Contents
Volume Nine 2015 Planning and Environment
Contents
Overview
The NSW Environment Protection Authority has reduced the average time to assess contaminated sites from 203 days in 2013-14 to 73 days in 2014-15. It is also improving transparency by making more information on its performance publicly available.
In 2014-15, the Department of Planning and Environment increased new housing approvals across New South Wales by 12 per cent to 58,252, exceeding the State priority target of 50,000. It also reduced the time taken to assess major projects from about three years in 2013-14 to four months in 2014-15.