Executive
Summary
|
|
The focus of our audit |
|
|
|
|
|
The
Roads and Traffic Authority (RTA) is responsible
for managing NSW’s arterial road network (State Roads). The |
|
|
|
|
|
This audit sought to
determine how well the RTA is meeting the
Government’s objective of maintaining roads and bridges at minimum whole of
life cost to ensure reliability, safety and retained
value. We wanted
to find out what: §
condition State Roads are in
§
condition State Roads should be in
§
the RTA is doing
to address any gap. |
|
|
|
|
|
Audit opinion |
|
|
|
|
|
The RTA has improved the
overall surface condition of State Roads in the last decade. Country road
surfaces are now generally much better. Ride quality has improved and
cracking has been reduced. The RTA has also achieved
a substantial reduction in the number of structurally deficient bridges over
the same period. Ride quality on While
the RTA has standards for road maintenance, it has
not specified appropriate condition standards. In the absence of these, it is
difficult for the Government, Parliament and public to judge how well the RTA is maintaining road assets. Despite
a significant increase in the State’s contribution to maintenance since 1999‑2000,
the RTA has deferred road rebuilding projects. The RTA is rebuilding at less than half its long term target,
and has not met this target at any time this decade. As a consequence, the
structural condition and expected life of State Roads is declining. This
presents a risk that roads may become unsafe or unreliable, and is likely to
lead to higher repair costs. While the RTA says it
has deferred rebuilding to manage more immediate risks to safety, it
acknowledges the current rate of rebuilding is not sustainable in the long
term and needs to increase. The
RTA has not identified how it will address deferred
rebuilding, although it advises it is developing a new road network
management plan which will address this. We recognise that tension exists between
the need to develop new roads while maintaining the existing network. Yet the
Government’s priority is maintenance, including rebuilding. Despite the need
to rebuild more existing roads, the RTA has been
increasing its spending on new work. While it advises that Commonwealth
funding arrangements reduce its capacity to redirect funds to rebuilding, it
needs to do so. Otherwise it will continue to push the problem onto future
generations. |
|
|
|
|
|
|
|
|
We recommend that the RTA: |
|
Determine the gap between actual and appropriate condition |
§ complete by 2008 its work on specifying appropriate condition standards for roads, and by 2009 for bridges (p28) |
|
§ assess if a gap exists
between the actual condition of roads and bridges and appropriate condition
standards (p29) |
|
|
§ determine what it needs to do to lift the network to appropriate condition standards, and long term funding needs (p29) |
|
|
Improve methods and systems |
§ finalise its current research and develop by 2008 a more rigorous and reliable method to assess the expected remaining life of roads (p19) |
|
|
§ develop by 2009 a more rigorous and reliable method to assess the future structural condition of bridges (p22) |
|
|
§ ensure regions use a consistent approach to assess risks and determine maintenance priorities and treatments (p34) |
|
|
§ investigate and implement improved systems to help staff identify the best maintenance solutions (p36) |
|
|
§ prepare a submission to the Minister outlining the costs and benefits to the community of closing roads or lanes for an extended period to allow rebuilding, compared to the current approach of undertaking work in the middle of the night (p36) |
|
Address deferred rebuilding |
§ extend the planning horizon for asset management and maintenance to at least ten years (p37) |
|
§ investigate and implement potential models to quantify the risks to current and future road safety and reliability of travel, as well as the cost of repair, for various funding levels (p37) |
|
|
|
§ give higher priority to the rebuilding program to achieve long-term sustainability at minimum whole of life cost (p39) |
|
Improve advice to Government, Parliament and the public |
§ complete its new road network management plan, setting out the funding required to maintain the road network at minimum whole of life cost, including risks, any gap between appropriate and actual condition and rebuilding needs, and report this to the Minister and Treasury (p40) |
|
§ report in its Annual Report any gap between appropriate and actual condition, and how it plans to address it (p40) |
|
|
§ report in its Annual Report deferred rebuilding, the progress of its road rebuilding efforts, the proportion of the network past the end of its expected life, and the risks this represents (p40). |
|
|
|
|
|
|
Key audit findings |
|
|
|
|
Chapter 1: What condition are State
Roads in? |
The RTA
uses leading edge technology to collect road surface condition data. This
data shows that the RTA has improved the overall
ride quality on State Roads in the last decade, despite substantial increases
in traffic levels and heavier vehicle loads. The ride quality on country
roads is much better than ten years ago and is now similar to |
|
|
|
|
|
During
the same period, however, ride quality on More
important in the long term, but less obvious than ride quality,
is the underlying structural condition of State Roads. While more difficult
to assess than surface condition, the RTA has done
well to recognise the importance of measuring structural condition and
progressively improve its methods to do so. In our opinion, however, the
structural condition and expected life of State Roads is declining as a
consequence of the RTA deferring road rebuilding
works. While
the level of rebuilding may fluctuate around the long term target, the RTA has not
achieved its target at any time this decade. The average expected life of State Roads
is 40 years, but the current rebuilding rate means the RTA
will need to get 83 years out of them on average. While still in service, 16
per cent or 3,000 kilometres of the network has reached its expected life and
its future performance is unpredictable. |
|
|
|
|
Chapter 2: What condition should State Roads be in? |
The RTA ranks State Roads according to function and use with the
aim of keeping the more important roads and bridges in better condition. It
also has intervention standards for maintenance, including minimum standards
for the timely repair of potholes, edge breaks and other routine maintenance.
