What this report is about

Results of the Regional NSW financial statements audits for the year ended 30 June 2023.

What we found

Unqualified audit opinions were issued on all completed audits in the Regional NSW portfolio agencies.

The number of monetary misstatements identified in our audits increased from 28 in 2021–22 to 30 in 2022–23.

What the key issues were

Effective 1 July 2023, staff employed in the Northern Rivers Reconstruction Corporation Division of the Department of Regional NSW transferred to the NSW Reconstruction Authority Staff Agency.

The Regional NSW portfolio agencies were migrated into a new government wide enterprise resourcing planning system.

The total number of audit management letter findings across the portfolio of agencies decreased from 36 to 23.

A high risk matter was raised for the NSW Food Authority to improve the internal controls in the information technology environment including monitoring and managing privilege user access.

What we recommended

Local Land Services should prioritise completing all mandatory early close procedures.

Portfolio agencies should:

  • ensure any changes to employee entitlements are assessed for their potential financial statements impact under the relevant Australian Accounting Standards
  • prioritise and address internal control deficiencies identified in audit management letters.

This report provides Parliament and other users of the Regional NSW portfolio of agencies financial statements with the results of our audits, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision-making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Regional NSW portfolio of agencies (the portfolio) for 2023.

Section highlights

  • Unqualified audit opinions were issued on all completed 30 June 2023 financial statements audits of the portfolio agencies. Two audits are ongoing.
  • The total number of errors (including corrected and uncorrected) in the financial statements increased compared to the prior year.
  • Portfolio agencies met the statutory deadline for submitting their 2022–23 early close financial statements and other mandatory procedures.
  • Portfolio agencies continue to provide financial assistance to communities affected by natural disasters.
  • A change to the NSW paid parental leave scheme, effective October 2023, created a new legal obligation that needed to be recognised by impacted government agencies. Impact to the agencies' financial statements were not material. 

 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision-making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the Regional NSW portfolio.

Section highlights

  • The 2022–23 audits identified one high risk and nine moderate risk issues across the portfolio. Of these, one was a moderate risk repeat issue.
  • The total number of findings decreased from 36 to 23 which mainly related to deficiencies in internal controls.
  • The high risk matter relates to the monitoring and managing of privilege user access at NSW Food Authority. 

 

Appendix one – Misstatements in financial statements submitted for audit

Appendix two – Early close procedures

Appendix three – Timeliness of financial reporting

Appendix four – Financial data

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Premier and Cabinet 2023

Premier and Cabinet 2023

Premier and Cabinet
Whole of Government
Asset valuation
Compliance
Cyber security
Financial reporting
Fraud
Information technology
Procurement
Regulation
Risk
Workforce and capability

What this report is about

Results of the Premier and Cabinet portfolio of agencies' financial statement audits for the year ended 30 June 2023.

What we found

Unqualified audit opinions were issued for all Premier and Cabinet portfolio agencies.

What the key issues were

The Administrative Arrangements Orders, effective 1 July 2023, changed the name of the Department of Premier and Cabinet to the Premier's Department and transferred parts of Department of Premier and Cabinet to The Cabinet Office.

The number of monetary misstatements identified in our audits decreased from 15 in 2021–22 to 12 in 2022–23.

The total number of management letter findings across the portfolio of agencies increased from ten in 2021–22 to 20 in 2022–23.

Thirty per cent of all issues were repeat issues. The most common repeat issues related to deficiencies in controls over financial reporting.

What we recommended

Portfolio agencies should:

  • ensure any changes to employee entitlements are assessed for their potential financial statements impact under the relevant Australian Accounting Standards
  • prioritise and address internal control deficiencies identified in Audit Office management letters.

This report provides Parliament and other users of the Premier and Cabinet portfolio of agencies’ financial statements with the results of our audits, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision-making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Premier and Cabinet portfolio of agencies (the portfolio) for 2023.

Section highlights

  • Unqualified audit opinions were issued on all the portfolio agencies 2022–23 financial statements.
  • The total number of errors (including corrected and uncorrected) in the financial statements decreased compared to the prior year. 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision-making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the Premier and Cabinet portfolio.

Section highlights

  • The 2022–23 audits identified eight moderate risk issues across the portfolio of agencies. Of these, two were repeat issues, and related to password and security configuration and management of excessive annual leave.
  • The total number of findings increased from ten to 20, which mainly related to deficiencies in controls over financial reporting and governance and oversight.
  • The most common repeat issues related to weaknesses in controls over financial reporting.

Appendix one – Early close procedures

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Stronger Communities 2023

Stronger Communities 2023

Community Services
Whole of Government
Asset valuation
Compliance
Cyber security
Financial reporting
Information technology
Internal controls and governance
Management and administration
Procurement
Project management
Shared services and collaboration

What this report is about

Results of the Stronger Communities financial statement audits for the year ended 30 June 2023.

What we found

Unqualified audit opinions were issued on all completed Stronger Communities portfolio agencies.

Machinery of government changes during the year returned the sports-related agencies to the Stronger Communities portfolio.

Resilience NSW was abolished on 16 December 2022 with most of its functions transferred to the newly created NSW Reconstruction Authority.

The Trustee for the First Australian Mortgage Acceptance Corporation (FANMAC) is a prescribed entity under the Government Sector Finance Regulation 2018. The Trustee should have presented the FANMAC's financial statements for audit after it became a GSF agency on 1 July 2020.

The number of monetary misstatements identified in our audits decreased from 42 in 2021–22 to 29 in 2022–23.

What the key issues were

In 2022–23, agencies in the portfolio recorded net revaluation uplifts to land and buildings totalling $643 million.

Out of home care and permanency support grant expenditure has increased by 27% since 2019–20. An upcoming performance audit report will focus on the timeliness and quality of the child protection services provided by the department and its non-government service providers.

A high-risk matter was raised for the department over segregation of duties deficiencies in the Justice Link system.

Four high-risk matters reported in 2021–22 have been resolved.

Thirty-three agencies were onboarded into a new government-wide enterprise resource planning system. Additional agencies will be onboarded in three tranches from April 2024 through to October 2024.

What we recommended

Portfolio agencies should:

  • ensure any changes to employee entitlements are assessed for their financial statement impact under the relevant Australian Accounting Standards
  • prioritise and address internal control deficiencies identified in our management letters.

This report provides Parliament and other users of the Stronger Communities portfolio of agencies’ financial statements with the results of our audits, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision-making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Stronger Communities portfolio of agencies (the portfolio) for 2023.

Section highlights

  • Unqualified audit opinions were issued on all completed 30 June 2023 financial statements audits of portfolio agencies, including the audit of the Crown Solicitor's Office's Trust Account for compliance with clause 14 of the Legal Profession Uniform Law Application Regulation 2015.
  • The financial statement audits of the NSW Trustee and Guardian Common Funds (the common funds) – year ended 30 June 2022 were certified by management on 6 December 2022 and independent auditor's reports issued 21 December 2022. The 30 June 2023 financial statements audits of the common funds are ongoing.
  • A variation to an agreement between the Commonwealth Attorney-General and the Legal Aid Commission of New South Wales for legal services to support the Royal Commission into Violence, Neglect and Exploitation of people with disability program extended the reporting period from 30 June 2023 to 29 September 2023 – the conclusion of the Royal Commission. The audit of the financial report acquitting expenditure under the agreement is expected to be completed before 28 February 2024.
  • The audit of the Home Purchase Assistance Fund's (the fund) 30 June 2022 financial statements remains incomplete. Those charged with governance of the fund have not provided sufficient and appropriate evidence to support the carrying value of material investments reported in the fund's financial statements. The financial audit of the fund's 2023 financial statements remain incomplete as a result.
  • The Trustee for the First Australian Mortgage Acceptance Corporation Master and Pooled Super Trusts had not prepared general purpose financial statements since 30 June 2021 when the financial reporting provisions of the Government Finance Sector Act 2018 were enacted and the Trustee was prescribed as a GSF agency under the regulations. The audits of these financial statements are ongoing.
  • Reported corrected misstatements decreased from 28 in 2021–22 to six with a gross value of $8.8 million in 2022–23 ($277 million in 2021–22).
  • Portfolio agencies met the statutory deadline for submitting their 2022–23 early close financial statements and other mandatory procedures.
  • In 2022–23, portfolio agencies collectively recorded net revaluation uplifts to the carrying values of land and buildings totalling $643 million (2021–22: $993 million) initiated through a combination of comprehensive and desktop valuations.
  • The Department of Communities and Justice (the department) had previously deferred performing a comprehensive revaluation of its land and building portfolio relating to the Corrective Services and Youth Justice functions. The deferral was due to the challenges in providing valuers sufficient access to the facilities due to the pandemic. The department is scheduled to perform a comprehensive revaluation of its full land and building portfolio in 2023–24. 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision-making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the Stronger Communities portfolio.

Section highlights

  • The number of findings reported to management has decreased from 142 in 2021–22, to 71 in 2022–23, and 35% were repeat issues (36% in 2021–22). Repeat issues related to non-compliance with key legislation and/or agency policies, information technology and internal control deficiencies.
  • A long-standing issue about segregation of duties over the JusticeLink system managed by the department has been elevated from moderate to high risk.
  • Four out of six high-risk issues reported in the prior year have been addressed.
  • Of the 15 newly identified moderate risk issues, 11 related to information technology and internal control deficiencies. 

Appendix one – Misstatements in financial statements submitted for audit

Appendix two – Early close procedures

Appendix three – Timeliness of financial reporting

Appendix four – Financial data

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Education 2023

Education 2023

Education
Whole of Government
Asset valuation
Compliance
Cyber security
Financial reporting
Information technology
Internal controls and governance
Procurement
Project management
Risk

What this report is about

Results of the Education portfolio of agencies’ financial statements audits for the year ended 30 June 2023.

What we found

Unqualified audit opinions were issued for all Education portfolio agencies.

