The focus of our audit

 

 

 

The Cross City Tunnel (CCT) has been marked by controversy since its opening. About 30,000 cars a day are using the tunnel so far, about one-third of the expected traffic volume. The road changes have resulted in slow, tangled traffic.

 

 

 

There has also been substantial public concern since the CCT opened over whether: road closures and changes were necessary; the toll is too high; the contract was awarded to CrossCity Motorway Pty Ltd (CCM) fairly.

 

 

 

This audit is one of several reviews and inquiries into the CCT with each review addressing various aspects of the project. In this report we have focused on three key issues:

§        was the upfront payment a legitimate reimbursement of necessary expenditure?

§        were the variations to contract in the amending deed of December 2004 reasonable, and were they handled appropriately?

§        were the changes to surface roads based on a robust assessment against stated objectives?

 

 

 

Audit opinion

 

 

 

In our opinion the Government’s ‘no net cost to government’ requirement was a legitimate (but not the only possible) basis for the tunnel bid process. The Government was entitled to decide that tunnel users meet the tunnel costs.

 

 

 

Structuring the bid process on the basis of an upfront reimbursement of costs incurred (or to be incurred) by the Roads and Traffic Authority (RTA) was therefore appropriate.

 

 

 

Whether these costs should have included ‘public domain’ costs not relating directly to the tunnel (and hence passing those costs on to tunnel users) was a decision the Government was entitled to make. A core and common role of government is to redistribute income between different groups in the community.

 

 

 

In our opinion, however, the Government, Treasury and the RTA did not sufficiently consider the implications of an upfront payment involving more than simple project cost reimbursement (i.e. the ‘Business Consideration Fee’ component).

 

 

 

While the RTA may have genuinely believed it was in the public interest to ‘capture’ some of the proponent’s ‘surplus’ through the Business Consideration Fee, no real thought was given to:

§        foregoing the fee to reduce the toll charges on tunnel users, or

§        how this amount was to be used (e.g. retained by the RTA for use on other roadworks or used by Treasury for allocation to other areas of government).

 

 

 

In one sense this issue ultimately became academic. The RTA’s
project-related costs will eventually absorb all of the upfront payment, once all claims are settled. No Business Consideration Fee will remain.

 

 

 

However, the principle of requiring a Business Consideration Fee remains an issue to be resolved.

 

 

 

In our opinion such a fee would need strong justification where:

§         the cost of it is met, in effect, by people not party to the contract (in this case the tunnel users), or

§         it achieves a current benefit to be paid for by future tunnel users (i.e. it distorts inter-generational equity).

 

 

 

In our opinion the RTA was wrong to change the toll escalation factor late in 2002 to compensate the tunnel operator, CCM, for additional costs.

 

 

 

This action distorts inter-generational equity between tunnel users. If it was appropriate for tunnel users to fund these costs, this should have been done by changing the base tolls. Escalation factors should do no more than reflect underlying cost movements or inflation.

 

 

 

In our opinion the variations in the amending deed were reasonable.

 

 

 

The net present value of the 15 cents toll increase accurately reflected the $35 million incurred by CCM in doing the extra work required after the signing of the original contract. But it made an already expensive toll even more expensive. By 2018, the toll will be about 35 per cent higher than it would have been due to this increase and the change to the escalation formula.

 

 

 

The handling of the amending deed also lacked transparency:

§        it was not made public until late 2005

§        no clear breakdown of the costs has been made available publicly, even to date

§        it was done without full probity assurance.

 

 

 

A widely held view is that the road changes were not necessary, but were introduced to force motorists into the tunnel to profit the tunnel operator.

 

 

 

When the project was put to tender, only limited road changes were specified. All bids were made on this basis.

 

 

 

In our opinion the RTA and the Department of Planning (DoP) communications and community consultation over road changes were sound at the detailed level but not effective in conveying the overall impact of the package of changes. We cannot say that the road changes were robustly assessed, either collectively or on a road-by-road basis.

 

 

 

Consultation with stakeholders about the road changes failed to clarify the cumulative impact of the changes, especially in eastern Sydney. It was not inclusive enough to capture the significant resentment the changes caused. Any loss of patronage from this resentment will further hinder the tunnel’s main objective of reducing traffic in the City.