Specifying
appropriate condition standards is essential for good asset management, but
the RTA has yet to do this for State Roads. It
therefore cannot judge if a gap exists between actual and appropriate
condition, nor can the Government, Parliament or the public. The absence of
condition standards also makes it difficult for the public and the Government
to judge if the condition the RTA is aiming for is
adequate or how well the RTA is managing State
Roads. The RTA has started work on developing
appropriate condition standards, and should give priority to completing this
work. |
|
|
|
|
Chapter 3: What
is the RTA doing to address any gap? |
The RTA
allocates its maintenance money on the basis of risk, giving priority to availability
and safety of roads and bridges. Its approach balances head office control
and local decision making. The RTA needs, however,
to ensure all its regions adopt a consistent risk assessment method and to
improve its systems to help staff identify the best maintenance solutions. The RTA has not identified how it will address deferred
rebuilding, but advises it is developing a new road network management plan
which will address this risk. |
|
|
|
|
|
The RTA’s 2003-2008 Infrastructure Maintenance Plan
acknowledges that it is not doing enough rebuilding to ensure the long-term
viability of the network, thereby presenting a risk to safety and
reliability, and of higher repair costs. The RTA
needs to examine and model the relationship between spending, safety and condition so that it can give its Minister and
Treasury more detailed advice on the implications of funding decisions. The RTA should also report publicly on its progress in
addressing deferred rebuilding. |
|
|
|
|
|
Total maintenance spending has
grown by 20 per cent in real terms since 1995-96, but spending on developing
the network has grown by more than 50 per cent. During this period, NSW’s contributions to maintenance and to development have
each grown by about a third. The Commonwealth’s contribution to development
more than doubled whereas its contribution to maintenance has fallen by a
fifth. |
|
|
|
|
|
The RTA also
faces a problem rebuilding very busy, worn State Roads. Traffic flow and
congestion means crews can only work on them for a few hours at a time,
usually in the middle of the night. The RTA advises
this is not an optimal approach, but it assumes the disruptions caused by
closing a road or lane for an extended period would be unacceptable to the
community. The RTA should put these options and
their respective costs and benefits to the Minister to decide. |
|
|
Response
from the Roads and Traffic Authority |
|
|
|
|
|
I
enclose the RTA’s response to the Final Report of the
subject audit for consideration. The RTA appreciates the cooperative and constructive approach
adopted by the Audit Office and its staff during the progress of the
audit. This approach reflects well on
the role of the Audit Office in contributing to improved delivery of
services.
In this
respect the RTA is already moving to refocus on our
core road maintenance task. This audit
report provides significant assistance in progressing
these reforms.
(signed) Les
Wielinga Chief
Executive Dated:
4 August 2006 |
|
|
Attachment
The RTA thanks the Audit Office for the opportunity to
comment on this report.
The
RTA regards the report as a useful contribution as
we refocus on our core tasks of maintenance, construction and service. And
we welcome the Audit Office’s acknowledgement of the RTA’s
good practice in:
§ improving the overall surface condition of roads over the last
decade;
§
risk management;
§
automated data collection;
§
cost effective design guidelines and flexible management structures;
and
§
keeping State Roads open and available to road users.
|
|
|
We
also welcome the Audit Office’s acknowledgment of the challenges faced by the
RTA in maintaining the Other
major challenges include the facts that over the last decade: §
An extra one million vehicles now use the 20,738 kilometres of
roads in
§
There are now 600,000 more licensed drivers in NSW. In
recognition of the challenges facing the organisation the RTA
is currently evaluating the most effective organisational structure and
maintenance plan for maximising our maintenance effort. |
|
|
To date, planning has
relied on trends in surface condition data, condition intervention standards,
age and renewal considerations. |
|
|
|
|
|
Effective asset
management, however, leading to the setting of appropriate condition
standards, needs reliable forecasts of the structural condition of road
pavements. This has not been available
due to the absence of technology to assess the structural condition across a
large road network. |
|
|
|
|
|
In
this respect, the Report notes that the RTA has
“done well to recognise the importance of
measuring structural condition and progressively improve its methods to do
so” (page 4). The Report also notes that the RTA:
§
“in conjunction with the
CSIRO, developed and patented new mobile technology (‘RoadCrack’)
to assess pavement cracking” (page 23) to “help plan maintenance” and
“identify where a visual inspection by RTA staff is
needed to determine the appropriate maintenance treatment;” (page 22)
§
integrates road rebuilding
with maintenance, measuring and reporting its rate of rebuilding against its
long term target; (page 20) and
§
is already improving its modelling capabilities by “leading research
into the latest models” to improve asset management and maintenance planning
(page 18). The Report recognises the need for a long term perspective when examining
the maintenance of road infrastructure.
