fears about contracting the virus with the knowledge that there was insufficient equipment to treat acute patients.

As it transpired, overall numbers of COVID-19 infections were lower than projected during the early months of the pandemic. The lower infection rates in the general population have meant fewer instances of patients requiring intensive care in NSW hospitals. In addition, HealthShare NSW has been able to increase the numbers of ventilators in NSW hospitals to prepare for future surges in patients requiring acute respiratory care.

SHEOC Executive advise that NSW Health undertook an accelerated procurement strategy in early 2020 to increase its stock of ventilators, and that ventilator capacity has always far-exceeded actual requirements.

NSW Health has developed a strategy to improve the management of PPE for the NSW health workforce

In August 2020, NSW Health released a strategy that sets out its future management and planning approaches to the provision of PPE for the NSW Health workforce. NSW Health’s Personal Protective Equipment (PPE) Strategy describes the learnings and challenges during the COVID-19 pandemic in sourcing and distributing PPE. It sets out the systems and methods for distributing PPE to staff and patients and focuses on how staff are kept informed on the appropriate use of PPE at all times. A supporting communications strategy has been developed to support its implementation.

The strategy contains enhanced transparency measures to regularly inform staff about PPE stock levels and to provide data about PPE usage rates by item types in wards in NSW hospitals. The NSW Health PPE strategy describes a changed approach to ordering, storing and allocating PPE. This includes diversifying the supply lines for PPE products to increase supply options in circumstances where supply lines become disrupted. It includes a centralised system for coordinating the supply of hospital PPE through Local Heath District coordination points and centralised distribution points in large hospitals.

Our interviews with hospital PPE stock managers and nurse managers indicate that staff find the new ordering system to be an improvement upon the previous stock ordering method.

According to the Personal Protective Equipment (PPE) Strategy, NSW health is upgrading its models for monitoring and benchmarking PPE usage across the health system. Systems are being improved for forecasting demand volumes during business as usual periods and during health emergency surges.

Appendix one – Response from agency

Appendix two – Audit methodology

Appendix three – About the audit 

Appendix four – Performance auditing 

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #344 - released 9 December 2020

Published

Actions for Health capital works

Health capital works

Health
Compliance
Infrastructure
Procurement
Project management

This report examines whether NSW Health effectively planned and delivered major capital works to meet the demand for health services in New South Wales.

The report found that NSW Health has substantially expanded health infrastructure across New South Wales since 2015. However, the program was driven by Local Health District priorities without assessment of the State’s broader and future‑focussed health requirements.

The report found that unclear decision making roles and responsibilities between Health Infrastructure and the Ministry of Health limited the ability of NSW Health to effectively test and analyse investment options.

Project delays and budget overruns on some major projects indicate that Health Infrastructure's project governance, risk assessment and management systems could be improved.

The Auditor‑General recommends that NSW Health ensure its capital projects offer the greatest value to New South Wales by establishing effective policy guidance and enhancing project governance and management systems.

Read full report (PDF)

Since 2011–12, NSW Health has aimed to improve its facilities and build 'future focused' infrastructure. The NSW Government’s 2015–16 election commitments established a four-year $5.0 billion capital program for NSW Health to build and upgrade more than 60 hospitals and health services. The 2019–20 State Budget committed a further $10.1 billion over four years for another 29 projects. This is the largest investment to date on health capital works in New South Wales.

Recent reviews of infrastructure have recognised that population and demographic growth will require a change in the delivery and composition of health infrastructure, including considering greater use of non-traditional, non-capital health service options and assets.

To ensure that expenditure on capital works represents the best value for money, NSW Health's business cases need to be robust and supported by evidence that demonstrates they are worthy investments. The NSW Process of Facility Planning has been the main framework guiding the detailed planning and development of NSW Health's capital works proposals. This framework was developed by the then NSW Department of Health in 2010. Its aim is to ensure investment proposals are supported by rigorous planning processes that address health service needs and provide value for money.

Infrastructure projects of the complexity and scale being delivered by NSW Health carry inherent risks. For example, unplanned cost escalations can potentially impact on the State’s finances. Unforeseen delays can also reduce the intended benefits. The growth in the State’s health capital spend and project profile, means its exposure to such risks has increased over time.

The objective of this audit was to assess the effectiveness of planning and delivery of major capital works to meet demand for health services in New South Wales. To address this objective, the audit examined whether:

  • the Ministry of Health has effective procedures for planning and prioritising investments in major health capital works
  • Health Infrastructure develops robust business cases for initiated major capital works that reliably inform government decision making
  • Health Infrastructure has effective project governance and management systems that support delivering projects on-time, within budget and achievement of intended benefits.

The audit focused on the Ministry of Health and Health Infrastructure – being the lead agencies within NSW Health responsible for prioritising, planning and delivering major health capital works across the State. The audit examined 13 business cases for eight discrete projects over a ten-year period.

Conclusion

NSW Health has substantially expanded health infrastructure across New South Wales since 2015. However, its planning and prioritisation processes were not assessed against a long-term statewide health infrastructure plan and lacked rigorous assessment against non-capital options creating a risk that they do not maximise value for New South Wales.

The scale of NSW Health's capital investment is significant and has grown substantially in recent years. The NSW Government’s election commitments in 2015–16 and 2019–20 collectively set out a $15.0 billion capital program to build and upgrade 89 hospitals and health services. NSW Health developed this infrastructure program in the absence of a statewide health infrastructure strategy and investment framework to focus its planning and decisions on the types of capital investments required to meet the long-term needs of the NSW health system.

Consequently, locally focused priorities of the State’s 17 Local Health Districts have been the primary drivers of NSW Health’s capital investments since 2015–16. Local Health District investment proposals for hospitals were developed without consideration of alternative health options such as community health service models, technology-driven eHealth care, or private sector options. Without rigorous assessment against a range of potential health service options, there is a risk that selected projects do not maximise value for New South Wales.

In recognition of the need for a statewide approach to infrastructure planning, the Ministry of Health recently developed a 20-year Health Infrastructure Strategy and prioritisation framework in 2019. The strategy was approved by the NSW Government in April 2020.

NSW Health's ability to effectively test and analyse its capital investment options has been compromised by unclear decision-making roles and responsibilities between its Health Infrastructure and the Ministry of Health agencies.

While both Health Infrastructure and the Ministry of Health have responsibilities for the assessment of business cases for proposed infrastructure projects, confusion about the roles of each agency at key steps compromised the efficacy of the process. Health Infrastructure and the Ministry of Health have differing views about which agency is responsible for testing business case inputs and conducting comprehensive options appraisals.

As a result of this confusion, Health Infrastructure and the Ministry of Health did not rigorously test Local Health District capital investment proposals against defined statewide health infrastructure investment priorities. The NSW Process of Facility Planning does not clarify the responsibilities of all parties in validating and prioritising Local Health District's Clinical Service Plans and progressing them to business cases.

NSW Health's infrastructure priorities are not sufficiently supported by transparent documentation of selection methodology and the rationale for decisions. Consequently, there is a risk that recommended options, whilst having some economic and health service merit, do not represent the greatest value.

Substantial delays and budget overruns on some major projects indicate that Health Infrastructure's project governance, risk assessment and management systems could be improved.

Health Infrastructure did not fully comply with NSW Government guidelines for developing business cases and making economic appraisals for proposed capital investments. These weaknesses, along with delays and budget overruns on some projects, demonstrate a need for Health Infrastructure to strengthen its project governance, management and quality control systems.

 

Over the period of review, NSW Government policies for business case development and submission have emphasised that effective governance arrangements are critical to a proposal's successful implementation.

NSW Health's Process of Facility Planning similarly highlights the importance of effective governance and project management for achieving good outcomes. It prescribes a general governance structure managed by Health Infrastructure that can be tailored to the planning and delivery of health infrastructure projects greater than $10.0 million.

Project challenges indicate opportunities for strengthening governance and project management

The three major hospital redevelopments examined in metropolitan, regional and rural areas had a combined Estimated Total Cost of more than $1.2 billion and comprised eight discrete projects and 13 separate business cases.

