Premier and Cabinet 2021

Auditor-General's foreword

This report analyses the results of our audits of the Premier and Cabinet cluster agencies for the year ended 30 June 2021.

Our preferred approach is to table the ‘Report on State Finances’ in Parliament before any other cluster report. This is because the 'Report on State Finances' focuses on the audit results and observations relating to the Total State Sector Accounts, in effect a consolidation of all government agencies. This year the 'Report on State Finances' has been delayed due to significant accounting issues being considered in the Total State Sector Accounts and which may impact the Treasury and Transport clusters.

As there are no outstanding matters relating to audits in the Premier and Cabinet cluster impacting the Total State Sector Accounts we have decided to break with normal practice and table this cluster report ahead of the ‘Report on State Finances’.

Report highlights

What the report is about

The results of the Premier and Cabinet cluster (the cluster) agencies' financial statement audits for the year ended 30 June 2021.

What we found

Unmodified audit opinions were issued for all Premier and Cabinet cluster agencies.

The number of monetary misstatements decreased from 49 in 2019–20 to 38 in 2020–21.

The Library Council of New South Wales corrected a prior period error of $325 million. In 2017, the council split its collection assets into six asset classes, but not the related asset revaluation reserves. To correct this error, some revaluation decrements previously recognised in asset revaluation reserves were reclassified to accumulated funds.

Eight agencies did not complete all of the mandatory early close procedures.

What the key issues were

The Premier and Cabinet cluster was impacted by three Machinery of Government (MoG) changes during 2020–21.

The changes resulted in the transfer of activities and functions in and out of the cluster and the creation of a new entity - Investment NSW.

The transferor entities continued to provide services to Investment NSW subsequent to 30 June 2021. There were no formal service level agreements in place for the provision of these services.

The New South Wales Electoral Commission (the Commission) and Sydney Opera House Trust obtained letters of financial support from their relevant Minister and/or NSW Treasury in 2020–21. The postponement of local government elections impacted the Commission's operations due to increased planned expenditure to support a COVID-safe election. Sydney Opera House Trust's ability to generate revenue was impacted due to the closure of the Concert Hall partly due to COVID-19 and planned renovations.

The number of repeated audit issues raised with management and those charged with governance increased from 22 in 2019–20 to 24 in 2020–21.

There were 47 moderate risk and 28 low risk findings identified. Of the total findings there were 24 repeat issues.

What we recommended

Investment NSW should ensure services received from other agencies are governed by service level agreements.

Fast facts

The Department of Premier and Cabinet supports the Premier and Cabinet to deliver the government's objectives, infrastructure, preparedness for disaster, incident recovery, arts and culture.

  • $11.9b of property, plant and equipment as at 30 June 2021
  • $4.4b total expenditure incurred in 2020-21
  • 100% unqualified audit opinions were issued on agencies' 30 June 2021 financial statements
  • 47 moderate risk findings were reported to management 
  • 38 monetary misstatements were reported in 2020-21
  • 32% of all reported issues were repeat issues.

1. Introduction

This report provides Parliament and other users of the Premier and Cabinet’s financial statements with the results of our audits, our observations, analysis, conclusions and recommendations in the following areas:

  • financial reporting
  • audit observations.

1.1 Snapshot of the cluster

Image
description of the premier and cabinet cluster including state outcomes and key agencies. For an accessible version please contact communications@audit.nsw.gov.au
Source: NSW Budget Papers 2021–22.
 

1.2 Changes to the cluster

Machinery of Government (MoG) changes

The Premier and Cabinet cluster was impacted by three Machinery of Government (MoG) changes during 2020–21. MoG refers to how the government organises the structures and functions of the public service. MoG changes are where the government reorganises structures and functions of the public service and they are given effect by Administrative Orders.

These changes were implemented through the following Administrative Changes Orders:

  • Administrative Arrangements (Administrative Changes - Miscellaneous) Order 2020, issued and effective 1 July 2020. This order transferred the Aboriginal Cultural Heritage Regulation Branch from Department of Planning Industry and Environment (DPIE) to the Department of Premier Cabinet (DPC).
  • Administrative Arrangements (Administrative Changes- Transfer of Staff to Western City and Aerotropolis Authority Staff Agency) Order 2020, issued 14 October 2020 and effective 16 October 2020. This order transferred:
    • persons employed in the Western Sydney City Deal Delivery Office of the Greater Sydney Commission Staff Agency to the Western City and Aerotropolis Authority Staff Agency. The City Deal Delivery Office Western City Liveability Program was also transferred
    • persons employed in the Western Sydney Investment Attraction Office of the NSW Treasury to the Western City and Aerotropolis Authority Staff Agency.
  • Administrative Arrangements (Administrative Changes – Miscellaneous) Order 2021, issued 26 March 2021 and effective 29 March 2021. This order established Investment NSW, transferring functions and activities from the Department of Education, NSW Treasury, DPC and the Department of Planning, Industry and Environment to Investment NSW. The persons employed in the Destination NSW Staff Agency were transferred to Investment NSW, abolishing the staff agency. Persons employed in the Treasury Precincts team were transferred to the Greater Sydney Commission Staff Agency. Additionally, the following agencies were transferred from the Treasury cluster to Premier and Cabinet cluster:
    • Western Parkland City Authority (previously Western City and Aerotropolis Authority) and its staff agency
    • Jobs for NSW Fund.