 

 

 

In our opinion the concept behind the road changes was to implement long-standing Government planning objectives to reduce congestion in and around Central Sydney, and to improve public transport routes and urban amenity.

 

 

 

The initial strategy was to make car travel on surface roads ‘unattractive’ and could therefore be described as ‘funnelling’ traffic into the tunnel. But the motivation was primarily to clear up the congestion on surface roads rather than to make the tunnel profitable. The financial viability of the tunnel, and the RTA’s interpretation of ‘no net cost to government’, did however influence some important planning decisions.

 

 

 

Maintaining direct toll-free alternative routes was a key principle in the DoP Director-General’s requirements, but was lost as the project developed.

 

 

 

Summary of recommendations

 

 

 

We recommend that the RTA:

§        define project costs and development costs more clearly (page 38)

§        require transport consultants to provide a clearly defined range of likely patronage outcomes (page 62)

§        consider the impact of various patronage outcomes on a project’s viability (page 62)

§        assess the affordability and public acceptability of any proposed tolls in future projects (page 47).

 

 

 

We recommend that Treasury and the RTA:

§        review the bidding model used for Public Private Partnership projects, including the CCT (page 33)

§        limit the upfront payment sought from the private sector to recovery of development costs, and abandon the option of a Business Consideration Fee (page 33)

§        consider receiving upfront payments progressively as project development costs are incurred (page 38)

§        consider making the toll level the point of competition in the bidding process (page 33)

§        make value for money for motorists an explicit objective of the assessment of bids for future tollway projects (page 33)

§        consider alternative funding methods for subsequent project cost increases, and ensure decisions are made with regard to motorists price sensitivity (page 38)

§        develop guidelines for setting any future tolls equitably, related to distance travelled and the cost of the project (page 51).

 

 

 

We recommend that Treasury and the Budget Committee of Cabinet:

§        clarify for any future contracts what ‘no net cost to government’ means, including whether agencies should use their capital budgets to cover any cost increases (page 36)

§        develop guidelines for the use of any surplus from current or future upfront payments (page 33)

§        consider direct funding of public domain improvements (page 38).

 

 

 

We recommend that Treasury and Premier’s Department require agencies to:

§        keep the full tender evaluation and review panels involved in complex high risk projects until the project deed is signed, and re-convene them if amending deeds are needed (page 52)

§        make any contract amendments subject to the same level of probity checks and scrutiny as the original contract process (page 52)

§        make any contract amendments, and their summaries, public in a timely manner (page 52).

 

 

 

We recommend that the DoP and the RTA:

§        improve the consultation process for major projects (page 70)

§        conduct a joint review of road changes that are not consistent with current traffic volumes (page 72)

§        resolve the inconsistency between current traffic arrangements and the stated objective of maintaining at least one direct toll-free alternative route on all sectors affected by the CCT (page 72).

 

 

 

We recommend that the DoP, in conjunction with Treasury:

§        review the use of open-ended conditions of approval of projects (page 38).

 

 

 

Audit findings

 

 

Chapter 2

Was the upfront payment a legitimate reimbursement of expenditure?

 

 

 

CCM offered the RTA $100.1 million as an upfront payment for the CCT project. The offer comprised a Development Fee of $54 million for the RTA’s initial estimate of its project development costs, and a Business Consideration Fee of $46.1 million. The actual payment reduced to just under $97 million on finalisation of the contract, mainly due to movements in interest rates.

 

 

 

The Business Consideration Fee was the price a proponent was willing to pay for the right to build and operate the tunnel. It was distinct from the estimated development costs. There were no government directions on its use.

 

 

 

The bidding model developed by Treasury allowed the bidders to compete on a number of variables. They could bid on the upfront payment, the concession period or the toll. CCM offered the highest upfront payment, and this became a decisive criterion in the assessment of bids.

 

 

 

The advantage of making the upfront payment a point of competition is that it makes it easier to compare bids. Difficulty in comparing bids has been the subject of past criticism. However, allowing the upfront payment to be a point of competition also presented significant risks, particularly the risk of higher tolls. If motorists perceive the level of tolls as unreasonable, they may avoid using the tunnel. Therefore, we consider that the Budget Committee of Cabinet should have reviewed and assessed the implications of this approach.