Almost all these projects experienced delivery challenges which impacted achievement of their original objectives and intended benefits. This is expected in complex and large-scale health infrastructure programs. However, in some projects the impacts were significant and resulted in substantial delays, unforeseen costs, and diversion of resources from other priority areas.

Our review of the selected case studies highlighted opportunities for enhancing governance and project management. Specifically, it indicates a need for improving transparency in the management of contingencies, risk management and assessments particularly relating to adverse site conditions and the selection of contractors. There is also a need to strengthen forward planning for options to address unfunded priorities within business cases that risk complicating the delivery of future project stages resulting in unforeseen costs and potentially avoidable budget overruns.

Need for increased transparency and accountability in the management of contingency funds

In February 2017, the Ministry's Capital Strategy Group approved the use of surplus funds of $13.76 million from Stage 1 of the Hornsby Ku-ring-gai Hospital Redevelopment for new works deemed needed to support Stage 2. Following this decision, Health Infrastructure finalised and submitted a business case addendum for Stage 1 to the Ministry in March 2017, addressing the new works comprising a two-storey building for medical imaging and paediatric floors. The business case addendum also addressed options to fit out and procure major medical imaging equipment. The Ministry approved the Stage 1 business case in July 2017, noting the Ministry's Capital Strategy Group had already approved the use of remaining Stage 1 funds to deliver the new works.

Stage 1 was completed in 2015, almost two years before the Stage 1 business case addendum was prepared in February 2017.

The Ministry's decision to approve the new works using $13.76 million of surplus Stage 1 funds did not comply with the NSW Treasury Circular TC 12/20. This policy establishes the Treasurer's approval must be sought and received before a new capital project with an Estimated Total Cost of $5.0 million or more can be approved by NSW Health. The Ministry therefore exceeded its delegated authority in making this decision, as it was not evident it had sought and received the Treasurer's approval prior to doing so.

Consequently, the surplus Stage 1 funds should not have been used by the Ministry to deliver new works in the circumstances. Instead, they should have been released from the Stage 1 project in accordance with established NSW Health procedures, and the Stage 1 Estimated Total Cost revised down accordingly. This did not occur, and NSW Health ultimately directed $11.0 million in surplus Stage 1 funds to the new works.

These circumstances indicate a need to strengthen transparency and accountability within NSW Health for the approval of new projects, and how contingency funds are used in the management of major health capital works. They also demonstrate the impact of weaknesses with options appraisal as the initial Stage 1 business case did not consider alternative options for addressing the initially unfunded works later covered by the Stage 1 business case addendum and ultimately funded from the Stage 1 contingency provision.

Weaknesses in service delivery planning resulted in unaccounted-for costs

In addition to proposing the above-noted new works, the 2017 Stage 1 Business Case Addendum for the Hornsby-Ku-ring-gai development sought to retrospectively address the estimated funding gap of around $14.0 million for the internal fit out, supply of major medical imaging equipment, and cost to operate the medical imaging service at Hornsby Ku-ring-gai Hospital also not addressed in the originally Stage 1 business case.

The Stage 1 business case addendum considered various procurement options to purchase and run the medical imaging services ranging from State operation purchase options to private operation purchase options.

It recommended outsourcing the operation and provision of equipment to the private sector based on estimated savings to the public sector initially of around $650,000 per annum reducing over time to $270,000. The Ministry endorsed this option in June 2017, but it did not ultimately proceed.

A July 2018 report to the Executive Steering Committee on the project shows NSW Health later decided to deliver operation of the medical imaging unit 'traditionally' with an updated estimate of the cost at approximately $16.4 million. The report also shows the Ministry supported the costs now being met by the Northern Sydney Local Health District.

This means the funding gap previously identified in the Stage 1 business case addendum for fitting out the medical imaging building and supply of major medical equipment would need to be met fully by the State, representing a $16.4 million cost overrun for the project.

Examined reports to the Executive Steering Committee show this was largely funded by the Northern Sydney Local Health District via the disposal of land realising approximately $15.0 million in proceeds.

This initially unforeseen cost, along with the additional $11.0 million for the new works approved under the Stage 1 business case addendum, were ultimately merged with the Stage 2 project initially approved in 2017–18 with an Estimated Total Cost of $200 million.

The extent of budget variation on the Hornsby Kur-ring-gai development has not been transparent

The 2019–20 State Budget provided an additional $65.0 million for a further Stage 2A to deliver additional built capacity to support outpatient services, enhanced allied health services, re-housed community health services and the delivery of prioritised clinical services unfunded as part of Stage 2. The funds were approved based on an Investment Decision Template (IDT) that examined two options in addition to the base case representing scoping alternatives to the preferred master planned capital solution.

However, we found the IDT showed around 23 per cent of the $65.0 million sought (i.e. $15.0 million) was to be allocated to fund the deficit in Stage 2, which had arisen as a result of project delays due to adverse site conditions. This was not discussed in the IDT.

The February 2020 report to the Executive Steering Committee shows a combined Stage 2 and 2A final forecast cost of $292.6 million against a potential budget of $290.7 million representing an overall deficit for the project of around 0.6 per cent.

However, this favourable final budget position does not transparently show the funding challenges experienced over the project's implementation to-date. The three major budget issues include:

  • inappropriate use of around $11.0 million in Stage 1 contingency for originally unfunded works contrary to Treasury policy
  • the additional $16.4 million cost unforeseen in the Stage 1 business case for delivering medical imaging services mostly funded through the sale of land
  • an additional $15.0 million from Stage 2A to cover the budget overrun in Stage 2 due to adverse site conditions.

The cumulative impact of these events is that Stages 1 and 2 of the Hornsby project cost approximately $42.4 million than it should have in the circumstances around 14 per cent more than what the revised combined Estimated Total Cost for both stages should have been after releasing the $11.0 million in surplus Stage 1 funds, with Stage 2 delayed by around 14 months.

Opportunity for strengthening risk management for adverse site conditions

Major construction projects often experience adverse site conditions which can be difficult to fully detect in advance. However, we found this was a common occurrence in the projects we examined sometimes with significant time and/or budget impacts indicating scope to enhance related risk and cost assessments. Specifically:

  • Hornsby Ku-ring-gai Hospital Redevelopment Stage 2: adverse site conditions during demolition works resulted in an 11-month delay for delivering the medical imaging unit and 14-month delay completing Stage 2 main works including need for additional $15.0 million in funds to cover the resultant budget deficit for the project.
  • Blacktown Mt Druitt Hospital Redevelopment Stage 2: adverse site conditions combined with project complexity delayed completion of the early works by approximately five months. This contributed to the delay in completing the main construction works which occurred around nine months later than planned in the business case.
  • Dubbo Health Service Redevelopment Stages 3 and 4: Health Infrastructure advised adverse site conditions including asbestos containing materials and ground conditions delayed works for the main building with completion forecast for March 2021, around 21 months later than planned in the final business case. This resulted in the need for additional $13.5 million to cover increased construction costs and risks, increasing the Stage 3 and 4 forecast final cost from $150 million to $163.5 million as at February 2020.

These examples indicate a risk the cumulative impact of adverse site conditions may be substantial when measured across both time and Health Infrastructure's full delivery program. They also point to potential for Health Infrastructure to achieve efficiencies and improved outcomes from strengthening its approach to assessing and mitigating the risks from adverse site conditions.

Limited due diligence with prospective contractors risks avoidable delays and costs

Main construction works on Stage 1 of the Dubbo Health Service Redevelopment were completed in October 2015, approximately 13 months later than planned in the final business case. Delays were mainly due to insolvency of the early works contractor resulting in their departure from the project. The ensuing 11-month delay in completing the early works significantly impacted the overall schedule and delivery of main construction works.

The insolvency event was significant as it affected nine separate Health Infrastructure projects – three of which had yet to reach practical completion. It also affected state-funded projects in other sectors. It resulted in the need for additional funding of $11.5 million that was provided in the 2014–15 State Budget increasing the total Stage 1 and 2 budget from $79.8 million to $91.3 million.

Health Infrastructure’s analysis of lessons learned shows it worked actively to mitigate the impacts of the insolvency event across all affected projects. However, it also indicates a risk the lessons were mainly focused on mitigating the impacts after an insolvency event occurred rather than on prevention.