An ‘other matter’ paragraph was included in the TAFE Commission’s independent auditor’s report as it did not have a delegation or sub-delegation from the Minister for Education and Early Learning to incur expenditure on grants from other portfolio agencies.

What the key issues were

Comprehensive valuations of buildings at the Department of Education (the department) and at the TAFE Commission found that certain assumptions applied in previous years needed to be updated, resulting in prior period restatements.

The department prepaid a building contractor for early works on a project and some of the prepayment is in legal dispute.

The department duplicated a claim for project funding from Restart NSW in 2021.

New parental leave legislation increased employee liabilities for portfolio agencies. The department and the NSW Education Standards Authority (the Authority) updated their financial statements to record parental leave liabilities.

A high risk matter was raised for the Authority to improve the quality and timeliness of information to support their financial statement close process.

What we recommended

Portfolio agencies should ensure any changes to employee entitlements are assessed for their potential financial statements impact under the relevant Australian Accounting Standards.

The department should:

  • improve processes to ensure project claims are not duplicated
  • assess the risks associated with providing prepayments to contractors.

This report provides Parliament and other users of the Education portfolio of agencies’ financial statements with the results of our audits, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision-making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Education portfolio (the portfolio) for 2023.

Section highlights

  • Unqualified audit opinions were issued on all the portfolio agencies 2022–23 financial statements.
  • An ‘other matter’ paragraph was included in the independent auditor’s report for the Technical and Further Education Commission (the TAFE Commission) as it did not have a delegation or sub-delegation from the Minister for Education and Early Learning to incur expenditure on grants from other portfolio agencies.
  • Comprehensive valuations of buildings in the current year identified that certain assumptions applied in previous years were incorrect. The effects of these corrections are disclosed as prior period errors in the financial statements of the Department of Education (the department) and the TAFE Commission.
  • The department made corrections to its financial statements to reflect increases to NSW teachers’ wages announced post balance date. This impacted amounts recorded as liabilities for a range of employee benefits and entitlements totalling $225.4 million, of which $147.9 million is accepted by the Crown and $77.5 million is borne by the department.
  • A change to the NSW paid parental leave scheme, effective October 2022, created a new legal obligation that needed to be recognised by impacted government agencies. Of the three affected portfolio agencies, only the department and the NSW Education Standards Authority recognised a liability to account for this change. The aggregated unrecorded liabilities of other agencies in the portfolio totalled $2.4 million. The errors within the individual agencies’ financial statements were not material.
  • The total number of errors (including corrected and uncorrected) in the financial statements increased compared to the prior year.
  • The NSW Childcare and Economic Opportunity Fund should prepare financial statements unless NSW Treasury releases a Treasurer’s Direction under section 7.8 of the GSF Act that will exempt the SDA from financial reporting requirements. 

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision-making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the Education portfolio.

Section highlights

  • The 2022–23 audits identified one high risk and 20 moderate risk issues across the portfolio. Of these, one was a high risk repeat issue and four were moderate risk repeat issues.
  • The total number of findings increased from 29 to 36, which mainly related to deficiencies in financial reporting, information technology, payroll and purchasing controls.
  • The high risk matter relates to the lack of quality and timely information to support the financial statement close process at the NSW Education Standards Authority. 

Appendix one – Early close procedures

Appendix two – Financial data

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

Published

Actions for Regional, rural and remote education

Regional, rural and remote education

Education
Management and administration
Project management
Service delivery

What this report is about

Students in rural and remote areas of NSW face greater challenges compared to their metropolitan peers.

This report examined how the NSW Department of Education (the department) is ensuring that rural and remote students have access to the same quality of early childhood, school education, and skills pathways as metropolitan students.

What we found

A decade since the previous (2013) strategy to address educational disadvantage, there remain considerable gaps in access and outcomes between rural and remote students and metropolitan students.

The Rural and Remote Education Strategy (2021–24) is unlikely to address these longstanding and known issues of educational disadvantage in rural and remote areas.

Key enabling factors such as resourcing a dedicated team, setting performance measures, and establishing suitable governance arrangements were not put in place to support effective implementation of the 2021 strategy.

The department has programs aimed at addressing remoteness challenges, but does not know if these initiatives improve access or outcomes.

The department does not monitor or report on student access or outcomes according to geographic location.

What we recommended

The Department of Education should:

  • develop a new strategy that addresses disadvantage in regional, rural and remote education
  • establish and report publicly on regional, rural and remote key performance indicators
  • improve data collection by using a standard remoteness classification
  • improve governance arrangements for regional, rural and remote education
  • review the resources provided for regional, rural and remote areas that recognises the additional costs
  • develop an approach that ensures all students can access best practice modes of delivery.

In February 2021, the department of Education (the department) released the ‘Rural and Remote Education Strategy (2021–2024)’. The strategy sets a vision that ‘every child in regional New South Wales has access to the same quality of education as their metropolitan peers’. It recognises that students in rural and remote areas of New South Wales face greater challenges compared to students in metropolitan locations. These challenges contribute to regional, rural and remote students underperforming on major educational indicators compared to their metropolitan peers.

In recent years, regional, rural and remote communities experienced a series of natural disasters as well as the COVID-19 pandemic. In response to the pandemic and subsequent school closures, the department introduced new initiatives aimed at minimising the disruption to children including online learning and small group tuition.

The department established a regional, rural and remote education policy unit in 2021 to support delivery of the strategy and its vision.

The objective of this audit was to assess the effectiveness of the department’s activities to ensure that regional, rural and remote students have access to the same quality of early childhood, school education, and skills pathways as their metropolitan peers.

In making this assessment, the audit examined whether:

  • The department developed and implemented a strategy that enables regional, rural and remote students to access the same quality of early childhood education, school education, and skills pathways as students in metropolitan New South Wales.
  • The department has been addressing the complexities and needs of regional, rural and remote early childhood education, school education, and skills pathways.
Conclusion

The department's rural and remote education strategy is unlikely to achieve its vision that every child in regional New South Wales has access to the same quality of education as their metropolitan peers. Shortcomings in the design and implementation of the strategy have meant there is little to report on its impact after more than two years since its release.

The department did not take on board lessons learned from the previous strategy. The department did not provide additional resources to meet the strategy aims, establish strong central coordination, set timeframes, set measures of success, or identify new programs to address gaps in regional and remote access and outcomes. Instead, the department relied on matching existing programs and activities across its business areas to meet the stated actions and goals of the strategy.

There was not enough work put in to plan for successful implementation. A changeover in staff responsible for coordinating implementation of the strategy and lack of fit-for-purpose governance arrangements slowed its momentum. The department took one year to recruit a central team and almost two years to set up governance that gives relevant department executives oversight of the strategy. This was not fast enough to support a four-year strategy with an ambitious vision.

The department did not establish a program logic model, set baseline measures or develop an evaluation plan to assess the impact of the strategy. Consequently, it has not adequately monitored changes in access or outcomes for regional, rural and remote students. Two years after its release, there has not been any public reporting against the actions or outcomes of the strategy.

The department is not addressing the complexities of delivering regional, rural and remote early childhood, school education and skills pathways. There are a range of programs targeted to overcoming challenges of remoteness, but the department does not monitor data to determine whether these programs are sufficient to close the persistent gaps in access and outcomes for regional, rural and remote students.

A decade after the Rural and Remote Education Blueprint was launched in 2013, there remain considerable gaps in access and outcomes between metropolitan and regional, rural and remote areas. The department identifies 'equity' as a key value in its strategic plan but does not monitor or report on performance against key indicators according to geographic location. Data produced in response to our requests for this report demonstrate that previously identified gaps in access and outcomes remain.

Different areas of the department recognise the challenges of delivering services in regional, rural and remote locations and have developed specific programs or approaches aimed at addressing these challenges. The department does not know whether these interventions are sufficient to close the gaps in access or outcomes. Schools we spoke with as part of the audit reported significant ongoing challenges with attracting and retaining staff, providing a full curriculum and accessing support services when needed. 

This chapter examines the process to develop the Rural and Remote Education Strategy (2021–2024). It considers whether there was a comprehensive program of stakeholder consultation, whether relevant research and evidence was incorporated and whether an effective performance monitoring system was established.

The department made genuine efforts to consult with stakeholders on the new strategy

The department had a clear process to engage and obtain feedback from key stakeholders during the development of the new strategy. It developed a range of documents to support the consultation process including a stakeholder engagement plan, communications plan, and presentation. The department used the International Association for Public Participation (IAP2) Spectrum of Public Participation principles to help ensure that relevant stakeholders were included in the planning and decision-making process.

In late 2019, the department began its first phase of consultations with internal and external stakeholders to get their views on rural and remote education. It consulted internally with department directors, advisory groups, and learning communities, and externally with government agencies, service providers, non-government schools, and universities.

In March 2020, the department developed a stakeholder engagement paper to test the key issues from stakeholder consultations. Four focus areas were identified and included in a consultation paper that went out to key stakeholders for the second round of consultations in May 2020.

In the third consultation phase, the department conducted a workshop with stakeholders to review the earlier feedback, prioritise issues, identify gaps, and provide further input.

This consultation process enabled the department to identify issues and challenges to inform the new strategy. However, it was already aware that the blueprint was having limited success, and had already identified potential focus areas, following the evaluation of the blueprint in 2019.

The department did not consider recent research when developing the new strategy

The department's guidance materials promote the importance of considering research during policymaking. The guidelines describe the need to understand a topic, consult with stakeholders, identify gaps in existing knowledge, and ensure future work is informed by current literature.

In 2013, the department published a literature review on rural and remote education to inform the blueprint. The literature review found that students in rural and remote schools were not performing as well as their metropolitan peers, and that this performance gap was widening. The review attributed this to the higher number of children from low socio-economic backgrounds attending rural and remote schools. The review also identified several other factors that could negatively impact performance outcomes for rural and remote students. The department used the findings of the literature review to develop the key focus areas in the 2013 blueprint.