Our performance audit report 'Machinery of Government changes' is expected to consider issues associated with MoG changes, including whether they achieved their effectiveness and efficiency goals and improved public sector administration. The report is scheduled to be published this month.

Changes to enabling legislation

On the 11 December 2020, Schedule 1 of Statue Law (Miscellaneous Provisions) Act 2020 altered the name of Western City and Aerotropolis Authority and its staff agency to Western Parkland City Authority. It did not affect the Authority's structure or financial reporting requirements.

2. Financial reporting

Financial reporting is an important element of good governance. Confidence and transparency in public sector decision making are enhanced when financial reporting is accurate and timely.

This chapter outlines our audit observations related to the financial reporting of agencies in the Premier and Cabinet cluster (the cluster) for 2021.

Section highlights

  • Unqualified audit opinions were issued on all completed cluster agencies' 2020–21 financial statements.
  • Monetary misstatements decreased from 49 in 2019–20 to 38 in 2020–21.
  • Thirteen agencies were exempt from financial reporting in 2020–21. 

2.1 Cluster financial information 2021

Agency Total assets $m Total liabilities $m Total income* $m Total expenses** $m
Principal department        
Department of Premier and Cabinet 1,374 335 2,620 2,459
Other cluster agencies listed in Appendix A of Treasury Direction TD21-02        
Art Gallery of New South Wales Trust 2,414 31 209 54
Australian Museum Trust 1,116 12 71 55
Destination NSW 28 27 198 190
Greater Sydney Commission 3 5 21 22
Historic Houses Trust of New South Wales 355 7 32 28
Independent Commission Against Corruption 17 16 29 29
Infrastructure NSW 2,113 1,244 756 326
Investment NSW 91 78 63 57
Jobs for NSW Fund 70 5 21 8
Law Enforcement Conduct Commission 12 10 22 22
Library Council of New South Wales 1,955 12 110 96
New South Wales Electoral Commission 69 49 87 82
Ombudsman's Office 13 13 26 27
Parliamentary Counsel's Office 4 4 12 11
Public Service Commission 12 8 40 39
Resilience NSW 492 323 637 576
State Archives and Records Authority of New South Wales 1,135 11 50 32
Sydney Opera House Trust 3,041 56 231 120
Trustees of the Museum of Applied Arts and Sciences 543 9 63 63
Western Parkland City Authority 47 4 93 53
Immaterial entities*** 268 121 182 172
* Include other gains.
** Include other losses.
*** Immaterial agencies not included in TD 21-02 and part of the cluster includes Art Gallery of New South Wales Foundation, Corporation Sole ‘Minister Administering the Heritage Act 1977’, Foundation for the Historic Houses Trust of New South Wales, Library Council of New South Wales (Staff Agency), National Art School, State Library of New South Wales Foundation, The Australian Institute of Asian Culture and Visual Arts Limited (VisAsia) and The Brett Whiteley Foundation.
**** Audit Office of NSW listed in Appendix A of TD 21-02 is excluded as it is not audited by the Auditor-General.
Source: Agencies' audited 2020–21 financial statements.

2.2 Quality of financial reporting

Audit opinions

Unqualified audit opinions were issued on agencies' financial statements

Unqualified audit opinions were issued on all completed cluster agencies' 30 June 2021 financial statements. Sufficient and appropriate audit evidence was obtained to conclude the financial statements were free of material misstatement.

Audits are ongoing for:

  • Corporation Sole 'Minister Administering the Heritage Act 1977'
  • Jobs for NSW Fund.

The number of identified monetary misstatements decreased in 2020–21

The number of monetary misstatements identified during the audit of the financial statements for the cluster decreased from 49 in 2019–20 to 38 in 2020–21. A monetary misstatement is an error in amount recognised in the financial statements initially submitted for audit.

Reported corrected misstatements decreased from 36 in 2019–20 to 28 in 2020–21. Reported uncorrected misstatements decreased from 13 in 2019–20 to 10 in 2020–21.

The table below shows the number and quantum of monetary misstatements for the past two years.