 

 

 

All of CCM’s bids predicted a higher number of cars using the tunnel than the RTA and the rival bidders. CCM’s projections for 2006 ranged from 12 per cent to 50 per cent higher than other bidders. This should have concerned the evaluation panel sufficiently to cause greater scrutiny of the projections. Actual patronage to date has been under a third of the CCM estimates.

 

 

 

After receiving the $97 million upfront payment in December 2002, the RTA used part of it to recover its project development costs, and committed another part to future CCT project costs. By April 2005, the RTA had not spent or committed about $9.0 million of the upfront payment, earmarked for the finalisation of outstanding project costs. The RTA used only $3.1 million of the unspent portion of the upfront payment on the subsequent cost increases, which largely flowed from the Planning Minister’s Project Conditions of Approval.

 

 

 

To recover subsequent cost increases, preserve the upfront payment, and avoid using funds from its capital expenditure budget, the RTA negotiated two deals with CCM. The first deal resulted in a change to the way the toll escalates. This was incorporated in the original contract. The second deal resulted in a 15 cents toll increase. This was incorporated in the First Amendment Deed.

 

 

 

CCM delivered the project to the RTA on time. The RTA delivered the project at ‘no net cost to government’ because it passed on all increased costs to motorists by way of toll increases. This was because it interpreted ‘no net cost to government’ to mean no net cost to the RTA budget. The RTA did not adequately consider using its capital expenditure budget to meet cost increases.

 

 

Chapter 3

Were the contract variations in the amending deed appropriate?

 

 

 

The $38.1 million cost increases identified at the amending deed stage were legitimate and were the responsibility of the RTA, not CCM.

 

 

 

After the contract was signed, new costs arose, totalling $38.1 million. The RTA accepted responsibility for these costs. It funded $3.1 million from the upfront payment, and CCM carried out the remaining $35 million worth of work. The RTA compensated CCM by allowing an increase of 15 cents in the base toll of $2.50 (in 1999 prices). The change was formalised in the First Amendment Deed (FAD), signed in December 2004. This is the only variation to the original contract.

 

 

 

The 15 cents base toll increase was an appropriate amount to reflect the net present value of the $35 million of work that CCM undertook. It will result in a 5.6 per cent increase in toll revenues to CCM.

 

 

 

The 15 cents base toll increase and the change to the toll escalation formula have a major and continuing impact on the toll:

§        the 15 cents increased the base toll for the main tunnel by 6.0 per cent, and for the shorter run (vehicles from the east exiting at Sir John Young Crescent) by 13.6 per cent. The RTA did not apply a pro rata increase

§        the change to the escalation formula has the biggest influence on the tolls; an increase of around $1.12 for the main tunnel by 2018. Adding the 15 cents to the base toll brings that up to around $1.43. Together, this means the toll would be 35 per cent higher than originally planned by 2018

§        the effect of the two changes is more severe for the shorter run, with an increase in the planned toll (base toll plus CPI) of 44 per cent by 2018.

 

 

 

There was a total of $110 million of extra project costs ($75 million at the Supplementary EIS stage resulting in changes to the toll escalation, and $35 million resulting in the 15 cents increase to the base toll). These were separate and additional to the upfront payment. If the Government had contributed this $110 million rather than pass it on to the users, the tolls could have been 51 cents lower on tunnel opening and more than one third lower by 2018.

 

 

 

The RTA obtained proper approval for the amending deed and instituted procedures to manage the works covered in the deed. But the handling of the amending deed is open to criticism:

§        it was not made public, amidst lack of clarity about whether the RTA was required to publish a summary, until late 2005

 

§        there is still no clear breakdown of the costs available publicly

§        it was entered into after all the protective structures set up to ensure fairness around the contracting process had been dismantled

§        the Treasurer’s consent to the amendment was sought in a short timeframe, which may have worked against full analysis of the issues.

 

 

Chapter 4

Were the road changes based on a robust assessment?

 

 

 

The RTA developed 73 road changes to integrate the CCT with the road network. Most are not road closures as such, but changes to lanes and road use. By May 2006, 63 had been completed, six reversed and four were still pending. Of the 73 road changes:

§        28 were in response to the EIS and 45 to the Supplementary EIS

§        22 are specified in the contract as Materially Adverse Events (MAEs) and so may trigger compensation to CCM if reversed.