When the department began developing the new rural and remote education strategy in 2019, it recognised the need to review the literature on recent international initiatives. However, it has not yet released this review. This means that the department could have missed important new developments since it last examined the literature in 2013. Incorporating up-to-date research is important where past strategies have not met all their intended outcomes.

A national review into rural and remote education in 2018 examined Australian and international literature to inform its findings. The review made 11 recommendations to the Australian and state governments. While the NSW Government was not required to formally respond to the review, it could have considered the work done by that review when developing the new strategy. Several review recommendations are addressed in the strategy, while several others are only partly addressed. Gaps between review recommendations and specific strategy actions include improving the availability of quality accommodation, substantially reducing the waiting times for specialist assessments of students with learning difficulties and disabilities and increasing access to high quality distance education.

In 2019, the department commissioned a rural and remote project to contribute a research and evidence base to the new strategy. The main aim of the project was to help the department understand how it could better support rural and remote schools to increase educational outcomes. There was not enough time for this review to be completed prior to the release of the strategy. As of June 2023, the research project had not yet been released.

The strategy did not address all findings and recommendations from a recent evaluation

In 2020, the department's Centre for Education Statistics and Evaluation (CESE) published an evaluation of the blueprint. The evaluation examined how the actions in the blueprint were implemented. It recommended that a new strategy be developed, and made recommendations for things that should be incorporated into the strategy.

The blueprint aimed to ensure students in rural and remote areas could access the same quality of education as their metropolitan peers. The blueprint identified four focus areas to meet that aim:

  • quality early childhood education
  • great teachers and school leaders
  • curriculum access for all
  • effective partnerships and connections.

The department developed several initiatives to help meet the objectives of each of the four focus areas. These initiatives are described in Exhibit 5 below.

Exhibit 5: Key initiatives in the Rural and Remote Education Blueprint (2013)
Key focus area Initiative
Quality early childhood education
  • Funding model to help vulnerable and disadvantaged children access preschool.
Great teachers and school leaders
  • Rental subsidy to help attract and retain teachers.
Curriculum access for all
  • Virtual school to provide a varied curriculum for high potential and gifted students.
Effective partnerships and connections
  • Education networks for teachers and school leaders to access expert advice to support student learning.
  • Networked specialist centres to bring together services to support student health and wellbeing.

Source: Department of Education, Rural and remote education: A blueprint for action 2013.

The evaluation found that initiatives in two of the four focus areas – Quality early childhood education and Curriculum access for all – had performed well. However, the evaluation found that initiatives in the other two focus areas – Great teachers and school leaders and Effective partnerships and connections – did not achieve intended outcomes.

On the whole, the evaluation found that the 'remoteness gap' between rural and remote students and metropolitan students had not reduced since the blueprint was introduced. It recommended that the department continue its focus on rural and remote education by developing a new evidence-based strategy that focused on student outcomes and clear measures of success.

Objectives and actions in the new strategy were similar to those in the blueprint

The 2021 strategy sets an overall vision that 'every child in regional New South Wales has access to the same quality of education as their metropolitan peers'. It also states that the department 'is committed to ensuring all rural and remote students have equitable access to educational opportunities'.

Exhibit 6: Comparison of objectives in the blueprint and the new strategy
Rural and Remote Education Blueprint (2013) Rural and Remote Education Strategy (2021–24)
Provide more children with access to quality early child education in the year before school. Ensure all students have access to quality preschool in the year before school.
Ensure rural and remote schools have greater capacity to attract and retain quality teachers and leaders. Increase supply of high-quality educators in rural and remote communities.
Build the capacity of teachers and leaders in rural and remote schools. Better develop rural and remote teachers to deliver quality learning opportunities.
Address wellbeing needs through effective partnerships and connections. Address wellbeing needs through connections with local communities.
Develop partnerships so that rural and remote students have access to quality pathways into further education, training, or employment. Build partnerships to increase student access to post-school opportunities.

Source: Audit Office summary of Department of Education information.

Four areas in the blueprint remained a focus in the new strategy – early childhood education, teacher recruitment and retention, curriculum, and student wellbeing support services. Each focus area identifies a goal, as well as the aims and actions that contribute to those goals.

While this shows the department identified that these areas required continued attention, most actions were to 'increase', 'expand' or 'improve' existing programs and resources. The new strategy did not propose any new ideas or solutions, despite the blueprint achieving limited success in improving outcomes for rural and remote students.

There were no baseline or target measures set to monitor progress of the new strategy

The blueprint evaluation recommended that the department develop a new evidence-based strategy which focused on improving student outcomes. It also recommended the department use a program logic methodology to ensure there was a clear definition of success, adequate measures of success, and continual monitoring to ensure success.

Program logic models are a visual representation of the various components of a program. They can be used to illustrate program priorities, inputs, activities, outputs, outcomes, and assumptions. Logic models are used to explain how a proposed solution will address a specific problem. They are important because they can help test assumptions, build business cases, and identify potential enablers or barriers that could impact the project.

The department did not complete a program logic model during development of the new strategy, nor did it define measures to monitor whether the strategy's overall vision for quality education or the commitment to equitable access was on track to be achieved.

The department has not comprehensively monitored changes in educational outcomes in regional, rural and remote areas since the evaluation of the blueprint in 2020. This evaluation had seven indicators of educational outcomes by remoteness. The measures used in the evaluation could have provided a starting point given the similarity in focus areas between the blueprint and the new strategy. Not addressing past review recommendations increases risks that issues will be repeated.

The policy unit advised it has plans to set up a dashboard to monitor performance across the department's business plan measures by remoteness. This is intended to identify areas where system-wide improvements are required. This is not a comprehensive account of the strategy outcomes because the business plan measures don't capture all the goals of the strategy.

There were no timeframes or resources identified for implementing new strategy actions

The strategy has an overall timeframe of 2021–2024 but does not clarify when it expects the vision, goals, or aims to be achieved, or actions to be implemented.

The department's guidance on policymaking sets out how projects should be transitioned between the policy and implementation teams. This guidance is intended to help ensure the policy intent and scope of the project are not lost during the delivery of the project. The guidance highlights that the policy team should establish clear project implementation timeframes. It is important to have clear timeframes because it enables teams to measure progress, manage resources, and prioritise actions to ensure project outcomes are achieved.

The strategy states that there is a further $1 billion of investment planned over the next three years for rural and remote education but does not identify how this is allocated across its focus areas. It is important to identify the resources required to support the implementation of a program so that program objectives are met in a timely and cost-effective manner. The previous blueprint identified much lower funding of $80 million but more clearly showed how it would be allocated for identified actions across the four focus areas.

In response to our requests, the department separately identified $1.286 billion in expenditure for regional, rural and remote schools referenced in the strategy. Most of this expenditure related to existing department programs and activities rather than new initiatives. The total amount included:

  • $576.9 million for new and upgraded schools
  • $365.8 million for upgraded information technology equipment and resources
  • $120 million for school facility upgrades to be co-funded by schools
  • $60 million to replace school roofs
  • $60 million for the COVID Intensive Learning Support Program
  • $32 million for the Early Action for Success program
  • $29.7 million for staffing incentives
  • $21.7 million for literacy and numeracy interventions
  • $18.8 million in school location allowances
  • $1.45 million for the Rural Learning Exchange Pilot
  • $0.4 million for Rural and Remote Network initiatives.

This chapter examines the arrangements in place to implement the strategy. It considers whether effective governance arrangements are in place and how progress is monitored and reported.

This chapter considers the effectiveness of arrangements to ensure regional, rural and remote students have access to quality early childhood education, school education, and post‑school transitions.

This chapter considers the department's arrangements to monitor educational and wellbeing outcomes of students by remoteness. It reports on differences in outcomes between students in metropolitan areas and those in regional, rural and remote areas.

Those living in regional, rural and remote areas can have greater difficulty in accessing government services, often needing to travel long distances, or facing lower service levels than provided in major cities. This context is important when considering educational and wellbeing outcomes, given the disruptive effects of waiting or missing out on important services.

The rest of this chapter details key measures in the department's outcome and business plan.

Appendix one – Response from agency

Appendix two – About the audit

Appendix three – Performance auditing

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #385 - released 10 August 2023

Published

Actions for Management of the Critical Communications Enhancement Program

Management of the Critical Communications Enhancement Program

Finance
Health
Justice
Whole of Government
Cyber security
Information technology
Infrastructure
Internal controls and governance
Project management
Risk
Service delivery
Shared services and collaboration

What the report is about

Effective radio communications are crucial to NSW's emergency services organisations.

The Critical Communications Enhancement Program (CCEP) aims to deliver an enhanced public safety radio network to serve the five emergency services organisations (ESOs), as well as a range of other users.

This report assesses whether the NSW Telco Authority is effectively managing the CCEP.

What we found

Where it has already been delivered (about 50% of the state), the enhanced network meets most of the requirements of ESOs.

The CCEP will provide additional infrastructure for public safety radio coverage in existing buildings agreed to with ESOs. However, radio coverage inside buildings constructed after the CCEP concludes will be at risk because building and fire regulations do not address the need for in-building public safety radio coverage.

Around 98% of radios connected to the network can be authenticated to protect against cloning, though only 42% are.

The NSW Telco Authority has not settled with ESOs on how call encryption will be used across the network. This creates the risk that radio interoperability between ESOs will not be maximised.

When completed, the public safety radio network will be the only mission critical radio network for ESOs. It is unclear whether governance for the ongoing running of the network will allow ESOs to participate in future network operational decisions.

The current estimated capital cost for the NSW Telco Authority to complete the CCEP is $1.293 billion. This is up from an estimated cost of $400 million in 2016. The estimated capital cost was not publicly disclosed until $1.325 billion was shown in the 2021–22 NSW Budget Papers.

We estimate that the full cost to government, including costs to the ESOs, of implementing the enhanced network is likely to exceed $2 billion.