Although Health Infrastructure initially commissioned a financial assessment of the now insolvent early works contractor before engagement, it did not detect any risks of the impending insolvency and instead concluded the contractor was in a strong financial position. However, the contractor became insolvent shortly after commencement approximately seven months later. This indicates a risk of weaknesses in the assessment performed that was not explicitly addressed by the lessons learned.

Delivery of the main construction works were further impacted by disputes with the main works contractor over the scope of works for the renal unit resulting in Health Infrastructure terminating the contract in November 2016 following lengthy negotiations over several months.

The scope of works relating to the renal unit were ultimately transferred to Stages 3 and 4 and were delivered in December 2019, around five years later than originally planned in the business case.

Health Infrastructure advised the delay was ultimately beneficial to the project because the refurbishment works for the renal unit, initially scheduled for Stages 1 and 2, would have been demolished to accommodate the new Western Cancer Centre proposed after Stages 1 and 2 and currently being delivered in parallel with Stages 3 and 4.

Health Infrastructure advised the actual cost of Stages 1 and 2 was $84.7 million against the budget of $91.3 million. The residual $6.6 million relates to the renal works not delivered during Stage 1 and 2 and transferred to Stage 3 and 4.

Health Infrastructure advised the contractual provisions for mitigating insolvency events 'in-flight' are limited highlighting the importance of proactive and effective due diligence prior to engaging contractors for significant construction projects.

Need for a quality framework linked to staff training and capability development

Health Infrastructure's 2017-20 Corporate Plan identifies the development of a quality framework to support delivery of future-focused outcomes as a key organisational priority. Related initiatives within the Corporate Plan describe a framework underpinned by a Quality Committee providing advice on:

  • records management, to meet the requirements of the State Records Act 1998
  • project assurance, to ensure future focused outcomes and enhance Health Infrastructure's Standards, Policies, Procedures and Guidelines, Templates and Design Guidance Notes
  • knowledge management and library services, to promote and leverage from project learnings.

Although Health Infrastructure has some elements of a quality framework it is not yet fully in place. Health Infrastructure advised it had yet to establish the quality framework and related committee described in its Corporate Plan due in part to its focus on responding to the growth of its capital program.

Health Infrastructure's Development and Innovation team has been active in supporting continuous improvement in knowledge and project management including development of business cases. Although useful, these initiatives have relied heavily on leveraging and disseminating insights from Gateway reviews and have not formed part of a systematic quality and continuous improvement framework.

The limited focus on the quality of business cases is reflected in internal performance monitoring and reporting which focuses mainly on tracking the delivery of projects against internal benchmarks, often revised from the baselines in the business case, and expenditure against cashflow targets. There is no evident internal monitoring and/or reporting to the Chief Executive and Board on defined quality metrics linked to business case development and staff capability.

Performance reporting on balanced scorecard metrics has similarly focused mainly on process rather than quality and has been inconsistent in recent years.

Appendix one – Response from agency

Appendix two – About the audit

Appendix three – Performance auditing

Appendix four – Ministry of Health planning tools and guidelines

Appendix five – Streamlined investment decision process for Health Capital Projects

Appendix six – Timeline of business cases and relevant policy guidelines

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #338 - released 12 August 2020

Published

Actions for Their Futures Matter

Their Futures Matter

Justice
Community Services
Education
Health
Whole of Government
Cross-agency collaboration
Internal controls and governance
Management and administration
Project management

The Auditor-General for New South Wales, Margaret Crawford, released a report today examining whether the Department of Communities and Justice had effective governance and partnership arrangements in place to deliver ‘Their Futures Matter’.

Their Futures Matter was intended to place vulnerable children and families at the heart of services, and direct investment to where funding and programs deliver the greatest social and economic benefits. It was a four-year whole-of-government reform in response to the 2015 Tune Review of out-of-home care.

The Auditor-General found that while important foundations were put in place, and new programs trialled, the key objective to establish an evidence-based whole-of-government early intervention approach for vulnerable children and families in NSW was not achieved.

Governance and cross-agency partnership arrangements to deliver Their Futures Matter were found to be ineffective. 'Their Futures Matter lacked mechanisms to secure cross portfolio buy‑in and did not have authority to drive reprioritisation of government investment', the Auditor-General said.

At the reform’s close, the majority of around $380 million in investment funding remains tied to existing agency programs, with limited evidence of their comparative effectiveness or alignment with Their Futures Matter policy objectives. The reform concluded on 30 June 2020 without a strategy or plan in place to achieve its intent.

The Auditor-General made four recommendations to the Department of Communities and Justice, aimed at improving implementation of outstanding objectives, revising governance arrangements, and utilising the new human services data set to address the intent of the reform. However, these recommendations respond only in part to the findings of the audit.

According to the Auditor-General, ‘Cross-portfolio leadership and action is required to ensure a whole-of-government response to delivering the objectives of Their Futures Matter to improve outcomes for vulnerable children, young people and their families in New South Wales.’

Read full report (PDF)

In 2016, the NSW Government launched 'Their Futures Matter' (TFM) - a whole-of-government reform aimed at delivering improved outcomes for vulnerable children, young people and their families. TFM was the government's key response to the 2015 Independent Review of Out of Home Care in New South Wales (known as 'the Tune Review').

The Tune Review found that, despite previous child protection reforms, the out of home care system was ineffective and unsustainable. It highlighted that the system was not client-centred and was failing to improve the long-term outcomes for vulnerable children and families. The review found that the greatest proportion of relevant expenditure was made in out of home care service delivery rather than in evidence-based early intervention strategies to support children and families when vulnerabilities first become evident to government services (such as missed school days or presentations to health services).

The then Department of Family and Community Services (FACS) designed the TFM reform initiatives, in consultation with central and human services agencies. A cross-agency board, senior officers group, and a new unit in the FACS cluster were established to drive the implementation of TFM. In the 2016–17 Budget, the government allocated $190 million over four years (2016–17 to 2019–20) to the reform. This resourced the design and commissioning of evidence-based pilots, data analytics work, staffing for the implementation unit and secretariat support for the board and cross-agency collaboration.

As part of the TFM reform, the Department of Premier and Cabinet, NSW Treasury and partnering agencies (NSW Health, Department of Education and Department of Justice) identified various existing programs that targeted vulnerable children and families (such as the preceding whole-of-government ‘Keep Them Safe’ reform coming to an end in June 2020). Funding for these programs, totalling $381 million in 2019–20, was combined to form a nominal ‘investment pool’. The government intended that the TFM Implementation Board would use this pool to direct and prioritise resource allocation to evidence-based interventions for vulnerable children and families in NSW.

This audit assessed whether TFM had effective governance and partnership arrangements in place to enable an evidence-based early intervention investment approach for vulnerable children and families in NSW. We addressed the audit objective with the following audit questions:

  • Was the TFM reform driven by effective governance arrangements?
  • Was the TFM reform supported by effective cross-agency collaboration?
  • Has the TFM reform generated an evidence base to inform a cross-agency investment approach in the future?

The audit did not seek to assess the outcomes for children, young people and families achieved by TFM programs and projects.

Conclusion

The governance and cross-agency partnership arrangements used to deliver the Their Futures Matter reform were ineffective. Important foundations were put in place, and new programs trialled over the reform's four years. However, an evidence-based whole-of-government early intervention approach for vulnerable children and families in NSW − the key objective of the reform − was not established. The reform concluded in June 2020 without a strategy or plan in place to achieve its intent.

The governance arrangements established for the Their Futures Matter (TFM) reform did not provide sufficient independence, authority and cross-agency clout to deliver on the reform’s intent. This hindered delivery of the reform's key elements, particularly the redirection of funding to evidence-based earlier intervention supports, and limited the impact that TFM could have on driving system change.

TFM increased focus on the contribution that other agencies outside of the former Family and Community Services portfolio could make in responding to the needs of vulnerable children and families, and in reducing the demand costs of related government service delivery. Despite being a whole-of-government reform, TFM lacked mechanisms to secure cross-portfolio buy-in and lacked the powers to drive reprioritisation of government investment in evidence-based and earlier intervention supports across agencies. At the reform’s close, the majority of the reform's investment pool funding remained tied to existing agency programs, with limited evidence of their comparative effectiveness or alignment with Their Futures Matter policy objectives.