There is uncertainty over whether any reversal of the other 51 road changes not specified as MAEs would trigger compensation.

 

 

 

A widely held view is that the road changes were not necessary, but were introduced to force motorists into the tunnel in order to profit the tunnel operator.

 

 

 

In our view this was not the case. We found that the objective of the road changes was to reduce through traffic in and around Central Sydney and to improve the public domain, not to be a tunnel funnel.

 

 

 

Both the RTA and the DoP relied on patronage estimates of over 80,000 vehicles a day using the tunnel in their decision to implement immediate road changes. This was because the agencies believed that such a large reduction in above ground traffic would immediately attract more cars and lose the benefits of reduced congestion. Actual usage has been below 25,000 vehicles a day (when the full toll has applied). Since the half-price period began, usage reached an average of 34,000 vehicles a day.

 

 

 

Maintaining toll-free alternative routes was a key principle in the DoP Director-General’s requirements. But road restrictions were added as the project developed because there was no mechanism to judge the cumulative magnitude of the road changes. This key principle was lost as the project progressed.

 

 

 

We cannot say that the road changes were robustly assessed, either collectively or on a road-by-road basis because:

§        the patronage scenario was not robustly assessed

§        ensuring the financial viability of the tunnel, and the RTA’s interpretation of ‘no net cost to government’, affected important planning decisions.

 

 

 

There was extensive consultation with stakeholders about the road changes. It did not however capture the significant resentment among prospective toll payers. This is a group which was admittedly diffuse and difficult to survey. Any loss of patronage from this resentment will further hinder the tunnel’s main objective of reducing through traffic in the City.

 

 

 

Response from the Roads and Traffic Authority

 

Thank you for your letter dated 5 May 2006 attaching a draft of the Auditor-General’s proposed Report concerning the Cross City Tunnel project.  This letter constitutes RTA’s submission for inclusion in the Report pursuant to Section 38C of the Public Finance and Audit Act 1983.

 

The RTA will ensure that the findings in the draft Report are carefully reviewed in its planning for and delivery of future Motorway projects.  In particular, the RTA will carefully review the recommendations set out in the draft Report in light of existing Government policy and in particular the recommendations of the Motorways Review undertaken on behalf of the NSW Government by David Richmond, AO.

 

The RTA notes that the Performance Audit did not extend to a full review of the RTA’s involvement in the Cross City Tunnel project.  In delivering this project the RTA paid careful regard to previous reports and recommendations of Auditors-General relating to other Motorway projects, as well as to ensuring regular communication with your office during the negotiation and finalisation of the project.  The RTA was pleased to see recognition of this fact in the draft Report.

 

The RTA will continue to strengthen its processes associated with the development and delivery of privately financed projects.

 

The RTA would also emphasise that in delivering the Cross City Tunnel project as a whole it ensured that it acted within the parameters of then Government policy, including the Treasury’s “Working with Government:  Guidelines for Privately Financed Projects”, that its tender process was thorough and transparent and that it obtained key Cabinet, planning and other statutory approvals for all aspects of the transaction.

 

The draft Report focuses on three key aspects of the Cross City Tunnel Project, namely:  the requirement for an upfront payment, the December 2004 Amending Deed and the surface road changes introduced as part of the project.

 

The RTA has reviewed the Audit opinion and findings and notes in particular that the Audit Office has reached positive conclusions in relation to the RTA’s role in project development and contract administration including the management of project variations.

 

The RTA also takes this opportunity to register three significant facts that:

 

·          There is no financial exposure to the tax payer associated with levels of patronage.  That is, the taxpayer has not accepted the ‘patronage risk’ associated with this project;

 

·          The CCT will be in public ownership in less than 30 years time – again achieved at no net cost to Government; and

 

·          As a result of the project there are now more than 30,000 fewer cars on Sydney City roads causing city congestion. In years ahead this number will continue to rise.