We made recommendations about

  • The governance of the enhanced Public Safety Network (PSN) to support agency relationships.
  • The need to finalise a Traffic Mitigation Plan for when the network is congested.
  • The need to provide advice to the NSW Government about the regulatory gap for ensuring adequate network reach in future buildings.
  • The need to clarify how encryption and interoperability will work on the enhanced network.
  • The need for the NSW Telco Authority to comply with its policy on Infrastructure Capacity Reservation.
  • Expediting measures to protect against the risk of cloning by unauthenticated radios.

Public safety radio networks are critical for operational communications among Emergency Services Organisations (ESOs), which in New South Wales include:

  • NSW Ambulance
  • Fire and Rescue NSW
  • NSW Police Force
  • NSW Rural Fire Service
  • NSW State Emergency Service.1

Since 1993, these five ESOs have had access to a NSW Government owned and operated radio communications network, the Public Safety Network (PSN), to support their operational communications. Around 60 to 70 other entities also have access to this network, including other NSW government entities, Commonwealth government entities, local councils, community organisations, and utility companies.

Pursuant to the Government Telecommunications Act 2018 ('the Act'), the New South Wales Government Telecommunications Authority ('NSW Telco Authority') is responsible for the establishment, control, management, maintenance and operation of the PSN.2

Separate to the PSN, all ESOs and other government entities have historically maintained their own radio communication capabilities and networks. Accordingly, the PSN has been a supplementary source of operational radio communications for these entities.

These other radio networks maintained by ESOs and other entities are of varying size and capability, with many ageing and nearing their end-of-life. There was generally little or no interoperability between networks, infrastructure was often co-located and duplicative, and there were large gaps in geographic coverage.

In 2016, the NSW Telco Authority received dedicated NSW Government funding to commence the Critical Communications Enhancement Program (CCEP).

According to NSW Telco Authority's 2021–22 annual report, the CCEP is a transformation program for operational communications for NSW government agencies. The CCEP '…aims to deliver greater access to public safety standard radio communications for the State’s first responders and essential service agencies'. The objective of CCEP is to consolidate the large number of separate radio networks that are owned and operated by various NSW government entities and to enhance the state’s existing shared PSN. The program also aims to deliver increased PSN coverage throughout New South Wales.

The former NSW Government intended that as the enhanced PSN was progressively rolled-out across NSW, ESOs would migrate their radio communications to the enhanced network, before closing and decommissioning their own networks.

About this Audit

This audit assessed whether the CCEP is being effectively managed by the NSW Telco Authority to deliver an enhanced PSN that meets ESOs' requirements for operational communications.

We addressed the audit objective by answering the following two questions:

  1. Have agreed ESO user requirements for the enhanced PSN been met under day-to-day and emergency operational conditions?
  2. Has there been adequate transparency to the NSW Government and other stakeholders regarding whole-of-government costs related to the CCEP?

In answering the first question, we also considered how the agreed user requirements were determined. This included whether they were supported by evidence, whether they were sufficient to meet the intent of the CCEP (including in considering any role for new or alternative technologies), and whether they met any relevant technical standards and compliance obligations (including for cyber security resilience).

While other NSW government agencies and entities use the PSN, we focused on the experience of the five primary ESOs because these will be the largest users of the enhanced PSN.

Both the cost and time required to complete the CCEP roll-out have increased since 2016. While it was originally intended to be completed in 2020, this is now forecast to be 2027. Infrastructure NSW has previously assessed the reasons for the increases in time and cost. A summary of the findings made by Infrastructure NSW is presented in Chapter 1 of this report. Accordingly, as these matters had already been assessed, we did not re-examine them in this performance audit.

The auditee for this performance audit is the NSW Telco Authority, which is a statutory authority within the Department of Customer Service portfolio.

In addition to being responsible for the operation of the PSN, section 5 of the Act also prescribes that the NSW Telco Authority is:

  • to identify, develop and deliver upgrades and enhancements to the government telecommunications network to improve operational communications for government sector agencies
  • to develop policies, standards and guidelines for operational communications using telecommunications networks.

The NSW Telco Authority Advisory Board is established under section 10 of the Act. The role of the board is to advise the NSW Telco Authority and the minister on any matter relating to the telecommunications requirements of government sector agencies and on any other matter relating to the functions of the Authority. As of 2 June 2023, the responsible minister is the Minister for Customer Service and Digital Government.

The five identified ESOs are critical stakeholders of the CCEP and therefore they were consulted during this audit. However, the ESOs were not auditees for this performance audit.

Conclusion

In areas of New South Wales where the enhanced Public Safety Network has been implemented under the Critical Communications Enhancement Program, the NSW Telco Authority has delivered a radio network that meets most of the agreed requirements of Emergency Services Organisations for routine and emergency operations.
In April 2023, the enhanced Public Safety Network (PSN) was approximately 50% completed. In areas where it is used by Emergency Services Organisations (ESOs), the PSN generally meets agreed user requirements. This is demonstrated through extensive performance monitoring and reporting, which shows that agreed performance standards are generally achieved. Reviews by the NSW Government and the NSW Telco Authority found that the PSN performed effectively during major flood events in 2021 and 2022.

Where it is completed, PSN coverage is generally equal to or better than each ESO's individual pre-existing coverage. The NSW Telco Authority has a dedicated work program to address localised coverage gaps (or 'blackspots') in those areas where coverage has otherwise been substantively delivered. Available call capacity on the network far exceeds demand in everyday use. Any operational issues that may occur with the PSN are transparent to ESOs in real time.

The NSW Telco Authority consulted extensively with ESOs on requirements for the enhanced PSN, with relatively few ESO requirements not being included in the specifications for the enhanced PSN. Lessons from previous events, including the 2019–20 summer bushfires, have informed the design and implementation of the enhanced PSN (such as the need to ensure adequate backup power supply to inaccessible sites). The network is based on the Project 25 technical standards for mission-critical radio communications, which is widely-accepted in the public safety radio community throughout Australia and internationally.

There is no mechanism to ensure adequate radio coverage within new building infrastructure after the CCEP concludes, but the NSW Telco Authority and ESOs have agreed an approach to prioritise existing in-building sites for coverage for the duration of the CCEP.
The extent to which the PSN works within buildings and other built structures (such as railway tunnels) is of crucial importance to ESOs, especially the NSW Police Force, NSW Ambulance, and Fire and Rescue NSW. This is because a large proportion of their operational communications occurs within buildings.

There is no mechanism to ensure the adequacy of future in-building coverage for the PSN in new or refurbished buildings after the CCEP concludes. Planning, building, and fire regulations are silent on this issue. We note there are examples in the United States of how in-building coverage for public safety radio networks can be incorporated into building or fire safety codes.

In regard to existing buildings, it is not possible to know whether a building requires its own in-building PSN infrastructure until nearby outside radio sites, including towers and antennae, have been commissioned into the network. Only then can it be determined whether their radio transmissions are capable of penetrating inside nearby buildings. Accordingly, much of this work for in-building coverage cannot be done until outside radio sites are finished and operating.

In March 2023, the NSW Telco Authority and ESOs agreed on a list of 906 mandatory and 7,086

non-mandatory sites for in-building PSN coverage. Most of these sites will likely be able to receive radio coverage via external antennae and towers, however this cannot be confirmed until those nearby external PSN sites are completed. The parties also agreed on an approach to prioritising those sites where coverage is needed but not provided by antennae and towers. Available funding will likely only extend to ensuring coverage in sites deemed mandatory, which is nonetheless expected to meet the overall benchmark of achieving 'same or better' coverage than what ESOs had previously.

There is a risk that radio interoperability between ESOs will not be maximised because the NSW Telco Authority has not settled with ESOs how encryption will be used across the enhanced PSN.
End-to-end encryption of radio transmissions is a security feature that prevents radio transmissions being intercepted or listened to by people who are not meant to. The ability of the PSN to provide end-to-end encryption of operational communications is of critical importance to the two largest prospective users of the PSN: the NSW Police Force and NSW Ambulance. Given that encryption excludes other parties that do not have the requisite encryption keys, its use creates an obstacle to achieving a key intended benefit of the CCEP, that is a more interoperable PSN, where first responders are better able to communicate with other ESOs.

Further planning and collaboration between PSN participants are necessary to consider how these dual benefits can be achieved, including in what operational circumstances encrypted interoperability is necessary or appropriate.

The capital cost to the NSW Telco Authority of the CCEP, originally estimated at $400 million in 2016, was not made public until the 2021–22 NSW Budget disclosed an estimate of $1.325 billon.
The estimated capital cost to complete all stages of the CCEP increased over time. This increasing cost was progressively disclosed to the NSW Government through Cabinet processes between 2015–16 and 2021–22.

In 2016, the full capital cost to the NSW Telco Authority of completing the CCEP was estimated to be $400 million. This estimated cost was not publicly disclosed, nor were subsequent increases, until the cost of $1.325 billion was publicly disclosed in the 2021–22 NSW Budget (revised down in the 2022–23 NSW Budget to $1.293 billion).

There has been no transparency about the whole-of-government cost of implementing the enhanced PSN through the CCEP.
In addition to the capital costs incurred directly by the NSW Telco Authority for the CCEP, ESOs have incurred costs to maintain their own networks due to the delay in implementing the CCEP. The ESOs will continue to incur these costs until they are able to fully migrate to the enhanced PSN, which is expected to be in 2027. These costs have not been tracked or reported as part of transparently accounting for the whole-of-government cost of the enhanced PSN. This is despite Infrastructure NSW in 2019 recommending to the NSW Telco Authority that it conduct a stocktake of such costs so that a whole-of-government cost impact is available to the NSW Government.