TFM began building an evidence base about ‘what works’, including piloting programs and creating a new dataset to identify risk factors for vulnerability and future costs to government. However, this evidence base does not yet comprehensively map how existing services meet needs, identify system duplications or gaps, nor demonstrate which government funded supports and interventions are most effective to make a difference to life outcomes for vulnerable children and families in NSW.
Despite these issues, the need, intent and vision for Their Futures Matter remains relevant and urgent, as issues identified in the Tune Review remain pertinent.

Their Futures Matter (TFM) is a whole-of-government reform to deliver improved outcomes for vulnerable children, young people and their families.

Supported by a cross-agency TFM Board, and the TFM Unit in the then Department of Family and Community Services (FACS), the reform aimed to develop whole-of-government evidence-based early intervention investment approaches for vulnerable children and families in NSW.

Governance refers to the structures, systems and practices that an organisation has in place to:

  • assign decision-making authorities and establish the organisation's strategic direction
  • oversee the delivery of its services, the implementation of its policies, and the monitoring and mitigation of its key risks
  • report on its performance in achieving intended results, and drive ongoing improvements.

We examined whether the TFM reform was driven by effective governance arrangements and cross-agency collaboration.

The reform agenda and timeframe set down for Their Futures Matter (TFM) were ambitious. This chapter assesses whether the TFM Board and TFM Unit had the capability, capacity and clout within government to deliver the reform agenda.

Creating a robust evidence base was important for Their Futures Matter, in order to:

  • identify effective intervention strategies to improve supports and outcomes for vulnerable children and families
  • make efficient use of taxpayer money to assist the maximum number of vulnerable children and families
  • inform the investment-based approach for future funding allocation.

This chapter assesses whether the TFM reform has developed an evidence base to inform cross-agency investment decisions.

Appendix one – Response from agency

Appendix two – TFM governance entities

Appendix three – TFM Human Services Data Set

Appendix four – TFM pilot programs

Appendix five – About the audit

Appendix six – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Parliamentary reference - Report number #337 - released 24 July 2020

Published

Actions for CBD South East Sydney Light Rail: follow-up performance audit

CBD South East Sydney Light Rail: follow-up performance audit

Transport
Infrastructure
Internal controls and governance
Management and administration
Procurement
Project management
Risk
Service delivery

This is a follow-up to the Auditor-General's November 2016 report on the CBD South East Sydney Light Rail project. This follow-up report assessed whether Transport for NSW has updated and consolidated information about project costs and benefits.

The audit found that Transport for NSW has not consistently and accurately updated project costs, limiting the transparency of reporting to the public.

The Auditor-General reports that the total cost of the project will exceed $3.1 billion, which is above the revised cost of $2.9 billion published in November 2019. $153.84 million of additional costs are due to omitted costs for early enabling works, the small business assistance package and financing costs attributable to project delays.

The report makes four recommendations to Transport for NSW to publicly report on the final project cost, the updated expected project benefits, the benefits achieved in the first year of operations and the average weekly journey times.

Read full report (PDF)

The CBD and South East Light Rail is a 12 km light rail network for Sydney. It extends from Circular Quay along George Street to Central Station, through Surry Hills to Moore Park, then to Kensington and Kingsford via Anzac Parade and Randwick via Alison Road and High Street.

Transport for NSW (TfNSW) is responsible for planning, procuring and delivering the Central Business District and South East Light Rail (CSELR) project. In December 2014, TfNSW entered into a public private partnership with ALTRAC Light Rail as the operating company (OpCo) responsible for delivering, operating and maintaining the CSELR. OpCo engaged Alstom and Acciona, who together form its Design and Construct Contractor (D&C).

On 14 December 2019, passenger services started on the line between Circular Quay and Randwick. Passenger services on the line between Circular Quay and Kingsford commenced on 3 April 2020.

In November 2016, the Auditor-General published a performance audit report on the CSELR project. The audit found that TfNSW would deliver the CSELR at a higher cost with lower benefits than in the approved business case, and recommended that TfNSW update and consolidate information about project costs and benefits and ensure the information is readily accessible to the public.

In November 2018, the Public Accounts Committee (PAC) examined TfNSW's actions taken in response to our 2016 performance audit report on the CSELR project. The PAC recommended that the Auditor-General consider undertaking a follow-up audit on the CSELR project. The purpose of this follow-up performance audit is to assess whether TfNSW has effectively updated and consolidated information about project costs and benefits for the CSELR project.

Conclusion

Transport for NSW has not consistently and accurately updated CSLER project costs, limiting the transparency of reporting to the public. In line with the NSW Government Benefits Realisation Management Framework, TfNSW intends to measure benefits after the project is completed and has not updated the expected project benefits since April 2015.

Between February 2015 and December 2019, Transport for NSW (TfNSW) regularly updated capital expenditure costs for the CSELR in internal monthly financial performance and risk reports. These reports did not include all the costs incurred by TfNSW to manage and commission the CSELR project.

Omitted costs of $153.84 million for early enabling works, the small business assistance package and financing costs attributable to project delays will bring the current estimated total cost of the CSELR project to $3.147 billion.

From February 2015, TfNSW did not regularly provide the financial performance and risk reports to key CSELR project governance bodies. TfNSW publishes information on project costs and benefits on the Sydney Light Rail website. However, the information on project costs has not always been accurate or current.

TfNSW is working with OpCo partners to deliver the expected journey time benefits. A key benefit defined in the business plan was that bus services would be reduced owing to transfer of demand to the light rail - entailing a saving. However, TfNSW reports that the full expected benefit of changes to bus services will not be realised due to bus patronage increasing above forecasted levels.

Appendix one – Response from agency

Appendix two – Governance and reporting arrangements for the CSELR

Appendix three – 2018 CSELR governance changes

Appendix four – About the audit

Appendix five – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #335 - released 11 June 2020

Published

Actions for Train station crowding

Train station crowding

Transport
Management and administration
Risk
Service delivery
Workforce and capability

This report focuses on how Transport for NSW and Sydney Trains manage crowding at selected metropolitan train stations.

The audit found that while Sydney Trains has identified platform crowding as a key strategic risk, it does not have an overarching strategy to manage crowding in the short to medium term. Sydney Trains 'do not have sufficient oversight to know if crowding is being effectively managed’, the Auditor-General said.

Sydney Trains' operational response to crowding involves restricting customer access to platforms or station entries before crowding reaches unsafe levels or when it impacts on-time running. Assuming rail patronage increases, it is likely that Sydney Trains will restrict more customers from accessing platforms or station entries, causing customer delay. ‘Restricting customer access to platforms or station entries is not a sustainable approach to manage station crowding’, said the Auditor-General.

The Auditor-General made seven recommendations to improve Transport for NSW and Sydney Trains' management of station crowding. Transport for NSW have accepted these recommendations on behalf of the Transport cluster.

Public transport patronage has been impacted by COVID-19. This audit was conducted before these impacts occurred.

Read full report (PDF)

Sydney Trains patronage has increased by close to 34 per cent over the last five years, and Transport for NSW (TfNSW) expects the growth in patronage to continue over the next 30 years. As patronage increases there are more passengers entering and exiting stations, moving within stations to change services, and waiting on platforms. As a result, some Sydney metropolitan train stations are becoming increasingly crowded.

There are three main causes of station crowding:

  • patronage growth exceeding the current capacity limits of the rail network
  • service disruptions
  • special events.

Crowds can inhibit movement, cause discomfort and can lead to increased health and safety risks to customers. In the context of a train service, unmanaged crowds can affect service operation as trains spend longer at platforms waiting for customers to alight and board services which can cause service delays. Crowding can also prevent customers from accessing services.