Many road pavements last longer than 50 years and bridges even
longer. The
Report acknowledges that “the level of rebuilding may
fluctuate around the long term target” (pages 4 and 12). Short term
variations in the rate of rebuilding can be accommodated provided all State
Roads are kept open without constraints on road users
due to their condition, and provided that the rate of rebuilding increases in
the longer term. Variations may occur
from time to time due to other priorities such as re-opening The
Report notes that the RTA receives $2 billion pa
for maintaining and developing the major arterial network. However, a significant part of this funding
is from the Commonwealth and is tied to specific development projects. One
of the constraints facing the RTA is the reduction
in Commonwealth funding for maintenance (page 5, 32 and 38). Indeed
under the Auslink agreement the State must
contribute funds to many Commonwealth projects. The overall effect is that the untied part
of the State development program is only about $420 million pa. Despite these limitations, the State has
increased its funding of maintenance in real terms by one third since 1995-96
(pages 5, 32, 37 and 38). |
|
|
The Report acknowledges as good practice, the RTA’s ranking of its State Roads by function and use
(page 26), with the aim of keeping the higher ranked roads in a better
condition. For best use of public
funds, it is important that those roads classified as State Roads continue to
fulfil arterial road functions, and a panel of Local Government and RTA representatives is currently finalising a review to
ensure that roads are appropriately classified.
|
|
|
|
|
|
In
summary then, the RTA will use this report in
developing our maintenance plans and most appropriate organisational
structures. More specifically, in addition to the above remarks the
following table details the RTA’s response to the
Audit Office’s individual recommendations
|
|
|
Recommendations and RTA Comments |
|
|
|
|
Determine the gap between actual and appropriate condition |
§
Complete by 2008 its work on
specifying appropriate condition standards for roads, and by 2009 for bridges
(p28) |
|
§
Assess if a gap exists between the actual condition of roads and
bridges and appropriate condition standards (p29) |
|
|
§
Determine what it needs to do to lift the network
to appropriate condition standards, and long term funding needs (p29) |
|
|
|
Agreed. The RTA has commenced this process. It must be noted that implementation is linked to improvements in methods and systems recommended below. |
|
Improve methods and systems |
§
Finalise its current research
and develop by 2008 a more rigorous and reliable method to assess the
expected remaining life of roads (p19) |
|
|
§
Develop by 2009 a more
rigorous and reliable method to assess the future structural condition of
bridges (p22) |
|
|
Agreed. The RTA will continue its work on structural assessment methods. This is necessary to achieve the above recommendations. |
|
|
§ Ensure regions use a
consistent approach to assess risks and determine maintenance priorities and
treatments (p34) |
|
|
§ Investigate and implement
improved systems to help staff identify the best maintenance solutions (p36) |
|
|
Agreed. |
|
|
§ Prepare a submission to
the Minister outlining the costs and benefits to the community of closing
roads or lanes for an extended period to allow rebuilding, compared to the
current approach of undertaking work in the middle of the night (p36) |
|
|
Agreed. |
|
Address
deferred rebuilding |
§ Extend the planning
horizon for asset management and maintenance to at least ten years (p37) |
|
Agreed. |
|
|
§ Investigate and implement
potential models to quantify the risks to current
and future road safety and reliability of travel, as well as the cost of
repair, for various funding levels (p37) |
|
|
Agreed. The RTA will
investigate potential models of this type. |
|
|
|
§ Give higher priority to
the rebuilding program to achieve long-term sustainability at minimum whole
of life cost (p39) |
Agreed.
Rebuilding of pavements will need to be increased for
long term sustainability.
|
|
|
Improve advice to Government, Parliament and the public |
§
Complete its new road network management plan, setting out the
funding required to maintain the road network at minimum whole of life cost,
including risks, any gap between appropriate and actual condition and
rebuilding needs, and report this to the Minister and Treasury (p40) |
|
Agreed. |
|
|
§ Report in its Annual Report any gap between
appropriate and actual condition, and how it plans to address it (p40) |
|
|
§ Report in its Annual Report deferred
rebuilding, the progress of its road rebuilding efforts, the proportion of
the network past the end of its expected life, and the risks this represents
(p40). |
|
|
Agreed. The reports are linked to improvements in
methods and systems and the implementation of appropriate standards and
models recommended above. |