1 The definition of 'emergency services organisation' is set out in the State Emergency and Rescue Management Act 1989 (NSW). In addition to the five ESOs discussed in this report, the definition also includes: Surf Life Saving New South Wales; New South Wales Volunteer Rescue Association Inc; Volunteer Marine Rescue NSW; an agency that manages or controls an accredited rescue unit; and a non-government agency that is prescribed by the regulations for the purposes of this definition.
2 Section 15(1) of the Government Telecommunications Act 2018 (NSW).

The NSW Telco Authority established and tracked its own costs for the CCEP

Over the course of the program from 2016, the NSW Telco Authority prepared a series of business cases and program reviews that estimated its cost of implementing the program in full, including those shown in Exhibit 6 below.

Exhibit 6: Estimated costs to fully implement the CCEP
Source Capital cost ($ million) Operating cost
($ million)
Completion date
March 2016 business case 400 37.3 2020
November 2017 internal review 476.7 41.7 2022
March 2020 business case 950–1,050 -- 2025
October 2020 business case 1,263.1 56.1 2026

Source: CCEP business cases as identified.

In response to the 2016 CCEP business case, the then NSW Government approved the NSW Telco Authority implementing the CCEP in full, with funding provided in stages. The NSW Telco Authority tracked its costs against approved funding, with monthly reports provided to the multi-agency Program Steering Committee

Throughout the program, the NSW Government was informed of increasing costs being incurred by the NSW Telco Authority for the CCEP

The various business cases, program updates, and program reviews prepared by the NSW Telco Authority were provided to the NSW Government through the required Cabinet process when seeking approval for the program proceeding and requests for both capital and operational funding. These provided clear indication of the changing overall cost of the CCEP to the NSW Telco Authority, as well as the delays that were being experienced.

There was no transparency to the Parliament and community about changes in the capital cost of the CCEP until the 2021–22 NSW Budget

As the business cases for the CCEP were not publicly available, the only sources of information about capital cost were NSW Budget papers and media releases. The information provided in the annual Budget papers prior to the 2021–22 NSW Budget provided no visibility of the estimated full capital cost to complete all stages of the CCEP. As shown in Exhibit 7 below, this information was fragmented and complex.

Media releases about the progress of the CCEP did not provide the estimated total cost to the NSW Telco Authority of $1.325 billion to complete all stages of the CCEP until June 2021. Prior to this date, media releases only provided funding for the initial stages of the program or for the stages subject to a funding announcement.

Even during the September 2019 and March 2020 Parliamentary Estimate Committee hearings where the costings and delays to the CCEP were raised, the estimated full cost of the CCEP was not revealed.

Exhibit 7: CCEP funding in NSW Budget papers from 2015–16 to 2022–23
Financial year Type of major work Description of expenditure Forecast estimate to complete ($ million) Estimated duration
2015–16 New work Infrastructure Rationalisation Program: Planning and Pilot 18.3 2015–16
2016–17 Work in progress CCEP Planning and Pilot 18.3 2015–17
New work CCEP 45 2016–17
2017–18 New work CCEP 190.75 2017–21
2018–19 Work in progress CCEP North Coast and State-wide Detailed Design 190.75 2017–21
New work CCEP Greater Metropolitan Area 236 2018–22
2019–20 Work in progress CCEP 426.9 2018–22
2020–21 Work in progress CCEP 664.8 2018–22
2021–22 Work in progress CCEP 1,325 2018–26
2022–23 Work in progress CCEP 1,292.8 2018–26

Source: NSW Treasury, Annual State Budget Papers.

The original business case for the CCEP included estimated ESO costs, though these costs were not tracked throughout the program

Estimates for ESO costs for operating and maintaining their own radio networks over the four years from 2016–17 were included in the original March 2016 business case. They included $75.2 million for capital expenditure and $95 million for one-off operating costs. These costs, as well as costs incurred by ESOs due to the delay in the program, were not subsequently tracked by the NSW Telco Authority.

In January 2017, Infrastructure NSW reviewed the CCEP business case of March 2016. In this review, Infrastructure NSW recommended that the NSW Telco Authority identify combined and apportioned costs and cashflow for all ESOs over the CCEP funding period reflecting all associated costs to deliver the CCEP. These to include additional incidental capital costs accruing to ESOs, transition and migration to the new network and the cost (capital and operational) of maintaining existing networks. This recommendation was implemented in the November 2017 program review, with ESO capital costs estimated as $183 million.

In 2019, Infrastructure NSW conducted a Deep Dive Review on the progress of the CCEP. In this review, Infrastructure NSW made what it described as a 'critical recommendation' that the NSW Telco Authority:

…coordinate a stocktake of the costs of operational bridging solutions implemented by PSAs [ESOs] as a result of the 18-month delay, so that a whole-of-government cost impact is available to the NSW Government.  

It should be noted that the delay to CCEP completion now is seven years and that further ‘operational bridging solutions’ have been needed by the ESOs.

'Stay Safe and Keep Operational' costs incurred by ESOs will be significantly higher than originally estimated

Stay Safe and Keep Operational (SSKO) funding was established to provide funding to ESOs to maintain their legacy networks while the CCEP was refreshing and enhancing the PSN. This recognised that much of the network infrastructure relied on by ESOs had reached – or was reaching – obsolescence and would either require extensive maintenance or replacement before the PSN was available for ESOs to migrate to it. ESOs may apply to NSW Treasury for SSKO funding, with their specific proposals being reviewed (and endorsed, where appropriate) by the NSW Telco Authority. Accordingly, SSKO expenditure does not fall within the CCEP budget allocation.

As shown in the table below, extracted from the March 2016 CCEP business case, the total expected cost for SSKO purposes over the course of the CCEP was originally $40 million, assuming the enhanced PSN would be fully available by 2020.

Exhibit 8: Stay Safe and Keep Operational forecast costs, 2017 to 2020
Year 2017 2018 2019 2020 Total
SSKO forecast ($ million) 12.5 15 10 2.5 40

Source: March 2016 CCEP business case.

In October 2022, the expected completion date for the CCEP was re-baselined to August 2027. Accordingly, ESOs will be required to continue to maintain their radio networks using legacy equipment for seven years longer than the original 2020 forecast. This will likely become progressively more expensive and require additional SSKO funding. For example, NSW Telco Authority endorsed SSKO bids for 2022–23 exceeded $35 million for that year alone.

Compared to the original forecast made in the March 2016 CCEP business case of $40 million, we found ESOs had estimated SSKO spending to 2027 will be $292.5 million.

A refresh of paging network used by ESOs and the decommissioning of redundant sites were both removed from the original 2016 scope of the CCEP

Paging

A paging network is considered an important user requirement by the Fire and Rescue NSW, NSW Rural Fire Service, and NSW State Emergency Service. The 2016 CCEP business case included a paging network refresh within the program scope of works. This was reiterated in the November 2017 internal review of the program. These documents did not estimate a cost for this refresh. The March 2020 and October 2020 business cases excluded paging from the program scope. The audit is unable to identify when, why or by whom the decision was made to remove paging from the program scope, something that was also not well communicated to the affected ESOs.

In 2021, after representations from the affected ESOs, the NSW Telco Authority prepared a separate business case for a refresh of the paging network at an estimated capital cost of $60.31 million. This program was subsequently approved by the NSW Government and included in the 2022–23 NSW Budget.

In determining an estimated full whole-of-government cost of delivering the enhanced PSN, we have included the budgeted cost of the paging network refresh on the basis that:

  • it was expressly included in the original approved March 2016 business case
  • the capability is deemed essential to the needs of three ESOs.

Decommissioning costs

The 2016 CCEP business case included cost estimates for decommissioning surplus sites (whether ‘old’ GRN sites or sites belonging to ESOs’ own networks). These estimates were provided for both the NSW Telco Authority ($38 million) and for the ESOs ($55 million). However, while these estimates were described, they were not included as part of the NSW Telco Authority's estimated capital cost ($400 million) or (more relevantly) operating cost ($37.3 million) for the CCEP. This is despite decommissioning being included as one of eight planned activities for the rollout of the program.

In the October 2020 business case, an estimate of $201 million was included for decommissioning agency networks based on a model whereby:

  • funding would be coordinated by the NSW Telco Authority
  • scheduling and reporting through an inter-agency working group and
  • where appropriate, agencies would be appointed as the most appropriate decommissioning party.

This estimated cost is not included in the CCEP budget.

In determining an estimated full whole-of-government cost of the enhanced PSN, we have included the estimated cost of decommissioning on the basis that:

  • decommissioning was included in the 2016 CCEP business case as one of eight 'planned activities for the rollout of the program'
  • effective decommissioning of surplus sites and equipment (including as described in the business case as incorporating asset decommissioning, asset re-use, and site make-good) is an inherent part of the program management for an enhanced PSN
  • costs incurred in decommissioning are entirely a consequence of the CCEP program.

The estimated minimum cost of building an enhanced PSN consistent with the original proposal is over $2 billion

We have derived two estimated minimum whole-of-government costs for delivering an enhanced PSN. These are:

  • $2.04 billion when calculated from NSW Telco Authority data – shown as estimate A in Exhibit 9 below.
  • $2.26 billion when calculated from ESO supplied data – shown as estimate B in Exhibit 9.

Both totals include:

  • budgeted amounts for both CCEP capital expenditure ($1,292.8 million) and operating expenditure ($139 million)
  • the NSW Telco Authority's 2020 estimated cost for decommissioning ($201 million)
  • the NSW Telco Authority's approved funding for paging refresh ($60.3 million).

The two estimated totals primarily vary around the capital expenditure of ESOs (particularly SSKO funding). To determine these costs, we used ESO provided actual SSKO costs to date, as well as their estimates for maintaining their legacy radio networks through to 2027.

The equivalent cost estimates from the NSW Telco Authority were sourced from the November 2017 internal review and the October 2020 business case for CCEP. It should be noted that the amounts for both estimates are not audited, or verified, but do provide an indication of how whole-of-government costs have grown over the course of the program.