Our 2017 performance audit, ‘Passenger Rail Punctuality’, found that rail agencies would find it hard to maintain train punctuality after 2019 unless they significantly increased the capacity of the network to carry trains and people. TfNSW and Sydney Trains have plans to improve the network to move more passengers. These plans are set out in strategies such as More Trains, More Services and in the continued implementation of new infrastructure such as the Sydney Metro. Since 2017, TfNSW and Sydney Trains have introduced 1,500 more weekly services to increase capacity. Additional network capacity improvements are in progress for delivery from 2022 onwards.

In the meantime, TfNSW and Sydney Trains need to use other ways of managing crowding at train stations until increased capacity comes on line.

This audit examined how effectively TfNSW and Sydney Trains are managing crowding at selected metropolitan train stations in the short and medium term. In doing so, the audit examined how TfNSW and Sydney Trains know whether there is a crowding problem at stations and how they manage that crowding.

TfNSW is the lead agency for transport in NSW. TfNSW is responsible for setting the standard working timetable that Sydney Trains must implement. Sydney Trains is responsible for operating and maintaining the Sydney metropolitan heavy rail passenger service. This includes operating, staffing and maintaining most metropolitan stations. Sydney Trains’ overall responsibility is to run a safe rail network to timetable.

Conclusion

Sydney Trains has identified platform crowding as a key strategic risk, but does not have an overarching strategy to manage crowding in the short to medium term. TfNSW and Sydney Trains devolve responsibility for managing crowding at stations to Customer Area Managers, but do not have sufficient oversight to know if crowding is being effectively managed. TfNSW is delivering a program to influence demand for transport in key precincts but the effectiveness of this program and its impact on station crowding is unclear as Transport for NSW has not evaluated the outcomes of the program.

TfNSW and Sydney Trains do not directly measure or collect data on station crowding. Data and observation on dwell time, which is the time a train waits at a platform for customers to get on and off trains, inform the development of operational approaches to manage crowding at stations. Sydney Trains has KPIs on reliability, punctuality and customer experience and use these to indirectly assess the impact of station crowding. TfNSW and Sydney Trains only formally assess station crowding as part of planning for major projects, developments or events.

Sydney Trains devolve responsibility for crowd management to Customer Area Managers, who rely on frontline Sydney Trains staff to understand how crowding affects individual stations. Station staff at identified key metropolitan train stations have developed customer management plans (also known as crowd management plans). However, Sydney Trains does not have policies to support the creation, monitoring and evaluation of these plans and does not systematically collect data on when station staff activate crowding interventions under these plans.

Sydney Trains stated focus is on providing a safe and reliable rail service. As such, management of station crowding is a by-product of its strategies to manage customer safety and ensure on-time running of services. Sydney Trains' operational response to crowding involves restricting customer access to platforms or stations before crowding reaches unsafe levels, or when it impacts on-time running. As rail patronage increases, it is likely that Sydney Trains will need to increase its use of interventions to manage crowding. As Sydney Trains restrict more customers from accessing platforms or station entries, it is likely these customers will experience delays caused by these interventions.

Since 2015, TfNSW has been delivering the 'Travel Choices' program which aims to influence customer behaviour and to manage the demand for public transport services in key precincts. TfNSW is unable to provide data demonstrating the overall effectiveness of this program and the impact the program has on distributing public transport usage out of peak AM and PM times. TfNSW and Sydney Trains continue to explore initiatives to specifically address crowd management.

Conclusion

TfNSW and Sydney Trains do not directly measure or collect data on station crowding. There are no key performance indicators directly related to station crowding. Sydney Trains uses performance indicators on reliability, punctuality and customer experience to indirectly assess the impact of station crowding. Sydney Trains does not have a routine process for identifying whether crowding contributed to minor safety incidents. TfNSW and Sydney Trains formally assess station crowding as part of planning for major projects, developments or events.

 

Conclusion

Sydney Trains has identified platform crowding as a strategic risk but does not have an overarching strategy to manage station crowding. Sydney Trains' stated focus is on providing a safe and reliable rail service. As such, management of station crowding is a by-product of its strategies to manage customer safety and ensure on-time running of services.

Sydney Trains devolve responsibility for managing crowding at stations to Customer Area Managers but does not have sufficient oversight to know that station crowding is effectively managed. Sydney Trains does not have policies to support the creation, monitoring or evaluation of crowd management plans at key metropolitan train stations. The use of crowding interventions is likely to increase due to increasing patronage, causing more customers to experience delays directly caused by these activities.

TfNSW and Sydney Trains have developed interventions to influence customer behaviour and to manage the demand for public transport services but are yet to evaluate these interventions. As such, their impact on managing station crowding is unclear.

Appendix one – Response from agency

Appendix two – Sydney rail network

Appendix three – Rail services contract

Appendix four – Crowding pedestrian modelling

Appendix five – Airport Link stations case study

Appendix six – About the audit

Appendix seven – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #333 - released 30 April 2020

 

Published

Actions for Managing demand for ambulance services 2017

Managing demand for ambulance services 2017

Health
Information technology
Management and administration
Risk
Service delivery
Shared services and collaboration
Workforce and capability

NSW Ambulance has introduced several initiatives over the past decade to better manage the number of unnecessary ambulance responses and transports to hospital emergency departments. However, there is no overall strategy to guide the development of these initiatives nor do NSW Ambulance's data systems properly monitor their impact. As a result, the Audit Office was unable to assess whether NSW Ambulance's approach to managing demand is improving the efficiency of ambulance services.

Demand for ambulance services is increasing. Demographic factors including population growth and ageing have contributed to this and ongoing growth in demand is likely. It is important that NSW Ambulance finds ways to respond to this demand more efficiently, while maintaining patient safety standards and meeting community expectations.

Most triple zero calls to NSW Ambulance do not involve medical issues that require an emergency response. NSW Ambulance has introduced a range of initiatives to change the way it manages these less urgent requests for assistance. Its major demand management initiatives include using a telephone advice line, referring some patients to services other than hospital emergency departments and using specialist paramedics to respond to less urgent cases.

The role of NSW Ambulance has changed in recent years. It is aiming to become a ‘mobile health service’ that identifies the needs of patients and provides or refers them to the most appropriate type of care. This change involves a significant expansion of the clinical decision-making role of paramedics. Considerable strategic and organisational efforts are required to make this work. The successful implementation of demand management initiatives is important to NSW Ambulance's ability to continue to meet demand for its services.

This audit assessed NSW Ambulance's major demand management initiatives that aim to reduce unnecessary demand for ambulance responses and unnecessary transport to hospital emergency departments. It aimed to assess the extent to which these initiatives have improved the efficiency of its services.

Conclusion

NSW Ambulance has introduced several initiatives that aim to manage demand for its services from less urgent cases more efficiently. There is no overall strategy for these initiatives and NSW Ambulance’s data systems do not measure their outputs or outcomes. As a result, we are unable to assess the impact of NSW Ambulance's demand management initiatives on the efficiency of ambulance services. More focus is needed to ensure these initiatives achieve the efficiency improvements necessary to help NSW Ambulance meet future increases in demand.

Increasing demand for ambulance services is a key issue for NSW Ambulance. Demand has increased at a faster rate than population growth in recent years and continued growth is expected. NSW Ambulance has introduced several initiatives that aim to manage demand for its services from people with less urgent medical issues more efficiently and align its approach with the rest of the health system in New South Wales.

These individual initiatives lack a broader strategy to guide their development. NSW Ambulance’s demand management initiatives also lack clear goals and performance targets, with insufficient organisational resources allocated to support their implementation. NSW Ambulance does not have a data system that allows it to conduct accurate routine monitoring of the activity and performance of these initiatives.

More effort is required to make demand management initiatives a core part of NSW Ambulance's work. Key relationships with other health services to support demand management initiatives have only recently been established. NSW Ambulance has not communicated proactively with the public about its demand management initiatives. To ensure paramedics are as well prepared as possible for their expanded roles, they need better professional development and up to date technology.

Demand for ambulance services in New South Wales is increasing steadily. Forecast future increases in demand due to population growth and ageing mean that NSW Ambulance must improve its efficiency to maintain its performance.

Demand for ambulance services is growing at a rate higher than population growth. The increase in demand is likely to continue as the population continues to grow and age. NSW Ambulance has made several recent changes to remove large parts of demand for its services, including moving non-emergency patient transport to a separate government agency and changing the way triple zero calls are categorised.