Year ended 30 June 2021 2020
  Corrected misstatements Uncorrected misstatements Corrected misstatements Uncorrected misstatements
Less than $50,000 4 3 5 4
$50,000 to $249,999 12 1 10 4
$250,000 to $999,999 4 4 7 5
$1 million to $4,999,999 7 2 8 --
$5 million and greater 1 -- 6 --
Total number of misstatements 28 10 36 13

Source: Engagement Closing Reports issued by the Audit Office of New South Wales.

Refer to Appendix one for details of corrected and uncorrected monetary misstatements by agency.

Of the 28 corrected misstatements, one had a gross value of greater than $5.0 million and related to a prior period error. The Library Council of New South Wales corrected a prior period error of $325 million. In 2017, the council split its collection assets into six asset classes, but not the related asset revaluation reserves. To correct this error, some revaluation decrements previously recognised in asset revaluation reserves were reclassified to accumulated funds.

New financial reporting provisions became effective from 1 July 2021

The financial reporting provisions in Division 7.2 of the Government Sector Finance Act 2018 (GSF Act) commenced on 1 July 2021. Agencies prepared their annual GSF financial statements for the 2020–21 financial year under Division 7.2 of the GSF Act.

Thirteen agencies were exempted from financial reporting in 2020–21

Part 3A Division 2 of the Government Sector Finance Regulation 2018 (GSF Regulation) prescribes certain kinds of GSF agencies not to be a reporting GSF agency. For 2020–21, the following cluster agencies have assessed and determined they met the reporting exemption criteria under the GSF Regulation, and therefore were not required to prepare annual financial statements:

Exempted agencies GSF Regulation reference Basis for reporting exemption
Special purpose staff agencies

Art Gallery of New South Wales Trust (Staff Agency)

Australian Museum Trust (Staff Agency)

Destination New South Wales (Staff Agency) - The staff agency ceased its operations as at 28 March 2021

Greater Sydney Commission (Staff Agency)

New South Wales Electoral Commission (Staff Agency)

Office of the Law Enforcement Conduct Commission (Staff Agency)

Sydney Opera House Trust (Staff Agency)

Trustees of the Museum of Applied Arts and Sciences (Staff Agency)

Western Parkland City Authority (Staff Agency)

Infrastructure NSW (Staff Agency).

Part 3A, Division 2, Section 9F of the GSF Regulation

GSF Regulation prescribes that a GSF agency that comprises solely of persons who are employed to enable another particular GSF agency to exercise its function not to be a reporting GSF agency.

All nine staff agencies satisfy this requirement and therefore were exempt from preparing financial statements in 2020–21.

 
Small agencies

Aboriginal Languages Trust

Office of the Inspector of Law Enforcement Conduct Commission

Heritage Council of NSW

Part 3A, Division 2, Section 9D of the GSF Regulation

GSF Regulation prescribes a GSF agency meeting all the following requirements not to be a reporting GSF agency:

  • the assets, liabilities, income, expense, commitments and contingent liabilities of the agency are each less than $5.0 million
  • the total cash or cash equivalent held by the agency is less than $2.5 million
  • at least 95 per cent of the agency’s income is derived from money paid out of the Consolidated Fund or money provided by other GSF agencies
  • the agency does not administer legislation for a Minister by or under which members of the public are regulated.

In 2019–20, the above staff agencies were also exempt from financial reporting under Schedule 2 of the Public Finance and Audit Regulation 2015.

2.3 Timeliness of financial reporting

Early close procedures

Early close mandatory procedures were submitted on time for all cluster agencies

NSW Treasury prescribes certain mandatory early close procedures to improve the quality and timeliness of agency year-end financial statements. In March 2021, NSW Treasury reissued Treasurer’s Direction TD19-02 ‘Mandatory Early Close as at 31 March each year’ (TD19-02) and released TPP21-01 ‘Agency Direction for the 2020–21 Mandatory Early Close’. These pronouncements require the GSF agencies listed in Appendix A of TD19-02 to perform the mandatory early close procedures and provide the outcomes to the audit team by 26 April 2021.

The table below summarises the agencies' completion of the 16 mandatory early close procedures, noting that some procedures are not relevant to all agencies. The 16 procedures are listed at Appendix two.

Agency Completed Not completed Not applicable*
Principal department
Department of Premier and Cabinet - cluster lead 12 2 2
Other cluster agencies listed in Appendix A of Treasury Direction TD19-02
Art Gallery of New South Wales Trust 13 -- 3
Australian Museum Trust 9 4 3
Destination NSW 2021 10 2 4
Greater Sydney Commission 10 1 5
Historic Houses Trust of New South Wales 16 -- --
Independent Commission Against Corruption 7 -- 9
Infrastructure NSW 8 3 5
Investment NSW ** ** **
Jobs for NSW Fund *** *** ***
Law Enforcement Conduct Commission 11 -- 5
Library Council of New South Wales 13 -- 3
New South Wales Electoral Commission 9 2 5
Ombudsman’s Office 12 -- 4
Parliamentary Counsel’s Office 11 -- 5
Public Service Commission 11 -- 5
Resilience NSW 12 -- 4
State Archives and Records Authority of New South Wales 16 -- --
Sydney Opera House Trust 15 -- 1
Trustees of the Museum of Applied Arts and Sciences 11 1 4
Western Parkland City Authority 8 2 6