The increase in and reasons for the increase in total CCEP costs (capital and one-off operating) incurred or forecast by the NSW Telco Authority (from $437.3 million in 2016 to $1,431.8 million in 2022) have been provided to the NSW Government through various business cases and reviews prepared by the NSW Telco Authority, as well as by reviews conducted by Infrastructure NSW as part of its project assurance responsibilities.

However, the growth in ESO costs and other consequential costs, such as paging and decommissioning, from around $263 million in the 2016 CCEP business case to between $600 million and $800 million, has to a large degree remained invisible and unexplained to the NSW Government and other stakeholders

Exhibit 9: Estimated whole-of-government costs of the enhanced PSN
  Estimated whole-of-government cost, over time
Cost type 20161 20172 20203 2023–Estimate A4 2023–Estimate B5
$ million $ million $ million $ million $ million
CCEP capital expenditure 400a 476.7b 1,263.1c 1,292.8d 1,292.8d
CCEP operating expenditure 37.3a 41.7b 41.5e 139d 139d
CCEP total 437.3 518.4 1,304.6 1,431.8 1,431.8
ESO capital expenditure 75.2a,f 183b,e 75.4e 258.4g 292.5
ESO one-off operating expenditure 93a n.a.l 86.5e 86.5h 273
ESO total 168.2 183 161.9 344.9 565.5
Paging n.a.i n.a.i n.a.j 60.3k 60.3k
Decommissioning 93 n.a.l 201.0 201h 201
Paging and decommissioning total 93 n.a. 201 261.3 261.3
Whole-of-government total 698.5 701.4 1,667.5 2,038 2,258.6

Notes:
  1. Financial year 2016 to Financial year 2020.
  2. Financial year 2016 to Financial year 2021.
  3. Financial year 2016 to Financial year 2025.
  4. Financial year 2016 to Financial year 2026.
  5. Financial year 2022 to Financial year 2025.
  6. Stay Safe and Keep Operational (SSKO) costs plus terminals costs.
  7. November 2017 internal review and October 2020 Business case.
  8. October 2020 Business case.
  9. Included in CCEP capital expenditure at that time.
  10. By 2020, a refresh of the paging network had been removed from the CCEP scope.
  11. A separate business case for a refresh of the paging network was approved by government in 2022.
  12. Figure not included in the source document.
Sources:
  1. March 2016 CCEP business case.
  2. November 2017 Internal Review conducted by the NSW Telco Authority.
  3. October 2020 CCEP business case.
  4. Derived from business cases, with ESO costs drawn from NSW Telco Authority data.
  5. Derived from business cases, with ESO costs based on data provided to the Audit Office of New South Wales by each of the five ESOs.

Appendix one – Response from agency

Appendix two – Trunked public safety radio networks

Appendix three – About the audit

Appendix four – Performance auditing

 

 

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #383 - released 23 June 2023

 

Published

Actions for Natural disasters

Natural disasters

Community Services
Environment
Finance
Local Government
Planning
Transport
Treasury
Whole of Government
Asset valuation
Compliance
Financial reporting
Infrastructure
Regulation
Risk
Service delivery

What this report is about

This report draws together the financial impact of natural disasters on agencies integral to the response and impact of natural disasters during 2021–22.

What we found

Over the 2021–22 financial year $1.4 billion from a budget of $1.9 billion was spent by the NSW Government in response to natural disasters.

Total expenses were less than the budget due to underspend in the following areas:

  • clean-up assistance, including council grants
  • anticipated temporary accommodation support
  • payments relating to the Northern Rivers Business Support scheme for small businesses.

Natural disaster events damaged council assets such as roads, bridges, waste collection centres and other facilities used to provide essential services. Additional staff, contractors and experts were engaged to restore and repair damaged assets and minimise disruption to service delivery.

At 30 June 2022, the estimated damage to council infrastructure assets totalled $349 million.

Over the first half of the 2022–23 financial year, councils experienced further damage to infrastructure assets due to natural disasters. NSW Government spending on natural disasters continued with a further $1.1 billion spent over this period.

Thirty-six councils did not identify climate change or natural disaster as a strategic risk despite 22 of these having at least one natural disaster during 2021–22.

Section highlights

  • $1.4 billion from a budget of $1.9 billion was spent by the NSW Government in response to natural disasters during 2021–22.
  • Budget underspent for temporary housing and small business support as lower than expected need.

Section highlights

  • 83 local council areas were impacted by natural disasters during 2021–22, with 58 being impacted by more than one type of natural disaster.
  • $349 million damage to council infrastructure assets at 30 June 2022.

 

Published

Actions for Regulation and monitoring of local government

Regulation and monitoring of local government

Planning
Whole of Government
Environment
Local Government
Compliance
Regulation
Risk

What the report is about

The Office of Local Government (OLG) in the Department of Planning and Environment is responsible for strengthening the local government sector, including through its regulatory functions.

This audit assessed whether the OLG is effectively monitoring and regulating the sector under the Local Government Act 1993. The audit covered:

  • the effectiveness of departmental arrangements for the OLG to undertake its regulatory functions
  • whether the OLG has effective mechanisms to monitor and respond to risks and issues relating to council compliance and performance.

What we found

The OLG does not conduct effective, proactive monitoring to enable timely risk-based responses to council performance and compliance issues.

The OLG has not clearly defined and communicated its regulatory role to ensure that its priorities are well understood.

The OLG does not routinely review the results of its regulatory activities to improve its approaches.

The department lacks an adequate framework to define, measure and report on the OLG's performance, limiting transparency and its accountability.

The OLG's new strategic plan presents an opportunity for the OLG to better define, communicate, and deliver on its regulatory objectives.

What we recommended

The OLG should:

  • publish a tool to support councils to self-assess risks and report on their performance and compliance
  • ensure its council engagement strategy is consistent with its regulatory approach
  • report each year on its regulatory activities and performance
  • publish a calendar of its key sector support and monitoring activities
  • enhance processes for internally tracking operational activities
  • develop and maintain a data management framework
  • review and update frameworks and procedures for regulatory responses.

 

The Local Government Act 1993 (the LG Act) provides the legal framework for the system of local government in New South Wales. The LG Act describes the functions of councils, county councils and joint organisations which should be exercised consistent with the guiding principles and requirements of the LG Act. Councils also have functions and responsibilities under other Acts.

There are 128 local councils, nine county councils and 13 joint organisations of councils in the New South Wales local government sector. Each council is unique in size and location, owns and manages assets, and delivers services for their communities. According to 2021–22 data provided by the Department of Planning and Environment (the department), local councils managed $175.2 billion in infrastructure, property plant and equipment, held $16.8 billion of cash and investments, collected $7.8 billion in rates and charges and entered into $3.7 billion of borrowings. Councils' decision-making responsibilities directly impact the communities they serve, including responsibilities relevant to financial management, economic development, environmental sustainability and community wellbeing.

Under the LG Act, each elected council is accountable to the community they serve. In addition to Auditor-General reports, issues relating to council performance and compliance have been identified in public inquiries commissioned by the Minister for Local Government and investigations by the Independent Commission Against Corruption, NSW Ombudsman and Office of Local Government (OLG). Challenges and opportunities related to the operations and sustainability of the local government sector have also been reported by the sector and identified in reports by NSW government agencies such as the Independent Pricing and Regulatory Tribunal.

The department is the primary state government agency with responsibility for policy, legislative, regulatory and program functions for local government matters. The Office of Local Government (OLG) is a business unit within the department that advises the Minister for Local Government and exercises delegated functions of the Secretary of the Department of Planning and Environment under the LG Act.

Key departmental planning documents state that the OLG is responsible for strengthening the sustainability, performance, integrity, transparency and accountability of the local government sector. As the state regulator of the local government sector, the OLG aims to promote voluntary compliance, build councils' capacity for high performance, and intervene only when 'warranted and appropriate'. Relevant regulatory activities include issuing guidelines, investigating councils and councillors, and supporting the Minister for Local Government's discretionary intervention powers. The OLG's other functions include developing policy, administering grants and programs, supporting local government election processes, and issuing certain approvals.

The objective of this audit was to assess whether the OLG is effectively monitoring and regulating the local government sector under the LG Act. The assessment included:

  • the effectiveness of departmental arrangements for the OLG to undertake its regulatory functions
  • whether the OLG has effective mechanisms to monitor and respond to risks and issues relating to council compliance and performance.

This report focuses on the OLG’s activities relevant to powers under Chapter 13 of the LG Act, and related regulatory activities, such as monitoring risks, issuing guidance and engaging with councils. It also examines strategic and operational planning for these activities in the context of the OLG's other activities, and departmental arrangements to oversee and enable the OLG's regulatory effectiveness.

Other OLG activities were not in scope of the audit but are commented on in this report where contextually relevant. This includes the OLG's responsibilities under the LG Act with respect to councillor misconduct, and the 2022 review of the councillor misconduct framework commissioned by the former Minister for Local Government.

Conclusion

The Office of Local Government (OLG) in the Department of Planning and Environment (the department) does not conduct effective, proactive monitoring to enable timely risk-based responses to council performance and compliance issues. Council performance and compliance varies and a range of issues continue across the local government sector – some significant – that can impact on councils' operations and sustainability.

The department recognises that an effective and efficient sector is 'crucial to the economic and social wellbeing of communities across the State,' but the OLG does not routinely review the results of its regulatory activities to improve its approaches. The OLG has also not clearly defined and communicated its regulatory role to ensure that its priorities are well understood.

Inadequate performance measurement and reporting on its regulatory activities is a significant transparency and accountability issue, and the OLG cannot demonstrate that it is effectively regulating the local government sector.

The department lacks an adequate framework to define, measure and report on the OLG's performance as the state regulator of the sector under the Local Government Act 1993 (the LG Act). The OLG's various council engagement activities are not well structured and coordinated towards delivering on a clearly defined regulatory role and its regulatory priorities are not well understood. In 2022, the OLG identified, in its new strategic plan, that there is a need for it to define its role in the sector. It would be expected that a clearly defined role already underpins its aim to 'strike the right mix of monitoring, intervention, capability improvement and engagement activities'.