 

The RTA notes that the Audit Office has raised concerns in relation to the extent to which the implications of an upfront payment were appropriately considered by Government, the toll escalation regime, the veracity of patronage projections for the project, the transparency associated with the execution of the Amending Deed and the extent to which the surface road changes were understood by road users.  While the RTA does not propose to respond formally to each of these matters individually, it would make the following points:

 

1.       RTA obtained appropriate approval to the inclusion of a toll escalation regime;

 

2.       RTA gave appropriate consideration to the expenditure of its own capital budget in connection with cost increases associated with the Cross City Tunnel Project.  Evidence from the former Premier and Treasurer to the Joint Select Committee Inquiry into the Cross City Tunnel made it clear that it was not a course open to the RTA.  Further, the Treasurer approved both the initial transaction and also the Amending Deed without any requirement that the RTA expend funds from its own Budget;

 

3.       The RTA does not accept criticisms in the Report that the differences in patronage projections between the RTA, CCM and the other bidders were such that more rigorous testing of them should have taken place.  The RTA’s evaluation of tenders thoroughly examined the patronage analysis put forward by CCM and other bidders and the RTA notes that CCM’s bid was supported by expert traffic modelling advice as well as detailed traffic studies.  The figures shown in the draft Report themselves indicate that the RTA’s patronage forecast, and that of another bidder, were both within 10% of CCM’s patronage forecast for the main tunnel in 2006.  This figure is well within any shortfall in traffic volume that may have been necessary to put the validity of CCM’s proposal at risk;

 

4.       RTA notes comments in the report in respect of patronage predictions.  The comparisons of estimated actual patronage compared to CCM’s projections do not adequately recognise the impacts of motorway ramp up for Cross City Tunnel.  It is likely that the Cross City Tunnel ramp up period will be in the order of 2 or 3 years and the appropriate time to make a comparison of actual versus projected traffic is after ramp up when equilibrium traffic has been achieved.  We also note that your report recognises the issues relating to ramp up and includes an opinion that Cross City Tunnel is not experiencing a standard ramp up;

 

5.       The RTA queries the validity of the ‘intergenerational equity’ argument put by the report.  To be a valid point it must assume that tunnel users will cease to be tunnel users after that period of time which defines a generation. Given that a substantial majority of motorists are active drivers for more than 30 years this ‘intergenerational equity distortion’ referred to in the report is overstated.  It needs also to be appreciated that private sector delivery of the project enables its benefits to be provided decades earlier than may have otherwise been the case.

 

The RTA also reiterates that in each case it ensured that it carefully consulted with the key government agencies to ensure that all applicable guidelines and policies were met.

 

(signed)

 

Brett Skinner

Acting Chief Executive

 

Dated: 23 May 2006

 

 

Response from Treasury

 

 

 

Thank you for providing me with a copy of the final draft of the Performance Audit – The Cross City Tunnel Project and inviting me to comment on the report.

 

A number of the recommendations you make are generally consistent with the Premier’s Department recent Review of Future Provision of Motorways in NSW and the Joint Select Committee’s Inquiry into the Cross-City Tunnel. As such Treasury is already in the process of implementing changes to address some of your recommendations.

 

In particular, your recommendation that Treasury publicly disclose contract amendments is being implemented by revising Ministerial Memorandum 2000-11 Disclosure on Information on Government Contracts with the Private Sector.

 

Also, Treasury is currently updating and revising the Working With Government Guidelines for Privately Financed Projects to address a number of your recommendations. In particular, the revised version will emphasise the importance that any user charges and/or taxpayer contributions for projects should be value for money and Budget Committee approval will be required prior to amending any contract.

 

I would also like to take the opportunity to clarify and elaborate on a few areas that you mentioned in your report.

 

Firstly, I would like to clarify your suggestion that the Government required the project to be delivered at no net cost to government (p2). There is not a general principle that required privately financed projects to be delivered at no net cost to government. The need for a Government funding contribution in addition to any user charges associated with a project is determined on a case by case basis, taking into account the Budget situation and the Government’s expenditure priorities.

 

The Government’s approval to proceed with the Cross-City Tunnel project was not conditional on there being ‘no cost to Government’. As your report points out, the Treasurer wrote to the Minister for Roads on 14 March 2002 stating that where additional funds were needed for the project they should come from the RTA’s existing forward capital program.