* Certain mandatory early close procedures are not applicable to agencies. For instance, if an agency did not have changes in accounting policy or a correction of material prior period error, those procedures would be considered as not applicable to the agency.
** Agency was created on 29 March and therefore exempt from early close procedures.
*** Special Deposit Account not required to perform early close procedures for the 30 June 2021 financial year.
Source: Reports on early close procedures 2021 issued by the Audit Office of New South Wales.

Agencies can improve their completion of early close procedures

The following agencies did not perform all required procedures. 

Cluster agencies Description of incomplete early close procedures
Principal department
Department of Premier and Cabinet - cluster lead
  • Revaluation of property, plant and equipment
    The results of comprehensive valuation undertaken by an external valuer of Department’s land and buildings as at 31 March 2021 were not finalised in time for early close.
  • Management did not finalise impairment assessment for leases managed by Property NSW by 31 March 2021.
Other agencies listed in Appendix A of TD19-02
Australian Museum Trust
  • Significant management judgements and assumptions
    Management did not:
    - finalise accounting treatment for Collection Enhancement Project related costs
    - document their assessment of the potential need to consolidate Australian Museum Foundation within the Australian Museum Trust's financial statements.
  • Changes to legislation
    Management did not formalise the process for assessing the impact of Government Sector Finance Act 2018 (GSF Act).
  • Prior year Management Letter and Engagement Closing Report issues
    A new process for additions to collection assets was established in 2020–21. However, the staff member responsible for the new process had left the organisation and there was uncertainty on whether the change was implemented.
  • Status of known accounting issues
    Management did not consider the financial implications of the Collection Enhancement Project and it is unclear whether all project functions meet the definition of a capital asset, creating a risk of material overstatement of intangible assets.
Destination NSW 2021
  • Inter and intra (cluster) agency transactions and balances
    Management did not update financial statements at 31 March 2021 to reflect latest Administrative Arrangements Order 2021 as these were effective 29 March 2021
  • New and updated accounting standard
    Management did not formalise the assessment of accounting standards issued but not yet effective in time for early close. The assessment of AASB 1059 ‘Service Concession Arrangements: Grantors’ when completed, resulted in no impact to Destination NSW.
Greater Sydney Commission
  • Inter and intra (cluster) agency transactions and balances
    Management did not reflect Administrative Changes - Transfer of Staff to Western City and Aerotropolis Authority Staff Agency that commenced on 16 October 2020. The budget transfers were not confirmed by 31 March 2021.
Infrastructure NSW
  • Fair value assessment of property, plant and equipment
    Management did not finalise an annual assessment of fair value of property, plant and equipment by the due date.
  • Significant management judgements and assumptions
    Management did not provide documentation by the due date to support significant judgements and assumptions used in the fair value assessment of property, plant and equipment, valuation of inventories and assets held for sale and discount rates and cash flows used in the receivable calculation for finance lease assets.
  • Finalise right-of-use assets and lease liability balances
    Management did not review the lease calculation and assumptions used by Property NSW who manage Infrastructure NSW's lease by the due date.
New South Wales Electoral Commission
  • Changes to legislation
    Changes to delegations for expenditure powers were not finalised by the due date.
  • Delegations
    The Commission’s Delegation Manual did not meet the requirements of the Government Sector Finance Act 2018.
Trustees of the Museum of Applied Arts and Sciences
  • Fair value assessment of property, plant and equipment
    Management did not perform an annual fair value assessment of collection assets and were granted an exemption on 3 March 2021 by NSW Treasury
Western Parkland City Authority
  • Significant management judgements and assumptions
    Capitalisation Policy to support the judgements and assumptions applied when capitalising expenditure had not been formally approved by the Board.
  • Prior year Management Letter and Engagement Closing Report issues
    Management did not provide sufficient audit evidence for capitalising employee costs.

Source: Reports on early close procedures 2021 issued by the Audit Office of New South Wales.

The review of agencies' early close procedures found more work needs to be done to:

  • appropriately document or perform a significant judgements and assumptions assessment
  • perform and or document their assessment fair value assessment of property, plant and equipment
  • finalise right-of-use assets/liabilities or perform an impairment assessment of right of use assets
  • appropriately assess the impact of implementing new accounting standards.

Year-end financial reporting

NSW Treasury extended financial reporting deadlines

Due to the COVID-19 pandemic, NSW Treasury extended the year-end financial reporting deadline for agencies listed in Appendix A of Treasury Direction TD21-02 'Mandatory Annual Returns to Treasury' (TD21-02) to 2 August 2021.