The OLG collects various sources of information about council compliance and performance but its systems and processes do not enable structured, proactive sector monitoring to enable timely, risk-based responses. Ineffective sector monitoring is a particular issue in the context of compliance, financial management and governance risks that have been identified in inquiries and reviews by other government agencies including integrity bodies and reported by the sector. Audit Office data for 2021–22 shows that 62 councils did not have or regularly update key corporate governance policies, and 63 do not have basic controls to manage cyber security risks. Further, 31 councils or joint organisations did not meet the statutory requirement to have an audit, risk and improvement committee by 30 June 2022.1

Overall, the OLG has made limited progress on projects that have been identified since 2019 to improve its sector monitoring, such as updating its performance measurement framework for councils. These factors limit its capacity to identify and act on issues early. In early 2023, the OLG started to implement a new council risk assessment tool.

The OLG's two main frameworks to guide its sector improvement and intervention activities were last updated in 2014 and 2017. The OLG considered relevant statutory criteria when advising the Minister on the use of powers to issue performance improvement and suspension orders under the LG Act. But the OLG lacks complete and approved procedures to guide staff when preparing advice and recommendations related to interventions, and other response options. This creates risks to the consistency and transparency of relevant processes.

The department and the OLG have identified that resourcing issues present a risk to the OLG's regulatory functions. Projects since 2021 to review the OLG's budget did not progress. The OLG does not routinely review the costs or evaluate the effectiveness of its regulatory activities.

The OLG's 2022–2026 strategic plan sets out a vision to be, 'A trusted regulator and capability builder enabling councils to better serve their communities'. Implementing the strategic plan presents an opportunity for the OLG to better define, communicate, and deliver on its regulatory objectives towards strengthening the sector. The OLG advises that a delivery plan and performance indicators for its new strategy are being developed, alongside work resulting from the 2022 review of the councillor misconduct framework.

 


1 This data has been sourced through the Audit Office's financial audits of councils. The Local Government 2022 report, which compiles results from the local government sector financial statement audits for the year ended 30 June 2022, will include this and additional data, and related information. This report is expected to be tabled in June 2023.

This chapter considers the effectiveness of departmental arrangements for the OLG to undertake its regulatory functions.

This chapter assesses whether the OLG has effective mechanisms to monitor and respond to risks and issues relating to council compliance and performance.

The OLG’s 2017 Improvement and Intervention Framework is intended to guide appropriate responses to council compliance or performance risks and issues. The publicly available framework states that generally, the OLG will encourage councils to meet their obligations before a more formal intervention will be considered. It also states that any intervention or improvement response will be proportionate to the circumstances.

Appendix one – Response from agency

Appendix two – Statutory powers relevant to council accountability under the Local Government Act

Appendix three – About the audit

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #380 - released 23 May 2023

Published

Actions for NSW government agencies' use of consultants

NSW government agencies' use of consultants

Treasury
Whole of Government
Compliance
Internal controls and governance
Management and administration
Procurement
Workforce and capability

What the report is about

This audit assessed how effectively NSW government agencies procure and manage consultants. It examined the role of the NSW Procurement Board and NSW Procurement (a unit within NSW Treasury) in supporting and monitoring agency procurement and management of consultants.

The audit used four sources of data that contain information about spending on consultants by NSW government agencies, including annual report disclosures and the State's financial consolidation system (Prime). It also reviewed a sample of consulting engagements from ten NSW government agencies.

What we found

Our review of a selection of consulting engagements indicates that agencies do not procure and manage consultants effectively.

We found most agencies do not use consultants strategically and do not have systems for managing or evaluating consultant performance. We also found examples of non-compliance with procurement rules, including contract variations that exceeded procurement thresholds.

NSW Procurement has made improvements to the information available about spending on consultants, including additional analysis and reporting. However, there is no single data source that accurately captures spending on consultants.

Our analysis of data on whole-of-government spending on consultants, drawn from agency annual reports, indicates that four large professional services firms accounted for about a quarter of consultancy expenditure from 2017–18 to 2021–22. This concentration increases strategic risks, including over-reliance on a limited number of providers and potential reduction in the independence of advice.

It is also highly unlikely that NSW government agencies will meet the government's 2019 policy commitment to reduce consultancy expenses by 20% each year, over four years, from 2019–20. NSW Treasury advised that to implement this commitment, agency budgets were reduced in Prime in line with the savings targets. However, actual spending on consulting in NSW Treasury's Reports on State Finances 2020–21 and 2021–22 was almost $100 million higher than the savings targets over the first three years since 2019–20.

What we recommended

The report made seven recommendations which aim to improve:

  • the quality and transparency of data on spending on consultants
  • monitoring of strategic risks and agency compliance with procurement and recordkeeping rules
  • agencies' strategic use of consultants, including evaluation and knowledge retention.

Between 2017–18 and 2021–22, NSW government agency annual reports disclosed total spending of around $1 billion on consultants across more than 10,000 engagements. More than 1,000 consulting firms provided services to NSW government agencies during this period. Consulting is a classification of professional services that is characterised by giving advice or recommendations on a specific issue. The NSW Procurement Board Direction PBD-2021-03 defines a consultant as a person or organisation that provides 'recommendations or professional advice to assist decision-making by management'. PBD-2021-03 notes that the advisory nature of the work of consultants is the main factor that distinguishes them from other providers of professional services.

The NSW Procurement Board is responsible for setting procurement policy, issuing directions to support policies, and monitoring and reporting on agency compliance with policies and directions. NSW Procurement, a division within NSW Treasury, supports agencies to comply with the NSW Procurement Board’s policies and directions. A 'devolved governance model' is used for procurement in New South Wales. This means the heads of government entities that are covered by the NSW Procurement Board’s directions are responsible for managing the entity's procurement, including managing risks, reporting and ensuring compliance, in line with procurement laws and policies.

This audit assessed how effectively NSW government agencies procure and manage consultants. It assessed the role of the NSW Procurement Board and NSW Procurement in supporting and monitoring agency procurement and management of consultants. It also reviewed a sample of consulting engagements from ten NSW government agencies to examine how agencies procured, managed and reported on their use of consultants. The ten NSW government agencies were:

  • NSW Treasury
  • Department of Communities and Justice
  • Department of Customer Service
  • Department of Education
  • Department of Planning and Environment
  • Department of Premier and Cabinet
  • Department of Regional NSW
  • Infrastructure NSW
  • Sydney Metro
  • Transport for NSW

There are four different sources of data that contain information about spending on consultants by NSW government agencies: the State's financial consolidation system (Prime), disclosures of spending on consultants in agency annual reports, and two systems operated by NSW Procurement (the Business Advisory Services (BAS) dashboard and Spend Cube). Each of these data sources serves a different purpose, and collects and categorises information differently. None of these provide a complete source of data on spending on consultants, either in their own right or collectively.

NSW Treasury considers Prime to be the 'source of truth' on consulting expenditure across the NSW public sector. An account within Prime records recurrent spending on consultants, but this account does not include capital expenditure (that is, spending on consultants that has from a financial reporting perspective been 'capitalised' to a project on the balance sheet). As the State's financial consolidation system, Prime captures all financial information. However, capitalised consulting expenditure is recorded within various capital accounts, and is not identifiable within these accounts. While this is appropriate for accounting purposes, it means that the Prime account that records recurrent consulting expenditure does not reflect total spending on consultants by NSW government agencies. We used the data in Prime to assess whether NSW government agencies met the NSW Government's policy commitment—stated before the 2019 election and costed by the Parliamentary Budget Office—to reduce recurrent expenditure on consulting by 20% each year, over four years, from 2019–20. We did this because, while the Prime account for recurrent consulting expenditure does not reflect all spending on consultants, it does capture the recurrent spending that was subject to the policy commitment.

Most NSW government agencies are required by legislation to disclose spending on consultants (as defined in PBD-2021-03) in their annual reports. These disclosures include both recurrent and capital expenditure. For consulting engagements that cost more than $50,000, the disclosures also provide itemised information, including the names of the individual projects and the consultants used. While this data is more complete than Prime because it includes capital expenditure, it also has some gaps. Some entities are excluded from public reporting requirements on consultant use. For example, NSW Local Health Districts (LHD) are not required to produce annual reports, and the Ministry of Health does not include LHD consulting expenditure in its annual report.1 We used annual report disclosure data to report on total expenditure on consultants, and the concentration of suppliers of consulting services to NSW government agencies.

The BAS dashboard and Spend Cube are systems created by NSW Procurement to collect information about spending on suppliers of professional services. This includes consultants, but also includes other professional services providers. The systems were not designed for reporting on spending on consulting as defined in PBD-2021-03. However, we have used this data to assess specific aspects of NSW Procurement's monitoring of the use of consultants by NSW government agencies.

In 2018, we conducted an audit titled 'Procurement and reporting of consultancy services'. This assessed how 12 NSW government agencies complied with procurement requirements and how NSW Procurement supported the functions of the NSW Procurement Board. The 2018 audit found that none of the 12 agencies fully complied with NSW Procurement Board Directions on the use of consultants and that the NSW Procurement Board was not fully effective in overseeing and supporting agencies’ procurement of consultants. Specific findings from the 2018 audit included: 

  • Agencies applied the definition of consultant inconsistently, which affected the accuracy of reporting on consultancy expenditure.
  • There was inadequate guidance from NSW Procurement for agencies implementing the procurement framework, with a need for additional tools, automated processes, and other internal controls to improve compliance.
  • NSW Procurement had insufficient data for effective oversight of procurement and did not publish any data on the procurement of consultancy services by NSW government agencies.