 

Secondly, your report infers that the CrossCity Motorway Consortium (CCM) won the tender on the basis of contributing the highest up-front payment (p26). Whilst the up-front was one of the main financial points of comparison in the competition, there were other important non-financial evaluation criteria. CCM’s winning bid was assessed to be a technically superior bid because there would be reduced traffic disruption during construction and the design enabled an increase in the speed limit to 80 kilometres per hour.

 

Thirdly, your report states that the high patronage estimates of CCM’s winning bid should have received greater scrutiny (p29). The patronage estimates of all bids were interrogated in detail. In addition, the financial models of all bidders were stress tested to determine the impact of much lower than forecast revenue projections and CCM’s bid performed well on these tests.

 

The traffic forecasts of CCM’s winning bid were only about 6 per cent higher in 2006 than the Public Sector Comparator (a tunnel with a 60 kilometre per hour speed limit) and 9 per cent higher in 2016. Given the challenges in accurately forecasting toll-road patronage particularly in the early ramp-up stages, it would have been difficult to conclude that these estimates were unreasonable. These challenges are evident from a Standard and Poor’s publication which found that traffic forecasts for various toll-roads around the world were underestimated on average by around 30% during the ramp-up phase (refer Global Project Financing Yearbook, October 2005). Whilst traffic flows are difficult to predict in the ramp-up phase, traffic on most of Sydney’s toll-roads have, after the first couple of years, been consistent with or exceeded initial forecasts.

 

It is also interesting to note that in contrast to the Cross-City Tunnel experience, Transurban, part owner of the Westlink M7, have made statements that their traffic forecasts “have proved extremely accurate” (refer Transurban Investor Briefing, February 2006).

 

Finally, I would like to thank you and your staff for the co-operative approach taken during the course of the audit and the opportunity to comment on the report.

 

(signed)

J Pierce

Secretary

 

Dated: 23 May 2006

 

 

Response from the Department of Planning

 

 

 

I refer to your letter of 5 May 2006 and the attached “Performance Audit – The Cross City Tunnel Project”.

 

You would be aware that the Department held discussions with the Audit Office at the officer (2 May 2006) and executive level (4 May 2006) to outline the issues raised in its review of the performance audit.  These issues were outlined in a letter dated 5 May 2006.

 

The Department has reviewed the “Auditor-General’s Report Performance Audit – The Cross City Tunnel Project – Final Report to Agencies” dated 5 May 2006.  The Department’s key issues are outlined in Attachment A.

 

I thank you for the opportunity of commenting on the Performance Audit report and trust that the Department’s comments are of assistance.

 

 

(signed)

 

Sam Haddad

Director General

 

Dated: 24 May 2006

 


 

Attachment A

1.           Strategic Issues

(a)         Public Domain Improvements

The issue of public domain improvement is twofold – whether these should be included as part of a project such as the Cross City Tunnel and secondly, how these should be funded.

As discussed, the Department’s policy framework at the time of assessing the Cross City Tunnel was one of integrated transport networks, intended to address the range of transport options of car use, public transport, pedestrians and cyclists.  In response to the first question, and in partial response to the issue raised in the report of a new road being able to stand on its own merits, it is difficult in many situations, particularly in road construction to not include such public domain improvements.  Road projects by nature bring opportunities where traffic switches are predicted to occur where a new, more efficient route is said to be provided.  A significant component of such a project’s justification is how these benefits can be ‘captured’ and converted to broader public benefit in the form of improved public transport facilities and services.  In order to address issues of government policy, including reducing car dependency by measurable indices such as vehicle kilometres travelled, it would be considered difficult to not include such public transport, pedestrian, cyclist and general community benefits such as those proposed for the Cross City Tunnel in justifying the proposal.

In response to the second component relating to funding of such public domain improvements, this matter is not a key consideration in the Department’s role in project assessment and is largely assumed to have been resolved by the time a proponent is seeking the Minister’s approval.  The Richmond Report into the future funding of motorways, the recommendations of which have been adopted by the Government, recommends that:

“In some circumstances, an alternative means of achieving public domain benefits might be followed.  This would involve capturing some funding upfront (either from the project or Government sources) and quarantining this funding for local benefits, with the use of such funding being decided following public consultation at a stage closer to, or following, the completion of the project. Delivery could remain the responsibility of the PPP private sector partner.”