These changes were expected to improve emergency response time performance, but the anticipated improvements have not been achieved. If demand continues to increase as forecast, NSW Ambulance will need to find more efficient ways to manage demand to maintain its performance.

NSW Ambulance has introduced initiatives to change the way it manages demand from patients who have less urgent medical issues. These have the potential to achieve positive results, but we were unable to fully assess their impact because of weaknesses in data systems and monitoring. More needs to be done to demonstrate progress toward the efficiency improvements required.

NSW Ambulance uses a telephone referral system to manage triple zero calls from people with medical issues that do not require an ambulance. This has the potential to achieve efficiency improvements but there are weaknesses in NSW Ambulance's use and monitoring of this system. Paramedics are now able to make decisions about whether patients need transport to a hospital emergency department. NSW Ambulance does not routinely measure or monitor the decisions paramedics make, so it does not know whether these decisions are improving efficiency. Extended Care Paramedics who have additional skills in diagnosing and treating patients with less urgent medical issues were introduced in 2007. NSW Ambulance analysis indicates that these paramedics have the potential to improve efficiency, but have not been used as effectively as possible.

Our 2013 audit of NSW Ambulance found that accurate monitoring of activity and performance was not being conducted. More than four years later, this remains the case. 

NSW Ambulance has recognised the need to change the way it manages demand and has developed initiatives that have the potential to improve efficiency. However, there are significant weaknesses in the strategy for and implementation of its demand management initiatives.

NSW Ambulance has identified the goal of moving from an emergency transport provider to a mobile health service and developed several initiatives to support this. Its demand management initiatives have the potential to contribute to the broader policy directions for the health system in New South Wales. However, there is no clear overall strategy guiding these initiatives and their implementation has been poor.

NSW Ambulance's reasons for changing its approach to demand management have not been communicated proactively to the community. Demand management initiatives that have been operating for over a decade still do not have clear performance measures or targets. Project management of new initiatives has been inadequate, with insufficient organisational resources to oversee them and inadequate engagement with other healthcare providers.

NSW Ambulance uses an in-house Vocational Education and Training course to recruit some paramedics, as well as recruiting paramedics who have completed a university degree. No other Australian ambulance services continue to provide their own Vocational Education and Training qualifications. Paramedics will need more support in several key areas to be able to fulfil their expanded roles in providing a mobile health service. Performance and development systems for paramedics are not used effectively. Up to date technology would help paramedics make better decisions and improve NSW Ambulance's ability to monitor demand management activity.

There are gaps in NSW Ambulance's oversight of the risks of some of the initiatives it has introduced, particularly its lack of information on the outcomes for patients who are not transported to hospital. Weaknesses in the way NSW Ambulance uses its data limit its ability to properly assess the risks of the demand management initiatives it has introduced.

Appendix one - Response from agency

Appendix two - About the audit

Appendix three - Performance auditing

 

Parliamentary reference - Report number #295 - released 13 December 2017

Published

Actions for Sharing school and community facilities

Sharing school and community facilities

Education
Infrastructure
Management and administration
Risk
Shared services and collaboration

Schools and the community would benefit if school facilities were shared more often. 

The Department of Education’s ‘Community Use of School Facilities Policy’ encourages but does not require schools to share facilities. Sharing depends heavily on the willingness of school principals and there are few incentives. There are many challenges in developing agreements with community users and there is only limited support available from the Department.

There are strategies and plans to support the sharing of facilities between schools and the wider community, but none are backed up with budgets, specific plans or timeframes.

Governments should strive for the best use of assets. This is particularly important in the context of a growing New South Wales population, fiscal constraints and increasing demand for services. 

Lack of available land, rising land costs and population growth highlighted in our April 2017 'Planning for school infrastructure' performance audit report mean that new and existing schools will need to share their facilities with communities more than is currently the case.

This audit assessed how effectively schools share facilities with each other, local councils and community groups. In making this assessment, the audit examined whether the Department of Education (Department):

  • has a clear policy to encourage and support facilities sharing
  • is implementing evidence-based strategies and procedures for facilities sharing
  • can show it is realising an increasing proportion of sharing opportunities.

Facilities sharing is the use of a physical asset, such as a building, rooms, or open spaces, by more than one group for a range of activities at the same time or at different times. For the purposes of this audit, we have divided sharing arrangements into two types: shared use and joint use.

Shared use refers to arrangements where existing school assets are hired out for non-school purposes, usually for a limited time. The assets remain under the control of the school. Generally, there is little alteration or enhancement to the asset required to enable shared use. Shared use can also refer to schools using external facilities, such as council pools, but these arrangements are not included within the scope of this audit. 

Joint use refers to arrangements where new or upgraded school and non-school facilities or community hubs are planned, funded, built and jointly shared between a school and other parties, usually involving significant investment. 

Both shared use and joint use agreements are governed by contractual obligations.

Conclusion
The sharing of school facilities with the community is not fully effective. The Department of Education is implementing strategies to increase shared and joint use but several barriers, some outside the Department’s direct control, must be addressed to fully realise benefits to students and the community of sharing school facilities. In addition, the Department needs to do more to encourage individual schools to share facilities with the community. 

A collaborative, multi-agency approach is needed to overcome barriers to the joint use of facilities, otherwise, the Department may need significantly more funds than planned to deliver sufficient fit-for-purpose school facilities where and when needed.
Government policies encourage, but do not mandate, shared and joint use of facilities.

Since the early 2000’s, several reviews in NSW and other jurisdictions have commented on the benefits of and need to increase the sharing of school facilities. 

Several NSW Government strategies and plans support shared and joint use of facilities between schools and the wider community, but none are backed up with financial incentives, or specific plans with implementation timeframes. In Victoria and Queensland whole-of-government processes are in place to support a more coordinated approach to planning, building and sharing community facilities. For example, Victoria has a comprehensive policy framework encompassing both existing and future use of community facilities and a $50 million program to seed the development of community facilities on school sites over the next four years.  
The Department recognises benefits from the shared use of school facilities, but provides insufficient support to Principals to ensure costs are recovered and that money raised from shared use can be spent by the school in a timely manner. 

There are examples of successful shared use, but more can be done. Information about the available facilities is not readily available to potential community users. Schools should work more closely with councils and other stakeholders to leverage shared use. 

Currently, the administrative burden, costs and risks associated with shared use can exceed the perceived benefits to schools, leading to reluctance amongst some Principals to share. In addition, a substantial backlog of school-initiated infrastructure proposals awaiting Departmental approval means that schools that raise money from sharing their facilities find it difficult to use the funds they raise on improved infrastructure. Some of these proposals have been waiting for approval for more than 12 months. 

The Department could do more to support Principals by ensuring the fees charged for facilities cover the costs incurred by schools, that Principals can access help with negotiating and managing contracts, and that infrastructure proposals initiated and funded by schools are approved in a timely manner. 

The Department is not monitoring shared use across the State, and does not evaluate different approaches as evidence to influence policies and procedures.

Recommendations
By December, 2018, the Department should:
  • increase incentives and reduce impediments for school Principals to share school facilities, including:
    • review the methodology for calculating fees charged for facilities to ensure that shared use of school facilities does not result in a financial burden to schools or the Department 
    • improve support provided to Principals by School Infrastructure NSW, including reducing the backlog of school-initiated infrastructure proposals awaiting approval
    • develop service standards, including timeframes, for assessing and approving school-initiated infrastructure proposals.
  • provide readily-accessible information about available school facilities to community groups and local councils
  • implement processes to monitor and regularly evaluate the implementation of the shared use policy and promote better practice to drive improvements.
The Department is planning a more strategic approach to increase the joint use of school facilities. However, several barriers, some outside the Department’s control, must be addressed to fully realise benefits of joint use agreements.

As discussed in our 2017 audit report on ‘Planning for school infrastructure’, joint use agreements are a key direction of the School Assets Strategic Plan. Joint use of school facilities will be necessary to ensure that there will be enough fit-for-purpose learning spaces for students when and where needed. Under the ‘Community Use of School Facilities Policy’ Principals play the leading role in identifying opportunities, and developing and managing agreements for sharing school facilities. This is impractical for joint use projects which involve substantial investment in new or refurbished assets, in particular for joint use projects in schools that are yet to be built. In addition, the policy does not address joint-use facilities built on land not owned by the Department. For these reasons, the Department is developing a new policy. 