Conclusion

Our review of a selection of consulting engagements from ten NSW government agencies indicates that these agencies do not procure and manage consultants effectively. We found that most agencies do not have a strategic approach to using consultants, or systems for managing or evaluating their performance. We also found examples of non-compliance with procurement rules, including contract variations that exceeded procurement thresholds. NSW Procurement, a division within NSW Treasury, provides frameworks and some guidance to agencies for procuring consultants. However, gaps in its data collection and analysis mean monitoring of strategic risks is limited and it does not respond to agency non-compliance consistently. There are limitations in ability of various data sources to accurately record spending on consultants. These limitations include incomplete recording of all spending, and different definitions of consulting for accounting and financial reporting purposes. Notwithstanding these limitations, and based on information in the State's financial consolidation system (Prime)—which records recurrent expenditure on consultants—it is highly unlikely that NSW government agencies will meet the government's 2019 policy commitment to reduce spending on consultants, as defined in the policy commitment and costed by the Parliamentary Budget Office. 

The use of a 'devolved governance model' for procurement means NSW government agencies are responsible for developing and implementing their own systems that align with the NSW Government Procurement Policy Framework. Agency heads are responsible for demonstrating compliance. Most agencies included in this audit did not have a clear strategic approach to how and when consultants should be used (for example, to seek advice and expertise not already available within the agency) and were using consultants in an ad hoc manner.

Our analysis of whole-of-government spending on consultants, drawn from agency annual reports, indicates that four large professional services firms account for around 27% of spending on consultants in the period from 2017–18 to 2021–22. The number of firms making up the top 50% of expenditure decreased from 11 to eight during this time, with the other 50% of expenditure spread across more than 1,000 firms. Concentration of consulting engagements within a small number of firms increases strategic risks, including that advice is not sufficiently objective and impartial, and that NSW government agencies become overly reliant on selected professional services firms.

Our review of a selection of consulting engagements by NSW government agencies found several examples of non-compliance with procurement policy. This included the use of variations to contract values which exceeded allowable limits. Record keeping was inadequate in many cases we reviewed, which limits transparency about government spending. Most agencies did not proactively manage their consulting engagements. The majority of consulting engagements that we reviewed were not evaluated or assessed by the agency for quality. Very few used any processes to ensure the transfer and retention of knowledge generated through consulting engagements. This means agencies miss opportunities to increase core staff skills and knowledge and to maximise value from these engagements.

NSW Procurement oversees a detailed policy framework that provides guidance and support to NSW government agencies when they are using consultants. The policy framework provides mandatory steps and some other guidance. Our audit on the procurement and reporting of consultancy services in 2018 found that agency reporting on the use of consultants was inconsistent and recommended that NSW Procurement should improve the quality, accuracy and completeness of data collection. NSW Procurement’s guidance on how agencies should classify and report on consulting engagements remains ambiguous. This contributes to continued inconsistent reporting by and across agencies, and reduces the quality of data on the use of consultants.

NSW Procurement has made some improvements to the information available about spending on consultants since our audit in 2018, including additional analysis and reporting that is available to agencies. However, there is still no single data source that accurately captures all spending on consultants. This is despite our recommendations in 2018 that NSW Procurement improve the quality of information collected from agencies and suppliers, which NSW Procurement accepted. This makes it harder for NSW Procurement or individual agencies to track trends and identify risks or improvement opportunities in the way consultants are used. 

In early 2019, the NSW Government made a policy commitment to reduce consultancy expenses by 20% each year, over four years, from 2019–20 (excluding capital-related consultancy expenses). This commitment was set out in the Parliamentary Budget Office's '2019 Coalition Election Policy Costings (Policy Costings)'. NSW Treasury subsequently advised that to implement this commitment, agency budgets were reduced in Prime in line with the savings targets. However, actual spending on consultants recorded in Prime in the first three years after the commitment was made was almost $100 million higher than the targets. We did not see any evidence that the financial data on actual expenditure was used to inform reporting on NSW government agencies' progress toward achieving the savings set out in the policy commitment.


1 The Government Sector Finance Legislation (Repeal and Amendment) Act 2018 No 70 will amend the Health Services Act 1997 to specify that annual reporting information for any or all NSW Health entities may be included in the annual reporting information prepared by the Ministry of Health under the Government Sector Finance Act 2018. This provision is expected to commence on 1 July 2023.

This chapter outlines our findings on the role of NSW Procurement in overseeing the use of consultants by NSW government agencies.

This chapter outlines our findings on the use of consultants by the ten NSW government agencies that were included in this audit.

Appendix one – Responses from auditees

Appendix two – About the audit

Appendix three – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 

Parliamentary reference - Report number #378 - released 2 March 2023

Published

Actions for Government advertising 2021–22

Government advertising 2021–22

Finance
Education
Whole of Government
Compliance
Management and administration
Procurement

What the report is about

The Government Advertising Act 2011 requires the Auditor-General to undertake a performance audit on government advertising activities each financial year.

This audit examined whether TAFE NSW's annual advertising campaign in 2021–22:

  1. was carried out effectively, economically, and efficiently
  2. complied with regulatory requirements and the Government Advertising Guidelines.

What we found

TAFE NSW complied with Section 6 of the Act, prohibiting political content.

It also complied with most other advertising requirements.
 
An important exception was that the Managing Director certified that the campaign complied with regulatory requirements and was an efficient and cost-effective means of achieving its public purpose, before a cost-benefit analysis (CBA) was completed.

We have found issues with agencies complying with CBA requirements in previous government advertising audits. This includes the failure to complete them before signing compliance certificates.

The policy owner, the Department of Customer Service (DCS), does not consider oversight of CBAs to be within the scope of their peer review process.  

TAFE NSW evaluated this advertising campaign by surveying a population significantly broader than the target audience. As such, survey results may not accurately reflect the views of the intended audience.

What we recommended

By 30 June 2023, TAFE NSW should:

  1. implement processes that ensure:
    1. CBAs are completed before the launch of campaigns over $1 million
    2. compliance certificates are completed only after all regulatory requirements are met
  2. consider adding to its current evaluation methods by surveying a population which closely reflects the age profile of its intended target audience.

By June 2023, DCS should:

  1. improve whole‑of‑government reporting and monitoring processes to provide the NSW Government with a central view of compliance, including the completion of CBAs by agencies.

The Government Advertising Act 2011 (the Act) sets out requirements that must be followed by a government agency when it carries out a government advertising campaign. The requirements include an explicit prohibition on political advertising, as well as a need to complete a peer review and cost-benefit analysis before the campaign commences. The accompanying Government Advertising Regulation 2018 (the Regulation) and Government Advertising Guidelines (the Guidelines) address further matters of detail.

The Act also requires the Auditor-General to conduct a performance audit on the activities of one or more government agencies in relation to government advertising campaigns in each financial year. The performance audit must assess whether a government agency (or agencies) has carried out activities in relation to government advertising campaigns in an effective, economical and efficient manner. It also assesses compliance with the Act, the Regulation, other laws and the Guidelines.

This audit examined TAFE NSW's advertising campaign for the 2021–22 financial year. TAFE NSW is the NSW Government's public provider of vocational education and training. TAFE NSW carries out an advertising campaign every year. In 2021–22, it spent $15.16 million on developing and implementing advertising. TAFE NSW used channels such as television, radio, internet and social media, press, and out of home advertising in public settings such as bus stops. The advertising aimed to increase the percentage of people considering TAFE NSW for training or education, grow the percentage of people who consider TAFE NSW to be the preferred education provider in NSW, and maintain the proportion of people who are aware of TAFE NSW more generally.

There are a range of private service providers helping to deliver vocational education and training in NSW.

Conclusion

TAFE NSW’s advertising campaign for 2021–22 was for an allowed purpose under the Act and did not include political advertising. TAFE NSW complied with most of the requirements set out in the Act, the Regulation, and the Guidelines, but it failed to complete a cost-benefit analysis for the campaign or provide sufficient support for the compliance certificate signed by TAFE NSW's Managing Director.

TAFE NSW complied with the requirement to complete a peer review of its campaign, but it did not meet the requirement to complete a cost-benefit analysis, either before it launched the campaign or during its implementation throughout 2021–22. Some of TAFE NSW's advertising did not meet the requirement for statements to be clearly supported by evidence.

The Act requires the head of an agency to sign a compliance certificate stating that, among other things, the campaign complies with the Act, the Regulation, and the Guidelines, and that the campaign is an efficient and cost-effective means of achieving the public purpose. TAFE NSW's Managing Director signed a compliance certificate in May 2021. However, TAFE NSW had not prepared a cost-benefit analysis as required under the Act and therefore TAFE NSW's Managing Director could not validly sign the compliance certificate. TAFE NSW did not subsequently complete a cost-benefit analysis during the campaign.

The campaign achieved many of its objectives and other performance measures and is likely to have been impactful. It is also likely that TAFE NSW’s advertising campaign in 2021–22 represented economical, efficient, and effective spend. However, the lack of a cost-benefit analysis meant that this could not be confidently demonstrated by TAFE NSW.

TAFE NSW used internal resources to create its advertising content, such as videos, radio scripts and press advertising, and relied upon a specialist partner to arrange and place its media in the appropriate advertising channel. TAFE NSW also adjusted the advertising campaign in response to performance data and in response to changes in the educational and advertising marketplaces.

TAFE NSW evaluated the impact of its advertising and tracked its brand performance using a survey which reflected the New South Wales general population aged between 16 and 60. However, this evaluation did not match TAFE NSW's advertising spend as TAFE NSW directed significantly more of its campaign budget to influencing younger people in this cohort.

This part of the report sets out key aspects of TAFE NSW's compliance with the government advertising regulatory framework. It considers whether TAFE NSW complied with the:

  • Government Advertising Act 2011
  • Government Advertising Regulation 2018
  • NSW Government Advertising Guidelines 2012 and other relevant policy.

This part of the report considers whether TAFE NSW's advertising program for 2021–22 was carried out in an effective, efficient, and economical manner.

Appendix one – Responses from agencies

Appendix two – About the campaign

Appendix three – About the audit

Appendix four – Performance auditing

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.

 