(b)         Provision of Alternative Routes

The key issue in relation to the alternative route policy relates to east to north moving traffic wishing to access the harbour crossings.  The Department recognises that most of the previously available routes from William Street to the Domain tunnel are no longer available.  Alternative toll-free routes do remain via Macquarie Street to the Cahill Expressway and Harbour Bridge or via Cowper Wharf Roadway to the Domain Tunnel, albeit that these are less direct.

Despite extensive consultation by the RTA, the immediate closure of access routes to the Harbour crossings on opening of the tunnel and the wider road users’ lack of understanding of these impacts is acknowledged.  With the exception of the Cowper Wharf Roadway closure, there were few concerns raised in consultation regarding access to the Harbour crossings and this issue may have been ‘lost’ due to the focus on the proposed changes to air quality management and public domain improvements.

The provision of alternative toll-free routes has been a standard policy of the Department in assessing road projects and it is considered that this policy has been retained to some degree for this project.  It is recognised that there are clearly toll-free routes available for east-west traffic, the traffic direction which the tunnel was largely constructed to address.  These remain as surface routes through the CBD as were previously available to motorists.

2.           Other Comments

         Action for Transport

On page 56, the audit report states:

“The Government’s strategic plan, Action for Transport 2010 saw the tunnel as …. part of a larger plan to improve life in the Central Business District.  The plan envisaged one lane would be closed on William Street to enable widening of pavements and landscaping work …”

Comment:  The Department acknowledges that the development of the Cross City Tunnel saw the project area extend further from the CBD than was acknowledged in the CBD, particularly with the modification (the “Long 80” tunnel) to the approved project.  Notwithstanding this, Action for Transport 2010 is a strategic planning document providing an overview of the project and the types of changes that were likely to be included as the project was known at the time and would not have been intended to present a final project.  Naturally more detailed plans developed over time as the project objectives were further refined and results of community consultation were taken into account.  This will continue to be the case where strategic planning documents identify key projects and the broad objectives to be further refined over time.

3.           Recommendations

With regards to the recommendations of the draft audit report relating to road changes, the Department provides the following:

Recommendation

Comment

We recommend that the Department of Planning (DoP) and the RTA:

§        conduct a joint review of all road changes and consider reversing those that are not appropriate to current traffic volumes

The reversal of road changes may or may not require a modification to the Minister’s approval for some or all of any proposed changes.  It is the responsibility of the proponent agency to determine the need for and to initiate a modification to a Minister’s approval.  The Department is obliged to consider any such request on its merits.  The Department is happy to co-operate with the RTA regarding the implications of any suggested road changes in the context of the Minister’s approval. Notwithstanding, it should be noted that the decision to make road changes should not be based on projected or actual traffic volumes alone but on a wider range of environmental impacts related to the project as a whole that may result from those changes.

§        restore at least one direct toll-free alternative route on all sectors affected by the CCT

As discussed above, any changes which may be required in relation to this recommendation would need to be considered in the context of the Minister’s approval and the potential impacts.  The need for a modification to enable reinstatement of a direct toll-free route would need to be initiated by the RTA.

We recommend that the DoP, in conjunction with the Treasury:

§        review the use of open-ended conditions of approval of projects.

The Department acknowledges the argument regarding the use of open-ended conditions and potential funding implications.  In particular open-ended conditions have tended to deal with issues related to air quality management, future changes in standards and the need for other actions including upgrading or retrofitting to meet those standards.  The Department recognises the need to have flexible conditions in these instances to enable future standards to be applied.  Like the issue for funding of public domain improvements, there may be scope for a more holistic approach to funding components of projects through mechanisms other than a toll such as the public domain improvements.

We recommend that the DoP and the RTA:

§        improve the consultation process for major projects.

The commencement of Part 3A of the Environmental Planning and Assessment Act provides opportunity for the Minister to approve concept plans for projects.  This process is intended to enable greater community and other stakeholder input at an early stage of a proposal’s development than is currently the case.

The Department also recognises that, in the case of the Cross City Tunnel, a comprehensive consultation process was undertaken and the impacts of the proposal were relatively well understood, the broader community and road users general particularly those wanting to access the harbour crossings were not understood until the road changes had been made.

The Department is willing to work with the RTA and other agencies to identify mechanisms to ensure that the potential implications of future projects are appropriately communicated.