Overview
The decision to seek development of Walsh Bay without a Master Plan and/or detailed study as to the state of the precinct presented significant problems throughout the life of the project. Now, four years later, negotiations still continue on the details of the final scheme. Based on the latest estimates, it will not provide a financial return as was originally expected. The audit found no evidence to indicate why the former Government wished to expedite Walsh Bay, but it is aware that there was an election due. Many of the problems which have been encountered could have been avoided with more careful and more extensive consideration at the start, particularly in the light of Property Services Group's recommendations.
Parliamentary reference - Report number #58 - released 17 December 1998