The Department is planning to develop joint use agreements in a more systematic way as part of school community planning, previously known as cluster planning, with a special focus on local councils. Several agreements are currently being piloted, and will be evaluated to provide an evidence-based foundation for this new approach. 

To develop or refurbish school facilities for joint use, the Department, councils and other key stakeholders must work together and prioritise joint use from the earliest stages of any project. A collaborative, multi-agency approach is needed to ensure sufficient fit-for-purpose facilities are available for school students within the funding framework proposed in the School Assets Strategic Plan. 

To increase shared and joint use, the Department is recruiting specialist staff in its Asset Division to assist with the brokerage, community engagement and development of agreements, but these staff are not dedicated to joint use projects and their available time may not be sufficient to provide the necessary support in the timeframes required.

Recommendations
By December, 2018, the Department of Education should:
  • ensure that the implementation of the new ‘Joint Use of School Facilities and Land Policy’ is adequately resourced, and has the support of Principals
  • implement processes to monitor and regularly evaluate the implementation of joint use policy and promote better practice to drive improvements.  

Published

Actions for Planning and evaluating palliative care services in NSW

Planning and evaluating palliative care services in NSW

Health
Management and administration
Service delivery
Workforce and capability

NSW Health’s approach to planning and evaluating palliative care is not effectively coordinated. There is no overall policy framework for palliative and end-of-life care, nor is there comprehensive monitoring and reporting on services and outcomes.

Palliative care is an essential component of modern health care services and an increasingly important part of the wider health and social care systems. Palliative care is healthcare and support for people with a life-limiting illness, their families and carers. It is provided by, or informed by, professionals who specialise in palliative care. ‘End of life’ care is provided to people approaching the end of life by health professionals, who may work in the health, community or aged care systems. Not everyone receiving end of life care needs palliative care.

NSW Health has a policy and planning role in palliative and end-of-life care, and it coordinates a wide range of service providers. Local Health Districts (LHDs) provide care services in settings such as homes, hospitals and clinics to patients with varying needs. There are several care providers that can be involved.

Due to this shared nature of palliative care — where many people, services and settings are involved in delivering care to the patient — availability and communication of information is critical. For service planning, data and evidence must be drawn from various sources in a timely and efficient way.

This audit assessed whether NSW Health is effectively planning and evaluating palliative care services, in the context of rising demand, increasingly complex needs, and the diversity of service providers.

Conclusion 

NSW Health’s approach to planning and evaluating palliative care is not effectively coordinated. There is no overall policy framework for palliative and end-of-life care, nor is there comprehensive monitoring and reporting on services and outcomes.  

NSW Health has a limited understanding of the quantity and quality of palliative care services across the state, which reduces its ability to plan for future demand and the workforce needed to deliver it. At the district level, planning is sometimes ad hoc and accountability for performance is unclear.

The capacity of LHDs to use accurate and complete data to plan and deliver services is hindered by multiple disjointed information systems and manual data collections. Further, a data collection on patient outcomes, for benchmarking and quality improvement, is not used universally. This limits the ability of districts to plan, benchmark and improve services based on outcomes data.

NSW Health's engagement with stakeholders is not systematic. The lack of an overall stakeholder engagement strategy puts at risk the sustainability and value of stakeholder input in planning and limits transparency.

Over the last two years, NSW Health has taken steps to improve its planning and support for districts. The Agency for Clinical Innovation has produced an online resource which will assist LHDs in constructing their own, localised models of care. eHealth, which coordinates information communication technology for the state’s healthcare, aims to invest in integrating and improving information systems. These initiatives should help to address many of the issues now inhibiting integrated service delivery, reporting on activity and outcomes, and planning for the future.

1. By July 2018, NSW Health should develop an integrated palliative and end-of-life care policy framework that:

  • clearly articulates the interface between palliative and end of life care and outlines the priorities for the respective areas
  • defines policy goals and objectives, and a performance and evaluation framework for palliative care service planning and delivery
  • informs a related workforce plan which supports the policy framework and is linked to the Health Professional Workforce Plan 2012–2022
  • reviews the funding allocation model to ensure future enhancement funds are distributed equitably and transparently based on the need and population of districts.

By December 2018, NSW Health should:

2. assess how the functionality provided in data collection programs such as the Palliative Care Outcomes Collaboration program can be provided across all palliative care services in NSW

3. complete its statewide review of systems and reporting for end of life management including specialist palliative care, and develop a business case to implement a more integrated set of solutions to:

  • support providers delivering end of life and palliative care
  • help monitor service quality and quantity
  • provide comprehensive data for service planning

4. improve stakeholder engagement by:

  • developing a statewide stakeholder engagement strategy that brings together current activity and good practice, and is transparent and publicly available
  • defining accountability for overseeing and implementing the strategy at state and district levels.

1. Performance monitoring is inadequate

NSW Government policy on palliative care is outlined in the NSW Government Plan to Increase Access to Palliative Care 2012–2016 (the Plan). Under the Plan, the overarching policy is ‘to ensure that everyone has access to quality palliative care regardless of their economic or social circumstances, their geographical location or their medical condition.’ Some initiatives under the Plan are still being implemented.

NSW Health only has measures in place to assess some processes and activities for individual initiatives under the Plan. There is no tracking of outcomes relating to the policy goals set out in the Plan, such as increased choice to die at home or the location of the patient’s choice, and improved access to specialist palliative care services. NSW Health has not conducted an overall assessment of the Plan’s outcomes to guide future priorities.

Further, there is no overall performance and reporting framework for palliative and end of life care, meaning there is no monitoring of performance of palliative care services for NSW as a whole. This lack of evaluation and performance measurement impacts on NSW Health's ability to monitor progress and achievements, address gaps in service, and plan for future service enhancement. 

2. Statewide planning and evaluation lacks coordination

Currently, palliative care services are complex to plan and evaluate. Many policies, strategies, guidelines, directives and data collections currently inform services. Even definitions of services vary. The split of policy functions for palliative care and end-of-life care between different branches within NSW Health adds further complexity. These arrangements create the risk of confusion, gaps in advice and support for LHDs.

Consistency is needed in the use of terminology and planning to achieve an integrated approach at all levels, including:

  • standard definitions of palliative care and end-of-life care
  • planning within a single structured policy framework to help clarify what services are to be delivered, who is accountable for delivering them and how to measure their outcomes.

Workforce planning is also affected. While NSW Health has identified significant gaps in the specialist palliative care workforce (especially in regional and remote areas) and it previously made workforce capacity one of its priorities, limited work has been undertaken in producing a statewide strategy to reduce these gaps.

3. District planning is not systematic and some external providers are poorly managed

An integrated approach would inform district-level service planning for palliative care. Planning in the districts we visited was sometimes ad hoc and accountability for performance unclear. Districts would benefit from:

  • better integrating data collection systems with planning
  • clearer guidelines, easy-to-use tools, monitoring and accountability systems.

The recently developed guide – A Blueprint for Improvement, from the Agency for Clinical Innovation – should help districts plan more effectively and consistently as it rolls out more widely in 2017. This takes an integrated approach to palliative and end-of-life care. Only one district we visited has finalised a comprehensive plan using the Blueprint.

Issues with district planning extend to external agreements with service providers, as these are sometimes poorly managed and do not support improved patient outcomes. Examples we reviewed showed a significant reporting burden with process-focused reporting. We also found little evidence of monitoring or action as a result of these reports.

4. Diverse information systems mean data collection and use are inconsistent

NSW Health gathers a broad range of data from many collection points and systems to inform palliative care services at hospital, ward or unit level, and community teams. However, the current data is limited because: 

  • activity is under-reported, particularly in community-based services
  • collection is not universal across districts and services.