During May and June 2021, NSW Treasury issued a suite of Treasurer's Directions, Treasury Circular and policy papers for 2020–21 financial reporting requirements and timetables:

  • Treasurer's Direction TD21-02 and Treasury Policy Paper TPP21-04 'Agency Direction for the 2020–21 Mandatory Annual Returns to Treasury' require agencies listed in the Appendix A of TD21-02 to submit their 2020–21 financial statements to both NSW Treasury and the Audit Office by 26 July 2021.
  • Treasury Circular TC21-04 '2020–21 Mandatory Annual Returns to Treasury for non-GSF agencies' requires NSW public sector agencies not listed in Appendix A of TD21-02 to submit their draft 2020–21 financial statements to NSW Treasury by 26 July 2021.
  • Treasurer's Direction TD21-03 'Submission of Annual GSF Financial Statements to the Auditor-General' requires reporting GSF agencies that are not listed in Appendix A of TD21-02 to submit their annual financial statements within six weeks after the year end.

The following agencies obtained NSW Treasury's approval to further delay submission of their 30 June 2021 financial statements: 

Cluster agencies Revised deadline Reason
Investment NSW 13 August 2021 Extension granted as newly created entity.
Jobs for NSW Fund 13 August 2021 Extension granted as affiliated with newly created entity.

Financial statements were submitted on time for all cluster agencies

Cluster agencies met the revised or approved reporting deadlines for submitting their 2020–21 financial statements.

On 1 July 2021, the Public Finance and Audit Act 1983 (PF&A Act) was renamed the Government Sector Audit Act 1983 (GSA Act). Whilst the PF&A Act required the Auditor-General to audit agencies' financial statements within ten weeks of their receipt, the GSA Act does not specify the statutory deadline for issuing the audit reports.

The table in Appendix three shows the timeliness of the year-end financial reporting for cluster agencies.

2.4 Key accounting issues

Financial sustainability

Two agencies received letters of financial support

The COVID-19 pandemic and its consequential impacts has affected the way in which some of the cluster agencies operate. The New South Wales Electoral Commission (the Commission) and Sydney Opera House Trust obtained letters of financial support from their relevant Minister and/ or NSW Treasury.

The Commission was impacted by the postponement of the local government elections to 4 December 2021. This deferral impacted the Commission's operations due to increased planned expenditure to support a COVID-safe election. The Sydney Opera House Trust's ability to generate revenue was impacted due to the closure of the Concert Hall, partly due to COVID-19 and planned renovations.

While not requiring a letter of financial support, Greater Sydney Commission continued to report negative equity of $2.7 million in 2020–21 ($1.6 million in 2019–20). The negative equity is primarily due to timing differences, as accrued expenditure in 2016–17 was not funded by grant revenue from DPC. Future financial support of $25.5 million is provided to Greater Sydney Commission in the 2021–22 NSW Budget Papers.

Prior period errors corrected retrospectively

The Library Council of New South Wales and Infrastructure NSW corrected prior period errors

The Library Council of New South Wales (the Council) and Infrastructure NSW reported the retrospective correction of prior period errors.

In 2017, the Council split its collection assets into six asset classes, but not the related asset revaluation reserves. Until 2020–21, revaluation adjustments were made against the total collection asset reserve balance. When the reserves were split into classes, it was identified that two of the asset class reserves did not have sufficient surplus to offset the revaluation decrements posted since 2017. This resulted in a $325 million prior period error.

Infrastructure NSW omitted the value of land under roads of $15.0 million from their 2019–20 financial statements. This was self-identified and corrected in 2020–21 before financial statements were submitted for audit.

Both agencies corrected the misstatements retrospectively in accordance with AASB 108 'Accounting Policies, Changes in Accounting Estimates and Errors'.

2.5 Key financial statement risks

The table below details our specific audit coverage and response over key areas of financial statements risks that had the potential to impact the financial statements of cluster agencies.

Department of Premier and Cabinet

The Department of Premier and Cabinet (DPC) leads the NSW public sector to deliver on the NSW Government's commitments and priorities. DPC supports the NSW Premier and Ministers by coordinating the initiatives of Ministers and their agencies, managing the passage of government legislation, supporting the delivery of major projects and planning significant state events.

  Key financial statement risk Audit response

Grants and subsidies expenditure

Grants and subsidies expenses for the year was $2.1 billion ($1.3 billion in 2019–20). Our audit risk rating is higher because:

  • the grants and subsidies are financially significant
  • the grants program has a diverse number of recipients including NSW Government agencies, NSW local councils and non-government organisations.

Our audit procedures tested for accuracy, validity, compliance with conditions and presentation and disclosure against the requirements of the Australian Accounting Standards and NSW Treasurer's Directions.

Investment NSW

Investment NSW is a new central agency created on 29 March 2021 by bringing together all of the NSW Government’s economic development and attraction activities into the one place, allowing the entity to leverage the state’s successful COVID-19 response to drive local and international investment and create jobs for NSW.

  Key financial statement risk Audit response

Completeness of general ledger

Investment NSW was created on 29 March 2021 by transferring functions and activities from the Department of Education, NSW Treasury, DPC, DPIE and the persons employed in Destination NSW staff agency. The transferred functions and activities continued to operate within each 'transferor' agency's financial environment through to 30 June 2021. The entity is still transitioning to a mature stand-alone entity.

Our audit risk rating is higher because Investment NSW relied on financial records and information provided by the respective transferor entities.

Our audit procedures reviewed management processes to help ensure transactions are complete and accurate including confirming balances with respective transferor entities.

Infrastructure NSW

Infrastructure New South Wales (INSW) provides independent advice to help the government identify, prioritise project delivery, and place management of critical public infrastructure across NSW.

  Key financial statement risk Audit response

Key infrastructure projects

Key large infrastructure projects for INSW include the development of Barangaroo precinct, Sydney Football Stadium and the redevelopment of Sydney Fish Market.

Our audit risk rating is higher because the projects:

  • are financially significant to INSW
  • require strong project governance and carry high reputational risk for INSW and the state
  • involve significant judgements and assumptions in their costing and lease accounting.

Our audit procedures included meeting the project team to understand the project and financial implications, reviewing external accounting advice, testing costs capitalised during the year on projects and assessing the methodology and assumptions used in the valuation including ensuring disclosures are in accordance with the Australian Accounting Standards.

 

South Barangaroo

During 2020–21, INSW had a substantial lease modification in respect of the South Barangaroo finance lease. The modification had an impact of $59.0 million which was recognised in the income statement. Our audit risk is higher because the accounting treatment for the lease modification was complex due to the significant underlying assumptions in the model.

Our audit procedures included assessing the accounting treatment of the lease modification, testing the assumptions, and reviewing the expert’s advice on the matter.

Art Gallery of New South Wales Trust

The Art Gallery of NSW Trust (the Trust) is one of Australia’s flagship art museums and the state’s leading visual arts institution. The Art Gallery serves as a centre of excellence for the collection, preservation, documentation, interpretation and display of Australian and international art, and a forum of scholarship, art education and the exchange of ideas.

  Key financial statement risk Audit response

Sydney Modern Project

$344 million

The Sydney Modern Project is the Trust’s $344 million expansion project which expects to complete in 2022. Our audit risk rating is higher because:

  • the financial and operational risks of this project are significant
  • the funding is sourced from the NSW Government and philanthropic support. Fundraising is expected to exceed $100 million.

Our audit procedures included reviewing significant contracts related to the project, assessing accounting of project costs and funding, reviewing costs incurred and capitalised in the current year and ensuring the adequacy of financial statement disclosures are in accordance with the Australian Accounting Standards.

Valuation of property, plant and equipment

The Trust’s property, plant and equipment assets consist of land, buildings, plant and equipment and collection assets totalling $2.2 billion. In 2020–21, the Trust conducted a comprehensive revaluation of its land ($27.1 million) using an independent external valuer. Our audit risk rating is higher because:

  • the assets are financially significant to the Trust
  • significant management judgements underpinning key assumptions are involved often requiring the assistance of qualified external valuers for revaluation and specialists for fair value assessments.
Our audit procedures included testing the completeness and accuracy of the asset register, assessing the competence and objectivity of management's valuation experts, reviewing the appropriateness of the valuation methodologies, key assumptions and judgements applied, and reviewing the disclosures on the fair value of the property, plant and equipment assets in the financial statements in accordance with Australian Accounting Standards.

Sydney Opera House Trust

Sydney Opera House operates as one of the State’s cultural institutions within the Arts portfolio. It provides a broad range of cultural, tourism, community and commercial experiences to people from Sydney, NSW Australia and around the world.

  Key financial statement risk Audit response

Fair value assessment of property, plant and equipment

Sydney Opera House recorded $2.9 billion in property, plant and equipment at fair value representing approximately 97 per cent of its non-current physical asset base.

Our audit risk rating is higher because:

  • the assets are financially significant to the Sydney Opera House
  • the valuation of non-current physical assets is highly complex, involves management judgement, relies on a valuation expert and various assumptions underpin the methodology to determine fair value
  • there is a risk that the carrying values of assets may not reflect fair value as required by Australian Accounting Standards.

Our audit procedures included testing the completeness and accuracy of the asset register, assessing the competence and objectivity of management's valuation experts, reviewing the appropriateness of the valuation methodologies, key assumptions and judgements applied, and reviewing the disclosures on the fair value of the property, plant and equipment assets in the financial statements in accordance with Australian Accounting Standards.