Districts also struggle with evidence-based planning and service delivery because multiple information systems mean data may be incomplete or inaccurate. Too often, clinicians and service managers rely on manual collection and paper-based systems. 

eHealth, which coordinates information communication technology (ICT) for the state’s healthcare, is planning a statewide approach to capture information and report on all palliative care activity. The current plans of eHealth to review and improve systems should make data more complete, robust and accessible for quality improvement and planning.

5. An overarching stakeholder strategy would strengthen engagement

Just as data is central to effective planning and evaluation, so too is stakeholder engagement. However, there is currently no explicit stakeholder strategy, which means consultation is inconsistent across the state and not systematic at a district level.

While NSW Health uses a range of platforms to consult, the purpose and value is often not clear to stakeholders. Individual districts have some good practices, but there are limited mechanisms to identify and share these with other areas. A state-wide strategy would improve the quality and consistency of engagement, which will in turn inform service planning and delivery.

A stakeholder engagement strategy would integrate current initiatives, such as the two major networks that consult with health planning staff and clinicians. But it will also need to extend the feedback gathered from families, carers and volunteers, and from the peak bodies that represent them. 

Published

Actions for Information and Communication Technologies in schools for teaching and learning

Information and Communication Technologies in schools for teaching and learning

Education
Information technology
Infrastructure
Management and administration
Service delivery
Workforce and capability

Several factors are reducing effective use of information and communication technology (ICT) in the classroom.

These are primarily:

  • ageing ICT equipment and inadequate wireless networks
  • variable student access to devices at school
  • variable teacher access to centrally provided devices for use outside of the classroom.

Information and communication technologies (ICT) are pervasive in modern life. Australian research has identified that the workforce demand for digital literacy and advanced digital skills is growing across most areas of work. There is broad agreement internationally and in Australian school systems that digital literacy is a core skill for the workforce and students will need to be confident with ICT. Education systems around the world are using ICT in classrooms to support learning and employment goals.  

The New South Wales Department of Education’s (the Department’s) overall strategic directions for teaching and learning with ICT are set in the 'Strategic Information Technology Plan 2016–19'. The Department centrally provides a base level of resources to schools for ICT and schools supplement funding from their existing school budget and Parents and Citizens Associations. Each school decides how to allocate these funds to meet local needs. Schools also set expectations for how teachers and students will use technology to help deliver outcomes.

This audit assessed how well New South Wales public schools are using ICT to improve teaching and learning. It focussed on planning and teacher and student use of ICT. We examined whether:

  • the Department identifies key strategic opportunities to enhance the use of ICT platforms and technologies in schools
  • teachers are integrating ICT into classroom practice
  • the Department monitors the impact of ICT on student learning.
Conclusion 

Several factors are reducing the effective use of ICT in the classroom. These are primarily:

  • ageing ICT equipment and inadequate wireless networks
  • variable student access to devices at school
  • variable teacher access to centrally provided devices to use outside of the classroom.

Many schools are struggling to keep up with growing ICT needs within available funding. The Department needs to review whether its current technology programs provide schools with sufficient resources and support to meet the Department’s strategic goals for 21st Century classrooms. The Department should also target additional support to schools to improve planning for ICT resources.  

Most teachers are using ICT in the classroom, however, teacher access to devices outside the classroom varies between schools. In practice, teacher working days extend outside classroom hours. Teachers need access to devices for activities such as lesson preparation and student assessment. With limited access to devices outside of the classroom, teachers may not be able to effectively integrate ICT into lessons. Teachers also require further professional learning to support them to develop their skills in using ICT.  

The Department is not sufficiently monitoring the digital literacy of New South Wales students, which has declined in national tests. Teachers could benefit from support to assess these skills at a school level. The Department also needs to investigate links between student use of ICT and learning outcomes, so they can better support teachers with evidence-based approaches to enhancing learning through ICT.

Old equipment and wireless networks are not keeping pace with modern demands

The Department’s vision for ICT is to enable ‘any learning opportunity, anywhere, anytime’. This vision is at risk due to an ageing stock of devices and wireless networks. The average age of devices in New South Wales schools is over four years. Older devices are less reliable, require greater maintenance and support, and cannot run demanding applications. Further, many school wireless networks are beyond the end of their useful life. This limits the number of teachers and students who can access online content on wireless networks at the same time.

The central funding model for ICT in schools is not meeting current needs

Funding for the Technology for Learning program to deliver ICT in schools has not increased since 2004, despite an increase in the number of students and emphasis placed on ICT in teaching and learning during this time. Schools supplement funding for ICT from their existing school budget and Parents and Citizens Associations.  

The Department’s current funding model for ICT is not adequately addressing a growing gap in the provision of contemporary ICT in classrooms between schools able to access funding from other sources and those which cannot. The Department needs to review whether the Technology for Learning program is equitable in equipping all schools with the modern technology needed to achieve its vision.

Many teachers are not provided with devices for use outside of the classroom

School Principals we interviewed reported that technology is an essential part of a modern classroom and teacher access to devices outside of the classroom can impact how they use ICT. This is because, in practice, teacher working days extend outside classroom hours and teachers need access to devices for activities such as lesson preparation and student assessment. The Department provides teachers with access to a suite of software tools for these tasks.

The Commonwealth Government’s Digital Education Revolution program provided teachers of secondary school students with laptops from 2009 to 2013. The Department’s evaluation of the Digital Education Revolution program found that teachers reported greater confidence with, and use of, ICT throughout the program.  
Providing desktop computers, laptops or tablets for teachers is now a school level decision and arrangements vary across schools. Each school must trade-off between allocating devices for students and teachers. Most other States and Territories provide all teachers with a laptop for use in and outside of the classroom or offer subsidised access to one.  

There is limited teacher professional learning in the use of ICT

The Department’s research has identified that professional learning is an important factor in how effectively teachers use ICT to enhance teaching and learning. Despite this, the Department provides few courses on using ICT in the classroom directly, and most of these are offered in Sydney. This limits accessibility for teachers outside of the metropolitan area. Schools we visited reported that the costs of courses and providing relief teachers limits the number of external courses or events that teachers attend, especially for rural and regional schools. Increasing the use of online learning would improve access for teachers in these areas.  

The Department is not adequately monitoring trends in professional learning in ICT or evaluating the overall effectiveness of courses. A recent upgrade to the professional learning system may provide the Department with better quality data to do this.

Greater monitoring and reporting on technology use in schools is required

The Local Schools, Local Decisions policy gives schools greater authority to make strategic decisions on the use of ICT appropriate to their local contexts. To support this, the Department needs to better monitor current trends, and identify emerging needs to determine future direction and how best to support schools.  

For example, the Department does not currently know how many devices are allocated to teachers or how many schools have implemented a student Bring Your Own Device scheme. This affects how schools are using ICT, and places demand on the network and the type of support the Department must provide. An assessment of the ICT maturity of schools would help the Department target its resources to schools requiring greater assistance with planning.

The Department does not regularly monitor or report on student capabilities with ICT. A national assessment found that the ICT literacy of a sample of Year 6 and Year 10 New South Wales students fell between 2011 and 2014. The fall was greater in New South Wales than in other States and Territories. Without more regular assessment or reporting, the reasons behind this fall and the distribution of student capabilities between schools will remain unknown. 

By July 2018, the Department of Education should:

  1. Review the Technology for Learning program and school ICT support resourcing to determine whether resourcing is adequate for modern school requirements.
     
  2. Develop a program to improve wireless networks in all NSW schools, for instance by expanding the Connecting Country Schools Program to all NSW schools.  
     
  3. Implement an assessment of school ‘ICT maturity’ and use this to target assistance to those schools requiring support with forward planning for ICT.
     
  4. Improve the use of evidence to inform plans and strategies, including:
    • more detailed monitoring of teacher and student access to and use of ICT
    • evaluating the impact of teacher professional learning on student outcomes 
    • further examining the links between ICT and student outcomes.
       
  5. Improve teacher access to devices for use outside of the classroom to improve how effectively they integrate ICT into teaching and learning.
     
  6. Improve teacher professional learning by providing more:
    • online learning opportunities for teachers in regional and remote areas
    • courses focused on pedagogy to make best use of ICT.
       
  7. Identify the ICT skills students need, and provide teaching resources to develop these skills and monitor their achievement.