For assets not subject to a comprehensive revaluation, management’s annual fair value assessment was reviewed.

Capital works and redevelopment of Concert Hall

Sydney Opera House’s capital and maintenance program is significant, with a forecast spend of approximately $113.7 million in 2020–21. Of note is the ongoing Concert Hall redevelopment which commenced in February 2020. The reopening of the hall is expected in early 2022.

Our audit risk rating is higher because:

  • the capital and maintenance program are significant
  • capital works programs create heighted financial reporting risks such as not correctly classifying costs between capital and expenses, not recognising completed assets timely and not recognising any obligations arising from contractual disputes.
Our audit procedures included assessing whether the capital expenditure was valid, how costs were classified between expenses and assets, recording of costs into separate identifiable assets in the asset register, timeliness of asset additions to the asset register, ensuring replaced assets were removed from the asset register, the process for capitalising work in progress and ensuring financial statements included all relevant disclosures in accordance with the Australian Accounting Standards.

Resilience NSW

Resilience NSW leads government disaster and emergency efforts from prevention to recovery by ensuring communities devastated by drought, bushfires, floods and COVID-19 get the help they need to rebuild and recover.

  Key financial statement risk Audit response

Natural disasters - grants and subsidies expenditure

Resilience NSW reimburses several NSW Government agencies for incurring eligible natural disaster expenditure. Grants and subsidies expenditure for 2020–21 was $525.5 million. Our audit risk rating is higher because:

  • the grants and subsidies are financially significant
  • the extent of the 2019–20 Australian Bushfire Emergency means the volume of claims across the state will continue to be significantly higher than normal
  • natural disaster payments have a diverse number of recipients.

Our audit procedures included testing a sample of transactions to ensure they were approved per delegation and ensuring the financial statements included the required disclosures in accordance with the Australian Accounting Standards.

3. Audit observations

Appropriate financial controls help ensure the efficient and effective use of resources and administration of agency policies. They are essential for quality and timely decision making.

This chapter outlines our observations and insights from our financial statement audits of agencies in the Premier and Cabinet cluster.

Section highlights

  • The 2020–21 audits identified 47 moderate risk issues across the cluster. Sixteen of the moderate risk issues were repeat issues. Many repeat issues related to governance and oversight and information technology.
  • The number of moderate risk findings increased by 42 per cent in 2020–21.
  • The moderate risk issues included information technology improvements, lack of service level agreements, risk management, contract and procurement and asset management improvements.

3.1 Findings reported to management

Thirty-two per cent of all issues were repeat issues

Breakdowns and weaknesses in internal controls increase the risk of fraud and error. Deficiencies in internal controls, matters of governance interest and unresolved issues were reported to management and those charged with governance of agencies. The Audit Office does this through management letters, which include observations, related implications, recommendations and risk ratings.

In 2020–21, there were 75 findings raised across the cluster (75 in 2019–20). Thirty-two per cent of all issues were repeat issues (29 per cent in 2019–20).

The most common repeat issues related to weaknesses in governance and oversight, excessive annual leave and information technology.

A delay in implementing audit recommendations increases the risk of intentional and accidental errors in processing information, producing management reports and generating financial statements. This can impair decision making, affect service delivery and expose agencies to fraud, financial loss and reputational damage. Poor controls may also mean agency staff are less likely to follow internal policies, inadvertently causing the agency not to comply with legislation, regulation and central agency policies.

The table below describes the common issues identified across the cluster by category and risk rating.

Risk rating   Issue
Information technology

Moderate2
8 new
5 repeat

Low1
4 new
2 repeat

The financial audits identified the need for agencies to improve information technology processes and controls that support the integrity of financial data used to prepare agencies' financial statements. Issues noted include:

  • lack of formally defined Information technology governance policy and disaster recovery plan
  • inefficient super user access and activity monitoring, including no privileged user access activity reviews of network, Sun, IPOS, Micropay and Aurion applications, and relevant Databases and Database Operating Systems
  • inadequate reporting of emerging Information technology risks and issues to senior management.
Internal control deficiencies or improvements

Moderate2
9 new
2 repeat

Low1
5 new
2 repeat

 

The financial audits identified internal control weaknesses across key business processes, including:

  • purchase orders approved after invoice date or goods and services received
  • delegation limits in SAP do not reflect the limits in the approved 'Instrument of Delegation'
  • lack of formal review of changes made to the payroll and vendor's master
  • outdated bank signatories for Westpac and ANZ bank accounts.
Financial reporting

Moderate2
12 new
3 repeat

Low1
3 new
2 repeat

The financial audits identified the need for agencies to strengthen financial reporting, including:

  • robust fair value assessment for infrastructure, property, plant and equipment assets
  • insufficient guidance for the capitalisation of expenditure
  • no formal documentation to support assessment of revenue recognition for AASB 15 or AASB 1059.
Governance and oversight

Moderate2
6 new
6 repeat

Low1
4 new
2 repeat

The financial audits identified the need for agencies to improve governance and oversight processes, including:

  • lack of service level agreement for service received from other agencies
  • outdated procurement policy
  • lack of a collection assets policy
  • lack of purchase cards policy.

2 Moderate risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.
1 Low risk from the consequence and/or likelihood of an event that has had, or may have a negative impact on the entity.
Note: Management letter findings are based either on final management letters issued to agencies, or draft letters where findings have been agreed with management.

The number of moderate risk findings increased from prior year

Forty-seven moderate risk findings were reported in 2020–21, representing a 42 per cent increase from 2019–20. Of these, 16 were repeat findings, and 31 were new issues.

Moderate risk findings related to:

  • incomplete risk registers
  • inadequate reporting of information technology risks to senior management
  • lack of formalised information technology policies and procedures
  • lack of privileged user activity reviews
  • lack of service level agreements
  • purchase orders being approved after receiving invoices
  • system delegations not reflecting the limits outlined in the instrument of delegation resulting in personnel approving expenditure outside of their limit
  • lack of a robust fair value assessment for assets
  • fully amortised and or depreciated assets still in use
  • lack of periodic review of master files
  • no encryption over payment files.

Matters of non-compliance Jobs for NSW Fund (Jobs Fund)

The Jobs Fund did not fully comply with the Government Sector Finance Act 2018 and Jobs for NSW Act 2015

The Jobs for NSW Fund (Jobs Fund) was established as a Special Deposits Account under the Jobs for NSW Act 2015 (the Act). The Jobs Fund, was previously administered by NSW Treasury during 2019–20. On 29 March 2021, the Administrative Arrangements (Administrative Changes – Miscellaneous) Order 2021, transferred the Jobs Fund to the Premier and Cabinet cluster.

The 2019–20 audit process was delayed due to the quality and timeliness of the financial reporting process. An unmodified audit opinion was issued on 18 August 2021. The following matters of non-compliance were noted during the 2019–20 audit process:

  • section 5(2) of the Act requires the board to consist of seven members, the board consisted of only two members
  • 5 payments from the Jobs Fund were authorised by an officer without the appropriate delegation from the Minister.

The 2020–21 Jobs Fund audit is ongoing, with draft financial statements provided on the 25 October 2021.

Machinery of Government changes - audit observations

Investment NSW arrangements not supported by service level agreements

The Premier and Cabinet cluster was subject to Machinery of Government (MoG) changes during 2020–21. These changes had an administrative impact on the cluster agencies. The changes resulted in transfer of activities and functions in and out of the cluster and the creation of a new entity (Investment NSW).

A number of activities and functions were transferred on 29 March 2021 from NSW Treasury, Department of Premier and Cabinet (DPC), Department of Planning, Industry and Environment (DPIE) and Department of Education to Investment NSW. On 29 March 2021, the Secretary of DPC confirmed in writing that DPC, DPIE and Treasury would initially provide corporate services to their former staff when they transferred into Investment NSW (and other impacted entities), and that an agreement would be developed by 30 June 2021 to formalise the arrangements. There were no formal service level agreements to 30 June 2021, which increased the risk of unclear responsibilities and accountabilities for deliverables. 

As at the date of this report, a Memorandum of Understanding is in place from 1 July 2021 with DPC which in time will be the only agency that continues to provide services to Investment NSW. We understand the other transferor entities continue to provide services to Investment NSW subsequent to 30 June 2021.

Recommendation

Investment NSW should ensure services received from other agencies are governed by service level agreements.

Purchase and recognition of land

Aerotropolis Core Project - Western Parkland City Authority

On 6 September 2021 (after the 30 June 2021 balance date), Western Parkland City Authority (the Authority) purchased 114.9 hectares of land located at Bringelly from the Commonwealth Department of Infrastructure, Transport, Regional Development and Communications for $293 million. A portion of the land may require remediation from contamination.

The Authority plans to perform a comprehensive revaluation of this parcel of land during the 2021–22 financial year. In addition, the Authority plans to determine and quantify the cost of any remediation of contaminated land. These matters will be an area of audit focus in 2021–22.

Appendices

Appendix one – Misstatements in financial statements submitted for audit

Appendix two – Early close procedures

Appendix three – Timeliness of financial reporting

Appendix four – Financial data

 

Copyright notice

© Copyright reserved by the Audit Office of New South Wales. All rights reserved. No part of this publication may be reproduced without prior consent of the Audit Office of New South Wales. The Audit Office does not accept responsibility for loss or damage suffered by any person acting on or refraining from action as a result of any of this material.